HomeMy WebLinkAbout108811 NEENAN CO - CONTRACT - RFP - P812 SECOND SHEET OF ICE AT EPICAGREEMENT
SECTION 00600
BONDS AND CERTIFICATES
00610 Performance Bond
00615 Payment Bond
00630 Certificate of Insurance
00635 Certificate of Substantial Completion
00640 Certificate of Final Acceptance
00650 Lien Waiver Release (CONTRACTOR)
00660 Consent of Surety
00670 Application for Exemption Certificate
The Neenan ComDanv Second Sheet of Ice at EPIC 11/29/2001
Ision Description
Takeoff Quantity
Total CosVUnit
Total Amount
'Paint - Ext Concrete
32.302.00 sqft
0.24 /sqft7,790!
I
Paint - Interior
32,302.00
1.24
40,000
Paint - DoorNVindow
_ 32.302.00 sqft _. _
0.04 /sqft _
1.248
Stain Door
32,302.00 sqft
0.03 (sqft
9801
100 Specialties
—
'Compartments/Cubicles
32302.00 sqft
0.10 /sqft
3.300
.Interior Signage__
32 302.00 sgft _
/sqft
7201
__
Lockers - Metal
_
32 302.00 sqft
_0.02
0.06 /sqft
_
1 800
Fire Protection Specialties-----------
_32,302.00 32,302.00 sqft _
0.01 /sgft
__425i
Toilet Accessories
32,302.00 sqft
0.97 /sqft
31.350
110',Equipment
- .. __.__
__
-
_iAthletic Equipment- _
32 302.00 sgft -
13.25 /sqft ._
_ 428,000
131':Fire Protection
:Fire Sprinkler System _
32,302.00 sqft
1.09 /sqft
35,233_
150_Mechanical . -
- - --
IHVACS_stem_ __, _32,302.00s
Y
9 ft
__6.36/s-fti.
q -
205,481
— ---
PLumbing System
32,302.00 sqft
3.59 /sqft
116,000
1 W Electrical
Electrical System
-. 32.302.00 soft
6.16 /sqft
199,000
Section 5.2.9.1-Page 4
:The Neenan Company Second Sheet of Ice at EPIC 11/29/01
Sub Plan Check Fee
Plan Check Fee
Building Permit
Performance Bond
Gen Liab Ins
Bldrs Risk Ins
Constr Cont.
Preconstruction
Systems Commissioning
Reimbursables Allowance
Interior Design
Civil Engineering
TNC Planning/Landscape Design
Traffic Study
Structural Engineering
Architectural Design
Low E Ceiling
Flourescent Lighting
Bleacher Allowance
OH&P
Estimate Totals
2,724.262 2,724,262
2,440
7.209
1 mi
20,740
2.745,002
26,479
26.479
2,771,481
23,526
1,344
24.870
2,796,351
98,905
19,956
1181861
2,915,212
24,000
13,000
9,150
20,000
13,000
5,000
16,500
132,770
233.420
3,148,632
31,000
2,211
26,650
59,861
3,208,493
152,403
Total
3,360,896
22.000
65.000
0,330
0.700 %
0.040 r
2.943
0.594 i
3.950 °o
4.750
104.046
Section 5.2.9.1 - Page 5
1
Name
Duration
City of Fort Collins Notice to Proceed 1 day 2/16/02 2/18/02 I .
NEENAN PROPOSED DESIGN AND PERMITTING PHASE
101 days
2/18/02
7/11102
General Design Criteria
26 days
2118102
312=2
Core and Shell Space Coordination
37 days
2118/02
419/02
Foundation Coordination (elev 100)
23 days
2/10/02
3121102
Site Coordination
23 days
2/19102
3/21/02
Structure Coordination
26 days
2119Po2
3126102
Skin Coordination
31 days
314102
4/16102
PLANNING/ENGINEERING APPROVAL PROCESS
80 days
3/6102
$126Po2
BUILDING PERMIT PACKAGE
10 days
4118Po2
4I29Po2
BUILDING DEPARTMENT PROCESS
60 days
4130/02
7/11/02
NEENAN PROPOSED CONSTRUC71ON PHASE
148 days
711/02
213103
Pre -Construction Activities
11 days
711IO2
7/17102
Site / Exterior Building
84 days
7112102
11/7/02
Foundations
36 days
7126102
9/13/02
Structure
43 days
8119/02
10117102
MOD 1 - Interior tat Floor
64 days
9/6Po2
J216/02
MOD 3 - Ice Sheet and Ice Equipment Room
96 days
9116102
213103
MOD 2 - Interior 2nd Floor
47 days
10/3IO2
12/10/02
NEENAN PROPOSED GO (Sharpen the Skateslll)
0 days
213/03
2i3/03
Ft: Contract Schedule 0.
2127/02
Epic Ice Rink Addition
Fort Collins, Colorado
Milestone Rolled Up Critical Task >i i S>i<r<[i [ -i [ Split . . ........... .
Task ::::::::::� :.:> - External Tasks . .
Critical Task :€ Summary ^ Rolled Up Milestone Q '
Progress Rolled Up Task Rolled Up Progress Proles Summary
WOMOMW
Group By Summary WMMNMMW
Ed
SECTi0Di 0 0 6 ' 0
PERFORMANCE 33ND
Bond No.103349728
KNOW ALL MEN BY THESE PRESENTS: that
(Firm) THE NEENAN COMPANY
(Address) 2620 E. PROSPECT ROAD, FORT COLLINS, CO 80525
, (a Corporation), hereinafter referred
to as the "Principal" and
(Firm) TRAVELERS CASUALTY AND SURETY COMPANY OF AMEUGA
(Address) ONE TOWER SQUARE HARTFORD CT 06183-6014
hereinafter referred to as "the Surety", are held and firmly bound unto
City of Fort Collins 300 Laporte Ave, Fort Collins, Colorado 80522 a
(Municipal Corporation) hereinafter referred to as the "OWNER", in the
penal sum of ** in lawful money of
the United States, for the payment of which sum well and truly to be
made, we bind ourselves, successors and assigns, jointly and severally,
firmly by these presents.
**THREE MILLION THREE HDNDRED SI%TY THODSAND EIGHT HONORED NINETY SIX AND NO/100--($3,360,896.00)
THE CONDITIONS OF THIS OBLIGATION are such that whereas the Principal
entered into a certain Agreement with the OWNER, dated the 15TH day
of FEBRUARY , 2002, a copy of which is hereto attached and made a part
hereof for the performance of The City of Fort Collins project,
EDORA POOL ICE CENTER (EPIC) - ADDITION - RFP #P-812
NOW, THEREFORE, if the Principal shall well, truly and faithfully perform
its duties, all the undertakings, covenants, terms, conditions and
agreements of said Agreement during the original term thereof, and any
extensions thereof which may be granted by the OWNER, with or without
Notice to the Surety and during the life of the guaranty period, and if
the Principal shall satisfy all claims and demands incurred under such
Agreement, and shall fully indemnify and save harmless the OWNER from all
cost and damages which it may suffer by reason of failure to do so, and
shall reimburse and repay the OWNER all outlay and expense which the
OWNER may incur in making good any default then this obligation shall be
void; otherwise to remain in full force and effect.
7/96 Section 00610
Page 1
PROVIDED, FURTHER, that the said Surety, for value received, hereby
stipulates and agrees that no change, extension of time, alteration or
addition to the terms of the Agreement or to the Work to be performed
thereunder or the Specifications accompanying the same shall in any way
affect its obligation on this bond; and it does hereby waive notice of
any such change, extension of time, alteration or addition to the terms
of the Agreement or to the Work or to the Specifications.
PROVIDED, FURTHER, that no final settlement between the OWNER and the
CONTRACTOR shall abridge the right of any beneficiary hereunder, whose
claim may be unsatisfied.
PROVIDED, FURTHER, that the Surety Company must be authorized to transact
business in the State of Colorado and be acceptable to the OWNER.
IN WITNESS WHEREOF, this
each one of which shall
MARCH , 2002.
IN PRESENCE OF:
(Corporate Seal)
IN PRESENCE OF:
instrument is executed in four (4) counterparts,
be deemed an original, this 6TH day of _
Prin ip 1
THE C MPANY
BY: V-�
(Title)
2620 E. PROSPECT ROAD, FORT COIJINS, CO 80525
(Address)
Other Partners
By:
By:
Surety TRA`�AN/1�y,/,S�
- �ALCY�DRETY C� AMERICA
B
,4NA. FECA�ESTAV; W1 rUKNKY(—FACT
ONE TOWER SODARE, HARTFORD, CT 06183-6014
(Address)
(Surety Seal)
NOTE: Date of Bond must not be prior to date of Agreement. If
CONTRACTOR is Partnership, all partners should execute
Bond.
LOCKTON
7/96 LOCKTONCOMRAMES Section 00610 Page 2
Post Office Box 469000 / Dem eS CO 80246.9000
(303) 753-2000/fax: (303) 753.2099
SECTION 00615
PAYMENT BOND
Bond No. 103349728
KNOW ALL MEN BY THESE PRESENTS: that
(Firm) THE NEENAN COMPANY
(Address) 2620 E. PROSPECT ROAD, FORT COLLINS, CO 80525
( , (a Corporation), hereinafter referred
to as the "Principal" and
(Firm) TRAVELERS CASUALTY AND SURETY COMPANY OF AMERICA
(Address) ONE TOWER SQUARE HARTFORD CT 06183-6014
hereinafter referred to as "the Surety", are held and firmly bound unto
the City of Fort Collins, 300 Laporte Ave., Fort Collins, Colorado 80522
a (Municipal Corporation) hereinafter referred to as "the OWNER", in the
penal sum of ** in lawful money
of the United States, for the payment of which sum well and truly to be
made, we bind ourselves, successors and assigns, jointly and severally,
firmly by these presents.
**THREE MILLION THREE HUNDRED SIXTY THOUSAND EIGHT HUNDRED NINETY SIX AND NO/100—(;3,360,896.00)
THE CONDITIONS OF THIS OBLIGATION are such that whereas the Principal
entered into a certain Agreement with the OWNER, dated the 15TH day
of FEBRUARY , 2002, a copy of which is hereto attached and made a part
hereof for the performance of The City of Fort Collins project,
EDORA POOL ICE CENTER (EPIC) - ADDITION - RFP #P-812
NOW, THEREFORE, if the Principal shall make payment to all persons,
firms, subcontractors, and corporations furnishing materials for or
performing labor in the prosecution of the Work provided for in such
Agreement and any authorized extension or modification thereof, including
all amounts due for materials, lubricants, repairs on machinery,
equipment and tools, consumed, rented or used in connection with the
construction of such Work, and all insurance premiums on said Work, and
for all labor, performed in such Work whether by subcontractor or
otherwise, then this obligation shall be void; otherwise to remain in
full force and effect.
7/96 Section 00615 Page 1
PROVIDED, FURTHER, that the said Surety, for value received, hereby
stipulates and agrees that no change, extension of time, alteration or
addition to the terms of the Agreement or to the Work to be performed
thereunder or the Specifications accompanying the same shall in any way
affect its obligation on this bond; and it does hereby waive notice of
any such change, extension of time, alteration or addition to the terms
of the Agreement or to the Work or to the Specifications.
PROVIDED, FURTHER, that no final settlement between the OWNER and the
CONTRACTOR shall abridge the right of any beneficiary hereunder, whose
claim may be unsatisfied.
PROVIDED, FURTHER, that the Surety Company must be authorized to transact
business in the State of Colorado and be acceptable to the OWNER.
IN WITNESS WHEREOF, this
each one of which shall
MARCH , 2002.
IN PRESENCE OF:
(Corporate Seal)
IN PRESENCE OF:
instrument is executed in four (4) counterparts,
be deemed an original, this 6TH day of _
Prin ip l
THE
By:
Title)
2620 E. PROSPECT ROAD FORT COLLINS, CO 80525
(Address)
Other Partners
IN ?PRESENCE OF
SURETY
'h1rl" A.
TOWER SQUARE, HARTFORD, CT 06183-6014
,dam
(Surety Seal)
NOTE: Date of Bond must not be prior to date of Agreement. If
CONTRACTOR is Partnership, all partners should execute
Bond.
ezm
qMP
LOCIRON
LOCKTON CbMPANILS
7/96 Past Office Box 469000,Denvec,CO80246.9000 Section 00615 Page 2
(303) 753.2000IFix: (303) 753.2099
TRAVELERS CASUALTY AND SURETY COMPANY OF AMERICA
TRAVELERS CASUALTY AND SURETY COMPANY
FARMINGTON CASUALTY COMPANY
Hartford, Connecticut 06183-9062
POWER OF ATTORNEY AND CERTIFICATE OF AUTHORITY OF ATTORNEY(S)-IN-FACT
KNOW ALL PERSONS BY THESE PRESENTS, THAT TRAVELERS CASUALTY AND SURETY COMPANY OF
AMERICA, TRAVELERS CASUALTY AND SURETY COMPANY and FARMINGTON CASUALTY COMPANY,
corporations duly organized under the laws of the State of Connecticut, and having their principal offices in the City of Hartford,
County of Hartford, State of Connecticut, (hereinafter the "Companies") hath made, constituted and appointed, and do by these
presents make, constitute and appoint: William M. O'Connell, Jr., Brad C. Gibson, Debbie Poppe, Shelley Czajkowski, Celeste
T. Moore -Helms, Debbie A. Haslam, Karen A. Feggestad, Garry L. Wesselink, of Denver, Colorado, their true and lawful
Attorney(s)-in-Fact, with full power and authority hereby conferred to sign, execute and acknowledge, at any place within the United
States, the following instrument(s): by his/her sole signature and act, any and all bonds, recognizances, contracts of indemnity, and
other writings obligatory in the nature of a bond, recognizance, or conditional undertaking and any and all consents incident thereto
and to bind the Companies, thereby as fully and to the same extent as if the same were signed by the duly authorized officers of the
Companies, and all the acts of said Attorney(s)-in-Fact, pursuant to the authority herein given, are hereby ratified and confirmed.
This appointment is made under and by authority of the following Standing Resolutions of said Companies, which Resolutions are
now in full force and effect:
VOTED: That the Chairman, the President, any Vice Chairman, any Executive Vice President, any Senior Vice President, any Vice President, any
Second Vice President, the Treasurer, any Assistant Treasurer, the Corporate Secretary or any Assistant Secretary may appoint Attomeys-in-Fact
and Agents to act for and on behalf of the company and may give such appointee such authority as his or her certificate of authority may prescribe
to sign with the Company's name and seal with the Company's seal bonds, recognizances, contracts of indemnity, and other writings obligatory in
the nature of a bond, recognizance, or conditional undertaking, and any of said officers'or the Board of Directors at any time may remove any such
appointee and revoke the power given him or her.
VOTED: That the Chairman, the President, any Vice Chairman, any Executive Vice President, any Senior Vice President or any Vice President
may delegate all or any part of the foregoing authority to one or more officers or employees of this Company, provided that each such delegation is
in writing and a copy thereof is filed in the office of the Secretary.
VOTED: That any bond, recognizance, contract of indemnity, or writing obligatory in the nature of a bond, recognizance, or conditional
undertaking shall be valid and binding upon the Company when (a) signed by the President, any Vice Chairman, any Executive Vice President, any
Senior Vice President or any Vice President, any Second Vice President, the Treasurer, any Assistant Treasurer, the Corporate Secretary or any
Assistant Secretary and duly attested and sealed with the Company's seal by a Secretary or Assistant Secretary, or (b) duly executed (under seal, if
required) by one or more Attomeys-in-Fact and Agents pursuant to the power prescribed in his or her certificate or their certificates of authority or
by one or more Company officers pursuant to a written delegation of authority.
This Power of Attorney and Certificate of Authority is signed and sealed by facsimile (mechanical or printed) under and by
authority of the following Standing Resolution voted by the Boards of Directors of TRAVELERS CASUALTY AND SURETY
COMPANY OF AMERICA, TRAVELERS CASUALTY AND SURETY COMPANY and FARMINGTON CASUALTY
COMPANY, which Resolution is now in full force and effect:
VOTED: That the signature of each of the following officers: President, any Executive Vice President, any Senior Vice President, any Vice
President, any Assistant Vice President, any Secretary, any Assistant Secretary, and the seal of the Company may be affixed by facsimile to any
power of attorney or to any certificate relating thereto appointing Resident Vice Presidents, Resident Assistant Secretaries or Attomeys-in-Fact for
purposes only of executing and attesting bonds and undertakings and other writings obligatory in the nature thereof, and any such power of attorney
or certificate bearing such facsimile signature or facsimile seal shall be valid and binding upon the Company and any such power so executed and
certified by such facsimile signature and facsimile seal shall be valid and binding upon the Company in the future with respect to any bond or
undertaking to which it is attached.
(11-00 Standard)
IN WITNESS WHEREOF, TRAVELERS CASUALTY AND SURETY COMPANY OF AMERICA, TRAVELERS
CASUALTY AND SURETY COMPANY and FARMINGTON CASUALTY COMPANY have caused this instrument to be
signed by their Senior Vice President and their corporate seals to be hereto affixed this 8th day of November 2001.
STATE OF CONNECTICUT
}SS. Hartford
COUNTY OF HARTFORD
.. Yw ,.�SY Ah0 GASU,f
L
NARifDFA� � a NARTFORD, < 2 1 9 8 2 O
TRAVELERS CASUALTY AND SURETY COMPANY OF AMERICA
TRAVELERS CASUALTY AND SURETY COMPANY
FARMINGTON CASUALTY COMPANY
�i"ri`" LIr
George W. Thompson
Senior Vice President
On this 8th day of November, 2001 before me personally came GEORGE W. THOMPSON to me known, who, being by me duly
sworn, did depose and say: that he/she is Senior Vice President of TRAVELERS CASUALTY AND SURETY COMPANY OF
AMERICA, TRAVELERS CASUALTY AND SURETY COMPANY and FARMINGTON CASUALTY COMPANY, the
corporations described in and which executed the above instrument; that he/she knows the seals of said corporations; that the seals
affixed to the said instrument are such corporate seals; and that he/she executed the said instrument on behalf of the corporations by
authority of his/her office under the Standing Resolutions thereof.
� TEl
*LOOS My commission expires June 30, 2006 Notary Public
C'Si' Marie C. Tetreault
CERTIFICATE
I, the undersigned, Assistant Secretary of TRAVELERS CASUALTY AND SURETY COMPANY OF AMERICA,
TRAVELERS CASUALTY AND SURETY COMPANY and FARMINGTON CASUALTY COMPANY, stock corporations of
the State of Connecticut, DO HEREBY CERTIFY that the foregoing and attached Power of Attorney and Certificate of Authority
remains in full force and has not been revoked; and furthermore, that the Standing Resolutions of the Boards of Directors, as set
forth in the Certificate of Authority, are now in force.
Signed and Sealed at the Home Office of the Company, in the City of Hartford, State of Connecticut. Dated this 6TH day of
MARCH , 2002.
xYWxµ 'L(Y ANp rjASU.,f
r.��\1roSWffY� 'J s� r.�ypv�� ry
a NAifrFOflD, � O 1 9 8 2 O
By
KoriM.Johanson
Assistant Secretary, Bond
CONTRACTOR
Insurance.
7/96
Page 1
SECTION 00630
CERTIFICATE OF INSURANCE
shall insert his own standard form
for Certificate of
Section 00630
aCORD CERTIFICATE OF LIABILITY
INSURANCFE OP ID Z
ECO01
DATE IMWDDm)
03/06/02
PRODUCER
THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION
ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE
Lockton Companies of Colorado
4500 Cherry Creek Dr. S., #400
HOLDER. THIS CERTIFICATE DOES NOT AMEND, EXTEND OR
ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW.
INSURERS AFFORDING COVERAGE
- -Ever CO 80246-1532
.Dne:303-753-2000 Fax:303-753-2099
INSURED
INSURER A. ST. PAUL FIRE, MARINE INS. CO
INSURER B: NATIONAL UNION FIRE
INSURER C. Pinnacol Assurance
The Neenan CompanKLLLP M5
2620 E. Prospect Rd. #100
Fort Collins CO 80525
INSURER D'
INSURER E:
COVERAGES
THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTWITHSTANDING
ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR
MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH
POLICIES. AGGREGATE LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS.
INSR
LTR
TYPE OF INSURANCE
POLICY NUMBER
POLICY EFFECTIVE
DATE MWDDm
POLICY EXPIRATION
DATE MWDDm
LIMITS
A
GENERAL LIABILITY
X COMMERCIAL GENERAL LIABILITY
CLAIMS MADE FX] OCCUR
XK08301734
01/01/02
01/01/03
EACH OCCURRENCE
$11000,000
FIRE DAMAGE (Any one fire)
$100,000
MED EXP (Any one person)
$ 5,000
PERSONAL &ADV INJURY
$ 1,000,000
GENERAL AGGREGATE
$ 2,000,000
GENT AGGREGATE LIMIT APPLIES PER:
POLICY X PRO- LOC
ECT
PRODUCTS -COMPIOP AGG
$ 2,000,000
A
AUTOMOBILE
LIABILITY
ANY AUTO
ALL OW NED AUTOS
SCHEDULED AUTOS
HIRED AUTOS
NON -OWNED AUTOS
RK08301734
01/01/02
01/01/03
COMBINED SINGLE LIMIT
(Ea axident)
$ 1, 000, 000
X
BODILY INJURY
(Per person)
$
X
BODILY INJURY
(Peraccident)
$
X
PROPERTY DAMAGE
(Per accident)
S
GARAGE LIABILITY
ANY AUTO
r
AUTOONLY-EAACCIDENT
S
OTHERTHAN EA ACC
AUTO ONLY: AGO
$
$
$
EXCESS LIABILITY
X OCCUR F]CLAIMS MADE
DEDUCTIBLE
RETENTION $
BE1390571
01/01/02
01/01/03
EACH OCCURRENCE
55,000,000
AGGREGATE
$5,000,000
S
$
$
C
WORKERS COMPENSATION AND
EMPLOYERS' LIABILITY
4025258
COLORADO ONLY
01/01/02
01/01/03
IAIU
X TORV LIMITS ER
E.L. EACH ACCIDENT
$100,000
E.L. DISEASE- EA EMPLOYEE$
100, D 00
E.L. DISEASE -POLICY LIMIT
I S500, 000
A
OTHER
Blanket Building
Coverage
CK08308052
01/01/02
01/01/03
Limit $4,635,000
I Ded. $1,000
DESCRIPTION OF OPERATIONSILOCATIONSIVEHICLESIEXCLUSIONS ADDED BY ENDORSEMENTISPECIAL PROVISIONS
RE: Edora Pool Ice Center (EPIC) Project. City of Fort Collins, their
respective officers and employees are included as Additional Insureds.
CERTIFICATE HOLDER Y I ADDRK)NAL INSURED; INSURER LETTER: _ CANCELLATION
CITF006 SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE THE EXPIRATION
City of Fort Collins
Box 580
Fort Collins CO 80522
DATE THEREOF, THE ISSUING INSURER WILL ENDEAVOR TO MAIL 30 DAYS WRITTEN
NOTICE TO THE CERTIFICATE HOLDER NAMED TO THE LEFT, BUT FAILURE TO DO SO SMALL
IMPOSE NO OBLIGATION OR LIABILFTY OF ANY KIND UPON THE INSURER, ITS AGENTS OR
(7197)
SECTION 00635
CERTIFICATE OF SUBSTANTIAL COMPLETION
TO: CITY OF FORT COLLINS
(OWNER)
DATE OF SUBSTANTIAL COMPLETION: PROJECT TITLE:
PROJECT OR SPECIFIED PART SHALL LOCATION: Fort Collins, Colorado
INCLUDE:
OWNER: City of Fort Collins
CONTRACTOR:
CONTRACT
DATE:
The Work performed under this contract has been inspected by authorized
representatives of the OWNER, CONTRACTOR, and the ENGINEER and the
project (or specified part of the project, as indicated above) is hereby
declared to be substantially completed on the above date.
A tentative list of items to be completed or corrected is appended
hereto. This list may not be exhaustive, and the failure to include an
item on it does not alter the responsibility of the CONTRACTOR to
complete all the Work in accordance with the Contract Documents.
ENGINEER AUTHORIZED REPRESENTATIVE
DATE
The CONTRACTOR accepts the above Certificate of Substantial Completion
and agrees to complete and correct the items on the tentative list within
the time indicated.
By:
CONTRACTOR AUTHORIZED REPRESENTATIVE
DATE
The OWNER accepts the project or specified area of the project as
substantially complete and will assume full possession of the project or
specified area of the project at 12:01 a.m., on The
responsibility for heat, utilities, security, and insurance under the
Contract Documents shall be as set forth under "Remarks" below.
CITY OF FORT COLLINS, COLORADO By:
OWNER AUTHORIZED REPRESENTATIVE
DATE
7/96 Section 00635
Page 1
AGREEMENT
THIS AGREEMENT is dated of the 15a' day of February, 2002 by and between the CITY
OF FORT COLLINS, COLORADO, a municipal corporation (hereinafter called OWNER) and The
Neenan Company, a Colorado Corporation (hereinafter called DESIGN/BUILDER).
OWNER AND DESIGN/BUILDER, in consideration of the mutual covenants hereinafter
set forth, agree as follows:
Article 1. WORK
1.01 DESIGNBUILDER shall complete all Work as specified or indicated in the Owner-
Design/Builder Contract Documents. The Work is generally described as follows: design and
construction of a second sheet of ice at EPIC.
Article 2. THE PROJECT
2.01 The design and construction of an approximately 32,302 square foot addition to the Edora
Pool Ice Center (EPIC) to house a full size ice arena and associated facilities and equipment as
depicted in the DESIGN/BBUILDER'S response to RFP P-812.
Article 3. CONTRACT TIMES
3.01 Days to Achieve Substantial Completion and Final Payment
The Work will be substantially completed within 249 work days after the date when the
Contract Times commence to run as provided in paragraph 2.02.A of the General Conditions and
completed and ready for final payment in accordance with paragraph 13.09 of the General
Conditions within 284 work days after the date when the Contract Times commence to run.
3.02 Liquidated Damages
A. DESIGNBUILDER and OWNER recognize that time is of the essence and the OWNER
will suffer financial loss if the Work is not completed within the times specified in paragraph 3.01
above, plus any extensions thereof allowed in accordance with Article 11 of the General Conditions.
The parties also recognize the delays, expenses and difficulties involved in proving the actual loss
suffered by OWNER if the Work is not completed on time. Accordingly, instead of requiring any
such proof, OWNER and DESIGN/BUILDER agree that as liquidated damages for delay (but not
as a penalty) DESIGNBUILDER shall pay OWNER Two Thousand Dollars ($2,000.00) for each
day that expires after the time specified in paragraph 3.01.
SECTION 00640
CERTIFICATE OF FINAL ACCEPTANCE
, 20
TO:
Gentlemen:
You are hereby notified that on the day of , 20_, the
City of Fort Collins, Colorado, has accepted the Work completed by _
for the City of Fort Collins
project,
A check is attached hereto in the amount of $ as Final
Payment for all Work done, subject to the terms of the Contract Documents
which are dated
In conformance with the Contract Documents for this project, your
obligations and guarantees will continue for the specified time from the
following date:
Sincerely,
OWNER: City of Fort Collins
By:
Title:
ATTEST:
Title:
7/96 Section 00640 Page 1
SECTION 00650
LIEN WAIVER RELEASE
(CONTRACTOR)
TO: City of Fort Collins, Colorado (OWNER)
fa.�r59
PROJECT:
(CONTRACTOR)
1. The CONTRACTOR acknowledges having received payment, except
retainage from the OWNER for all work, labor, skill and material
furnished, delivered and performed by the CONTRACTOR for the OWNER
or for anyone in the construction, design, improvement, alteration,
addition or repair of the above described project.
2. In consideration of such payment and other good and valuable
consideration, the receipt and adequacy of which are hereby
acknowledged, the CONTRACTOR voluntarily waives all rights, claims
and liens, including but not limited to, mechanic's liens, Miller
Act claims (40 U.S.C.A. 270 a and b), stop notices, equitable liens
and labor and material bond rights which the CONTRACTOR may now or
may afterward have, claim or assert for all and any work, labor,
skill or materials furnished, delivered or performed for the
construction, design, improvement, alteration, addition or repair
of the above described project, against the OWNER or its officers,
agents, employees or assigns, against any fund of or in the
possession or control of the OWNER, against the project or against
all land and the buildings on and appurtenances to the land improved
by the project.
3. The CONTRACTOR affirms that all work, labor and materials,
furnished, delivered or performed to or for the construction,
design, improvement, alteration, addition or repair of the project
were furnished, delivered or performed by the CONTRACTOR or its
agents, employees, and servants, or by and through the CONTRACTOR
by various Subcontractors or materialmen or their agents, employees
and servants and further affirms the same have been paid in full and
have released in full any and all existing or possible future
mechanic's liens or rights or claims against the project or any
funds in the OWNER'S possession or control concerning the project
or against the OWNER or its officers, agents, employees or assigns
arising out of the project.
4. The CONTRACTOR agrees to defend and hold harmless the OWNER, the
lender, if any, and the Surety on the project against and from any
claim hereinafter made by the CONTRACTOR'S Subcontractors,
materialmen, employees, servants, agents or assigns against the
project or against the OWNER or its officers, employees, agents or
assigns arising out of the project for all loss, damage and costs,
7/96 Section 00650 Page 1
including reasonable attorneys fees, incurred as a result of such
claims.
5. The parties acknowledge that the description of the project set
forth above constitutes and adequate description of the property and
improvements to which this Lien Waiver Release pertains. It is
further acknowledged that this Lien Waiver Release is for the
benefit of and may be relied upon by the OWNER, the lender, if any,
and Surety on any labor and material bonds for the project.
Signed this
ATTEST:
Secretary
STATE OF COLORADO
COUNTY OF LARIMER
day of
CONTRACTOR
By:
Title:
Subscribed and sworn to before me this
20 , by
Witness my hand and official seal.
My Commission Expires:
20
day of
Notary Public
7/96 Section 00650 Page 2
SECTION 00660
CONSENT OF SURETY
TO: City of Fort Collins, Colorado
(hereinafter referred to as the "OWNER")
CONTRACTOR:
PROJECT:
CONTRACT DATE:
In accordance with the provisions of the Contract between the OWNER and
the CONTRACTOR as indicated above, for
on bond of (Surety
hereby approves of the Final
Payment to the CONTRACTOR, and agrees that Final Payment to the
CONTRACTOR shall not relieve the Surety Company of any of its obligations
to the OWNER, as set forth in the said Surety Company's Bond.
IN WITNESS WHEREOF, the Surety Company has hereunto set its hand this
day of
(Surety Company)
0
ATTACH: Power of Attorney and Certificate of Authority of Attorney(s)-
in-Fact.
7/96 Section 00660 Page 1
SECTION 00670
APPLICATION FOR EXEMPTION CERTIFICATE
Insert State certificate here.
7/96 Section 00635
Page 0
DR 0172 (12198)
COLORADO DEPARTMENT OF REVENUE
D
l
L
ENVER C080261 CONTRACTOR APPLICATION
303)
232-241 B
FOR
EXEMPTION CERTIFICATE
PursuanttoStatute
Section 39-2 J. .11 I Y(l )(a)(M)
DO NOT WRITE IN THIS SPACE
The exemption certificate for which you are applying must be used only for the purpose of purchasing construction and building
materials for the exempt projectdescribed below. This exemption does not include or apply to the purchase or rental of equipment,
supplies, and materials which are purchased, rented, or consumed by the contractor and which do not become a part of the
structure, highway, road, street, or other public works owned and used by the exempt organization.
Anyunauthorized use of the exemption certificate will result in revocation of your exemption certificate and otherpenalties provided
by law.
A separate certificate is required for each contract.
Subcontractors will not be issued Certificates of Exemption by the Department of Revenue. It is the responsibility of the prime
contractor to Issue certificates to each of the subcontractors. (See reverse side.)
FAILURE TO ACCURATELY COMPLETE ALL BOXES WILL CAUSE THE APPLICATION TO BE DENIED.
RogWmtiordAcoount No. (to be assigned by DOR)
Period
0170-750 (999) $0.00
89 -
Trade name/DB
Owner, partner, or corporate name.
Mailing address (City, State, Zip): -
Dontact Person
E-Mail address:
Federal Employefs Identification Number:
Bid amount for your contract
Fax number.
Business telephone number:
Colorado withholding tax account number:
1=.�,.: PI .. ...c
irg i ed_
el?d'(21#:. RIt19 9. rfcoti
Name of exempt organization (as shown on contract): Exempt organization's number:
98 -
Address of exempt organization (City, State, Zip):
Principal contact at exempt organization:
Principal contact's telephone number:
Physical location of project site (give actual address when applicable and Cities and/or County (ies) where project is located)
Scheduled Month Day Year
Estimated Month Day Year
construction start date:
completion date:
, A
-'An�yty}�' f��� l � 5
£.dt�'+'er`' �'•` �.:
I^,iW `• 1' § nYf:. S ifj i�t 4 3 5afll .,. y':.: `�.�Y s .. � �d.X��,iYt �=.M" f V'E..Et .�b / . A3. 1
k,
1 declare under penalty of perjury in the second degree that the statements made in this application are true and
complete to the best of my knowledge.
Signature of owner, partner or corporate officer: Title of corporate officer:
Date:
DO NOT WRITE BELOW THIS LINE
STANDARD GENERAL CONDITIONS
OF THE
CONTRACT BETWEEN OWNER AND DESIGN/BUILDER
TABLE OF CONTENTS
ARTICLE 1--11EFINPageIIT
ONS
1.01 ....................
DefinedTerms ........ ........................................
ARTICLE 2-.PRELIA]NARY MATTERS .................
2.01
Delivery of Bonds .............
2.02
2.03
............. .
Commencement of Contract Times; Notice to Proce............
Starting the Work ed ..........• • • • •
2.04
.......... ..........................
Before Starting Construction
2.05
Initial Conference
- 2.06
.Sc......... .
Initially Acceptable hedules
............ . .
. .
ARTICLE 3-CONTRACT DOCUMENTS:
INTENT, AMENDING, REUSE .....................
Intent................
33.01
.02
.
References ......................
.............
3.03
3•04
.
Amending and Supplementing Contract Documents . . . . . . . . ' •
Reuse of Documents ....:. " " " " ... • • • • • . • • • • .............
............ .............
ARTICLE 4-AVAILABILTIZ• OF LANDS; DIFFERING SITE CONDITIONS; REFERENCE
POINTS; HAZARDOUS CONDITIONS
4.01
........ . ...........................
Availability of Lands
4.02
...............
Differing Site Conditions . . . • ' . ' ' ' ' ' ' • ' • • • • • • • • • • .
4.03
.................................
Reference Points
4.04
Hazardous Conditions
ons......... ......... I.............................
_
ARTICLE 5--BONDS AND INSURANCE
5.01
5.02
............ .
Performance, Pa " ........• • • • • Payment Other Bonds
5.03
........................
DESIGN/BUII-DER's Liability Insurance
5.04
............................ .
OWNER's Liability Insurance .....................
Property Insurance .
5.05
......,
Waiver of Rights .............. " " " ' ............
5.06
Receipt and Application of Proceeds
5.07
5.08
Acceptance of Bonds and Insurance; Option to Replace .................
Partial Utilization-Property
Insurance5.09 Licensed Sureties and Insurers;
Certificates of Insurance ..............
.
ARTICLE 6-• DESIGNBUH,DER'SRESPONSIBII,TI7ES..,,,,,••,..•••.•_•..••••••,...•.•'
6.01
Design Professional Services
6.02
6.03
. , , , , • .
Supervision and Superintendence of Construction
Labor, Materials and Equipment
6.04
Progress Schedule :...........
6.05
6.06
.
Concerning Subcontractors, Suppliers and Others
...... .
Patent Fees and Royalties
6.07
.......................................
Permits ...............
6.08
. .. . .
...............
Laws and Regulations ..........
6.09
Taxes ............
6.10
Use of Site and Other Areas " " " " " • . •
6.11
Record Documents ......... ....................................
i
1
1
4
4
4
4
S
5
5
I
7
7
7
8
8
9
9
9
10
10
11
12
12
12
12
13
13
14
14
14
15
15
16.
16
16
16
17
6.12
Safety and Protection ..........................................
17
6.13
Safety Representative ...........................................
6.14
Hazard Communication Programs
17
6.15
..................................
Emergencies ..........................
17
6.16
.............. ..........
Submittals
17
6.17
...................................................
Continuing the Work
18
6.18
...........................................
DESIGNBUILDER's General Warranty and Guarantee ................
18
18
6.19
Indemnification
..............................................
19
ARTICLE 7--OTHER
CONSTRUCTION
7.01
...............................................
Related Construction at Site
19
7.02
......................................
Coordination
19
.................................................
20
ARTICLE 8--OWNER'S RESPONSIBILITIES
, , , , , , , , , , , , , , • • • . , , • • • • .................
.01 General
20
.............:.......
8.02 Scope of OWNER's Safety and Hazardous Waste Responsibilities
20
21
8.03 Resident Project Representation ...................................
21
ARTICLE 9--CHANGES IN THE WORM, CLAIMS
.......................................
9.01 General --Rights and Obligations ...................................
21
21
9.02 Notice of Intent to Make Claim ................. . .................
21
9.03 Claim Documentation ...........................................
22
9.04 Decision .........................................
............
22
9.05 Time Limit Extension ...........................................
22
9.06 Exceptions ....... .............................
22
9.07 Execution of Change Orders ..................... .
22
...
9.08 Notice to Sureties ..............................................
22
ARTICLE 10--CHANGE OF CONTRACT PRICE
........................................:
10.01 General
22
.....................................................
10.02 Cost of the Work .. , ...... .
22
10.03 Cash Allowances ...............................................
25
10.04 Unit Prices ...................................................
25
ARTICLE 11--CHANGE OF CONTRACT TIMES
......................................
11.01 General
26
.....................................................
11.02 Time Extensions ...............................................
26
26
ARTICLE 12-TESTS AND INSPECTIONS; CORRECTION, REMOVAL OR ACCEPTANCE OF
DEFECTIVE CONSTRUCTION
..............................................
12.01 Notice of Defects ..............................................
26
26
12.02 Access to Construction ...........:...............................
27
12.03 Tests and Inspections ...........................................
12.04 Uncovering Construction ........................................
27
27
12.05 Owner May Stop the Construction
.................................
12.07 Correction or Removal of Defective Construction
27
......................
12.07 Correction Period ..............................................
28
28
12.08 Acceptance of Defective Construction ........ I ......... I .......
28
I ....
12.09 OWNER May Correct Defective Construction
............. I ..........
28
ii
_ ARTICLE 13--PAYMENTS TO DESIGN/BUH,DERAND
13.01
COMPLETION .
Schedule of Values .....................
13.02
13.03
..... , ,
Application for Progress Payment ....
DESIGNB..............................
13.04
Warranty of Title ..... , • , .
Progress Payments ...................
13.05
, , ,
Substantial Completion ........... ...............
.06
.......... .
Partial Utilisation .....................
13.07
.......... .
Final Inspection ' • " " . * .... • . • • • • • .
OS
13.10
..........................:.
Final Application for Payment ..................
Final Payment and Acceptance
13.10
.... •' ............
Waiver of Claims ' ' ' ' ' ' ' ' ...............
ARTICLE 14--SUSPENSION OF WORK AND TERMINATION(
14.01
, '
Owner May Suspend Work
14.02
14.03
Owner May Terminate for Cause . . . . '
............. ................. •
Owner May Terminate
14.04
for Con n
DESIGN/BUILDER May • •
StopveWork • • ..... ' ' ' ' ' '
or Terminate .
ARTICLEI5-- ...................
DISPUTE RES
ARTICLE 16--MISCEOLUTION ...............................................
LLANEOUS
16.01 .............
Giving Notice ..... � � � � � � � � "
.................... 16.02 Computation of Times ..................
16.03 Notice of Claim .. . ..................... • ........ . ...........
16.04
Cumulative Remedies . ... ... ................................... .
.... 16.05 Survival of Obligations ...... .
...............................
E 1BIT GC -A to GENERAL CONDITIONS DESIGNBUILDER DATED OF THE AGREEMENT BETWEEN OWNER AND
15.01 Dispute Resolutiontion Agreement
.. ' ' ' ' ' ' • • .
..........................
iii
29
29
29
29
30
30
31
31
31
32
32
32
32
32
33
34
34
34
34
34
34
35
35
36
36
Article 4. CONTRACT PRICE
4.01 OWNER shall pay DESIGN/BUILDER for completion of the Work in accordance with the
Contract Documents a sum equal to the Cost of the Work plus a DESIGN/BUILDER'S Fee for
overhead and profit, both of which shall be determined as provided below.
Article 5. COST OF THE WORK
5.01 Cost of the Work shall be determined as provided in paragraphs 10.02.A and B of the
General Conditions, but, in addition to any limitations therein set forth, it shall not include costs in
excess of any Guaranteed Maximum Contract Price as set forth in Article 7 hereof.
Article 6. DESIGN/BUILDER'S FEE
6.01 The DESIGNBUILDER's Fee shall be determined as follows:
A. A fixed fee of $ N/A which shall be subject to increases or decreases for changes in
the Work as provided in paragraph 8.01 below.
B. No fee shall be paid for costs listed in paragraph 10.02.13 of the General Conditions.
C. DESIGN/BUILDER guarantees that the maximum amount payable by OWNER in
accordance with this paragraph 6.01 as a percentage fee will not exceed $ N/A
subject to increases or decreases for changes in the Work as provided in paragraph
8.01 below.
Article 7. GUARANTEED MAXIMUM PRICE
7.01 DESIGNBUILDER guarantees that the maximum obligation of OWNER for the sum of the
Cost of the Work plus the DESIGNBUILDER's Fee will not exceed Three Million, Three Hundred
Sixty Thousand, Eight Hundred Ninety-six Dollars ($3,360,896) (the "GMP") subject to increases
or decreases for changes in the Work. Any unused contingency shall be shared as provided in
Paragraph 7.02.
7.02 In the event that the Cost of the Work plus the DESIGN/BUILDER'S Fee shall be less than
the GMP, as adjusted by Change Orders, the resulting Savings shall be shared by the OWNER and
the DESIGNBUILDER as follows:
A. OWNER shall be entitled to Seventy-five percent (75%) of the Savings;
B. DESIGNBUILDER shall be entitled to Twenty-five percent (25%) of the Savings,
at the time of Final Payment.
C. Except all savings from the Bleacher Allowance will be credited 100% to the
OWNER.
Note: A marginal arrow in these General Conditions indicates a paragraph or
section that has been revised or added to in the Supplementary Conditions,
and is shown for the convenience of the reader only. Any use of these
General Conditions must include the complete interrelationship with the
Supplementary Conditions and the Contract Documents.
GENERAL CONDITIONS
ARTICLE 1--DEFINITIONS
1.01 Defined Terms
A. Wherever used in these General Conditions or
in the other Contract Documents the following terms
have the meanings indicated which are applicable to
both the singular and plural thereof:
I. Addenda --Written or graphic instruments
issued prior to the opening of Proposals which
clarify, correct or change the Request for Proposals
or the Contract Documents.
2. Agreement --The written contract between
OWNER and DESIGNBUILDER covering the
Work; other Contract Documents are attached to
_._ the Agreement and made a part thereof as provided
therein,
3. Application for Payment --The form which is
to be used by DESIGNBUILDER in requesting
progress or final payments and which is to be
accompanied by such supporting documentation as
is required by the Contract Documents.
4. Asbestos --Any material that contains more
than one percent asbestos and is friable or is
releasing asbestos fibers into the air above current
action levels established by the United States
Occupational Safety and Health Administration.
5. Bonds --Performance and payment bonds
and other instruments of security,
6. Cash Flow Projection --A schedule prepared
by DESIGNBUILDER estimating that portion of
the Contract Price to be due during each month of
performance.
7. Change Order --A written order which is
signed by DESIGNBUILDER and OWNER
which authorizes an addition, deletion or revision in
the Work or an adjustment in the Contract Price
or the Contract Times, issued on or after the
Effective Date of the Agreement.
8• Conceptual Doluments--The
specifications and/or other graphic drawings
t written
OWNials, criteria and ER's reinformation requirements for Project,, suchtas design objectives and constraints, space, capacity
and performance requirements, flexibility and
expandability, including those items enumerated in
the Request for Proposals which show or describe
the character and scope of, or relate to, the Work
to be performed or furnished and which have been
prepared by or for OWNER.
9. Construction --The performing or furnishing
Of labor, the furnishing and incorporating of
materials and equipment into the Work and the
furnishing of services (other than Design
Professional Services) and documents, all as
required by the Contract Documents.
10. Construction Subagreemenr--A written
agreement between DESIGNBUILDER and a
construction contractor for provision of
Construction.
IL Contract Documents --The Agreement, the
Conceptual Documents, Addenda (which pertain to
the Contract Documents), DESIGNBUILDER's
Proposal, the Notice to Proceed, the Bonds, these
General Conditions, the Supplementary Conditions,
the Specifications and the Drawings together with
III Work Change Directives, Change Orders, Written Amendments, and Field Orders, issued on or after the Effective Date of the Agreement. The
Contract Documents also include those documents
specifically identified by the OWNER in the
Request for Proposals.
12. Contract Price --The moneys payable by
OWNER to DESIGNBUILDER for completion of
the Work in accordance with the Contract
Documents.
13. Contract Times --The numbers of days or
he dates stated in the Agreement (i) to achieve
Substantial Completion, and (ii) to complete the
Work so that it is ready for final payment in
accordance with paragraph 13.08.A.
ec14. defective --An adjective which when
odifying the term Construction refers to
onstructio❑ that is unsatisfactory, faulty or'
deficient, in that it does not conform to the
Contract Documents, or does not meet the
requirements of any inspection, reference standard,
test or approval referred to in the Contract
Documents, or has been damaged prior to
OWNER'S final payment (unless responsibility for
the protection thereof has been assumed by
OWNER at Substantial Completion).
15. DESIGN/BUILDER--The individual or
entity with whom OWNER has entered into the
Agreement.
16. Design Subagreement--A written agreement
between DESIGNBUILDER and a design
professional for provision of Design Professional
Services.
17. Design Professional Services --Services
related to the preparation of Drawings,
Specifications, and other design submittals specified
by the Contract Documents and required to be
performed by licensed design professionals, as well
as services provided by or for licensed design
professionals during Bidding/Negotiating,
Construction, or Operational phases.
18. Drawings --Those portions of the Contract
Documents prepared by or for DESIGNBUILDER
and approved by OWNER consisting of drawings,
diagrams; illustrations, schedules and other data
which show the scope, extent, and character of the
Work.
19. Effective Date of the Agreement --The date
indicated in the Agreement on which it becomes
effective, but if no such date is indicated it means
the date on which the Agreement is signed and
delivered by the last of the two parties to sign and
deliver.
20. Engineer --A duly licensed individual or
entity designated by DESIGN/BUILDER to
perform or furnish specified Design Professional
Services in connection with the Work.
21. Field Order --A written order issued by
OWNER which orders minor changes in the Work
but which does not involve a change in the
Contract Price or the Contract Times.
22. Hazardous Condition —The presence at the
Site of Asbestos, Hazardous Waste, PCBs,
Petroleum Products or Radioactive Materials in
such quantities or circumstances that there is a
danger to persons or property.
e123. Hazardous Woste--The term Hazardous
Waste shall have the meaning provided in Section
004 of the Solid Waste Disposal Act (42 USC
Section 6903).
24. Laws and Regulations Laws orRegulations—
Any and all applicable laws, rules, regulations,
ordinances, codes and orders of any and all
governmental bodies, agencies, authorities and
courts having jurisdiction.
25. Liens --Charges, security interests or
encumbrances upon real property or personal
property.
26. Milestone --A principal event specified in the
Contract Documents relating to an intermediate
completion date or time prior to Substantial
Completion of all the Work.
27. Notice of Award --The written notice by
OWNER to the successful proposer stating that
upon compliance by the successful proposer with
the conditions precedent enumerated therein,
within the time specified, OWNER will sign and
deliver the Agreement.
2
28. Notice to Proceed --A written notice given by
OWNER to DESIGNBUILDERfixingthe dateon
which the Contract Times will commence to run.
29, OWNER --The public body, or authority,
individual or entity with whom
OESIGN/BUILAgreement D enteredER has
andfor whom the Work tisoto the
provided.
30, OWNER's Consultant --An individual or
entity having a contract with OWNER to furnish
servicesas OWNER's consultantwith respect to the
Project and who is identified as such in the
Supplementary Conditions.
31, OWNER's Representative --A person
designated in writing to act as OWNER's
representative with respect to
DESIGNBUI DER's performance of the Work.
Such person shall have complete authority to
transmit instructions, receive information, interpret
and define OWNER's policies, make decisions with
respect to performance of the Work, and provide
such other services as may be agreed upon,
32. Partial Utilization --Use by OWNER of a
substantially completed part of the Work for the
.purpose for which it is intended (or a related
Purpose) prior to Substantial Completion of all the
Work.
33. PCBs --Polychlorinated biphenyls.
34. Petroleum --Petroleum, including crude oil
or any fraction thereof which is liquid at standard
conditions of temperature and pressure (60 degrees
Fahrenheit and 14.7 pounds per square inch
absolute), such as oil, petroleum, fuel oil, oil
sludge, oil refuse, gasoline, kerosene, and oil mixed
with other non -Hazardous Wastes and crude oils.
35, Project --The total construction of which the
Construction to be provided under the Contract
Documents may be the whole, or a part as
indicated elsewhere in the Contract Documents.
36. Proposal --The documents submitted by
DESI,GNBUILDER in response to the Request
for Proposals setting forth the design concepts,
proposed prices, and other conditions for the Work
to be performed.
37. Radioactive Material --Source, special
nuclear, or byproduct material as defined by the
Atomic Energy Act of 1954 (42 USC Section 2011
et seq.) as amended from time to time.
38. Request for Proposals --The document
prepared by or, for OWNER specifying and
describing OWNER's objectives and the procedure
to be followed in preparing and submitting a
Proposal and awarding a contract.
39. Resident Project Representative --The
authorized representative of OWNER who may be
assigned to the Site or any part thereof.
40. Schedule of Values --A schedule prepared by
DESIGNBUILDER and acceptable to OWNER
indicating that portion of the Contract Price to be
paid for each major component of the Work.
41, Sue --Lands or other areas designated in the Contract Documents as being furnished by
OWNER for the performance of the Construction,
storage, or access.
42• Specifications --Those portions of the
Contract Documents prepared by or for
DESIGNBUILDER and approved by OWNER
consisting of written technical descriptions of
materials, equipment, construction systems,
standards and workmanship as applied the
Construction and certain administrative details
applicable thereto.
43. Subcontractor --An individual or entity other
than a Supplier or Engineer having a direct
contract with DESIGNBUILDER or with any
other Subcontractor for the performance of a part
of the Work.
44. Submittal --A written or graphic document
prepared by or for DESIGNBUILDER which is
3
required by the Contract Documents to be
submitted to OWNER by DESIGNBUILDER.
Submittals may include Drawings, Specifications,
progress schedules, shop drawings, samples, Cash
Flow Projections, and Schedules of Values.
Submittals other than Drawings and Specifications
are not Contact Documents.
45. Substantial Completion --The time at which
the Construction (or a specified part) has
progressed to the point where it is sufficiently
complete, in accordance with the Contract
Documents, so that the Construction (or a specified
part) can be utilized for the purposes for which it is
intended. The terms "substantially complete" and
"substantially completed" as applied to all or part of
the Construction refer to Substantial Completion
thereof.
46. Supplementary Conditions --The part of the
Contract Documents which amends or supplements
these General Conditions.
47. Supplier --A manufacturer, fabricator,
supplier, distributor, materialman or vendor having
a direct contract with DESIGNBUILDER or with
any Subcontractor to furnish materials or
equipment to be incorporated in the Work by
DESIGNBUILDER or any Subcontractor.
48. Unit Price Work --Work to be paid for on
the basis of unit prices.
49. Work --The entire completed construction or
the various separately identifiable parts thereof
required to be performed or furnished under the
Contact Documents. Work includes and is the
result of performing or furnishing Design
Professional Services and Construction required by
the Contract Documents.
50. Work Change Directive --A written directive
to DESIGNBUILDER, issued on or after the
Effective Date of the Agreement and signed by
OWNER ordering an addition, deletion or revision
in the Work, or responding to differing site
conditions under which the Work is to be
performed as provided in paragraph 4.02 or to
emergencies under paragraph 6.15. A Work
Change Directive will not change the Contract
Price or the Contract Times, but is evidence that
the parties expect that the change directed or
documented by a Work Change Directive will be
incorporated in a subsequently issued Change
Order following negotiations by the parties as to its
effect, if any, on the Contract Price or Contract
Times.
51. Written Amendment --A written amendment
of the Contract Documents, signed by OWNER
and DESIGNBUILDER on or after the Effective
Date of the Agreement and normally dealing with
the nonengineering or nontechnical rather than
strictly design or construction -related aspects of the
Contract Documents.
ARTICLE 2--PRELEVIINARY MATTERS
2.01 Delivery of Bonds
A. When DESIGNBUILDER delivers the
executed Agreements to OWNER,
DESIGNBUILDER shall also deliver to OWNER
such Bonds as DESIGN/ BUILDER may be required
to furnish in accordance with paragraph 5.01.A.
2.02 Commencement of Contract Timer Notice to
Proceed
A. The Contract Times will commence to run on
the thirtieth day after the Effective Date of the
Agreement, or,.if a Notice to Proceed is given, on the
day indicated in the Notice to Proceed. A Notice to
Proceed may given at any time within thirty days
after the Effective Date of the Agreement. in as @4 elti
Will the Goal -- ---
'e -
2.03 Starting the Work
A. DESIGNBUILDER shall start to perform the
Work on the date when the Contract Times ence
o run. comm
2 04 Before Stav ng Construction
ItA DESIGN/BUILDER shall submit the following
for review within ten days after commencement of the
Contract Times:
I. A preliminary progress schedule indicating
the times (numbers of days or dates) for starting
and completing the various stages of the Work
including each Milestone specified in the Contract
Documents;
2. A preliminary schedule of required
Submittals and the times for submitting, reviewing
and processing each Submittal;
3. A preliminary Schedule of Values for all of
the Work which will include quantities and prices of
items aggregating the Contract Price and will
subdivide the Work into component parts sufficient detail to serve as the basis for proin
ss Payments during performance of the Work gre
Such
prices will include a pro rasa amount of overhead
and profit applicable to each item of Work; and
4. A Preliminary Cash Flow projection.
B.
to the er, with copies to addition
identifiediat lementa each
ured
of insurance and of ry s,certificates
vi e of insurance which
either of them o
reasonably r st) which DESItonal insured may
OW respectively are required to ut and
. P and
2.05 Initial Conference
A Within twenty days after the Contract Times
start to run a conference attended by OWNER and
DESIGN/BUILDER and others as appropriate will be
held to establish a working understanding among the
parties as to the Work and to discuss the design
concepts, schedules referred to in paragraph 2s, process.04. procedures for handling Submittals,
Applications for Payment, maintaining required
records, items required pursuant to paragraph 8.0I.A.6
and other matters.
2.06 Initially Acceptable Schedules
�-94- DESIGNBUILDER shall have an additiona:
ten days to make corrections and adjustments and to
complete and resubmit the schedules. No progress
Payment shall be made to DESIGNBUILDER until
the schedules are submitted to and acceptable to
OWNER as provided below. The progress schedule
Will be acceptable to OWNER as providing an orderly
Progression of the Work to completion within. any
specified Milestones and the Contract Times, but such
acceptance will neither impose on OWNER
responsibility for the sequencing, scheduling Progress of the Work nor interfere with or relieve
DESIGNBUILDER from DESIGNBUILDER's fun
responsibility therefor. The format and structure of
the progress schedule will be as set forth in the
Contract Documents. OWNER's acceptance shall not
be deemed to confirm that the schedule is a reasonable
plan for performing the Work. DESIGNBUILDER's
schedule of Submittals will be acceptable to OWNER
as providing a workable arrangement for reviewing and
processing the required Submittals.
DESIGNBUILDER's Schedule of Values and Cash
Flow Projection will be acceptable to OWNER as to
form and substance.
ARTICLE 3--CONTRACT DOCUMENTS: INTENT,
AMENDING, REUSE
3.01 Intent
A. The Contract Documents comprise the entire
agreementbetween OWNER and DESIGNBUILDER
concerning the Work. The Contract Documents are
complementary; what is called for by one is as binding
as if called for by all. The Contract Documents will be
construed in accordance with the law of the place of
the Project.
B. It is the intent of the Contract Documents to
describe a functionally complete Project (or pari
thereof) to be designed and constructed in accordance
with the Contract Documents. Any Work, materials or
equipment that may reasonably be inferred from the
Contract Documents or from prevailing custom or
trade usage as being required to produce the intended
result will be furnished and performed whether or not
specifically called for. When words or phrases which
have a well-known technical or construction industry or
trade meaning are used to describe work, materials or
equipment, such words or phrases shall be interpreted
in 4taccordance with that meaning.
.02 References
A. Reference to standards, specifications, manuals or
codes of any technical society, organization or
association, or to the Laws or Regulations of any
governmental authority, whether such reference be
specific or by implication, shall mean the latest
standard, specification, manual, code or Laws or
Regulations is 499e; en the jest do) fei jeeeik,! OF
B. Except as otherwise specifically stated in the
Contract Documents or as may be provided by
amendment or supplement thereto issued by one of the
methods indicated in paragraph 3.03.A , the provisions
of the Contract Documents shall take precedence in
resolving any conflict, error, ambiguity or discrepancy
between the provisions of the Contract Documents
and:
I. the provisions of any such standard,
specification, manual, code or instruction (whether
or not specifically incorporated by reference in the
Contract Documents); or
2. the provisions of any such Laws or
Regulations applicable to the performance of the
Work (unless such an interpretation of the
provisions of the Contract Documents would result
in violation of such Law or Regulation).
C. No provision of any such standard, specification,
manual, code or instruction shall be effective to change
the duties and responsibilities of OWNER,
DESIGNBUILDER or any of their subcontractors,
consultants, agents, or employees from those set forth
in the Contract Documents, nor shall it be effective to
assign to OWNER any duty or authority to supervise
or direct the furnishing or performance of the Work or
any duty or authority to undertake responsibility
inconsistent with the provisions of paragraph 8.02 or
eany other provision of the Contract Documents.
3.03 Amending and Supplementing Contract
Documents
A. The Contract Documents may be amended to
provide for additions, deletions and revisions in the
Work or to modify the terms and conditions thereof in
one or more of the following ways:
1. OWNE'R's approval of required Submittals
(pursuant to paragraph 6.16.13);
2. A Work Change Directive;
3. A Change Order•,
4. A formal Written Amendment; or
5. A Field Order.
3.04 Reuse of Documents
A. All documents including Drawings and
Specifications prepared or furnished by
DESIGNBUILDER pursuant to this Agreement are
instruments of service in respect of the Project and
DESIGNBUILDER shall retain an ownership and
property interest therein whether or not the Project is
completed. OWNER may make and retain copies for
information and reference in connection with the use
and occupancy of the Project by OWNER and others;
however, such documents are not intended or
represented to be suitable for reuse by OWNER or
others on extensions of the Project or on any other
Project. Any reuse without written verification or
adaptation by DESIGNBUILDER for the specific
Purpose intended will be at OWNER's sole risk and
without liability or legal exposure to
DESIGNBUILDER and OWNER shall indemnify and
hold harmless DESIGNBUILDER, Subcontractors,
and Engineer from all claims, damages, losses and
expenses including attorneys' fees arising out of or
resulting therefrom. Any such verification or
adaptation will entitle DESIGNBUILDER to further
compensation. at rates to be agreed upon by OWNER
and DESIGNBUILDER.
RTICLE 4--AVAILABILITY OF
tDIFFERDVG SITE CONDITIONS; LANDS;
DINTS; HAZARDOUS CONDITIONSNCE
4.01 Availability of Lands
A. OWNER shall furnish, as indicated in the
Contract Documents, the lands upon which the
Construction is to . be performed, rights -of -way and
easements for access thereto, and such other lands
which are designated for the use of
DESIGNBUILDER.
cord legal title and le a
the ]ands u on, tption of
P the truction is to be
Performed and p ' s inte erein as necessary
for giI- ue of'o I filing a mechanic aoa;n ,
OWNER shall identify any encumbrances
or restrictions not of general application but
specifically related to use of lands so furnished with
which DESIGNBUILDER will have to comply in
Performing the Work. Easements for permanent
structures or permanent changes in existing facilities
will be obtained and paid for by OWNER, unless
otherwise provided in the Contract Documents. If
DESIGNBUILDER and OWNER are unable to agree
on entitlement to or the amount or extent of any
adjustments in the Contract Price or the Contract
Times as a result of any delay in OWNER'S furnishing
these lands, rigbts-of•way or easements,
DESIGNBUILDER may make a claim therefor as
provided in Article 9.
C. DESIGNBUILDER shall provide for all
additional lands and access thereto that may be
required for temporary construction facilities or storage
of materials and equipment.
4.02 Differing Site Conditions
NER of (i) subsurface or latent physical ct
at t Site which differ materially from those i
in the on[ract Documents, or (ii) unknown
conditio at the Site, of an unusual natyy��
differmate 'ally from tbose ordina.iiv, ,, 1_.
generally
character
B. OWNER
promptly after re,
do materially so
decrease in the D
time required for,
whether or not cb
an equitable adjt
clause and the
writing by Clip e
:d as inhering in
by the Contract Iy
, which
red and
of the
�r investigat the site conditions
:eivi the ice. If the conditions
differ a cause an increase or
ESIGN ILDER's cost of, or the
per min any part of the Work,
an d as a re It of the conditions,
ment shall b made under this
mtract Price or es modified in
Order in accordant with Article 9.
C. N request by DESIGN/BUILD
equita an
a adjustment under paragraph 4A2 fall be
all? d unless DESIGNBUILDER has give the
wr' ten notice required; provided that the t e
.t _:L_J. n- _
4.03 Reference Points
A. DESIGNBUILDER shall be responsible for
laying out the construction and shall protect and
preserve the reference points established by OWNER
pursuant to paragraph 8.01.A.6.e and shall make no
changes or relocations without the prior written
approval of OWNER. DESIGNBUILDER shall
report to OWNER whenever any reference point or
property monument is lost or destroyed or requires
relocation because of necessary changes in grades or
locations, and shall be responsible for the accurate
replacement or relocation of such reference points or
property monuments by professionally qualified
personnel.
4.04 Hazardous Conditions
idbktified in the Contract Documents to be within e
sco of the Work. OWNER shall not be respo ble
for m erials creating a Hazardous Condition b ught
to the "te by DESIGN/BUILDER, Subco actors,
Supplie or anyone else fo whom
DESIGN/BIVILDER is responsible.
B. DESIG BUILDER and any affected
Subcontractor all neimmediate - (i) stop all
Construction in ction wi such Hazardous
Condition and in any rea affe ed thereby (except in
an emergency as requir by aragraph 6.15), and (ii)
notify OWNER (and the ter confirm such notice in
writing). OWNER sh romptly determine the
necessity of retaining qua' ied expert to evaluate
such Hazardous Con ion or t e corrective action, if
BU
any. DESIGNDER shall of be required to
resume Constr ion in tonne ion with such
Hazardous Co ttion or in any such a ected area until
after OWN has obtained any re ired permits
related they to and delivered to DESIG UILDER
special tten notice (i) specifying at such
Hazard s Condition and any affected area or has
been ndered safe for the resumption of Constr tion,
or 1) specifying any special conditions under ich
s h Construction may be resumed safely. If OWN
s ecial conditions under which Construction is agre d
b DESIGNBUILDER to be resumed, either p ty
ma make a claim therefor as provided in Article
C. If after receipt of such special written notice
DESI BUILDER does not agree to resume
Constru lion based on a reasonable belief it ' unsafe,
or does n t agree to resume such Construe on. under
such speci conditions, then OWNER ma order such
portion oft e Work that is related [o su Hazardous
Condition or 'n such affected area to b deleted from
the Work. OWNER and DESI NBUILDER
cannot agree a to entitlement too the amount or
extent of an adl stment, if any, in utract Price or
Contract Times a a result of dele ' g such portion of
the Work, then eit r party may ke a claim therefor
as provided in Arti le 9. OW R may have such
deleted portion of th Work pe ormed by OWNER's
own forces or others i actor In
with Article 7.
D. To the fullest ex n permitted by Laws and
Regulations, OWNER 11 indemnify and hold
harmless DESIGNBU DER, Subcontractors,
Suppliers, Engineers d the officers, directors,
employees, agents, oth consultants and
subcontractors of ea and a y of them from and
against all claims, cos s, losses a damages (including
but not limited to fees and c arges of engineers,
architects, attorne and other p fessionals and all
court or arbitrati n or other disput resolution costs)
arising out of r resulting from uch Hazardous
Condition, pro ded that (i) any such laim, cost, loss
or damage is attributable to bodily
oi 'ury, sickness,
disease or ath, or to injury to or struction of
tangible pr erty (other than completed onstruction
Services), ' eluding the loss of use resulting herefrom,
and (ii) thing in this paragraph 4.04.D sha obligate
OWNE to indemnify any individual or en 'ty from
and a inst the consequences of that individ al's or
entity s own negligence or willful misconduct.
. The provisions of paragraph 4.02 are of
in ended to apply to materials uncovered or revea d
the Site which are or could be a Hazardo
r J �vacn�mr:r
ARTICLE 5..130NDS AND INSURANCE
5.01 Performance, Payment and Other Bonds
A. DESIGNBUILDER shall furnish performance
and payment Bonds, each in an amount at least equal
to the Contract Price as security for the faithful
performance and payment of allDESIGN/BUILDER'S
obligations to furnish, provide and pay for Construction
and related materials under the Contract Documents,
These Bonds shall remain in effect at least until one
year after the date when final payment becomes due,
except as provided otherwise by Laws or Regulations
or by the Contract Documents. DESIGNBUILDER
shall also furnish such other Bonds as are required by
the Supplementary Conditions. All Bonds shall bein
the form prescribed by the Contract Documents except
as provided otherwise by Laws or Regulations, and
shall be executed by such sureties as are named in the
current list of "Companies Holding Certificates of
Authority as Acceptable Sureties on Federal Bonds
and as Acceptable Reinsuring Companies" as published
in Circular 570 (amended) by the Audit Staff, Bureau
Of Government Financial Operations, U.S. Treasury
Department, All Bonds signed by an agent must be
accompanied by a certified copy of such a
authority to act. gent's
eB. If the surety on any Bond furnished by
beESIGNBUILDER is declared a bankrupt or
comes insolvent or its right to do business is
terminated in any state where any part of the Project
is located or it ceases to meet the requirements of
Paragraph 5.01.A, DESIGNBUILDER shall within
thirty days thereafter substitute another Bond and
surety meeting the requirements of paragraphs 5.01.A and 5.09.
5.02 DES7GN1BU1LDER's Liability Insurance
A. DESIGNBUILDER shall purchase and
maintain such Comprehensiveor Commercial General
Liability (subject to customary exclusions in respect of
professional liability), Automobile Liability and
Worker's Compensation insurance as is appropriate for
the Work being performed and furnished and as will
provide protection from claims set forth below which
may arise out of or result from DESIGNBUILDER's
performance and furnishing of [he Work and
DESIGNBUILDER's other obligations under the
Contract Documents, whether it is to be performed or
furnished by DESIGNBUILDER, any Subcontractor
or Supplier,
directly indirectly
employed by any of them to perform or furnish any of
the Work, or by anyone for whose acts any of them
may be liable:
L Claims under workers' compensation, disability benefits and other similar employee
benefit acts;
2. Claims for damages because of bodily
injury, occupational sickness or disease, or death of
DESIGNBUILDER's employees;
3. Claims for damages because of bodily
injury, sickness of disease, or death of any person
other than DESIGN/BUILDER's employees;
rzo^'
sustaine i son a
directly or ' e ate a _ Offense
o merit of
5. Claims for damages, other than to the
Work itself, because of injury to or destruction of
tangible property wherever located, including loss
of use resulting therefrom; and
6. Claims for damages because of bodily injury
or death of any person or property damage arising
out of the ownership, maintenance or use of any
motor vehicle.
B. Thepoliciesofinsurance requiredby paragraph
5.02.A shall:
1• With respect to insurance required by
paragraphs 5.02.A.3 through 5.02.A.6 inclusive,
include as additional insureds OWNER and
OWNER's Consultants and any other persons or
entities indicated in the Supplementary Conditions,
all of whom shall be listed as additional insureds,
and include coverage for the respective officers and
employees of all such additional insureds;
2. Include at least the specific coverages and
be written for not less than the limits of liability
provided in the Supplementary Conditions or
required by Laws or Regulations, whichever is
greater;
it3. Include completed operations insurance;
4. Include contractual liability insurance
covering DESIGN/BUILDER'S indemnity
obligations under paragraphs 6.06, 6.10 and 6.19;
S. Contain a provision or endorsement that
the coverage afforded will not be cancelled,
materially changed or renewal refused until at least
30 days prior written notice has been given to
OWNER and each other additional insured
indicated in the Supplementary Conditions to whom
a certificate of insurance has been issued (and the
certificates of insurance furnished .by the
DESIGNBBUILDER pursuant to paragraph 5.09.13
will so provide);
6. Remain in effect at least until final
payment and at all times thereafter when
DESIGNBUILDER may be correcting, removing
or replacing defective Construction in accordance
with paragraphs 12.06 and 12.07; and
7. With respect to completed operations
insurance, and any other insurance coveragewritten
on a claims -made basis, remain in effect for at least
two years after final payment (and
DESIGNBUILDER shall furnish OWNER and
each other additional insured indicated in the
Supplementary Conditions to whom a certificate of
ingi—nce has been issued evidence satisfactory to
OWNER and any such additional insured of
continuation of such insurance at final payment and
tO3OTTWER's
ne year thereafter).
Liability Insurance
A. In addition to the insurance required to be
provided by DESIGNBUILDER under paragraph
5.02, OWNER, at OWNER's option, may purchase
and maintain at OWNER's expense OWNER's own
liability insurance as will protect OWNER against
claims which may arise from operations under the
Contract Documents.
5.04 Property Insurance
-uusp
p perty insurance upon the Construction at
in Ve amount of the full replacement cost
(sub ct to such deductible amounts as
provi din the Supplementary Conditions or
by La and Regulations). This insurance wi:
1. Nnclude the interests of WNER,
DESIG BUILDER, Subcontractors, and any
other p sons or entities indica d in the
Suppleme\1n
Conditions, each f whom is
deemed toe an insurable inter t and shall be
listed as aured oradditional' cured:
2. Be writt on a B
open peril or spec l cause
shall at least includ 'nsura
damage to the Cons ucti
falsework and all
transit, and shall
following perils or
extended coverage,
mischief, earthqua
demolition occasio
Regulations, war
or causes of loss s
the SUDDlemen ary
uilde s Risk "all-risk" or
s of oss policy form that
n for physical loss and
o , temporary buildings,
als and equipment in
against at least the
of loss: fire, lightning,
th/ft, Nlpdalism and malicious
coil se, debris removal,
d by eaf cement of Laws and
damage, an such other perils
may be spec ically required by
Conditions;
3. Incl 96e expenses incurred in the repair or
replacemej of any insured property (t cluding but
not limitr to fees and charges of en 'neers and
4. Cover materials and equipment sto ed at
the ite or at another location that was agre d to
in ruing by OWNER prior to being incorpor ed
i the Construction, provided that such materi s
10
Article 8. CHANGES IN THE WORK
8.01 The amount of any increases or decreases in the DESIGNBUILDER's Fee or in any
Guaranteed Maximum Price or Fee which results from a Change Order shall be set forth in the
applicable Change Order subject to the following:
A. Any increase or decrease in the DESIGN/BUILDER'S Fee resulting from net
additions or decreases in the Cost of the Work shall be determined in accordance with paragraph
10.02.0 of the General Conditions.
B. In the case of net additions or deletions in the Work, the amount of any increase or
decrease in the Guaranteed Maximum Price shall be determined in accordance with paragraph
10.02.0 of the General Conditions.
Article 9. PAYMENT PROCEDURES
9.01 DESIGNBUILDER shall submit and OWNER will process Applications for Payment in
accordance with Article 13 of the General Conditions. Applications for Payment will indicate the
amount of the DESIGN/BUILDER'S Fee then payable.
A. Progress Payments; Retainage. OWNER shall make progress payments on account
of the Contract Price on the basis of DESIGN/BUILDER'S Applications for Payment, on or about
the 15th day of each month during performance of the Work as provided in paragraphs 9.0l.A.1 and
A.2 below. All such payments will be subject to the limitations of any Guaranteed Maximum Price
or DESIGNBUILDER's Fee and will be measured by the acceptable Schedule of Values established
in paragraph 2.06 of the General Conditions (and in the case of Unit Price Work based on the
number of units completed).
For Cost of Work: Progress payments on account of the Cost of the Work will be
made as follows:
a. Prior to Substantial Completion, in an amount equal to the percentage
indicated below, but, in each case, less the aggregate of payments previously made
and less such amounts as OWNER may withhold in accordance with paragraph
13.04.13 of the General Conditions.
(1) 90 percent of Cost of the Work completed (with the balance
being retainage). If the Work has been 50% completed as determined by
OWNER, and if the character and progress of the Work have been
satisfactory to OWNER, OWNER may determine that as long as the character
and progress of the Work remain satisfactory, there will be no additional
retainage on account of Work completed, in which case the remaining
progress payments prior to Substantial Completion will be in an amount
equal to 100% of the Work completed.
(2) 90 percent of (with the balance being retainage) of the cost of
'NER and DESIGN/BUILDER with thirty da
ten notice to each other additional insured o
m a certificate of insurance has been Is
III
6. Allow partial ut Hzation in accorda/e with
gra h 5.08.
B. OW R
boiler and ma in
insurance as m
Conditions or La
the interests o
Subcontractors, an
indicated in the S
whom is deemed to
be listed as an insu
shall purchase and
b7einsurance or adc
brequired by the
s and Regulations wi
OWNER, DESI13 JJ
any other indivjfluais or entities
/ditions, each of
interest and shall
insured.
an
ain such
property
will include
C. A11 the po&ci of insurance (and the
certificates or other evid ce hereof) required to be
Purchased and maintained OWNER in accordance
With paragraph 5.04 will contain a provision or
endorsement that the cov r e afforded will not be
cancelled or materially an d or renewal refused
until at least 30 days' rior tten notice has been
given to DESIGNS IL DER and to each other
additional insured to hom a ce ificate of insurance
has been issued and '11 contain fiver provisions in
accordance with pa agraph 5.OS.A
D. OWNE shall not be r
purchasing aad aintaiain an spoasible for
Protect the interests of y proper insurance to
Subcthe
ontracto ,Suppliers, Engineers or fiefs In
Work to the extent of any deductible amou is that are
identified i the Supplementary Conditions. The risk
of loss wi in such identified deductible am unt, will
be born by DESIGNBUILDER, Subconit for or
Others ffering any such loss and if any of them ishes
prope y insurance coverage within the limits o such
amo is, each may purchase and maintain it at the
pur aser's own expense.
E. f DEr'tS'INGauNcB�UI_L_DER requests iIl witing th`
94
ESIGNBUILDER by appropriate Change Order r itten Amendment. Prior to commencement of e
Wo k at the Site, OWNER shall in writing a ise
DE GNBUILDER whether or not such insura ce has been procured by OWNER. they
5.05 fiver of Rights
A- O ER and DESIGNBUILDE intend that
all policies urchased in accordance wi paragraph
5.04 will p tect OWNER, DESI
Engineers
Su BUILDER,
ntractors, and all oth individuals or
entities indicate in the Supplement Conditions to
be listed as insu ads or additiona insureds in such
Policies and will pr vide primary cq erage for all losses
and damages caus by the pens or causes of loss
covered thereby, such licies shall contain
provisions to the effec that in a event of payment of
any loss or damage the 'nsur s will have no rights of
recovery against any o th insureds or additional
insureds thereund
DESIGNBUII DER waiv OWNER a n d
aginst each th at
and their respective offi rs,ll tractors,aemploy es and
agents for all losses and ama s caused by, arising out
of or resulting from a of the erils or causes of loss
covered by such p icies and any other property
insurance applicabl to the Wo and, in addition,
waive all such righ against Sub co ractors, Suppliers,
Engineersandall therindividuaIso entities indicated
in the Supple entary Conditions o be listed as
insureds or ad tional insureds under ch policies for
losses and d ages so caused. None of the above
waivers shall xtend to the rights that any arty making
such waive may have to the proceeds insurance
held by O NER as trustee or otherwise pa ble under
any poll so issued. In addition, OWNER aives all
rights ainst DESIGNBUILDER
Eng n e, Subcon actors,
rs and Suppliers and the officers, di ctors,
empl yees and agents of any of them for bu 'ness
inte ruption, loss of use of OWNER's property an ny
of r consequential damages caused by, arising out of
o resulting from any of such insured perils or caus
11
5.06 Receipt and Application of Proceeds
A. Any insured loss under the policies of
insurance required by paragraph 5.04 will be adjusted
With OWNER and made payable to OWNER as
fiduciary for the insureds, as their interests may
appear, subject to the requirements of any applicable
mortgage clause and of paragraph 5.06.B. OWNER
shall deposit in a separate account any money so
received, and shall distribute it in accordance with such
agreement as the parties in interest may reach. If no
other special agreement is reached the damaged Work
shall be repaired or replaced, the moneys so received
applied on account thereof and the Work and the cost
thereof covered by an appropriate Change Order or
Written Amendment.
B. OWNER as fiduciary shall have power to
adjust and settle any loss with the insurers unless one
of the parties in interest shall object in writing within
fifteen days after the occurrence of loss to OWNER's
exercise of this power. If such objection,be made,
OWNER as fiduciary shall make settlement with the
insurers in accordance with such agreement as the
parties in interest may reach. If no such agreement
among the parties in interest is reached, OWNER as
fiduciary shall adjust and settle the loss with the
insurers as ;squiFsd_ L
ia;eFest
---- � -r -
5.07 Acceptance of Bonds and Insurance; Option to
Replace
or rance required to be purchased and MainWIed
by the o r party in accordance with Artic on the
bass of th ' not complying wit e Contract
Documents, the ecting part all so notify the
other party in writing i n days after receipt of
the certificates (or othe t ce requested) required
by paragraph ,04.B. OWNER and
DESIGNBU ER shall each provt to the other
such ad onal information in respect o ' surance
pro ' ed as the other may reasonably reque . If
the of the Work, or of such failure t r ntain
prior to any a in the required c� age. Without
prejudice to any othe t t medy, the other party
may elect to obtain a onds or insurance to
protect such r parry's interests a expense of
the o was supposed to providesuc ra¢e,
5.08 Partial Utilization --Property Insurance
A. If OWNER finds it necessary to occupy or use
a portion or portions of the Work prior to Substantial
Completion of all the Construction, such use or
occupancy may be accomplished in accordance with
paragraph 13.06; provided that no such use or
occupancy shall commence before the insurers
providing the property insurance have acknowledged
notice thereof and in writing effected any changes in
coverage necessitated thereby. The insurers providing
the property insurance shall consent by endorsement
on the policy or policies, but the property insurance
shall not be cancelled or permitted to lapse on account
of any such partial use or occupancy.
5.09 Licensed Sureties and Insurers; Certificates of
Insurance
A. All Bonds and insurance required by the
Contract Documents to be purchased. and maintained
by OWNER or DESIGN/BUILDER shall be obtained
from surety or insurance companies that are duly
licensed or authorized in the jurisdiction in which the
Project is located to issue Bonds or insurance policies
for the limits and coverages so required. Such surety
and insurance companies shall also meet such
additional requirements and qualifications as may be
provided in the Supplementary Conditions.
B. DESIGNBUILDER shall deliver to OWNER,
with copies to each additional insured indicated in the
Supplementary Conditions, certificates of insurance
(and other evidence of insurance requested by
OWNER or any other additional insured) which
DESIGNBUILDER is required to purchase and
maintain in accordance with paragraph 5.02.A.
12
3
' c--Sc--aad�.actd;ticaa�yysy�.' '
Supplem onditions, certificat
(and other evidence surance
DESIG rance requested by
or any other a sured)
ARTICLE 6--DESIGN/BUILDER'S
RESPONSIBILITIES
6.01 Design Professional Services
A. Standard of Care. DESIGNBBUILDER shall
perform or furnish Design Professional Services and
related services in all phases of the project. The
standard of care for all such services performed or
furnished under this Agreement will be the care and
skill ordinarily used by members of the engineering
profession practicing under similar conditions at the
same time and locality.
B. Preliminary Design Phase. After the Contract
Times commence to run, DESIGNBUILDER shall:
I. Consult with OWNER to understand
OWNER's requirements for the Project and review
available data.
2. Advise OWNER as to the necessity of
OWNER's providing or obtaining from others
additional reports, data or services of the types
provided in paragraph 8.0l.A.6.a-f and assist
OWNER in obtaining such reports, data, or
services.
3. Identify and analyze requirements of
_governmental authorities having jurisdiction to
approve the portions of the Project designed or
specified by DESIGNBUILDER with whom
consultation is to be undertaken in connection with
the Project.
4. Obtain such additional geotechnical and
related information which it deems necessary for
Performance of the Work.
5. On the basis of th� nceptual Documents
and DESIGNBUILDER'sA Proposal, prepare
preliminary design documents consisting of final
design criteria, preliminary drawings, outline
specifications, and written descriptions of the
Project.
6. Furnish the preliminary design documents
to and review them with OWNER within the time
indicated in the schedules described in paragraph
2.06.A.
C. Final Design Phase; After written acceptance by
OWNER of the preliminary design phase documents
DESIGNBUILDER shall:
I. On the basis of the accepted Preliminary
Design Phase documents, prepare final Drawings
showing the scope, extent, and character of the
Construction to be performed and furnished by
DESIGNBUILDER and Specifications (which will
be prepared, where appropriate, in general
conformance with the sixteen division format of the
Construction Specifications Institute).
2. Provide technical criteria, written
descriptions and design data required for obtaining
approvals of such governmental authorities as have
jurisdiction to review or approve the final design of
the Project, and assist OWNER in consultations
With appropriate authorities.
3. Furnish the above documents, Drawings
and Specifications to and review them with
OWNER within the time indicated in the schedules
described in paragraphs 2.04.A and 2.06.A.
D.Operational Phase. During the Operational
Phase, DESIGNBUILDER shall:
I. Provide assistance in connection with the
start-up, testing, refining and adjusting of any
equipment or system.
2. Assist OWNER in training staff to operate
and maintain the Project.
13
3. Assist OWNER in developing systems and
procedures for control of the operation and
maintenance of and record keeping for the Project.
6.02 Supervision and Superintendence of Construction
A. DESIGNBUILDER shall supervise, inspect
and direct the Construction competently and efficiently,
'devoting such attention thereto and applying such skills
and expertise as may be necessary to provide the
Construction in accordance with the Contract
Documents. DESIGNBUILDER shall be solely
responsible for the means, methods, techniques,
sequences and procedures employed for the provision
of Construction. DESIGNBUILDER shall be
responsible to see that the completed Construction'
complies accurately with the Contract Documents and
shall keep OWNER advised as to the quality and
progress of the Construction.
B. DESIGNBUILDER shall keep on the Site at
all times during construction a competent resident
superintendent, who shall not be replacedwithout
written notice to OWNER except under extraordinary
circumstances. The superintendent will be
DESIGNMUILDER's representative at the Site and
shall have authority to act on behalf of
DESIGNBUILDER. All communications to the
superintendent shall be as binding as if given to
DESIGNBUILDER.
6.03 Labor, Materials and Equipment
A. DESIGNBUILDER shall provide competent,
suitably qualified personnel to survey and lay out the
Construction and perform Construction as required by
the Contract Documents. DESIGNBUILDER shall at
all times maintain good discipline and order at the
Site. Except as otherwise required for the safety or
protection of persons or the Work or property at the
Site or adjacent thereto, and except as otherwise
indicated in the Contract Documents, all Construction
at the Site shall be performed during regular working
hours, and DESIGNBUILDER will not permit
overtime work or the performance of Construction on
Saturday, Sunday or any legal holiday without
OWNER's written consent, �,hieh
B. Unless otherwise specified in the Contract
Documents, DESIGNBUILDERshall furnish or cause
to be furnished and assume full responsibility for
materials, equipment, labor, transportation,
construction equipment and machinery, tools,
appliances, fuel, power, light, beat, telephone, water,
sanitary facilities, temporary facilities and all other
facilities and incidentals necessary for the furnishing,
performance, testing, start-up and completion of the
Work. DESIGNBUILDER, in the presence of
OWNER's personnel, will direct the checkout of
ethutilities and operations of systems and equipment.
C. All materials and equipment incorporated into
e Work shall be of good quality and new, except as
otherwise provided in the Contract Documents. All
warranties and guarantees specifically called for by the
Contract Documents shall expressly run to the benefit
of OWNER. If required by OWNER,
DESIGNBUILDER shall furnish satisfactory evidence
(including reports of required tests) as to the kind and
quality of materials and equipment. All materials and
equipment shall be applied, installed, connected,
erected, used, cleaned and conditioned in accordance
with instructions of the applicable Supplier, except as
otherwise provided in the Contract Documents.
6.04 Progress Schedule
A. DESIGNBUILDER shall adhere to the
progress schedule established in accordance with
paragraph 2.06.A as it may be adjusted from time to
time.
1. DESIGNBUILDER shall submit to
OWNER for acceptance proposed adjustments in
the progress schedule that will not change the
Contract Times (or Milestones). Such adjustments
will conform generally to the progress schedule
then in effect.
No
2. Proposed adjustments in the progress
schedule that will change the Contract Times (or
Milestones) shall be submitted in accordance with
the requirements of Article 11. Such adjustments
may only be made by a Change Order or Written
Amendment.
14
6.05 Concerning subcontractors, Suppliersand Others
A. DESIGNBUILDER shall not employ any
Subcontractor, Engineer, Supplier or other individual
or entity against whom OWNER may have reasonable
objection. DESIGNBUILDER shall not be required
to employ any Subcontractor, Engineer, Supplier or
other individual or entity to furnish or perform any of
the Work against whom DESIGNBUILDER has
reasonable objection.
B. DESIGN/BUILDER shall be fully responsible
to OWNER for all acts and omissions of the
Subcontractors, Engineers, Suppliers and other
individuals or entities performing or furnishing any of
the Work under a direct or indirect contract with
DESIGNBUILDER. Nothing in the Contract
Documents shall create for the benefit of any such
Subcontractor, Engineer, Supplier or other individual
or entity any contractual relationship between OWNER
and, any such Subcontractor, Engineer, Supplier or
other individual or entity, nor shall it create any
obligation on the part of OWNER to pay or to see to
the payment of any moneys due any such
Subcontractor, Engineer, Supplier or other individual
or entity except as may otherwise be required by Laws
and Regulations.
C. DESIGNBUILDER shall be solely responsible
for scheduling and coordinating Subcontractors,
Engineers, Suppliers and other individuals and entities
Performing or furnishing any of the Work under a
direct or indirect contract with DESIGNBUILDER.
DESIGNBUILDER shall require all Subcontractors,
Engineers, Suppliers and such other individuals and
entities performing or furnishing any of the Work to
communicate with the OWNER through
DESIGNBUILDER.
D. All services performed or provided to and tmaterial and equipment supplied DESIGN/BUILDER by a Subcontractor or Supplietor
will be pursuant to an appropriate Design
Subagreement or Construction Subagreement between
DESIGNBUILDER and the Subcontractor, Engineer
or Supplier which specifically binds the Subcontractor,
Engineer or Supplier to the applicable terms and
conditions of the Contract Documents for the benefit
Of OWNER. are
an or al insured on the property insurance ' ed
in para h 5.04pro .A or 5.04.B, the agreemen etween
the DESI UILDER and the S ontractor,
Engineer or Su ier will contain p tsions whereby
the Subcontractor, gineer o upplier waives all
right against OW DESIGNBUILDER,
OWNER's Consultant a all other additional
insureds for all I and dam s caused by, any of
the perils or ca s of loss covered b ch policies and
any other perty insurance applicable the. Work.
If the ' urers on any such policies require arate
war forms to be signed by any Subcontr or,
4414 caa,
6.06 Patent Fees and Royalties
A. DESIGNBUILDER shall pay all license fees
and royalties and assume all costs incident to the use
in the performance of the Work or the incorporation
in the Work of any invention, design, process, product
or device which is the subject of patent rights or
copyrights held by others. If a particular invention,
design, process, product or device is specified in the
Conceptual Documents for use in theperformance of
the Construction and if to the actual knowledge of
OWNER its use is subject to patent rights or
copyrights calling for the payment of any license fee or
royalty to others, the existence of such rights shall be
disclosed by OWNER in the Conceptual Documents.
To the fullest extent permitted by Laws and
Regulations, DESIGNBUILDER shall indemnify and
hold harmless OWNER, from and against all claims,
costs, losses and damages (including but not limited to
all fees and charges of engineers, architects, attorneys
and other professionals and all court or arbitration or
other dispute resolution costs) arising out of or
resulting from any infringement of patent rights or
copyrights incident to the use in the performance of
the Work or resulting from the incorporation in the
Work of any invention, design, process, product or
device not specified in the Conceptual Documents.
15
6.07 Permits
A. Unless otherwise provided in the Contract
Documents, DESIGNBUILDER shall directly or
through one or more Subcontractors obtain and pay for
all necessary permits and licenses. OWNER shall
assist DESIGN/BUILDER, when necessary, in
obtaining such permits and licenses.
DESIGNBUILDER shall pay all governmental
charges and inspection fees necessary for the
,prosecution of the Construction, which are applicable
on the last day for receipt of Proposals.
DESIGNBUILDER shall pay all charges of utility
owners for connections to the Work, and OWNER
shall pay all charges of such utility owners for capital
costs related thereto.
6.08 Laws and Regulations
A. DESIGNBUILDER shall give all notices and
comply with all Laws and Regulations of the place of
the Project which are applicable to furnishing and
Performance of the Work. Except where otherwise
expressly required by applicable Laws and Regulations,
OWNER shall not be responsible for monitoring
DESIGNBUILDER's compliance with any Laws or
Regulations.
B. If DESIGNBUILDER performs. any Work
knowing or having reason to know that it is contrary to
Laws or Regulations, DESIGNBUILDER shall bear
all costs arising therefrom.
C. Changes in Laws and Regulations not known or
foreseeable on the date of receipt of Proposals having
an effect on the cost or time of performance may be
the subject of a claim under Article 9.
6.09 Tares
A. DESIGNBUILDER shall pay all sales,
consumer, use, gross receipts and other similar taxes
required to be paid by DESIGNBUILDER in
accordance with the Laws and Regulations of the place
of the Project which are applicable during the
performance of the Work.
6.10 Use of Site and Other Areas
A. DESIGNBUILDER shall confine construction
equipment, the storage of materials and equipment and
the operations of construction workers to those lands
and areas permitted by the OWNER and other land
and areas permitted by Laws and Regulations, rights -
of -way, permits and easements, and shall not
unreasonably encumber the premiseswith construction
equipment or other materials or equipment.
DESIGNBUILDER shall assume full responsibility for
any damage to any such land or area, or to the owner
or occupant thereof or of any adjacent land or areas,
resulting from the performance of the Construction.
Should any claim be made by any such owner or
occupant because of the performance of the
Construction, DESIGNBUILDER shall promptly
settle with such other party by negotiation or otherwise
resolve the claim by arbitration or other dispute
resolution proceeding or at law. DESIGNBUILDER
shall, to the fullest extent permitted by Laws and
Regulations, indemnify and hold harmless OWNER,
OWNER's Consultants and anyone directly or
indirectly employed by any of them from and against
all claims, costs, losses and damages (including, but not
limited to, fees of engineers, architects, attorneys and
other professionals and court and arbitration or other
dispute resolution costs) arising out of or resulting
from any claim or action, legal or equitable, brought by
any such owner or occupant against OWNER, or any
other party indemnified hereunder to the extent caused
by or based upon DESIG UILDER's performance
of the Construction.
B. During the performance of the Construction,
DESIGNBUILDER shall keep the premises free from
accumulations of waste materials, rubbish and other
debris resulting from the Construction. At the
completion of the Construction DESIGNBUILDER
shall remove all waste materials, rubbish and debris
from and about the premises as well as all tools,
appliances, construction equipment, temporary
construction and machinery and surplus materials.
DESIGNBUILDER shall leave the Site clean and
ready for occupancy by OWNER at Substantial
Completion. DESIGNBUILDER shall restore to
original condition all property not designated for
alteration by the Contract Documents.
16
i
C. DESIGNBUILDER shall not load nor permit
any part of any structure to be loaded in any manner
that will endanger the structure, nor shall DESIGN
BUILDER subject any part of the Work or adjacent
Property to stresses or pressures that will endanger it.
6.11 Record Documents
A. DESIGNBUILDER shall maintain in a safe
Place at the Site one record copy of all Drawings,
Specifications,Addenda, Written Amendments, Change
Orders, Field Orders and Work Change Directives, in
good order and annotated to show all changes made
during construction. These record documents together
with all approved Submittals will be available to
OWNER for reference. Upon completion of the
Work, these record documents and Submittals,
including a reproducible set of record drawings, will be
delivered to OWNER.
6.12 Safery and Protection
A. DESIGNBUILDER shall be solely responsible
for initiating, maintaining and supervising all safety
precautions and programs in connection with the
Construction. DESIGNBUILDER shall take all
necessary precautions for the safety of, and shall
provide the necessary protection to prevent damage,
injury or loss to:
1. all persons on the Site or who may be
affected by the Construction;
2. all Work and materials and equipment to
be incorporated therein, whether in storage on or
Off the Site; and
3. other property at the Site or adjacent
thereto, including trees, shrubs, lawns, walks,
pavements, roadways, structures, utilities and
underground facilities not designated for removal,
relocation or replacement in the course of
construction.
B. DESIGNBUILDER shall comply with
applicable Laws and Regulations of any public body
having jurisdiction for safety of persons or property or
to protect them from damage, injury or loss; and shall
erect and maintain all necessary safeguards for such
safety and protection. DESIGNBUILDER shall notify
owners of adjacent property and of underground
facilities and utility owners when prosecution of the
Work may affect them, and shall cooperate with them
in the protection, removal, relocation and replacement
of their property. All damage, injury or loss to any
property caused, directly or indirectly, in whole or in
part, by DESIGNBUILDER, any Subcontractor,
Supplier or any other individual or entity directly or
indirectly employed by any of them to perform or
furnish any of the Work or anyone for whose acts any
Of them may be liable, shall be remedied by
DESIGNBUILDER. DESIGNBUILDER's duties
and responsibilities for safety and for protection of the
construction shall continue until such time as all the
Work is completed and OWNER has issued a notice to
DESIGNBUILDER in accordance with paragraph
13.09 that the Work is acceptable (except as otherwise
expressly provided in connection with Substantial
Completion).
6.13 Safety Representarive
A. DESIGNBUILDER shall designate a qualified
and experienced safety representative at the Site whose
duties and responsibilities shall be the prevention of
accidents and the maintainingand supervising of safety
precautions and programs.
6.14 Hazard Communication Programs
A. DESIGNBUILDER shall be responsible for
coordinating any exchange of material safety data
sheets or other hazard communication information
required to be made available to or exchanged between
or among employers at the Site in accordance with
Laws or Regulations.
6.15 Emergencies
A. In emergencies affecting the safety or protection
of persons or the construction or property at the Site
or adjacent thereto, DESIGNBUILDER, without
special instruction or authorization from OWNER, is
obligated to act to prevent threatened damage, injury
or loss. DESIGNBUILDER shall give OWNER
prompt written notice if DESIGNBUILDER believes
10
17
that any significant changes in the Construction or
variations from the Contract Documents have been
caused thereby. If a change in the Contract
Documents is required because of the action taken by
DESIGNBUILDER in response to such an
emergency, a Work Change Directiveor Change Order
will be issued to document the consequences of such
action.
6.16 Submittals /
A. OWNER will review and approve Submittals in
accordance with the schedule of required Submittals
accepted by OWNER as requiredby paragraph 2.06.A.
OWNER's review and approval will be only to
determine if the items covered by the Submittals will,
after installation or incorporation in the construction,
conform to the information given in the Contract
Documents and be compatible with the design concept
of the completed Project as a functioning whole as
indicated by the Contract Documents. OWNER's
review and approval will not extend to means,
methods, techniques, sequences or procedures of
construction (exceptwhere a particular means, method,
technique, sequence or procedure of construction is
specifically and expressly called for by the Contract
Documents) or to safety precautions or programs
incident thereto. The review and approval of a
separate item as such will not indicate approval of the
assembly in which the item functions.
DESIGNBUILDER shall make corrections required
by OWNER, and shall return the required number of
corrected copies of the required Submittal for review
and approval. DESIGNBUILDER shall direct specific
attention in writing to revisions other than the
corrections called for by OWNER on previous
Submittals.
B. OWNER's review and approval of required
,Submiazds shall not relieve DESIGNBUILDER from
responsibility for any variation from the requirements
of the Contract Documents unless DESIGNBUILDER
has in writing called OWNER'S attention to each such
variation at the time of submission and OWNER has
given written approval of each such variation by
specific written notation thereof incorporated in or
accompanying the Submittal.
C. Where a Submittal is required by the Contract
Documents or the final schedule of Submittals
accepted by OWNER as required by paragraph 2.06.A,
any related Construction provided prior to OWNER's
review and approval of the pertinent Submittal will be
at the sole expense and responsibility of
DESIGNBUILDER.
6.17 Continuing the Work
A. DESIGNBUILDER shall carry on the Work
and adhere to the progress schedule during all disputes
or disagreements with OWNER. No Work shall be
delayed or postponed pending resolution of any
disputes or disagreements, except as
DESIGNBUILDER and OWNER may otherwise
agree in writing.
6.18 DESIGN/BUILDER'S General Warranty and
Guarantee
eA. DESIGNBUILDER warrants and guaranteesto
OWNER that all Construction will be in accordance
with the Contract Documents and will not be defective.
DESIGNBUILDER's warranty and guarantee
hereunder excludes defects or damage caused by:
1. Abuse, modification or improper
Dmaintenance or operation by persons other than
ESIGN/BUILDER, Subcontractors or Suppliers;
or
2. Normal wear and tear under normal usage.
B. DESIGNBUILDER'sobligationtoperform and
complete the Work in accordance with the Contract
Documents shall be absolute. None of the following
will constitute an acceptance of Work that is not in
accordance with the Contract Documents or a release
of DESIGNBUILDER's obligation to perform the
Work in accordance with the Contract Documents:
L Observations by OWNER;
2. The making of any progress or final pay-
ment;
18
3. The issuance of a certificate of Substan[ia
Completion;
4. Use or occupancy of the Work or any part
thereof by OWNER;
5. Any acceptance by OWNER or any failure
to do so;
6. Any review and approval of a Submittal;
or 7. Any inspection, test or approval by others;
8• Any correction of defective Construction by
OWNER.
6.19 Indemnification
A. DESIGNBUILDER shall indemnify and hold
armless OWNER, OWNER's officers, directors,
employees, agents and consultants from and against all
'1 claims, costs, losses and damages (including but not
limited to all fees and charges of engineers, architects,
attorneys and other professionals and all court or
arbitration or other dispute resolution costs) arising
out of or resulting from the performance of
Construction, provided that any such claim, cost, loss
or damage is attributable to bodily injury, sick
disease or death, or to ness,
injury to or destruction of
tangible property (other than the Work itself),
including the loss of use resulting therefrom, but only
to the extent such claim, cost or damage is caused by
any negligent act or omission of DESIGNBUILDER,
any Subcontractor, Engineer, any Supplier, any
individual or entity directly or indirectly employed by
any of them to perform or furnish any of the Work or
anyone for whose acts any of them may be liable.
S. In any and all aaims against OWNER or any
Of
their respective consultants, agents, officers, direc•
tors or employees by any employee (or the survivor or
personal representative of such employee) of
DESIGN/BUILDER, any Subcontractor, any Engineer,
any Supplier, any individual or entity directly or
indirectly employed by any of them to perform or
furnish any of the Work or anyone for whose acts any
of them may be liable, the indemnification obligation
under paragraph 6.19.A shall not be limited in any way
by any limitation on the amount or type of damages,
compensation or benefits payable by or for DESIGN -
BUILDER or any such Subcontractor, Engineer,
Supplier or other individual or entity under workers'
compensation acts, disability benefit acts or other
employee benefit acts.
C. The indemnification obligations of
DESIGNBUILDER under paragraph 6.19 shall not
extend to the liability of OWNER's Consultants,
officers, directors, employees or agents arising out of
the preparation or approval of maps, drawings,
opinions, reports, surveys, designs, or specifications.
ARTICLE 7-OTHER CONSTRUCTION
Z01 Related Construction at Site
A. OWNER may perform other Work related to
the Project at the Site by OWNER's own forces, or let
other direct contracts therefor or have other work
Performed by utility owners. If the fact that such other
work is to be performed was not noted in the
Conceptual Documents then (i) written notice thereof
will be given to DESIGNBUILDER prior to starting
any such other work and (ii) DESIGN/BUILDER may
make a claim therefor as provided in Article 9 if
DESIGNBUILDER believes that such performance
will involve additional expense to DESIGNBUILDER
or requires additional time and the parties are unable
to agree as to the amount or extent thereof.
13. DESIGN/BUILDER shall afford each other
contractor who is a party to such a direct contract and
each utility owner (and OWNER, if OWNER is
Performing the additional work with OWNER's
employees) proper and safe access to the Site and a
reasonable opportunity for the introduction and storage
of materials and equipment and the execution of such
other work and shall properly connect and coordinate
the Construction with theirs. Unless otherwise
provided in the Contract Documents,
DESIGNBUILDER shall do all cutting, fitting and
Patching of the Work that may be required to make its
severalparts come together properly and integratewith
191
such other work. DESIGNBUILDER shall not
endanger any work of others by cutting, excavating or
otherwise altering their work and will only cut or alter
their work with the written consent of OWNER and
the others whose work will be affected. Ile duties and
responsibilities of DESIGNBUILDER under this
paragraph are for the benefit of such utility owners and
other contractors to the extent that there are
comparable provisions for the benefit of DE-
SIGNBUILDER in said direct contracts between
OWNER and such utility owners and other contrac-
tors.
C. If the proper execution or results of any part of
D'p'SIGNBUILDER's Work depends upon work
performed or services provided by others under this
Article 7, DESIGNIBUILDER shall inspect such other
work and appropriate instruments of service and
promptly repor[.,t. OWNER in writing any delays,
defectsSr deficiencies in such other work or services
that render it unavailable or unsuitable for the proper
execution and results of DESIGNBUILDER's Work.
DESIGNBUILDER's failure so to report will
constitute an acceptance of such other work as fit and
proper for integration with DESIGNBUILDER's
Work except for latent or nonapparent defects and
deficiencies in such other work.
7.02 Coordination
A. If OWNER contracts with others for the
performance of other work on the Project at the Site,
the following will be set forth in Supplementary
Conditions:
I. The individual or entity who will have
authority and responsibility for coordination of the
activities among the various prime contractors will
be identified;
2. The specific matters to be covered by such
authority and responsibility will be itemized; and
3. The extent of such authority and responsi-
bilities will be provided.
B. Unless otherwise provided in the Supplementary
Conditions, OWNER shall have sole authority and
responsibility in respect of such coordination.
ARTICLE 8--OWNER'S RESPONSIBILITIES
8.01 General
A. OWNER shall do the following in a timely
manner so as not to delay the services of
DESIGNBUILDER.
1. Designate in writing a person to act as
OWNER's Representative with respect to the
services to be rendered under this Agreement.
2. Provide such legal services as OWNER may
require with regard to legal issues pertaining to the
Project including any that may be raised by
DESIGNBUILDER.
funds area
cost of the
deuce is ft
required to
to DESIGNBUILDER, that
and committeesthe entire
reasonable evi-
ILDER is not
!yam Work, or
n mtence or cot
evidence is not
4. Make payments to DESIGNBUILDER
promptly when they are due as provided in para-
graph 13.04 and 13.09.
5. Furnish lands and easements as set forth in
paragraph 4.0I.A.
6. Furnish to DESIGNBUILDER, as re-
quired for performance of DESIGNBUILDER's
Services the following, all of which
DESIGNBUILDER may use and rely upon in
performing services under this Agreement:
Of,
materials and equipment not incorporated in the Work (but delivered, suitably
stored and accompanied by documentation satisfactory to OWNER as
provided in paragraph 13.02.A of the General Conditions).
b. Upon Substantial Completion, in an amount sufficient to increase total
payments to DESIGN/BUILDER to 95 percent of the Contract Price (with the
balance being retainage), less such amounts as OWNER shall determine that
OWNER may withhold, in accordance with paragraph 13.04.13 of the General
Conditions.
2. For DESIGNBUILDER's Fee: Progress payments on account of the
DESIGN/BUILDER'S Fee will be made as follows:
a. Payments prior to Substantial Completion will be in an amount equal to
90 percent of such Fee earned to the date of the approved Application for Payment
(less in each case payments previously made on account of such fee) based on the
progress of the Work measured by the Schedule of Values established as provided
in paragraph 2.06.A of the General Conditions (and in the case of Unit Price Work
on the number of units completed) and upon Substantial Completion in an amount
sufficient to increase total payments to DESIGN/BUILDER on account of that fee
to 95 percent of the DESIGN/BUILDER'S Fee.
B. Final Payment. Upon final completion and acceptance of the Work in accordance
with paragraph 13.09 of the General Conditions and statutorily required procedures as set forth in
Supplementary Condition 16, OWNER shall pay remainder of the Contract Price.
Article 10. DESIGNBUILDER'S REPRESENTATIONS
10.01. DESIGN/BUILDER makes the following representations:
A. DESIGNBUILDER has examined and carefully studied the Contract Documents
(including the Addenda) listed in paragraphs 12.01.A through J but excluding the documents
described in paragraph 12.01.K and the other related data identified in the Request for Proposals.
B. DESIGNBUILDER has visited the Site and become familiar with and is satisfied as
to the general, local and Site conditions that may affect cost, progress, performance or furnishing of
the Work.
C. DESIGNBUILDER is familiar with and is satisfied as to all federal, state and local
Laws and Regulations that may affect cost, progress, performance or furnishing of the Work.
D. DESIGNBUILDER has carefully studied all reports of explorations and tests of
subsurface conditions at or contiguous to the Site and all drawings of physical conditions in or
relating to existing surface or subsurface structures at or contiguous to the Site which have been
made available by OWNER.
rd
a. Environmental assessment and impact
statements;
b. Property, boundary, easement, right-of-
way, topographic and utility surveys;
c. Property descriptions;
d. Zoning, deed and other land use -re-
strictions;
e. Engineering surveys to establish refer-
ence points for design and construction which
in OWNER's judgment are necessary to enable
DESIGN/BUILDER to proceed.with the
Work;
f. Assistance in filing documents required
to obtain necessary approvals of governmental
authorities having jurisdiction over the Project;
g. Subsurface data used in preparation of
the Conceptual Documents.
7. Review submittals subject to OWNER
review pursuant to paragraph 6.16.A.
8. Provide information known to or in the
Possession of OWNER relating to the presence of
materials and substances at the site which could
create a Hazardous Condition.
B. OWNER's responsibilities in respect of
purchasing and maintaining liability and property insurance are set forth in paragraphs 5.03.A through
5.04.E.
8.02 Scope of OWNER's Safety and Hazardous Waste
Responsibilities
supervise,A- The OWNER shall not or
have control oor authority overr nor beesdirect
responsible for
DESIGNBUILDER's means, methods, techniques,
sequences or procedures of construction or the safety
precautions and programs incident thereto, or for any
failure of DESIGNBUILDER to comply with haws
and Regulations applicable to the furnishing or perfor-
mance of the Work. OWNER will not be responsible
for DESIGNBUILDER's failure to perform or furnish
the Work in accordance with the Contract Documents.
Gigged
e .
8.03 Resident Project Representation
A. OWNER may furnish a Resident Project
Representative to observe the performance of
Construction. The duties, responsibilities and
limitations of authority of any such Resident Project
Representative and assistants will be as provided in the
Supplementary Conditions.
ARTICLE 9--CHANGES IN THE FORK; CLAIMS
9.01 General--Righrs and Obligations
A. WithoutinvalidatingtheAgreement and without
notice to any surety, OWNER may, at any time or
from time to time, order additions, deletions or
revisions in the Work within the general scope of the
contract by a Written Amendment, a Change Order, or
a Work Change Directive. Upon receipt of any such
document, DESIGN/BUIL DER shallpromptlyproceed
with the Work involved which will be performed under
the applicable provisions of the Contract Documents
(except as otherwise specifically provided).
9.02 Notice of Intent to Make Claim
A. If OWNER and DESIGN/BUILDER are unable
to agree as to the extent, if any, of an adjustment in
the Contract Price or an adjustment of the Contract
Times that should be allowed as a result of any order
Of OWNER pursuant to paragraph 9.01.A or other
occurrence for which the Contract Documents provide
that such adjustment(s) may be made, a claim may be
made therefor. Written notice of intent to make such
a claim shall be submitted to the other party promptly
and in no event more than 30 days after the start of
the occurrence or event giving rise to the claim.
21
9.03 Claim Documentation
A. Substantiating documentation shall be
submitted by the claiming party within 30 days after
delivery of the notice required by paragraph 9.02.A.
9.04 Decision
A. The other party shall render a decision on the
claim no more than 30 days after the receipt of the
substantiating documentation required by paragraph
9.03.A. This decision will be final and binding unless
the claiming party gives notice of intention to exercise
its rights under Article 15 within 30 days of receipt of
the decision and exercises such rights within 30 days of
giving the notice of intent.
9.05 Time Limit Extension
A. The time limits of paragraphs 9.03.A and
9.04.A may be extended by mutual agreement.
9.06 Exceptions
A. DESIGNBUILDER shall not be entitled to an
increase in the Contract Price or an extension of the
Contract Times with respect to any Work performed
that is not required by the Contract Documents as
amended, modified and supplemented as provided in
paragraph 3.03, except in the case of an emergency as
provided in paragraph 6.15 or in the case of uncovering
n.struction as provided in paragraph 12.04.
9.117 Execution of Change Orders
A. OWNER and DESIGNBUILDER shall
execute appropriate Change Orders or Written
Amendments covering.
1.1'; .changes in the Work which are (i) ordered
by OWNER pursuant to paragraph 9.01, (ii)
required because of acceptance of defective
Construction under paragraph 12.08 or correcting
defective Work under paragraph 12.09 or (iii)
agreed to by the parties; and
2. changes in the Contract Price or Contract
Times which are agreed to by the parties.
9.08 Notice to Sureties
A. If notice of any change affecting the general
scope of the Work or the provisions of the Contract
Documents (including, but not limited to, Contract
Price or Contract Times) is required by the provisions
of any Bond to be given to a surety, the giving of any
such notice will be DESIGNBUILDER's responsibili-
ty, and the amount of each applicable Bond will be
adjusted accordingly.
ARTICLE 10--CHANGE OF CONTRACT PRICE
10.01 General
A. The Contract Price constitutes the total com-
pensation (subject to authorized adjustments) payable
to DESIGNBBUILDER for perforating the Work. � 1,
B. The Contract Price may only be changed by a
Change Order or by a Written Amendment. Any claim
for an adjustment in the Contract Price shall be based
on written notice delivered by the party making the
claim to the other party promptly in accordance with
paragraph 9.02.A.
C. The value of any Work covered by a Change
Order or of any claim for an adjustment in the Con-
tract Price will be determined as follows:
I. Where the Work involved is covered by unit
prices contained in the Contract Documents, by
application of such unit prices to the quantities of
the. items involved;
2. Where the Work involved is not covered by
unit prices contained in the Contract Documents,
by a mutually agreed lump sum (which may include
an allowance for overhead and profit not necessari-
ly in accordance with paragraph 10.02) or by
mutually agreed unit prices;
3. Where the Work involved is not covered by
unit prices contained in the Contract Documents
and agreement to a lump sum is not reached under
paragraph 10.01.C.2, on the basis of the Cost of the
22
Work (determined as provided in paragraph 10.02)
plus a DESIGNBUILDER's Fee for overhead and
profit (determined as provided in paragraph
10.02.C).
10.02 Cost of the Work
A. Costs Included: The term Cost of the Work
means the sum of all costs necessarily incurred and
paid by DESIGNBUILDER in the proper perfor-
mance of the Work. Except as otherwise may be
agreed to in writing by OWNER, such costs shall be in
amounts no higher than those prevailing in the locality
of the Project, shall include only the in
items
and shall not include any of the costs itemized in
paragraph 10.02.B:
I. Payroll costs for employees in the direct
employ of DESIGNBUILDER in the performance
of the Work under schedules of job classifications
agreed upon by OWNER and DESIGNBUILDER.
? a. Such employees shallinclude without
limitation superintendents, foremen and other
personnel employed full-time at the Site.
Payroll costs for employees not employed full
time on the Site shall be apportioned on the
basis of their time spent on the Site. Payroll
costs shall �� be limited to, sala-
ries and wages plus the cost of fringe benefits
which shall include social security
contributions, unemployment, excise and
Payroll taxes, workers' compensation, health
t� benefits, ibe
applicable thereto.
The expenses of performing Work after regular
working hours, on Saturday, Sunday or legal
holidays, shall be included in the above to the
extent authorized by OWNER.
b. Such employees shall also include
eng neers and engineering technicians provid-
ing Design Professional Services. For purposes
of this paragraph 10.02.A,I
DESIGNBUILDER shall be entitled to pay-
ment for such employees an amount equal to
salary costs times a factor, both as designated
in the Agreement, for all services performed or
furnished by such employees engaged on the
Project.
2. Cost of all materials and equipment fur-
nished and incorporated in the Work, including
costs of transportation and storage thereof, and
Suppliers' field services required in connection
therewith. All cash discounts shall accrue to
DESIGNBUILDER unless OWNER deposits
funds with DESIGNBUILDER with which to
make payments, in which case the cash discounts
shall accrue to OWNER. All trade discounts,
rebates and refunds and returns from sale of
surplus materials and equipment shall accrue to
OWNER, and DESIGNBUILDER shall make
provisions so that they may be obtained.
3. Payments made by DESIGNBUILDER to
Subcontractors for Work performed or furnished b
Subcontractors.
4. Payments made by DESIGN/BUILDERto
Engineers for Design Professional Services provid-
ed or furnished by Engineers under a Design
Subagreement.
S. Costs ofspecial,consultants (including but
not limited to testing laboratories, surveyors,
attorneys and accountants) employed for services
specifically related to the Work.
6. Supplemental costs including the following
items:
a. The proportion of necessarytransporta-
tion, travel and subsistence expenses of DE-
SIGNBUILDER's employees incurred in
discharge of duties connected with the, Work.
b. Cost, including transportation and
maintenance, of all materials, supplies, equip-
ment, machinery, appliances, office and tempo-
rary facilities at the Site and hand tools not
owned by the workers, which are consumed in
the performance of the Work, and cost less
market value of such items used but not con-
sumed which remain the property of
DESIGN/BUILDER,
23
C. Rentals of all Work equipment and
machinery and the parts thereof whether
rented from DESIGNBUILDER or others in
accordance with rental agreements approved by
OWNER, and the costs of transportation,
loading, unloading, installation, dismantling
and removal thereof --all in accordance with the
terms of said rental agreements. The rental of
any such equipment, machinery or parts shall
cease when the use thereof is no longer neces-
sary for the Work.
d. Sales, consumer, use or similar taxes
related to the Work, and for which
DESIGNBUILDER is Gable, imposed by Laws
and Regulations.
e. Deposits lost for causes other than
negligence of DESIGNBUILDER, any
Subcontractor or anyone directly or indirectly
employed by any of them or for whose acts any
of them may be Gable, and royalty payments
and fees for permits and licenses.
I. Losses, damages and related expenses
caused by damage to the Work not compensat-
ed by insurance or otherwise, sustained by
DESIGNBUILDER in connection with the
furnishing and performance of the Work pro-
vided they have resulted from causes other
than the negligence of DESIGN/BUILDER,
any Subcontractor, or anyone directly or
indirectly employed by any of them or for
whose acts any of them may be liable. Such
losses shall include settlements made with the
written consent and approval of OWNER. No
such losses, damages and expenses shall be
included in the Cost of the Work for the
Purpose of determining DESIGNBUILDER's
fee. If, however, any such loss or damage
requires rework and DESIGNBUILDER is
placed in charge thereof, DESIGNBUILDER
shall be paid for services a fee proportionate to
that stated in paragraph 10.02.C.
g. The cost of utilities, fuel and sanitary
facilities at the Site.
h. Minor expenses such as telegrams, long
distance telephone calls, telephone service at
the Site, expressage and similar petty cash items
in connection with the Work.
i. Cost of premiums for all Bonds and
insurance DESIGNBUILDER is required by
the Contract Documents to purchase and
maintain.
B. Costs Excluded. The term Cost of the Work
shall not include any of the following-.
I. Payroll costs and other compensation of
DESIGNBUILDER's officers, executives, princi-
pals (of partnerships and sole proprietorships),
general managers, engineers, architects, estimators,
attorneys, auditors, accountants, purchasing and
contracting agents, expediters, timekeepers, clerks
and other personnel employed by
DESIGNBUILDER whether at the Site or in
DESIGNBUILDER's principal or a branch office
for general administration of the Work and not
specifically included in the agreed upon schedule of
job classifications referred to in paragraph
10.02.A.1 -- all of which are to be considered
administrative costs covered by the
DESIGNBUILDER's fee.
2. Expenses of DESIGNBUILDER's princi-
pal and branch offices other than
DESIGNBUILDER's office at the Site.
3. Any part of DESIGNBUILDER's capital
expenses, including interest on
DESIGNBUILDER's capital employed for the
Work and charges against DESIGN/BUILDER for
delinquent payments.
4. Costs due to the negligence of
DESIGNBUILDER, any Subcontractor, or anyone
directly or indirectly employed by any of them or
for whose acts any of them may be liable, including
but not limited to, the correction of defective Work,
disposal of materials or equipment wrongly sup-
plied and making good any damage to property.
24
5. Other overhead or general expense costs of
any kind and the costs of any item not specifically
and expressly included in paragraph 10,02.
C. Fee: The DESIGNBUILDER'sfee allowed to
DESIGNBUILDER for overhead and profit on
Change Orders priced by paragraph 10-01.C.3 shall be
determined as follows:
I. A mutually acceptable fixed fee; or
2. If a fixed fee is not agreed upon, then a fee
based on the following percentages of the various
portions of the Cost of the Work:
.a. For costs incurred under paragraphs
10.02.A.1, A. 2, A.5 and A.6 the
DESIGNBUILDER's fee shall be 15r percent;
b. For costs incurred under paragraph
10.02.A.3 and 10.02.A.4, the
DESIGN/BUILDER's fee shall be €tve percent;
c. Where one or more tiers of subcon-
tracts are on the basis of Cost of the Work
plus a fee and no fixed fee is agreed upon, the
intent of paragraphs 10.02.A 1, 10.02.A.2 and
10.02A.3 is that the Subcontractor who
actually performs or furnishes Work, at
whatever tier, will be paid a fee of 15 percent
of the costs incurred by such Subcontractor
under paragraphs 10.02.A-1 and 10.02.A.2 and
that any higher tier Subcontractor and
DESIGNBUILDER will each be paid a fee of
five percent of the amount paid to the next
lower tier Subcontractor;
d. The amount of credit to be allowed by
DESIGNBUILDER to OWNER for any
change which results in a net decrease in cost
will be the amount of the actual net decrease
in cost plus a deduction in
DESIGNBUILDER's fee by an amount equal
to 4ve percent of such net decrease; and,
e. When both additions and credits are
involved in any one change, the adjustment in
DESIGNBUILDER's fee shall be computed
on the basis of the net change in accordance
with paragraphs 10.02.C.2.athrough10.02.C.2.d,
inclusive.
D. Documentation: Whenever the cost of any Work
is to be determined pursuant to paragraph 10.02.A and
10,02.13, DESIGNBUILDER will establish and
maintain records thereof in accordance with generapy
accepted accounting practices atfd submit in a form
acceptable to OWNER an itemized cost breakdown
together with supporting data.
10.03 Cash Allowances
A. The Contract Price includes all allowances so
named in the Contract Documents.
I. The allowances include the cost to DE-
SIGNBUILDER (less any applicable trade dis-
counts) of materialsand equipment required by the
allowances to be delivered at the Site, and all
applicable taxes; and
2. Except as set forth in the Contract Docu-
ments, DESIGNBUILDER's costs for unloading
and handling on the Site, labor, installation costs,
overhead, profit and other expenses contemplated
for the allowances have been included in the
Contract Price and not in the allowances and no
demand for additional payment on account of any
of the foregoing will be valid.
B. Prior to final payment, an appropriate Change
Order will be issued to reflect actual amounts due
DESIGNBUILDER on account of Work covered by
allowances, and the Contract Price shall be corre.
spondingly adjusted.
10.04 Unit Prices
A. Where the Contract Documents provide that all
or part of the Work is to be Unit Price Work, initially
the Contract Price will be deemed to include for all of
Unit Price Work an amount equal to the sum of the
established unit prices for each separately identified
item of Unit Price Work times the estimated quantity
Of each item as indicated in the Agreement. The
estimated quantities of items of Unit Price Work are
25
not guaranteed and are solely for the purpose of
comparison of Bids and determining an initial Contract
Price. Determinations of the actual quantities and
classifications of Unit Price Work performed by
DESIGNBUILDER will be made by OWNER.
B. Each unit price will be deemed to include an
amount considered by DESIGNBUILDER to be
adequateto cover DESIGNBUILDER'soverhead and
profit for each separately identified item.
C. DESIGNBUILDER or OWNER may make a
claim for an adjustment in the Contract Price in
accordance with Article 9 if:
1. the quantity of any item of Unit Price
Work performed by DESIGNBUILDER differs
from the estimated quantity of such item indicated
in the Contract Documents by more than the
percentage indicated in the Supplementary
Conditions; and
2. there is no corresponding adjustment with
respect to any other item of Work; and
3. DESIGNBUILDER believes that
DESIGNBUILDER is entitled to an increase in
Contract Price as a result of having incurred
additional expense or OWNER believes the
OWNER is entitled to a decrease in Contract Price
and the parties are unable to agree as to the
amount of any such increase or decrease.
ARTICLE 11--CHANGE OF CONTRACT TIMES
11.01 General
"'A. The Contract Times (or Milestones) may only
be changed by a Change Order or a Written
Amendment. Any claim for an adjustment of the
Contract Times (or Milestones) shall be based on
written notice pursuant to paragraph 9.02.
B. All Contract Times and Milestones are of the
essence of the Agreement.
26
11.02 Time Extensions
A. Where DESIGNBUILDER is prevented from
completing any part of the Work within the Contract
Times (or Milestones) due to delay beyond the control
of DESIGNBUILDER, the Contract Times (or
Milestones) will be extended in an amount equal to the
time lost due to such delay if a claim is made therefor
as provided in Article 9. Delays beyond the control of
DESIGNBUILDER shall include, but not be, limited
to, acts or neglect by OWNER, governmental agencies,
acts or neglect of utility owners or other contractors
performingother construction work as contemplatedby
Article 7, fires, floods, epidemics, abnormal weather
conditions or acts of God Delays attributable to and
within the control of a Subcontractor or Supplier shall
be deemed to be delays within the control of
DESIGNBUILDER.
B. Nothing•in this paragraph.11.02-bars a change in
Contract Price pursuant to Article 10 to compensate
for the direct costs incurred by DESIGNBUILDER
due to delay, interference, or disruption directly
attributable to actions or inactions of OWNER or
OWNER's Consultants. However, OWNER shall not
be liable to DESIGNBUILDER for costs or damages
arising out of or resulting from (i) delays caused by or
within the control of DESIGNBUILDER, or (ii)
delays beyond the control of both parties including but
not limited to fires, floods, epidemics, abnormal
weather conditions, acts of God or acts or neglect by
governmental agencies, utility owners, or other
contractors performing other work as contemplated by
Article 7.
ARTICLE 12--TESTS AND INSPECTIONS;
CORRECTION, REMOVAL OR ACCEPTANCE O
DEFECTIVE CONSTRUCTION
12.01 Notice of Defects
A. Prompt written notice of all defective
Lbnstruz,on of which OWNER has actual knowledge
will be given to DESIGNBUILDER by OWNER. All
defective Construction may be rejected, corrected or
accepted as provided in this Article 12,
12.02 Access to Construction
A. OWNER, OWNER's Consultants, other
representatives and personnel of OWNER,
independent testing laboratories and governmental
agencies with jurisdictional interests will have access to
the Construction at the Site at reasonable times for
their observation, inspe5ing and testing.
DESIGNBUILDER shall provide them proper and
safe conditions for such access and advise them of
DESIGNBUILDER's Site safety procedures and
programs so that they may comply therewith as
applicable.
12.03 Tests and Inspections
A. If the Contract Documents or Laws of
Regulations of any public body having jurisdiction
rt of the Construction specifically to be
require any pa
inspected, tested or approved, DESIGNBUILDER
shall assume full responsibility for arranging and
obtaining such inspections, tests or approvals, pay all
costs in connection therewith, and furnish OWNER the
required certificates of inspection or approval.
DESIGNBUILDER shall also be responsible for
arranging and obtaining and shall pay all costs in
connection with any inspections, tests or approvals
required for OWNER'S acceptance of materials or
equipment to be incorporated in the Construction or of
materials, mix designs, or equipment submitted for
approval prior to DESIGNBUILDER's purchase
thereof for incorporation in the Construction.
B. DESIGNBUILDER shall give OWNER
reasonable notice of the planned schedule for all
required inspections, tests or approvals.
C. If any Construction (or the construction work
Of others) that is required to be inspected, tested or
approved is covered by DESIGNBUILDER without
written concurrence of OWNER, it must, if requested
by OWNER, be uncovered for observation at
DESIGN/BUILDER'S expense unless
DESIGNBUILDER has given OWNER timely notice
of DESIGNBUILDER's intention to cover the same
and OWNER has not acted with reasonable
promptness in response to such notice.
4
12,04 Uncovering Construction
A. If any Construction is covered contrary to the
written request of OWNER, it must, if requested by
OWNER, be uncovered for OWNER's observation and
recovered at DESIGNBUILDER's expense.
B. If OWNER considers it necessary or advisable
that covered Construction be observed by OWNER or
inspected or tested by others, DESIGNBUILDER, at
OWNER's request, shall uncover, expose or otherwise
make available for observation, inspection or testing as
OWNER may require, that portion of the Construction
in question, furnishing all necessary labor, material and
equipment. If it is found that such Construction is
defective, DESIGNBUILDER shall pay all costs and
damages caused by or resulting from such uncovering,
exposure, observation, inspection and testing and of
satisfactory replacement or rework, (including but not
limited to all fees and charges of engineers, architects,
attcMevs and other professionals, all court or
arbitration or other dispute resolution costs, and all
costs of repair or replacement of work of others); and
OWNER shall be entitled to an appropriate decrease
in the .Contract Price, and, if the parties are unable to
agree as to the amount thereof, may make a claim
therefor as provided in Article 9. If, however, such
Construction is not found to be defective,
DESIGNBUILDER shall be allowed an increase in
the Contract Price or an extension of the Contract
Times (or Milestones), or both, directly attributable to
such uncovering, exposure, observation; inspection,
testing, replacement and rework; and, if the parties are
unable to agree as to the amount or extent thereof;
DESIGNBUILDER may make a claim therefor as
Provided in Article 9.
12.05 Owner May Stop the Construction 40
A. If the Construction is defective, or
DESIGNBUILDER fails to supply sufficient skilled
workers or suitable materials or equipment, or fails to
furnish or perform the Construction in such a way that
the completed Construction will conform to the
Contract Documents, OWNER may order
DESIGNBUILDER to stop Construction or any
portion thereof, until the cause for such order has been
eliminated; however, this right of OWNER to stop
27
Construction will not give rise to any duty on the part
Of OWNER to exercise this right for the benefit of
DESIGNBUILDER or any other party.
12.06 Correction orRemoval ofDefective Construction
A. OWNER will have authority to disapprove or
reject defective Construction and will have authority to
require special inspection or testing of the
Construction whether or not the Construction is
fabricated, installed or completed. If required by,
OWNER, DESIGNBUILDER shall promptly, as
directed, either correct all defective Construction;
whether or not fabricated, installed or completed, or,
if the Construction has been rejected by OWNER,
remove it from the Site and replace it with
nondefective Construction. DESIGNBUILDER shall
bear all direct, indirect and consequential costs of such
correction or removal (including but not limited to fees
and charges of engineers, architects, attorneys and
other professionals) made necessary thereby.
12.07 Correction Period
A. If within one year after the date of Substantial
Completion or such longer period of time as may be
prescribed by Laws or Regulations or by the terms of
any applicable special guarantee required by the
Contract Documents or by any specific provision of the
Contract Documents, any Construction is found to be
defective, DESIGNBUILDER shall promptly, without
cost to OWNER and in accordance with OWNER's
written instructions, (i) correct such defective
Construction, or, if it has been rejected by OWNER,
remove it from the Site and replace it with
Construction that is not defective, and (ii) satisfactorily
correct or remove and replace any damage to other
Construction or the work of others resulting therefrom.
If DESIGNBUILDER does not promptly comply with
the terms of such instructions, or in an emergency
where delay would cause serious risk of loss or
damage, OWNER may have the defective Construction
corrected or the rejected Construction removed and
replaced, and all costs and damages caused by or
resulting from such removal and replacement
(including but not limited to all fees and charges of
engineers, architects, attorneys and other professionals,
all court or arbitration or other dispute resolution
costs, and all costs of repair or replacement of work of
others) will be paid by DESIGNBUILDER.
B. In special circumstances where a particular item
of equipment is placed in continuous service before
Substantial Completion of all the Construction, the
correction period for that item may start to run from
Ian earlier date if so provided in the Specifications or
by Written Amendment.
C. Where defective Construction (and damage to
they Construction resulting therefrom) has been
corrected, removed or replaced under this paragraph
12.07, the correction period hereunder with respect to
such Construction will be extended for an additional
period of one year after such correction or removal
and replacement has been satisfactorily completed.
12.08 Acceptance of Defective Construction 1i
A. If, instead of requiring correction or removal
and replacement of defective Construction, OWNER
prefers to accept it, OWNER may do so.
DESIGNBUILDER shall pay all costs attributable to
OWNER's evaluation of and determination to accept
such defective Construction (such costs to include but
not be limited to all fees and charges of engineers,
architects, attorneys and other professionals and all
court or arbitration or other dispute resolution costs).
If any such acceptance occurs prior to final payment,
a Change Order will be issued incorporating the
necessary revisions in the Contract Documents with
respect to the Construction; and OWNER shall be
entitled to an appropriate decrease in the Contract
Price, and, if the parties are unable to agree as to the
amount thereof, OWNER may make a claim therefor
as provided in Article 9. If the acceptance occurs after
final payment, an appropriate amount will be paid by
DESIGNBUILDER to OWNER.
12.09 OWNER May Correct Defective Construction
A. If DESIGNBUILDER fails within a reasonable
time after written notice from OWNER to correct
defective Construction or to remove and replace
rejected Construction as required by OWNER in
accordance with paragraphs 12.06.A or 12.07.A, or if
DESIGNBUILDER fails to perform the Construction
28
in accordance with the Contract Documents, or if
DESIGNBUILDER fails to comply with any other
provision of the Contract Documents, OWNER may,
after seven days' written notice to
DESIGNBUILDER, correct and remedy any such
deficiency. In exercisingthe rights and remedies under
this paragraph OWNER shall proceed expeditiously.
In connection with such corrective and remedial action,
OWNER may exclude DESIGNBUILDER from all or
part of the Site, take possession of all or part of the
Construction, and suspend DESIGNBUILDER's
services related thereto, take possession of
DESIGNBUILDER's tools, appliances, construction
equipment and machinery at the Site and incorporate
in the Construction all materials and equipment stored
at the Site or for which OWNER has paid
DESIGNBUILDER but which are stored elsewhere.
DESIGNBUILDER shall allow OWNER, OWNER's
representatives, agents and employees, OWNER's
other contractors and Consultants access to the Site to
enable OWNER to exercise the rights and remedies
under this paragraph. All costs and damages incurred
or sustained by OWNER in exercising such rights and
remedies will be charged against DESIGNBUILDER
and a Change Order will be issued incorporating the
necessary revisions in the Contract Documents and
OWNER shall be entitled to an appropriate decrease
in the Contract Price, and, if the parties are unable to
agree as to the amount thereof, OWNER may make a
claim therefor as provided in Article 9. Such costs and
damages will include but not be limited to all fees and
charges of engineers, architects, attorneys and other
professionals, all court or arbitration or other disput
resolution costs and all costs of repair or replacement
Of work of others destroyed or damaged by correction,
removal or replacement of DESIGNBUILDER's
defective Construction. DESIGNBUILDER shall not
be allowed an extension of the Contract Times (or
it
-Milestones) because of any delay in the performance of
the Construction attributable to the exercise by A. DESIGNBUILDER warrants and guarantees
OWNERof OWNER's rights and remedies hereunder. that title to all construction materials and equipment
covered by any Application for Payment, whether
incorporated in the Project or not, will pass to
OWNER no later than the time of payment free and
clear of all Liens. This paragraph 13.03.A does not
apply to any documents covered by paragraph 3.04.A.
ARTICLE 13--PAYMENTS TO DESIGN/BUILDER
AND COMPLETION
13.01 Schedule of Values
A. The Schedule of Values established as provided
in paragraph 2.06.A will serve as the basis for progress
payments and will be incorporated into a form of
Application for Payment acceptable to OWNER.
Progress payments on account of Unit Price Work will
be based on the number of units completed.
13.02 Application for Progress Payment
A. At least twenty days before the date established
for each progress payment (but not more often than
once a month), DESIGNBUILDER shall submit to
OWNER for review an Application for Payment filled
out and signed by DESIGNBUILDER covering the
Work completed as of the date of the Application and
accompanied by such supporting documentation as is
required by the Contract Documents. If payment is
requested on the basis of materials and equipment not
incorporated in the Work but delivered and suitably
stored at the Site or at another location agreed to in
writing, the Application for Payment shall also be
accompanied by a bill of sale,, invoice or other
documentation warranting that OWNER has received
the materials and equipment free and clear of all Liens
and evidence that the materials and equipment are
covered by appropriate property insurance and other
arrangements to protect OWNER's interest therein, all
of which will be satisfactory to OWNER. The amount
of retainage with respect to progress payments will be
as stipulated in the Agreement.
13.03 DESIGNIBUILDER's Warranry of Title
29
40 13.04 Progress Payments
A. Progress payments shall be made by the
OWNER to the DESIGNBUILDER according to the
following procedure:
I. OWNER will, within ten days of receipt of each Application for Payment, either indicate in writing its acceptance of the Application and state
that the Application is being processed for payment,
or return the Application to DESIGNBUILDER indicating in writing its reasons for refusing to
accept the Application. Not more than ten days
after accepting such Application the amount will
become due and when due will be paid by OWNER
to DESIGN/BUILDER.
OWould fail to Pay
DESIGNBUILDER atRthe me the paymenttof any amount becomes due, then
DESIGNBUILDER may, at any time thereafter,
upon serving written notice that he will stop the
Work within seven days after receipt of the notice
by the OWNER, and after such seven day period,
stop the Work until payment of the amount owing
has been received. Written notice shall be deemed
to have been duly served if sent by certified mail to
the last known business address of the OWNER,
3. Payments due but unpaid shall bear interest
at the rate specified in the Agreement.
4. No Progress Payment nor any partial or
entire use or occupancy of the Project by the
OWNER shall constitute an acceptance of any
Work not in accordance with the Contract
Documents,
13, OWNER may refuse to make the whole or any
Part of any such payment, or because of subsequently
discovered evidence or the results of subsequent
inspections or tests, nullify any previous payment, to
The extent that is reasonably necessary to protect
OWNER from loss because:
I. The Work is defective, or completed Work
has been damaged requiring correction or
replacement; or
2• The Contract Price has been reduced by
Written Amendment or Change Order; or
3. OWNER has been required to correct
defective Work or complete Work in accordance
with paragraph 12.09.A, or
4. OWNER has actual knowledge of the
occurrence of any of the events enumerated in
paragraphs 14.02.A.1 through A.3 inclusive; or
5. Claims have been made against OWNER
on account of DESIGNBUILDER's performance
or furnishing of the Work; or
6. Liens have been filed in connection with
the Work, except where DESIGNBUILDER has
delivered a specific Bond satisfactory to OWNER
to secure the satisfaction and discharge of such
Liens; or
7. There are other items entitling OWNER to
a set off against the amount for which application
eis made.
1305 Substantial Completion
A. When DESIGNBUILDER considers the
Construction ready for its intended use
DESIGNBUILDER shall notify OWNER in writing
that the Construction is substantially complete (except
for items specifically listed by DESIGNBUILDER as
incomplete) and request that OWNER issue a
certificate of Substantial Completion. Within a
reasonable time thereafter, OWNER and
DESIGNBUILDER shall make an inspection of the
Construction to determine the status of completion. If
OWNER does not consider the Construction
Substantially complete, OWNER will notify
DESIGNBUILDER in writing giving the reasons
therefor. If OWNER considers the Construction
substantially complete, OWNER will prepare and
deliver to DESIGNBUILDER a certificate of
Substantial Completion which shall fix the date of
Substantial Completion. There shall be attached to the
certificate a list of items to be completed or corrected
before final payment. At the time of delivery of the
certificate of Substantial Completion OWNER will
30
E. DESIGN/BUILDER is aware of the general nature of work to be performed by
OWNER and others at the Site that relates to the Work as indicated in the Contract Documents.
F. DESIGN/BUILDER has correlated the information known to DESIGN/BUILDER,
information and observations obtained from visits to the Site, reports and drawings identified in the
Contract Documents and all additional examinations, investigations, explorations, tests, studies and
data with the Contract Documents.
G. DESIGN/BUILDER has given OWNER written notice of all conflicts, errors,
ambiguities or discrepancies that DESIGNBUILDER has discovered in the Contract Documents and
the written resolution thereof by OWNER is acceptable to DESIGN/BUILDER, and the Contract
Documents and the written resolution thereof by OWNER is acceptable to DESIGNBUILDER, and
the Contract Documents are generally sufficient to indicate and convey understanding of all terms
and conditions for performance and furnishing of the Work.
Article 11. ACCOUNTING RECORDS
11.0 DESIGNBUILDER shall keep such full and detailed accounts as may be necessary for
proper financial management under the Contract Documents with respect to all materials, equipment
and labor entering into the Work. The accounting methods shall be satisfactory to OWNER.
OWNER shall be afforded reasonable access to all of DESIGN/BUILDER'S records, books,
correspondence, instructions, drawings, receipts, vouchers, memoranda and similar data relating to
the Cost of Work and DESIGNBUILDER's Fee. DESIGN/BUILDER shall preserve all such
documents for a period of three years after final payment by OWNER.
Article 12. CONTRACT DOCUMENTS
12.01 The Contract Documents which comprise the entire agreement between OWNER and
DESIGN/BUILDER concerning the Work consist of the following:
A. This Agreement (pages 1 to 8, inclusive).
B. Exhibits to this Agreement - N/A
C. OWNER's Request for Proposal No. P-812 along with Conceptual Documents
identified therein.
D. DESIGNBUILDER's Proposal in Response to OWNER'S Request for Proposal No.
P-812.
E. Notices to Proceed.
F. Performance, payment, and other Bonds, identified as Section 00600, consisting of
14 pages.
G. Standard General Conditions of the Contract Between Owner and Design/Builder
5
deliver to DESIGNBUILDER a written determination
as to division of responsibilities pending final payment
between OWNER and DESIGNBUILDER with
respect to security, operation, safety, maintenance, heat, utilities, insurance and warranties and guarantees.
B. OWNER will have the right to exclude
DESIGN/BUILDER from the Site after the date of
Substantial Completion, but OWNER will allow
DESIGN/BUILDER reasonable access to complete or
correct items on the list of items to be completed.
13.06 Partial Utilization
A. Use by OWNER at OWNER's option of any
substantially completed part of the Construction which
(i) has specifically been identified in the Contract
Documents, or (ii) OWNER and DESIGNBUILDER
agree constitute a separately functioning and usable
part of the Construction that can be used by OWNER
for its intendecipurposewithout Significant interference
with DESIGNBUILDER's performance of the
remainder of the Construction, may be accomplished
prior to Substantial Completion of all the Construction
subject to the following:
I. OWNER at any time may request
DESIGNBUILDER in writing to permit OWNER
to use any such part of the Construction which
OWNER believes to be ready for its intended use
and substantially complete. If DESIGNBUILDER
agrees that such part of the Construction is substantially complete, DESIGNBUILDER will
certify to OWNER that such part of the
Construction is substantially complete and request
OWNER to issue a certificate of Substantial
Completion for that part of the Construction
DESIGNBUILDER at any time may notify
OWNER in writing that DESIGNBUILDER considers any such part of the Construction ready
for its intended use and substantially complete and
request OWNER to issue a certificate of
Substantial Completion for that part of the
Construction. Within a reasonable time after either
such request, OWNER and DESIGNBUILDER
Shall make an inspection of that part of the
Construction to determine its status of completion. If OWNER does not consider that part of the
31
Construction to be substantially complete, OWNER
will notify DESIGNBUILDER in writing giving
the reasons therefor. If OWNER considers that
part of the Construction to be substantially
complete, the provisions of paragraph 13.05 will
aPPIY with respect to certification of Substantial
Completion of that part of the Construction and
the division of responsibility in respect thereof and
access thereto.
2. No occupancy or separate operation of part
of the Construction will be accomplished prior to
compliance with the requirements of paragraph
5.08 in respect of property insurance.
13.07 Final inspection
A. Upon written notice from DESIGNBUILDER
that the entire Construction or an agreed portion
thereof is complete, OWNER will make a final
inspection with DESIGNBUILDER and will notify
DESIGNBUILDER in writing of all particulars in
which this inspection reveals that the Construction is
incomplete or defective. DESIGNBUILDER shall
immediately take such measures as are necessary to
complete such Construction or remedy such
deficiencies.
13.08 Final Application for Payment
A. After DESIGNBUILDER has completed all
such corrections to the satisfaction of OWNER and
delivered in accordance with the Contract Documents
all maintenance and operating instructions, schedules,
guarantees, Bonds, certificates or other evidence of
insurance required by paragraph 5.09.13, certificates of
inspection, marked -up record documents (as provided
in paragraph 6.11) and other documents,
DESIGNBUILDER may make application for final
payment following the procedure for progress
payments. The final Application for Payment shall be
accompanied (unless previously delivered) by: (i) all
documentation called for in the Contract Documents,
including but not limited to the evidence of insurance
required by subparagraph 5.02.B.7, (ii) consent of the
surety, if any, to final payment, and (iii) complete and
legally effective releases or waivers (satisfactory to
OWNER) of all Liens arising out of or filed in
connection with the Work. In lieu of such releases or
waivers of Liens and as approved by OWNER,
DESIGNBUILDER may furnish receipts or releases
in full and an affidavit of DESIGNBUILDER that:
(i) the releases and receipts include all labor, services,
material and equipment for which a Lien could be
filed, and (ii) all payrolls, material and equipment bills
and other indebtedness connected with the Work for
which OWNER or OWNER's property might in any
way be responsible have been paid or otherwise
satisfied. If any Subcontractor or Supplier fails to
furnish such a release or receipt in full,
DESIGNBUILDER may furnish a Bond or other
collateral satisfactory to OWNER to indemnify
OWNER against any Lien.
13,09 Final Payment and Acceptance No
A. If OWNER is satisfied that the Work has been
completed and DESIGNBUILD ER'sother obligations
under the Contract Documents have been fulfilled,
OWNER will, within ten days after receipt of the final
Application for Payment, give written notice to
DESIGNBUILDER that the Work is, acceptable.
Otherwise, OWNER will return the Application to
DESIGNBUILDER, indicating in writing the reasons
for refusing to process final payment, in which case
DESIGNBUILDER shall make the necessary
corrections and resubmit the Application. Thirty days
after the presentation to OWNER of the acceptable
Application and accompanying documentation, in
appropriate form and substance and with OWNER's
notice of acceptability, the amount will become due
and will be paid by OWNER to DESIGNBUILDER.
B. If, through no fault of DESIGNBUILDER,
final completion of the Work is significantly delayed,
OWNER shall, upon receipt of DESIGNBUILDER's
final Application for Payment, and without terminating
the Agreement, make payment of the balance due for
thmportion of the Work fully completed and accepted.
If the remaining balance to be held by OWNER for
Work not fully completed or corrected is less than the
retainage stipulated in the Agreement, and if Bonds
have been furnished as required in paragraph 5.01.A,
the written consent of the surety to the payment of the
balance due for that portion of the Work fully
completed and accepted shall be submitted by
32
DESIGNBUILDER to OWNER with the Application
for such payment. Such payment shall be made under
the terms and conditions governing final payment,
except that it shall not constitute a waiver of claims.
13.10 Waiver of Claims
A. The making and acceptance of final payment
will constitute:
I. A waiver of all claims by OWNER against
DESIGNBUILDER, except claims arising from
unsettled Liens, from defective Construction
appearing after final inspection pursuant to
paragraph 13.07, from failure to comply with the
Contract Documents or the terms of any special
guarantees specified therein, or from
D ESIGNBUILDER'sco ntinuing obligations under
the Contract Documents; and
2. A waiver of all claims by
DESIGNBUILDER against OWNER other than
those previously made in writing and still unsettled.
ARTICLE 14--SUSPENSION OF WORK AND
TERNUNATION
14.01 Owner May Suspend Work
A. At any time and without cause, OWNER may
suspend the Work or any portion thereof for a period
of not more than 90 days by notice in writing to
DESIGN/BUILDER which will fix the date on which
Work will be resumed. DESIGNBUILDER shall
resume the Work on the date so fixed.
DESIGNBUILDER shall be allowed an adjustment in
the Contract Price or an extension of the Contract
Times, or both, directly attributable to any such
suspension if DESIGNBUILDER makes a claim
therefor as provided in Article 9.
14.02 Owner May Terminate for Cause
A. The occurrence of any one or more of the
following events justifies termination for cause:
I
L DESIGNBUILDER persistently fails to
perform the Work in accordance with the Contract
Documents (including, but not limited to, failure to
supply sufficient skilled workers or suitable
materials or equipment or failure to adhere to the
progress schedule established under paragraph
2.06.A as revised from time to time.
2- DESIGNBUILDER disregards Laws or
Regulations of any public body having jurisdiction.
3. DESIGNBUILDER otherwise violates in
any substantial way any provisions of the Contract
Documents.
DB
ESIGNBUILDER (and the surety, if any) seven
days' written notice and to the extent permitted by
Laws and Regulations, terminate the services of
DESIGNBUILDER, exclude DESIGN/BUILDER
from the Site and take possession of the Work and of
all DESIGNBUILDER', tools, appliances, construction equipment and machinery at the Site and
use the same to the full extent they could be used by
DESIGN/BUILDER (without liability to
DESIGNBUILDER for trespass or conversion),
incorporate in the Work all materials and equipment
stored at the Site or for which OWNER has paid
DESIGNBUILDER but which are stored elsewhere,
and finish the Work as OWNER may deem expedient.
In such case DESIGNBUILDER shall not be entitled
to receive any further payment until the Work is
finished. If the unpaid balance of the Contract Price
exceeds all costs, losses and damages sustained by
OWNER arising out of or resulting from completing
the Work (including but not limited to all fees and
charges bf engineers, architects, attorneys and other
professionals and all court or arbitration or other
dispute resolution costs) such excess will be paid to
DESIGNBUILDER. If such costs, losses and
damages exceed such unpaid balance,
DESIGNBUILDER shall pay the difference to
OWNER. Such costs, losses and damages incurred by
OWNER will be incorporated in a Change Order,
Provided that when exercising any rights or remedies
under this paragraph OWNER shall not be required to
obtain the lowest price for the Work performed.
C. Where DESIGNBUILDER'sservices have been
SO terminated by OWNER, the termination will not
affect any rights or remedies of OWNER against
DESIGNBUILDER then existing or which may
thereafter accrue. Any retention or payment of
moneys due DESIGNBUILDER by OWNER will not release DESIGNBUILDER from liability.
14.03 Owner May Terminate for Convenience
A. Upon seven days' written notice to
DESIGNBUILDER, OWNER may, without cause and
without prejudice to any other right or remedy of
OWNER, elect to terminate the Agreement. In such
case, DESIGNBUILDER shall be paid (without
duplication of any items) for:
I. Completed and acceptable Work executed
in accordance with the Contract Documents prior
to the effective date of termination, including fair
and reasonable sums for overhead and profit on
such Work;
2. Expenses sustained prior to the effective
date of termination in performing services and
furnishing labor, materials or equipment as
required by the Contract Documents in connection
with uncompleted Work, plus fair and reasonable
sums for overhead and profit on such expenses;
^ of ncluding but not limited t r
charges of eng n chile es and
professionalsand orneysandother
rt itration or other
dispute ton costs incurred in con
_,.r ---. - _ _ nwith
4. Reasonable expenses directly attributable to
termination.
B. DESIGNBUILDER shall not be paid on
account of loss of anticipated profits or revenue or
other economic loss arising out of or resulting from
such termination.
33
14.04 DESIGN/BUILDER May Stop Work or
Terminate
A. If, through no act or fault of
DESIGNBUILDER, the Work is suspended for a
period of more than ninety days by OWNER or under
an order of court or other public authority, or
OWNER fails to act on any Application for Payment
within thirty days after it is submitted or OWNER fails
for thirty days to pay DESIGNBUILDER any sum
finally determined to be due, then DESIGNBUILDER
may, upon seven days' written notice to OWNER, and
provided OWNER does not remedy such suspension or
failure within that time, terminate the Agreement and
recover from OWNER payment on the same terms as
provided in paragraph 14.03.A. In lieu of terminating
the Agreement and without prejudice to any other
right or remedy, or OWNER has failed for thirty days
to pay DESIGNBUILDER any sum finally determined
to be due, DESIGNBUILDER may upon seven day's
written notice to OWNER stop the Work until
payment is made of all such amounts due
DESIGNBUILDER, including interest thereon. The
provisions of this paragraph 14.04.A are not intended
to preclude DESIGNBUILDER from making claim
under Article 9 for an increase in Contract Price or
Contract Times or otherwise for. expenses or damage
directly attributable to DESIGNBUILDER's stopping
Work as permitted by this paragraph.
ARTICLE 15--DISPUTE RESOLUTION
If and to the extent that OWNER and
DESIGNBUILDER have agreed on the method and
procedure for resolving disputes between them that
may arise under this Agreement, such dispute
resolution method and procedure, if any, shall be as set
forth in Exhibit GC -A, "Dispute Resolution
Agreement", to be attached hereto and made a part
hereof. If no such agreement on the method and
procedure for resolving such disputes has been
reached, OWNER and DESIGNBUILDER may
exercise such rights or remedies as either may
otherwise have under the Contract Documents or by
Laws or Regulations in respect of any dispute.
ARTICLE 16--MISCELLANEOUS
16.01 Giving Notice
A. Whenever any provision of the Contract
Documents requires the giving of written notice, it will
be deemed to have been validly given.
1. If delivered in person to the individual or
to a member of the firm or to an officer of the
corporation for whom it is intended;
2. If delivered at or sent by registered or
certified mail, postage prepaid, to the last business
address known to the giver of the notice; or
3. If transmitted by facsimile, the time at
which a machine generated confirmation states the
notice was received at the facsimile telephone
number of the intended recipient last known by the
sender.
16.02 Computation of Times
A. When any period of time is referred to in the
Contract Documents by days, it will be computed to
exclude the first and include the last day of such
period. If the last day of any such period falls on a
Saturday or Sunday or on a day made a legal holiday
by the law of the applicable jurisdiction, such day will
be omitted from the computation.
B. A calendar day of twenty-four hours measured
from midnight to the next midnight will constitute a
day.
16.03 Notice of Claim
A. Should OWNER or DESIGNBUILDER suffer
injury or damage to person or property because of any
error, omission or act of the other party or of any of
the other party's employees or agents or others for
whose acts the other party is legally liable, claim will be
made in writing to the other party within a reasonable
time of the first observance of such injury or damage.
The provisions of this paragraph 16.03.A shall not be
construed as a substitute for or a waiver of the
34
provisions of any applicable statute of
repose. limitations or
16.04 Cumulative Remedies
A. The duties and obligations imposed by these
General Conditions and the rights and remedies
available hereunder to the parties hereto, and, in
particular but without limitation, any general or
specific warranties, guarantees and indemnities
imposed upon DESIGNBUILDER and all of the
rights and remedies available to OWNER thereunder,
are in addition to, and are not to be construed in any
way as a limitation of, any rights and remedies
available to any or all of them which are otherwise
imposed or available by Laws or Regulations, by
special warranty or guarantee or by other provisions of
the Contract Documents, and the provisions of this
paragraph will be as effective as if repeated specifically
in the Contract Documents in connection with each
particular duty, obligation, right and remedy to which
they apply.
16.05 Survival of Obligations
A. All representations, indemnifications,
warranties and guarantees made in, required by or
given in accordance with the Contract Documents, as
well as all continuing obligations indicated in the
Contract Documents, will survive final payment,
Completion and acceptance of the Work and
termination or completion of the Agreement.
35
EXHIBIT GC -A to GENERAL CONDITIONS OF
THE AGREEMENT BETWEEN OWNER AND
DESIGNBUILDER DATED
For use with EJCDC No. 1910-40 (19 55 ed.)
15.01 Dispute Resolution Agreement
A. Article 15 of the General Conditions of the
Contract between OWNER and DESIGNBUILDER
is amended to include paragraphs 15.01.13-15.01.F.
B. OWNER and DESIGN/BUILDER agree that
they will first submit any and all unsettled claims,
counterclaims, disputes and other matters in question
between them arising out of or relating to the Contract
Documents or the breach thereof ("disputes"), to
mediation by
prior to either of them initiating against the other a
demand for arbitration pursuant to paragraph 15.01.0
through 15.01.1', unless delay in initiating arbitration
would irrevocably prejudice one of the parties. Any
time limits within which to file a demand for
arbitration shall be suspendedwith respect to a dispute
submitted to mediation within those same applicable
time limits and shall remain suspended until 10 days
after the termination of the mediation. The mediator
of any dispute submitted to mediation under this
Agreement shall not serve as arbitrator of such dispute
unless otherwise agreed.
C. All claims, disputes and other matters in
question between OWNER and DESIGNBUILDER
arising out of or relating to the Contract Documentsor
the breach thereof (except for claims which have been
waived by the making or acceptance of final payment
as provided by paragraph 13.10) will be decided by
binding arbitration in accordance with
subject to the limitations of this paragraph 15.01. This
agreement so to arbitrate and any other agreement or
consent to arbitrate entered into in accordance
her as provided in this paragraph 15.01 will be
specifically enforceable under the prevailing law of any
court having jurisdiction.
D. Notice of the demand for arbitration will be
filed in writing with the other parry to the Agreement
and with the designated arbitration entity. The
demand for arbitration will be made within a
reasonable time after the claim, dispute or other
matter in question has arisen, and in no event shall any
36
such demand be made after the date when institution
of legal or equitable proceedings based on such claim,
dispute or other matter in question would be barred by
the applicable statute of limitations.
E. Except as provided in paragraph 15.01.F below,
no arbitration arising out of or relating to the Contract
Documents shall include by consolidation, joinder or in
any other manner any other individual or entity who is
not a party to this contract unless:
1. the inclusion of such other individual or
entity is necessary if complete relief is to be
afforded among those who are already parties to
the arbitration, and
2. such other individual or entity is
substantially involved in a question of law or fact
which is common to those who are already parties
to the arbitration and which will arise in such
proceedings, and
3. the written consent of the other individual
or entity.sought to be included and of OWNER
and DESIGNBUILDER has been obtained for
such inclusion, which consent shall make specific
reference to this paragraph; but no such consent
shall constitute consent to arbitration of any
dispute not specifically described in such consent or
to arbitration with any party not specifically
identified in such consent.
F. Notwithstanding paragraph 15.01.E, if a claim,
dispute or other matter in question between OWNER
and DESIGNBUILDER involves the Work of a
Subcontractor, Supplier or Engineer either OWNER or
DESIGNBUILDER mayjoin such entity as a party to
the arbitration between OWNER and
DESIGNBUILDER hereunder. DESIGNBUILDER
shall include in all subcontracts required by paragraph
6.05.D a specific provision whereby the Subcontractor
consents to being joined in an arbitration between
OWNER and DESIGNBUILDER involving the Work
of such Subcontractor. Nothing in this paragraph
15.01.F nor in the provision of such subcontract
consenting to joinder shall create any claim, right or
cause of action in favor of Subcontractor, Supplier or
Engineer against OWNER.
SUPPLEMENTARY CONDITIONS
SECTION 00800
SUPPLEMENTARY CONDITIONS
Conditions of the Contract
These Supplementary Conditions amend or supplement the Standard General
Conditions of the Contract Between Owner and Design/Builder (1910-40, 1995
edition) and other provisions of the Contract Documents as indicated below.
Deletions (without revisions) to the General Conditions are made by
in the General Conditions and are not separately referenced in the
Supplementary Conditions. Revisions to the General Conditions are shown in the
Supplementary Conditions below the descriptor "REVISE", with deleted language
shown by nt=_!_=thrcg, ` and added language shown by underline, except that the
addition of completely new paragraph (s), or of completely new sentence(s) added
to a paragraph (without other revisions) are not underlined. Such completely new
language is shown below the descriptor "ADD".
SC-1 DEFINITIONS
REVISE the following definitions in ARTICLE 1, Paragraph 1.01, Defined Terms, of
' the General Conditions:
13. Contract Times --The numbers of days or the dates stated in the
Agreement (i) to achieve Substantial Completion, and (ii) to complete the Work
so that it is ready for final payment, as evidenced by OWNER's Representative's
written recommendation of final payment and in accordance with paragraph
13.08.A.
14. defective --An adjective which when modifying the term Construction gy
the term Work refers to Construction or Work that is unsatisfactory, faulty or
deficient , in that it does not conform to the Contract Documents, or does not
( meet the requirements of any inspection, reference standard, test or approval
I' referred to in the Contract Documents, or has been damaged prior OWNER's final
11 payment (unless responsibility for the protection thereof has been assumed by
OWNER at Substantial Completion).
f 20..Engineer--A duly licensed individual or entity. in >>ding b+ no
( limited to an Engineer Architect, designated by DESIGN/BUILDER to perform or
furnish specified Design Professional Services in connection with the Work.
f 21. Field Order --A written order issued by OWNER which orders minor
it changes in the Work inaccordancewith ARTICLE 9--CHANGES 9--CHANGESIN THE WORx CLAIMS
but which does not involve a change in the Contract Price or the Contract Times.
23. Hazardous Waste --The term Hazardous Waste shall have the meaning
provided in Section 1004 of the Solid Waste Disposal Act (42 USC Section 6903)
as amended from time to time.
28. Notice to Proceed --A written notice given by OWNER to DESIGN/BUILDER
fixing the date on which the Contract Times will commence to run and on which
DESIGN/BUILDER shall start to perform DESIGN/BUILDER'S obligations under the
ContractQQntract Documents.
f
00800-1
35. Project --The total construction of which theme Work to be
provided under the Contract Documents may be the whole, or a part as indicated
elsewhere in the Contract Documents.
ADD the following definitions to ARTICLE 1, Paragraph 1.01, Defined Terms, of the
General Conditions:
24A. Legal Holidays --shall be those holidays observed by the City of Fort
Collins.
37A. Regular Working Hours --are defined as 7:00 am to 6:00 pm, Monday
through Friday, unless otherwise specified in the Contract Documents.
39A. Samples --Physical examples of materials, equipment, or workmanship
that are representative of some portion of the Work and which establish the
standards by which such portion of the Work will be judged.
40A. Shop Drawings --All drawings, diagrams, illustration, schedules and
other data or information which are specifically prepared or assembled by or for
DESIGN/BUILDER and submitted by DESIGN/BUILDER to illustrate some portion of the
Work.
47A. Underground Facilities --All pipelines, conduits, ducts, cables,
wires, manholes, vaults, tanks, tunnels or other such facilities or attachments,
and any encasements containing such facilities which have been installed
underground to furnish any of the following services or materials: electricity,
gases, steam, liquid petroleum products, telephone or other communications, cable
television, sewage and drainage removal, traffic or other control systems or
water.
SC-2 PRELIMINARY NATTERS
REVISE the following language in ARTICLE 2, Paragraph 2.03, Starting the Work,
of the General Conditions:
2.03.A. DESIGN/BUILDER shall start to perform the Work on the date when 1
the Contract Times commence to run but no Work shall t, ,a r the prior -
.to_ the date on which the Contract Times commence
ADD the following Paragraph to ARTICLE 2, Paragraph 2.04, Before Starting
Construction, of the General Conditions, to precede Paragraph 2.04.A:
2.04.AA. Before undertaking each part of the Work, DESIGN/BUILDER shall
carefully study and compare the Contract Documents and check and verify pertinent
figures shown thereon and all applicable field measurements. DESIGN/BUILDER shall
promptly report in writing to OWNER any conflict, error, ambiguity, or
discrepancy which DESIGN/BUILDER may discover and shall obtain a written
interpretation or clarification from OWNER before proceeding with any Work
affected thereby; however, DESIGN/BUILDER shall not be liable to OWNER for
failure to report any conflict, error, ambiguity, or discrepancy in the Contract
Documents, unless DESIGN/BUILDER knew or reasonably should have known thereof.
REVISE the following language in ARTICLE 2, Paragraph 2.04.A.2, Before Starting
Construction, of the General Conditions:
2.04.A.2. A preliminary schedule of required Submittals and the times for
submitting, reviewing and processing each Submittal; in no case will a Schedule
be accentable which allows legs than's (7) gglendar days LQK each review by {
OWNER. L.
00800-2
REVISE the following language in the final sentence in ARTICLE 2, Paragraph
2.04.A.3, Before Starting Construction, of the General Conditions:
2.04.A.3. .... Such prices will include a pre Eata Appropriate amount of
overhead and profit applicable to each item of Work; ....
f'
REVISE ARTICLE 2, Paragraph 2.04.B, Before Starting Construction, by DELETING
Paragraph 2.04.B of the General Conditions and ADDING this replacement Paragraph
2.04.B:
2.04.B. Before any Work is started, DESIGN/BUILDER shall deliver to OWNER
certificates of insurance (and other evidence of insurance requested by OWNER)
which DESIGN/BUILDER is required to purchase and maintain in accordance with
ARTICLE 5--BONDS AND INSURANCE.
REVISE ARTICLE 2, Paragraph 2.06.A, Initially Acceptable Schedules, by DELETING
the first sentenceofParagraph 2.06.A of the General Conditions and ADDING this
replacement sentence at the beginning of Paragraph 2.06.A:
2.06.A. Unless otherwise provided in the Contract Documents, before any
work at the site begins, a conference attended by DESIGN/BUILDER, OWNER's
Representative, and others as designated by OWNER will be held to review for
acceptability to OWNER as provided herein the schedules submitted in accordance
with paragraph 2.04.A. ....
SC-3 CONTRACT DOCUMENTS: INTENT, ANENDING, REUSE
ADD the following Paragraph to ARTICLE 3, Paragraph 3.01, Intent, of the General
Conditions:
i. 3.01.C. Whenever in the Contract Documents the terms "as ordered", "as
directed", "as required", "as approved" or terms of like effect or import are used,
or the adjectives "reasonable", "suitable", "acceptable", "proper" or "satisfactory"
or adjectives of like effect or import are used to describe a requirement,
direction, review. or judgment of OWNER as to the Work, it is intended that such
requirement, direction, review or judgment will be solely to evaluate, in
general, the completed Work for compliance with the requirements of and
information in the Contract Documents and conformance with the design concept of
the completed Project as a functioning whole as shown or indicated in the
Contract Documents (unless there is a specific statement indicating otherwise).
i The use of any such term or adjective shall not be effective to assign to OWNER
any duty or authority to supervise or direct the furnishing or performance of the
Work or any duty or authority to undertake responsibility contrary to any
provision of the Contract Documents.
1( ADD the following Paragraph to the end of Paragraph 3.02.B in ARTICLE 3,
i Paragraph 3.02, References, of the General Conditions:
II 3.02.B.3. In the event of conflicting or ambiguous provisions within the
Contract Documents, specifications will take precedence over the drawings and
addenda will take precedence over both. Notwithstanding the foregoing, the more
specific provision will take precedence over the less specific; the more
stringent will take precedence over the less stringent; the more expensive item
I4 will take precedence over the less expensive. On all drawings, figures take
00800-3
(pages 1 to 36,inclusive).
H. Supplementary Conditions (pages 00800-1 to 00800-25, inclusive).
I. Addenda numbers 1 through 2 inclusive.
GMP Proposal dated 11/29/2001 and Other Documentation submitted by
DESIGN/BUILDER prior to Notice of Award (pages 1 to 5, inclusive).
K. Application for Payment (pages 1 to 2, inclusive)
Change Order Form (page 1, inclusive)
L. The following, which may be delivered, prepared or issued after the Effective Date
of this Agreement and are not attached hereto:
All Written Amendments and other documents amending, modifying or
supplementing the Contract Documents pursuant to paragraph 3.03.A of the
General Conditions.
Specifications as defined in Paragraph 1.01.A.42 of the General Conditions.
3. Drawings as defined in Paragraph 1.01.A.18 of the General Conditions.
M. Milestone Schedule.
12.02 The documents listed in paragraph 12.01 above are attached to this Agreement (except as
otherwise expressly noted).
12.03 There are no Contract Documents other than those listed above in this Article 12. The
Contract Documents may only be amended, modified or supplemented as provided in paragraph
3.03.A of the General Conditions.
12.04 In the case of any irreconcilable ambiguity, inconsistency or conflict between
DESIGN/BUILDER'S Proposal (Section 12.01.13) and the Request for Proposal (Section 12.0l.C),
the terms of the Proposal shall be controlling. In the case of any irreconcilable ambiguity,
inconsistency or conflict among the Contract Documents listed in Section 12.01, the documents
listed in Section 12.0I.K shall govern, and in the case of any irreconcilable ambiguity, inconsistency
or conflict among the documents listed in Section 12.01.K, the documents listed in Sections
12.0l.K.1, Section 12.0l.K.2, and Section 12.0l.K.3 shall take precedence, in the order herein listed.
Article 13. MISCELLANEOUS
13.01 The Standard General Conditions of the Contract Between Owner and Design/Builder are
referred to herein as the General Conditions.
13.02. Terms used in this Agreement which are defined in Article 1 of the General Conditions will
f
precedence over scaled dimensions. Scaling of dimensions, if done, is done at
the DESIGN/BUILDER'S own risk.
ADD the following Paragraph to ARTICLE 3, Paragraph 3.02, References, of the
General Conditions:
3.02.D. If, during the performance of the Work, DESIGN/BUILDER discovers ;
any conflict, error, ambiguity, or discrepancy within the Contract Documents or
between the Contract Documents and any provision of any such Law or Regulation
applicable to the performance of the Work or of any such standard, specification,
manual or code or of any instruction of any Supplier referred to in paragraph
6.03.C, DESIGN/BUILDER shall report it to OWNER in writing at once, and
DESIGN/BUILDER shall not proceed with the Work affected thereby (except in an
emergency as authorized by paragraph 6.15) until an amendment or supplement to
the Contract Documents has been issued by one of the methods indicated in
paragraph 3.03.A; provided, however, that DESIGN/BUILDER shall not be liable to
OWNER for failure to report any such conflict, error, ambiguity, or discrepancy
unless DESIGN/BUILDER knew or reasonably should have known thereof.
ADD the following Paragraph to the end of Paragraph 3.04.A in ARTICLE 3,
Paragraph 3.04, Reuse of Documents, of the General Conditions:
3.04.B. Upon conclusion of the Project and before final payment,
DESIGN/BUILDER shall provide OWNER with reproducible drawings and electronic
computer files of the Project containing accurate information on the Project as
constructed. Drawings shall be of archival quality, prepared on stable mylar
base material using a non -fading process proven suitable for long-term storage
and high -quality reproduction. Electronic computer files shall. be in AutoCAD
Version 13 format.
SC-4 AVAILABILITY OF LANDS; SUBS13RFACE AND PHYSICAL CONDITIONS; REFERENCE
POINTS; HAZARDOUS CONDITIONS a
i
REVISE the title of ARTICLE 4 of the General Conditions:
ARTICLE 4--AVAILABILITY OF LANDS; SVBSURFACE AND PHYSICAL
CONDITIONS; REFERENCE POINTS; HAZARDOUS CONDITIONS
REVISE ARTICLE 4, Paragraph 4.02, Differing Site Conditions, by DELETING
Paragraph 4.02 of the General Conditions and ADDING this replacement Paragraph
4.02:
4.02. Subsurface and Physical Conditions.
A. Reports and Drawings: Refer to these Supplementary Conditions for
identification of:
1. Subsurface Conditions: Those reports of explorations and tests of
subsurface conditions at or contiguous to the site that have been utilized by
OWNER in preparing the Contract Documents.
a. The following report of exploration and tests of subsurface
conditions at the site of the work:
Proposed City of Fort Collins Administration Building, LaPorte Ave. and
Mason St., Fort Collins, Colorado, Project #20985047, dated April 27, 1998 by:
Terracon Consultants Western, Inc., Fort Collins, Colorado.
00800-4
Contractor may rely upon the accuracy of the technical data contained in
the geotechnical documents, but not upon nontechnical data, interpretations or
opinions contained therein or upon the completeness of any information in the
report.
2. Physical Conditions: Those drawings of physical conditions in or
( relating to existing surface or subsurface structures at or contiguous to the
site (except Underground Facilities) that have been utilized by OWNER in
preparing the Contract Documents.
a. No drawings of physical conditions in or relating to existing
surface or subsurface structures (except Underground Facilities referred to in
Paragraph 4.02.G) which are at or contiguous to the site have been utilized in
preparation of the Contract Documents, except the following:
Not Applicable.
B. Limited Reliance by DESIGN/BUILDER Authorized; Technical Data:
DESIGN/BUILDER may rely upon the general accuracy of the "technical data,,
contained in such reports and drawings, but such reports and drawings are not
Contract Documents. Such "technical data" is identified in the Request for
�- Proposals or in these Supplementary Conditions. Except for such reliance on such
"technical data,,, DESIGN/BUILDER may not rely upon or make any claim against
OWNER, with respect to:
(i) the completeness of such reports and drawings for DESIGN/BUILDER'S
purposes, including, but not limited to, any aspects of the means, methods,
i techniques, sequences and procedures of construction to be employed by
DESIGN/BUILDER and safety precautions and programs incident thereto, or
(ii) other data, interpretations, opinions and information contained in
such reports or shown or indicated in such drawings, or
(iii) any DESIGN/BUILDER interpretation of or conclusion drawn from any
1. "technical data,, or any such data, interpretations, opinions or information.
C. Notice of Differing Subsurface or Physical Conditions: If
DESIGN/BUILDER believes that any subsurface or physical condition at or
(-- contiguous to the site that is uncovered or revealed either:
(i) is of such a nature as to establish that any "technical data" on which
DESIGN/BUILDER is entitled to rely as provided in paragraphs 4.02.A and 4.02.E
is materially inaccurate, or
(ii) is of such a nature as to require a change in the Contract Documents,
or
(iii) differs materially from that shown or indicated in the Contract
Documents, or
(iv) is of an unusual nature, and differs materially from conditions
ordinarily encountered and generally recognized as inherent in work of the
character provided for in the Contract Documents; or
(v) is of such a nature as to reasonably be suspected of containing or
constituting Asbestos, PCBs, Petroleum, Hazardous Waste, or Radioactive Material,
or such other substances or materials that may result in significant damage or
injury or require compliance with specifically applicable regulatory
requirements, unless confirmation of the absence of such condition has previously
been provided;
then DESIGN/BUILDER shall, immediately after becoming aware thereof and
before further disturbing conditions affected thereby or performing any Work in
connection therewith (except in an emergency as permitted by paragraph 6.15),
notify OWNER in writing about such condition. DESIGN/BUILDER shall not further
00800-5
disturb such conditions or perform any Work in connection therewith (except as
aforesaid) until receipt of written order to do so.
D. OWNER's Review: OWNER will promptly review the pertinent conditions,.
determine the necessity of obtaining additional exploration or tests with respect
thereto.
E. Possible Contract Documents Change: If OWNER concludes that a change
in the Contract Documents is required as a result of a condition that meets one
�•
or more of the categories in paragraph 4.02.C, a work Change Directive or a
Change Order will be issued as provided in Article 9 to reflect and document the
consequences of such change.
F. Possible Price and Times Adjustments: An equitable adjustment in the
Contract Price or in the Contract Times, or both, will be allowed to the extent
that the existence of such uncovered or revealed condition causes an increase or
decrease in DESIGN/BUILDER'S cost of, or time required for performance of, the
Work; subject, however, to the following:
1. such condition must meet any one or more of the categories described in
paragraph 4.02.C;
2. a change in the Contract Documents pursuant to paragraph 4.02.E will
not be an automatic authorization of nor a condition precedent to entitlement to
any such adjustment;
3. with respect to Work that is paid for on a Unit Price Basis, any
j
adjustment in Contract Price will be subject to the provisions of paragraph
10.04; and
4. DESIGN/BUILDER shall not be entitled to any adjustment in the Contract
1
Price or Times if:
i.
(i) DESIGN/BUILDER knew of the existence of such conditions at the time
DESIGN/BUILDER made a final commitment to OWNER in respect of Contract Price and
Contract Times by the submission of a bid or becoming bound under a negotiated
1
contract; or
(ii) the existence of such condition could reasonably have been discovered
a
or revealed as a result of any examination, investigation, exploration, test or
study of the site and contiguous areas required by the Request for Proposals or
Contract Documents to be conducted by or for DESIGN/BUILDER prior to
DESIGN/BUILDER'S making such final commitment; or
(iii) DESIGN/BUILDER failed to give the written notice within the time and
as required by paragraph 4.02.0 above.
If OWNER and DESIGN/BUILDER are unable to agree on entitlement to or as to
the amount or length of any such equitable adjustment in the Contract Price or
Contract Times, a claim may be made therefor as provided in Articles 10 and 11.
However, OWNER shall not be liable to DESIGN/BUILDER for any claims, costs,
j
losses or damages sustained by DESIGN/BUILDER on or in connection with any other
1
project or anticipated project.
G. Physical Conditions --Underground Facilities:
1. Shown or Indicated: The information and data shown or indicated in the
}
Contract Documents with respect to existing Underground Facilities at or
1
contiguous to the site is based on information and data furnished to OWNER by the
owners of such Underground Facilities or by others. Unless it is otherwise
expressly provided in the Supplementary Conditions:
a. OWNER shall not be responsible for the accuracy or completeness
of any such information or data; and
,
00800-6
f
f
b. the cost of all of the following will be included in the
Contract Price and DESIGN/BUILDER shall have full responsibility for:
(i) reviewing and checking all such information and data,
(ii) locating all Underground Facilities shown or indicated in the
Contract Documents,
(iii) coordination of the Work with the owners of such Underground
? Facilities during construction, and
(iv) the safety and protection of all such Underground Facilities as
provided in paragraph 6.12 and repairing any damage thereto resulting from the
Work.
_ 2. Not Shown or Indicated: If an Underground Facility is uncovered or
revealed at or contiguous to the site which was not shown or indicated in the
Contract Documents, DESIGN/BUILDER shall, immediately after becoming aware
thereof and before further disturbing conditions affected thereby or performing
any Work in connection therewith (except in an emergency as required by
paragraph 6.15), identify the owner of such Underground Facility and give written
notice to that owner and to OWNER. OWNER will promptly review the Underground
�. Facility and determine the extent, if any, to which a change is required in the
Contract Documents to reflect and document the consequences of the existence of
the Underground Facility. If OWNER concludes that a change in the Contract
Documents is required, a Work Change Directive or a Change Order will be issued
as provided in Article 9 to reflect and document such consequences. During such
time, DESIGN/BUILDER shall be responsible for the safety and protection of such
Underground Facility as provided in paragraph 6.12. DESIGN/BUILDER may be
i- allowed an increase in the Contract Price or an extension of the Contract Times,
or both, to the extent that they are attributable to the existence of any
Underground Facility that was not shown or indicated in the Contract Documents
and that DESIGN/BUILDER did not know of and could not reasonably have been
expected to be aware of or to have anticipated. If OWNER and DESIGN/BUILDER are
unable to agree on entitlement to or the amount or length of any such adjustment
in Contract Price or Contract Times, DESIGN/BUILDER may make a claim therefor as
provided in Articles 10 and 11. However, OWNER shall not be liable to
DESIGN/BUILDER for any claims, costs, losses or damages incurred or sustained by
DESIGN/BUILDER on or in connection with any other project or anticipated project.
REVISE ARTICLE 4, Paragraph 4.04, Hazardous Conditions, by DELETING Paragraph
4.04 of the General Conditions and ADDING this replacement Paragraph 4.04:
4.04. Asbestos, PCBs, Petroleum, Hazardous Waste or Radioactive Material
A. OWNER shall be responsible for any Asbestos, PCBs, Petroleum, Hazardous
Waste or Radioactive Material uncovered or revealed at the site which was not
shown or indicated in Drawings or Specifications or identified in the Contract
Documents to be within the scope of the Work and which may present a substantial
danger to persons or property exposed thereto in connection with the Work at the
site unless such substance or material should have been ascertained by
`- DESIGN/BUILDER in accordance with paragraph 4.02.C.(v). OWNER shall not be
responsible for any such materials brought to the site, managed, stored, or
disposed of by DESIGN/BUILDER, Subcontractors, Suppliers, or anyone else for whom
DESIGN/BUILDER is responsible.
I SC-5 BONDS AND INSURANCE
a 00800-7
REVISE the following language in ARTICLE 5, Paragraph 5.01.B, Performance,
Payment and Other Bonds, of the General Conditions:
5.01.B. If any surety on any Bond furnished by DESIGN/BUILDER is declared
a bankrupt or becomes insolvent or its right to do business is terminated in any
state where any part of the Project is located or it ceases to meet the
requirements of paragraph S.Ol.A, DESIGN/BUILDER shall within thlr-Ey ten (10)
days thereafter substitute another Bond and surety, meeting the ".^ me of
paFaqEaphs _ 0, r ,-a ^ both of which must be acceptable to OWNER.
REVISE the following language in ARTICLE 5, Paragraph 5.02, DESIGN/BUILDER'S
Liability Insurance, of the General Conditions:
5.02.B.1. With respect to insurance required by paragraphs 5.02.A.3
through 5.02.A.6 inclusive, 5.02.B.3. and 5.02.C. include as additional insureds
(subject to any customary exclusion in respect of orofess' nai liability) OWNER
and OWNER's Consultants and any other persons or entities indicated in the
Supplementary Conditions, all of whom shall be listed as additional insureds, and
include coverage for the respective officers and employees of all such additional
insureds.
ADD the following language to the end of Paragraph 5.02.B.2 in ARTICLE 5, �.
Paragraph 5.02.B, DESIGN/BUILDER's Liability Insurance:
5.02.B.2. .... The limits of liability for the insurance required by the
paragraph numbers of the General Conditions listed below are as follows:
For Paragraphs 5.02.A.1 and 5.02.A.2: Coverage A - Statutory Limits; '
Coverage B - $100,000 / $100,000 / $500,000
For Paragraphs 5.02.A.3 and 5.02.A.5: The Commercial General Liability �-
policy will have limits of $1,000,000 combined single limits (CSL). This policy
will include coverage for Explosion, Collapse, and Underground coverage unless
waived by the Owner.
For Paragraph 5.02.A.6: The Comprehensive Automobile Liability Insurance 3
policy will have limits of $1,000,000 combined single limits (CSL).
For Paragraph 5.02.B.3: This policy will include completed operations
coverage / product liability coverage with limits of $1,000,00o combined single_
limits (CSL). This policy shall also include an Umbrella Excess Liability as
follows: General liability and automobile liability insurance in an amount not
less than $1,000,000 per occurrence in excess of the above stated primary limits.
For Paragraph 5.02.C: The Professional Liability Errors & Omissions policy
will have limits of $5,000,000.
ADD the following Paragraph in ARTICLE 5, Paragraph 5.02, DESIGN/BUILDER'S 1.
Liability Insurance, of the General Conditions:
5.02.C. DESIGN/BUILDER's Professional Liability Errors & Omissions
Insurance. DESIGN/BUILDER shall purchase and maintain such Professional
Liability Errors & Omissions insurance as is appropriate for the Work being
performed and furnished and as will provide protection from claims which may
arise out of or result from DESIGN/BUILDER's performance and furnishing of the (i
Work and DESIGN/BUILDER'S other obligations under the Contract Documents, whether L:
it is to be performed or furnished by DESIGN/BUILDER, any Subcontractor or
Supplier, or by anyone directly or indirectly employed by any of them to perform
00800-8
is
or furnish any of the Work, or by anyone for whose acts any of them may be
liable.
REVISE ARTICLE 5, Paragraph 5.04, Property Insurance, and Paragraph 5.05, Waiver
of Rights, by DELETING the entirety of Paragraphs 5.04 and 5.05 of the General
�- Conditions and ADDING this replacement Paragraph 5.04:
f 5.04. Property Insurance
The Owner shall purchase and maintain, in a company or companies lawfully
authorized to do business in the State of Colorado, Builder's Risk insurance for
! 100% of the contract value for the entire project at the site on a replacement
cost basis with a deductible of $10,000 for all perils. This Builder's Risk
policy shall provide "all risk" coverage including Earthquake and Flood. The
policy shall be maintained, unless otherwise provided in the contract documents
or otherwise agreed upon in writing by all persons and entities who are
beneficiaries of such insurance, until final payment has been made or until no
person or entity other than the Owner has an insurable interest in the property
to be covered, whichever is earlier. The Builder's Risk policy shall include the
interests of the Owner, the Design -Builder, subcontractors, and sub -
subcontractors in the project.
In the event of a covered loss, the Design -Builder shall be responsible for
payment of the $10,000 deductible, which shall be considered as a cost of the
work.
A waiver of subrogation clause applies to the Builder's Risk policy against all
parties named as insureds, but only to the extent that any loss is covered.
' Losses insured by the Builder's Risk policy that are in excess of the $10,000
deductible shall be adjusted strictly with the Owner. Any insurance
payments/proceeds shall be made payable to the Owner subject to the requirements
C of any applicable mortgagee clause. The Owner shall pay the Design -Builder their
just share of any insurance proceeds. The Design -Builder shall pay their
1.. subcontractors their just shares of any insurance proceeds received by the
l_ Design -Builder, and by appropriate agreements, written where legally required for
validity, shall require subcontractors to make payments to their sub -
subcontractors in similar manner.
REVISE ARTICLE 5, Paragraph 5.07, Acceptance of Bonds and Insurance; Option to
Replace, by DELETING Paragraph 5.07.A of the General Conditions and ADDING this
replacement Paragraph 5.07.A.:
5.07.A. If OWNER has any objection to the coverage afforded by or other
provisions of the insurance required to be purchased and maintained by
DESIGN/BUILDER in accordance with Article 5 on the basis of non-conformance with
the Contract Documents, OWNER will notify DESIGN/BUILDER in writing within
fifteen (15) days after delivery of the certificates to OWNER as required by
paragraph 2.04.B.
{ 00800-9
i�
SC-6 DESIGN/BUILDER'S
REVISE the final sentence in ARTICLE 6, Paragraph 6.01.A., Standard of Care,. of
the General Conditions:
6.01.A. .... The standard of care for all such services performed or
furnished under this Agreement will be the care and skill ordinarily used by
members of the architectural and engineering professions practicing under similar
conditions at the same time and locality.
ADD the following sentence to the end of Paragraph 6.03.A in ARTICLE 6, Paragraph
6.03, Labor, Materials and Equipment, of the General Conditions:
6.03.A. .... DESIGN/BUILDER shall submit requests to OWNER no less than 48
hours in advance of any Work to be performed on Saturday, Sunday, Legal Holidays,
or outside Regular Working Hours.
ADD the following Paragraphs in ARTICLE 6, Paragraph 6.03, Labor, Materials and
Equipment, of the General Conditions:
6.03.B.1. Purchasing Restrictions: DESIGN/BUILDER must comply with the
City's purchasing restrictions. Copies of the resolution(s) are available for
review in the offices of the Purchasing and Risk Management Division or the City
Clerk's office. (_
6.03.B.2. Cement Restrictions: City of Fort Collins Resolution 91-121
requires that suppliers and producers of cement or products containing cement
certify that the cement was not made in cement kilns that burn hazardous waste
as a fuel.
ADD the following Paragraphs in ARTICLE 6, Paragraph 6.03, Labor, Materials and
Equipment, of the General Conditions:
6.03.D. Substitutes and "Or -Equal" Items: Whenever an item of material or
equipment is specified or described in the Contract Documents by using the name
of a proprietary item or the name of a particular Supplier, the specification or
description is intended to establish the type, function and quality required.
Unless the specification or description contains or is followed by words reading
that no like, equivalent, or "or -equal" item or no substitution is permitted,
other items of material or equipment or material or equipment of other Suppliers
may be accepted by OWNER under the following circumstances:
1. "Or -Equal": If in OWNER's sole discretion an item of material or
equipment proposed by DESIGN/BUILDER is functionally equal to that named and
sufficiently similar so that no change in related Work will be required, it may
be considered by OWNER as an "or -equal" item, in which case review and approval
of the proposed item may, in OWNER's sole discretion, be accomplished without
compliance with some or all of the requirements for acceptance of proposed
substitute items.
2. Substitute Items: If in OWNER's sole discretion an item of material or
equipment proposed by DESIGN/BUILDER does not qualify as an "or -equal" item under
paragraph 6.03.D.1, it will be considered a proposed substitute item.
DESIGN/BUILDER shall submit sufficient information as provided below to allow
OWNER to determine that the item of material or equipment proposed is essentially
equivalent to that named and an acceptable substitute therefor. The procedure for
review by the OWNER will include the following as supplemented in the General
00800-10
L
Requirements and as OWNER may decide is appropriate under the circumstances.
Requests for review of proposed substitute items of material or equipment will
not be accepted by OWNER from anyone other than DESIGN/BUILDER. If
DESIGN/BUILDER wishes to furnish or use a substitute item of material or
equipment, shall first make written application to OWNER for acceptance thereof,
certifying that the proposed substitute will perform adequately the functions and
achieve the results called for by the general design, be similar in substance to
that specified and be suited to the same use as that specified. The application
,
will state the extent, if any, to which the evaluation and acceptance of the
proposed substitute will prejudice DESIGN/BUILDER'S achievement of Substantial
Completion on time, whether or not acceptance of the substitute for use in the
Work will require a change in any of the Contract Documents (or in the provisions
of any other direct contract with OWNER for work on the Project) to adapt the
design to the proposed substitute, and whether or not incorporation or use of the
substitute in connection with the Work is subject to payment of any license fee
or royalty. All variations of the proposed substitute from that specified will
be identified in the application and available maintenance, repair and.
replacement service will be indicated. The application will also contain an
itemized estimate of all costs or credits that will result directly or indirectly
( from acceptance of such substitute, including costs of redesign and claims of
1 other contractors affected by the resulting change, all of which will be
considered by OWNER in evaluating the proposed substitute. OWNER may require
DESIGN/BUILDER to furnish additional data about the proposed substitute.
3. DESIGN/BUILDER'S Expense: All data to be provided by DESIGN/BUILDER in
support of any proposed "or -equal" or substitute item will be at DESIGN/BUILDER's
r_ expense.
4. Substitute Construction Methods or Procedures: If a specific means,
i method, technique, sequence or procedure of construction is shown or indicated
in and expressly required by the Contract Documents, DESIGN/BUILDER may furnish
or utilize a substitute means, method, technique, sequence or procedure of
construction acceptable to OWNER. DESIGN/BUILDER shall submit sufficient
information to allow OWNER, in OWNER's sole discretion, to determine that the
(- substitute proposed is equivalent to that expressly called for by the Contract
Documents. The procedure for review by OWNER will be similar to that provided
t' in paragraph 6.03.D.2.
_ 5. OWNER's Evaluation: OWNER will be allowed a reasonable time within
lwhich to evaluate each proposal or submittal made pursuant to paragraphs
6.03.D.2 and 6.03.D.4. OWNER will be the sole judge of acceptability. No "or -
equal" or substitute will be ordered, installed or utilized without OWNER's prior
i written acceptance which will be evidenced by either a Change Order or an
+ approved Shop Drawing or Submittal. OWNER may require DESIGN/BUILDER to furnish
1
at DESIGN/BUILDER'S expense a special performance guarantee or other surety with
respect to any "or -equal" or substitute. OWNER will record time required by
OWNER and OWNER's Consultants in evaluating substitutes proposed or submitted by
DESIGN/BUILDER pursuant to paragraphs 6.03.D.2 and 6.03.D.4. and in making
changes in the Contract Documents (or in the provisions of any other direct
contract with OWNER for work on the Project) occasioned thereby. Whether or not
C; OWNER accepts a substitute item so proposed or submitted by DESIGN/BUILDER,
DESIGN/BUILDER shall reimburse OWNER for the charges of OWNER and OWNER's
Consultants for evaluating each such proposed substitute item.
00800-11
L:
REVISE the following language in ARTICLE 6, Paragraph 6.04, Progress Schedule,
of the General Conditions:
6.04.A.1. DESIGN/BUILDER shall submit to OWNER for acceptance proposed
adjustments in the progress schedule that will not change the Contract Times (or
Milestones). Such adjustments will conform generally to the progress schedule
then in effect, an& additionally will comply with any provisionprovisioag of the Contract
Documents applicable thereto.
ADD the following language to the end of Paragraph 6.05.A in ARTICLE 6, Paragraph
6.05, Concerning Subcontractors, Suppliers and Others, of the General Conditions:
605.A. .... DESIGN/BUILDER shall perform not less than 20 percent of the
Work with its own forces (that is, without subcontracting). The 20 percent
requirement shall be understood to refer to the Work the value of which totals
not less than 20 percent of the Contract Price.
ADD the following Paragraph in ARTICLE 6, Paragraph 6.05, Concerning
Subcontractors, Suppliers and Others, of the General Conditions:
6.05.C.1. The divisions and sections of the Specifications and the
identifications of any Drawings shall not control DESIGN/BUILDER in dividing the
Work among Subcontractors or Suppliers or delineating the Work to be performed
by any specific trade.
REVISE the final two sentences in ARTICLE 6, Paragraph 6.07, Permits, of the
General Conditions:
6.07.A. .... DESIGN/BUILDER shall pay all governmental charges and
inspection fees necessary for the prosecution of theGensti-uetje: Work, which are
applicable on the last day for receipt of Proposals or on the effectivedate f
the Agreement. DESIGN/BUILDER shall pay all charges of utility owners for
connections to the Work, and DESIGN/BUILDER shall nay for all of the following
fees: Building Permit Fee and Plan Check Fee.
ADD the following Paragraph in ARTICLE 6, Paragraph 6.09, Taxes, of the General
Conditions:
6.09.B. OWNER is exempt from Colorado state and local sales and use taxes
on materials to be permanently incorporated into the project. Said taxes shall
not be included in the Contract Price.
DESIGN/BUILDER must apply for, and receive, a Certificate of Exemption
from the Colorado Department of Revenue for construction materials to be
physically incorporated into the project. This Certification of Exemption
provides that the DESIGN/BUILDER shall neither pay nor include in his Proposal,
sales and use taxes on those building and construction materials physically
incorporated into the project.
Address: Colorado Department of Revenue
State Capital Annex
1375 Sherman Street
Denver, Colorado 80261
Sales and use taxes for the State of Colorado, Regional Transportation
District (RTD) and certain Colorado counties are collected by the State of
Colorado and are included in the Certification of Exemption.
All applicable sales and use taxes (including State collected taxes) on
any items other than construction and building materials physically incorporated
00800-12
into the project are to be paid by DESIGN/BUILDER and are to be included in
appropriate Work items.
REVISE Paragraph 6.10.A by DELETING each of the three appearances of the word
"Construction" and ADDING "Work" in ARTICLE 6, Paragraph 6.10, Use of Site and
Other Areas, of the General Conditions:
6.10.A. .... GQRStrustle Wo
rk ....
REVISE the final sentence in ARTICLE 6, Paragraph 6.11, Record Documents, of the
General Conditions:
6.11.A. .... Upon completion of the Work and prior to r i agg of final
payment, these record documents and Submittals, including a reproducible set of
record drawings as provided in paragraph 3.04.B, will be delivered to OWNER.
REVISE the following sentence in ARTICLE 6, Paragraph 6.15, Emergencies, of the
General Conditions:
6.15. .... DESIGN/BUILDER shall give OWNER prompt written notice if
DESIGN/BUILDER believes that any significant changes in the PR_.,,._,eti en Work or
variations from the Contract Documents have been caused thereby. ....
REVISE the first sentence in Paragraph 6.18.A in ARTICLE 6, Paragraph 6.18,
DESIGN/BUILDER'S General Warranty and Guarantee, of the General Conditions:
6.18.A. DESIGN/BUILDER warrants and guarantees to OWNER that all
Gens==aRe Work will be in accordance with the Contract Documents and will not
be defective. ....
REVISE the following language in Paragraph 6.18.A.1 in ARTICLE 6, Paragraph 6.18,
= DESIGN/BUILDER's General Warranty and Guarantee, of the General Conditions:
6.18.A.1. Abuse, modification, or improper maintenance or operation by
persons other than DESIGN/BUILDER, Subcontractors or Suppliers. .11aless such
abuse modification or improper maintenance gr operation was permitted by or
could reasonably have been prevented b DESIGN/BUILDER.
yb on to o
Suppliers.
REVISE the following
language in Paragraph 6.18.B.3 in ARTICLE 6, Paragraph 6.18,
DESIGN/BUILDER's General Warranty and Guarantee, of the General Conditions:
6.18.B.3. The issuance of a certificate of Substantial Completion or any
1 payment by OWNER to DESIGN/BUILDER under the QQntract Documents,,
REVISE ARTICLE 6, Paragraph 6.19.A, Indemnification, of the General Conditions:
6.19.A. DESIGN/BUILDER shall indemnify and hold harmless OWNER, OWNER's
officers, directors, employees, agents and consultants from and against all
claims, costs, losses and damages (including but not limited to all fees and
charges of engineers, architects, attorneys and other professionals and all court
or arbitration or other dispute resolution costs) arising out of or resulting
from the performance of GeastEuet4mea Wor , provided that any such claim, cost,
loss or damage is attributable to bodily injury, sickness, disease or death, or
to injury to or destruction of tangible property (other than the Work itself),
including the loss of use resulting therefrom, but only to the extent such claim,
cost or damage is caused in whole or :n -art by any negligent act or omission of
00800-13
l_.
have the meanings indicated therein.
13.03 No assignment by a party hereto of any rights under or interests in the Contract Documents
will be binding on another party hereto without the written consent of the party sought to be bound;
and, specifically but without limitation, moneys that may become due and moneys that are due may
not be assigned without such consent (except to the extent that the effect of this restriction maybe
limited by law), and unless specifically stated to the contrary in any written consent to an assignment
no assignment will release or discharge the assignor from any duty or responsibility under the
Contract Documents, except that the OWNER may assign all rights and responsibilities of the
OWNER under this Agreement to the Fort Collins Capital Leasing Corporation ("FCCLC"), and
FCCLC may assign the same to the Bank of Cherry Creek, N.A., as trustee under the terms of a trust
indenture between said parties in connection with OWNER's lease Certificates of Participation
issued in connection with the Project.
13.04 OWNER and DESIGN/BUILDER each binds itself, its partners, successors, assigns and legal
representatives to the other party hereto, its partners, successors, assigns and legal representatives
in respect to all covenants, agreements and obligations contained in the Contract Documents.
13.05. Any provision or part of the Contract Documents held to be void or unenforceable under any
Law or Regulation shall be deemed stricken, and all remaining provisions shall continue to be valid
and binding upon OWNER and DESIGN/BUILDER, who agree that the Contract Documents shall
be reformed to replace such stricken provision or part thereof with a valid and enforceable provision
that comes as close as possible to expressing the intention of the stricken provision.
13.06 The Contract Documents shall constitute public records under the Colorado Public Records
Act, and shall be available for public review upon request, except for the Audited Financial
Statement of DESIGN/BUILDER included in DESIGN/BUILDER'S Proposal.
IN WITNESS WHEREOF, OWNER and DESIGN/BUILDER have signed this Agreement
in duplicate. One counterpart each has been delivered to OWNER and DESIGN/BUILDER. All
portions of the Contract Documents have been signed, initiated or identified by OWNER and
DESIGN/BUILDER.
This Agreement will be effective on February(6, 2002.
7
DESIGN/BUILDER, any Subcontractor, Engineer, any Supplier, any individual or
entity directly or indirectly employed by any of them to perform or furnish any
of the Work or anyone for whose acts any of them may be liable, regardless o
whether or not caused in by any nealigengg Qr omission of an individual o _
entity in indpmnif ied hereunder or whether liability imposed upon such
indemnified party by Laws and Regulations regardless of the negligence of any
Such individual or entitv.
REVISE the first portion of Paragraph 6.19.B. in ARTICLE 6, Paragraph 6.19,
Indemnification, of the General Conditions:
6.19.B. In any and all claims against OWNER or any of their OWNER's
respective consultants, agents, officers, directors, or employees ...
ADD the following Paragraph 6.20 in ARTICLE 6 of the General Conditions:
6.20. Survival of obligations.
All representations, indemnifications, warranties and guarantees made in,
required by or given in accordance with the Contract Documents, as well as all
continuing obligations indicated in the Contract Documents, will survive final
payment, completion and acceptance of the work and termination or completion of
the Agreement. {'
i
SC-7 OTHER CONSTRUCTION
REVISE the title of Paragraph 7.01 in ARTICLE 7, Paragraph 7.01, Related
Construction at Site, of the General Conditions:
7.01. Related t4e; Work at Site
REVISE the first sentence in Paragraph 7.01.B in ARTICLE 7, Paragraph 7.01,
Related Work at Site, of the General Conditions:
7.01.B. DESIGN/BUILDER shall afford each other contractor who is a party !
to such a direct contract and each utility owner (and OWNER, if OWNER is j
performing the additional work with OWNER's employees) proper and safe access to
the Site and a reasonable opportunity for the introduction and storage of !
materials and equipment and the execution of such other work and shall properly It
connect and coordinate the Gensti-aetie Work with theirs. ....
SC-8 RESIDENT PROJECT
8.03.B. The Resident Project Representative deals in matters pertaining
to the work. Any such dealings will be with or through the Design/Builder.
Dealings with subcontractors will only be through or with the full knowledge and
approval of the Design/Builder.
00800-14
r
l
Duties and Responsibilities of the Resident Project Representative are:
Attend meetings with the Design/Builder such as preconstruction
conferences, progress meetings and other job conferences.
Serve as owner's liaison with Design/Builder working principally
through Design/Builder's superintendent to assist the Design/Builder
in obtaining from OWNER additional details or information, when
required, for proper execution of the Work.
Advise the Design/Builder of the commencement of any Work pertaining
to a Shop Drawing, data, or sample submission which does not meet
the Contract Documents.
Conduct on -site observations of the Work in progress in determining
that the Work is proceeding in accordance with the Contract
Documents.
Report to the Design/Builder's superintendent whenever the Resident
Project Representative believes that the Work is unsatisfactory,
faulty or defective, does not conform to the Contract Documents, or
! has been damaged, or does not meet the requirements of any
t
inspections, tests or approvals required to be made; and advise the
Owner's Representative and Design/Builder when he believes work
should be corrected or rejected or should be uncovered for
observation, or requires special testing, inspection or approval.
Accompany visiting inspectors representing public or other agencies
having jurisdiction over the Project.
1
Consider and evaluate Design/Builder suggestions for modification in
r Drawings or Specifications and report these recommendations to
Owner's Representative.
I
Maintain at the Resident Project Representative office orderly files
concerning correspondence, reports of job conferences, Shop
Drawings, data, and samples, reproductions or original Contract
Documents including all Work Directive Changes, Addenda, Change
Orders, Field orders, additional drawings issued subsequent to the
execution of the Agreement, Design/Builder clarifications and
interpretations of the Contract Documents, progress reports and
other project documents.
Keep a diary, daily report form, or log book, recording hours on the
job site, weather conditions, data relative to questions of work
directive changes, Change Orders, or changed conditions, list of job
site visitors, daily activities, decisions, observations in general
and specific observations in more detail as in the case of observing
test procedures.
00800-15
Report immediately to Owner's Representative the occurrence of any
accident.
Review application for payment with Design/Builder for compliance
with the established procedure for their submission and will submit
to the Owner's Representative.
Conduct final inspection with the Design/Builder and Owner's
Representative observe that all items on the final inspection list
have been corrected or completed and make recormnendations to Owner's
Representative concerning acceptance.
The Resident Project Representative shall not:
Authorize any deviations from the Contract Documents or accept any
substitute materials or equipment.
Exceed limitations of Resident Project Representative authority as
set forth in the Contract Documents. Undertake any of the
responsibilities of the Design/Builder, Subcontractors, or
Design/Builder's superintendent.
Advise on, or issue directions relative to, or assume control over
any aspect of the means, methods, techniques, sequences or
procedures for construction unless such is specifically called for
in the Contract Documents.
Advise on or issue directions regarding or assume control over
safety precautions and programs in connection with the Work.
a
Accept Shop Drawings, data, or samples submittals from anyone other y
than the Design/Builder.
r
SC-9 CHANGES IN THE WORK; CLAIMS
i
REVISE the first sentence, thereby creating two sentences, in ARTICLE 9,
Paragraph 9.01, General --Rights and Obligations, of the General Conditions:
9.0I.A. Without invalidating the Agreement and without notice to any
surety, OWNER may, at any time or from time to time, order additions, deletions
or revisions in the work within the geeeaFal--seepe—e€ the eentraet. such
additions, deletions or revisions will be authorized by a Written Amendment, a +
Change Order, or a Work Change Directive. .... 1,
REVISE Paragraph 9.07.A.1 in ARTICLE 9, Paragraph 9.07, Execution of Change
Orders, of the General Conditions:
9.07.A.1. changes in the Work which are
(i) ordered by OWNER pursuant to paragraph 9.01,
00800-16
(ii) required because of the acceptance of defective Construction or Work
under paragraph 12.08 or correcting defective Construction or Work under
paragraph 12.09 or
(iii) agreed to by the parties; and
S ADD the following language to the conclusion of Paragraph 9.07.A, after Paragraph
9.07.A.2, in ARTICLE 9, Paragraph 9.07, Execution of Change Orders, of the
General Conditions:
9.07.A. ....provided that, in lieu of executing any such Change order, an
appeal may be taken from any such decision in accordance with the provisions of
the Contract Documents and applicable Laws and Regulations, but during any such
appeal, DESIGN/BUILDER shall carry on the Work and adhere to the progress
schedule as provided in paragraph 6.17.
ADD the following Paragraph in ARTICLE 9 of the General Conditions:
9.09. By the execution of a Change Order, a Work Change Directive, or
Written Agreement, OWNER and DESIGN/BUILDER expressly acknowledge and agree that
i said Change Order, Work Change Directive, or Written Agreement provides for a
fair and equitable adjustment in Contract Price and/or Contact Time for the
additions, deletions, or revisions in the Work as authorized by said Change
Order, Work Change Directive or Written Agreement. OWNER and DESIGN/BUILDER
further expressly acknowledge and agree that claims for adjustments to the
s Contract Price and/or Contract Time covered by a Change Order, Work Change
y Directive or Written Agreement are not valid.
�. SC-10 CHANGE OF CONTRACT PRICE
{ ADD the following sentence in ARTICLE 10, Paragraph 10.01, General, at the
conclusion of Paragraph 10.01.A of the General Conditions:
1O.O1.A. .... All duties, responsibilities and obligations assigned to or
undertaken by DESIGN/BUILDER in these Contract Documents shall be at
DESIGN/BUILDER'S expense without change in the Contract Price.
REVISE ARTICLE 10, Paragraph 10.01, General, of the General Conditions:
_ 10.01.C.2. Where the Work involved is not covered by unit prices contained
in the Contract Documents, by a mutually agreed payment basis, 'n ding lump sum
i (which may include an allowance for overhead and profit not necessarily in
accordance with paragraph 10.02) or by mutually agreed unit prices;
r
Y ADD the following language to the conclusion of Paragraph 10.02.A.3 in ARTICLE
10, Paragraph 10.02.A, Costs Included, of the General Conditions:
t 10.02.A.3. .... If required by OWNER, DESIGN/BUILDER shall obtain
j competitive bids from Subcontractors acceptable to OWNER and DESIGN/BUILDER, and
t shall deliver such bids to OWNER who will then determine which bids, if any, will
be accepted. If any subcontract provides that the Subcontractor is to be paid
on the basis of Cost of the Work plus a fee, the Subcontractor's Cost of the Work
and fee shall be determined in the same manner as DESIGN/BUILDER's Cost of the
Work and fee as provided in ARTICLE 10. All subcontracts shall be subject to the
' other provisions of the Contract Documents insofar as applicable.
00800-17
l-
The following work will be performed as self -work by DESIGN/BUILDER, or
subcontracted to the following firms (subject to executing a subcontract
agreements.)
REVISE the first sentence in Paragraph 10.02.A.6.f in ARTICLE 10, Paragraph
10.02.A, Costs Included, of the General Conditions:
10.02.A.6.f. Losses, damages and related expenses caused by damage to the
Work not compensated by insurance or otherwise, sustained by DESIGN/BUILDER in
connection with the furnishing and performance of the Work (except losses
damages within the deductible amo n s of proparty insurance established by OWNER
in accordance with paragraph 5.04 above) provided they have resulted from causes
other than the negligence of DESIGN/BUILDER, any Subcontractor, or anyone
directly or indirectly employed by any of them or for whose acts any of them may
be liable. ....
REVISE Paragraph 10.02.A.6.i in ARTICLE 10, Paragraph 10.02.A, Costs Included, ,
of the General Conditions:
10.02.A.6.i. Cost of premiums for a3-1 additional Bonds and insurance j
DESIGN/BUILDER is required by the Contract Documents to purchase and maintain i-
hggause of chaaaggin the Work.
ADD the following Paragraph in ARTICLE 10, Paragraph 10.02.B, Costs Excluded, of
the General Conditions:
10.02.B.6. Cost of premiums for all Bonds and for all insurance whether or _
not DESIGN/BUILDER is required by the Contract Documents to purchase and maintain
the same (except for the cost of premiums covered by paragraph 10.02.A.6.i
above).
REVISE Paragraphs 10.02.C.2.a, 10.02.C.2.b, 10.02.C.2.c and 10.02.C.2.d in
ARTICLE 10, Paragraph 10.02_C, Fee, of the General Conditions:
10.02.C.2.a For costs incurred under paragraphs 10.02A.1, A.2, A.5 and A.6
the DESIGN/BUILDER's fee shall be-i3 3 percent;
10.02.C.b For costs incurred under paragraph 10.02.A.3 and 10.02.A.4,
the DESIGN/BUILDER'S fees shall be five 3 percent; �
10.02.C.2.c. Where one or more tiers of subcontracts are on the basis of
Cost of the Work plus a fee and no fixed fee is agreed upon, the intent of '.
paragraphs 10.02.A.1, 10.02.A.2, and 10.02.A.3 is that the Subcontractor who
actually performs or furnishes Work, at whatever tier, will be paid a fee of 15
percent of the costs incurred by such Subcontractor under paragraphs 10.02.A.1
i
and 10.02.A.2 and that any higher tier Subcontractor and DESIGN/BUILDER will each
be paid a fee of five peL-een€- of the &mean paj:d—te—t-}3e—&east lewer timer
SaAieeatr&eteE to be negotjated in good faith wi h OWNER h t
-ugt to exceed f!YC
percent of the 9M91ant paid to the next lower tier Subcontractor;
10.02.C.d. The amount of credit to be allowed by DESIGN/BUILDER by OWNER
for any change which results in a net decrease in cost will be the amount of the �-
00800-18
r
t,
i
actual net decrease in cost plus a deduction in DESIGN/BUILDER'S fee by an amount
equal to #$ve .1 percent of such net decrease;
REVISE Paragraph 10.04.C.1 in ARTICLE 10, Paragraph 10.04, Unit Prices, of the
General Conditions:
r 10.04.C.1. the quantity of any item of Unit Price Work performed by
DESIGN/BUILDER differs materially and significantly from the estimated quantity
of such item indicated in the Contract Documents by more than the percentage
indicated in the Supplementary Conditions, and
ADD the following Paragraph in ARTICLE 10, Paragraph 10.04, Unit Prices, of the
General Conditions:
10.04.D. DESIGN/BUILDER acknowledges that OWNER has the right to add or
delete items of the Work or change quantities at OWNER's sole discretion without
affecting the Contract Price of any remaining item so long as the deletion or
addition does not exceed twenty-five percent of the estimated ciantity for h
item 6r-i-gi__'l `etal ..g...tr-aet P ee..SC-11
CHANGE OF CONTRACT TIMES
f'
i
REVISE Paragraph 11.02.B in ARTICLE 11, Paragraph 11.02, Time Extensions, of the
General Conditions:
11.02.B. N9thing in th _ _h
i
BFSIFW/-BA_T-anrn due tze delay, Katie fer-e_-- --- disrupt4sn
Est- 4llere DESIGN/BUTLD R is n v * a from completing any Part of the Work within
�- the Contract Times (or Milestones) due to delay b yond the control of OWNER and
DESIGN/BUILDER an extension of the on r t m' (or Milestones) PS) in an amount
equal to the time lost due o such delay shad be DESIGN/BUILDER sole and
exclusive remedy for such dplay. In no -event hall OWNER be liable to
DESIGN/BUILDER for costs or damages arising out of or resulting from:
( (i) delays caused by or within the control of DESIGN/BUILDER, or
;�. (ii) delays beyond the control of both parties, including but not limited
to fires, floods, epidemics, abnormal weather conditions, acts of God, or acts
of neglect by governmental agencies, utility owners or other contractors
performing other work as contemplated by Article 7.
1
L�
SC-12 TESTS AND INSPECTIONS; CORRECTION, REMOVAL OR ACCEPTANCE OF DEFECTIVE
CONSTRUCTION
REVISE the title of Article 12, TESTS AND INSPECTIONS; CORRECTION,. REMOVAL OR
ACCEPTANCE OF DEFECTIVE CONSTRUCTION, of the General Conditions:
ARTICLE 12--TESTS AND INSPECTIONS; CORRECTION, REMOVAL OR ACCEPTANCE OF
DEFECTIVE CONSTRUCTION OR WOR&
REVISE the following language in Paragraph 12.01.A in ARTICLE 12, Paragraph
12.01, Notice of Defects, of the General Conditions:
12.01.A. Prompt %FEittea notice of all defective Construction or Work of
which OWNER has actual knowledge will be given to DESIGN/BUILDER by OWNER. All
00800-19
defective Construction or Work may be rejected, corrected or accepted as provided
in this Article 12.
REVISE the first sentence of Paragraph 12.03.A in ARTICLE 12, Paragraph 12.03,
Tests and Inspections, of the General Conditions:
12.03.A. If the Contract Documents or Laws or Regulations of any public
body having jurisdiction require any part of the GenstEiaetle Wor specifically
to be inspected, tested or approved, DESIGN/BUILDER shall assume full
responsibility for arranging and obtaining such inspections, tests or approvals,
pay all costs in connection therewith, and furnish OWNER the required
certificates of inspection or approval. ....
ADD the following Paragraph in ARTICLE 12, Paragraph 12,03, Tests and
Inspections, of the General Conditions:
12.03.D. OWNER shall employ and pay for the services of an independent
testing laboratory to perform all inspections, tests, or approvals required by ,
the Contract Documents except (i) for inspections, tests, or approvals covered
by paragraph 12.03.A above; (ii) that costs incurred in connection with tests or
inspections conducted pursuant to paragraph 12.04.B below shall be paid as
provided in said paragraph 12.04.B; and (iii) as otherwise specifically provided
in the Contract Documents. �.
REVISE the first portion of the second sentence in Paragraph 12.04.B in ARTICLE
12, Paragraph 12.04, Uncovering Construction, of the General Conditions:
12.04.B. .... If it is found that such Construction is defective,
DESIGN/BUILDER shall pay all claims. costs, losses and damages caused by, arising _
out of or resulting from such uncovering, exposure, observation, inspection and
testing and of satisfactory replacement or rework ... i
REVISE the following language, including the title, in ARTICLE 12, Paragraph `
12.05, OWNER May Stop the Construction, of the General Conditions:
12.05 OWNER May Stop the Construction or Work
12.05.A. If the Construction or Work is defective, or DESIGN/BUILDER fails
to supply sufficient skilled workers or suitable materials or equipment, or fails
to furnish or perform the Construction or Work in such a way that the completed }'
GenstFiaetiea Work will conform to the Contract Documents, OWNER may order _
DESIGN/BUILDER to stop Construction or Work or any portion thereof, until the [
cause for such order has been eliminated; however, this right of OWNER to stop (.
Construction shall not give rise to any duty on the part of OWNER to exercise
this right for the benefit of DESIGN/BUILDER or any surety or other party.
REVISE the following language, including the title, in ARTICLE 12, Paragraph
12.06, Correction or Removal of Defective Construction, of the General
Conditions:
12.06 Correction or Removal of Defective Construction or Work
12.06.A. OWNER will have the authority to disapprove or reject defective
Construction or Work and will have the authority to require special inspection
or testing of the Construction or Work whether or not the Construction or Work
is fabricated, installed or completed. If required by OWNER, DESIGN/BUILDER
shall promptly, as directed, either correct all defective whether or not the
Construction or Work is fabricated, installed or completed Construction or Work,
00800-20
whether or not fabricated, installed or completed, or, if the Construction gX
Work has been rejected by OWNER, remove it from the Site and replace it with
nondefective Construction or Work. DESIGN/BUILDER shall bear all direct, indirect
and consequential costs of such correction, replacement, and/or removal
(including but not limited to all claims, costs, losses and damages
arising out of...or ul ing from such correctign, Igiplacement,and/or removal.
and fees and charges of engineers, architects, attorneys and other professionals --
made necessary thereby)-.
- REVISE the following language in Paragraph 12.07.A in ARTICLE 12, Paragraph
12.07, Correction Period, of the General Conditions:
12.07.A. If within one year after the date of Substantial Completion or
such longer period of time as may be prescribed by Laws or Regulations or by the
terms of any applicable special guarantee required by the Contract Documents or
by any specific provision of the Contract Documents, any Construction or Work is
found to be defective, DESIGN/BUILDER shall promptly, without cost OWNER and in
accordance with OWNER's written instructions,
t_ (i) correct such defective Construction or Work, or, if it has been
rejected by OWNER, remove it from the Site and replace it with Construction that
is not defective, and
(ii) satisfactorily correct or remove and replace any damage to other
Construction or Work or the work of others resulting therefrom.
r If DESIGN/BUILDER does not promptly comply with the terms of such
instructions, or in an emergency where delay would cause serious risk of loss or
`- damage, OWNER may have the defective Construction or Work corrected or the
rejected Construction or Work removed and replaced, and all claims. costs, losses
and damages caused b � g y, arising out of or resulting from such correction or
i removal (including but not limited to all fees and charges of engineers,
architects, attorneys and other professionals, all court or arbitration or other
' dispute resolution costs, and all costs of repair or replacement of work of
others) will be paid by DESIGN/BUILDER.
j REVISE the following language in Paragraph 12.07.0 in ARTICLE 12, Paragraph
}- 12.07, Correction Period, of the General Conditions:
( 12.07.C. where defective Construction or Work (and damage to other
Construction or Work resulting therefrom) has been corrected, removed or replaced
under this paragraph 12.07, the correction period hereunder with respect to such
i Construction or Work will be extended for an additional period of one year after
correction or removal and replacement has been satisfactorily completed.
i REVISE the following language, including the title, in ARTICLE 12, Paragraph
12.08, Acceptance of Defective Construction, of the General Conditions:
t 12.08 Acceptance of Defective Construction or Work
12.08.A. If, instead of requiring correction or removal and replacement of
r defective Construction or Work, OWNER may do so. DESIGN/BUILDER shall pay all
costs attributable to OWNER's evaluation of and determination to accept such
defective Construction or Work (such costs to include but not be limited to all
fees and charges of engineers, architects, attorneys and other professionals and
all court or arbitration or other dispute resolution costs). If any such
�- acceptance occurs prior to final payment, a Change Order will be issued
00800-21
incorporating the necessary revisions in the Contract Documents with respect to
the Construction and Work; and OWNER shall be entitled to an appropriate decrease
in the Contract Price, and, if the parties are unable to agree as to the amount
thereof, OWNER may make a claim therefor as provided in Article 9. If the
acceptance occurs after final payment, an appropriate amount will be paid by
DESIGN/BUILDER to OWNER.
REVISE the following language, including the title, in ARTICLE 12, Paragraph
12.09, OWNER May Correct Defective Construction, of the General Conditions:
12.09 OWNER May Correct Defective Construction or Work-
12.09.A. If DESIGN/BUILDER fails within a reasonable time after wr-ii-tsn
;
notice from OWNER to correct defective Construction or Work or to remove and
replace rejected Construction or Work as required by OWNER in accordance with
paragraphs 12.06.A or 12.07.A, or -if DESIGN/BUILDER fails to perform the
-
Construction or Work in accordance with the Contract Documents, or if
DESIGN/BUILDER fails to comply with any other provision of the Contract
Documents, OWNER may, after seven days' written notice to DESIGN/BUILDER, correct
_
and remedy any such deficiency. In exercising the rights and remedies under this
paragraph OWNER shall proceed expeditiously. In connection with such corrective
and remedial action, OWNER may exclude DESIGN/BUILDER from all or part of the
Site, take possession of all or part of the Construction or Work, and suspend
-
DESIGN/BUILDER'S services related thereto, take possession of DESIGN/BUILDER'S
tools, appliances, construction equipment and machinery at the Site and
incorporate in the Construction or Work all materials and equipment stored at the
Site or for which OWNER has paid DESIGN/BUILDER but which are stored elsewhere.
DESIGN/BUILDER shall allow OWNER, OWNER's representatives, agents and employees,
OWNER'S other contractors and Consultants access to the Site to enable OWNER to
exercise the rights and remedies under this paragraph. All costs and damages
incurred or sustained by OWNER in exercising such rights and remedies will be
charged against DESIGN/BUILDER and a Change Order will be issued incorporating
the necessary revision in the Contract Documents and OWNER shall be entitled to
an appropriate decrease in the Contract Price, and, if the parties are unable to
agree as to the amount thereof, OWNER may make a claim therefor as provided in
Article 9. Such claims, costs, losses and damages will include but not be
limited to all fees and charges of engineers, architects, attorneys and other
professionals, all court or arbitration or other dispute resolution costs, and
all costs of repair or replacement of work of others destroyed or damaged by
correction, removal or replacement of DESIGN/BUILDER's defective Construction 2
Work. DESIGN/BUILDER shall not be allowed an extension of the Contract Times (or
Milestones) because of any delay in the performance of the Construction or Work
i
attributable to the exercise by OWNER of OWNER's rights and remedies hereunder.
'
i
00800-22
is
r
t
SC-13 PAYMENTS TO DESIGN/BUILDER AND COMPLETION
REVISE the following language in Paragraph 13.02.A in ARTICLE 13, Paragraph
13.02, Application for Progress Payment, of the General Conditions:
13.02.A. .... If payment is requested on the basis of materials and
equipment not incorporated in the Work but delivered and suitably stored at the
Site or at another location agreed to in writing, the Application for Payment
shall also be accompanied by a bill of sale, invoice or other documentation
warranting that OWNER has received the materials and equipment free and clear of
all Liens and evidence that the materials and equipment are covered by
appropriate property insurance provided by DESIG_ N/BIDER and other arrangements
to protect OWNER's interest therein, all of which will be satisfactory to OWNER.
ADD the following Paragraph in ARTICLE 13, Paragraph 13.02, Application for
Progress Payment, of the General Conditions:
13.02.B. Any funds that are withheld by OWNER shall not be subject to
substitution by DESIGN/BUILDER with securities or any arrangements involving an
escrow or custodianship. By executing the Application for Payment form,
DESIGN/BUILDER expressly waives his right to the benefits of Colorado Revised
Statutes, Section. 24-91-101, et seq.
REVISE the title in ARTICLE 13, Paragraph 13.04, Progress Payments, of the
' General Conditions:
13.04. Review of Appliad.tions for progress Payment
REVISE the first sentence of Paragraph 13.04.A.2 in ARTICLE 13, Paragraph 13.04,
Review of Applications for Progress Payment, of the General Conditions:
' 13.04.A.2. If the OWNER should fail to pay the DESIGN/BUILDER at the time
the payment of any amount becomes due, =cgpt as providtd in paragraph 13 04 a
and as otherwise prgyid d in thQ Contract Documents, .then DESIGN/BUILDER may, at
any time thereafter, upon serving written notice that he will stop the Work with
seven days .after receipt of the notice by the OWNER, and after such seven day
t period, stop the Work until payment of the amount owing has been received. ....
ADD the following Paragraph to Paragraph 13.04.E in ARTICLE 13, Paragraph 13.04,
! Review of Applications for Progress Payment, of the General Conditions:
13.04.B.8. OWNER has actual knowledge of the occurrence of any of the
events enumerated in paragraphs 13.04.13.1 through 13.04.B.3 inclusive, or
paragraphs 14.02.A.1 through 14.02.A.3 inclusive.
ADD the following language at the conclusion of Paragraph 13.04.B, following
Paragraph 13.04.B.8, in ARTICLE 13, Paragraph 13.04, Review of Applications for
Progress Payment, of the General Conditions:
13.04.B. .... but OWNER must give DESIGN/BUILDER immediate written notice
stating the reasons for such action and promptly pay DESIGN/BUILDER the amount
so withheld, or any adjustment thereto agreed to by OWNER and DESIGN/BUILDER,
when DESIGN/BUILDER corrects to OWNER's satisfaction the reasons for such action.
00800-23
OWNE IT/Y pOF,FORT � COLLINS
By:
John . Fischbach
Ci Manager(
By: l
s B. O'Neill II, CPPO, FNIGP
D' ector_of P/urch ing and Risk Management
Date: `� / / n Z�
AA ES�L�I:
� o
City Clerk
Address for giving notices:
PO Box 580
Fort Collins, CO 80522
APPRO ED AS TO FORM:
lvk _
Assistant City Attorney
Designated Representative:
Name: Ron Kechter
Title: Facilities Project Manager
Address: PO Box 580
Fort Collins, CO 80522
Phone: 970-221-6805
DESIGN/BUILDER: The Neenan CompanyLL L?
By: `l
N e: J es J. Nee
314-I o Z-
ATTEST
-r,! lyj
Address for giving notices:
2620 E. Prospect
Fort Collins. CO 80525
License No.A-11-11
(If DESIGN/BUILDER is a corporation,
attach evidence of authority to sign.)
Designated Representative:
Name: Bob Merserve
Title: Senior Project Manager
Address: 2620 E. Prospect Rd. Suite 100
Fort Collins, CO 80525
Phone: 970-495-6319
Facsimile: 970-221-6534 Facsimile: 970-493-5869
r
ADD the following language at the conclusion of Paragraph 13.08.A in ARTICLE 13,
Paragraph 13.08, Final Application for Payment, of the General Conditions:
13.08.A. ..... Releases or waivers of liens and the consent of the surety
to finalize payment are to be submitted on forms conforming to the format of the
OWNER's standard forms bound in the Project manual.
REVISE the final sentence of Paragraph 13.09.A in ARTICLE 13, Paragraph 13,09,
Final Payment and Acceptance, of the General Conditions:
13.09.A. ....Thirty days after the presentation to OWNER of the acceptable
Application and accompanying documentation, in appropriate form and substance and
with OWNER's notice of acceptability, the amount will become due and will be paid
by OWNER to DESIGN/BUILDER subiect to naraaraph 16 06 B of h Supplementary
Conditions.
SC-14 SUSPENSION OF WORK AND TERMINATION
REVISE the title and initial language of Paragraph 14.02.A in ARTICLE 14,
Paragraph 14,02, OWNER May Terminate for Cause, of the General Conditions:
14.02. OWNER May Terminate
A. Upon the occurrence of any one or more of the following events {
jast.r.__ teEFnina#iA19GWNER may terminat this A5— r
herein. dement a v d d ;
REVISE each appearance of the phrase "costs, losses and damages" as follows in
Paragraph 14.02.B in ARTICLE 14, Paragraph 14.02, OWNER May Terminate, of the
General Conditions:
14.02.B. ....claims, costs, losses and damages
SC-16 MISCELLANEOUS
ADD the following paragraphs in ARTICLE 16 of the General Conditions:
16.06. Applicable Law. ,.
The laws of the State of Colorado apply to this Agreement, including but
not limited to the following pertinent Colorado statutes: t
16.06.A. Colorado Revised Statutes (CRS 8-17-101) requires that Colorado _
labor be employed to perform the work to the extent of not less than 80 percent
(80%) of each type or class of labor in the several classifications of skilled l�
and common labor employed on the project. Colorado labor means any person who
is a bona fide resident of the State of Colorado at the time of employment,
without discrimination as to race, color, creed, age, religion or sex.
16.06.B. If a claim is filed, OWNER is required by law (CRS 38-26-107) to
withhold from all payments to DESIGN/BUILDER sufficient funds to insure the
payment of all claims for labor, materials, team hire, sustenance, provisions,
provender, or other supplies used or consumed by DESIGN/BUILDER or his
Subcontractors in or about the performance of the work. Such funds must be
withheld until said claims have been paid or such claims as filed have been
withdrawn, such payment or withdrawn to be evidenced by filing with OWNER a
receipt in full or an order for withdrawal in writing and signed by the person
filing such a claim or his duly authorized agents or assigns. Such funds shall
00800-24
,
not be withheld longer than ninety (90) days following the date fixed for final
settlement, as published in a public newspaper in accordance with the law, unless
an action is commenced within that time to enforce such unpaid claim and a notice
of lis pendens is filled with the OWNER. At the expiration of such ninety (90)
day period, OWNER shall pay to DESIGN/BUILDER such moneys and funds as are not
the subject of suit and lis pendens notices, and shall retain only sufficient
funds to insure the payment of judgments which may result from the suit.
SC -GC -A Exhibit GC -A to GENERAL CONDITIONS: Dispute Resolution Agreement
REVISE the first sentence in Paragraph 15.01.B in Exhibit GC -A to GENERAL
CONDITIONS, Paragraph 15.01, Dispute Resolution Agreement, of the General
Conditions:
15.0l.B. OWNER and DESIGN/BUILDER agree that they will first submit any
and all unsettled claims, counterclaims, disputes and other matters in question
between them arising out of or relating to the Contract Documents or the breach
thereof ("disputes") to mediation by the American Arbitration Association under
the Construction Industry mediation Roles of the American Arbitration Association
then obtaining, prior to either of them initiating against the other a demand for
arbitration pursuant to paragraphs 15.01.0 through 15.0l.F, unless delay in
initiating arbitration would irrevocably prejudice one of the parties. ....
REVISE the first sentence in Paragraph 15.0l.0 in Exhibit GC -A to GENERAL
( CONDITIONS, Paragraph 15.01, Dispute Resolution Agreement, of the General
Conditions:
15.01.C. All claims, disputes and other matters in question between OWNER
V and DESIGN/BUILDER arising out of or relating to the Contract Documents or the
breach thereof (except for claims which have been waived by the making or
acceptance of final payment as provided by paragraph 13.10 will be decided by
'i binding arbitration in accordance with the Construction Industry Arbitration
Roles of the American Arbitration Association then obtaining, subject to the
r limitations of this paragraph 15.01. ....
ADD the follow Paragraph 15.0l.G in Exhibit GC -A to GENERAL CONDITIONS, Paragraph
15.01, Dispute Resolution Agreement, of the General Conditions:
r 15.01.G. The award rendered by the arbitrators will be final; judgment may
j be entered upon it in any court having jurisdiction thereof, and it will not be
subject to modification or appeal.
00800-25
APPLICATION FOR PAYMENT
AND
CHANGE ORDER FORM
APPLICATION FOR PAYMENT
PROJECT: Second Sheet of Ice at EPIC
PAY ESTIMATE NO:
DATE:
CONTRACTOR: The Neenan Company
ADDRESS: 2620 East Prospect Road, Suite 100
Fort Collins, CO 80525
PARTIAL TO
The undersigned Contractor certifies that to
the best of his knowledge, information and
belief the work covered by this application
for Payment has been completed in
accordance with the Contract Documents,
that all accounts have been paid by him for
Work for which previous Certificates for
Payment were issued and payments
received in this current payment shown
herein is now due.
CONTRACTOR: The Neenan Company
FINAL TO
In accordance with the Contract Documents,
based on site observations and the data
comprising the above application, the
Architects Certifies to the Owner that the
Work has progressed to the point indicated;
that to the best of his knowledge, information
and belief, the quality of the Work is in
accordance with the Contract Documents,
and that the Contractor is entitled to payment
of the AMOUNT CERTIFIED.
ENGINEER: The Neenan Company
By:,
Application is made for Payment, as shown below, in connection with the Contract. Schedule of Values is
attached.
The present status of the account for this Contract is as follows:
ORIGINAL CONTRACT AMOUNT
APPROVED CHANGE ORDERS TO DATE
ADJUSTED CONTRACT AMOUNT
TOTAL WORK COMPLETED AND MATERIALS USED
RETAINAGE (10% OF TOTAL)
TOTAL EARNED LESS RETAINAGE
LIQUIDATED DAMAGES WITHHELD
TOTAL EARNED LESS LIQUIDATED DAMAGES
LESS PREVIOUS PAYMENTS
CURRENT PAYMENT DUE
APPROVED BY:
Facilities Project Manager
cc: Accounting City Clerk
Contractor Engineer
Project File
DATE:
CONTINUATION SHEET AIA DOCUMENT G703
Pepe 2
CNy of Fort CoNlns Progress PaMOnt Form for Second Sheol of Ice at EPIC APPLICATION 0:
APPLICATION DATE:
PERIOD FROM:
PERIOD TO:
ARCHITFCTC PRfIIPr T Kln
�
��■ems
>, .,
o��
,...
��
o
„r
SECTION 00950
CHANGE ORDER NO.
PROJECT TITLE: Second Sheet of Ice at EPIC
CONTRACTOR: The Neenan Company
BID NUMBER:
DESCRIPTION
In preparing change orders show in order as separate numbered paragraphs the following:
Reason for change:
2. Description of change:
3. Change in Contract Cost:
4. Change in Contract Time:
(Attach additional sheets as reauired)
ORIGINAL CONTRACT COST $0
TOTAL APPROVED CHANGE ORDERS 0
TOTAL PENDING CHANGE ORDERS 0
TOTAL THIS CHANGE ORDER 0
ADJUSTED CONTRACT COST $0
(Assuming all chanae orders approved)
ACCEPTED BY:
Contractor's Representative
APPROVED BY:
Facilities Project Manager
cc: City Clerk Project File
Contractor Purchasing
Engineer
Date
Date
GMP PROPOSAL DATED 11/29/2001
AND
OTHER DOCUMENTATION
The Neenan Company Second Sheet of Ice at EPIC
11/29/2001
ision Description
Takeoff Quantity
Total Cost/Unit
i Total Amount
010,General Conditions
Project Manager.. . . .....
Salaried - PM
--- - -------- ......
19.50 wk
3 140.00 /wk
61,230.
Superintendent
Salaried - Super
26.00 wk
3,540.00 /wk
92,040
Copier
Off Supply_- Copier
5.50 mnth
100.00 /mnth
550
Water Cooler
.Off Supply .,_Water ,Cooler
5.50 mnth 1-
50.00 /mnth
275
Jobsite Trailer
-------- ---- -
Office - Jobsite Trailer ..... .....
6.00 ninth
. .. . .. . ........ .....
500.00 /mnth
. .. ..... . . .. ....
.........
3000
Toilet
. ...... ... Office .- Temp Net ..........
5.50 mnth
...... ..
120.00 /mnth
Storage, Trailer-,
Stor - Tamp_Stor�lc a Trailer
5.50 mnth
300.00 /mnth
1,650
Trailer Set-Up/Tear.Down
CM ice - Trl.r.Set-upjear Down
1.00 Is
500.00 /is
Boo
Job Site ID Sign
------ ---- -------
- - --- - -------- ---------
Sign Job ID Sign .. . ... .... .
694.00opq
694
'Eiectric Bill
.Temp Elec - Monthly Charge
5.50 mnth
500.00 /mnth
2.750
Water Bill
Temp Water - Monthly Charge
Storm Drainage Bill
Temp Storm, - Monthly Charge--..
Temp Water Service Install
iRsTa"
-.1.00 hr 75.00 /hr
020 Sitework
- Temporary Protection 32,302.00 sqft 0.02 Iscift 484
- -- --- ----- -
'Temporary Fence 32,302.00 soft OAS /soft 4906
!Selective Structural Demo
---,Site-Demo----
32,302.00spift
--32.302.0-0-
0.16 /sqft
---- - 5,0100
sqft-
0.62 /sqft
19 ,961'
-
:Site Demo Sawcut Cone
32.302.00
0.01 Isqft
�0 0
1
Site Demo - Sawcut Asphalt
32,302.00 sqft
0.01 lss�
400
io
'Clear/Grub - Site
32.302.00 sqft
0.06 /sqft T
1.826�
-.-StrJpPStock -Topsoil
32.302.00 soft
-- -
O.Oo -Lsgft-
941
Site Cut/Fill
32,302.00 sqft
0-95'/sqft
30,606
Site Overexcavation
- --------
32,30200 sqft
----
0.40 /sqft
12=906
Recom ct . rig
-
-Replace
32302.00 scift
003 iscift
8891
I Topsoi 1Pv
32.302.00 soft
0.03 Iscift
896
r--
il - din - g Grading
32,3021DO soft
-0.07-iscift-
2 393'
_______Curb/Gutter/Pavement Grading
32,302.00 sqft
0.03 /sqft
-----------
1,051
I
Earthwork Mobilization
32,302.00 sqft
0.03 /sqft
1,0001
Excav/Trenching - Structural
32,302.00 sqft
0.02 /sqft
730j
Haul -off Caisson Spoils
I I - . - - ,
32,302.00 scift
11 - - ,
0.04 /sqft
1,116
". 1 -
Machine Backfill
/C omp a ction
32 ,302. 0 0 sqft
0.25 /sqft
8 2 0 21
Import Fill and Compact
32 302.00scift
0.72 /sqft
23.149
Subbase Material
32.302.00 soft
0.09 Iscift
2.907
Section 5.2.9.1 -Page 1
The Neenan Companv Second Sheet of Ice at EPIC 11/29/2001
,ision
Description
1 Takeoff Quantity
Total Cost/Unit
Total Amount
Erosion Control
32,302.00, sqft ---
0.91 /Sqft_
29,300
?Caisson Drilling/Casing L
32,302.00 sqft
0.54 /sqft
17,354
'Place Caisson Concrete
32.302.00 sqft
0.16 /sqft
5.032
Site Storm Drainage
321302.00 sqft
0.19 /sqft
6,200
- ---------- - - - Asphalt Pvmnt Patch
32,302.00 sqft
0.22 /sqft
7,000
Asphalt Pvmnt Place
�2,302.00 sqft
0.18 /sqft
5.833
C&G Form/Place
.. ........ 32.302,00 sqft
0.02 /sqft
469
C&G Cone Matl
32302.00 sqft
0.01 /sqft
255
Cone Sidewalk - Form/Place
32,302.00 sqft
0.07 s ft
q
2.162
-- ---- -- - -----
:Cone Sidewalk - Cone Matt
32,302.00 sqft
0.02 /sqft
733
-.Allowance - Landscaping_
32,302.00 sqft
1.36 /sqft
44.000
030iConcrete
Form/Place - Trench
32,302.00 sqft
0.11 /sqft
3.568
;Form/Place - Int Curb/Pad/Pit
32.302.00 scift
0.05 /sqft
Form/Place - Ice Pit
... .... ....
32,302.00 sqft
. .... ......... ... .. - -----
0.16 /sqft i
"" L ....... ... .. 1. 1. -1. - I---,.,-,-,-
5,244
''.. . --I
.Concrete Accessories
32,302.00 sqft
0.01 /sqft
160
.Cone Access. - SOG ExD Joint
32.302.00 saft
0.04 /saft
1.250
L41L
Rebar - Caisson
--------- - - ------
32.302.00 sqft --- ---
0.27 /sqft
8,604
Rebar - Trench
32,302.00 sqft
0.02 /sqft
Rebar - Site Cast Panel
..... ... - ----- - .... ..... 11 - ---------
32.302.00 sqft
0.22 /sqft
6,956
Wire Mesh
32,302.00 sqft
2.668
Cone Marti - Wall Footing
32,302.00 sqft
0.02 /sqft ..
. ..... .. 475
Matl - Caisson
32,302.00 sqft
0.40 /sqft 1
13,020
------lConc
Cone Matl - Decki!
---- - ----- -
0.04 /sqft -
1.200
!Cone Matt - SOG
32,302.00 sqft
0.75 /sqft
24,085
Cone Matl - Trench . .....
32,302.DO scift
....... . L ... ....
0.04 Iscift
1,200
!Cone Matl - Int Curb/Pad/Pit
32,302.00 sqft
0.02 ASO
639
Matl - Ice Pit
- - -- ------------------ -- - --
y
32,302.00 sqft
0.04 is
--- qft
(Finish - Misc. - ---------32,302.00
scAL_
0.03 /sqft
828
--Place/Ti-ni'sh Deck- - - - --- ---- -
0:17 /sqft
5,609
Place/Finish - SOG
32,302,00 sqft
0.25 /sgft
8,189
'Concrete Sawcutting
32,302.00 scift
0.05 Iscift
1.592
Cone Pump - Deck/Topp�ng
32.302.00 soft
0.01 /sqft
318
Cone Pump - SOG
32,302.00 sqft . . .....
... 0.05 /sqft
1,592
Cone Pump - Trench
32,302.00 s9ft
0.01 /sqft
272
Pump - Ice Pit
32302.00 sqft
0.02 /sqft
531L
Cone Cure
32.302.00 Sqft
0.03 /sqft
8191,
Precast -,Dy,na,,s pan.
32,302.00 sqft
.............
0.76 /sqft
24,624
Precast PnI - Insulated
32,302.00 sqft
9.13 /sqft
294,816,
(Precast- - Bracing
32.302.00 sqft
0.25 /sqft
8,000
040 Masonry
E xt CM U- E x t Wall
32,302.00 sqft
0.51 /sqft
16.558
Int CMU Partition
32.302.00 sqft
2.40 /sqft
77.520
Brick Veneer - Exterior
32.302.00 sqft
3.86 /sqft
124.7821
050 Steel
- -
Steel Bar Joists
32.302.00 sqft
6.30 /sqft
Z63.4231
Section 5.2.9.1 -Page 2
The Neenan Comoanv Second Sheet of Ice at EPIC 11/29/2001
ision Description Takeoff Quantity Total Cost/Unit Total Amount
Int Stair - Steel
32.302.00 sgft
0.23 /sqft
7,500
Int Handrail - Steel Tubular_. _
32 302.00 sqft _.
1.57 /sqft -.
50,600
Header Trench Cover
32 302.00 sqft
0.21 /sqft
6.720
0601Wood Carpentry
'.Ext Door Frame Install
32,302,00 sqft_
0.04 /sgft_-_
1,180
Ext Door Install
32.302.00 sqft
0.06 /sqft
:Int Door Door Frame Install
32.302.00 sqft
0.04 /sqft
1,116
int Door Install
- - __.-. - _..._
32 302.D0 sgft
.._. __._.
,1..11 /sgft-. _
..
35,949
_._....
__Carp Labor _Wd Sheathing
_.__ 32,302.00 sqft
0.06 /sqft
2,058
Wd Framing Roof
32 302.00 sgft
0.12 /sqft
4,000
070,Thermal & Moisture
iDampproof Foundation _ -
-_, 32302.00 sqft
0.03 /sqft -
1,095
Waterproof -Trench
32.302.00 soft
0.04 /soft ':.
1.174
(Insulation Foundation
,! 32,302.D0 sqft _
.0.05 /sgft___
1
_Insulation _ Under Ice
32 302.00 sgft
0.56 /sqft
_18
EDPM Roof Ballasted
32 302.00 _sqft___
2.11 /sgft
67
.Sheet Metal Roofing_
32,302.00 sqft
0.28 !sgft _
9
-,.Flashings_ Sheet Metal _
32302.D0 sqft
_
,0.26 /sqft __
8
Rf Accessory -. Roof Hatch
32,302.00 sqft
0.04 /sqft
1
. _-
'.Fireproof-BarJoist/Deck
32302.OD sqft
_ 0.03 /sgft
1
'.Firesafe - Ext Fire Wall
32.302.00 sail __
-.0.03 /sqft
Caulking - Exterior
32,302.00 sgft
0.46 /sqft__
14
Doors & Windows
Ext Door Frame - Hollow Mtl
32 302.00 sqft
0.03 /sqft-
1
Ext Door -Hollow Mtl
32 302.00 sgft _
0.08 /sqft
2
!Int Door Frame Hollow Mtl
32 302,00 sqft -
0.13 /sqft !
4
!, Int Door - Hollow Mtl
32.302.00 sqft
0.13 /sgft -.
4
,Coiling Doors/Grilles
, 32.302.00
0.40 /sqft '�,
13_sgft
'.Storefront -Ext Wndw
.------.......-..._. .-----_- -------.._.
-------------
32,302.00 sqft
._-- ..__... .---_.__..
_
0.10 /sgft
_..._........ .._.......-----
-
3
........_.---_.
'..Hollow Mtl Wndw Frame_ Int
32,302.00 sqft
/sgft
1
_
Door Hardware - Ext
_
'.. 32.302.00 soft
-__0.03 _
0.18 /soft
. _ -
5
-
Door Weatherstrip/Seals- Ext
32.302.00 soft
Weatherstrip/Seals-_Int
32,302.00 sgft_
',,..Glazing - Interior,
32 302.00 sqft _
091 Framing & Drywall
Gyp _Board Ceiling
__, 32.302.00_sgft_-_
Gyp Board - Soffit
32.302.00 sqft _
095'Ceiling Finishes
- ------
________Acoustical Cig_ 2x4 - _. _ _-
_. 32.302.00-sgft_
,Paint - Interior
_ 32,302.00 sqft
096iFloor Finishes
'.Flooring - Rubber
- 32,302.00 soft_
'..Base - Rubber
32.302.00 sqft
__.. Epoxy Flooring _..._
__..,,. 32,302,00sqft
--
097 Wall Finishes
0.03 /sqft 945
0.01 /sgft_ 308
0.09 /sqft ., 2.800
__. 0.56 /sqft 18.000
0.67 /sqft 21,545
0.05 /sqft
0_.87 /sgtt_
1_59 /sgft..
0.05 /sgtt
0.10 /sqft
-..-. _--1.680
28.200
51.300
-....... 1,750
3.100
Section 5.2.9.1-Page 3