HomeMy WebLinkAbout429212 GLH CONSTRUCTION - CONTRACT - BID - 6075 TROLLEY BRICK RESTORATIONSPECIFICATIONS
.m
CONTRACT DOCUMENTS
FOR
Trolley Brick Restoration Project
BID NO 6075
PURCHASING DIVISION
215 NORTH MASON STREET, 2ND FLOOR, FORT COLLINS
December 6, 2007 — 3 00 P M (OUR CLOCK)
where renewal i5 a way of life
CONTRACT DOCUMENTS TABLE OF CONTENTS
Section Pages
BID INFORMATION
00020 Notice Inviting Bids 00020-1 - 00020-2
00100 Instruction to Bidders 00100-1 - 00100-9
00300 Bid Form 00300-1 - 00300-3
00400 Supplements to Bid Forms 00400-1
00410 Bid Bond 00410-1 - 00410-2
00420 Statements of Bidders Qualifications 00420-1 - 00420-3
00430 Schedule of Major Subcontractors 00430-1
CONTRACT DOCUMENTS
00500
Agreement Forms
00500-1
00510
Notice of Award
00510-0
00520
Agreement
00520-1 00520-6
00530
Notice to Proceed
00530-1
00600
Bonds and Certificates
00600-1
00610
Performance Bond
00610-1 - 00610-2
00615
Payment Bond
00615-1 - 00615-2
00630
Certificate of Insurance
00630-1
00635
Certificate of Substantial Completion
00635-1
00640
Certificate of Final Acceptance
00640-1
00650
Lien Waiver Release(Contractor)
00650-1 - 00650-2
00660
Consent of Surety
00660-1
00670
Application for Exemption Certificate
00670-1 - 00670-2
CONDITIONS OF THE CONTRACT
00700 General Conditions 00700-1 - 00700-34
Exhibit GC -A GC -Al - GC-A2
00800 Supplementary Conditions
00800 1 - 00800-2
FEDERAL FORMS
Work Change Directive
Request for Interpretation
Clarification Notice
Field Order
David Bacon Wages
00900 Addenda Modifications and Payment
00900-1
00950 Contract Change Order
00950-1 - 00950-2
00960 Application for Payment
00960-1 - 00960-4
SPECIFICATIONS
Labor Materials and Equipment 6 3-6 5 CONTRACTORS other 7
Laws and Regulations 614 Contractual Liability Insurance 54 10
Liability Insurance 54 Contractual Time Limits 122
Article or Paragraph
Number
Notice of variation from Contract
Documents
627
Patent Fees and Royalties
612
Permits
013
Progress Schedule
66
Record Documents
619
related Work performed prior to
ENGINEER s approval of required
submittals
628
safe structural loading
618
Safety and Protection 620 72, 132
Safety Representative
621
Scheduling the Wok
692
Shop Drawings and Samples
624
Shop Drawings and Samples Review
by ENGINEER
626
Site Cleanliness
617
Submittal Procedures
625
Substitute Construction Methods
and Procedures
672
Substitutes and Or Equal Items
67 1
Superintendence
62
Supervision
01
Survival of Obligations
634
Taxes
6 15
Tests and Inspections
135
To Report
25
Use of Premises 6 16-6 18 6 30 2 4
Review Prior to Shop Drawing m
Sample Submittal
625
Right to adjustment for changes in the Work 102
right to claim 4 71 94 95 911
102112
119 121 139 148 151
155 173
Safety and Protection 6 20 6 22
7 2 13 2
Safety Representative
621
Shop Drawings and Samples Submittals
624628
Special Consultants
1144
Substitute Construction Methods and Procedures 6 7
Substitutes and Or Equal Items
Expense 67
1 672
Subcontractors Suppliers and Others
68 611
Supervision and Superintendence 61
62 621
Taxes, Payment by
6 15
Use of Premises
6 16 6 18
Warranties and guarantees
65 630
Warranty of Title
143
Written Notice Required
CONTRACTOR stop Work or terminate
15 5
Reports of Differing Subsurface
and Physical Conditions
4 23
Substantial Completion
148
na
Article or Paragraph
Number
Coordination
CONTRACTOR s responsibility
692
Copies of Documents
22
Correction Period
1312
Correction Removal or Acceptance
of Defective Work
in general
1041 1310 1314
Acceptance of Defective Work
1313
Correction or Removal of
Defective Work
630 1311
Correction Period
13 12
OWNER May Correct Defective Wok
1314
OWNER May Stop Work
1310
Cost
of Tests and Inspections
134
Recordsl1 7
Cost of the Wok
Bonds and insurance additional
11459
Cash Discounts
1142
CONTRACTORsFee
116
Employee Expenses
11 4 5 1
Exclusions to
115
General11 4-11 5
Hone office and overhead expenses
115
Losses and damages
11456
Materials and equipment
1142
Minor expenses
11458
Payroll costs on changes
11 4 1
performed by Subcontractors
11 43
Recordsl1 7
Rentals of construction equipment
and in achmery
11453
Royalty payments permits and
license fees
11455
Site office and temporary facilities
11452
Special Consultants CONTRACTOR,
1144
Supplemental
1145
Taxes related to the Work
11454
Tests and Inspection
134
Trade Discounts
1142
Utilities fuel and sanitary facilities
11457
Wok after regular hours
11 4 1
Covering Wok
136 137
Cumulative Remedies
174 175
Cutting fitting and patching
72
Data to be furnished by OWNER
83
Day definition of
1722
Decisions on Disputes
911 912
defective definition of
114
defective Work
Acceptance of
1041 1313
ETCDC GENERAL CONDITIONS 1910 a (1990 EDITION)
W CITY OF FORT COLLINS MODIFICATIONS (REv 9/99)
Correction or Removal of
1041 1311
Correction Period
1312
in general 13 147 1411
Article or Paragraph
Number
Observation by ENGINEER
92
OWNER May Stop Work
1310
Prompt Notice of Defects
131
Rejecting
96
Uncovering the Work
138
Definitions
1
Delays 41 629
123 124
Delivery of Bonds
21
Delivery of certificates of insurance
2 7
Determ mations for Unit Prices
910
Differing Subsurface or Physical Conditions
Notice of
423
ENGINEER s Review
424
Possible Contract Documents Change
4 2 5
Possible Price and Times Adjustments
4 2 6
Discrepancies -Reporting
and Resolving 25
332 6 142
Dispute Resolution
Agreement
161 166
Arbitration
161 165
gmera116
Mediation
166
Dispute Resolution Agreement
161 166
Disputes, Decisions by ENGINEER
931 912
Documents
Copies of
22
Record 6 19
Reuse of
37
Drawings definition of
1 15
Easements
41
Effective date of Agreement definition of
1 16
Emergencies
623
ENGINEER
as initial interpreter on disputes
911 912
definition of
1 17
Limitations on authority and responsibilities
913
Replacement of
82
Resident Project Representative
93
ENGINEER s Consultant definition of
1 18
ENGINEERS
authority and responsibility hm itations on 913
Authorized Variations in the Weak
95
Change Orders responsibility for
97 10 11 12
Clarifications and Interpretations
363 94
Decisions on Disputes
911 912
defective Work notice of
131
Evaluation of Substitute Items
673
Liability
632 912
Notice Work is Acceptable
1413
Observations
6102 92
OWNER s Representative
91
Payments to the CONTRACTOR,
Responsibility for
99 14
Recommendation of Payment 144
1413
Article or Paragraph
Number
Responsibilities Limitations op
9 11 913
Review of Reports on Differing Subsurface
and Physical Conditions
424
Shop Drawings and Samples, review
responsibility
626
Status During Construction
authorized variations in the Work
95
Clarifications and Interpretations
9 4
Decisions on Disputes
911 912
Determinations on Unit Price
910
ENGINEER as Initial Interpreter
911 912
ENGINEER s Responsibilities
91 912
Limitations on ENGINEER s Authority
and Responsibilities
913
OWNERS Representative
91
Project Representative
93
Rejecting Defective Work
96
Shop Drawings Change Orders
and Payments
9799
Visits to Site
92
Una Price determinations
910
Visits to Site
92
Written consent required
72 91
Equipment, Labor Materials and
6 3 6 5
Equipment rental Cost of the Work
11453
Equivalent Materials and Equipment
07
error or omissions
633
Evidence of Financial Arrangements
8 11
Explorations of physical conditions
4 2 1
Fee CONTRACTORS Costs Plus
116
Field Order —
definition of
1 19
issued by ENGINEER
36 1 95
Final Application for Payment
14 12
Final Inspection
1411
Final Payment
and Acceptance
1413 1414
Prior to for cash allovances
11 8
General Provisions
173 174
General Requirements
definition of
1 20
principal references to 26 64 6 6 6 7 624
Giving Notice
171
Guarantee of Work by CONTRACTOR
630 1412
Hazard Communication Programs
622
Hazardous Waste
definition of
1 21
general
4 5
OWNER s responsibility for
8 10
EICDC (ZNERAL CONDITIONS 1910 8 (1990 EDITION)
w/ CITY OF FORT COLLINS MODIFICATIONS (REV 9/99)
Indemnification 612, 616 631 633
Insurance
53
Initially Acceptable Schedules
29
Precedence
3 1 333
Inspection
Reference to
3 3 1
Certificates of 9 13
4 13 5 14 12
Safety and Protection
620 132
Final
1411
Subcontractors Suppliers and Other*
6 8 6 11
Article
or Paragraph
Article or Paragraph
Number
Number
Special required byENGINEER
96
Tests and Inspections
135
Tests and Approval
87 133 134
Use of Premises
616
Insurance
Visits to Site
9 2
Acceptance of by OWNER
5 14
Liability Insurance
Additional required by changes
CONTRACTORS
54
in the Work
11459
OWNERS
55
Before starting the Work
27
Licensed Sureties and Insurer*
53
Bonds and in general
5
Liens
Cancellation Provisions
5 8
Application for Progress Payment
142
Certificates of 2 7 5 5 3 5 4 11 5 4 13
CONTRACTORS Warranty of Title
143
5 6 5 5 8 5 14
9 13 4 14 12
Final Application for Payment
1412
completed operations
5413
definition of
123
CONTRACTORS Liability
54
Waiver of Clams
1415
CONTRACTORS objection to coverage
514
Limitations on ENGINEER s authority and
Contractual Liability
5410
responsibilities
913
deductible amounts CONTRACTORs
Limited Reliance by CONTRACTOR
responsibility
59
Authorized
422
Final Applicaton for Payment
1412
Mamtenance and Operating Manuals
Licensed Insurers
53
Final Application for Payment
1412
Notice requirements material change*
58 105
Manuals (of others)
Option to Replace
514
Precedence
$3 3 1
other special insurances
510
Reference to in Contract Documents
3 3 1
OWNER as fiduciary for msureds
5 12 5 13
Materials and equipment
OWNERs Liability
55
furnished by CONTRACTOR
63
OWNERS Responsibility
85
not Incorporated in Work
14 2
Partial Utilization Property Insurance
5 15
Materials or equipment equivalent
6 7
property
56510
Mediation (Optional)
167
Receipt and Application of Insurance
Milestones definition of
1 24
Proceeds
5 12 5 13
Miscellaneous
Special Insurance
5 10
Computation of Tunes
172
Waiver of Rights
5 11
Cumulative Remedies
174
Intent of Contract Docum ents
31 34
Giving Notice
171
Interpretations and Clarifications
3 6 3 9 4
Notice of Clain
173
Investigations of physical conditions
4 2
Professional Fees and Court Costs Included
175
Labor Materials and Equipment
6 3 6 5
Multi prime contracts
7
Lands
Not Shown or Indicated
4 3 2
and Easements
8 4
Notice of
Availability of
4 1 84
Acceptability of Project
14 13
Reports and Tests
8 4
Award definition of
125
Laws and Regulations Law s or Regulations
Claim
173
Bonds
5 1 S 2
Defects 13 1
Changes in the Work
10 4
Differing Subsurface or Physical Conditions
4 2 3
Contract Documents
3 1
Giving
171
CONTRACTOR s Responsibilities
614
Correction Period defective Wok
J3 12
Tests and Inspection*
133
Cost of the Work, taxes
11 4 5 4
Variation, Shop Drawing and Sample
627
definition of
1 22
Notice to Proceed
general6 14
definition of
126
Indemnification
6 31 6 33
giving of
23
x
E1CDC GENERAL. CONDITIONS 1910 8
(1990 EDITION)
w/ CITY OF FORT COLLINS MODIFICATIONS (REV 9199)
Notification to Surety
Jos
Observations, by ENGINEER
630 92
Occupancy of the Work
5 15 6 30 2 4 14 10
Omissions or acts by CONTRACTOR 69 913
Open Peril policy form Insurance
562
Option to Replace
514
Article or Paragraph
Number
Or Equal Items
67
Other work 7
Overtime Work prohibition of
63
OWNER
Acceptance of defective Work
1313
appoint an ENGINEER
82
as fiduciary
5 125 13
Availability of Lands responsibility
41
definition of
127
data furnish
83
May Correct Defective Work
1314
May refuse to make payment
147
May Stop the Work
1310
May Suspend Work
Terminate 8 8
13 10 15 1 15 4
Payment make prompt
83 144 14 13
performance of other work
71
permits and licenses, requirements
613
purchased insurance requirements
56 510
OWNER s-
Acceptance of the Work
Change Orders obligation to execute
Communications
Coordination of the Work
Disputes, request for deusron
Inspections tests and approvals
Liability Insurance
Notice of Defects
Representative During Construction
ENGINEERS Status
Responsibilities
Asbestos PCBs, Petroleum Hazardous
Waste or Radioactive Material
Change Orders
Changes in the Work
communications
CONTRACTOR s responsibilities
evidence of financial arrangements
inspections tests and approvals
insurance
lands and easements
prompt payment by
replacement of ENGINEER
reports and tests
63025
86 104
81
74
911
87 134
55
131
stop or suspend Work 88 13 10
terminate CONTRACTOR s
91
$ 10
86
101
81
89
8 11
87
85
84
83
82
84
151
services 88 152
separate representative at site 93
testing independent
use or occupancy
of the Work
wntten consent or approval
required
134
515 63024 1410
91 63 114
EJCDC GENERAL CONDITIONS 1910 8 (1990 EDITION)
w/ CITY OF FORT COLLINS MODIFICATIONS (REv 9/99)
Article or Paragraph
Number
written notice required
71 94 911
112 119 14 7 15 4
PCBs
definition of
1 29
general
45
OWNERS responsibility for
810
Partial Utilization
definition of
128
general 6 30 2 4 14 10
Property Insurance
5 15
Patent Fees and Royalties
612
Payment Bonds
5 1 5 2
Payments Recommendation of
144147 1413
Payments to CONTRACTOR and Completion
Application for ProgressPayments
142
CONTRACTORS Warranty of Title
143
Final Application for Payment
1412
Final Inspection
1411
Final Payment and Acceptance
1413 1414
general
$ 3 14
Partial Utilization
1410
Retamage
142
Review of Applications for
Progress Payments
prompt payment
Schedule of Values
Substantial Completion
Waiver of Claims
when paym ents due
withholding payment
Performance Bonds
Permits
Petroleum
definition of
general
OWNER s responsibility for
Physical Conditions
Drawings of in or relating to
ENGINEER s review
emsting structures
general 2 1 2
Notice of Differing Subsurface or
Possible Contract Documents Change
Possible Price and Times Adjustments
Reports and Drawings
Subsurface and
Subsurface Conditions
Technical Data Limited Reliance by
CONTRACTOR Authorized
Underground Facilities
general
Not Shown or Indicaed
Protection of
144147
83
141
148 149
1415
44 1413
147
5152
613
1 30
45
8 10
4212
424
422
423
425
426
421
42
4211
422
43
432
43 620
Article or Paragraph
Number
Shown or Indicated 4 3 1
Technical Data 422
Preconstruction Conference 28
Preliminary Matters 2
Prelnnmary Schedules 26
Premises Use of 616618
Price Change of Contract 11
Price Contract definition of 1 11
Progress Payment, Applications for{ 142
Progress Payment retamage 142
Progress schedule CONTRACTOR s 26 28 29
66 629 104 1521
Project definition of 131
Project Representative
ENGINEER s Status During Construction
Project Representative Resident definition of
prompt payment by OWNER
Property Insurance
Additional
general5 6 5 10
93
133
83
57
Partial Utilization 5 15 14 10 2
receipt and application of proceeds 5 12 5 13
Protection Safety and 6 20-6 21 132
Punch list 1411
Radioactive Material
defrition of
genera14 5
OWNER s responsibility for
Recommendation of Payment 144 145
Record Documents 619
Records procedures for maintaining
Reference Points
Reference to Standards and Specifications
of Technical Societies
Regulations Laws and (or)
Rejecting Defective Work
Related Work
at Site
Perfumed prior to Shop Drawings
and Samples submittals review
Remedies cumulative
Removal Or Correction ofDefecnve Work
rental agreements OWNER approval required
replacement of ENGINEER by OWNER
Reporting and Resolving
132
810
1413
1412
28
44
33
614
96
7173
628
174 175
13 11
11453
82
Discrepancies
25 3 3 2 6 142
Reports
and Drawings
4 2 1
and Tests OWNER s responsibility
84
Resident and Project Representative
definition of
133
provision for 93
xu E1CDC GENERAL CONDITIONS 1910 8 (1990 EDITION)
w/ CITY OF FORT COLLINS MODIFICATIONS (REV 9199)
Article or Paragraph
Number
Resident Superintendent CONTRACTOR s 62
Responsibilities
CONTRACTOR s-in general 6
ENGINEER s in general
9
Limitations on
913
OWNERS in general
8
Retamage
142
Reuse of Docum ents
37
Review by CONTRACTOR Shop Drawings
and Samples Prior to Submittal
625
Review of Applications for
Progress Payments
144 147
Right to an adjustment
102
Rights of Way
41
Royalties, Patent Fees and
612
Safe Structural Loading
618
Safety
and Protection
432 616 618
620-621
72 132
general
620623
Representative CONTRACTOR s
¢ 21
Samples
definition of
134
general
¢ 24 6 28
Review by CONTRACTOR
625
Review by ENGINEER
626 627
related Work
¢ 28
submittal of
0242
submittal procedures
625
Schedule of progress
26 28 29 66
629 104 1521
Schedule of Shop Drawing and Sample
Submittals 2 6 2 8 2 9 6 24-6 28
Schedule of Values
26 29 29 141
Schedules
Adherence to
152 1
Adjusting
66
Change of Contract Times
104
Imhally Acceptable
28 29
Preluninary,
26
Scope of Changes
103 104
Subsurface Conditions
4 2 1 1
Shop Drawings
and Samples general
624628
Change Orders & Applications for
Payments and
9 7 9 9
definition of
1 35
ENGINEERS approval of
3 6 2
ENGINEER s responsibility
for review
97 6 24-6 28
related Work
¢ 28
review procedures
28 624628
ani
Article or Paragraph
Number
submittal required
Submittal Procedures
use to approve substitutions
Shown or Indicated
Site Access
Site Cleanliness
Site Visits to —
by ENGINEER
by others
special causes of loss policy form
insurance
definition of
Specifications
defination of
of Technical Societies reference t9
precedence
Standards and Specifications
of Technical Societies
Starting Construction Before
Starting the Work
Stop or Suspend Work
by CONTRACTOR
by OWNER 88
Storage of materials and equipment
Structural Loading Safety
Subcontractor
6 24 1
625
673
431
72 132
617
92 132
132
562
136
136
331
333
33
2528
24
155
13 10 151
41 72
618
Concerning
68 611
definition of
1 37
delays
123
waiver of rights
611
Subcontractors in general
68 611
Subcontracts required provisions 5 11 611
1143
Subm ittals
Applications for Payment
142
Maintenance and Operation Manuals
1412
Procedures
625
Progress Schedules
26 29
Samples
624628
Schedule of Values
26 141
Schedule of Shop Drawings and Samples
Subm issions 26
28 29
Shop Drawings
624 628
Substantial Completion
certification of 6 30 2 3
14 8 14 9
definition of
138
Substitute Construction Methods or Procedures
672
Substitutes and Or Equal Items
6 7
CONTRACTORS Expense
07 13
ENGINEERS Evaluation
6 73
Or Equal
6 7 1 1
Substitute Construction Methods
EJCDC GENERAL CONDITIONS I910 8 (1990 EDITION
w/ CITY OF FORT COLLINS MODIFICATIONS (REV 9/99)
Article or Paragraph
Number
or Procedures
6 7 2
Substitute Items
67 12
Subsurface and Physical Conditions
Drawings of in or relatng to
42 12
ENGNEERs Review
4 2 4
general
4 2
Limited Reliance by CONTRACTOR
Authorized
422
Notice of Differing Subsurface or
Physical Conditions
423
Physical Conditions
4 2 1 2
Possible Contract Documents Change
4 2 5
Possible Price andTmies Adjustments
426
Reports and Drawings
4 2 1
Subsurface and
4 2
Subsurface Conditions at the Site
4 2 1 1
Technical Data
422
Supervision
CONTRACTOR s responsibility
41
OWNER shall not supervise
8 9
ENGINEER shall not supervise
92 9 132
Superintendence
6 2
Superintendent, CONTRACTOR s resident
6 2
Supplemental costs
11 4 5
Supplementary Conditions
definition of
139
principal references to 110 118
22 2 7
42 43 51 53
54 5659
511 68 613 74 811
93 910
Supplementing Contract Documents
3 6
Supplier
definition of
principal references to 37 65 68611
624 913
Waiver of Rights
Surety
consent to final payment
ENGINEER has no duty to
Notification of
qualification of
Survival of Obligations
Suspend Work OWNER May
Suspension of Work and Termination
CONTRACTOR May Stop Work
or Term mate
OWNER May Suspend Work
OWNER May Terminate
Taxes Payment by CONTRACTOR
Technical Data
Limited Reliance by CONTRACTOR
Possible Price and Times Adjustments
Reports of Differing Subsurface and
Physical Conditions
xry
140
620
1412
611
1412 1414
913
101 105 152
5153
634
13 10 151
15
155
151
152154
615
422
426
423
Temporary construction facilities
41
Article a Paragraph
Number
Termination
by CONTRACTOR
155
by OWNER
98 15 1 154
of ENGINEERS employment
82
Suspension of Work in general
15
Terms and Adjectives
34
Tests and Inspections
Access to the Work, by others
132
CONTRACTOR s responsibilities
135
cost of 13 4
covermg Work prior to
136 137
Laws and Regulations (or)
135
Notice of Defects
131
OWNER May Stop Work
1310
OWNERS independent testing
134
special required by ENGINEER
96
timely notice required
134
Uncovering the Work, at ENGINEER s
request
138 139
Times
Adjusting
66
Change of Contract
12
Computation of
172
Contract Times definition of
1 12
day
1722
Milestones
12
Requirements
appeals
910 16
clarifications
claims and disputes
911 112 12
Commencement of Contract Times
23
Preconstrucnon Conference
28
schedules
26 29 66
Starting the Work
24
Title Warranty of
143
Uncovering Work
138 139
Underground Facilities Physical Conditions
definition of
141
Not Shown a Indicated
4 3 2
protection of
43 620
Shown or Indicated
4 3 1
Unit Price Work
claims
1193
definition of
142
generall 1 9 141 145
Unit Prices
generall1 3 1
Determination for
910
Use of Premises 6 16 6 18 6 30 2 4
Utility owners 613
620 7173 132
Utilization Partial 128 5
15 6 30 2 4 14 10
Value of the Work
11 3
Values Schedule of
26 28 2 9 14 1
E1CDC GENERAL CONDITIONS 1910 8 (1990 EDITION)
w/ CITY OF FORT COLLINS MODIFICATIONS (REV 9199)
Variations in Work Minor
Authorized
625 627 95
Article or Paragraph
Number
Visits to Site by ENGINEER
92
Waiver of Clams -on Final Payment
1415
Waiver of Rights by insured parties
511 611
Warranty and Guarantee General by
CONTRACTOR
§30
Warranty of Title CONTRACTORS
143
Work
Access to
132
by others
7
Changes in the
10
Continuing the
029
CONTRACTOR May Stop Work
or Terminate
155
Coordination of
74
Cost of the
11 4 115
definition of
1 43
neglected by CONTRACTOR
1314
other Work
7
OWNER May Stop Work
13 10
OWNERMay Suspend Work
1310 151
Related, Work at Site
7 1 7 3
Starting the
24
Stopping by CONTRACTOR
155
Stopping by OWNER
151 154
Variation and deviation authorized, minor 36
Work Change Directive
clams pursuant to
102
definition of
144
principal references to
35 3 101 102
Written Amendment
definition of 145
principal references to 1 10 3 5 5 10 15 12
662 682 619 101 104
112 121 13 12 2 1472
Written Clarifications and
Interpretations 3 6 3 94 9 11
Written Notice Required
by CONTRACTOR 71 9 10 9 11
104 112 121
by OWNER 910911 104 112 1314
xv E1CDC GENERAL CONDITIONS 1910 8 (1990 EDITION)
W/ CITY OF FORT COLLINS MODIFICATIONS (REV 9/99)
(This page left blank intentionally)
xn EJCDC GENERAL CONDITIONS 1910 8 (1990 EDITION)
w/ CITY OF FORT COLLINS MODIFICATIONS (REV 9199)
GENERAL CONDITIONS
ARTICLE 1 DEFINITIONS
Wherever used in these General Conditions or in the other
CorAract Documents the following terms have the
meanings indicated which are applicable to bah the
singular and plural thereof
1 1 Addenda Written or graphic instruments Issued
pnor to the opening of Bids which clarify correct or
change the Bidding Requirements or the Contract
Documents
12 Agreement -The written contract between OWNER
and CONTRACTOR covering the Work to be perfumed
other Contract Documents are attached to the Agreement
and made a part thereof as provided therem
13 Application for Payment —Thu form accepted by
ENGINEER which is to be used by CONTRACTOR in
requesting progress or final payments and which is to be
accompamed by such supporting documentation as is
required by the Contract Documents
14 Asbestos Any material that contains more than one
percent asbestos and is friable or is releasing asbestos fibers
into the an above current action levels established by the
United States Occupations] Safety and Health
Adimmstration
15 Bid —The offer or proposal of the bidder submitted
on the prescnbed form setting forth the prices for the Work
to be performed
16 Bzddm$ Doctonents—The advertisement or
invitation to Bid Instructions to bidders, the Bid form and
the proposed Contract Documents (including all Addenda
Issued prior to receipt of Bids)
17 Bidding Requirements The advertisement or
invitation to Bud, instructions to bidders and the Bid form
1 8 Bonds —Performance and Payment bonds and other
Instruments of security
19 Change Order —A document recommended by
EN(INEER which IS signed by CONTRACTOR and
OWNER and authorizes an addition, deletion or revision in
the Work ar an adjustment in the Contract Price or the
Contract Times, issued on or after the Effective Dam of the
Agreement
110 Contract Documents —The Agreement Addenda
(which pertain to the Contract Documents)
CONTRACTORS Bid (including documentation
accompanying the Bid and any post Bid documentation
Submitted prior to the Notice of Award) when attached as
an exhibit to the Agreement, the Nance to Proceed, the
Bonds, these General Conditions, the Supplementary
Conditions, the Specifications and the Drawings as the
EJCDC GENERAL CONDITIONS 1910 8 (1990 ENnm)
W CITY OF FORT COLLINS MODIFICATIONS (REV 42000)
same are more specifically identified in the Agreement
together with all Written Amendments, Change Ordera,
Work Change Directives Fuld Orders and ENGINEERS
written mtapretatrors and clanficahos Issued pursuant to
Paragraphs 3 5 3 6 1 and 3 6 3 on or after the Effective
Date of the Agreement Shop Drawing Submittals
approved pursuant to paragraphs 6 26 and 6 27 and the
reports and drawings referred to in paragraphs 4 2 1 and
4 2 2 are not Contract Documents
111 Contract Price —The moneys payable by
OWNER to CONTRACTOR for completion of the Work
in accordance with the Contract Documents as stated in
the Agreement (subject to the provisions of
paragraph 119 1 in the case of Unit Price Work)
1 12 Contract Tzmes—The numbers of days or the
dates stated in the Agreement (i) to achieve Substantial
Completion, and (n) to complete the Weak so that it its
ready feu final payment as evidenced by ENGINEERS
written recommendation of foal payment in accordance
with paragraph 14 13
1 13 CONTRACTOR —The person, firm or corporation
with whom OWNER has entered into the Agreement
114 defective —An adjective which when modifying
the word Work refers to Work that its unsatisfactory faulty
or deficient in that it does not conform to the Contract
Documents or does not meet the requirements of any
inspection, reference standard, test or approval referred to
in the Contract Documents, or has been damaged prior to
ENGINEERs recommendation of final payment (udess
responsibility for the protection thereof has been assumed
by OWNER at Substantial Cunplehon in accordance with
paragraph 14 8 or 14 10)
1 15 Drawings- The drawings wluch show the scope
extent and character of the Work to be furnished and
performed by CONTRACTOR and which have been
prepared or approved by ENGINEER and are referred to
In the Contract Documents Shop drawings are not
Drawings as so defined
116 Effective Date of the Agreement —The date
indicated in the Agreement on which it becomes effective
but if no such dam s indicated it means the date on which
the Agreement is signed and delivered by the last of the
two parties to sign and deliver
117 ENGINEER —The person firm or corporation
named as such in the Agreement
118 ENGINEERS Consaltam A person, firm or
corporation having a contract with ENGINEER to fumsh
services as ENGINEERS independent professional
associate or consultant with respect to the Project and who
is identified as such in the Supplementary Conditions
119 Field Order —A written order issued by
ENGINEER which orders minor changes in the Work in
accordance with paragraph 9 5 but which does not involve
a change in the Contract Price or the Contract Times
SECTION 00020
INVITATION TO BID
Rev 10/20/07 Section 00020 Page 2
120 General Requirements —Sections of Division 1 of
the Specifications
121 Hazardous Waste —The term Hazardous Waste shall
have the meaning provided in Section 1004 of the Solid
Waste Disposal Act (42 USC Section 6903) as amended
from time to time
122 a Laws and Regulations Laws or Regulations Any
and all applicable laws, rules, regulations, ordinances,
codes and orders of any and all governmental bodies,
agencies, authorities and courts having lurisdnetion
1 22 b Legal Hohdays -shall be those holidays observed
by the City of Fat COIhnS
123 Liens Liens, charges, secunty Interests or
encumbrances upon real property or personal property
124 Milestone A principal event specified in the
Contract Documents relating to an in termedmte completion
date or time prior to Substantial Completion of all the
Work
125 Nonce ofAward—A written notice by OWNER to
the apparent successful bidder stating that upon comphance
by the apparent successful bidder with the conditions
precedent enumerated therein, within the time specified,
OWNER will sign and deliver the Agreement
126 Nonce to Proceed —A written notice given by
OWNER to CONTRACTOR (with a copy to ENGINEER)
fixing the date ort which the Contract Times will
commence to run and on which CONTRACTOR shall start
to perform CONTRACTORS obligations under the
Contract Documents
127 OWNER —The public body or authority
corporation, association, firm or person with whom
CONTRACTOR has entered into the Agreement and for
whom the Work is to be provided
128 Partial Utilization —Use by OWNER of a
substantially completed part of the Work for the purpose
for which it is intended (or a related purpose) prior to
Substantial Completion of all the Work
129 PCBs—Polychlonnatedbiphenyls
130 Petroleum Petroleum including crude oil or any
fraction thereof which is liquid at standard conditions of
temperature and pressure (60 degrees Fahrenheit and
14 7 pounds per square inch absolute) such as oil
petroleum fuel oil, oil sludge oil refuse gasolme kerosene
and oil mixed with other non Hazardous Wastes and crude
oils
131 Project —The total construction of which the Work
to be provided under the Contract Documents may be the
whole or a part as indicated elsewhere in the Contract
Documents
132 a Radroachre Material —Source special nuclear or
byproduct material as defined by the Atomic Energy Act of
E1CDC GENERAL CONDITIONS 19105 (1990 Eehtmn)
w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000)
1954 (42USC Section 2011 et seq) as amended from
time to time
132 b Regidar Working Hours Regular working he
are defined as 700am to 600pm unles otherwise
specified in the General Requirements
133 Resident Project Representatme—The authorized
representative of ENGINEER who may be assigned to the
site or any part thereof
134 Samples —Physical examples of materials
equipment, or workmanship that we representative of
some portion of the Work and which establish the
standards by which such portion of the Work will be
judged
135 Shop Drawengs All drawings, diagrams
illustrations. schedules and other data or information
which are speafically prepared or assembled by or fa
CONTRACTOR and submitted by CONTRACTOR to
Illustrate some portion of the Work
136 Specifications —Those portions of the Contract
Documents comisttng of written technical descriptions of
materials, equipment, construction systems, standards and
workmanship as applied to the Work and certain
administrative details applicable thereto
137 Subcontractor An individual firm or corporation
having a direct contract with CONTRACTOR or with any
other Subcontractor for the performance of a part of the
Work at the site
138 Substantial Complehon-TheWork (or a
specified part thereof) has progressed to the point where
in the Opinion of ENGINEER as evidenced
by
ENGINEERs definitive certificate of Substantial
Completion, it is sufficiently complete in accordance with
the Contract Documents so that the Work (or specified
Part) can be utilized for the purposes for which it is
intended or if no such certificate is issued when the
Work is complete and ready for final payment as
evidcirced by ENGINEERs written recommendation of
final payment in accordance with paragraph 1413 The
terms substantially complete and substantially
completed as applied to all or part of the Work refer to
Substantial Completion thereof
139 Supplementary ConaShons—The part of the
Contract Documents which amends or supplements these
General Conditions
140 Suppher—A manufactura fabricator supplier
distributor mmaialman or vendor having a direct contract
with CONTRACTOR or with any Subcontractor to
furnish matenals or equipment to be incorporated in the
Work by CONTRACTOR or any Subcontractor
141 Underground Facilities —All pipelines conduits
ducts, cables, wires, manholes, vaults, tanks tunnels or
other such facilities or attachments, and any encasements
containing such facilities which have been installed
underground to furnish any of the following services or
materials electricity gases, steam liquid petroleum
products, telephone or other communications, cable
television, sewage and drainage removal traffic or other
control systems or water
142 Unit Price Work -Work to be paid for on the basis
of unit prices
143 Work The entire completed construction or the
various separately identifiable parts thereof required to be
furnished under the Contract lesocmnents Work includes
and is the result of performing or famishing labor and
furnishing and mcorpomttrng materials and egmpment into
the construction, and performing or furnishing services and
frnashinig documents, all as required by the Contract
Documents
144 Work Change Directive -A written directive to
CONTRACTOR, issued on or after the Effective Date of
the Agreement and signed by OWNER and recommended
by ENGINEER, ordering an addition, deletion m revision
in the Wok, or responding to differing or unforeseen
Physical conditions under which the Work is to be
performed as provided in pamgraph42 or 43 or to
emergencies under paragmph623 A Work Change
Directive will not change the Contract Price or the Contract
Times, but is evidence that the parties expect that the
change directed or documented by a Work Change
Directive will be Incorporated in a subsequently issued
Change Order following negotiations by the parties m to its
effect, if any on the Contract Price or Contract Times as
provided in paragraph 10 2
145 Written Amendment A written amendment of the
Contract Documents, signed by OWNER and
CONTRACTOR m or after the Effective Date of the
Agreement and normally dealing with the nonengmeeri ng
or nontechnical rather than strictly construction related
aspects of the Contract Documents
ARTICLE 2-PREIdMINARY MATTERS
Dehvery of Bonds
21 When CONTRACTOR delivers the executed
Agreements to OWNER CONTRACTOR shall also
deliver to OWNER such Bonds as CONTRACTOR may
be required to furnish in accordance with paragraph 5 1
Copies of Documents
22 OWNER shall furnish to CONTRACTOR up to ten
copies (unless otherwise specified in the Supplementary
Condmons) of the Contract Documents as are reasonably
necessary for the execution of the Work Addn umal copies
will be furnished upon request at the cost of reproduction
Commencement of Contract Times Nonce to Proceed
23 The Contract Times will commence to run on the
thirtieth da) after the Effective Date of the Agreement, or
EICDC GENERAL CONDITIONS 1910.8 (1990 EAnm)
w/ CITY OF FORT COLLINS MODIFICATIONS (REV 411000)
if a Notice to Proceed is given, on the day indicated in the
Notice to Proceed A Notice to Proceed may be given at
any time within thirty days after the Effective Date of the
Agreement In nA wmt ••••i
Starting the Work
24 CONTRACTOR shall start to perform the Work
on the date when the Contract Times commence to run,
but no Work shall be done at the site prior to the date an
which the Contract Times commence to run.
Before Starting Constiuchon
25 Before undertaking each part of the Work
CONTRACTOR shall carefully study and compare the
Contract Documents and check and verify ent
figures shown thereon and all applicable field
measurements CONTRACTOR shall promptly report in
writing to ENGINEER any conflict error ambiguity or
dlserepmq which CONTRACTOR may discover and
shall obtain a written interpretation or clarification from
ENGINEER before proceeding with an Work affected
thereby however CONTRACTOR shall not be liable to
OWNER or ENGINEER for fadure to report any conflict,
error ambiguity or discrepancy in the Contract
Documents, unless CONTRACTOR knew or reasonably
should have known thereof
26 Within ten days after the Effective Date of the
Agreement (unless otherwise specified in the General
Requirements) CONTRACTOR shall submit to
ENGINEER for review
261 a preliminary progress schedule indicating
the tunes (numbers of days or dates) for starting and
completing the venous stages of the Work, including
any Milestones specified in the Contract Documents
262 a preliminary schedule of Shop Drawing and
Sample submittals which will list each required
submittal and the tines for submitting reviewing and
processing such Submittal
2621 In no case will a schedule be
accenmble which allows less than 21 calendar
days for each review by Engineer
263 A preliminary schedule of values for all of
the Work which will include quantities and prices of
items aggregatmg the Contract Price and will
subdivide the Work into component parts in sufficient
detail to serve as the basis for progress payments
during construction Such prices will include an
appropriate amount of overhead and profit applicable
to each tram of Wort.
27 Before any Work at the site is started
CONTRACTOR and -OWNER shall each deliver to the
Other 0 opies to
ENGINEER
certificates of iawrance (and other evidence of insurance
which e..h.._ „o a__ _ ..dt..__.., unsia:ed may
CONT requeated by OWNER) which
s required
to purchase and =ntain in aceordsnce with
paragraphs 5 4` 6 a„M `
Preconstruction Conference
28 Within twenty days alter the Contract Tunes start to
run but before any Work at the site a started, a conference
attended by CONTRACTOR ENGINEER and others as
appropriate will be held to establish a working
understanding amorig the parties as to the Work and to
dacuss the schedules referred to in paragraph 2 6
procedures for handling Shop Drawings and other
Submittals processing Applications for Payment and
maintaining required records
Inaragy Acceptable Schedules
29 Unless otherwise provided in the Contract
Documents,
before any work et the site beeins
a conference attended by CONTRACTOR ENGINEER
and others as appropriate desumated by OWNER will be
held to review ffor acceptability to ENGINEER as provided
below the schedules submitted in accordance with
paragraph 26 and Division 1 General Requirement
CONTRACTOR shall have an additional ten days to make
corrections and adjustments and to complete and resubmit
the schedules No progress payment shall be made to
CONTRACTOR urilrl the schedules are submitted to and
acceptable to ENGINEER as provided below The
progress schedule will be acceptable to ENGINEER as
providing an orderly progression of the Work to
completion within any specified M lestones and the
Contract Tames, but such acceptance will neither appose on
ENGINEER responsibility for the sequencing, scheduling
a progress of the Work not interfere with or relieve
CONTRACTOR from CONTRACTORS full
responsibility therefor CONTRACTORS schedule of
Shop Drawing and Sample submissions will be acceptable
to ENGINEER as providing a workable arrangement for
reviewing and processing the required submittals
CONTRACTOR schedule of values will be acceptable to
ENGINEER as to form and substance
ARTICLE 3 -CONTRACT DOCUMENTS INTENT
AMENDING REUSE
Intent
31 The Contract Documents comprise the entire
agreement between OWNER and CONTRACTOR
concerning the Work The Contract Documents are
complementary what is called for by one is as binding as if
called for by all The Contract Documents will be
construed in accordance with the law of the place of the
Project
32 It is the intent of the Contract Documents to
ETCDC GENERAL CONDITIONS 191M (1990 Eth0m)
wi CITY Of FORT COLLINS MODIFICATIONS (REV 42000)
describe a functionally complete Project (or part thereof)
to be constructed in accordance with the Contract
Documents Any Work, materials ar equipment that may
reasonably be inferred from the Contract Documents or
from prevailing custom or trade usage as being required to
produce the intended result will be famished and
performed whether or not specifically called for When
words or phrases which have a well known technical or
construction industry or trade meaning are used to
describe Work materials or equipment such words or
phrases shall be interpreted in accordance with that
mearmig Clarifications and interpretations of the Contract
Docwnems shall be issued by ENGINEER as provided in
paragraph 9 4
33 Reference to Standard; and Spectfncadons of
Technical Societies Raw ling and Rminng
Discrepancies
331 Reference to standards, specifications
manuals or codes of any technical society orgamzation
a association a to the Laws or Regulations of any
governmental authority whether such reference be
specific or by implication, shall mean the latest
standard specification, manual code or Laws or
Regulations in effect at the time of opening of Bids or
on the Effective Date of the Agreement if there were
no Bids) except as may be otherwise specifically
stated in the Contract Documents
332 If; during the performance of the Work
CONTRACTOR discovers any conflict, error
ambiguity or discrepancy within the Contract
Documents or between the Contract Documents and
any provision of any such Law or Regulation
applicable to the performance of the Work or of any
such standard, specification, manual or code or of any
nstruction of any Supplier referred to in paragraph 6 5
CONTRACTOR shall report it to ENGINEER in
writing at once and, CONTRACTOR shall not
proceed with the Work affected thereby (except in an
emergency as authonud by paragraph 623) until an
amendment or supplement to the Contract Documents
has been issued by one of the methods educated in
paragraph 3 5 or 3 6 provided, however that
CONTRACTOR shall not be liable to OWNER or
ENGINEER for failure to report any such conflict
error ambiguity or discrepancy unless
CONTRACTOR knew m reasonably should have
known thereof
333 Except as otherwise specifically stated in the
Contract Documents or as may be provided by
amendment or supplement thereto issued by one of the
methods indicated in paragmph 3 5 or 36 the
prmisions of the Contract Documents shall take
precedence inresolving any conflict error ambiguity
or discrepancy between the provisions of the Contract
Documems and
3 3 3 1 the provisions of any such standard
specification manual, code or instruction (whether
or not specifically incorporated by reference in the
Contract Documents) or
3 3 3 2 the provisions of arty such Laws or
Regulations applicable to the performance of the
Work (unless such an interpretation of the
Provisions of the Contract Docmnents would result
in violation of such Law or Regulation)
No provision of any such standard specification, manual
code or instruction shall be effective to change the duties
and responsibilities of OWNER CONTRACTOR or
ENGINEER or any of their subcontractors, consultants,
agents or employees from those set forth in the Contract
Documents, nor shall it be effective to assign to OWNER.
ENGINEER or any of ENGINEERS Consultants, agents o
employees any duty or authority to supervise or direct the
furnishing or performance of the Work or any duty or
authority to undertake responsibility mconsnstent with the
Provisions of paragraph 9 13 or any other provison of the
Contract Documents
34 Whenever in the Contract Documents the terms as
ordered as directed as required as allowed as
approved or teams of like effect or unport are used, or the
adjectives reasonable Suitable acceptable proper'
or Satisfactory or adjectives of like effect or import are
used to describe a requirement, direction, review or
Judgment of ENGINEER as to the Work it is intended that
such requirement, direction, review or judgment will be
solely to evaluate in general, the completed Work for
compliance with the requirements of and udormatron in the
Contract Documents and conformance with the design
concept of the completed Project as a functioning whole as
shown or radiated in the Contract Documents (unless there
is a specific statement indicating otherwise) The use of
any Such Teri or adjective shall not be effective to assign to
ENGINEER any duty or authority to supervise or direct the
furnishing or performance of the Wok or any duty or
authority to undertake responsibility contrary to the
provisions of paragraph 9 13 or any other provision of the
(,ontract Documents
Amending and Supplementing Contract Documents
3 5 The Contract Documents may be amended to
provide for additions, deletions and revisiots in the Work
or to modify the terms and conditions thereof in one or
more of the following ways
35 1 a formal Witten Amendment,
3 5 2 a Change Order (pursuant to paragraph 10 4)
or
E]CDC GENERAL CONDTTI ONS 1910 8 (1990 E(bam)
w/ CITY OF FORT COLLINS MODIFICATIONS (REV 42000)
3 5 3 a Work Change Directive (pursuant to
paragraph 10 1)
36 In addition. the requirements of the Contract
Documents may be supplemented and mmor variations
and deviations in the Work may be authorized, in one or
more of the following ways
36 1 A Field Order (pursuant to paragraph 9 51
362 ENGINEERS approval of a Shop Drawing or
Sample (pursuant to paragraphs 6 26 and 6 27) or
3 6 3 ENGINEERs written interpretation or
clarification (pursuant to paragraph 9 4)
Reuse of Documents
37 CONTRACTOR and any Subcontractor or
Supplier or other person o organization performing or
furnishing any of the Work under a direct or mdiract
contract with OWNER (I) shall not have or acquire any
title to or ownership rights many of the Drawmgs,
Specifications or other documents (or copies of any
thereof) prepared by or hearing the seal of ENGINEER or
INGINEERs Consuhant, and (u) shall not reuse any of
such Drawings Specifications other documents or copies
on extensions of the Project or any other project without
written consent of OWNER and ENGINEER and specific
written verification or adaptation by ENGINEER
ARTICLE 4- AVAILABILITY OF LANDS
SUBSURFACE AND PHYSICAL CONDITIONS
REFERENCE POINTS
Avmlabubly ofLandv
41 OWNER shell furnish, as indicated in the Contract
Documents, the lands upon which the Work is to be
performed nghtsof way and easements for access
thereto and such other lands which are designated for the
uwofCONTRACTOR
03A4IER-she14- isne—sh CONTRACTOR
of ^" filing ow ..e
OWNER shall identify any encumbrances or restrictions
not of general application but specifically related to use of
lands so furnished with which CONTRACTOR will have
to comply in perfommg the Work Easements for
permanent structures or permanent changes in exnstmg
facilities will be obtained and paid for by OWNER, unless
Otherwise provided in the Contract Documents If
CONTRACTOR and OWNER are unable to agree on
entitlement to or the amount or extent of any adjustments
in the Contract Price or the Contract Times as a result of
any delay in OWNERS fumislumg these lands, rights -of
way or easements CONTRACTOR may make a claun
therefor as provided in Articles I I and 12
CONTRACTOR shall provide for all additional land, and
access thereto that may be required for temporary
construction facilities or storage of materials and
equipment
42 Subsurface and Physical Condtions
4 2 1 Reports and Drawings Reference is made to
the Supplementary Condiuons for Identification of
42 1 1 Subsurface Condtaoits Those reports of
explorations and tests of subsurface conditions at or
contiguous to the site that have been utilized by
ENGINEER in preparing the Contract Documents
and
4212 Physical Conettions Those drawings of
physical conditions in or relating to existing surface
or subsurface structures at or contiguous to the site
(except Underground Facilities) that have been
utilized by ENGINEER in preparing the Contract
Documents
4 2 2 Limited Rehance by CONMACTOR Authonzed
Technical Data CONTRACTOR may rely upon the
general accuracy of the technical data contained in such
reports and drawmgs, but such reports and drawings are not
Contact Documents Such technical data is identified in
the Supplementary Conditions Except for such reliance on
such technical data CONTRACTOR may not rely upon
Or make any claim against OWNER, ENGINEER or any of
ENGINEERS Consultems with respect to
4 2 2 1 the completeness of such reports and
drawings for CONTRACTORS purposes,
Including but not limited to any aspects of the
means methods techniques sequences and
procedures of construction to be employed by
CONTRACTOR and safety precautions and
programs incident thereto or
4222 other data interpretations, opinions
and information contained in Such reports or shown
or indicated in Such drawings or
4223 any CONTRACTOR interpretation of
or conclusion drawn from any technical data or
any Such data interpretations, opinions or
information
423 Nonce of Dieing Subsurface or Physical
Conchnons If CONTRACTOR believes that any
subsurface or physical condition at Or contiguous to the site
that is uncovered or revealed either
423 1 is of such a nature as to establish that
any technical data on which CONTRACTOR is
entitled to rely as provided in paragraphs 4 2 1 and
4 2 2 is materially maccunue or
4232 Is of such a nature as to require a
change in the Contract Documents, or
4233 differs materially from that shown or
EJCDC GENERAL CONDITIONS 1910 a (1990 Edam)
W CITY OF FORT COLLINS MODIFICATIONS (REV 4k0o0)
indicated in the Contract Documents, or
4234 is of an unusual nature and differs
materially Fran conchttons ordinarily encountered
and generally recognized as inherent in work of
the character provided for in the Contract
Documents then
CONTRACTOR shall promptly unmedtately after
becovlvig aware thereof and before further disturbuig
conditions affected thereby or perfn mg any Work in
connection therewith (except in an emergency as
permitted by paragmph623) notify OWNER and
ENGINEER in writing about such condition
CONTRACTOR shall not further disturb such conditions
a perform any Work in connection therewith (except as
aforesaid) until receipt of wnuen order to do so
424 ENGINEER s Review ENGINEER will
promptly review the pertinent conditions, determine the
necessity of OWNER s obtaining additional exploration or
tests with respect thereto and advise OWNER in writing
Zh a copy to CONTRACTOR) of ENGINEERS
ings and conclusions
425 Possible Contract Documents Change If
ENGINEER concludes that a change in the Contract
Documents is required as a result of a condition that meets
one or more of the categories in paragraph 4 2 3 a Work
Change Directive or a Change Order will be Issued w
provided in Article 10 to reflect and document the
consequences of such charge
4 2 6 Possible Price and Times Ad#usAnents An
equitable adjustment in the Contract Price or in the
Contract Times, or both, will be allowed to the extent that
the existence of Such uncovered or revealed condition
causes an increase or decrease in CONTRACTORS cost
of or time required for performance of; the Work subject
however to the following
4 2 6 1 Such condition must meet any one or
more of the categories described in
Paragraphs 4 2 3 1 through 4 2 3 4 inclusive
4262 a change in the Contract Documents
pursuant to paragraph 4 2 5 will not be an
automatic authorization of nor a condition
precedent to entitlement to any such adjustment
4263 with respect to Work that is paid for
on a Unit Price Basis, any adjustment in Contract
Price will be subject to the provisions of
Paragraphs 9 10 and 119 and
4264 ( ONTRACTOR shall not be entitled
to any adjustment in the Contract price or Tunes
if
42641 CONTRACTOR knew of
the existence of such conditions at the
Fire CONTRACTOR made a final
commitment to OWNER in respect of
Contract Price and Contract Times by the
submission of a bid or becoming bound
under a negotiated contract, or
42642 the existence of such
condition could reasonably have been
discovered or revealed as a result of any
examumucT4 mvesugahon, exploration,
test or study of the site and contiguous
areas required by the Bidding
Requirements a Contract Documents to be
conducted by or for CONTRACTOR prior
to CONTRACTORS making such final
conmrtment, a
42643 CONTRACTOR failed to
give the written notice within the time and
as required by paragraph 4 2 3
If OWNER and CONTRACTOR are unable to agree on
entitlement to or as to the amount or length of any such
equitable adjustment in the Contract Rice or Contract
Times a clam may be made therefor as provided in
Articles 11 and 12 However OWNER, ENGINEER and
ENGINEERs Consultants shall not be liable to
CONTRACTOR for any clams, eosK losses or damages
sustained by CONTRACTOR on or in connection with any
other project or anticipated project.
43 Physical Conditions —Underground Facihtnes
4 3 1 Shom orindtcated The information and data
shown or indicated in the Contract Documents with
respect to existing Underground Facilities at or
contiguous to the site is based on information and data
furnished to OWNER or ENGINEER by the owners of
such Underground Facilities or by others Unless it is
otherwise expressly provided in the Supplementary
Conditions
4 3 1 1 OWNER and ENGINEER shall not be
responsible fa the accuracy or completeness of any
such information or data and
4 3 1 2 The cost of all of the following will be
included in the Contract Price and CONTRACTOR
shall have full responsibility for (i) reviewing and
checking all such information and data (11) locating
all Underground Facilities shown or indicated in the
Contract Documents (tit) coordmation of the Work
with the owners of such Underground Facilities
during construction and (iv) the safety and
protection of all such Underground Facibties as
provided in paragraph 620 and repairing any
damage thereto resulting from the Work
432 Not Shown of Indicated If an Underground
Facility is uncovered or revealed at or contiguous to
the site winch was not shown or indicated in the
Contract Documents, CONTRACTOR shall, pmmfQy
mmediately after becoming aware thereof and before
father disturbing conditions affected thereby or
performing any Work in connection therewith (except
in an emergency as required by paragraph 623)
identify the owner of such Underground Facility and
EJCDC GENERAL CONDITIONS 19104a (1990 MUM)
w/ CITY OF FORT COLLINS MODIFICATIONS (REV 42000)
give written notice to that owner and to OWNER and
ENGINEER ENGINEER will promptly review the
Underground Facility end determine the extent, if
any to winch a change is required in the Contract
Documents to reflect and document the consequences
of the existence of the Underground Facihty If
ENGINEER concludes that a change in the Contract
Documents is required, a Work Change Directive or a
Change Order will be issued m provided in Article 10
to reflect and document such consequences During
such tune CONTRACTOR shall be responsible for
the safety and protection of such Underground
Facility as provided in paragraph 620
CONTRACTOR shallmay be allowed an me ease in
the Contract Price a an extension of the Contract
Tunes, or both, to the extent that they are attrbutable
to the existence of any Underground Facility that was
not shown or indicated in the Contract Documents
and that CONTRACTOR did no know of and could
not reasonably have been expected to be aware of or
to have anticipated If OWNER and CONTRACTOR
we unable to agree on entitlement to or the amount or
length of any such adjustment in Contract Price or
Contract Tunes, CONTRACTOR may make a claim
therefor as provided in Articles 11 and 12 However
OWNER, ENGINEER and ENGINEEPs
Consultants shall not be liable to CONTRACTOR for
any clams, costs, losses or damages incurred or
sustained by CONTRACTOR on a in connection
with any other project or anticipated project
Reference Points
44 OWNER shall provide engmeermg surveys to
establish reference points for construction winch in
ENGINEERS judgment are necessary to enable
CONTRACTOR to proceed with the Work
CONTRACTOR shall be responsible for laying out the
Work, shall protect and preserve the established reference
points and shall make no changes or relocations without
the prior written approval of OWNER CONTRACTOR
shall report to ENGINEER whenever any reference point
Is lost or destroyed or requires relocation because of
necessary changes in grades or locations, and shall be
responsible for the accurate replacement or relocation of
such reference points by professionally qualified
personnel
4 5 Asbestos, PCBs Petroleum Hazardous Wage or
Raiboactive Material
451 OWNER shall be responsible for any
Asbestos PCBs, petroleum Hazardous Waste or
Radioactive Material uncovered or revealed at the site
which was not shown or indicated in Dmwngs or
Specifications or identified in the Contract
Documents to be within the scope of the Work and
which may present a substantial danger to persons or
property exposed thereto in connection with the Work
at the site OWNER shall not be responsible for any
such materials brought to the site by
CONTRACTOR Subcontractors Suppliers or
anyone else for whom CONTRACTOR is
responsible
ARTICLE 5- BONDS AND INSURANCE
Performance Payment and Other Bonds
51 CONTRACTOR shall furnish performance and
Payment Bonds each in an amount at least equal to the
Contract Price as security for the faithful performance and
payment of all CONTRACTORS obligations under the
Contract Documents These Bonds shall remain in effect
at least until one year after the date when final payment
becomes due except as provided otherwise by Laws or
Regulations or by the Contract Documents
CONTRACTOR shall also furnish such other Bonds as
are required by the Supplementary Conditions All Bonds
shall be in the form prescribed by the Contract Documents
except as provided otherwise by Laws or Regulations and
shall be executed by such sureties as we named m the
current list of Coinpames HoldCertificates of
Authority as Acceptable Sureties on Fvig feral Bonds and as
Acceptable Remaining Companies as published m
Circular 570 (amended) by the Audit Stag Bureau of
Government Fuiareial Operations US Treasury
Department All Bonds signed by an agent must be
accompanied by a certified copy of such agents authority
to act
52 If the surety on any Bond furnished by
CONTRACTOR is declared a banlovpt or becomes
insolvent or its right to do business u terminated many
state where any part of the Project is located a it ceases to
meet the requirements of paragraph 5 1 CONTRACTOR
shall within ten days thereafter substitute another Bond
and surety both of which must be acceptable to OWNER
53 Licensed Sureties and Insurers Cerhficates of
Insurance
5 3 1 All Bards and Insurance required by the
Contract Documents to be purchased and maintained
by OWNER or CONTRACTOR shall be obtamed
from surety or insurance companies that we duly
licensed or authorized in the jurisdiction in which the
Project is located to issue Bonds or insurance policies
for the ]units and coverages so required Such surety
and Insurance companies shall also meet such
additional requirements and qualifications as may be
provided in the Supplementary Conditions
532 CONTRACTOR shall deliver to OWNER,
with copies to each additional insured identified in the
Supplementary Conditions, certificates of insurance
(and other evidence of insurance requested by
OWNER or any other additional Insured) which
CONTRACTOR is required to purchase and maintain
in accordance with paragraph o 4 (UI;NER-shell
EICDC GENERAL CONDITIONS 1910-8 (1990 Elhtim)
wi a rY OF FORT COLLINS MODIFICATIONS (REV 4t2000)
CONTRACTOR s L abibty Insurance
54 CONTRACTOR shall purchase and maintain such
liability and other insurance as Is appropriate for the Work
being performed and furtushed and as will provide
protection from claims set forth below which may arise out
of or result from CONTRACTORS performance and
furnishing of the Work and CONTRACTORS other
obligations under the Contract Documents, whether it is to
be performed or famshed by CONTRACTOR army
Subcontractor or Supplier or by anyone directly or
indirect] y employed by any of them to perform or furnish
any of the Work or by anyone for whose acts any of them
may be liable
5 4 1 claims under workers compensation, disability
benefits and other similar employee benefit acts
542 clams for damages because of bodily injury
occupational sickness or disease or death of
CONTRACTORS employees
543 clams for damages because of bodily injury
sickness or disease or death of any person other than
CONTRACTORS employees
545 clams for damages, other than to the Work
itself because of injury to or destruction of tangible
property wherever located, including loss of use
resulting therefrom and
546 clams for damages because of bodily mjury or
death of arty person or property damage ansing out of
the ownership maintemance or use of any motor
vehicle
The policies of insurance so required by this paragraph 5 4
to be purchased and maintained shall
5 4 7 with respect to insurance required by
paragraphs 5 4 3 through 5 4 6 inclusive and 5 4 9
include as additional insureds (subject to any
customary exclusion in respect of professional
liability) OWNER ENGINEER ENGINEERS
Consultants and any other persons or entities identified
in the Supplementary Conditions, all of whom shall be
listed as additional insureds and include coverage for
the respective officers and employees of all such
additional insureds
5 4 8 include the specific coverages and be written
for not less than the limits of liability provided in the
Supplementary Conditions or required by Laws or
Regulations whichever is greater
5 4 9 include completed operations insurance
E]CDC GENERAL CONDITIONS 19104 (1990 ENnm)
w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000)
5 410 include contractual liability insurance
covering CONTRACTORS mdemmty obligations
under paragraphs 6 12 6 16 and 6 31 through 6 33
5 4 11 contain a provision or endorsement that the
coverage afforded will not be cancelled, materially
changed or rermewal refused until at least thirty days'
prior written nonce has been given to OWNER and
CONTRACTOR and to each other additional insured
identified in time Supplementary Conditions to whom
a certificate of insurance has been issued (and the
certificates of insura ice furnished by the
CONTRACTOR pursuma to paragraph 5 3 2 will so
provide)
5 4 12 remain in effect at least until final payment
and at all tares thereafter when CONTRACTOR may
be correcting, removing or replacing defectrve Work
in accordance with paragraph 13 12 and
5 4 13 with respect to completed operations
insurance and any insurance coverage written on a
claims -made basis, remain in effect for at least two
years after final payment (and CONTRACTOR shall
fmush OWNER and each other additional insured
identified in the Supplementary Conditions to whom
a certificate of insurance has been issued evidence
satisfactory to OWNER and any Such additional
insured of continuation of such insurance at final
payment and one year thereafter)
OWNER s Liability Insurance
55 In addition to insurance required to be provided
by CONTRACTOR under paragmph54 OWNER at
OWNERS option, may purchase and maintain at
OWNERS expense OWNER own liability insurance as
will protect OWNER against claims winch may anse from
operations under the Contract Documents
Property Inmmace
♦ IpJFi�iY�M4iii�l�i11!!lIJY.$iNl7�_i11!Y
59 OWNER shall not be responsible for purchastng
and maratatrung any property Insurance to protect the
Interests of CONTRACTOR Subcontractors or others to
alsk of
�e
at th
Vf
10 E]CDC GENERAL CONDITIONS 39104(1990EMIM)
W CITY OF FORT COLLINS MODIFICATIONS (REV 4,2000)
rITM or nrnrccn ., n,,.,....t..._...
Receipt andApphcnaon ofImmnce Proceeds
512 Any ensured loss under the policies of insurance
required by pamgaphs 5 6 and 5 7 will be adjusted with
OWNER and made payable to OWNER as fiduciary for the
insureds, as their interests may appear subject to the
requirements of any applicable mortgage clause and of
paragraph 513 OWNER shall deposit in a separate
account any money so received, and shall distribute it in
accordance With such agreement as the parties in interest
may reach If no other special agreement s reached the
damaged Work shall be repawbd or replaced, the moneys so
received applied on account thereof and the Work and the
cost thereof covered by an appropriate Change Order or
Witten Amendment
513 OWNER as fiduciary shall have power to adjust
and settle any loss With the insurers unless one of the
Parties in interest shall object in writing within fifteen days
after the occurrence of loss to OWNER exercise of this
power If such objection be made, OWNER as fiduciary
shall make settlement with the insurers in accordance with
such agreement as the parties in interest may reach If no
such agreement among the parties in interest is reached,
OWNER as fiduciary shall adjust and settle the loss with
the msurers Ttt _ __d ._
. unby�g s
r ,_entaest; ��a
wrr%.eFfeem___ _rN
AccepranceojBondvandlnsumnce Ophonto Replace
514 If
OWNER has any objection to the coverage afforded by or
other provisions of the $arils-; insurance required to be
purchased and maintained by the ether —party
CONTRACTOR in accordance with Article 5 on the basis
of nonconfonmmce with the Contract Documents the
in WrmT Witt
the certi&cates
27
Partial Uhhsahon—Property Insurance
5 15 If OWNER funds it necessary to occupy or use a
portion or portions of the Work prior to Substantial
EICDC GENERAL CONDITIONS 19104 (1990 Edt,m)
w/ CI IY OF FORT COLWNS MODIFICATIONS (REV 42000)
Completion of all the Work, such use or occupancy may
be accomplished in accordance with paragraph 14 16
provided that no such use or occupancy shall commence
before the insurers providing the property insurance have
acknowledged notice thereof and in writing effected any
changes in coverage necessitated thereby The usurers
providing the property insurance shall consent by
endorsement on the policy or policies, but the property
insurance shall not be cancelled a permitted to lapse on
account of any such partial use or occupancy
ARTICLE 6—CONTRACTOR S
RESPONSIIRLUM
Supervision andSuperu tendmce
61 CONTRACTOR shall supervise inspect and
direct the Work competently and efficiently devoting
such attention thereto and applying such skills and
expertise as may be necessary to perform the Work in
accordance with the Contract Documents
CONTRACTOR shall be solely responsible for the means
methods techniques, sequences and procedures of
construction, but CONTRACTOR shall not be responsible
for the negligence of others in the design or specification
of a specific means, method, technique sequence or
procedure of construction which is shown or indicated in
and expressly required by the Contract Documents.
CONTRACTOR shall be responsible an see that the
completed Work complies accurately With the Contract
62 CONTRACTOR shall keep on the Work at all
tunes during its progress a competent resident
superintendent, who shall not be replaced without written
nonce to OWNER and ENGINEER except under
extraordinary circumstances The superintendent will be
CONTRACTORS representative at the site and shall have
authority to act on behalf of CONTRACTOR All
communications to the superintendent shall be as binding
m if given to CONTRACTOR
Labor MateradsandEquipment
63 CONTRACTOR shall provide competent
suitably qualified personnel to survey lay out and
construct the Work as required by the Contract
Documents CONTRACTOR shall at all tuna maintain
good discipline and order at the site Except as otherwise
required for the safety a protection of persons or the
Work or property at the site or adjacent thereto and
except as otherwise indicated in the Contract Documents
all Work at the site shall be performed cluing regular
working hours and CONTRACTOR will not permit
overtime work or the performance of Work on Saturday
Sunday or any legal holiday without OWNERS written
consent given after prior written notice to ENGINEER
CONTRACTOR shall submit requests m the ENGINEER
no less than 4g hours in advance of any Work to be
RMOM ed on Saturday. Sunday, Holidays or outside the
Regular Working Hours
11
SECTION 00020
INVITATION TO BID
Date November 15, 2007
Sealed Bids will be received by the City of Fort Collins (hereinafter referred
to as OWNER), at the office of the Purchasing Division, 3 00 P M our clock
on December 6 2007 for the Trolley Brick Restoration Project, BID NO 6075
If delivered, they are to be delivered to 215 North Mason Street 2°a Floor
Fort Collins Colorado 80524 If mailed, the mailing address is P 0 Box
580 Fort Collins CO 80522-0580
At said place and time and promptly thereafter all Bids that have been duly
received will be publicly opened and read aloud
The Contract Documents provide for the construction of Bid 6075 Trolley Brick
Restoration Project, This work shall consist of the removal salvage and
restoration of the existing brick/concrete roadbed adjacent to the historical
trolley tracks on East Mountain Avenue between College Avenue and Peterson
Street in the City of Fort Collins The bricks shall be removed and salvaged
to the maximum extent feasible The salvaged bricks supplemented by new
bricks shall be replaced in the trolley roadbed This work will also include
related concrete removal and traffic control
This is a Federally Funded project and the UDBE goal is 7%
The CDOT Form 347 Certification of EEO Compliance is no longer required to
be submitted in the bid package This form certified that the
contractor/proposed subcontractors were in compliance with the Joint Reporting
Committee EEO-1 form requirements The EEO-1 Report must still be submitted to
the Joint Reporting Committee if the contractors and subcontractors meet the
eligibility requirements (29CFR 1602 7) we will however no longer require
certification For additional information regarding these federal
requirements please refer to
http //www eeoc gov/stats/jobpat/elinstruct html
Forms 606 Anti -Collusion Affidavit and 714 UDBE must be in the bid package
and submitted with the contractor s bids Bids will not be accepted if they
don t have these forms
All Bids must be in accordance with the Contract Documents on file with The
City of Fort Collins 215 North Mason St 2nd floor Fort Collins Colorado
80524
Contract Documents will be available November 15 2007
A prebid conference and lob walk with representatives of prospective Bidders
will be held at 1 30 pm, on November 29, 2007, at 215 North Mason, conference
roon 1B, Fort Collins
Prospective Bidders are invited to present their questions relative to this
Bid proposal at this meeting
Rev 10/20/07 Section 00020 Paae 1
64 Unless otherwise specified in the General
Requirements CONTRACTOR shall furnish and assume
full responsibility for all materials equipment, labor
transportation oomtmction equrpmem and machinery
tools, appliances, fuel, power light, heat, telephone water
sanitary facilities, temporary facilities and all other
facilities and merdentals necessary for the f tnushin&
performance tesung start up and completion of the Work
641 Purchzsm¢ Restrictions CONTRACTOR
must comply with the City s omnchasm¢ restrictions A
copy of the resoluhos are available for review in the
offices of the Purdnasin¢ and Risk Management
Ihvismnor the CnY Clerks office
642 Cement Restrictions City of Fart Collins
Resolution 91 121 reonues that suppliers and producers
of cement or products co huim cement to certify that
the cement was not made in cement lams that bum
hazardous waste as a fuel
65 All materials and equipment shall be of good
quality and new except as otherwise provided in the
Contract Documents All warranties and guarantees
Specifically called for by the Specifications shall expressly
run to the benefit of OWNER If required by ENGINEER,
CONTRACTOR shall furnish satisfactory evidence
(including reports of required tests) as to the kind and
quality of materials and equipment All materials and
equipment shall be applied installed, connected, erected,
used, cleaned and conditioned in accordance with
instructions of the applicable Supplier except as otherwise
provided in the Contract Documents
Progress Schedule.
66 CONTRACTOR shall adhere to the progress
schedule established in accordance with paragraph 2 9 as it
may be adjusted from time to time as provided below
661 CONTRACTOR shall submit to ENGINEER
for acceptance (to the extent indicated in
pa h29) proposed adjustments in the progress
schedule that will not change the Contract Times (or
Milestones) Such adjustments will conform generally
to the progress Schedule then in effect and additionally
will comply with any provisions of the General
Requirements applicable thereto
6 6 2 Proposed adjustments in the progress schedule
that will change the Contract Tunes (or Milestones)
shall be submitted in accordance with the requirements
of paragraph 12 1 Such adjustments may only be
made by a Change Order or Witten Amendment in
accordance with Article 12
67 Substdutes and Or Equal Items
6 7 1 Whenever an Item of maternal or equipment its
specified or described in the Contract Documents by
using the name of a proprietary item or the name of a
particular Supplier the specification or description is
intended to establish the type function and quality
required Unless the specification or description
PJCDC OENERAL CONDITIONS 1910-e (1990 Rdtim)
12 w/ CITY OF FORT COLLINS MODIFICATIONS (REV 411000)
contains or is followed by words reading that no like
equivalent or or equal item or no substitution is
pemiitted, other items of material or equipment or
material o equipment of other Suppliers may be
accepted by ENGINEER under the following
circumstances
6711 UrEqual If in ENGINEERS sole
discretion an item of material or equgmient
proposed by CONTRACTOR is furichoally
equal to that named and sufficiently similar so that
no change in related Work will be required, it may
be considered by ENGINEER as an oral
item in which case review and approval of the
proposed item may in ENGINEERS sole
discretion, be accomplished without compliance
with some or all of the requirements for
acceptance of proposed substitute items
6712 Subsntuteltens If mENGINEERs sole
discretion an item of material or equipment
proposed by CONTRACTOR does no qualify as
an orequal item under subparagraph 6 7 1 1 it
will be considered a proposed substitute item
CONTRACTOR shall submit sufficient
information as provided below to allow
ENGINEER to determine that the item of material
or equipment proposed its essentially equivalent to
that named and an acceptable substitute therefor
The procedure for review by the ENGINEER will
include the following as supplemented in the
General Requmremeras and as ENGINEER may
decide is appropriate under the circumstances
Requests for review of proposed substitute items
of maternal or equipment will not be accepted by
ENGINEER from anyone other than
CONTRACTOR If CONTRACTOR wishes to
furnish or use a substitute item of material or
equipment, CONTRACTOR shall first make
written application to ENGINEER for acceptance
thereof certifying that the proposed substitute will
perform adequately the functions and achieve the
results called for by the general design, be sunder
in substance to that specified and be suited to the
same use as that specified The application will
state the extent, if any to which the evaluation
and acceptance of the proposed substitute will
prejudice CONTRACTORS achievement of
Substantial Completion on time whether or not
acceptance of the substitute for use in the Work
will require a change in any of the Contract
Documents (or in the provisions of any other
direct contract with OWNER for work on the
Project) to adapt the design to the proposed
substitute and whether or not incorporation or use
of the substitute in connection with the Work is
subject to payment of any license fee or royalty
All vanatios of the proposed substitute from that
specified will be identified in the application and
available maintenance repair and replacement
service will be indicated The application will
also contain an Itemized estimate of all costs or
credits that will result directly or indirectly from
acceptance of Such substitute including costs of
redesign and claims of other contractors affected
by the resulting change all of which will be
considered by ENGINEER in evaluating the
proposed substitute ENGINEER may require
CONTRACTOR to furnish additional data about
the proposed substitute
6 7 13 CONTRACTOR s Expense All data to be
provided by CONTRACTOR in support of any
proposed or -equal or substitute item will be at
CONTRACTORS expense
672 Substitute Construction Methods or
Procedures If a specific means method, technique,
sequence a procedure of construction Is shown or
indicated in and expressly required by the Contract
Documents, CONTRACTOR may fumish or utilize a
substitute means method, technique sequence or
procedure of construction acceptable to ENGINEER
CONTRACTOR shall submit suftictent information to
allow ENGINEER, in ENGINEERs sole discretion, to
detennme that the substitute proposed is equivalent to
that expressly called for by the Contract Documents
The procedure for review by ENGINEER will be
similar to that provided in subparagraph 6 7 12
6 7 3 Engineer's Evaluation ENGINEER will be
allowed a reasonable time within which to evaluate
each proposal or submittal made pursuant to
paragraphs 6 7 12 and 6 7 2 ENGINEER will be the
sole judge of acceptability No or-squal or
substitute will be ordered, Installed or utilized without
ENGINEERS prior written acceptance which will be
evidenced by either a Change Order or an approved
Shop Drawing OWNER may require
CONTRACTOR to furnish at CONTRACTORS
expense a special performance, guarantee a other
surely with respect to
any orcqueI a substitute
ENGINEER will record tune required by
ENGINEER and ENGINEERS Consultants in
evaluating substitutes proposed or submitted by
CONTRACTOR pursuant to paragraphs 6 7 12 and
6 7 2 and in making changes in the Contract
Documents (a in the provisions of any other direct
contract with OWNER for work on the Project)
occasioned thereby Whether or not ENGINEER
accepts a substitute item so proposed or submitted by
CONTRACTOR, CONTRACTOR shall reanburse
OWNER fa the charges of ENGINEER and
ENGINEERS Consultants for evaluating each such
proposed substitute item
68 Concerning Subcontractors Suppliers and
Others
6 8 1 CONTRACTOR shall not employ any
Subcontractor Supplier or other person or organization
(including those acceptable to OWNER and
ENGINEER as Indicated in paragraph 6 8 2) whether
initially or as a substitute against whom OWNER or
ENGINEER may have reasonable objection
CONTRACTOR shall not be required to employ any
Subcontractor Supplier or other person or Organization
to furnish or put.orrm any of the Work against whom
CONTRACTOR has reasonable objection
EJCDC GENERAL CONDITIONS 1910 8 (1990 Edrtim)
w/ CITY OF FORT COLLINS MODIFICATIONS (REV 42000)
69
CONTRACTOR shall perform not less than 20
percent of the Work with its on faces (that Is,
without subcontractma) The 20 percent mowers
shall be understood to refer to the Work the value of
which totals not less than 20 percent of the Contract
Puce
682 Baldme
Documents require the identity of certain
Subcontractors, Suppliers or other persons or
organizations (Including those who are to furnish the
pruiclpal items of materials or equipment) to be
submitted to OWNER
date prior to the Effective Date of the Agreement for
acceptance by OWNER and ENGINEEP,—Ora rf
GGNTRn O li__� Otiseef Is
OWNERS or ENGINEERS aweptmoe (either in
venting or by failing to make written objection thereto
by the date indicated for acceptance or objection in
the bidding documents or the Contract Documents) of
nffiku�shffi se. y be
,jai. Offie GQ9R
auepamce oy uwNbK a
ENGINEER of any such Subcontractor Supplier or
other person or organization shall constitute a waiver
Of any right of OWNER or ENGINEER to reject
defective Work
691 CONTRACTOR shell be fully resperos�ble to
OWNER and ENGINEER fa all acts and omissions
of the Subcontractors, Suppliers and other persons
and organizations performing or furnishing any of the
Work under a direct Or Indirect contract with
CONTRACTOR just as CONTRACTOR is
responsible for CONTRACTORS own acts and
omissions Nothing in the Contract Documents shall
create for the benefit of any such Subcontractor
Supplier or other person or Organization any
contractual relationship between OWNER or
ENGINEER and any such Subcontractor Supplier or
other person Or organization, nor shall it create any
Obligation on the part of OWNER a ENGINEER to
Pay or to see to the payment of any moneys due any
Such Subcontractor Supplier or other person or
organnanon except as may otherwise be required by
Laws and Regulations OWNER or ENGINEER may
furnish to env subcontracts sutroher or other person
or organization evidence of amounts paid to
CONTRACTOR in accordance with
CONTRACTORS Arrohcationsfor Payment
13
692 CONTRACTOR shall be solely responsible
for scheduling and coordinating the Work of
Subcontractors, Suppliers and other persons and
organizations performing or fpmishung any of the
Work under a direct or indirect contract with
CONTRACTOR CONTRACTOR shall require all
Subcontractors, Suppliers and such other persons and
organizations performing or furnishing arty of the
Work to communicate with the ENGINEER through
CONTRACTOR
610 The divisions and sections of the Specifications and
the identifications of any Drawings shall not control
CONTRACTOR individi g the Work among
Subcontractors or Suppler or delineating the Work to be
performed by any specific trade
611 All Work performed for CONTRACTOR by a
Subcontractor or Supplier will be pursuant to an
appropriate agreement between CONTRACTOR and the
Subcontractor or Supplier which specifically binds the
Subcontractor or Supplier to the applicable terns and
conditions of the Contract Documents for the benefit of
Potent Fees and Royalhes
612 CONTRACTOR shall pay all license fees and
royalties and assume all costs incident to the use in the
performance of the Work or the incorporation in the Work
of any invention, design, process, product or device which
is the subject of patent rights or copyrights held by others
If a particular invention, design, process, product or device
is specified in the Contract Documents for use in the
performance of the Work and if to the actual knowledge of
OWNER or ENWNEER its use is Subject to patent rights
or copyrights calling for the payment of any license fee or
royalty to others, the existence of such rights shall be
disclosed by OWNER in the Contract Documents To the
fullest extent permitted by Laws and Regulations,
CONTRACTOR shall Indemnify and hold harmless
OWNER, ENGINEER, ENGINEERS Consultants and the
officers directors employees agents and other consultants
of each and any of them from and against all clams costs,
losses and damages arising out of or resulting from any
infringement of patent rights or copyrights mcident to the
use in the performance of the Work or resulting from the
incorporation in the Work of any invention design,
process product or device not speafied in the Contract
Documents
14 EJCDC GENERAL CONDITIONS 1910b (1990 Eiham)
w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000)
Permds
613 Unless otherwise provided in the Supplementary
Conditions, CONTRACTOR shall obtain and pay for all
construction permits and hoenses, OWNER shall assist
CONTRACTOR, when necessary in obtaining such
permits and licenses CONTRACTOR shall pay all
governmental charges and mspechon fees necessary for
the prosecution of the Work, which are applicable at the
time of opening of Bids, or if there are no Bids on the
Effective Date of the Agreement CONTRACTOR shall
pay all charges of utility owners for connections to the
Work, and OWNER shall pay all charges of such utility
owners for capital costs related thereto such as plant
investment fees
614. Laws andRegulahons
6141 CONTRACTOR shall give all nouces and
comply with all Laws and Regulations applicable to
furnishing and performance of the Work Except
where otherwise expressly required by applicable
Laws and Regulations, neither OWNER nor
ENGINEER shall be responsible for monitoring
CONTRACTORS compliance with any Laws or
Regulations
6142 If CONTRACTOR performs any Work
knowing or having reason to know that it is contrary
to Laws or Regulations, CONTRACTOR shall bear
all claims, costs, losses and damages caused by
arising out of or resulting therefrom however it shall
not be CONTRACTORS primary responsibility to
make certain that the Speci canons and Drawings are
in accordance with Laws and Regulations, but this
Shall not relieve CONTRACTOR of
CONTRACTORS obligations under paragraph 3 3 2
Taxes
615 CONTRACTOR shall pay all sales, consumer
use and other similar taxes required to be paid by
CONTRACTOR in accordance with the Laws and
Regulations of the place of the Project which we
applicable during the performance of the Work
6 15 1 OWNER is exempt from Colorado State and
local sales and use taxes on materials to be
rcemmanently inconxirated into the project Said taxes
shall not beincluded in the Contract Price
Address
Colorado Department of Revenue
State Capital Annex
1375 Sherman Street
Denver. Colorado 80261
Sales and Use Taxes for the State of Colorado
Regional Trarsoortation District (RTD) and certain
Colorado counties are collected by the State of
Colorado and are included in the Certification of
Exemmlon
All anohwble Sales and Use Taxes (micl�__nja State
collected taxesl. on any items other than corstruction
and budmakings MMcally incorporated into the
pwo�ect are to be ti2id by CONTRACTOR and are to
be included in aomaxiak bid items
Use ofPiemrses
616 CONTRACTOR shall confine construction
equipment the storage of materials and equipment and the
oopperations of workers to the site and land and areas
identified in and permitted by the Contract Documents and
other land and areas permitted by Laws and Regulations,
rights -of way permits and easements and shall not
unseasonably encumber the premises with construction
equipment or other materials or equipment
CONTRACTOR shall assume full responsibility for any
damage to any such land or area, or to the owner or
occupant thereof or of any adjacent land or areas resulting
from the performance of the Work Should any clam be
made by any such owner or occupant because of the
performance of the Work CONTRACTOR shall promptly
settle with such other party by negotiation or otherwise
resolve the claim by arbitration or other dispute resolution
proceeding m at law CONTRACTOR shall to the fullest
extent permitted by Laws and Regulations, indemnify and
hold harmless OWNER, ENGINEER ENGINEERS
Consultant and anyone directly or mdirectly employed by
any of them from and against all claims costs losses and
damages ansmg out of or resulting from any claim or
action, legal or equitable, brought by any such owner or
occupant against OWNER, ENGINEER or any other party
indemnified hereunder to the extent caused by or based
upon CONTRACTOR s performance of the Work
6 17 During the progress of the Work CONTRACTOR
shall keep the premises free from accumulations of waste
materials, rubbish and other debris resulting from the
Work At the completion of the Work CONTRACTOR
shall remove all waste materials, rubbish and debris from
and about the premises as well as all tools, appliances,
construction equipment and machinery and surplus
materials CONTRACTOR shall leave the site clean and
ready for occupancy by OWNER at Substantial
Completion of the Work CONTRACTOR shall restore to
original condition all property not designated for alteration
by the Contract Documents
618 CONTRACTOR shall not load nor permit any par
of any structure to be loaded in any manner that will
endanger the structure nor shall CONTRACTOR subject
any part of the Work or adjacent property to stresses or
pressures that will endanger it
Record Documents
FaCDC GENERAL. CONDI nONs 191o.8 (1990 Ed1um)
w/ CITY OF FORT COLLINS MODIFICATIONS (REV 42000)
619 CONTRACTOR shall maintain in a safe place at
the site one record copy of all Drawings, Specifications,
Addenda, Written Amendments, Change Orders, Work
Change Drrectives, Field Orders and written
Interpretations and clarifications (Issued pursuant to
paragraph 9 4) in good order and annotated to show all
changes made during construction. These record
documents together with all approved Samples and a
counterpart of all approved Shop Drawings will be
available to ENGINEER for reference Upon completion
of the Weak, and prior to release of final oavmem these
record documents, Samples and Shop Drawings will be
delivered to ENGINEER for OWNER
Safety andProteenon
620 CONTRACTOR shall be responsible for
mM1umg, maintaining and supervising all safety
precautions and programs in connection with the Work
CONTRACTOR shall take all necessary precautions for
the safety of� and shall provide the necessary protection to
prevent damage injury or loss to
6201 all persons on the Work site orwho may be
affected by the Work
6202 all the Work and materials and equipment to
be incorporated therein, whether in storage on or off
the site and
6 20 3 other property at the site or adjacent thereto
including trees, shrubs, lawns walllm pavements,
roadways, structures, utilities and Underground
Facilities not designated for removal, relocation or
replacement in the course of construction
CONTRACTOR shall comply with all applicable Laws
and Regulations of any public body having jurisdiction for
safety of persons or property or to protect them from
damage, injury or loss and shall erect and maintain all
necessary safeguards tot such safety and protection
CONTRACTOR shall notify owners of adjacent property
and of Underground Facilities and utility owners when
prosecution of the Work may affect them and shall
cooperate with them in the protection, removal relocation
and replacement of their property All damage injury or
loss to any property referred to in paragraphs 6 20 2 or
6 20 3 caused, directly or indirectly in whole or in part, by
CONTRACTOR any Subcontractor Supplier or any
other person or organization directly or indirectly
employed by any of them to perform or furnish any of the
Work or anyone for whose acts any of them may be liable
shall be remedied by CONTRACTOR (except damage or
loss attributable to the fault of Drawings or Specmficanons
or to the acts or omissions of OWNER or ENGINEER or
ENGINEERS Consultant or anvone employed by any of
them or anyone for whose acts any of them may be liable
and not attributable directly or indirectly in whole or in
Part, to the fault or negligence of CONTRACTOR or any
Subcontractor Supplier or other person or organization
directly or indirectly employed by any of them)
CONTRACTORS duties and responsibilities for the safety
and protection of the Work shall commue until such time
as all the Work is completed and ENGINEER has issued a
15
notice to OWNER and CONTRACTOR in accordance
with paragraph 14 13 that the Work is acceptable (except as
otherwise expressly provided in connection with
Substantial Completion)
6.21 S5*0 Representative
CONTRACTOR shall desigtiete a quahfied and
experienced safety representative at the site whose duties
and responsibilities shall be the prevention of accidents and
the maintaining and supervising of safety precautions and
programs
Hazard Communication Programs
622 CONTRACTOR shall be responsible for
coordinating any exchange of material safety data sheets or
other hazard communication Information required to be
made available to or exchanged between or among
employers at the site in accordance with Laws or
Regulations
Emergencies
623 In emergencies affecting the safety or protection of
persons or the Work or property at the site or adjacent
thereto CONTRACTOR, without special insuuction or
authonmtlon from OWNER or ENGINEER is obligated to
act to prevent threatened damage mjury or loss
CONTRACTOR shall give ENGINEER prompt wnuen
nonce if CONTRACTOR believes that any significant
changes in the Work or variations from the Contract
Documents have been caused thereby If ENGINEER
determines that a change in the Contract Documents is
required because of the action taken by CONTRACTOR in
response to such an emergency a Work Change Directive
or Change Order will be Issued to document the
consequences of such action-
6 24 Shop Drawings and Samples
6 24 1 CONTRACTOR shall submit Shop Drawings
to ENGINEER for review and approval in accordance
with the accepted schedule of Shop Drawings and
Sample submittals (see paragraph 2 9) All submittals
wIll be identified as ENGINEER may require and in
the number of copies specified in the General
Requirements The data shown on the Shop Drawings
will be complete with respect to quantities
dimensions specified performance and design criteria
materials and similar data to show ENGINEER the
materials and equipment CONTRACTOR proposes to
provide and to enable ENGINEER to review the
mformation for the limited purposes required by
paragraph 6 26
6 24 2 CONTRACTOR shall also submR Samples to
ENGINEER for review and approval in accordance
with said accepted schedule of Shop Drawings and
Sample submittals Each Sample will be identified
clearly as to material Supplier pertinent data such as
catalog numbers and the use for which intended and
otherwise as ENGINEER may require to enable
ENGINEER to review the submittal for the limited
16 EICDC GENERAL CONDITIONS 19105 (1990 ENtim)
w/ CITY OF FORT COLLINS MODIFICATIONS (REV 42000)
purposes required by paragraph 6 26 The numbers
of each Sample to be submitted will be as specified in
the Specifications
625 Submittal Procedures
6 25 1 Before submitting each Shop Drawing or
Sample CONTRACTOR shall have determined and
verified
62511 all field measurements, quantities,
dunenvons specified performance cntena
uatallat' requirements, materials, catalog
numbers and similar information with respect
thereto
62512 all materials with respect to intended
use fabrication, sluppppiing handling storage
assembly and Installation pertammg to the
performance of the Work and
62513 all Information relative to
CONTRACTORS sole respotaibrhnes in respect
of means, methods techniques, sequences and
procedures of construction and safety precautions
and programs incident thereto
CONTRACTOR shall also have reviewed and
coordinated each Shop Drawing or Sample with other
Shop Drawings and Samples and with the
requirements of the Work and the Contract
Documents
6 25 2 Each submittal will bear a stamp or specific
written indication that CONTRACTOR has satisfied
CONTRACTORS obligations under the Contract
Documents with respect to CONTRACTORS review
and approval of that submittal
6 25 3 At the time of each submrsvon,
CONTRACTOR shall give ENGINEER specific
written notice of such vanatims if any that the Shop
Drawing or Sample submitted may have from the
requirements of the Contract Documents, such notice
to be in a written commumWim separate from the
submittal and in addition, shall cause a specific
notation to be made on each Shop Drawing and
Sample submitted to ENGINEER for review and
approval of each siuh variation
626 ENGINEER will review and approve Shop
Drawings and Samples in accordance with the schedule of
Shop Drawings and Sample submittals accepted by
ENGINEER as required by paragraph 2 9 ENGINEERS
review and approval will be only to determine if the items
covered by the submittals will after Installation or
incorporation in the Work conform to the information
given in the Contract Documents and be compatible with
the design concept of the completed Project as a
tunctionmg whole as indicated by the Contract
Documents ENGINEERS review and approval will not
extend to means methods techniques sequences or
procedures of construction (except where a particular
means method, technique sequence or proi.edure of
construction is specifically and expressly called for by the
Contract Documents) or to safety precautions or programs
incident thereto The review and approval of a separate
item as such will not Indicate approval of the assembly in
which the item functions CONTRACTOR shall make
corrections required by ENGINEER, and shall return the
required number of coriected copies of Shop Drawings and
submit as required new Samples for review and approval
CONTRACTOR shall direct specific attention in writing to
revistam other than the corrections called for by
ENGINEER on previous submittals
627 ENGINEERS review and approval of Shop
Dmwmgs or Samples shall not relieve CONTRACTOR
from responsibility for any variation from the requirements
of the Contract Documents unless CONTRACTOR has in
writing called ENGINEERS attention to each such
variation at the time of submission as required by
paragraph 6 25 3 and ENGINEER has given written
approval of each such variation by a specific written
notation thereof incorporated in or accompanying the Shop
Drawing or Sample approval nor will any approval by
ENGINEER relieve CONTRACTOR from responsibility
for conrplying with the requirements of paragraph 6 25 1
6 28 Where a Shop Drawing or Sample is required by
the Contract Documents or the schedule of Shop Drawing
and Sample submissions accepted by ENGINEER as
required by paragraph 29 any related Work performed
prior to ENGINEERS review and approval of the pertinent
submittal will be at the sole expense and responsibility of
CONTRACTOR
Conanumg the Work
629 CONTRACTOR shall tarty on the Work and
adhere to the progress schedule during all disputes or
disagreements with OWNER No Work shall be delayed or
postponed pending resolution of any disputes or
dlsagreements, except as permitted by paragraph 15 5 a as
OWNER and CONTRACTOR may otherwise agree in
writing
630 CONTRACTOR s Genaal Warranty and
Guarantee
6 30 1 CONTRACTOR warrants and guarantees to
OWNER ENGINEER and ENGINEERS Consultants
that all Work will be in accordance with the Contract
Documents end will not be defective
CONTRACTORS warranty and guarantee hereunder
excludes defects a damage caused by
63011 abuse, modification or Improper
maintenance or operation by persons other than
CONTRACTOR- Subcontractors or Suppliers or
6301 2 normal wear and tear under normal
usage
6 30 2 CONTRACTORS obligation to perform and
complete the Work in accordance with the Contract
Documents shall be absolute None of the following
will constitute an acceptance of Work that is not in
EJCDC(ENRAL CONDITIONS 1910.8 (1990 Edam)
w/ CITY OF FORT COLLINS MODIFICATIONS (REV 412000)
accordance with the Contract Documents or a release
of CONTRACTORS obligation to perform the Work
in accordance with the Contract Documents
6 30 2 1 observations by ENGINEER
63022 recommendation of any progress or
fmal payment by ENGINEER
63023 the issuance of a certificate of
Substantial Completion or any payment by
OWNER to CONTRACTOR under the Contract
Documents
63024 use or occupancy of the Work or any
part thereof by OWNER
63025 any acceptance by OWNER or any
failure to do so
63026 any review and approval of a Shop
Drawing or Sample submittal a the issuance of a
notice of acceptability by ENGINEER pursuant
to paragraph 1413
63027 any mspection, test or approval by
others or
63028 any correction of defective Work by
OWNER
/nd mizifleanon
631 To the fullest extent permitted by Laws and
Regulations, CONTRACTOR shall indemnify and hold
harmless OWNER, ENGINEER, ENGINEERS
Consultants and the officers, directors, employees, agents
and other consultants of each and any of them from and
against all clans, costs, losses and damages (including
but not limited to all fees and charges of engineers,
architects, attorneys and other professionals and all court
or arbitration or other dispute resolution costs) caused by
ansrng out of or resulting from the performance of the
Work provided that any such claim cost, loss or damage
(1) is attributable to bodily mlury sickness disease a
death, or to injury to or destruction of tangible property
(other than the Work itself) including the loss of use
resulting therefrom and (it) is caused in whole or in part
by any negligent act or omission of CONTRACTOR, any
Subcontractor any Supplier any person or organization
directly or indirectly employed by any of them to perform
or famish any of the Work or anyone for whose acts any
of them may be liable regardless of whether or not caused
m part by any negligence or omission of a person or entity
in unified hereunder a whether Lability is imposed
upon such indemnified party by Laws and Regulations
regardless of the negligence of any such person or entity
632 In any and all claims against OWNER or
ENGINEER or any of their respective consultants, agents
officers directors or employees by any employee (or the
survivor or personal representative of such employee) of
CONTRACTOR any Subcontractor any Supplier any
person or organization directly or indirectly employed by
17
any of them to perform or furnish any of the Work or
anyone for whose acts any of then may be liable the
mdemmficanon obligation under paragraph 631 shall not
be hutted in any way by any Imitation on the amount n
type of damages, conpeaatron or benefits payable by or
for CONTRACTOR or arty such Subcontractor Supplier or
other person or organization under workers compensation
acts, disability benefit acts or other employee benefit acts
633 The indemnification obligations of
CONTRACTOR under paragraph 631 shall not extend to
the liability of ENGINEER and ENGINEERS Consultants,
Officers directors, employees or agents caused by the
professional negligence errors or omissions of any of them
Sit val ofONigahons
634 All representations, mdemmfications, warranties
and guarantees made m, required by Or given in accordance
with the Contract Documents, as well as all contimmig
obligations indicated in the Contract Documents, will
survwe final payment, completion and acceptance of the
Work and termination or completion of the Agreement
ARTICLE 7 OTBER WORK
Related Work at Site
71 OWNER may perform other work related to the
Project at the site by OWNERS own forces, or let other
direct contracts therefor which shall contain General
Conditions San flar to these or have other work performed
by utility owners If the fact that such other work its to be
performed was not noted in the Contract Documents, than
(1) written nonce thereof will be given to CONTRACTOR
Prior to starting any such other work and
(u) CONTRACTOR may make a clan therefor as
provided in Articles 11 and 12 of CONTRACTOR believes
that such performance will involve additional expense to
CONTRACTOR a requires additional time and the parties
are unable to agree as to the amount or extent thereof
72 CONTRACTOR shall afford each other contractor
who Is a party to such a direct contract and each utility
owner (and OWNER, If OWNER is performing the
additional work with OWNERS employees) proper and
safe access to the site and a reasonable opportunity for the
introduction and storage of materials and equipment and
the execution of such other work and shall properly connect
and coordinate the Work with theirs Unless otherwise
Provided in the Contract Documents, CONTRACTOR
shall do all cutting, fitting and patching of the Work that
may be required to make its several parts come together
properly and integrate with such other work
CONTRACTOR shall not endanger any work of others by
cutting excavating or otherwise altering their work and
will only cut or alter thew work with the written consent of
ENGINEER and the others whose work will be affected
The duties and yes bylines of CONTRACTOR under
this paragraph are of�e benefit of such utility owners and
Other contactors to the extent that there are comparable
18 EJCDCGENERA CONDITIONS 1910-8(1990 E&.)
w/ CITY OF FORT COLLINS MODIFICATIONS (REV 42000)
Provisions for the benefit of CONTRACTOR in said
direct contracts between OWNER and such utility owners
and other contractors
73 If the proper execution or results of any part of
CONTRACTORS Work depends upon work perforated
by others under thus Article 7 CONTRACTOR shall
inspect such other work and promptly report to
ENGINEER in writing any delays, defects or deficiencies
in such other work that render it unavailable or unsurtable
for the proper execution and results of CONTRACTORs
Wok CONTRACTORs failure so to report will
constitute an acceptance of such other wok as fit and
Proper for integration with CONTRACTORS Work
except for latent or nonapparent defects and deficiencies
in such other work
Coorrbnahon
74 If OWNER contracts with others for the
performance of other work on the Project at the site the
following will be set forth in Supplementary Conditions
741 the person, firm or corporation who will have
authority and responsibility for coordination of the
activities among the various prime contractors will be
identified
742 the specific matters to be covered by such
authority and responsibility will be itemized and
743 the extent of such authority and
responsibnbnes will be provided
Unless otherwise provided in the Supplementary
Conditions OWNER shall have sole authority and
responsibility in respect of such coordination
ARTICLE ti OWNERS RESPONSIMLITIES
8 1 Except as otherwise provided in these Geneml
Conditions, OWNER shall issue all communications to
CONTRACTOR through ENGINEER
82 In case of termination of the employment of
ENGINEER, OWNER shall appoint an engineer against
whose status under the Contract Documents shall be that
of the former ENGINEER
83 OWNER shall furnish the data required of
OWNER under the Contract Documents promptly and
shall make payments to CONTRACTOR promptly when
they are due as provided in paragraphs 14 4 and 14 13
84 OWNERs duties in respect of providing lands
and easements and providing engineering surveys to
establish reference points are set forth in paragraphs 4 1
and 4 4 Paragraph 4 2 refers to OWNER s identifying
and making available to CONTRACTOR copies of
reports of explorations and tests of subsurface conditions
at the site and drawings of physical conditions in existing
structures at or contiguous to the site that have been utilized
by ENGINEER in preparing the Contract Documents
_
86 OWNER is obligated to execute Change Orders as
indicated in paragraph 10 4
87 OWNERs responsibility in respect of certain
inspections, tests and approvals is set forth in
paragraph 13 4
88 In connection with OWNERS right to stop Work or
suspend Work, we paragraphs 13 10 and 15 1
Paragraph152 deals with OWNERS right to terminate
Services of CONTRACTOR under certain circumstances
89 The OWNER shall not supervise direct or have
control or authority over nor be responsible for
CONTRACTORS means, methods, techniques, sequences
or procedures of construction or the safety precautions and
programs incident thereto or for any failure of
CONTRACTOR to comply with Laws and Regulations
applicable to the furnishing or performance of the Work
OWNER will not be responsible for CONTRACTORS
failure to perform or furnish the Work in accordance with
the Contract Documents
ARTICLE 9—ENGINEER S STATUS DURING
CONSTRUCTION
OIFNER s Representarve
91 ENGINEER will be OWNERS representative
during the construction period The dunes and
responsibilities and the limitations of authority of
ENGINEER as OWNERS representative during
construction are set forth in the Contract Documents and
shall not be extended without written consent of OWNER
and ENGINEER
Visits to &te
92 ENGINEER will make visits to the site at intervals
appropriate to the various stages of construction as
ENGINEER deems necessary in order to observe as an
experienced and qualified design professional the progress
EJCDC (FNERAL CONDITIONS I910 R (1990 E&IM)
w/ CITY OF FORT COLLINS MODIFICATIONS (REV 42000)
that has been made and the quahty of the various aspects
of CONTRACTORS executed Work Based on
information obtained during such visits and observations,
ENGINEER will endeavor for the benefit of OWNER to
determine in general if the Work is proceeding in
accordance with the Contract Documents ENGINEER
will not be required to make exhaustive or continuous on.
site inspections to check the quality or quantity of the
Work ENGINEERS efforts will be directed toward
Providing fix OWNER a greater degree of confidence that
the completed Work will conform generally to the
Contract Documents On the basis of such visits and on
site observations, ENGINEER will keep OWNER
informed of the progress of the Work and will endeavor to
guard OWNER against defective Work ENGINEERS
visits and on -site observations are subject to all the
Initiations on ENGINEERS authority and responsibility
set forth in paragraph 9 13 and particularly but without
Initiation, awn or as a result of ENGINEERs on site
visits or observations of CONTRACTORS Work
ENGINEER will not supervise direct, control a have
authority over or be responsible for CONTRACTOR,
means, methods techniques, sequences or procedures of
construction, or the safety precautions and programs
incident thereto or for any failure of CONTRACTOR to
comply with Laws and Regulations applicable to the
furnishing or performance of the Work
Protect Representative
93 If OWNER and ENGINEER agree ENGINEER
will furnish a Resident Project Representative to assist
ENGINEER in providing more continuous observation of
the Work The resporabilines and authority and
limitations thereon of any such Resident Project
Representative and assistants will be as provided in
paragraphs93 and 913 ^nclis the
Canditiens of these General Conditions Iit OWNER
designates another representative or agent to represent
OWNER at the site who is not ENGINEERS Consultant
agent or employee the responsibilities and authority and
limitations thereon of Such other person will be as
Provided in the SuPplanentain, Garmlittens oamaranh 9 3
931 The Representatives deahTs in matters
peltaininn to the onsite work will m ceneml be wdh
the ENGINEER and CONTRACTOR But,the
Representative will keep the OWNER properly
advised about such matters The Remesentanves
dealm¢s with subcontractors will only be through or
with the full knowledge and approval of the
CONTRACTOR
932 Duties and Responsibilities Representative
will
9321 Schedules Review the progress
19
schedule and other schedules mevared by the
CONTRACTOR and consult with the
ENGINEER corionti rig acceptability
9 3 2 2 Conferences and Meeting Attend
meeting with the CONTRACTOR such es
econstruction conferences ms me
and other sob conferences ap prepare and
arculate copses of minutes of meetings
9 3 2 3 Liaison
9 3 2 3 1 Serve as ENGINEERS list
with CONTRACTOR work m m=ipallv
though CONTRACTORS mMixtendent to
assist the CONTRACTOR in understandnm
the ContractDoctInents
9 3 2 3 2 Assist in obtain= from OWNER
additional details or mfomratiop when
required for mocer execution of the Work
93233 Advise the ENGINEER and
CONTRACTOR of the commencement of
airy Work requiring a 4hnp Drawuig or
sample submission if the submission has not
lien aomoved by the ENGINEER
9 3 2 4 Review of Work. Retection of Defective
Work Inspections and Tests
9 3 2 4 1 Conduct on site observations of
the Work m ess to assist the ENGINEER
in detemwnng t the Work is moceedpo in
accordance with the Contract Docmnents
9 3 2 4 3 Accomwny vis�ectors
represent pubhc m other agencies having
lunsdicuon over the Project record the results
of these lnscecuons and report to the
ENGINEER
9 3 2 5 Interpretation of Contract
Documents Report to ENGINEER when
clantications and paermetations of the Contmct
Documents are needed and transmit to
CONTRACTOR clarification and interpmtation
of the Contract Documents as issued by the
ENGINEER
9326 Modifications Consider and
evaluate CONTRACTORS suggestions for
20 EICDC GENERAL CONDi TIONS 1910-a(1990 Edibm)
w/ CITY OF FORT COLLINS MODIFICATIONS (REV 42000)
modification in Drawings or Smcnfrcetiors and
report these recommendations to ENGINEER
Accurately bansntt to CONTRACTOR
decvwons issued by the ENGINEER
9 3 2 7 Records
9 3 2 8 Reports
9 3 2 8 1 Furnish ENGINEER periodic
reportj% as required of the progress of the
Work end of the CONTRACTORS
comnhance with the progress schedule and
schedule of shop Drawing and sample
submittals
9 3 2 8 2 Consult with ENGINEER m
advance of scheduling maim tcs s
uMecuons or start of important phases of the
Work
9 3 2 8 3 Draft proposed Change Orders
and Work Directive Changes, obtainin
backup material from the CONTRACTOR
and recommend to ENGINEER Change
Orders, Work Directive Changes and field
orders
932 84 Report immediately to
ENGINEER and OWNER the occurrence of
any accident
9329 Payment Requests Review applications
fin ymem with CONTRACTOR for comphance
with the established mocedure for their
submission and forward with recommendation to
ENGINEER noting parttcularI the relatioristuo of
the ravment requested to the schedule of values
Work compleed and materials and eqm era
delivered at the site but not mcomorated mTthe
Work
9 3 2.10 Completion
932101 Befon ENGINEER Issues a
Certificate of Substantial Completion submit
to CONTRACTOR a list of observed items
re unmg correction or completion
932102 Conduct final inspection in the
company of the ENGINES OWNER and
CONTRACTOR and oreoere a fire] list of
items to be corrected or completed
932103 Observe that all items on the
final lest have been corrected or completed and
make ncommeodations to ENGINEER
concett»ng acceptance
9 3 3 Limitation of Authority The Representative shall
not
9 3 3 1 Authorize am deviations from the
Contract Documents or accept any substitute
materials or egmnment unless autl+Anud by the
ENGINEER
9 3 3 2 Exceed lanitations of ENGINEERS
auihonty as set forth in the Contract Documents
9 3 3 3 Undertake any of the responsibilities
of the CONTRACTOR. Subcontractors or
CONTRACTOR S superintendent
9334 Advise on or issue directions relative
to, or assume control over any aspect of the
means, methods. mchmgues sequences or
procedures for construction unless such is
smifrcally called for in the Contract Documents
9335 Advise on or issue directions
regarding or assume control over safes
precautions and programs in connections with the
Work
Q 3 3 6 Accept Shop Drawings or sample
submittals from anyone other than the
I'ONIR UI OR
9337 Authonze OWNER to occupy the
Work in whole or in part
9 3 3 8 Pelncipate in specialized field or
laboratory tests or inspections conducted by others
extent as specifically authonzed by the
ENGINEER
Clanfrcanons and Interpretations
94 ENGINEER will issue with reasonable promptness
such written clanficatlons or interpretations of the
EJCDC GENERAL CONDITIONS i910-s (1990I dinar)
w/ CITY OF FORT COLLINS MODIFICATIONS (REV 42000)
requmemems of the Contract Documents (in the form of
Drawings or otherwise) as ENGINEER may determine
necessary which shall be consistent with the intent of and
reasonably inferable from the Contract Documents Such
written clarifications and interpretations will be binding on
OWNER and CONTRACTOR If OWNIIt or
CONTRACTOR believes that a written clarification or
interpretation justifies an adjustment in the Contract price
or the Contract Times and the parties are unable to agree
to the Mount or extent thereof if any OWNER or
CONTRACTOR may make a written clam therefor as
provided in Article 11 or Article 12
Authorized Vanationsin Work
95 ENGINEER may authorize manor variations in
the Work from the requirements of the Contract
Documents which do not involve an a ustment in the
Contract Price or the Contract Times and are compatible
with the design concept of the completed Project as a
functioning whole as indicated by the Contract
Documents These maybe accomplished by a Field Order
and will be binding on OWNER and also on
CONTRACTOR who shall perform the Work urvolved
promptly If OWNER or CONTRACTOR beheves that a
Field Orderjustifies an adjustment in the Contract Price or
the Contract Times and the parties are unable to agree as
to the amount or extent thereof OWNER or
CONTRACTOR may make a written claim therefor as
provided in Article 11 or 12
Rejecting DefeJdrve Work.
96 ENGINEER will have authority to disapprove or
reject Work which ENGINEER believes to be defective
or that ENGINEER believes will not produce a completed
Project that conforms to the Contract Documents or that
will prejudice the integrity of the design concept of the
completed Project as a functioning whole as indicated by
the Contract Documents ENGINEER will also have
authority to require special inspection or testing of the
Work as provided in paragraph 13 9 whether or not the
Work Is fabricated, installed or completed
Shop Draivwgs Change Orders and Payments
97 In connection with ENGINEERs authority as to
Shop Drawings and Samples we paragraphs 6 24 through
6 28 inclusive
98 In connection with ENGINEERS authority as to
Change Orders we Articles 10 11 and 12
99 In connection with ENGINEERs authority as to
Applications for Payment we Article 14
Determinations for Unit Prices
910 ENGINEER will determine the actual quantities
and classifications of Unit Price Work performed by
CONTRACTOR ENGINEER will review with
CONTRACTOR the ENGINEERS preliminary
determmatnons on such matters before rendering a written
decision thereon (by recommendation of an Application
21
The Contract Documents and Construction Drawings may be examined online at
1 City of Fort Collins BuySpeed https //secure2 fcgov com/bso/login jsp
Bids will be received as set forth in the Bidding Documents
The Work is expected to be commenced within the time as required by Section
2 3 of General Conditions Substantial Completion of the Work is required as
specified in the Agreement
The successful Bidder will be required to furnish a Performance Bond and a
Payment Bond guaranteeing faithful performance and the payment of all bills
and obligations arising from the performance of the Contract
No Bid may be withdrawn within a period of forty-five (45) days after the date
fixed for opening Bids
The OWNER reserves the right to reject any and all Bids and to waive any
informalities and irregularities therein
Bid security in the amount of not less than 5% of the total Bid must accompany
each Bid in the form specified in the Instructions to Bidders
Sales Prohibited/Conflict of Interest No officer employee or member of City
Council shall have a financial interest in the sale to the City of any real
or personal property, equipment material supplies or services where such
officer or employee exercises directly or indirectly any decision -making
authority concerning such sale or any supervisory authority over the services
to be rendered This rule also applies to subcontracts with the City
Soliciting or accepting any gift gratuity favor entertainment kickback or
any items of monetary value from any person who has or is seeking to do
business with the City of Fort Collins is prohibited
City of Fort Collins Q
By 0" W-
4J es B 0 Neill II CPPO FNIGP
u chasing & Risk Management Director
Rev 10/20/07 Section 00020 Page 2
for Paymentor otherwise) ENGINEERS written decision
thereon will be final and binding upon OWNER and
CONTRACTOR, unless, within ten days after the date of
any such decision, either OWNER or CONTRACTOR
delivers to the other and to ENGINEER written notice of
intention to appeal from ENGINEERS decision and. (I) an
appeal from ENGINEERS decisum is taken within the time
limits and in accordance with the procedures set forth in
Exhibit GC A, Dispute Resolution Agreement entered
unto between OWNER and CONTRACTOR pursuant to
Article 16 or (it) of no such Dispute Resolution Agreement
has been entered into a formal proceeding is Instituted by
the appealing party in a forum of competent jurisdiction to
exercise Such rights or remedies as the appealing party may
have with respect to ENGINEERS decision, unless
otherwise agreed in writing by OWNER and
CONTRACTOR Such appeal will not be subject to the
procedures of paragraph 911
Decisions on &"tes
911 ENGINEER will be the Initial interpreter of the
requnemenm of the Contract Documents and judge of the
acceptability of the Work thereunder Claims, disputes and
other matters relating to the acceptability of the Work or
the interpretation of the requirements of the Contract
Documents pertaining to the performance and furnishing of
the Work and claims under Articles 11 and 12 in respect of
changes in the Contract Price or Contract Tunes will be
refined initially to ENGINEER in writing with a request
for a formal decision in accordance with tins paragraph
Written notice of each such claim dispute or other matter
will be delivered by the claumem to ENGINEER and the
other party to the Agreement promptly (but in no event
later then ihuty days) after the start of the occurrence or
event giving rise thereto and written supporting data will
be submitted to ENGINEER and the other party within
so* days after the start of such occurrence or event unless
ENGINEER allows an additional period of time for the
submission of additional or more accurate data in support
of such claim dispute or other matter The opposing party
shall submit any response to ENGINEER and the claimant
within thirty days after receipt of the claimants last
submittal (unless ENGINEER allows additional time)
ENGINEER will render a formal decision in writing within
flinty days after receipt of the opposing party s submittal if
any in accordance with this paragraph ENGINEERS
written decision on such claim dispute or other matter will
be final and binding upon OWNER and CONTRACTOR
unless (I) an appeal from ENGINEERS decision is taken
within the time limits and in accordance with the
procedures set forth in EXHIBIT GGA, Dispute
Resolution Agreement entered into between OWNER and
CONTRACTOR pursuant to Article 16 or (u) of no such
Dispute Resolution Agreement has been entered into a
written notice of intention to appeal from ENGINEERS
written decision is delivered by OWNER or
CONTRACTOR to the other and to ENGINEER within
dirty days after the date of such decision and a formal
Proceeding Is instituted by the appealing party in a forum of
competent jurisdiction to exercise such rights or remedies
as the appealing party may have with respect to such claim
dispute or other matter in accordance with applicable Laws
and Regulations within sixty days of the date of such
22 EICDCGENERAL CONDITIONS 19I0A(1990 Ednm)
w/ CITY OF FORT COLLINS MODIFICATIONS (REV 42000)
decision, unless otherwise agreed in venting by OWNER
and CONTRACTOR
912 When functioning as interpreter and judge under
paragraphs 9 10 and 911 ENGINEER will not show
partiality to OWNER or CONTRACTOR and will not be
liable in connection with any interpretation or decision
rendered in good faith in such capacity The rendering of
a decision by ENGINEER pursuant to paragraphs 910 or
9 11 with respect to any such claim dispute or other
matter (except any which have been waived by the making
or acceptance of final payment as provided in
paragraph 14 15) will be a condition precedent to any
exercise by OWNER or CONTRACTOR of such rights or
remedies as either may otherwise have under the Contract
Documents or by Laws or Regulations in respect of any
such claim dispute or other matter-puEsamnaAine(a--lg
913 Lmdanons on ENGINEER's Authority and
Responsibilities
9 13 1 Neither ENGINEERS authority or
responsibility under tins Article 9 or undo any other
provision of the Contract Documents nor any decision
made by ENGINEER in good faith either to exercise
or not exercise such authority or responsibility or the
undertaking exercise or performance of any authority
or responsibility by ENGINEER shall cents, impose
or give rise to any duty owed by ENGINEER to
CONTRACTOR, any Subcontractor any Supplier
any other person or organization, or to any surety for
or employee or agent of any of then
9 13 2 INGINEER will not supervise direct,
control or have authority over or be responsible for
CONTRACTORS means, methods techniques,
sequences or procedures of construction, or the safety
Precautions and programs Incident thereto or for any
failure of CONTRACTOR to comply with Laws and
Regulations applicable to the furnishing or
performance of the Work ENGINEER will not be
responsible for CONTRACTORs failure to perform
or famish the Work in accordance with the Contract
Documents
9 13 3 ENGINEER will not be responsible for the
acts or omissions of CONTRACTOR or of wry
Subcontractor any Supplier or of any other person or
organization performing or furnishing any of the
Work
9134 ENGINEER s review of the final Application
for Payment and accompanying documentation and
all maintenance and operating instructions, schedules
guarantees, Bonds and certificates of Inspection, tests
and approvals and other documentation required to be
delivered by paragraph 1412 will only be to
determine generally that their content complies with
the requirements of and in the case of certificates of
inspections, tests and approvals that the results
certified indicate compliance wnth, the Contract
Documents
9 13 5 The limitations upon authority and
responsibility set forth in this paragraph 9 13 shall also
apply to ENGINEERS Consultants, Resident Project
Representative and assistants
ARTICLE 10—CHANGES IN THE WORK
101 Without invalldatmg the Agreement and without
notice to any surety OWNER may at any time or from
time to tune, order additmns deletions or revisions in the
Work Such additions, deletions a revisions will be
authorized by a Written Amaidrient, a Change Order Or a
Work Change Directive Upon receipt of any such
document, CONTRACTOR shall promptly proceed with
the Work involved which will be performed under the
applicable conditions of the Contract Documents (except as
otherwise specifically provided)
102 If OWNER and CONTRACTOR are unable to
agree as to the extent, if any of an adjustment in the
Contract Price Or an adjustment of the Contract Times that
should be allowed as a result of a Work Change Directive
a claim may be made therefor as provided in Article 11 or
Article 12
10 3 CONTRACTOR shall not be entitled to an increase
in the Contract Price a an extension of the Contact Tunes
with respect to any Work performed that is not requued by
the Contract Documents as amended, modified and
supplemented as provided in paragraphs 3 5 stun 3 6 except
in the case of an emergency as provided in paragraph 6 23
or in the case of uncovering Work m provided in
paragraph 13 9
104 OWNER and CONTRACTOR shall execute
appropriate Change Orders recommended by ENGINEER
(or Written Amendments) covering
1041 changes in the Work which are (1) Ordered
by OWNER pursuant to paragraph 10 1 (m) required
because of acceptance of defective Work under
paragraph 13 13 a correcting defedrve Work under
paragraph 13 14 Or (m) agreed to by the parties
1042 changes in the Contract Price a Contract
Times which are agreed to by the parties and
1043 changes in the Contract Price or Contract
Times which embody the substance of any written
decision rendered by ENGINEER pursuant to
paragraPh 9 11
provided that, in lieu of executing any such Change Order
an appeal may be taken from any such decision in
accordance with the provisions of the Contract Documents
and applicable Laws and Regulations, but during any such
appeal CONTRACTOR shall car
on the Work and
ule
adhere to the progress schedas proi ided in
paragraph 6 29
10 5 If notice of any change affecting the general scope
Of the X%ork Or the provisions of the Contract Documents
E1CDC GENERAL CONDITIONS 1910.9 (1990 Edihm)
w/ CITY OF FORT COLLINS MODIFICATIONS (REV 42000)
(including but not limited to Contract Price Or Contract
Times) its required by the provisions of any Bond to be
given to a surety the giva� of any such notice will be
CONTRACTORS responsibility and the amount of each
applicable Bond will be adjusted accordingly
ARTICLE 11—CHANGE OF CONTRACT PRICE
111 The Contract Price constitutes the total
compensation (subject to authorized adjustments) payable
to CONTRACTOR for performing the Work All dukes,
responsibilities and obbgattora assigned to or undertaken
by CONTRACTOR shall be at CONTRACTORS expense
without change in the Contract Price
112 The Contract Price may only be changed by a
Change Order Or by a Written Amendment Any claim
for an adjustment in the Contract Price shall be based on
written notice delivered by the party making the clam to
the other party and to ENGINEER promptly (but in no
event hater than thirty days) after the start of the
occurrence or event giving rise to the claim and stating the
general nature of the claim Notice of the amount of the
clam with supporting data shall be delivered within sixty
days after the start of such occurrence or event (unless
ENGINEER allows additional time for claimant to submit
additional a more accurate data in support of the claim)
and shall be accompanied by claimants written statement
that the adjustment claimed covers all known amounts to
which the claimant is entitled as a result of said
occurrence or event All clams for adjustment in the
Contract Price shall be determined by ENGINEER in
accordance with paragraph 911 if OWNER and
CONTRACTOR cannot otherwise agree on the amount
involved No claim for an adjustment in the Contract
Price will be valid if not submitted in accordance with this
paragraph 112
113 The value of any Work covered by a Change
Order or of any claim for an adjustment in the Contract
Price will be determined as follows
I 1 3 1 where the Work involved is covered by unit
prices contained in the Contact Documents by
application of such unit prices to the quantities of the
items involved (subject to the provisions of
23
paragraphs 119 1 through 119 3 inclusive)
I1 32 where the Work involved is not covered by
unit prices contained in the Contract Documents, by a
mutually agreed payment basis, including lump sum
(which may include an allowance for overhead and
profit not necessanly in accordance with
paragraph 116 2)
113 3 where the Work involved is not covered by unit
prices contained in the Corinact Documents and
agreement to a lump sum is not reached under
paragraph 113 2 on the basis of the Cost of the Work
(determined as provided in paragraphs 114 and 11 5)
plus a CONTRACTORS fee for overhead and profit
(determined as provided in paragraph I 1 6)
Cost of the Work
114 The tens Cost of the Work means the sum of all
costs necessarily mounted and pmd by CONTRACTOR in
the proper performance of the Work Except as otherwise
may be agreed to in writing by OWNER, such casts shall
be in amounts no higher than those prevailing in the
locahty of the Project, shall Include only the following
items and shall not include any of the costs itemized in
paragraph 115
1141 Paroll costs for employees in the direct
employ of CONTRACTOR in the performance of the
Work under schedules of job classifications agreed
upon by OWNER and CONTRACTOR Such
employees shall include without lunitation
superintendents, foremen and other personnel
employed full time at the site Payroll costs for
employees no employed full time on the Work shall
be apportioned on the basis of their time spent on the
Wok Payroll costs shall txskuds,butnet be limited to -
salaries and wages plus the cost of fringe benefits
which shall include Social security contnbutions,
unemployment, excise and payroll taxes, workers
conperisation, health and-reurema benefits,
applicable thereto
The expenses of performing Work after regular
working hours, on Saturday Sunday or legal holidays,
shall be Included in the above to the extent authorized
by OWNER
11 42 Cost of all materials and equipment furnished
and meorpomted in the Work including costs of
transportation and storage thereof and Suppliers field
services required in connection therewith All cash
discounts shall accrue to CONTRACTOR unless
OWNER deposits funds with CONTRACTOR with
which to make payments in which case the cash
discounts shall accrue to OWNER All trade
discounts rebates and refunds and returns from sale of
surplus materials and equipment shall accrue to
OWNER, and CONTRACTOR shall make provisions
so that they may be obtained
1143 Payments made by CONTRACTOR to the
Subcontractors for Work performed or f i mshed by
Subcontractors If required by OWNER,
24 EICDC GENERAL CONDITIONS 19103 (1990 Edmm)
w/ CIT7 OF FORT COLLINS MODIFICATIONS (REV 42000)
CONTRACTOR shall obtain competitive bids from
Subcontractors acceptable to OWNER and
CONTRACTOR and shall deliver such bids to
OWNER who will then determine with the advice of
ENGINEER, which bids, if any will be accepted If
any Subcontract provides that the Subcontractor is to
be paid on the basis of Cost of the Work plus a fee
the Suboontrectcds Cost of the Work and fee shall be
determined in the Same manner as CONTRACTORs
Cost of the Work and fee as provided in
paragraphs 114 115 116 and 117 AN
subcontracts shall be subject to the other provisions of
the Contract Documents vnofar as applicable
1144 Costs of special consultants (including but
not limited to engineers architects, testing
laboratories, surveyors, attorneys and accountants)
employed for services specifically related to the
Work
1145 Supplemental costs Including the following
11451 The proportion of necessary
transportation, travel and Subsistence expenses of
CONTRACTORS employees Incurred in
discharge of duties connected with the Work
11452 Cost, including transportation and
maintenarnce of all materials, supplies,
equipment, machmery appliances, office and
temporary facilmes at the site and hand tools not
owned by the workers, which are consumed in the
performance of the Work, and cost less market
value of such items used but not consumed which
remain the property of CONTRACTOR
11 4 5 3 Rentals of all construction
equipment and machinery and the parts thereof
whether rented from CONTRACTOR o others in
accordance with rental agreements approved by
OWNER with the advice of ENGINEER, and the
costs of transportation, loading unloading
installation, dismantling and removal thereof —all
in accordance with temps of said rental
agreements The rental of any Such equipment
machinery or pans shall cease when the use
thereof is no longer nnecessary, for the Work
11454 Sales, consumer use or smiler taxes
related to the Wok, and for which
CONTRACTOR Is liable, Imposed by Laws and
Regulations
11455 Deposits lost for causes other than
negligence of CONTRACTOR, any
Subcontractor or anyone directly or indirectly
employed by any of them or for whose acts any
of them may be liable and royalty payments and
fees for permits and licenses
11456 Losses and damages (and related
expenses) caused by damage to the Work, not
compensated by insurance or otherwise sustained
by CONTRACTOR in connection with the
performance and furnishing of the Work (except
losses and damages within the deductible amounts
of property insurance established by OWNER in
aceordarrce with paragraph 5 9) provided they
have resulted from causes other than the
negligence of CONTRACTOR, any
Subcontractor a anyone directly or indirectly
employed by any of them or for whose acts any of
them may be liable Such losses shall include
settlements made with the written consent and
approval of OWNER No such losses, damages
and expenses shall be included in the Cost of the
Work for the purpose of deterin
CONTRACTORS fee If however any such loss
or damage requires reconstruction and
CONTRACTOR is placed in charge thereof
CONTRACTOR shall be paid for services a fee
proportionate to that stated m pamgmph 1162
11457 The cost of utilities, fuel and samtary,
facilities at the site
11458 Mmor expenses such as telegrams
long distance telephone calls, telephone service at
the site expressage and similar petty cash items in
connection with the Work
11459 Cost of premiums for additional Bonds
and insurance required because of changes in the
Wink
115 The term Cost of the Work shall not include any of
the following
1151 Payroll costs and other compensation of
CONTRACTORS officers, executives, pnnapahs (of
partnership and sole proprietorships) general managers,
engineers arclutects, estimators, wmmeys, auditors,
accountants, purchasing and contracting agents,
expediters timekeepers, clerks and other personnel
employed by CONTRACTOR whether at the site or in
CONTRACTORS principal or a branch office for
general administration of the Work and not specifically
mcluded in the agreed upon schedule of job
classifications referred to in paragraph 11 4 1 or
specifically covered by paragraph 114 4—all of which
are to be considered administrative costs covered by the
CONTRACTORsfee
1152 Expenses of CONTRACTORS principal and
branch offices other than CONTRACTOR s office at
the site
1153 Any part of CONTRACTORS capital
expenses, including interest on CONTRACTORS
capital employed for the Work and charges against
CONTRACTOR for delinquent payments
11 5 4 Cost of premiums for all Bonds and for all
insurance whether or not CONTRACTOR is required
by the Contract Documents to purchase and manitain
the same (except for the cost of premiums covered by
subparagraph 11 4 5 9 above)
EJCDC UENERAL CONDITIONS 191M (1990 Edhnm)
w/ CITY OF FORT COLLINS MODIFICATIONS (REV 42000)
1155 Costs due to the negligence of
CONTRACTOR, any Subcontractor or anyone
directly or indirectly employed by my of them or for
whose acts any of them may be liable including but
not limited to the correction of defective Work,
disposal of materials or equipment wrongly supplied
and makag good any damage to property
115 6 Other overhead a general expense costs of
arty kind and the costs of any item not spemfically and
expressly included in paragraph 114
116 The CONTRACTORs fee allowed to
CONTRACTOR for overhead and profit shall be
determined as follows
116 1 a mutually acceptable fixed fee or
116 2 if a fixed fee is not agreed upon, then a fee
based on the following percentages of the various
portions of the Cost of the Work
11621 for costs incurred under
paragraphs 114 1 and 1142 the
CONTRACTORs fee shall be fifteen percent,
11622 for costs incurred under
Paragraph 114 3 the CONTRACTORS fee shall
be five percent
11623 where one or more tiers of
subcontracts are on the basis of Cost of the Work
plus a fee and no Fixed fee is agreed upon, the
intent of paragraphs 114 1 114 2 114 3 and
1162 is that the Subcontractor who actually
performs or furnishes the Work at whatever tier
will be paid a fee of fifteen percent of the costs
mcuried by such Subcontractor under paragraphs
114 1 and 11 4 2 and that any higher tier
Subcontractor and CONTRACTOR will each be
paid a fas _a five p.F.wt of the ,,eurA
aid to
amen to be negotiated
in good faith with the OWNER but not to exceed
five Percent of the amount paid to the next lower
tier Subcontractor
11624 no fee shall be payable on the basis
of costs itemized under paragraphs 114 4 114 5
and 1 1 5
11625 the amount of credit to be allowed
by CONTRACTOR to OWNER for any change
which results in a net decrease in cost will be the
amount of the actual net decrease in cost plus a
deduction in CONTRACTORs fee by an amount
equal to five percent of such net decrease and
11626 when both additions and credits are
involved m any one change the adjustment in
CONTRACTORS tee shall be computed on the
basis of the net change in accordance with
paragraphs 116 2 1 through 116 2 5 inclusive
117 Whenever the cost of any Work is to be
25
determined pursuant to paragraphs 114 and 115
CONTRACTOR will establish and maintain records
thereof in accordance with generally accepted accounting
practices and submit in form acceptable to ENGINEER an
Rem razed cost breakdown together with supporting data
Cask AUmvances
118 It is understood that CONTRACTOR has included
in the Contract Price all allowances so named in the
Contract Documents and shell cause the Work so covered
to be furnished and performed for such sums as may be
acceptable to OWNER and ENGINEER CONTRACTOR
agrees that
1181 the allowances include the cost to
CONTRACTOR (less arty applicable trade discounts)
of materials and egwpmem required by the allowances
to be delivered at the site, and all applicable taxes and
1182 CONTRACTORS costs for unloading and
handling on the site labor installation costs, overhead,
profit and other expenses contemplated for the
allowances have been included in the Contract Price
and not in the allowances and no demand for
additional payment on account of any of the foregoing
will be valid
Prior to final payment, an appropriate Change Order will be
Issued as recommended by ENGINEER to reflect actual
amounts due CONTRACTOR on account of Work covered
by allowances, and the Contract Price shall be
correspondingly adjusted
119 Unit Pi ice Work
I1 91 Where the Contract Documents provide that all
Or part of the Work a to be Unit Price Work, initially
the Contract price will be deemed to include for all
Unit Price Work an amount equal to the sum of the
established unit prices for each separately Identified
Item of Unit Price Work tunes the estimated quantity
of each item as indicated in the Agreement The
estimated quantities of items of Unit Price Work are
not guaranteed and are solely for the purpose of
companson of Bids and determming an Initial Contract
Price Determinations of the actual quantities and
classifications of Unit Price Work performed by
CONTRACTOR will be made by ENGINEER in
accordance with paragraph 9 10
11 92 Each unit price will be deemed to include an
amount considered by CONTRACTOR to be adequate
m cover CONTRACTORS overhead and profit for
each separately identified item
1193 OWNER or CONTRACTOR may make a
clams for an adjustment in the Contract Price in
accordance with Article I if
I 1 9 3 1 the quantity of any item of Unit Price
Work performed by CONTRACTOR differ
materially and significantly from the estimated
quantity of such item indicated in the Agreement
26 EJCDC GENERAL CONDITIONS 1910.8(19902nOm)
W CITY OF FORT COLLINS MODIFICATIONS (REV 42000)
and
11932 there is no corresponding adjustment
with respect to any other item of Work and
11933 if CONTRACTOR believes that
CONTRACTOR is entitled to an increase in
Contract Price as a result of having incurred
additional expense or OWNER believes that
OWNER is entitled to a decrease in Contract Price
and the parties we unable to agree as to the
amount of arty such increase or decrease
11934 CONTRACTOR acknowledges that
the OWNER has the npht to add a delete items in
the Bid or change %mirtities at OWNERS sole
eiisoretion without affecting the Contract Price of
RATa rem item so I as the deletionor
does not exceed twenty five percent of
the Mgmal total Contract Price
ARTICLE 12 CHANGE OF CONTRACT TIMES
121 The Contract Times (or Milestones) may only be
changed by a Change Order or a Wriam Amendment
Any clams for an adjustment of the Contract Times (or
Milestones) shall be based on written notice delivered by
the party making the clan to the other party and to
ENGINEER promptly (but in no event later than thuty
days) after the occurrence of the event giving rise to the
claim and stating the general nature of the claim Nonce
of the extent of the claim with supporting data shall be
delivered within sixty days after such occurrence (unless
ENGINEER allows additional time to ascertain more
accurate data in support of the clan) and shall be
accompanied by the clamiants written statement that the
adjustment claimed is the entire adjustment to which the
clamant has reason to believe it Is entitled as a result of
the occurrence of mid event All claims for adjustment m
the Contract Times (or Milestones) shall be determined by
ENGINEER in accordance with paragraph 911 if
OWNER and CONTRACTOR cannot otherwise agree
No claim for an adjustment in the Contract Times (or
Milestones) will be valid if not submitted in accordance
with the requirements of this paragraph 12 1
122 All time limits stated in the Contract Documents
are of the essence of the Agreement
123 Where CONTRACTOR is prevented from
completing any part of the Work within the Contract
Times (or Milestones) due to delay beyond the control of
CONTRACTOR the Contract Tunes (or Milestones) will
be extended in an amount equal to time lost due to such
delay if a claim is made therefor as provided in
paragraph 12 1 Delays beyond the control of
CONTRACTOR shall include but not be limited to acts
or neglect by OWNER acts or neglect of utility owners or
other contractors performing other work as contemplated
by Article 7 Eger floods, epidemics abnormal weather
wnditions or acts of God Delays attributable to and
within the control of a Subcontractor or Supplier shall be
deemed to be delays within the control of CONTRACTOR
124 Where CONTRACTOR is prevented from
completing any part of the Work within the Contract Times
(or Ivfilestoiies) due to delay beyond the control of both
OWNER and CONTRACTOR, an extension of the
Contract Times (or Milestones) in an amount equal to the
time lost due to such delay shall be CONTRACTORS sole
and exclusive remedy for Such delay In no event Shall
OWNER be liable to CONTRACTOR, any Subcontractor
any Supplier any other person or organization, a to any
suthe
rely for or employee or agent of any of m for
damages ansing out of or resulting from (t) delays caused
by or within the control of the CONTRACTOR, or
(u) delays beyond the control of both parties including, but
not Immted to fires, floods, epidemics, abnormal weather
conditions, acts of God a acts or neglect by utility owners
or other contractors performing other work as contemplated
by Article 7
ARTICLE 13 TESTS AND INSPECTIONS
CORRECTION REMOVAL OR ACCEPTANCE OF
DEFECTIVE WORK
131 Notice of Defects
Prompt nonce of all defective Work of which OWNER or
ENGINEER have actual knowledge will be given to
CONTRACT OR All defective Work may be rejected
corrected a accepted as provided in this Article 13
Access to Work
132 OWNER, ENGINEER, ENGINEERs Consultants,
other representatives and personnel of OWNER,
independent testing laboratories and governmental agencies
with jurisdictional interests will have access to the Work at
reasenablesnnm for then observation, inspecting and
testing CONTRACTOR shall provide than proper and
safe conditions for such access and advise than of
CONTRACTORS site Safety procedures and programs So
that they may comply therewith as applicable
Tests andlnspecnons
133 CONTRACTOR shall give ENGINEER timely
notice of readiness of the Work for all required inspections,
tests or approvals, and shall cooperate with inspection and
testing personnel to facilitate required Inspections or tests
134 OWNER shall employ and pay for the services of
an independent testing laboratory to perform all
mspectons tests or approvals required by the Contract
Documents except
1341 for inspections, tests or approvals covered
by paragraph 13 5 below
1342 that costs incurred in connection with tests
or inspections conducted pursuant to paragraph 13 9
EJCDC UENERAL COMMONS 1910.8 (1990 EAtim)
w/CITY OF FORT COLLINS MODIFICATIONS (REV 4R000)
below shall be paid as provided in said
paragraph 13 9 and
1343 as othemse specifically provided in the
Contract Documents
135 If Laws or Regulations of any ppubhc body having
jurisdiction require any Work (or part diawl) specifically
to be inspected, tested or approved by an employee or
other representative of such public body CONTRACTOR
shall assume full responsibility for arranging and
obtaining such inspections: tests or approvals, pay all costs
in connection therewith, and famish ENGINEER the
required certificates of inspection, or approval
CONTRACTOR shall also be respirable for arranging
and obtaining and shall pay all costs in connection with
any inspections, tests a approvals required for OWNERS
and ENGINEERS acceptance of materials or equipment to
be incorporated in the Work or of materials, mix designs,
or equipment Submitted for approval prior to
CONTRACTORS purchase thereof for incorporation in
the Work
136 If any Work (or the work of others) that is to be
inspected, tested or approved IS covered
CONTRACTOR without written concurrence of
ENGINEER, it must, if requested by ENGINEER, be
uncovered for observatiori.
137 Uncovering Work as provided in paragraph 13 6
Shall be at CONTRACTORS expense unless
CONTRACTOR has given ENGINEER timely notice of
CONTRACTORS intention to cover the Same and
ENGINEER has not acted with reasonable promptness in
response to Such notice
Uncovering Work
138 If any Work is covered contrary to the written
request of ENGINEER, it must, if requested by
ENGINEER, be uncovered for ENGINEERS observation
and replaced at CONTRACTORS expense
139 If ENGINEER considers it necessary or advisable
that covered Work be observed by ENGINEER or
inspected a tested by others, CONTRACTOR, at
ENGINEER s request, shall uncover expose or otherwise
make available for observation, inspection or testing as
ENGINEER may require that portion of the Work in
question, furnishing all necessary labor material and
equipment If it is found that Such Work is daf enve
CONTRACTOR shall pay all claims, costs, losses and
damages caused by arising out of or resulting from such
uncovering, exposure observation, inspection and testing
and of Satisfactory replacement a reconstruction
(including but not limited to all costs of repair or
replacement of work of others) and OWNER shall be
entitled to an appropriate decrease in the Contract Price
and, of the parties are unable to agree as to the amount
thereof may make a claim therefor as provided in
Article 11 If however such Work is not found to be
defective CONTRACTOR shall be allowed an increase in
the Contract Price or an extension of the Contract Times
(or Milestones) or both, directly attributable to Such
27
uncovering exposure observation, inspection, testing
replacement and reconstruction rod, of the parties we
unable to agree as to the amount a extent thereof
CONTRACTOR may make a clans therefor m provided in
Articles 1 I and 12
OWNER May Stop the Work
1310 If the Work is defective or CONTRACTOR falls
to supply sufficient skilled workers or suitable materials or
equipment, or fails to fumish or perform the Work in such a
way that the completed Work will conform to the Contract
Documents, OWNER may order CONTRACTOR to stop
the Work or any portion thereof until the cause for such
order has been eliminated however this right of OWNER
to stop the Work shall not give nse to any duty on the part
of OWNER to exercise this right for the benefit of
CONTRACTOR or any surety or other party
Correction or Removal ofDefachve Work.
13 11 If required by ENGINEER CONTRACTOR shall
promptly as directed, either correct all defective Work,
whether or not fabricated, installed or completed, or if the
Work has been rejected by ENGINEER remove it from the
site and replace it with Work that is not defective
CONTRACTOR shall pay all clamns, costs, losses and
damages caused by or resulting from Such correction or
removal (includmg but not limited to all costs of repair or
replacement of work of others)
1312 Correction Pend.
13 12 1 If within one-year two vears after the date of
Substantial Completion m such longer period of time as
may be prescribed by Laws or Regulations or by the
terms of any applicable special guarantee required by
the Contract Documents or by arty specific provision of
the Contract Documenas, any Weak is found to be
defective CONTRACTOR shall promptly without cost
to OWNER and in accordance with OWNERS written
irlstnicttom (1) correct Such defective Work, or if it has
been rejected by OWNER, remove it from the site and
replace it with Work that is not defective and (it)
satisfactorily correct or remove and replace any damage
to other Work or the work of others resulting therefrom
If CONTRACTOR does not promptly comply with the
terms of such instructions, or in an emergency where
delay would cause serious risk of loss or damage
OWNER may have the defective Work corrected or the
rejected Work removed and replaced, and all claims,
costs, losses and damages caused by or resulting from
such removal and replacement (including but not
Witted to all costs of repair or replacement of work of
others) will be paid by CONTRACTOR
13 12 2 In special circumstances where a particular
item of equipment is placed in continuous Service
before Substantial Completion of all the Work, the
correction period for that item may start to inn from an
earlier date if so provided in the Specifications or by
Written Amendment
13 12 3 Where defective Work (and damage to other
28 EJCDC GENERAL CONDITIONS 1910-8 (1990 MUM)
W1 CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000)
Work resulting therefrom) has been corrected
removed or replaced under this paragraph 13 12 the
correction period hereunder with respect to such Work
will be extended for an addinonal period of ene yem
two Years after such correction or removal and
replacement has been sansfactonly completed
Acceptance of Defective Work
13 13 If mead of requiring correction or removal and
replacement of defective Work, OWNER (and, prior to
ENGINEERS recommendation of final payment, also
ENGINEER) prefers to accept it OWNER may do so
CONTRACTOR shall pay all clauns, costs, losses and
damages attributable to OWNERS evaluation of and
detemtmation to accept such defechve Work (Such costs to
be approved by ENGINEER as to reasonableness) If any
such acceptance occurs prior to ENGINEERS
recommendation of final payment, a Change Order w fl be
Issued incorporating the necessary revistom m the
Contract Documents with respect to the Work and
OWNER shall be entitled to an appropriate decrease in the
Contract Price and, if the parties are unable to agree as to
the amount thereof OWNER may make a clams therefor
as provided in Article I If the acceptance occurs after
Such recommendation, an appropriate amount will be paid
by CONTRACTOR to OWNER
OWNER May CorrectDefechve Work
1314 If CONTRACTOR fails within a reasonable time
after written nonce from ENGINEER to correct defective
Work or to remove and replace rejected Work as required
by ENGINEER in accordance with paragraph 13 11 or if
CONTRACTOR fails to perform the Work in accordance
with the Contract Documents, or if CONTRACTOR fails
to comply with any other provision of the Contract
Documents, OWNER may after seven days written
notice to CONTRACTOR correct and remedy any such
deficiency In exercising the rights and remedies under
this paragraph OWNER shall proceed expeditiously In
connection with such corrective and remedial action,
OWNER may exclude CONTRACTOR from all or part of
the site, take possession of all or part of the Work, and
suspend CONTRACTORS services related thereto take
possession of CONTRACTORS tools, appliances,
construction equipment and machinery at the site and
mcorporate in the Work all materials and equipment
stored at the site or for which OWNER has paid
CONTRACTOR but winch are stored elsewhere
(,ONTRA('IOR shall allow OWNER, OWNERS
represerm eves, agents and employees, OWNERS other
contractors and ENGINEER and ENGINEERS
Consultants access to the site to enable OWNER to
exercise the rights and remedies under this paragraph All
clans, costs, lasses and damages incurred or sustained by
OWNER in exercising Such rights and remedies will be
charged against CONTRACTOR and a Change Ordei will
be Issued mcorpomting the necessary revisions in the
Contract Documents with respect to the Work and
OWNER shall be entitled to an appropriate decrease in the
Contract Price and, if the parties are unable to agree as to
the amount thereof OWNER may make a claim therefor
as provided in Article 11 Such claims costs losses and
damages will Include but not be limited to all costs of
repair a replacement of work of others destroyed or
damaged by correction, removal or replacement of
CONTRACTORS defective Work CONTRACTOR diall
not be allowed an extension of the Contract Tames (or
Milestones) because of any delay in performance of the
Work attributable to the exercise by OWNER of OWNERS
rights and remedies hereunder
ARTICLE 14- PAYMENTS TO CONTRACTOR AND
COMPLETION
Schedule of Values
141 The schedule of values established as provided in
Paragraph 2 9 will serve as the basis for progress payments
and will be incorporated into a form of Application for
Payment acceptable to ENGINEER Progress payments on
account of Unit price Work will be based on the number of
units completed
Apphcatmn for ProgressPnymant
142 At least twenty days before the date established for
each progress payment (but not more often than once a
month) CONTRACTOR dull submit to ENGINEER for
review an Application for Payment filled out and signed by
CONTRACTOR covering the Work completed as of the
date of the Application and accompanied by such
supporting documentation as Is required by the Contract
Documents If payment is requested on the basis of
materials and equipment not incorporated in the Work but
delivered and suitably stored at the site or at another
location agreed to in writing the Application for Payment
shall also be accompanied by a bill of sale invoice or other
documentation warranting that OWNER has received the
materials and equipment free and clear of all Liens and
evidence that the materials and equipment are covered by
appropriate property Insurance and other arrangemems to
protect OWNERS interest therein, all of which will be
satisfactory to OWNER The amount of retamage with
respect to progress payments will be as stipulated in the
Agreement Any funds that am withheld by the OWNER
shall not be subject to substitution by the CONTRACTOR
with securities or anv srmneements mvolvin_ an escrow or
custodianduo By executing the atrohcation for payment
form the CONTRACTOR essly waives his rmht to the
benefits of Colorado Revised StatutesSection 24 91 101
et sea
CONTRACTOR s Warranty of Title
143 CONTRACTOR warrants and guarantees that title
to all Work, materials and equipment covered by any
Application for Payment, whether incorporated in the
Project or not, will pass to OWNER no later than the time
of payment free and clear of all Liens
Renew ofApphcahons for Progress Payment
14 4 ENGINEER will within ten days after receipt of
each Application for Payment either indicate in writing a
ECDC bENERA CONDITIONS 1910 9(1990 Edmm)
w/ CITY OF FORT COUINS MODIFICATIONS (REV 412000)
recommendation of payment and present the Application
to OWNER a return the Application to CONTRACTOR
mcbmttrlg in writing ENGINEER s reasons for refusing to
recommend payment In the latter case CONTRACTOR
may make the necessary corrections and resubmit the
Application Ten days after presentation of the
Apphcafion for Payment to OWNER with ENGINEERS
recommendation, the amount recommended will (subject
to the Provisions of the last sentence of paragraph 147)
become due and when due will be paid by OWNER to
CONTRACTOR
145 ENGINEERS recommendation of any payment
requested in an Application for Payment will corls[Itute a
representation by ENGINEER to OWNER, based on
ENGINEERS on site observations of the executed Work
as an experienced and qualified design professional and on
ENGINEERS review of the Apphcatnon for Payment and
the accompanying data and schhedules, that to the best of
ENGINEER s knowledge information and belief
14 5 1 the Work has progressed to the point
indicated
14 5 2 the quality of the Work Is generally in
accordance with the Contract Documents (subject to
an evaluation of the Work as a functioning whole
Pnor to or upon Substantial Completion, to the results
of any subsequent tests called for in the Contract
Documents, to a final determination of quanfitim and
classlfnoatmois for Unit Price Work under
Paragraph 9 10 and to any other qualifications stated
in the recommendation) and
14 5 3 the conditions precedent to
CONTRACTORS being entitled to such payment
appear to have been fulfilled insofar as it Is
ENGINEER s responsibility to observe the Work
However by recommending any such payment
ENGINEER will not thereby be deemed to have
represented that (I) exhaustive or continuous on -sae
inspections have been made to check the quality or the
quantity of the Work beyond the responsibilities
specifically assigned to ENGINEER in the Contract
Documents or (n) that there may not be other matters or
issues between the parties that might entitle
CONTRACTOR to be paid additionally by OWNER or
entitle OWNER to withhold payment to CONTRACTOR
146 ENCrINFERs recommendation of any payment
including final payment, shall not mean that ENGINEER
is responsible for CONTRACTORS means, methods,
techniques, sequences or procedures of construction, or
the safety precautions and programs mcident thereto a
for arty failure of CONTRACTOR to comply with Laws
and Regulations applicable to the furnishing or
Performance of Work or for any failure of
CONTRACTOR to perform or furnish Work in
accordance with the Contract Documents
147 ENGINEER may refuse to recommend the whole
or any part of any payment If in ENGINEERs opinion, it
would be incorrect to make the representations to
29
OWNER referred to in paragraph 14 5 ENGINEER may
also refuse to recommend any such payment or because of
subsequently discovered evidence or the results of
subsequent inspections or tests, nullify any such payment
previously recommended, to such extent aS may be
necessary in ENGINEERS opinion to protect OWNER
from loss because
14 7 1 the Work is defective or completed Work has
been damaged requiring correction or replacement
1472 the Contract Price has been reduced by
Written Amendment or Change Order
1473 OWNER has been required to correct
defective Work or complete Work in accordance with
paragraph 13 14 or
14 7 4 ENGINEER has actual knowledge of the
occurrence of any of the events enumerated in
paragraphs 15 2 1 through 15 2 4 inclusive
OWNER may refuse to make payment of the full amount
recommended by ENGINEER because
1475 clams have been made against OWNER on
account of CONTRACTORS performance or furnishing
of the Work,
14 7 6 Liens have been filed in connection with the
Work, except where CONTRACTOR has delivered a
specific Bond satisfactory to OWNER to secure the
satisfaction and discharge of such Liens,
14 7 7 there are other Items entitling OWNER to a sa
off against the amount recommended, or
1478 OWNER has actual knowledge of the
occurrence of any of the events enumerated in
paragraphs 14 71 through 14 7 3 or paragraphs 15 2 1
through 15 2 4 Inclusive
but OWNER must give CONTRACTOR Immediate
written notice (with a copy to ENGINEER) stating the
reasons for such action and promptly pay CONTRACTOR
the amount so withheld, or any adjustment thereto agreed
to by OWNER and CONTRACTOR, when
CONTRACTOR corrects to OWNERS satisfaction the
reasons for such action
Substanhd Completion
148 When CONTRACTOR considers the entire Work
ready for its intended use CONTRACTOR shall notify
OWNER and ENGINEER in writing that the entire Work
is substantially complete (except for items specifically
listed by CONTRACTOR as uncomplete) and request that
ENGINEER issue a certificate of Substantial Completion
Within a reasonable time thereafter OWNER
CONTRACTOR and ENGINEER shall make an uispection
of the Work to determine the status of completion If
ENGINEER does not consider the Work substantially
complete ENGINEER will notify CONTRACTOR in
writing giving the reasons therefor If ENGINEER
30 FJCDC GENERAL CONDITIONS 19104 (1990 Edium)
w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000)
considers the Work substantially complete ENGINEER
will prepare and deliver to OWNER a tentative certificate
of Substantial Completion which shall fix the date of
Substantial Completion There shall be attached to the
certificate a tentative list, of items to be completed or
corrmted before final payment OWNER shall have seven
days after receipt of the tentative certificate during which
to make written objection to ENGINEER as to any
provisions of the certificate or attached list If after
considering such objections, ENGINEER concludes that
the Work is net substantially complete, ENGINEER will
within fourteen days after submission of the tentative
certificate to OWNER notify CONTRACTOR in writing
stating the reasons therefor If after consideration of
OWNERS objections, ENGINEER considers the Work
substantially complete, ENGINEER will within said
fourteen days execute and deliver to OWNER and
CONTRACTOR a definitive certificate of Substantial
Completion (with a revised tentative list of items to be
completed or corrected) reflecting such changes from the
tentative certificate as ENGINEER behaves justified after
cormderation of any objections from OWNER At the
time of delivery of the tentative certificate of Substantial
Completion ENGINEER will deliver to OWNER and
CONTRACTOR a written recommendation as to division
of responsibilities pending final payment between
OWNER and CONTRACTOR with respect to security
operation, safety maintenance heat, utilities, insurance
and warranties and guarantees Unless OWNER and
CONTRACTOR agree otherwise in writing and so inform
ENGINEER in writing prior to ENGINEER s nssmng the
definitive certificate of Substantial Completion,
ENGINEEWs aforesaid recommendation will be binding
on OWNER and CONTRACTOR until firml payment
149 OWNER shall have the right to exclude
CONTRACTOR from the Work after the date of
Substantial Completion, but OWNER shall allow
CONTRACTOR reasonable access to complete or correct
items on the tentative list
Parted Uhhzation
1410 Use by OWNER at OWNERS option of any
substantially completed part of the Work, which (I) has
specifically been identified in the Contract Documents, or
(u) OWNER ENGINEER and CONTRACTOR agree
constitutes a separately functioning and usable part of the
Work that can be used by OWNER for its intended
purpose without significant interference with
CONTRACTORS perfannance of the remainder of the
Work may be accomplished prim to Substantial
Completion of all the Work subject to the following
14 10 1 OWNER at any time may request
CONTRACTOR in writing to permit OWNER to use
any such part of the Work which OWNER believes to
be ready for its intended use and substantially
complete If CONTRACTOR agrees that such part of
the Work Is substantially complete CONTRACTOR
will certify to OWNER and ENGINEER that Such
part of the Work is substantially complete and request
ENGINEER to issue a certificate of Substantial
Completion for that part of the Work
CONTRACTOR at any time may notify OWNER and
ENGINEER in writing that CONTRACTOR considers
any such pert of the Work ready for its intended use
and substantially complete and request ENGINEER to
Issue a certificate of Substantial Completion for that
Part of the Work Within a reasonable time otter either
such request, OWNER, CONTRACTOR and
ENGINEER shall make an inspection of that part of
the Work to determine its status of completion If
ENGINEER does not consider that part of the Wok to
be substantially complete ENGINEER will notify
OWNER and CONTRACTOR in writing giving the
reasons therefor If ENGINEER considers that part of
the Work to be substantially complete the provisions
of paragraphs 14 8 and 14 9 will apply with respect to
certification of Substantial Completion of that part of
the Work and the division of responsibility in respect
thereof and access thereto
14 10 2 No occupancy or separate operation of part
of the Work will be accomplished prior to compliance
with the requirements of paragraph 5 15 in respect of
property insurance
Frnallnspechon
1411 Upon written notice from CONTRACTOR that the
entae Work or an agreed portion thereof is complete,
ENGINEER will make a final inspection with OWNER
and CONTRACTOR and will notify CONTRACTOR in
writing of all particulars in which this inspection reveals
that the Work is incomplete or defective CONTRACTOR
shall Immediately take such measures as are necessary to
complete such work or remedy such deficiencies
final Application jar Payment
1412 After CONTRACTOR has completed all such
corrections to the satisfaction of ENGINEER and delivered
in accordance with the Contract Documents all
maintenance and operating instructions schedules
guarantees Bonds, certificates or other evidence of
insurance required by paragraph 5 4 certificates of
inspection, marked up record documents (as provided in
paragraph 619) and other documents, CONTRACTOR
may make application for final payment following the
procedure for progress payments The final Apphmtion for
Payment shall be accompanied (except as previously
delivered) by (i) all documentation called for in the
Contract Documents, including but not limited to the
evidence of insurance required by subparagraph 5 4 13
(a) consent of the surety if any to final payment and
(III) complete and legally effective releases or waivers
(satisfactory to OWNER) of all Liens arising out of or filed
in correction with the Work In lieu of such releases or
waivers of Liens and as approved by OWNER
CONTRACTOR may furnish receipts or releases in full
and affidavit of CONTRACTOR that (I) the releases and
receipts include all labor services material and equipment
tor which a Lien could be tiled, and (I) all payrolls,
material and equipment bills, and other Indebtedness
connected with the Work for which OWNER or OWNERS
properly might many way be responsible have been paid or
otherwise satisfied If any Subcontractor or Supplier fails
AJCDC GENERAL CONDITIONS 1910.8 (1990 Edjnm)
w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000)
to furnish such a release or receipt in full
CONTRACTOR may famish a Bond or other collateral
satisfactory to OWNER to indemnify OWNER against
MY Lien Releases or waivers of liens and the consent of
the surety to finalize payment me to be submitted on
forms conforming to the format of the OWNER S standard
Corms bound in the protect manual
Final Payment and Acceptance
1413 If on the basis of ENGINE.ERs observation of
the Work during construction and final inspection, and
ENGINEERS review of the final Application for Payment
and accompanying documentation as required by the
Contract Documents, ENGINEER Is satisfied that the
Work has been completed and CONTRACTORS other
obligations under the Contract Documents have been
fulfilled, ENGINEER will within ten days after receipt of
the final Application for Payment, indicate in writing
ENGINEERS recommendation of payment and }resent
the Application to OWNER for payment At the same
time ENGINEER will also give written notice to OWNER
and CONTRACTOR that the Wok is acceptable subject
to the provisions of paragraph 14 15 Otherwise
ENGINEER will return the Application to
CONTRACTOR, indicating in writing the reasons for
refusing to recommend final payment, in which case
CONTRACTOR shall make the necessary corrections and
resubmit the Application Thirty days after presentation to
OWNER of the Application and accompanying
documentation, in appropriate form and substance and
with ENGINEERS recommendation and notice of
acceptability the amount recommended by ENGINEER
will become due and will be paid by OWNER to
CONTRACTOR subject to paragraph 1762 of these
General Conditions
1414 If through no fault of CONTRACTOR, final
completion of the Work is Significantly delayed and if
ENGINEER so confirms, OWNER shall, upon receipt of
CONTRACTORs final Application tor Payment and
recommendation of ENGINEER and without terminating
the Agreement, make payment of the dance due for that
portion of the Work fully completed and accepted If the
remeining balance to be held by OWNER for Wok not
filly completed or corrected is less than the retainage
stipulated in the Agreement, and if Bonds have been
f irmshed as required in paragraph 5 1 the written consent
of the surety to the payment of the balance due for that
portion of the Work fully completed and accepted shall be
submitted by CONTRACTOR to ENGINEER with the
Application for such payment Such payment shall be
made under the terms and conditions governing final
payment except that it shall not constitute a waiver of
claims
Wmver of Claims
1415 The making and acceptance of final payment will
constitute
14 15 1 a waiver of all claims by OWNER against
CONTRACTOR, except clams arising from
unsettled Liens from defective Work appearing after
01
SECTION 00100
INSTRUCTIONS TO BIDDERS
final mspectim pursuant to paragraph 14 11 from
failure to comply with the Contract Documents or the
terms of arty special guarantees specified therein, or
from CONTRACTORS contmumg obligations under
the Contract Documents and
14 15 2 A waiver of all claims by CONTRACTOR
against OWNER other than those previously made in
writing and still unsettled
ARTICLE 15- SUSPENSION OF WORK AND
TERMINATION
OWiVER May Suspend Work
151 At any time and without cause OWNER may
suspend the Work or any portion thereof for a period of not
more than ninety days by notice in writing to
CONTRACTOR and ENGINEER which will fix the date
on which Work will be resumed CONTRACTOR shall
resume the Work an the date so feed CONTRACTOR
shall be allowed an adjustment in the Contract Price or an
extension of the Contract Tunes or both, directly
attributable to any such suspension of CONTRACTOR
makes an approved clan therefor as provided in
Articles 11 and 12
OWNER May Terminate
152 Upon the occurrence of any one or more of the
following events
1521 tf CONTRACTOR persistently fails to perform
the Work in accordance with the Contract Documents
(including, but not limited to failure to supply sufficient
skilled workers or suitable materials or equipment or
failure to adhere to the progress schedule established
under paragmph29 as adjusted from time to tune
pursuant to paragmph 6 6)
1522 if CONTRACTOR disregards Laws or
Regulations of any public body havingjurisdiction,
1523 If CONTRACTOR disregards the authority of
ENGINEER or
15 2 4 if CONTRAC TOR otherwise violates in any
substantial way any provisions of the Contract
Documents
OWNER may after giving CONTRACTOR (and the
surety it any) seten days written notice and to the extent
permitted by Laws and Regulations, terminate the services
of CONTRACTOR, exclude CONTRACTOR from the site
and take possession of the Work and of all
CONTRACTORS tools appliances construction
equipment and machinery at the site and use the same to
the full extent thev could be used by CONTRACTOR
(without liability to CONTRACTOR for trespass or
conversion) incorporate in the Work all materials and
equipment steed at the site or for which OWNER has paid
ETCDC GENERAL CONDITIONS 191M (1990 F bum)
32 w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/3000)
CONTRACTOR but which are stored elsewhere and
finish the Work m OWNER may deem expedient In such
case CONTRACTOR shall not be entitled to receive any
father payment until the Work is finished If the unpaid
balance of the Contract Price exceeds all clans, costs,
losses and damages sustained by OWNER arising out of
or resulting from completing the Work such excess will be
paid to CONTRACTOR If such clams costs, losses and
damages exceed such unpaid balance CONTRACTOR
shalt pay the difference to OWNER Such claims, costs
lessee and damages incurred by OWNER will be reviewed
by ENGINEER as to thew reasonableness and when so
approved by ENGINEER mcorpormad in a Change Order
provided that when exercising any rights or remedies
under tins paragraph OWNER shall not be required to
obtain the lowest price for the Work performed
153 Where CONTRACTORS services have been so
terminated by OWNER, the termination will not affect
any rights or remedies of OWNER against
CONTRACTOR then existing or which may thereafter
accrue Any retention or payment of moneys due
CONTRACTOR by OWNER will not release
CONTRACTOR from liability
154 Upon seven days written notice to
CONTRACTOR and ENGINEER, OWNER may
without cause and without prejudice to any other right or
remedy of OWNER, elect to temimme the Agreement In
such case CONTRACTOR shall be paid (without
duplication of any items)
15 4 1 for completed and acceptable Work executed
in accordance with the Contract Documents prior to
the effective date of termination, including fair and
reasonable sums for overhead and profit on such
Work
15 4 2 for expenses sustained prior to the effective
date of tenninmton in performing services and
furnishing labor materials or equipment as required
by the Contract Documents in connection with
uncompleted Work plus fair and reasonable sums for
overhead and profit on such expenses
1543 for all clams costs, losses and damages
mounted in settlement of termmated contracts with
Subcontractors Suppliers and others and
15 4 4 for reasonable expenses directly attributable
to termination
CONTRACTOR shall no be paid on account of loss of
anticipated profits or revenue or other economic loss
ansmg out of or resulting from such termination
CONTRACTOR May Stop Work or Terminate
155 If through no act or fault of CONTRACTOR, the
Work is suspended for a period of more than ninety days
by OWNER or under an order of court or other public
authority or ENGINEER fads to act on any Application
for Payment within thirty days after it is submitted o
OWNER fails for thirty days to pay CONTRACTOR any
sum finally determined to be due than CONTRACTOR
may upon seven days written notice to OWNER and
ENGINEER, and provided OWNER orENGINEER do not
remedy such suspension or failure within that time
terminate the Agreement and recover from OWNER
payment on the same terns as provided in paragraph 15 4
In lieu of terminating the Agreement and without pre).udice
to any other right or remedy if ENGINEER has failed to
act on an Application fix Payment within thirty days after it
IS submitted, or OWNER has failed for thirty days to pay
CONTRACTOR any sum finally determined to be due
CONTRACTOR may upon seven days written notice to
OWNER and ENGINEER stop the Work until payment of
all such amounts due CONTRACTOR, including interest
thereon The provisions of this paragraph 15 5 are not
imended to preclude CONTRACTOR from making claim
under Articles 11 and 12 for an increase in Contract Price
or Contract Times or otherwise for expenses or damage
duectly attributable to CONTRACTORS stopping Work as
permitted by this paragraph
ARTICLE 16 DISPUTE RESOLUTION
If and to the extent that OWNER and CONTRACTOR
have agreed on the method and procedure for resolving
disputes between them that may arise under this
Agreement such dispute resolution method and procedure
If any shall be as set forth in Exhibit GC -A, Dispute
Resolution Agreement to be attached hereto and made a
part hereof If no such agreement on the method and
procedure for resolving such disputes has been reached,
and subject to the provisions of paragraphs 9 10 911 and
912 OWNER and CONTRACTOR may exercise such
rights or remedies as either may otherwise have under the
Contract Documents or by Laws or Regulations in respect
of any dispute
ARTICLE 17—MISCELLANEOUS
Giving Nonce
171 Whenever any provision of the Contract
Documents requires the giving of written notice it will be
deemed to have been validly given if delivered in person to
the individual or to a member of the firm or to an officer of
the corporation for whom it is intended, or of delivered at or
sent by registered or cemfied mail postage prepaid, to the
last business address known to the giver of the nonce
172 Computation of Tune
1721 When any period of time is referred to in the
Contract Documents by days, it will be computed to
exclude the first and Include the last day of such
penod If the last day of any such period falls on a
Saturday or Sunday or on a day made a legal holiday
by the law of the applicable jurisdiction such day will
be omitted from the i.ompumtion
EJCDC GENERAL CONDITIONS 19104 (1990 EAmm)
W1CITY OF FORT COLLINS MODIFICATIONS (REV 42000)
17 2 2 A calendar day of twenty four hours measured
from midnight to the next midnight will constitute a
day
Notice ofCkum
17 3 Should OWNER or CONTRACTOR suffer mjury
or damage to person or property because of any error
omission ar ad of the other party or of any of the other
party employees or agents or others for whose acts the
other party is legally liable claim will be made in writing
to the other party within a reasonable time of the fist
observance of such injury o damage The prwlsrois of
this paragraph 17 3 shall not be construed as a substitute
for or a waiver of the provisions of any applicable statute
Of limitations or repose Cumulative Rem ifies
174 The duties and obligations unposed by these
General Conditions and the rights and remedies available
hereunder to the parues hereto and, in particular but
without limitation, the warranties, guarantees and
obligations unposed upon CONTRACTOR by
paragraphs 6 12 6 16 6 30 6 31 6 32 13 1 13 12 13 14
14 3 and 15 2 and all of the rights and remedies available
to OWNER and ENGINEER thereunder are in addition
to and are not to be construed in any way as a limitation
of any rights and remedies available to any or all of them
which are otherwise imposed m available by Laws or
Regulations by special warranty or guarantee or by other
provisions of the Contract Documents and the provisions
of this paragraph will be as effective as if repeated
specifically in the Contract Documents in connection with
each particular duty obligation, nght and remedy to which
they apply
Profesnonal Fees and Court Costs Included
175 Whenever reference is made to claim, costs
losses and damages I stall include in each case but not
be (muted to all fees and charges of engineers, arclntects,
attorneys and other professionals and all court or
arbitration or other dispute resolution costs
176 The laws of the State of Colorado apply to this
Aareemenx Reference to two pertinent Colorado statutes
are as follows
1762 If a clam is filed OWNER is re uued by
law CRS 38 26 107) to withhold Iron all payments to
CONTRACTOR sufficient funds to insure the
payment of all clams for labor materials team hire
sustenanceprovisions, provender, or other supplies
used or consumed by CONTRACTOR or his
33
34 EICDC GENERAL CONDITIONS 19103 (1990 ENlim)
w/ CITY OF FORS COLLINS MODIFICATIONS (REV 42000)
(Tlus page left blank lruenti n lly )
EJCDCc ENERAL CONDITIONS 191M (1990Edaim) 35
W CITY OF FORT COLUNS MODIFICATIONS (REV 4/2000)
E1CDC GENERAL CONDITIONS 1910- (19%E`hlm)
36 W CITY OF FORT COLLINS MODIFICATIONS (REV 4l1000)
EXHIBIT GC -A to General Conditions
of the Construction Contract Between
OWNER and CONTRACTOR
DISPUTE RESOLUTION AGREEMENT
OWNER and CONTRACTOR hereby agree that
Article 16 of the General Conditions of the Construction
Contract between OWNER and CONTRACTOR is
amended to include the following agreement of the parties
161 All clans, disputes and other mattes in
question between OWNER and CONTRACTOR ansing
out of or relating to the Contract Documents or the breach
thereof (except for clams which have been waived by the
making or acceptance of final payment as provided by
paragraph 1415) will be decided by arbitration in
accordance with the Construction Industry Arbitration
Rules of the American Arbitration Association then
obtaming subject to the limitations of the Article 16 This
agreement so to arbitrate and any other agreement or
consent to arbitrate entered into in accordance herewith as
provided in this Article 16 will be specifically enforceable
under the prevathng law of any court having jurisdiction
162 No demand for arbitration of any claim dispute
or other matter that Is required to be referred to
ENGINEER usually for decision in accordance with
paragraph 9 11 will be made until the earlier of (a) the date
on which ENGINEER has rendered a written decision or
(b) the thirty fast day after the parties have presented their
evidence to ENGINEER if a written decision has no been
rendered by ENGINEER before that date No demand for
arbitration of any such clam dispute or other matter will
be made later than thirty days after the date on which
ENGINEER has rendered a written decision in respect
thereof in accordance with paragraph 9 11 and the failure
to demand arbitration within said thirty days period will
result in ENGINEERS decision being final and binding
upon OWNER and CONTRACTOR If ENGINEER
renders a decision after arbitration proceedings have been
Initiated, such decision may be entered as evidence but will
not supersede the arbitration proceedings, except where the
decision its acceptable to the parties concerned No demand
for arbitration of any written decision of ENGINEER
rendered in accordance with paragraph 9 10 will he made
later than ten days after the party making such demand has
delivered written notice of intention to appeal as provided
in paragraph 9 10
163 Notice of the demand for arbitration will be
filed in writing with the other party to the Agreement and
with the 4mencan Arbitration Association, and a copy wdl
be sent to ENGINEFR for information The demand for
arbitration will be made within the thirty day or ten-day
period specified in paragraph 16 2 as applicable and in all
other cases within a reasonable time after the claim dispute
or other matter or question has ansen, and in no event shall
an} such demand be made after the date when institution of
legal or equitable proceedings based on such claim dispute
or other matter in question would be barred by the
applicable statute of limitations
EJCDC GENERAL CONDITIONS 1910 8 (1990ENtim)
W CITY OF FORT COLLINS MODIFICATIONS (REV 9199)
164 Except as provided in paragraph 16 5 below
no arbitration arising out of or relating to the Connect
Documents shall include by consolidation, joinder or in any
other manner any other person or entity (including
ENGINEER, ENGINEERS Consultant and the officers
directors, agents, employees or consultants of any of them)
who is not a party to this contract unless
16 4 1 the inclusion of such other person or entity Is
necessary of complete relief is to be afforded among
those who are already parties to the arbitratiml, and
16 4 2 such other person or entity is substantially
involved in a question of law or fact which its common
to those who are already parties to the arbitration and
which will anse in such pmcwdmgs, and
16 4 3 the written consent of the other person or
entity sought to be included and of OWNER and
CONTRACTOR has been obtained for such mclumon,
which consent shall make specific reference to this
paragraph but no such consent shall constitute consent
to arbitration of any dispute not specifically described
in such consent or to arbitration with any party not
specifically identified in such consent
165 Notwithstanding paragraph 16 4 of a clam
dispute or other matter in question between OWNER and
CONTRACTOR involves the Work of a Subcontractor
either OWNER or CONTRACTOR may join such
Subcontractor as a party to the arbitration between OWNER
and CONTRACTOR hereunder CONTRACTOR shall
include in all subcontracts required by paragraph 611 a
specific provision whereby the Subcontractor consents to
being joined in an arbitration between OWNER and
CONTRACTOR involving the Work of such
Subcontractor Nothing in this paragraph 16 5 nor in the
provision of such subcontract consenting to joinder shall
create any clam right or cause of action in favor of
Subcontractor and against OWNER, ENGINEER or
ENGINEERS Consultants that does not otherwise exist
166 The award rendered by the arbitrators will be
final judgment may be entered upon it many court having
jurisdiction thereof and it will not be subject to
modification or appeal
167 OWNER and CONTRACTOR agree that they
shall fast submit any and all unsettled claims
counterclaims disputes and other matters in question
between them ansnng out of or relating to the Contract
Documents or the breach thereof ( disputes ) to mediation
by the American Arbitration Association under the
Construction Industry Mediation Rules of the American
Arbitration Association pnor to either of them imitating
against the other a demand for arbitration pursuant to
paragraphs 16 1 through 16 6 unless delay in Imbuing
arbitration would urevccably prejudice one of the parties
The respective thirty and ten day time limits within which
to file a demand for arbitration as provided in paragraphs
16 2 and 16 3 above shall be suspended with respect to a
dispute submitted to mediation within those same
applicable time lemits and shall remain suspended until ten
days after the termination of the mediation The mediator
of any dispute submitted to medtation under this Agreement
shall not serve as arbitrator of such dispute unless otherwise
agreed
bC At
SECTION 00800
SUPPLEMENTARY CONDITIONS
SECTION 00800
SUPPLEMENTARY CONDITIONS
Conditions of the Contract
These Supplementary Conditions amend or supplement the General Conditions of
the Construction Contract (EJCDC General Conditions 1910-8 1990 edition with
City of Fort Collins modifications) and other provisions of the Contract
Documents as indicated below
SC-5 4 8 Limits of Liability
A Add the following language at the end of paragraph 5 4 8
The limits of liability for the insurance required by the paragraph
numbers of the General Conditions listed below are as follows
5 4 1 and 5 4 2
Coverage A - Statutory Limits
Coverage B - $100 000/$100 000/$500 000
5 4 3 and 5 4 5 Commercial General Liability policy will have limits of
$1 000,000 combined single limits (CSL) This policy will include
coverage for Explosion, Collapse and Underground coverage unless waived
by the Owner
5 4 6The Comprehensive Automobile Liability Insurance policy will have
limits of $1 000 000 combined single limits (CSL)
5 4 9 This policy will include completed operations coverage/product
liability coverage with limits of $1 000 000 combined single limits
(CSL)
Rev 10/20/07 Section 00800 Page 1
WORK CHANGE DIRECTIVE
INSTRUCTIONS
A GENERAL INFORMATION
This document was developed for use in situations Involving changes in the Work which, if not processed
expeditiously, might delay the Project these changes are often initiated in the field and may affeet the
Contract Price or the Contract Times This is not a Change Order, but only a dnwtive to proceed with Work
that may be included in a subsequent Change Order
For supplemental instructions and minor shangea not involving a change in the Contract Price or the Contract
Times a Field Order should be used
& COMPLETING THE WORK CHANGE DIRECTIVE FORM
Engineer initiates the form, msludmg a description of the items involved and attachments
Based on conversations between Engineer and Contractor Engineer completes the following
MFTHOD OF DETERMINING CHANGE, If ANY, IN CONTRACT PRICE Mark the method to
be used in determining the final cost of Work involved and the estimated net effect on the Contract
Price If the change involves an increase in the Contract Price and the estimated amount is
approached before the additional or changed Work is completed, another Work Change Directive
must be issued to change the estimated pruc or Contractor may stop the changed Work when the
estimated time is reached If the Work Change Directive ism likely to change the Contract price,
the space for estimated increase (decrease) should be marked "Not Applicable"
Once Engineer has completed and signed the form, all copies should be sent to Owner for authorization
because Fngmeer alone doss not have authority to authorize changes in Price or Times Once authorized
by Owner a copv should be sent by Engineer to Contractor Price and Times may only be changed by
Change Order signed by Ownet and Contractor with Engineer's recommendation
Paragraph 14 03 A 2 of the General Conditions requires that a Change Order be initiated and processed to
covet any undisputed stun or amount of time for Work actually performed pursuant to this Work Change
Directive
Once the Work covered by this directive is completed or final cost and tunes are determined, Contractor
should submit documentation for inclusion m a Change Order
THIS IS A DIRECTIVF TO PROCEED WI A CHANGE THAT MAY AFFECT THE CONTRACT
PRICE OR CONTRACT TIMES A CHANGF ORDER, IF ANY, SHOULD BE CONSiIlMD
PROMPTLY
WORK CHANGE DIRECTIVE
No
DATE OF ISSUANCE EFFECTIVE DATE
OWNER
CONTRACTOR _
Contract
Project
OWNER's Contract No
ENGINEER s Project No
You are directed to proceed promptly with the following change(s)
Description
Purpose of Work Change Directive
Attachments (List documents supporting change)
If OWNER oT CONTRACTOR believe that the above change has affected Contract Price any Claim for a
Change Order based thereon will involve one or more of the following methods as defined in the
Contract Documents
Method of determining change in
Contract Price
Unit Prices
Lump Sum
Cost of the
Estimated increase (decrease) in Contract Price Estimated increase (decrease) in Contract
$ Times
If the change involves an increase the estimated Substantial Completion _ days
amount is not to be exceeded without further Ready for final payment _days
authorization
RECOMMENDED AUTHORIZED
ENGINEER OWNER
R
EJCDC No 1%EtlRion) By
by
Wide, ,e ananounr rtlini6wmr tbaunmrComnlou pN mdmrd OY 7fie AroGred Gmanl ConnaclortofAmrip rid as Conwoedan Spclawkw aWmro
SECTION 00100
INSTRUCTIONS TO BIDDERS
1 0 DEFINED TERMS
Terms used in these Instructions to Bidders which are defined in
the Standard General Conditions of the Construction Contract (No
1910-8 1990 ed ) have the meanings assigned to them in the
General Conditions The term "Bidder means one who submits a Bid
to OWNER as distinct from a sub -bidder who submits a Bid to
Bidder The terms "Successful Bidder" means the lowest
qualified responsible and responsive Bidder to whom OWNER (on
basis of OWNER's evaluation as hereinafter provided) makes an
award The term "Bidding Documents' includes the Advertisement or
Invitation to Bid, Instructions to Bidders the Bid Form and the
proposed Contract Documents (including all Addenda issued prior to
receipt of Bids)
2 0 COPIES OF BIDDING DOCUMENTS
2 1 Complete sets of Bidding Documents may be obtained as stated
in the Invitation to Bid No partial sets will be issued The
Bidding Documents may be examined at the locations identified in
the Invitation to Bid
2 2 Complete sets of Bidding Documents shall be used in
preparing Bids neither OWNER nor Engineer assumes any
responsibility for errors or misinterpretations resulting from the
use of incomplete sets of Bidding Documents
2 3 The submitted Bid proposal shall include Sections 00300
00410 00420 and 00430 fully executed
2 4 OWNER and Engineer in making copies of Bidding Documents
available on the above terms do so only for the purpose of
obtaining Bids on the Work and do not confer a license or grant
for any other use
3 0 QUALIFICATION OF BIDDERS
3 1 To demonstrate qualifications to perform the Work each
Bidder must submit at the time of the Bid opening a written
statement of qualifications including financial data a summary of
previous experience previous commitments and evidence of
authority to conduct business in the jurisdiction where the
Project is located Each Bid must contain evidence of Bidder s
qualification to do business in the state where the Project is
located or covenant to obtain such qualification prior to award of
the contract The Statement of Qualifications shall be prepared
on the form provided in Section 00420
Rev 10/20/07 Section 00100 Page 1
Advencamant
ofc-hnolaegoa
t�a^dapY
REQUEST FOR
INTERPRETATION
Project
R F I Number
From
To
Date
A/E project Numba
Re
Contract For
Specification Smion Paragraph
Drawing Reference
Detail
Request
Signed by
Daze
Response
❑ Attachments
Response From TO Date Rec d Date Retad
Signed by Date
Copses ❑ Owner ❑ Consultants ❑ ❑ ❑ ❑
❑ He
Copyright 1994 Construction Spwlflcaaom hntnute Page of July 19N
99 COW[ C w Plea Suite 300 Almandna VA 22314 CSI Fonn 13 2A
nd'—fogy
rant
v' aruoo
nnoagy
CLARIFICATION
NOTICE
project Clarification Notice Number
To
Form
Date
A/E Project Number
Re ContractFor
This Chinfidatinn Notice is issued for the purpose of clanfymg the Contract Documents based on an interpretation reasonably inferable
from the Contract Documents and therefore has no effect on the Contract Sum or Contract Time Proonding with Wore in accordance
with this Clarification Nonce indicates acceptance with no change in the Contract Sum or Contract Time
SPemfieanon Section Paragraph Drawing Reference Detail
Description
❑ Attachments
Signed by
Date
Copies ❑ Owner ❑ Consultants ❑ ❑ ❑ ❑ ❑ File
CePYnsm 1994 Construction Specificenom merman, Page of July 19
99 Canal Cema 94
22114 Pfau Store 300 Alexandria VA CSI Form 13 94
IV of Ccuc.maemem
err Ccnon
Uehaabpy
FIELD
ORDER
Project
To
Re
Field Order Number
From
Date
A/E Project Number
Contract For
You are hereby directed to execute promptly this Field Order which interprets the Contract Documents or orders minor changes in the
Work without change in Contract Sum or Contract Time
If you consider that a change in Contract Sum or Contract Time is required submit a Change Order Request to the A/E Immediately and
prior to Isweading with this Work
Specification Section Paragraph Drawing Reference Detail
Description of Interpretation or Change
❑ Attachments
Signed by
Date
Copies ❑ Owner ❑ Consultants ❑ ❑ ❑ ❑
❑ Fit,
Copyright 1994 Cansuoction Specifimtion institute Page of July 1994
99 Canal Caner Plea Suite 300 Alexandria VA 22314 CSI Form 13 4A
October 05, 2007
US DEPT OF LABOR,
DAVIS BACON MINIMUM WAGES, COLORADO
GENERAL DECISION NUMBERS CO20070014 AND CO20070015
HIGHWAY CONSTRUCTION
NOTICE
This is a standard special provision that revises or modifies CDOT s Standard Specifications for Road and Bridge
Construction It has gone through a formal review and approval process and has been issued by CDOT s Project
Development Branch with formal instructions for its use on CDOT construction projects It is to be used as
written without change Do not use modified versions of this special provision on CDOT construction projects
and do not use this special provision on CDOT projects in a manner other than that specified in the instructions,
unless such use is first approved by the Standards and Specification Unit of the Project Development Branch The
instructions for use on CDOT construction projects appear below
Other agencies which use the Standard Spectf cations for Road and Bridge Construction to administer
construction projects may use this special provision as appropriate and at their own risk
Instructions for use on CDOT construction projects
Use this standard special provision on all federal aid projects with contracts exceeding $2000 except for
projects on roadways classified as local roads or rural minor collectors which are exempt
-1-
Decision Nos CO20070014 and CO20070015 dated February 09,
Modifications
ID
2007 supersedes Decision Nos CO030014 and CO030015 dated
June 13 2003
Pages 1 5
MOD 1 04 06-07 paes 1 2, 5
MOD 2 06-01 07 5
1
2
When work within a project is located ing
two or more counties and
the minimum wages and fringe benefits are different for one or more
MOD 3 08 03-07 &
3
job classifications, the higher nunmium wages and fringe benefits
MOD 4 09-07 07 Pages 1 5
4
shall apply throughout the project
MOD 5 10-05-07 Pages 1 5
5
Pages 1 2 4
General Decision No CO20070014 applies to the following counties Adams, Arapahoe, Boulder Denver, Douglas El Paso,
Jefferson Latimer Mesa Pueblo and Weld counties
General Decision No CO20070014
The wage and fnn a benefits listed below reflect collectively bar lained rates
Basic Hourly
Fringe Benefits
Last
Code
Classification
Rate
Mod
ELECTRICIANS
1200
Electrical work $150,000 or less (Pueblo county)
2214
8 85 + 3%
1201
Electrical work over $150,000 (Pueblo county)
2629
8 85 + 3%
1
1202
Electricians (Adams Arapahoe, Boulder Denver,
Douglas Jefferson Lanmer, and Weld counties)
2g 91
10 33
1203
Electricians (El Paso county)
2680
12 00 + 3%
3
1204
Electricians (Mesa county)
2031
856
2
1205
Traffic Signal Installer (Zone 1)
23 83
4 75 + 13 75%
4
1206
Traffic Signal Installer (Zone 2)
2683
4 75 + 13 75%
4
Traffic Installer Zone Definitions
Zone I - Within a 35 mile radius measured from the
addresses
of the following cities
Colorado Springs Nevada & Bijou
Denver Ellsworth Avenue & Broadway
Ft Collins - Prospect & College
Grand Junction 12th & North Avenue
Pueblo 125 & Highway 50
Zone 2 All work outside these areas
POWER EQUIPMENT OPERATORS
1300
Asphalt Screed
21 67
822
2
1301
Bituminous or Asphalt Spreader/Laydown Machine
21 67
822
2
1302
Bulldozer
21 67
822
2
-2-
General Decision No CO20070014
The wage and fringe benefits listed below reflect collectively bargained rates
Basic Hourly
Fringe Benefits
Last
Code
Classification
Rate
Mod
POWER EQUIPMENT OPERATORS (cont)
Crane
1305
50 tons and under
2182
822
2
1306
51 to 90 tons
2197
822
2
1307
91 to 140 tons
2212
822
2
1308
141 tons and over
2288
822
2
Drill Operator
1309
William MF/Watson 2500 only
2197
822
2
Grader/Blade
1310
Rough
2167
822
2
1311
Finish
2197
822
2
Loader
1312
Barber Green etc 6 cubic yards and under
2167
822
2
1313
Over 6 cubic yards
2182
822
2
Mechanic and/or Welder (Includes heavy duty and
combination mechanic and welder)
1314
Mechanic and/or Welder
21 82
822
2
1315
Mechanic/Welder (Heavy duty)
21 97
822
2
1316
Oiler
2097
822
2
Power Broom
1317
Under 70 HP
2097
822
2
1318
70 HP and over
2167
822
2
Roller (excluding dirt and soil compaction)
1319
Self propelled, rubber tires under 5 tons
21 32
822
2
1320
Self propelled all types over 5 tons
21 67
822
2
Scraper
1321
Single bowl under 40 cubic yards
2182
822
2
1322
Single bowl including pups 40 cubic yards and tandem
bowls and over
21 97
822
2
1323 1
Trackhoe
21 82
822
2
General recision No CO20070014
The wage and fringe benefits listed below reflect collectively bargained rates
Basic Hourly
Fringe Benefits
Last
Code
Classification
Rate
Mod
Laborers
1400
Asphalt Laborer/Raker Common Laborer
and Concrete Laborer/Mason Tender
1629
425
General Decision No CO20070014
The wage and fringe benefits listed below do not reflect collectively bargained rates
1500
Bricklayers
1555
285
Carpenters
1600
Form Work (Excluding curbs and gutters)
1654
390
1601
All other work
1661
388
1700
Concrete Finishers/Cement Masons
1605
300
Ironworkers
1900
Reinforcing
1669
545
1901
Bridge Rail (Excludes guardrail)
1822
601
Laborers
2001
Fence Erector (Includes fencing on bndges)
1302
320
2002
Form Work (Curbs and gutters only)
1185
345
2003
Guardrail Erector (Excludes bndgerail)
1289
320
2004
Landscape and Irrigation Laborer
1226
3 16
2005
Pipelayer
1355
241
2006
Striping Laborer (Pre -form layout and removal of
pavement markings)
12 62
3 21
2007
Traffic Director/Flagger
955
305
2008
Traffic and Sign Laborer (Sets up barricades and cones
and installs permanent signs)
12 43
3 22
PAINTERS
2100
Brush
1694
2 10
2101
Spray
1699
287
POWER EQUIPMENT OPERATORS
2200
Backhoes
1654
424
2201
Bobcat/Skid Loader
1537
428
2202
Concrete Pump Operator
1652
430
General Decision No CO20070014
The wage and fringe benefits listed below do not reflect collective) bargained rates
Basic Fringe Benefits Last
Code Classification Hourly Rate Mod
POWER EQUIPMENT OPERATORS (cont)
Drill Operator
2203
All except William MF/Watson 2500
1674
266
2204
Forklift
1591
409
2205
Rotomill Operator
1622
441
2206
Post Dnver/Punch Machine
1607
441
2207
Tractor
13 13
295
2208
Compactor (Dirt and soil only)
1670
330
Groundman (Traffic signalization)
2301
Class C
1144
325
Truck Drivers
2400
Floats Semi Truck
1486
308
2401
Multipurpose Truck — Specialty & Hoisting
1435
349
2402
Truck Mechamc
1691
301
2403
Pickup Truck (Includes Pilot and Sign/Bamcade Truck)
1393
368
2405
Single Axle Truck
1424
3 77
2406
Distributor Truck
1580
527
2407
Dump Truck
2408
14 cubic yards and under
1493
527
2409
15 to 29 cubic yards
1527
527
2410
30 to 79 cubic yards
15 80
527
2411
80 cubic yards and over
1645
527
2412
Low Boy Truck
1725
527
2413
Water Truck
1493
527
5
WELDERS Receive rate prescribed for craft performing operation to which welding is incidental
Unlisted classifications needed for work not included within the scope of the classifications listed may be added
after award only as provided in the labor standards contract clauses [29 CFR 5 5(a)(1)(ii))
END OF GENERAL DECISION NUMBER CO20070014
M
General Decision No CO070015 applies to the following counties Alamosa Archuleta Baca, Bent, Chaffee, Cheyenne, Clear
ICreek Conejos, Costrlla, Crowley Custer Delta, Dolores Eagle, Elbert Fremont, Garfield Gilpin Grand Gunnison, Ilmsdale,
Huerfano, Jackson Kiowa Kit Carson, La Plata Lake, Las Ammas, Lincoln, Logan Mineral, Moffat, Montezuma, Montrose,
Morgan Otero Ouray Park Phillips Pitkin Prowers Rio Blanco, Rio Grande Routt Saguache, San Juan San Miguel
Sedgwick, Summit, Teller, Washington and Yuma counties
When work within a project is located in two or more counties, and the mmnnum wages and fringe benefits are different for one
or more job classifications the higher mmunum wages and fringe benefits shall apply throughout the project
General Decision No CO20070015
The wa a and fringe benefits listed below reflect collectively bar ained rates
Basic Fringe Benefits Last
Code Classification Hourly Rate Mod
ELECTRICIANS (Including traffic signal installation)
Electrical work $150 000 or less (Alamosa Archuleta,
3200 Baca, Bent Chaffee, Conejos, Costilla Crowley Custer 22 14 8 85 + 3%
Fremont Huerfano, Kiowa, Las Ammas, Mineral, Otero,
Prowers Rio Grande and Saguache counties)
Electrical work over $150 000 (Alamosa Archuleta
3201 Baca Bent, Chaffee Conejos Costrlla Crowley, Custer, 26 29 8 85 + 3% 1
Fremont, Huerfano Kiowa Las Animas Mineral Otero
Prowers Rio Grande and Saguache counties)
Electricians (Clear Creek Eagle Gilpm, Grand Jackson
3202 Lake Logan Morgan Phillips Sedgwick Summit 2891 1033
Washington, and Yuma counties)
3203 Electricians (Cheyenne Elbert Kit Carson Lincoln 26 80 12 00+ 3% 3
Park and Teller counties)
Electricians (Dolores Garfield Gunnison Hinsdale La
3204 Plata, Moffat, Montezuma Ouray, Pitkin, Rio Blanco 2806 876 2
Routt, San Juan and San Miguel counties)
3205 Electricians (Delta and Montrose counties) 2031 856 2
3206 Traffic Signal Installer (Zone 1) 2383 4 75 + 13 75% 4
3207 Traffic Signal Installer (Zone 2) 2683 4 75 + 13 75% 4
Traffic Installer Zone Defimtions
Zone 1 — Within a 35 nine radius measured from the
addresses
of the following cities
Colorado Springs Nevada & Bijou
Denver Ellsworth Avenue & Broadway
Ft Collins Prospect & College
Grand Junction 12th & North Avenue
Pueblo I-25 & Highway 50
Zone 2 - All work outside these areas
We
General Decision No CO20070015
The wage and fringe benefits listed below reflect collectively bargained rates
Basic Hourly
Fringe Benefits
Last
Code
Classification
Rate
Mod
POWER EQUIPMENT OPERATORS
3300
Bituminous or Asphalt Spreader/Laydown Machine
2167
822
2
3301
Bulldozer
21 67
822
2
Crane
3302
50 tons and under
2182
822
2
3303
51 to 90 tons
21 97
822
2
3304
91 to 140 tons
2212
822
2
3305
141 tons and over
2288
822
2
3306
Grade Checker
21 82
822
2
Loader
3307
Barber Green etc 6 cubic yards and under
21 67
822
2
3308
Over 6 cubic yards
21 82
822
2
Roller (excluding dirt and soil compaction)
3309
Self-propelled rubber tires under 5 tons
21 32
822
2
3310
Self propelled all types over 5 tons
21 67
822
2
3311
Trackhoe
21 82
822
2
3312
Oiler
2097
822
2
3313
Water Wagon
21 82
822
2
General Decision No CO20070015
The wage and fringe benefits listed below do not reflect collectively bargained rates
Carpenters
3600
Form Building and Setting (Excluding curbs and gutters)
1592
5 38
3601
All other work
1630
371
3700
Concrete Finishers/Cement Masons
1555
285
3800
Groundman (Traffic signalization)
11 57
350
Ironworkers
3900
Reinforcing
1694
677
3901
Bridge Rail (Excluding guardrail)
1676
601
4 0
3 2 In accordance with Section 8-160 of the Code of the City of
Fort Collins in determining whether a bidder is responsible, the
following shall be considered (1) The ability capacity and skill
of the bidder to perform the contract or provide the services
required (2) whether the bidder can perform the contract or
provide the service promptly and within the time specified without
delay or interference, (3) the character integrity reputation,
judgment experience and efficiency of the bidder (4) the quality
of the bidder's performance of previous contracts or services (5)
the previous and existing compliance by the bidder with laws and
ordinances relating to the contract or service (6) the
sufficiency of the financial resources and ability of the bidder
to perform the contract or provide the service, (7) the quality
availability and adaptability of the materials and services to the
particular use required (8) the ability of the bidder to provide
future maintenance and service for the use of the subject of the
contract and (9) any other circumstances which will affect the
bidder s performance of the contract
3 3 Each Bidder may be required to show that he has handled
former Work so that no just claims are pending against such Work
No Bid will be accepted from a Bidder who is engaged on any other
Work which would impair his ability to perform or finance this
Work
3 4 No Bidder shall be in default on the performance of any other
contract with the City or in the payment of any taxes licenses or
other monies due to the City
EXAMINATION OF CONTRACT DOCUMENTS AND SITE
4 1 It is the responsibility of each Bidder before submitting a
Bid to (a) examine the Contract Documents thoroughly (b) visit
the site to familiarize himself with local conditions that may in
any manner affect cost progress or performance of the Work (c)
familiarize himself with federal state and local laws
ordinances rules and regulations that may in any manner affect
cost progress or performance of the Work (d) study and carefully
correlate Bidder s observations with the Contract Documents and
(e) notify Engineer of all conflicts, errors or discrepancies in
the Contract Documents
4 2 Reference is made to the Supplementary Conditions for
identification of Subsurface and Physical Conditions SC-4 2
4 3 The submission of a Bid will constitute an incontrovertible
representation by Bidder that Bidder has complied with every
requirement of this Article 4 that without exception the Bid is
premised upon performing and furnishing the Work required by the
Rev 10/20/07 Section 00100 Page 2
-7-
General Decision No CO20070015
The wage and fnnge benefits listed below do not reflect collectively bargained rates
Basic Hourly
Fringe Benefits
Last
Code
Classification
Rate
Mod
Laborers
4000
Asphalt Laborer/Raker
1240
292
4001
Common
1244
353
4002
Concrete Laborer/Mason Tender
1244
3 10
4003
Striping -Paint Laborer (Pre -form layout and removal of
pavement markings)
12 90
3 07
4004
Traffic Director/Flagger
942
321
4005
Traffic/Sign Laborer (Sets up barricades and cones,
and installs permanent signs)
12 39
3 20
4007
Guardrail (Excludes bndgerail)
1278
331
4008
Formwork (Curbs and gutters only)
1292
454
4009
Landscape Laborer (Including imgation work)
1221
3 16
Painters
4100
Spray
1754
352
POWER EQUIPMENT OPERATORS
4200
Asphalt Plant
1723
120
4201
Asphalt Screed
1621
376
4202
Backhoe
1642
442
4203
Compactor (Dirt and soil only)
1652
3 13
4204
Grader/Blade
1639
420
4205
Mechanic and or Welder (Includes heavy duty and
combination mechanic welder)
1674
420
4206
Post Dnver/Punch Machine
1607
441
4207
Rotomill Operator
1628
441
4209
Scraper
1762
3 16
m
General Decision No CO20070015
The wage and fringe benefits listed below do not reflect collectively bargained rates
Basic Hourly
Fringe Benefits
Last
Code
Classification
Rate
Mod
Truck Driers
4400
Dump
1415
383
4401
Low Boy
1507
456
4402
Truck Mechanic
1597
461
4403
Multipurpose Truck -Specialty and Hoisting
1460
349
4404
Pickup (Including pilot car)
1404
349
4405
Water Truck
1488
207
4406
Distributor
1580
527
WELDERS - Receive rate prescribed for craft perfomvng operation to which welding is incidental
Unlisted classifications needed for work not included within dde
the scope of the classifications listed may be ad
after award only as provided in the labor standards contract clauses [29 CFR 5 5(a)(1)(ri)]
ENDOFGENERAL DECISION NUMBER CO20070015
WAGE DETERMINATION APPEALS PROCESS
1 ) Has there been an initial decision in the matter? This can be
♦ an existing published wage determination
♦ a survey underlying a wage determination
♦ a Wage and Hour Division letter setting forth a position on a wage determination matter
♦ a conformance (additional classification and rate) ruling
On survey related matters initial contact including requests for summaries of surveys should be with
the Wage and Hour Regional Office for the area in which the survey was conducted because those
Regional Offices have responsibility for the Davis -Bacon survey program If the response from this
initial contact is not satisfactory then the process described in 2 ) and 3 ) should be followed
With regard to any other matter not yet ripe for the formal process described here initial contact should
be with the Branch of construction wage Determinations Write to
Branch of Construction Wage Determinations
Wage and Hour Division
US Department of Labor
200 Constitution Avenue N W
Washington D C 20210
2 ) If the answer to the question in 1 ) is yes then an interested party (those affected by the action) can
request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 18 and
29 CFR Part 7) Write to
Wage and Hour Administrator
U S Department of Labor
200 Constitution Avenue N W
Washington D C 20210
The request should be accompanied by a full statement of the interested party s position and by any
information (wage payment data protect description area practice material etc ) that the requestor
considers relevant to the issue
3 ) If the decision of the Administrator is not favorable an interested party may appeal directly to the
Administrative Review Board (formerly the Wage Appeals Board) Write to
Administrative Review Board
U S Department of Labor
200 Constitution Avenue N W
Washington D C 20210
4 ) All Decisions of the Administrative review board are final
Rev 10/20/07
SECTION 00900
ADDENDA MODIFICATIONS AND PAYMENT
00950 Contract Change Order
00960Application for Payment
SECTION 00950
CHANGE ORDER NO
PROJECT TITLE
CONTRACTOR
PROJECT NUMBER
DESCRIPTION
1 Reason for change
2 Description of Change
3 Change in Contract Cost
4 Change in Contract Time
ORIGINAL CONTRACT COST
$ 00
TOTAL APPROVED CHANGE ORDER
0 00
TOTAL PENDING CHANGE ORDER
0 00
TOTAL THIS CHANGE ORDER
0 00
TOTAL % OF THIS CHANGE ORDER
TOTAL C 0 % OF ORIGNINAL CONTRACT
ADJUSTED CONTRACT COST
$ 0 00
(Assuming all change orders approved)
ACCEPTED BY
DATE
Contractor's Representative
ACCEPTED BY
DATE
Project Manager
_
REVIEWED BY
DATE
Title
APPROVED BY
DATE
Title
APPROVED BY
DATE
Purchasing Agent over $30 000
cc City Clerk Contractor
Project File Architect
Engineer Purchasing
Rev 10/20/07 Section 00950 Page 1
nnQro
APPLICATION FOR PAYMENT PAGE 1 OF 4
OWNER City of Fort Collins PROJECT APPLICATION NUMBER
APPLICATION DATE
PERIOD BEGINNING
ENGINEER CONTRACTOR PERIOD ENDING
PROJECT NUMBER
CHANGE ORDERS Application is made for Payment as shown below in connection with Contract
NUMBER DATE AMOUNT
1
2
3
The present status of the account for this Contract is as
follows
Original Contract Amount
Net Change by Change Order
Current contract Amount
Total Completed and Stored to Date
Less Previous Applications
Amount Due this Application Before Retamage
Less Retamage
Net Change by Change Order $0 00 I AMOUNT DUE THIS APPLICATION
CERTIFICATION
The undersigned CONTRACTOR certifies that all obligations of CONTRACTOR incurred in connection with
the Work have been satisfied as required in Paragraph 14 3 of the General Conditions of the Contract
The above Amount Due This Application is requested by the
CONTRACTOR
Date
By
Payment of the above Amount Due This Application is recommended by the ENGINEER
Date
By
Payment of the above Amount Due This Application has been reviewed by the OWNER S Project Manager
Date
M
Payment of the above Amount Due This Application is approved by the OWNER
$0 00
$0 00
Section 00960 Page 1
APPLICATION FOR
CONTRACT AMOUNTS
PAYMENT
PAGE 2 OF 4
Work
Work
Work
Completed
Completed
Completed
Stored
Bid
This
Previous
To
Item
Month
Periods
Date
Materials
Total
Unit
This
Earned Percent
Number Description Quantity Units Price Amount
Qty
Amount
Qty Amount
Qty
Amount
Period
To Date Billed
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
TOTALS $0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
Section 00960 Page 2
CHANGE ORDERS
Bid
Item
Unit
Number Description Quantity Units Price
Amount
APPLICATION FOR PAYMENT
Work Work
Work Completed Completed Completed
This Previous To
Month Periods Date
Qty Amount Qty Amount Qty Amount
Stored
Materials
This
Period
PAGE 3 OF 4
Total
Earned Percent
To
Date Billed
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0
$0 00
$0 00
$0 00
00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$o 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$o 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$o 00
$o 00
$0 00
$0 00
$0 00
TOTALS CHANGE ORDERS
$0 00
$0 00
$0 00
$0 00
$0 00
PROJECT TOTALS
$0 00
$0 00
$0 00
$0 00
$o 00
Section 00960 Page 3
STORED MATERIALS
SUMMARY
PAGE 4OF4
On Hand Received Installed
Item Invoice
On Hand
Previous This This
Number Number Description Application Period Period
This
ADDlication
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
$0 00
TOTALS $0 00 $0 00
$0 00 $0 00
Section 00960 Page 4
TROLLEY BRICK RESTORATION PROJECT
GENERAL REQUIREMENTS INDEX
SECTION
01010 Summary of Work
01040 Coordination
01310 Construction Schedules
01330 Survey Data
01340 Shop Drawings
01410 Testing
01510 Temporary Utilities
01560 Temporary Controls
01700 Contract Closeout
01800 Method of Measurement and Basis of Payment
PAGE NUMBERS
General Requirements 1 2
General Requirements 34
General Requirements 5 6
General Requirements 7
General Requirements 8 10
General Requirements 11 12
General Requirements 13
General Requirements 14 15
General Requirements 16
General Requirements 17
Contract Documents and such means methods techniques sequences
or procedures of construction as may be indicated in or required
by the Contract Documents and that the Contract Documents are
sufficient in scope and detail to indicate and convey
understanding of all terms and conditions for performance and
furnishing of the Work
5 0 INTERPRETATIONS AND ADDENDA
5 1 All questions about the meaning or intent of the Bidding Documents
are to be submitted in writing to the Engineer and the OWNER
Interpretation or clarifications considered necessary in response
to such questions will be issued only by Addenda Questions
received less than seven days prior to the date for opening of the
Bids may not be answered Only questions answered by formal
written Addenda will be binding Oral and other interpretations
or clarifications will be without legal effect
5 2 All questions concerning the scope of this project should be
directed to the Engineer Questions regarding submittal of bids
should be directed to the City of Fort Collins' Purchasing
Division
5 3 Addenda may also be issued to modify the Bidding Documents
as deemed advisable by OWNER or Engineer
5 4 Addenda will be mailed or delivered to all parties recorded
by the OWNER as having received the Bidding documents
6 0 BID SECURITY
6 1 Each Bid must be accompanied by Bid Security made payable to
OWNER in the amount stated in the Invitation to Bid The required
security must be in the form of a certified or bank cashier's
check payable to OWNER or a Bid Bond on the form enclosed
herewith The Bid Bond must be executed by a surety meeting the
requirements of the General Conditions for surety bonds
6 2 The Bid Security of the successful Bidder will be retained
until such Bidder has executed the Agreement and furnished the
required contract security whereupon Bid Security will be
returned If the successful Bidder fails to execute and deliver
the Agreement and furnish the required contract security within 15
days of the Notice of Award OWNER may annul the Notice of Award
and the Bid Security of that Bidder will be forfeited The Bid
Security of other Bidders whom OWNER believes to have reasonable
chance receiving the award may be retained by OWNER until the
earlier of the seventh day after the effective date of the
Agreement or the thirty-first day after the Bid Opening whereupon
Bid Security furnished by such Bidders will be returned Bid
Security with Bids which are not competitive will be returned
Rev 10/20/07 Section 00100 Page 3
SECTION 01010
SUMMARY OF WORK
1 1 DESCRIPTION OF WORK
A This work shall consist of the removal salvage and restoration of the existing bnck/concrete roadbed adjacent to
the historical trolley tracks on East Mountain Avenue between College Avenue and Peterson Street m the Cityof
Fort Collins The bricks shall be removed and salvaged to the maximum extent feasible The salvaged bricks
supplemented by new bricks shall be replaced in the trolley roadbed This work will also include and related
concrete removal and traffic control Specific locations are described in Section 3500 Project Map
B Protection and Restoration
I Replace to equal or better conditions all items removed and replaced or damaged during construction Restore
all areas disturbed to match surrounding surface conditions Also see tree protection standards
C Construction Hours
Construction hours except for emergencies shall be limited to 7 00 a in to 6 00 p in Monday through Friday
unless otherwise authorized in writing by the Engineer After hour equipment operation shall be in accordance
with Section 1560
Any work performed by the Contractor outside of the construction hours whether or not authorized by the
Engineer shall entitle the Owner to deduct from compensation due to the Contractor sufficient funds to cover
the Owner s costs in providing field engineering and/or inspection services because of such work The cost for
field engineering and inspection shall be $50 00 per hour
1 2 NOTICES TO PRIVATE OWNERS AND AUTHORITIES
A Notify private owners of adjacent property utilities irrigation canal and affected governmental agencies when
prosecution of the Work may affect them
B Give notification 48 hours in advance to enable affected persons to provide for their needs when it is necessary to
temporarily deny access or services
C Contact utilities at least 48 hours prior excavating near underground utilities
D Contact all agencies at least 72 hours prior to start of construction Notify all agencies of the proposed scope of
work schedule and any items which would affect their daily operation
E Enka Keeton will be the ENGINEER (Project Engineer/Manager)
Enka Keeton 970 221 6605 Mobile/Pager 970 222 0787
F Names and telephone numbers of affected agencies and utilities in the area are listed below for Contractors
convenience
General Requirements Page 1 of 17
UTILITIES
Water
City of Fort Collins Colorado
970 221 6700 Meter Shop 970 221 6759
Storm Sewer
City of Fort Collins Colorado
970 221 6700
Sanitary Sewer
City of Fort Collins Colorado
970 221 6700
Electrical
City of Fort Collins Colorado
970 221 6700
Gas
Excel Energy
970-482 5922 970 221 8553
Telephone
Qwest
970 484 0300 970 226 6310
Traffic Operations
City of Ft Collins Colorado
970 221 6608
Cable Television
Comcast
970 493 7400
*Uhhty Locates Under One call System
1 800 922 1987
AGENCIES
Safety
Occupational Safety and Health Administration
(OSHA) 844 3061
Fire
Poudre Fire Authority
Non -Emergency 970 221 6581
Emergency 911
Police
City of Fort Collins Police Department
Non Emergency 970 221 6550
Emergency 911
Postmaster
US Postal Service 970 225 4111
Transportation
Transfort 970 221 6620
Traffic Engineering 970 221 6608
END OF SECTION
Larimer County Sheriffs Department
Non Emergency 970 221 7177
Ambulance
Poudre Valley Hospital
Non Emergency 970-484 1227
Emergency 911
General Requirements Page 2 of 17
SECTION 01040
COORDINATION
I 1 GENERAL CONTRACTOR RESPONSIBILITIES
A Coordinate operations under contract in a manner which will facilitate progress of the Work The Contractor shall
also coordinate with the Landscape Contractor whose Work is separate from the General Contractor' s contract
B Conform to the requirements of public utilities and concerned public agencies in respect to the timing and manner
of performance of operations which affect the service of such utilities agencies or public safety
C Coordmate operations under contract with utility work to allow for efficient completion of the Work
D Coordinate all operations with the adjoining property owners business owners and surrounding neighborhoods to
provide satisfactory access at all times and keep them informed at all times
12 CONFERENCES
A A Pre construction Conference will be held prior to the start of construction
Contractor shall participate to the conference accompanied by all major Subcontractors including the Traffic
Control Supervisor assigned to the project
Contractor shall designate/introduce Superintendent and major Subcontractors supervisors assigned to project
The Engineer shall invite all utility companies involved
The Utilities will be asked to designate their coordination person provide utility plans and their anticipated
schedules
The Engineer shall introduce the project Representatives
B Additional project coordination conferences will be held prior to start of construction for coordination of the Work
refining project schedules and utility coordination
C Engineer may hold coordination conferences to be attended by all involved when Contractor's operations affects or
is affected by the work of others
1 Contractor shall participate in such conferences accompanied by Subcontractors as required by the Engineer
13 PROGRESS MEETINGS
A Contractor and Engineers Project Representatives shall schedule and hold regular progress meetings at least
weekly and at other times as requested by the Engineer or required by the progress of the Work
B Attendance shall include
Contractor and Superintendent
Owner s Representatives
Engineer and Resident Project Representative
Traffic Control Supervisor
Others as may be requested by Contractor Engineer or Owner
General Requirements Page 3 of 17
C Minimum agenda shall include
1 Review of work progress since last meeting
2 Identification and discussion of problems affecting progress
3 Review of any pending change orders
4 Revision of Construction Schedule as appropriate
D The Engineer and Contractor shall agree to weekly quantities at the progress meetings The weekly quantity sheets
shall be signed by both parties These quantity sheets when signed shall be final and shall be the basis for the
monthly progress estimates This process ensures accurate monthly project pay estimates
END OF SECTION
General Requirements Page 4 of 17
SECTION 01310
CONSTRUCTION SCHEDULES
11 GENERAL
A The contractor shall prepare a detailed schedule of all construction operations and procurement after review of
tentative schedule by parties attending the pre construction conference This schedule will show how the contractor
intends to meet the milestones set forth
1 No work is to begin at the site until Owners acceptance of the Construction Progress Schedule and Report of
delivery of equipment and materials
12 FORMAT AND SUBMISSIONS
A Prepare construction and procure schedules in a graphic format suitable for displaying scheduled and actual
progress
B Submit two copies of each schedule to Owner for review
1 Owner will return one copy to Contractor with revisions suggested or necessary for coordination of the Work
with the needs of Owner or others
C The schedule must show how the street landscaping and various utility work will be coordinated
13 CONTENT
A Construction Progress Schedule
1 Show the complete work sequence of construction by activity and location
2 Show changes to traffic control
3 Show project milestones
B Report of delivery of equipment and materials
Show delivery status of critical and major items of equipment and materials
Include a schedule which includes the critical path for Shop Drawings tests and other submittal requirements for
equipment and materials reference Section 01340
14 PROGRESS REVISIONS
A Submit revised schedules and reports at weekly project coordination meetings when changes are foreseen when
requested by Owner or Engineer and with each application for progress payment
B Show changes occurring since previous submission
1 Actual progress of each item to date
2 Revised projections of progress and completion
C Provide a narrative report as needed to define
1 Anticipated problems recommended actions and their effects on the schedule
2 The effect of changes on schedules of others
General Requirement& Page 5 of 17
15 OWNERS RESPONSIBILITY
A Owners review is only for the purpose of checking conformity with the Contract Documents and assisting
Contractor in coordinating the Work with the needs of the Project
B It is not to be construed as relieving Contractor from any responsibility to determine the means methods techniques
sequences and procedures of construction as provided in the General Conditions
END OF SECTION
General Requirements Page 6 of 17
SECTION 01330
SURVEY DATA
1 1 SURVEY REQUIREMENTS
A The Owner will provide the construction surveying for the street and landscaping improvements City Survey
Crews will perform the surveying required
B The Contractor must submit a survey request form to the City Surveyors a minimum of 48 hours prior to needing
surveying
C If the requested surveying cannot be accomplished in the time frame requested by the Contractor the survey
personnel shall notify the Contractor with the date on which the requested work will be completed
D Should a sudden change in the Contractor s operations or schedule require the survey personnel to work overtime
the Contractor shall pay the additional overtime expense
E The Contractor shall protect all survey monuments and construction stakes If it is unavoidable to remove a survey
monument or construction stakes the Contractor is responsible for notifying the Surveyor and allowing enough
time for the monuments or stakes to be relocated The Contractor will be responsible for the cost of re staking
construction stakes and for the cost of re establishing a destroyed monument
F The Contractor shall be responsible for transferring the information from the construction stakes to any necessary
forms and for constructing all pipelines drainage ways pavements inlets walls and other structures in accordance
with the information on the stakes and grade sheets supplied by the Owner
END OF SECTION
General Requirements Page 7 of 17
SECTION 01340
SHOP DRAWINGS
11 GENERAL
A Submit Shop Drawings Samples and other submittals as required by individual specification sections
1 Engineer will not accept Shop Drawings or other submittals from anyone but Contractor
B Schedule Reference Section 01310 Construction Schedules Submittals received by Engineer prior to the time set
forth in the approved schedule will be reviewed at any time convenient to Engineer before the time required by the
schedule
C Any need for more than one re submission or any other delay in obtaining Engineer s review of submittals will not
entitle Contractor to extension of the Contract Time unless delay of the Work is directly caused by failure of
Engineer to return any scheduled submittal within 10 days after receipt in his office of all information required for
review of the submittals or for any other reason which prevents Engineer's timely review Failure of Contractor to
coordinate submittals that must be reviewed together will not entitle Contractor to an extension of Contract Time or
an increase in Contract Price
D Resubmit for review a correct submittal if errors are discovered during manufacture or fabrication
E Do not use materials or equipment for which Shop Drawings or samples are required until such submittals stamped
by Contractor and properly marked by Engineer are at the site and available to workmen
F Do not use Shop Drawings which do not bear Engineers mark NO EXCEPTION TAKEN inthe performance of
the Work
Review status designations listed on Engineers submittal review stamp are defined as follows
1 NO EXCEPTION TAKEN
Signifies material or equipment represented by the submittal conforms with the design concept complies with
the information given in the Contract Documents and is acceptable for incorporation in the Work Contractor is
to proceed with fabrication or procurement of the items and with related work Copies of the submittal are to be
transmitted for final distribution
2 REVISE AS NOTED
Signifies material or equipment represented by the submittal conforms with the design concept complies with
the information given in the Contract Documents and is acceptable for incorporation in the Work in accordance
with Engineers notations Contractor is to proceed with the Work in accordance with Engineer's notations and
is to submit a revised submittal responsive to notations marked on the returned submittal or wntten in the letter
of transmittal
3 REJECTED
Signifies material or equipment represented by the submittal does not conform with the design concept or
comply with the information given in the Contract Documents and is not acceptable for use in the Work
Contractor is to submit submittals responsive to the Contract Documents
General Requirements Page 8 of 17
4 FOR REFERENCE ONLY
Signifies submittals which are for supplementary information only pamphlets general information sheets
catalog cuts standard sheets bulletins and similar data all of which are useful to Engineer or Owner in design
operation or maintenance but which by their nature do not constitute a basis for determining that items
represented thereby conform with the design concept or comply with the information given in the Contract
Documents Engineer reviews such submittals for general information but not for substance
1 2 SHOP DRAWINGS
A Include the following information as required to define each item proposed to be furnished
Detailed installation drawings showing foundation details and clearances required for construction
Relation to adjacent or critical features of the Work or materials
Field dimensions clearly identified as such
Applicable standards such as ASTM or Federal Specification numbers
Drawings catalogs or parts thereof manufacturers specifications and data instructions performance
characteristics and capacities and other information specified or necessary
a For Engineer to deterrine that the materials and equipment conform with the design concept and comply
with the intent of the Contract Documents
b For the proper erection installation and maintenance of the materials and equipment which Engineer will
review for general information but not for substance
c For Engineer to determine what supports anchorages structural details connections and services are
required for materials and equipment and the effect on contiguous or related structures materials and
equipment
Complete dimensions clearances required design criteria materials of construction and the like to enable
Engineer to review the mfomiation effectively
B Manufacturers standard drawings schematics and diagrams
1 Delete information not applicable to the Work
2 Supplement standard information to provide information specifically applicable to the Work
C Format
1 Present in a clear and thorough manner
2 Minimum sheet size 8 '/2' x 11
3 Clearly mark each copy to identify pertinent products and models
4 Individually annotate standard drawings which are furnished cross out items that do not apply describe exactly
which parts of the drawing apply to the equipment being furnished
5 Individually annotate catalog sheets to identify applicable items
6 Reproduction or copies of portions of Contract Documents
a Not acceptable as complete fabrication or erection drawings
b Acceptable when used as a drawing upon which to indicate information on erection or to identify detail
drawings
7 Clearly identify the following
a Date of submission
b Project title and number
c Names of Contractor Supplier and Manufacturer
d Specification section number specification article number for which items apply intended use of item in the
work and equipment designation
e Identify details by reference to sheet detail schedule or room numbers shown in the Contract Documents
f Deviations from Contract Documents
g Revisions on re submittals
General Requirements Page 9 of 17
h Contractors stamp metaled or signed certifying to review of submittal verification of products field
measurements and field construction cntena and coordination of the information within the submittal with
requirements of the Work and the Contract Documents
1 3 SUBMISSION REQUIREMENTS
A Make submittals promptly in accordance with approved schedule and in such sequence as to cause no delay in the
Work or in the work of any other contractor
B Minimum number required
1 Shop Drawings
a Three (3) copies minimum two (2) copies which will be retained by Engineer
14 RE SUBMISSION REQUIREMENTS
A Make corrections or changes required by Engineer and resubmit until accepted
B In writing call Engineers attention to deviations that the submittal may have from the Contract Documents
C In writing call specific attention to revisions other than those called for by Engineer on previous submissions
D Shop Drawings
1 Include additional drawings that may be required to show essential details of any changes proposed by
Contractor along with required wrong and piping layouts
END OF SECTION
General Requirements Page 10 of 17
within seven days after the Bid opening
7 0 CONTRACT TIME
The number of days within which or the date by which the Work is
to be substantially complete and also completed and ready for
Final Payment (the Contract Times) are set forth in the Agreement
8 0 LIQUIDATED DAMAGES
Provisions for liquidated damages are set forth in the Agreement
9 0 SUBSTITUTE ( OR EQUAL") MATERIAL AND EQUIPMENT
The Contract if awarded will be on the basis of material and
equipment described on the Drawings or specified in the
Specifications without consideration of possible substitute or -or
equal items Whenever it is indicated on the Drawings or
specified in the Specifications that a substitute or or equal"
item of material or equipment may be furnished or used by
CONTRACTOR if acceptable to Engineer, application for such
acceptance will not be considered by Engineer until after the
effective date of the Agreement The procedure for submittal of
any such application by CONTRACTOR and consideration by Engineer
is set forth in the General Conditions which may be supplemented
in the General Requirements
10 0 SUBCONTRACTORS SUPPLIERS AND OTHERS
10 1 Each Bidder shall submit at the Bid opening to OWNER a list
of principal subcontractors he proposes to use in the Work Refer
to Section 00430 contained within these Documents
10 2 If OWNER or Engineer after due investigation has reasonable
objection to any proposed Subcontractor either may before the
Notice of Award is given request the apparent successful Bidder
to submit an acceptable substitute without an increase in Bid
price If the apparent successful Bidder declines to make any
substitution OWNER may award the contract to the next lowest
responsive and responsible Bidder that proposes to use acceptable
subcontractors Subcontractors suppliers other persons or
organization listed and to whom OWNER or Engineer does not make
written objection prior to the giving of the Notice of Award will
be deemed acceptable to OWNER and ENGINEER subject to revocation
of such acceptance after the effective date of the Agreement as
provided in the General Conditions
10 3 CONTRACTOR shall not be required to employ any
subcontractor supplier or other persons or organizations against
whom he has reasonable objection The use of subcontractors
listed by the Bidder and accepted by OWNER prior to the Notice of
Award will be required in the performance of the Work
Rev 10/20/07 Section 00100 Page 4
SECTION 01410
TESTING
11 GENERAL
A Provide such equipment and facilities as the Engineer may require for conducting field tests and for collecting and
forwarding samples Do not use any materials or equipment represented by samples until tests if required, have
been made and the materials or equipment are found to be acceptable Any product which becomes unfit for use
after approval hereof shall not be incorporated into the work
B All materials or equipment proposed to be used maybe tested at anytime during their preparation or use Furnish
the required samples without charge and give sufficient notice of the placing of orders to permit the testing
Products may be sampled either prior to shipment or after being received at the site of the work
C Tests shall be made by an accredited testing laboratory selected by the Owner Except as otherwise provided
sampling and testing of all materials and the laboratory methods and testing equipment shall be in accordance with
the latest standards and tentative methods of the American Society for Testing Materials (ASTM)
D Where additional or specified information concerning testing methods sample sizes etc is required such
information is included under the applicable sections of the Specifications Any modification of or elaboration on
these test procedures which may be included for specific materials under their respective sections in the
Specifications shall take precedence over these procedures
12 OWNERS RESPONSIBILITIES
A Owner shall be responsible for and shall pay all costs in connection with testing for the following
1 Soil tests except those called for under Submittals thereof
2 Tests not called for by the Specifications of materials delivered to the site but deemed necessary by Owner
3 Concrete test except those called for under Submittals thereof
13 CONTRACTORS RESPONSIBILITIES
A In addition to those inspections and tests called for in the General Conditions Contractor shall also be responsible
for and shall pay all costs in connection with testing required for the following
1 All performance and field testing specifically called for by the specifications
2 All retesting for Work or materials found defective or unsatisfactory including tests covered under 12 above
3 All mimmum call out charges or standby time charges from the tester due to the Contractors failure to pave
pour or fill on schedule for any reason except by action of the Engineer
B Contractor shall notify the Project Engineer 48 hours prior to performing an operation that would require testing
14 CONTRACTOR S QUALITY CONTROL SYSTEM
A General The Contractor shall establish a quality control system to perform sufficient inspection and tests of all items
of Work including that of his subcontractors to ensure conformance to the functional performance of this project
This control shall be established for all construction except where the Contract Documents provide for specific
compliance tests by testing laboratories or engineers employed by the Owner The Contractor s control system shall
specifically include all testing required by the various sections of these Specifications
General Requirements Page 1 I of 17
B Superintendence The Contractor shall employ a full time Superintendent to momtor and coordinate all facets of the
Work The Supenmendent shall have adequate experience to perform the duties of Superintendent
C Contractor's quality control system is the means by which he assures himself that his construction complies with the
requirements of the Contract Documents Controls shall be adequate to coverall construction operations and should
be keyed to the proposed construction schedule
D Records Maintain correct records on an appropriate form for all inspections and tests performed instructions
received from the Engineer and actions taken as a result of those instructions These records shall include evidence
that the required inspections or tests have been performed (including type and number of inspections or test nature
of defects causes for rejection etc ) proposed or directed remedial action and corrective action taken Document
inspections and tests as required by each section of the Specifications Provide copies to Engineer weekly
END OF SECTION
General Requirements Page 12 of 17
SECTION 01510
TEMPORARY UTILITIES
1 1 UTILITIES
A Furnish all utilities necessary for construction
B Make arrangements with Owner as to the amount of water required and time when water will be needed
I Meters may be obtained through the Water Utility Meter Shop at 221 6759
2 Unnecessary waste of water will not be tolerated
C Finnish necessary water trucks pipes hoses nozzles and tools and perform all necessary labor
1 2 SANITARY FACILITIES
A Fumish temporary sanitary facilities at each site for the needs of construction workers and others performing work or
furnishing services on the Project
B Properly maintain sanitary facilities of reasonable capacity throughout construction periods
C Enforce the use of such sanitary facilities by all personnel at the site
D Obscure from public view to the greatest practical extent
END OF SECTION
General Requirements Page 13 of 17
SECTION 01560
TEMPORARY CONTROLS
1 1 NOISE CONTROL
A Take reasonable measures to avoid unnecessary noise when construction activities are being performed inpopulated
areas
B Construction machinery and vehicles shall be equipped with practical sound muffling devices and operated in a
manner to cause the least noise consistent with efficient performance of the Work
C Cease operation of all machinery and vehicles between the hours of 6 00 p in and 7 00 a in
12 DUST CONTROL
A Dusty materials in piles or in transit shall be covered when necessary to prevent blowing
B Earth and road surfaces subject to dusting due to construction activities and detouring of traffic shall be kept moist
with water or by application of a chernical dust suppressant
1 Chemical dust suppressant shall not be injurious to existing or future vegetation
1 3 POLLUTION CONTROL
A Prevent the pollution of drains and water courses by sanitary wastes concrete sediment debris and other substances
resulting from construction activities
I Retain all spent oils hydraulic fluids and other petroleum fluids in containers for disposal off the site
2 Prevent sediment debris or other substances from entering sanitary sewers storm drains and culverts
14 EROSION CONTROL
A Take such measures as are necessary to prevent erosion of soil that might result from construction activities
Measures in general will include
a Control of runoff
b Trapping of sediment
c Minimizing area and duration of soil exposure
d Temporary materials such as hay bales sand bags plastic sheets nprap or culverts to prevent the erosion of
banks and beds of watercourses or drainage swales where runoff will be increased due to construction
activities
B Preserve natural vegetation to greatest extent possible
C Locate temporary storage and route construction traffic so as to preserve vegetation and minimize erosion
D Comply with the City of Fort Collins Storm Drainage Erosion Control Manual
General Requirements Page 14 of 17
1 5 TRAFFIC CONTROL
A Maintain traffic control in accordance with the Manual of Uniform Traffic Control Devices (MUTCD) the City of
Fort Collins Work Area Traffic Control Handbook and the current Latimer County Urban Area Street
Standards In the event of a conflict between the MUTCD criteria and the City is criteria the City s cntena shall
govem
1 6 HAUL ROUTES
The Engineer reserves the right to set haul routes in order to protect pavements both new and old from heavy loads
These pavements may include but are not limited to recently constructed pavements recently overlaid pavements
and/or pavements whose condition would be significantly damaged by heavy loads
END OF SECTION
General Requirements Page 15 of 17
SECTION 01700
CONTRACT CLOSEOUT
1 1 CLEANING AND RESTORATION
A Return the premises and adjacent properties to conditions existing or better than existing at the time the work was
begun This will include providing labor equipment and materials for cleaning repairing and replacing facilities
damaged or soiled during construction The Engineer will be the judge of the degree of restoration required
12 PROJECT RECORD DOCUMENTS
A Maintain on the job site and make available to the Engineer upon request one current marked up set of the
drawings which accurately indicate all approved variations to the completed work that differ from the design
information shown on the drawings Further these drawings should reflect all underground obstacles encountered
B These record drawings along with any survey records photographs and written descriptions of said work as may be
required by the Engineer shall be submitted prior to project acceptance
END OF SECTION
General Requirements Page 16 of 17
SECTION 01800
METHOD OF MEASUREMENT AND BASIS OF PAYMENT
I 1 DEFECTIVE WORK
A Owner will not pay for defective work and will not pay for repair or additional work required to brig the project to
a point of acceptance
12 BID PRICE
A The Total Bid Price covers all Work required by the Contract Documents All work not specifically set forth as a
pay item in the Bid Form shall be considered a subsidiary obligation of Contractor and all costs in connection
therewith shall be included in the prices bid for the various items of Work
B Prices shall include all costs in connection with the proper and successful completion of the Work including
furnishing all materials equipment and tools and performing all labor and supervision to fully complete the Work
C Unit prices shall govern over extensions of sums
D Unit prices shall not be subject to re negotiation
1 3 ESTIMATED QUANTITIES
A All quantities stipulated in the Bid Form at unit prices are approximate and are to be used only as a basis for
estimating the probable cost of the Work and for the purpose of comparing the bids submitted to the Work The
basis of payment shall be the actual amount of materials famished and Work done
B Contractor agrees that he will make no claim for damages anticipated profits or otherwise on account of any
difference between the amount of Work actually performed and materials actually furnished and the estimated
amount therefor
END OF SECTION
General Requirements Page 17 of 17
FEDERAL AID PROJECT NO STE M455 072 October 26 2007
PROJECT CODE NO 15281
COLORADO
DEPARTMENT OF TRANSPORTATION
SPECIAL PROVISIONS
FORT COLLINS TROLLEY BRICK RESTORATION PROJECT
The Colorado Department of Transportation Standard Specifications for Road and Bridge Construction 2005 and
the current Lanmer County Urban Area Street Standards (hereafter referred to as the Standard Specifications )
are made a part of this Contract by this reference except as revised herem and are hereby adopted as the nummum
Standard Specifications of Compliance for this project The following special provisions supplement or modify the
Standard Specifications and take precedence over the Standard Specifications and plans
PROJECT SPECIAL PROVISIONS
Index Page
I
Notice to Bidders
2
Contract Goal
3
Revision of Section 101
Definition of Terms
4
Revision of Section 104
Traffic and Parking Control
5 7
Revision of Section 105
Claims for Contract Adjustment
8
Revision of Section 105
Control of Work
9 10
Revision of Section 107
Protection and Restoration of Property and Landscape
11 12
Revision of Section 107
Insurance
13
Revision of Section 108
Prosecution and Progress
14 15
Revision of Section 201
Clearing and Grubbing
16
Revision of Section 202
Removal of Structures and Obstructions
17 18
Revision of Section 203
Excavation and Embankment
1920
Revision of Section 212
Seeding Fertilizer and Sodding
21 22
Revision of Section 304
Aggregate Base Course
23
Revision of Section 610
Brick Trolley Roadbed
24 25
Revision of Section 630
Construction Zone Traffic Control
2630
Force Account
31
Utilities
32
1
FEDERAL AID PROJECT NO STE M455 072
PROJECT CODE NO 15281
NOTICE TO BIDDERS
City of Fort Collins contact for the project is
Enka Keeton
281 North College Avenue
Fort Collins CO 80524
Office Phone (970) 221 6605
October 26 2007
The above referenced individuals are the only representatives of the Department with authority to provide any
information clarification or interpretation regarding the plans specifications and any other contract documents or
requirements
All references to the Colorado Division of Highways Colorado Department of Transportation and/or Department or
Division shall also mean City of Fort Collins
FEDERAL AID PROJECT NO STE M455 072 October 26 2007
PROJECT CODE NO 15281
CONTRACT GOAL (COMBINED)
The Department has determined that Underuhhzed Disadvantaged Business Enterprises (UDBEs) will participate by
contracting for apart of the work of this Contract The contract goal for participation in this Contract by certified DBEs
who have been determined to be underutilized has been established as follows
UDBE 70 Percent
The percentage will be calculated from proposals received for this project according to the following formula
*Dollar amount of work to be contracted to undemtilized DBEs (UDBEs)
Percentage = 100 X
Total dollar amount of the original Contract
* Based on DBE contract unit pries rather than prune contract unit pries
"All DBEs will be considered to be UDBEs
NOTE Specific Good Faith Efforts required to meet the Contract Goal specified above are defined in the
Standard Special Provisions In addition the Transportation Commission has determined an overall 12 69% annual
goal for the participation of all DBEs
11 0 BID FORM
11 1 A copy of the Bid Form is bound in the Contract Documents
which may be retained by the Bidder A separate unbound copy is
enclosed for submission with the Bid
11 2 Bid Forms must be complete in ink or typed All lump sum
prices on the form must be stated in words and numerals, in case
of conflict words will take precedence Unit prices shall govern
over extensions of sums
11 3 Bids by corporations must be executed in the corporate name
by the president or a vice-president (or other appropriate officer
accompanied by evidence of authority to sign) and the corporate
seal shall be affixed and attested by the secretary or an
assistant secretary The corporate address and state of
incorporation shall be shown below the corporate name
11 4 Bids by partnerships must be executed in the partnership
name and signed by a partner his title must appear under his
signature and the official address of the partnership must be
shown below the signature
11 5 Bids by joint venture shall be signed by each participant
in the joint venture or by an authorized agent of each
participant The full name of each person or company interested
in the Bid shall be listed on the Bid Form
11 6 The Bid shall contain an acknowledgement of receipt of all
Addenda (the numbers of which must be filled in on the Bid Form)
11 7 No alterations in Bids or in the printed forms therefore
by erasures interpolations or otherwise will be acceptable
unless each such alteration is signed or initialed by the Bidder
if initialed OWNER may require the Bidder to identify any
alteration so initialed
11 8 The address and telephone number for communications
regarding the Bid shall be shown
12 0 BID PRICING
Bids must be priced as set forth in the Bid Schedule or Schedules
13 0 SUBMISSION OF BIDS
13 1 Bids shall be submitted at the time and place indicated in
the Invitation to Bid and shall be enclosed in an opaque sealed
envelope marked with the Project title Bid No and name and
address of the Bidder and accompanied by the Bid Security Bid
Rev 10/20/07 Section 00100 Page 5
FEDERAL AID PROJECT NO STE M455 072 October 26 2007
PROJECT CODE NO 15281
REVISION OF SECTION 101
DEFINITION OF TERMS
Certain terms utilized in the latest edition of the Colorado Department of Transportation Standard Specifications for
Road and Bridge Construction shall be interpreted to have different meanings within the scope of this Contract A
summary of redefinitions follows
Subsection 10127
Department shall mean City of Fort Collins Colorado
Subsection 10128
Engineer shall mean City Engineer City of Fort Collins Colorado or a designated representative
Subsection 10147
Project Engineer shall mean the City Engineer Fort Collins Colorado or a designated representative
Subsection 10170
State shall mean City of Fort Collins Colorado (where applicable)
4
FEDERAL AID PROJECT NO STE M455 072 October 26 2007
PROJECT CODE NO 15281
REVISION OF SECTION 104
TRAFFIC AND PARKING CONTROL
Section 104 of the Standard Specifications is hereby revised as follows
Subsection 104 04 shall include the following
It shall be the Contractors responsibility to clear parking from the streets when such parking will interfere
with the work Prior to work that requires the street(s) to be closed to parking and/or traffic the street(s)
shall be posted for 'NO PARKING The placement of these signs shall take place at least 24 hours prior
to the commencement of work and shall clearly show the type of work and the day date and times that the
message on the sign is in effect (For example if a street is to be patched on Wednesday July 2 the street
shall be posted no later than Tuesday July 1 by 7 00 am with a sign that reads similar to NO
PARKING WEDNESDAY JULY 2 7 00 A M TO 6 00 P M PATCHING ) See sample NO
PARKING sign NO PARKING signs shall remain in place until the street is opened to traffic and all
clean up operations completed
Encroachment permits must be obtained for each parking space eliminated in order to
perform the Work Permits are available from the City of Fort Collins Parking Services office at
215 North Mason Street Permits for spaces directly related to the repairs will be paid for by the
Owner Additional spaces for staging will be the responsibility of the Contractor If spaces are not
available the Contractor is solely responsible for finding a suitable staging area The location of the
staging area must be submitted and approved by the Engineer prior to use Written authorization to
use private property to store equipment and materials shall be obtained from the property owner and
submitted to the Owner prior to mobilization and use The Contractor shall also submit a letter of
indemnification to the Owner and the property owner
Parking Parking for Contractor employees will NOT be permitted in the work zone or in the
general Downtown vicinity Rooftop Parking Passes for two Downtown parking structures are
available for $24/month per vehicle from the City of Fort Collins Parking Services Office The
Civic Center structure is located on the southeast corner of Mountain and Mason and the Old Town
structure is located on the southeast corner of Remington and Mountain Both are conveniently
located near the project All vehicles not required to perform the Work shall obtain a Rooftop
Parking Pass or be confined to the limits of the staging area (if applicable)
All information on the NO PARKING signs with the exception of the date shall be in block letters
permanently affixed to the sign Any information added to a sign such as dates shall be clearly legible and
written in block style letters
Any work done by the Contractor without traffic control will not be paid for under the terms of this
Contract The Contractor will not be paid for traffic control costs incurred during Contractor caused
delays
At or near the end of each work day a representative of the Contractor the Traffic Control Supervisor and
the Engineer will meet to discuss the progress of the work and the placement of traffic control devices
including NO PARKING signs Any necessary adjustments shall be made The Contractor shall also
review at this time with the Engineer the proposed means of handling parking and traffic control for
upcoming work It is the responsibility of the Contractor to minimize any inconvenience to the public as a
result of this work
FEDERAL AID PROJECT NO STE M455 072 October 26 2007
PROJECT CODE NO 15281
REVISION OF SECTION 104
TRAFFIC AND PARKING CONTROL
At the above referenced meeting the quantity of traffic control devices used that day shall be agreed upon
by the Contractor and the Engineer The Contractor shall utilize forms approved by the Engineer for the
tabulation of Traffic Control Devices utilized
The Contractor shall maintain pedestrian and vehicular access to all businesses within the project,
including crosswalks, at all times Pedestrian access must be clearly delineated and buffered from
construction activities at all limes, and may include construction and installation of temporary ramps
and wooden walkways as necessary
The Contractor shall maintain two way traffic on Mountain Avenue at all times
Any changes in the traffic control including additional signs barricades and/or flaggers needed in the field
shall be immediately implemented as directed by the Engineer
The cost for traffic control is covered in Revision of Section 630 Construction Zone Traffic Control
found herein
FEDERAL AID PROJECT NO STE M455 072
PROJECT CODE NO 15281
REVISION OF SECTION 104
TRAFFIC AND PARKING CONTROL
October26 2007
NO
PARKING
Wea Jull 7
7:00 AM - 6:00 PM
PATCHING
FEDERAL AID PROJECT NO STE M455 072 October 26 2007
PROJECT CODE NO 15281
REVISION OF SECTION 105
CLAIMS FOR CONTRACT ADJUSTMENT
Section 105 of the Standard Specifications is hereby revised for this project as follows
Subsection 105 21 shall be revised as follows
The Colorado Department of Transportation will not participate in the resolution process for any claims
filed by the Contractor
FEDERAL AID PROJECT NO STE M455 072 October 26 2007
PROJECT CODE NO 15281
REVISION OF SECTION 105
CONTROL OF WORK
Section 105 of the Standard Specifications is hereby revised as follows
COOPERATION WITH UTILITIES
Subsection 105 10 shall include the following
Construction and/or reconstruction operations at intersections may involve the destruction and replacement
of traffic signal loop detectors The existing traffic signal loop detectors shall be removed by the contractor
at no additional cost New loop detectors may be installed at other intersections where they do not now
exist New and replacement loop detectors will be installed by the City Traffic Division The Contractor
shall cooperate with the schedule of this work to insure the timely installation of new loop detectors
Also the Contractor shall coordinate with the City Traffic Division to insure that any cleanup required after
the installation of the loop detectors will be completed before concrete placement operations begin
City Utilities Parks Traffic concrete and utility contractors may perform work related to the project within
or near the limits of this project The Contractor shall coordinate extensively with these entities to minimize
traffic control and scheduling conflicts and ensure timely completion of all the work
COOPERATION BETWEEN CONTRACTORS
Subsection 105 11 shall include the following
City Utilities Parks Traffic concrete and utility contractors may perform work related to the project within
or near the limits of this project The Contractor shall conduct the work without interfering or hindering the
progress or completion of the work being performed by other contractors The Contractor shall coordinate
extensively with these entities to minimize traffic control and scheduling conflicts and ensure timely
completion of all the work
INSPECTION AND TESTING OF WORK
Subsection 105 15 shall include the following
The Contractor shall keep the Engineer informed of his future construction operations to facilitate
scheduling of required inspection measuring for pay quantities and sampling The Contractor shall notify
the Engineer a minimum of 24 hours in advance of starting any construction operation that will require
inspection measuring for pay quantities or sampling Failure of the Contractor to provide such notice will
relieve the owner and the Engineer from any responsibility for additional costs or delays caused by such
failure
Inspection of the work or materials shall not relieve the Contractor of any of his obligations to fulfill his
contract as prescribed Work and materials not meeting specifications shall be corrected and unsuitable
work or materials may be rejected notwithstanding that such work or materials have been previously
inspected by the Engineer or that payment therefore has been included in the progress estimate
FEDERAL AID PROJECT NO STE M455 072 October 26 2007
PROJECT CODE NO 15281
REVISION OF SECTION 105
CONTROL OF WORK
MAINTENANCE DURING CONSTRUCTION
Subsection 105 18 shall include the following
The roadway area including curb gutter and sidewalk adjacent to and through the construction area shall
be cleaned of debris by the Contractor at the earliest opportunity but in no case shall the area be left
uncleaned after the completion of the days work It shall be the Contractors responsibility to provide the
necessary manpower and equipment to satisfactorily clean the roadway area
The Contractor shall utilize a combination of pick up brooms side brooms and/or other equipment as
needed to clean the streets All sweeping and clean up equipment shall be approved by the Engineer prior
to the commencement of work
The Contractor shall maintain the streets during the construction process as prescribed above
If a street requires additional sweeping by City forces the Owner shall deduct from compensation due the
Contractor sufficient funds to cover the Owner's cost to provide said service
All cost of maintaining the work during construction and before the project is accepted will not be paid for
separately but shall be included in the work
10
FEDERAL AID PROJECT NO STE M455 072 October 26 2007
PROJECT CODE NO 15281
REVISION OF SECTION 107
PROTECTION AND RESTORATION OF PROPERTY AND LANDSCAPE
Section 107 of the Standard Specifications is hereby revised as follows
Subsection 107 12 shall include the following
The fact that any underground facility - sprinkler systems utility services etc is not shown on the plans
details or construction documents shall not relieve the Contractor of his responsibilities as provided for in
the Contract It shall be the Contractors responsibility pursuant thereto to ascertain the location of such
underground improvements which may be subject to such damage by reason of his operations
Any pruning of vegetation shall require the written permission of the property owner and/or the Engineer
In the event surrounding landscaping is damaged by construction operations the repairs shall be made as
follows
If the area to be repaired is five (5) inches or less in width the Contractor shall clean the area of all debris
(i a concrete road base etc ) to a minimum depth of four (4) inches prepare all edges to be clean and
vertical and place (see below) and compact topsoil The topsoil shall be compacted utilizing a hand
operated roller or other method approved by the Engineer
The topsoil shall consist of loose friable loam reasonably free of admixtures of subsoil refuse stumps
roots rocks brush weeds heavy clay hard clods toxic substances or other material which would be
detrimental to the proper development of vegetative growth The material to be utilized shall be approved
by the Engineer prior to placement
The topsoil shall be in a relatively dry state and placed during dry weather The topsoil shall be fine graded
to eliminate rough and low areas and ensure positive drainage The existing levels profiles and contours
shall be maintained
If any portion of the area to be repaired is greater than five (5) inches in width the Contractor shall clean
and prepare the area along the entire length of the repair location as stated above to a minimum of one (1)
foot place sod over the entire area water once and notify the property owner in writing of the nature of the
work that has taken place and that the sod will be watered only once
If the area to be repaired is only damaged on the surface the Contractor shall remove the damaged areas of
sod to a depth that will allow new sod to be placed place new sod water once and notify the property
owner in writing of the nature of the work that has taken place and the fact that the sod will be watered only
once The minimum overall width of the area to be sodded shall be one (1) foot
Sprinkler systems Sprinkler systems shall be protected from damage by the contractor Sprinkler systems
damaged as a result of construction operations shall be replaced at the Contractors expense within three
(3) working days from the date of damage In areas where the Engineer directs new work or the
reconstruction areas require grade adjustment the placement of topsoil sod and sprinkler relocation will be
provided by the City under separate contract
All landscaping that is damaged due to construction operations shall be replaced by the Contractor at his
expense unless a written waiver is obtained from the property owner and submitted to the Engineer Re
sodded lawns shall be watered once by the Contractor
11
FEDERAL AID PROJECT NO STE M455 072 October 26 2007
PROJECT CODE NO 15281
REVISION OF SECTION 107
PROTECTION AND RESTORATION OF PROPERTY AND LANDSCAPE
All costs for protecting and restoring landscaping and lawns shall be considered a subsidiary obligation of
the Contractor in connection with the various items of the Work and no measurement or payment shall be
made separately for the protection and restoration of landscaping and lawns All restoration of landscaping
and lawns damaged by construction operations shall take place within three (3) working days from the date
of damage
All labor materials tools equipment incidentals and work involved in protecting or repairing
underground facilities shall be considered incidental to the work being done and shall not be measured and
paid for separately
12
FEDERAL AID PROJECT NO STE M455 072 October 26 2007
PROJECT CODE NO 15281
REVISION OF SECTION 107
INSURANCE
Section 107 18 is hereby revised to read
For this project all insurance certificates shall name the Colorado Department of Transportation as an additionally
insured party
13
ADDENDUM No 2
SPECIFICATIONS AND CONTRACT DOCUMENTS
Description of Bid 6075 Trolley Brick Restoration Project
OPENING DATE December 18 2007 (Our Clock) 3 00 P M
To all prospective bidders under the specifications and contract documents described above
the following changes are hereby made
CHANGE
Delay of Opening date to allow all Vendors the opportunity to complete all Federal forms
required, attached heroin. Any bids that have been received wdl not be opened Vendors
may pickup their Bids and submit new Bids
Please contact John D Stephen CPPO CPPB Senior Buyer at (970) 221-6777 with any
questions regarding this addendum
RECEIPT OF THIS ADDENDUM MUST BE ACKNOWLEDGED BY A WRITTEN STATEMENT
ENCLOSED WITH THE BID/QUOTE STATING THAT THIS ADDENDUM HAS BEEN
RECEIVED
where renewal is a way of life
Form Bid Bond Statement of Bidders Qualifications and Schedule
of Subcontractors as required in Section 00430 If the Bid is
sent through the mail or other delivery system, the sealed
envelope shall be enclosed in a separate envelope with the
notation BID ENCLOSED' on the face of it
13 2 Bids shall be deposited at the designated location prior to
the time and date for receipt of Bids indicated in the Invitation
to Bid or any extension thereof made by addendum Bids received
after the time and date for receipt of Bids will be returned
unopened Bidder shall assume full responsibility for timely
delivery at the location designated for receipt of Bids
13 3 Oral telephonic telegraphic or facsimile Bids are
invalid and will not receive consideration
13 4 No Bidder may submit more than one Bid Multiple Bids
under different names will not be accepted from one firm or
association
14 0 MODIFICATION AND WITHDRAWAL OF BIDS
14 1 Bids may be modified or withdrawn by an appropriate
document duly executed (in a manner that a Bid must be executed)
and delivered to the place where Bids are to be submitted at any
time prior to the opening of Bids
14 2 Bids may also be modified or withdrawn in person by the
Bidder or an authorized representative provided he can prove his
identity and authority at any time prior to the opening of Bids
14 3 Withdrawn Bids may be resubmitted up to the time designated
for the receipt of Bids provided that they are then fully in
conformance with these Instructions to Bidders
15 0 OPENINGS OF BIDS
Bids will be opened and (unless obviously non -responsive) read
aloud publicly as indicated in the Invitation to Bid An abstract
of the amounts of the Base Bids and ma3or alternates (if any) will
be made available after the opening of Bids
16 0 BIDS TO REMAIN OPEN SUBJECT TO ACCEPTANCE
All Bids shall remain open for forty-five (45) days after the day
of the Bid Opening but OWNER may in his sole discretion release
any Bid and return the Bid Security prior to that date
17 0 AWARD OF CONTRACT
Rev 10/20/07 Section 00100 Page 6
FEDERAL AID PROJECT NO STE M455 072
PROJECT CODE NO 15281
REVISION OF SECTION 108
PROSECUTION AND PROGRESS
Section 108 of the Standard Specifications is hereby revised as follows
SCHEDULE
Subsection 108 03 shall include the following
October26 2007
A schedule of work must accompany any bid and shall include number of working days to complete all
unit work items covered by the contract The schedule should take any priorities into consideration The
schedule should also include projected start and end dates
Prior to award mutually acceptable milestones shall be determined by the Contractor and the City based on
the schedule of working days discussed above
LIMITATION OF OPERATIONS
Subsection 108 04 shall include the following
The work shall be completed within the following calendar months
JAN FEB MAR APR MAY JUN JUL AUG SEPT OCT NOV DEC
The City of Fort Collins is committed to maintaining a positive working relationship with the
businesses and residents of the downtown area Every effort will be made to maintain pedestrian
flow, and to accommodate special events and high volume holidays for businesses, pedestrians,
parking, and vehicle traffic Contractor shall be responsible for communicating accurate scheduling
information to the project team to assure proper notification of businesses and residents
Work shall be completed during the months of January through April 2008
The Contractor shall notify businesses and residents of daily activities which may affect parking or
access Contractor shall provide a local contact phone number to facilitate communications with
businesses and residents regarding the project
City Holidays and specific dates that require work to stop or are limited to specific types of work are
described below At a minimum exceptional pedestrian parking and vehicle access must be maintained on
these dates as determined by the Engineer
New Year s Day Tuesday
Martin Luther King Day Monday
President s Day Monday
St Patrick s Day Parade TBA
January 1 2008
January 21 2008
February 18 2008
14
FEDERAL AID PROJECT NO STE M455 072 October 26 2007
PROJECT CODE NO 15281
REVISION OF SECTION 108
PROSECUTION AND PROGRESS
DETERMINATION AND EXTENSION OF TIME
Subsection 108 07 shall include the following
Work hours shall be 7 00 a in to 6 00 p in Monday through Friday or as approved by the Engineer
All Work is to be completed in twenty (20) consecutive working days
FAILURE TO COMPLETE WORK ON TIME
Subsection 108 08 shall include the following
Failure to meet the agreed upon milestones or fully complete the project in twenty (20) working days shall
result in damages assessed against the Contractor
At the City s option liquidated damages in the amount of $1000 00 per day may be retained from any
monies due the Contractor or the City may retain an additional contractor(s) to complete the work or
portion thereof and retain any costs incurred above and beyond the bid prices of the Contractor from any
monies due the Contractor in lieu of liquidated damages
15
FEDERAL AID PROJECT NO STE M455 072 October 26 2007
PROJECT CODE NO 15281
REVISION OF SECTION 201
CLEARING AND GRUBBING
Section 201 of the Standard Specifications is hereby revised as follows
CONSTRUCTION REQUIREMENTS
Subsection 20102 shall be amended to include the following
When any tree roots are encountered during construction operations the Contractor shall notify the
Engineer prior to any root removals The Engineer and the City Foresters representative shall then make a
determination regarding removal
Tree roots shall be removed with a sharpened sanitized saw cut orthogonally to its longitudinal axis as
closely as practical to leave the freshly cut root surface in a clean and smooth condition Axes or other
blunt objects shall not be used to cut tree roots
Where it is anticipated that tree roots may be encountered great care shall be taken by the Contractor to
prevent any damage to the roots with tools or equipment
BASIS OF PAYMENT
Subsection 20104 shall be amended to include the following
All costs for removing tree roots shall be considered a subsidiary obligation of the Contractor in connection
with the various items of the Work and no measurement or payment shall be made separately for the
removal of tree roots
16
FEDERAL AID PROJECT NO STE M455 072 October 26 2007
PROJECT CODE NO 15281
REVISION OF SECTION 202
REMOVAL OF STRUCTURES AND OBSTRUCTIONS
Section 202 of the Standard Specifications is hereby revised as follows
DESCRIPTION
Subsection 202 01 is revised to include the following
This work consists of removal and disposal of existing concrete pavement and removal salvage and
storage of existing trolley roadbed bricks Portions of the brick trolley roadbed that are within the existing
landscaped median will NOT be restored with this project
CONSTRUCTION REQUIREMENTS
Subsection 202 02 is revised to include the following
Trolley roadbed bricks shall be salvaged to the maximum extent feasible and reused in the restoration of
the brick roadbed Extreme care shall be taken during removal to protect the bricks and adjacent rails from
damage Salvable material shall remain the property of the City of Fort Collins and shall be stockpiled by
the Contractor within the project limits for reuse The Contractor shall safeguard salvable materials and
shall be responsible for the expense of repairing or replacing damaged or missing material until it is
incorporated into the work Any material that is not salvable shall be disposed of at the Contractors
expense In all cases the existing trolley rails shall be protected from damage and shall remain in place
Sections where the bricks have been previously removed and replaced with concrete or asphalt shall be
removed and the rails cleaned and exposed to receive new/salvaged trolley roadbed bricks The Remove
Concrete item shall include saw cutting removal and disposal of existing asphalt or concrete and
protection of existing bricks and rails as directed by the Engineer
METHOD OF MEASUREMENT
Subsection 202 11 is revised to include the following
Saw cutting for concrete removal shall be considered a subsidiary obligation of the Contractor and shall
not be measured or paid for separately
Remove Concrete shall be measured by the square foot of area removed and shall include all costs for
stockpiling haul and disposal
Remove and Salvage Existing Bricks shall be measured by the square foot of area removed and shall
include all costs for stockpiling storage and protection of existing bricks and disposal of inferior bricks
17
FEDERAL AID PROJECT NO STE M455 072
PROJECT CODE NO 15281
REVISION OF SECTION 202
REMOVAL OF STRUCTURES AND OBSTRUCTIONS
BASIS OF PAYMENT
Subsection 202 12 is revised to include the following
Payment will be made under
Pay Item Unit
October26 2007
202 01 Remove Concrete Square Foot
20202 Remove and Salvage Existing Bricks Square Foot
The above prices and payments shall include full compensation for furnishing all labor materials tools
equipment and incidentals and for doing all work involved in Removal of Structures and Obstructions
including saw cutting storage and cleanup as specified in these specifications as shown on the plans and
as directed by the Engineer
18
FEDERAL AID PROJECT NO STE M455 072 October 26 2007
PROJECT CODE NO 15281
REVISION OF SECTION 203
EXCAVATION AND EMBANKMENT
Section 203 of the Standard Specifications is hereby revised as follows
DESCRIPTION
Subsection 203 01 is revised to include the following
This work shall consist of removing and disposing of unsuitable subgrade base or other material and
preparing the subgrade for the subsequent course in accordance with the specifications and in reasonably
close conformity with the lines grades and typical cross sections shown on the plans or as designated by
the Engineer All excavation will be classified Unclassified Excavation as hereafter described The
Contractor shall haul and dispose of all excavated material
CONSTRUCTION REQUIREMENTS
Subsection 203 05 is revised to include the following
Unclassified Excavation shall consist of the excavation of all materials of whatever character required for
the work not being removed under some other item
The Contractor shall be responsible for the protection of the subgrade/base course until subsequent courses
have been placed
The excavation will be accomplished in the following manner
Unclassified Excavation
The areas to be removed will be marked on the surface by the Engineer with paint If in the opinion of the
Engineer the subgrade material is unsuitable it shall be removed to the limits and depths designated
Where excavation to the finished grade section results in a subgrade of unsuitable soil the Engineer may
require the Contractor to remove the unsuitable materials and backfill to the finished grade section with
aggregate base course
After the material has been removed to the depth specified by the Engineer the Contractor shall prepare the
subgrade by compacting with a sheepsfoot roller rubber tired roller and/or other compaction equipment as
approved by the Engineer The subgrade preparation shall not be measured and paid for separately but
shall be included in the contract unit price for Unclassified Excavation
METHOD OF MEASUREMENT
Subsection 203 13 is revised to include the following
The Contractor and the Engineer shall field measure and agree upon the excavated quantity before any
further work continues Should the Contractor fail to request the Engineer to measure any work and
perform other work that would prevent the Engineer from measuring pay quantities the Contractor shall
not be compensated for materials not measured by the Engineer
The accepted quantities of Excavation will be paid for at the contract unit price per cubic yard Subgrade
preparation haul and disposal will not be measured and paid for separately
19
FEDERAL AID PROJECT NO STE M455 072
PROJECT CODE NO 15281
REVISION OF SECTION 203
EXCAVATION AND EMBANKMENT
BASIS OF PAYMENT
Subsection 203 14 shall include the following
Payment will be made under
Pay Item
203 01 Unclassified Excavation
Unit
Ceyd
October26 2007
The above pries and payments shall include full compensation for furnishing all labor materials tools equipment
and incidentals and for doing all the work involved in Unclassified Excavation including haul stockpiling watering
or drying sod compaction proof rolling finish grading and disposal of unusable materials as shown on the plans
as specified in these specifications and as directed by the Engineer
20
FEDERAL AID PROJECT NO STE M455 072 October 26 2007
PROJECT CODE NO 15281
REVISION OF SECTION 212
SEEDING FERTILIZER AND SODDING
Section 212 of the Standard Specifications is hereby revised as follows
DESCRIPTION
Subsection 212 01 is revised to include the following
This work shall consist of soil preparation and furnishing and placing topsoil and blue grass sod in
accordance with these specifications accepted horticulture practice and in reasonably close conformity
with the locations and details shown on the plans or as designated Also see Protection and Restoration of
Property & Landscape found herein
MATERIALS
Subsection 212 02 is revised to include the following
Topsoil shall conform to the requirements of Protection and Restoration of Property found herein
Bluegrass sod shall be nursery grown 99% Kentucky Blue Grass and 99% weed free Other sod type may
be used only if approved in writing by the Engineer The 1% allowable weeds shall not include any
undesirable perennial or annual grasses or plants Soil thickness of sod cuts shall not be less than 3/4 inch
nor more than one inch Sod shall be cut in uniform strips with minimum dimensions of 12 inches in width
and 48 inches in length The Contractor shall submit a sample of the sod he proposes to furnish Said
sample shall serve as a standard Any sod famished whether in place or not that is not up to the standard
of the sample maybe rejected Sod that has been cut for more than 24 hours shall not be used
Each load of sod shall be accompanied by a certificate from the grower stating the type of sod and the date
and time of cutting
CONSTRUCTION REQUIREMENTS
Subsection 212 05 is revised to include the following
Sodding
Soil Preparation The area shall be cleaned with a minimum depth of four (4) inches (where topsoil does
not exist) and a minimum width of one (1) foot all irregularities in the ground surface shall be removed
and all edges clean and vertical Sticks stones debris and other similar material more than %, inch in
diameter shall be removed Any objectionable depressions or other vanances from a smooth grade shall be
corrected
Topsoil Placement Topsoil shall be placed and compacted with a minimum depth of four (4) inches The
amount of compaction required shall be as directed by the Engineer
Sod Placement The minimum width for sod shall be one (1) foot The area to be sodded shall be smooth
The sod shall be lard by staggering joints with all edges touching On any slopes the sod shall run
approximately parallel to the slope contours The Contractor shall water the sod once and notify the
property owner in writing of the nature of the work that has taken place and that the sod will only be
watered once
Sod placement/replacement required due to Contractor negligence shall follow the requirements of this
section but will not be measured and paid for under the terms of this contract
21
FEDERAL AID PROJECT NO STE M455-072 October 26 2007
PROJECT CODE NO 15281
REVISION OF SECTION 212
SEEDING FERTILIZER AND SODDING
BASIS OF PAYMENT
Subsection 212 08 is revised to include the following
No measurement for payment shall be made for re sodding lawn damaged by the Contractor adjacent to
new concrete when the grade of the exr sting lawn reasonably matches the grade of the new concrete Re
sodding in this instance shall be considered incidental to the work being performed
22
FEDERAL AID PROJECT NO STE M455 072 October 26 2007
PROJECT CODE NO 15281
REVISION OF SECTION 304
AGGREGATE BASE COURSE
Section 304 of the Standard Specifications is hereby revised as follows
MATERIALS
Subsection 304 02 is revised to include the following
Base material shall conform to the requirements of Section 703 03 CDOT Standard Specifications Class 5
Aggregate Base Course The material must have an R value of 72 or greater and must be moisture stable
METHOD OF MEASUREMENT
Subsection 304 07 is revised to include the following
Aggregate Base Course will be measured by the ton at the proper moisture Haul and water necessary to
bring mixture to optimum moisture content will not be measured and paid for separately but shall be
included in the contract unit price for Aggregate Base Course
Failure to protect open excavations or any other use not directly related to the Work shall not be measured
or paid for separately but shall be included in the Work
Load slips shall be consecutively numbered for each day and submitted to the Engineer daily
The accepted quantities for Aggregate Base Course will be paid for at the contract unit price per ton
BASIS OF PAYMENT
Subsection 304 08 is revised to include the following
Payment will be made under
Pay Item
304 01 Aggregate Base Course (Class 5)
Unit
Ton
The above prices and payments shall include full compensation for furnishing all labor materials tools
equipment and incidentals and for doing all work involved in the placement of Aggregate Base Course
complete in place including haul and water as shown on the plans as specified in these specifications and
as directed by the Engineer
23
17 1 OWNER reserves the right to reject any and all Bids to
waive any and all informalities not involving price time or
changes in the Work to negotiate contract terms with the
Successful Bidder and the right to disregard all nonconforming
nonresponsive, unbalanced or conditional Bids Also OWNER
reserves the right to reject the Bid of any Bidder if OWNER
believes that it would not be in the best interest of the Project
to make an award to that Bidder whether because the Bid is not
responsive or the Bidder is unqualified or of doubtful financial
ability or fails to meet any other pertinent standard or criteria
established by OWNER Discrepancies between the indicated sum of
any column of figures and the correct sum thereof will be resolved
in favor of the correct sum
17 2 In evaluating Bids OWNER will consider the qualifications
of the Bidders whether or not the Bids comply with the prescribed
requirements and such alternates unit prices and other data, as
may be requested in the Bid Form or prior to the Notice of Award
17 3 OWNER may consider the qualification and experience of
Subcontractors Suppliers and other persons and organizations
proposed for those portions of the Work as to which the identity
of Subcontractors Suppliers and other persons and organizations
is submitted as requested by OWNER OWNER also may consider the
operating costs, maintenance requirements performance data and
guarantees of major items of materials and equipment proposed for
incorporation in the Work when such data is required to be
submitted prior to the Notice of Award
17 4 OWNER may conduct such investigations as OWNER deems
necessary to assist in the evaluation of any Bid and to establish
the responsibility qualifications and financial ability of the
Bidder s proposed Subcontractors, Suppliers and other persons and
organizations to do the Work in accordance with the Contract
Documents to OWNER s satisfaction within the prescribed time
17 5 If the Contract is to be awarded it will be awarded to the
lowest responsive and responsible Bidder whose evaluation by OWNER
indicates to OWNER that the award will be in the best interest of
the OWNER Award shall be made on the evaluated lowest base bid
excluding alternates The basis for award shall be the lowest Bid
total for the Schedule or in the case of more than one schedule
for sum of all schedules Only one contract will be awarded
17 6 If the Contract is to be awarded OWNER will give the
Successful Bidder a Notice of Award within forty-five (45) days
after the date of the Bid opening
18 0 CONTRACT SECURITY
Rev 10/20/07 Section 00100 Page 7
FEDERAL AID PROJECT NO STE M455 072 October 26 2007
PROJECT CODE NO 15281
REVISION OF SECTION 610
BRICK TROLLEY ROADBED
Section 610 of the Standard Specifications is hereby revised as follows
DESCRIPTION
Subsection 610 01 is revised to include the following
This work consists of providing new bricks to supplement salvaged on site bricks and the installation of
the brick trolley roadbed using both new and salvaged material Portions of the brick trolley roadbed that
are within the existing landscaped median will NOT be restored with this project
MATERIALS
Subsection 610 02 is revised to include the following
New brick shall be 4 x 8 x 2 % Heavy Duty Recreated Historical Pavers by Colonial Brick Corporation
of Cayuga Indiana or approved equal These pavers shall be made to order to best match the existing
historical brick color and size The color shall be Red and the texture wire cut and rounded on the 8
edges Brick shall meet the requirements of ASTM Designation C1272 99 for Heavy Vehicular Paving
Brick
Colonial Brick Corporation
Contact Dan Swartz
Physical Address 817 W Park St Cayuga IN 47928
Mailing Address Box 365 Cayuga IN 47928
Phone 765 492 3355
Fax 765 492 3015
CONSTRUCTION REQUIREMENTS
Subsection 610 03 is revised to include the following
Once a section of Mountain Avenue is closed for repair the concrete bricks shall be removed replaced and
reopened to traffic within 5 calendar days For special circumstances the Contractor may submit written
requests for exceptions to this requirement to the Engineer for approval prior to demolition
The Contractor shall compact the subgrade and spread bedding sand evenly in the area defined and shall
screed the sand to an appropriate embedment depth not to exceed 1 The Contractor shall use a plate
vibrator to embed the pavers into the sand Joint spacing between paver units and the pattern design shall
match as closely as possible the original layout (see photo below) Joints shall be filled completely with
joint sand Excess sand shall be removed by sweeping The brick pavers shall match as closely as possible
the elevation of the surrounding concrete pavement
24
FEDERAL AID PROJECT NO STE M455 072
PROJECT CODE NO 15281
REVISION OF SECTION 610
BRICK TROLLEY ROADBED
METHOD OF MEASUREMENT
Subsection 610 04 is revised to include the following
October 26 2007
Removal and salvage of existing bricks shall be paid for at the contract unit price for Remove and Salvage
Existing Bricks, under Revision of Section 202 Removal of Structures and Obstructions
Supply New Trolley Bricks shall be measured by the square foot of surface area of new brick placed in the
brick roadbed
Install Brick Trolley Roadbed shall be measured by the square foot of brick new and salvaged complete
in place including grading compaction brick placement and Joint sand
BASIS OF PAYMENT
Subsection 610 05 is revised to include the following
Payment will be made under
Pay Item
Unit
61001 Supply New Trolley Bricks —Material Only SF
610 02 Install Brick Trolley Roadbed SF
The above prices and payments shall include full compensation for furnishing all labor materials tools
equipment and incidentals and for doing all work involved in Brick Trolley Roadbed complete in place
including haul and water grading and compaction as shown on the plans as specified in these
specifications and as directed by the Engineer
25
FEDERAL AID PROJECT NO STE M455 072 October 26 2007
PROJECT CODE NO 15281
REVISION OF SECTION 630
CONSTRUCTION ZONE TRAFFIC CONTROL
Section 630 of the Standard Specifications is hereby revised as follows
DESCRIPTION
Subsection 630 01 shall he revised as follows
This work shall consist of furnishing installing moving maintaining and removing temporary traffic signs
advance warning arrows panels barricades channelizmg devices and delmeators as required by the latest
revision of the Manual on Uniform Traffic Control Devices for Streets and Highways (MUTCD) the
City of Fort Collins Work Area Traffic Control Handbook and the Latimer County Urban Area Street
Standards
In the event of a conflict between the MUTCD criteria and the City criteria the City criteria shall
govem
When a device is not in use the Contractor shall remove it from the project for the period it is not needed
Devices temporarily not in use shall as a minimum be removed from the area Moving will include
devices removed from the project and later returned to use
This Work also includes Traffic Control Management and flagging
MATERIALS
Subsection 630 02 shall include the following
All traffic control devices placed for this project must meet or exceed the inuumum standards set forth in
the MUTCD All traffic control devices shall be clean and in good operating condition when delivered and
shall be maintained in that manner on a daily basis All traffic control devices shall be clearly marked and
free of crossed out information or any other form of defacement that detracts from the purpose for which
they are intended (i a crossed out information information written in long hand style etc )
Additionally any sign blank with sign faces on both sides must have the back sign face covered when in
use to avoid confusion to motorists traveling in the opposite direction and other potentially affected parties
such as residents affected by any information the sign may present
NO PARKING Sign with Stand shall consist of a metal sign attached to a device (stand) such as a
Vertical Panel or Type I Barricade The sign material and stand shall be approved by the Engineer
CONSTRUCTION REQUIREMENTS
Subsection 630 09 shall be revised as follows
TRAFFIC CONTROL PLAN
Traffic control through the construction areas is the responsibility of the Contractor
For all locations a Traffic Control Plan shall be prepared The Traffic Control Plans shall be on City
supplied forms The Traffic Control Plans shall be submitted for approval to the Engineer by 8 00 a in
two working days prior to the commencement of work (Note Traffic Control Plans for work done on
Monday and Tuesday shall be submitted the previous Friday by 8 00 a in ) Full road closure plans shall be
99
FEDERAL AID PROJECT NO STE M455 072 October 26 2007
PROJECT CODE NO 15281
REVISION OF SECTION 630
CONSTRUCTION ZONE TRAFFIC CONTROL
submitted no later than Friday mornings by 8 00 a in for projects starting the following week All plans
shall be delivered to City Engineering 281 North College Avenue Facsimiles of plans shall not be
allowed No phase of the construction shall start until the Traffic Control Plan has been approved Failure
to have an approved Traffic Control Plan shall constitute cause for the City to stop work as well as the
Contractors forfeiture of payment for all work and materials at that location with no adjustment in the
contract time
All costs associated with Traffic Control Plan review will not be measured or paid for separately but shall
be considered incidental to the Work
The Traffic Control Plan shall include as a minimum the following
(1) A detailed diagram which shows the location of all sign placements including advance
construction signs (if not previously approved) and speed limit signs method length and time
duration for lane closures and location of flag persons
(2) A tabulation of all traffic control devices shown on the detailed diagram including but not limited
to construction signs vertical panel vertical panel with light Type I Type II and Type III
barricades cones drum channehzing devices advance warning flashing or sequencing arrow
panel Certain traffic control devices may be used for more than one operation or phase
However all devices required for any particular phase must be detailed and tabulated for each
phase
(3) Number of flaggers to be used
(4) Parking Restrictions to be in affect
Approval of the proposed method of handling traffic is intended to indicate those devices for which
payment is to be made Such approval does not relieve the Contractor of liability specifically assigned to
him under this contract
Parking Restriction Plans shall be submitted and approved which show the location and quantity of NO
PARKING signs the date to be placed and the date to be removed The plans shall be prepared on City
supplied forms The Parking Restriction Plans shall be submitted to the Engineer by 8 00 a in two
working days prior to the commencement of work (Note Parking Restriction Plans for work done on
Monday and Tuesday shall be submitted the previous Friday by 8 00 a in ) All plans shall be delivered to
City Engineering 281 North College Avenue Facsimiles of plans shall not be allowed No phase of the
construction shall start until the Parking Restriction Plan has been approved Failure to have an approved
Parking Restriction Plan shall constitute cause for the City to stop work as well as the Contractors
forfeiture of payment for all work and materials at that location with no adjustment in the contract time
Subsection 630 10 shall be revised as follows
TRAFFIC CONTROL MANAGEMENT
Traffic Control Management shall be performed by a Traffic Control Supervisor (TCS) The TCS(s) shall
possess a current American Traffic Safety Services Association (ATSSA) certification as a Worksite
Traffic Control Supervisor or Colorado Contractors Association (CCA) certification as a Traffic Control
Supervisor (Proof of certification shall be presented to the City Traffic Control Manager and when
requested by a City representative for each TCS utilized on this project )
27
FEDERAL AID PROJECT NO STE M455 072 October 26 2007
PROJECT CODE NO 15281
REVISION OF SECTION 630
CONSTRUCTION ZONE TRAFFIC CONTROL
One TCS shall be designated as the Head TCS The Head TCS shall have a minimum of one year
experience as a certified TCS Qualifications shall be submitted to the Engineer for approval a
minimum of one week pnor to commencement of the work
The Head TCS shall be on site at all times during the construction and shall be equipped with a cellular
phone
It is the intent of the specifications that the Head TCS be the same throughout the project If the Head TCS
is to be replaced during the project the Engineer shall be given a minimum of one (1) weeks notice and
qualifications shall be submitted for approval for the replacement
The TCS s duties shall include but not be limited to
(1) Preparing revising and submitting Traffic Control Plans as required (Review fees will not be
measured or paid for separately but shall be considered incidental to the Work )
(2) Direct supervision of project flaggers
(3) Coordinating all traffic control related operations including those of the Subcontractors and
suppliers
(4) Coordinating project activities with appropriate police and fire control agencies Transfort school
districts and other affected agencies and parties prior to construction Typed hand delivered
notification to all businesses and residents at least 24 hours prior to construction (The notification
of residents and businesses may be accomplished by a representative of the TCS )
(5) Maintaining a project traffic control diary which shall become part of the City s project records
(6) Inspecting traffic control devices on every calendar day for the duration of the project
(7) Insuring that traffic control devices are functioning as required
(8) Overseeing all requirements covered by the plans and specifications which contribute to the
convenience safety and orderly movement of traffic
(9) Flagging
(10) Setting up traffic control devices
Notification of residents and businesses shall be the responsibility of the TCS and shall consist of
distributing letters indicating the nature of the work to be completed any special instructions to the
residents (i a limits on lawn watering during concrete pouring etc ) the dates and times of the work and
the parking and access restrictions that will apply as well as thorough information placed on NO
PARKING signs Sample letters will be provided by the Engineer and shall be distributed prior to the
commencement of each phase of the work Letters shall be submitted with the Traffic Control Plans for
approval Approved letters shall be distributed a minimum of 24 hours prior to the commencement of
work (Note The time frame criteria for distributing letters are the same as for posting NO PARKING
signs )
Traffic control management shall be maintained on a 24 hour per day basis The Contractor shall make
arrangements so that the Traffic Control Supervisor or their approved representative will be available on
28
FEDERAL AID PROJECT NO STE M455 072 October 26 2007
PROJECT CODE NO 15281
REVISION OF SECTION 630
CONSTRUCTION ZONE TRAFFIC CONTROL
every working day on call at all times and available upon the Engineer's request at other than normal
working hours
All traffic control devices shall be placed under the supervision of a Traffic Control Supervisor
The Traffic Control Supervisor shall have up to date copies of the City of Fort Collins Work Area Traffic
Control Handbook" and Part VI of the MUTCD pertaining to traffic controls for street and highway
construction available at all times
NO PARKING signs must remain in place until the street is open to traffic
Subsection 630 12 shall be revised as follows
GENERAL
Traffic control devices shall be placed and/or stored in the City right of way in such a manner that
minimizes the hazards to pedestrians bicyclists and vehicles
Traffic control devices shall be removed from the site immediately upon completion of the work
METHOD OF MEASUREMENT
Subsection 630 14 shall be revised as follows
Construction Zone Traffic Control will be paid Lump Sum and shall be full compensation for TCS and
flagging furnishing erecting maintaining moving removing and disposing of construction traffic control
devices necessary to complete the work
In addition the Owner shall deduct from compensation due the Contractor $10 00 for each traffic control
device per day for said conditions including NO PARKING signs and any signs which are not removed
from the site immediately upon completion of the work
BASIS OF PAYMENT
Subsection 630 15 shall be revised as follows
Pay Item
630 01 Traffic Control
Unit
Lump Sum
Flagger hand signs will not be measured and paid for separately but shall be included in the work
The flaggers shall be provided with electronic communication devices when required These devices will
not be measured and paid for separately but shall be included in the work
The cost of batteries electricity and/or fuel for all lighting or warning devices will not be paid for
separately but will be considered subsidiary to the item
Sand bags will not be measured and paid for separately but shall be included in the work
29
FEDERAL AID PROJECT NO STE M455 072 October 26 2007
PROJECT CODE NO 15281
REVISION OF SECTION 630
CONSTRUCTION ZONE TRAFFIC CONTROL
The Contractor may provide larger construction traffic signs than those typically used in accordance with
the MUTCD if approved
The City shall not be responsible for any losses or damage due to theft or vandalism
SPECIAL CONDITIONS FOR WORK ON ARTERIALS AND COLLECTORS
NOTE CROSS STREET TRAFFIC SHALL BE MAINTAINED AT ALL TIMES UNLESS AUTHORIZED BY
THE ENGINEER IN WRITING
NOTE FULL CLOSURES ON ARTERIALS AND COLLECTORS INCLUDING THOSE LISTED ABOVE
WILL BE ALLOWED UNDER EXTREME CIRCUMSTANCES AND ONLY UPON APPROVAL OF
THE ENGINEER PLANS SHALL BE APPROVED A MINIMUM OF ONE WEEK PRIOR TO THE
COMMENCEMENT OF WORK AND/OR THE TIME REQUIRED TO ADEQUATELY NOTIFY THE
PUBLIC THROUGH THE MEDIA
SPECIAL CONDITIONS FOR WORK ON RESIDENTIAL STREETS
NOTE FULL CLOSURES ON ALL RESIDENTIAL STREETS SHALL BE ALLOWED AS SHOWN ON THE
TRAFFIC CONTROL PLANS
30
FEDERAL AID PROJECT NO STE M455 072 October 26 2007
PROJECT CODE NO 15281
FORCE ACCOUNT ITEMS
DESCRIPTION
This special provision contains the Divisions estimate for Force Account Items included in the Contract The
estimated amounts marked with an asterisk will be added to the total bid to determine the amount of the performance
and payment bonds Force Account work shall be performed as directed by the Engineer
BASIS OF PAYMENT
Payment will be made in accordance with Subsection 109 04 Payment will constitute full compensation for all
work necessary to complete the item
Force Account work valued at $5 000 or less that must be performed by a licensed Journeyman in order to comply
with federal state or local codes may be paid for after receipt of an itemized statement endorsed by the Contractor
ESTIMATED
FORCE ACCOUNT ITEM
QUANTITY
AMOUNT
F/A *Mmor Contract Revision
F A
$3 000
F/A On the Job Trainee
Hour
$0
F/A OJT Colorado Training Program
F A
$150
*To be included in the bond amount
31
FEDERAL AID PROJECT NO STE M455 072 October 26 2007
PROJECT CODE NO 15281
UTILITIES
Known utilities within the limits of this project are
Qwest
Terry Speer
(970)377 6405
Fort Collins CO
Xcel Energy
Pat Kreager
(970)225 7865
Fort Collins CO
Comcast
Dennis Greenwalt
(970) 484 7166
Fort Collins CO
City of Ft Collins Traffic
Dan Holland
(970)221 6816
Fort Collins CO
City of Fort Collins Utilities
Doug Martine
(970)224 6152
Fort Collins CO
The work described in these plans and specifications may require coordination between the Contractor and the
utility companies in accordance with subsection 105 10 in conducting their respective operations
GENERAL
The Contractor shall comply with Article 15 of Title 9 CRS ( Excavation Requirements ) when excavation or
grading is planned in the area of underground utility facilities The Contractor shall notify all affected utilities at
least two (2) business days not including the day of notification prior to commencing such operations The
Contractor shall contact the Utility Notification Center of Colorado (UNCC) at 1 800 922 1987 to have locations of
UNCC registered Imes marked by member companies All other underground facilities shall be located by
contacting the respective company Utility service laterals shall also be located prior to beginning excavating or
grading
The locations of utility facilities as shown on the plan and profile sheets and herein described were obtained from
the best available information
All costs incidental to the foregoing requirements will not be paid for separately but shall be included in the work
32
FEDERAL AID PROJECT NO STE M455 072
PROJECT CODE NO 15281
COLORADO
DEPARTMENT OF TRANSPORTATION
SPECIAL PROVISIONS
FORT COLLINS TROLLEY TRACK
STANDARD SPECIAL PROVISIONS
Revision of Section 105 — Disputes and Claims for Contract Adjustments
Revision of Section 106 — Certificates of Compliance and Certified Test Reports
Revision of Section 107 — Project Safety Planning
Revision of Section 107 — Responsibility for Damage Claims Insurance Types
and Coverage Limits
Revision of Section 107 — Ton Mile Taxes
Revision of Section 109 — Fuel Cost Adjustment
Revision of Section 109 — Measurement of Quantities
Revision of Sections 614 and 630 — Retroreflective Sign Sheeting
Revision of Section 630 — Construction Zone Traffic Control
Revision of Section 630 — Method of Handling Traffic
Revision of Section 630 — NCHRP 350 Requirements
Revision of Section 630 — Payment for Construction Traffic Control Devices
Revision of Section 630 — Portable Sign Storage
Affirmative Action Requirements — Equal Employment Opportunity
Disadvantaged Business Enterprise — Definitions and Requirements
Minimum Wages Colorado U S Department of Labor General Decision Numbers
CO20070014 and CO20070015 MOD 2 Highway Construction Statewide
On the Job Training
Required Contract Provisions — Federal Aid Construction Contracts
October26 2007
Date No of Pages
(August1 2005) 7
(June 29 2006) 1
(August 1 2005) 3
(August1 2005)
(April 12 2007)
(Nov 30 2006)
(August1 2005)
(Sept 2 2005)
(April 7 2006)
(April 7 2006)
(August2 2007)
(June 7 2007)
(August 1 2005)
(August1 2005)
(Dec 8 2005)
(October 5 2007)
(April 12 2007)
(August1 2005)
2
1
2
1
1
1
1
1
I
10
12
9
5
10
The General Conditions and the Supplementary Conditions set forth
OWNER's requirements as to performance and other Bonds When the
Successful Bidder delivers the executed Agreement to the OWNER it
shall be accompanied by the required Contract Security
19 0 SIGNING OF AGREEMENT
When OWNER gives a Notice of Award to the Successful Bidder it
will be accompanied by the required number of unsigned
counterparts of the Agreement with all other written Contract
Documents attached Within fifteen (15) days thereafter
CONTRACTOR shall sign and deliver the required number of
counterparts of the Agreement and attached documents to OWNER with
the required Bonds Within ten (10) days thereafter, OWNER shall
deliver one fully signed counterpart to CONTRACTOR Each
counterpart is to be accompanied by a complete set of the Drawings
with appropriate identification
20 0 TAXES
OWNER is exempt from Colorado State Sales and Use Taxes on
materials and equipment to be incorporated in the Work Said
taxes shall not be included in the Contract Price Reference is
made to the General and Supplementary Conditions
21 0 RETAINAGE
Provisions concerning retainage are set forth in the Agreement
22 0 PURCHASING RESTRICTIONS
Purchasing restrictions The Bidder s authorized signature of
this Bid assures the Bidder s compliance with the City s
purchasing restrictions A copy of the resolutions are available
for review in the Purchasing and Risk Management Division or the
City Clerk s office
A Cement Restrictions City of Fort Collins Resolution 91-121
requires that suppliers and producers of cement or products
containing cement to certify that the cement was not made in
cement kilns that burn hazardous waste as a fuel
23 0 COLLUSIVE OR SHAM BIDS
Any Bid deemed by the City in its sole discretion to be a
collusive or sham Bid will be rejected and reported to authorities
as such Your authorized signature of this Bid assures that such
Bid is genuine and is not a collusive or sham Bid
24 0 BID RESULTS
Rev 10/20/07 Section 00100 Page 8
August 12005
1
REVISION OF SECTION 105
DISPUTES AND CLAIMS FOR CONTRACT ADJUSTMENTS
Section 105 of the Standard Specifications is hereby revised for this project as follows
Subsection 105 21(1)2 second paragraph shall include the following
The CDOT modified version of AAA s Construction Industry Arbitration Rules shall be as follows
August 2005
2
REVISION OF SECTION 105
DISPUTES AND CLAIMS FOR CONTRACT ADJUSTMENTS
CONSTRUCTION INDUSTRY ARBITRATION RULES of the AMERICAN ARBITRATION ASSOCIATION
AS MODIFIED FOR USE WITH CDOT SPECIFICATION SUBSECTION 105 21
April 27 1997
Regular Track
R 1 Agreement of Parties
The parties shall have been deemed to have made these rules a part of their arbitration agreement whenever they have provided for
arbitraton by the American Arbitration Association (hereinafter AAA) or under its Construction Industry Arbitration Rules These rules and
any amendment of them shall apply in the form obtaining at the time the demand for arbitration or submission agreement is received by the
AAA
R 2 Name of Tribunal
Any tribunal constituted by the parties for the settlement of their dispute under these rules shall be called the Construction Industry
Arbitration Tribunal
R 3 Administrator and Delegation of Duties
When parties agree to arbitrate under these rules or when they provide for arbitration by the AAA and an arbitration is initiated under these
rules they thereby authorize the AAA to administer the Arbitration The authority and duties of the AAA are prescribed in the agreement of
the parties and in these rules and may be carried out through such of the AAA s representatives as it may direct
R-4 National Roster of Neutrals
In cooperation with the National Construction Disoute Resolution Committee the AAA shall establish and maintain a National Roster of
Construction Neutrals and shall appoint arbitrators as provided in these rules
R 5 Regional Offices
The AAA may in its discretion assign the administration of an arbitration to any of its regional offices
R 6 Initiation under an Arbitration Provision in a Contract
Arbitration under an arbitration provision in a contract shall be initiated in the following manner
The initiating party (hereinafter claimant) shall within the time period specified in the contract(s) give written notice to the other party
(hereinafter respondent) of its intention to arbitrate (demand) which notice shall contain a statement setting forth the nature of the dispute
the amount involved if any the remedy sought and the hearing locale requested
R 9 Preliminary Matters
Administrative Conference
At the request of any party or at the discretion of the AAA an administrative conference with the AAA and the parties and/or their
representatives will be scheduled in appropriate cases to expedite the arbitration proceedings
Preliminary Hearing
At the request of any party or at the discretion of the arbitrator or the AAA a preliminary hearing with the parties and/or their
representatives and the arbitrator may be scheduled by the arbitrator to specify the issues to be resolved to stipulate to uncontested facts
to establish a schedule for hearings and to consider any other matters that will expedite the arbitration proceedings
With the consent of the parties the AAA at any stage of the proceeding may arrange a mediation conference under the Construction
Industry Mediation Rules The mediation shall proceed in advance of the arbitration unless the parties agree otherwise The mediator
August 2005
3
REVISION OF SECTION 105
DISPUTES AND CLAIMS FOR CONTRACT ADJUSTMENTS
shall not be an arbitrator appointed to the case unless otherwise agreed by the parties Where the parties to a pending arbitration agree
to mediate under AAA s rules no additional administrative fee is required to initiate the mediation
R 10 Exchange of Information
Consistent with the expedited nature of arbitration the arbitrator may direct (1) the production of documents and other information and (0)
the identification of any witnesses to be called At least two business days prior to the hearing the parties shall exchange copies of all
exhibits they intend to submit at the hearing The arbitrator is authorized to resolve any disputes concerning the exchange of information
R 12 Qualification of an Arbitrator
Any arbitrator appointed pursuant to Section R 13 or selected by mutual choice of the parties or their appointees shall be subject to
disqualification for the reasons specified in Section R 19 If the parties specifically so agree in writing the arbitrator shall not be subject to
disqualification for those reasons
The term arbitrator' in these rules refers to the arbitration Roster of Neutrals whether composed of one or more arbitrators and whether
the arbitrators are neutral or party appointed
R 13 Appointment from Roster
If the parties have not appointed an arbitrator and have not provided any other method of appointment the arbitrator shall be appointed in
the following manner immediately after the filing of the submission the AAA shall send simultaneously to each party to the dispute an
identical list of names of persons chosen from the Roster of Neutrals
Each party to the dispute shall have ten days from the transmittal date in which to strike names objected to number the remaining names
in order of preference and return the list to the AAA In a single arbitrator case each party may strike three names on a peremptory basis
In a multi arbitrator case each party may strike five names on a peremptory basis If a party does not return the list within the time
specified all persons named therein shall be deemed acceptable From among the persons who have been approved on both lists and in
accordance with the designated order of mutual preference the AAA shall invite the acceptance of an arbitrator to serve If the parties fail
to agree on any of the persons named or if acceptable arbitrators are unable to act or if for any other reason the appointment cannot be
made from the submitted lists the AAA shall have the power to make the appointment from among other members of the Roster of
Neutrals without the submission of additional lists
R 18 Notice to Arbitrator of Appointment
Notice of the appointment of the arbitrator whether appointed mutually by the parties or by the AAA shall be sent to the arbitrator by the
AAA together with a copy of these rules and the signed acceptance of the arbitrator shall be filed with the AAA prior to the opening of the
first hearing
R 19 Disclosure and Challenge Procedure
Any person appointed as arbitrator shall disclose to the AAA any circumstance likely to affect impartiality including any bias or any
financial or personal interest in the result of the arbitration or any past or present relationship with the parties or their representatives Upon
receipt of such information from the arbitrator or another source the AAA shall communicate the information to the parties and if it deems
it appropriate to do so to the arbitrator and others Upon objection of a party to the continued service of an arbitrator the AAA shall
determine whether the arbitrator should be disqualified and shall inform the parties of its decision which shall be conclusive
R 20 Vacancies
If for any reason an arbitrator is unable to perform the duties of the office the AAA may on proof satisfactory to it declare the office
vacant Vacancies shall be filled in accordance with the applicable provisions of these rules
In the event of a vacancy in a panel of arbitrators after the hearings have commenced the remaining arbitrator or arbitrators may continue
with the hearing unless the parties agree otherwise
August 2005
4
REVISION OF SECTION 105
DISPUTES AND CLAIMS FOR CONTRACT ADJUSTMENTS
R 21 Date, Time and Place of Hearing
The arbitrator shall set the date time and place for each hearing The AAA shall send a notice of hearing to the parties at least ten days in
advance of the hearing date unless otherwise agreed by the parties
R 24 Interpreters
Any party wishing an interpreter shall make all arrangements directly with the interpreter and shall assume the costs of the service
R 25 Attendance at Hearings
The arbitrator shall maintain the privacy of the hearings unless the law provides to the contrary Any person having a direct interest in the
arbitration is entitled to attend hearings The arbitrator shall otherwise have the power to require the exclusion of any witness other than a
party or other essential person during the testimony of any other witness It shall be discretionary with the arbitrator to determine the
propriety of the attendance of any other person
R 26 Postponements
The arbitrator for good cause shown may postpone any hearing upon the request of a party or upon the agreements of all parties or upon
the arbitrator's own initiative
R 27 Oaths
Before proceeding with the first hearing each arbitrator may take an oath of office and if required by law shall do so The arbitrator may
require witnesses to testify under oath administered by any duly qualified person and if it is required by law or requested by any party
shall do so
R 28 Majority Decision
All decisions of the arbitrators must be by a majority The recommendation must be made by a majority unless the concurrence of all is
expressly required by the arbitration agreement or by law
R 29 Order of Proceedings and Communications with Arbitrator
A hearing shall be opened by the filing of the oath of the arbitrator
The Claimant shall first present evidence to support its claim The Respondent party shall then present evidence supporting its defense
Witnesses shall submit to questions or other examination The arbitrator has the discretion to vary this procedure and shall afford a full and
equal opportunity to all parties to be heard Exhibits when offered by either party may be received in evidence by the arbitrator
The arbitrator shall control the proceedings with a view to expediting the resolution of the dispute In order to expedite the proceedings the
arbitrator may control the order of proof bifurcate proceedings exclude cumulative or irrelevant testimony or evidence and direct the
parties to focus the presentation of evidence on decisive issues The arbitrator shall entertain motions including motions that dispose of all
or part of a claim or that may expedite the proceedings
There shall be no direct communication between the parties and an arbitrator other than at the hearing unless the parties and the
arbitrator agree otherwise Any other oral or written communication from the parties to the arbitrator shall be directed to the AAA for
transmittal to the arbitrator
R 30 Arbitration in the Absence of a Party or Representative
Unless the law provides to the contrary the arbitration may proceed in the absence of any party or representative who after due notice
fails to be present or fails to obtain a postponement A recommendation shall not be made solely on the default of a party The arbitrator
shall require the party who is present to submit such evidence as the arbitrator may require for the making of a recommendation
August 2005
5
REVISION OF SECTION 105
DISPUTES AND CLAIMS FOR CONTRACT ADJUSTMENTS
R-31 Evidence and Claim Record
CDOT will provide one copy of the claim record for each arbitrator and one copy for the AAA administrative staff
The parties may offer such evidence as is relevant and material to the dispute and shall produce such evidence as the arbitrator may deem
necessary to an understanding of the dispute and recommendation
The arbitrator shall be the judge of the relevance and materiality of the evidence offered and conformity to legal rules of evidence shall not
be necessary The arbitrator may request offers of proof and may reject evidence deemed by the arbitrator to be cumulative unreliable
unnecessary or of slight value compared to the time and expense involved All evidence shall be taken in the presence of all of the
arbitrators and all of the parties except where
1) any of the parties is absent in default or has waived the right to be present or
2) the parties and the arbitrators agree otherwise
R 32 Evidence by Affidavit
The arbitrator may receive and consider the evidence of witnesses by affidavit but shall give it only such weight as the arbitrator deems it
is entitled to after consideration of any objection made to its admission
R 33 Inspection or Investigation
An arbitrator finding it necessary to make an inspection or investigation in connection with the arbitration shall advise the parties by notice
transmitted at the hearing or through the AAA of the date and time Any party who so desires may be present at such an inspection or
investigation
R 35 Closing of a Hearing
When satisfied that the presentation of the parties is complete the arbitrator shall declare the hearing closed
R 37 Waiver of Oral Hearing
The parties may provide by wntten agreement for the waiver of oral hearings If the parties agree to waive oral hearings after the
appointment of the arbitrator the consent of the arbitrator must be obtained
R 38 Waiver of Rules
Any party who proceeds with the arbitration after knowledge that any provision or requirement of these rules has not been complied with
and who fails to state an objection in writing shall be deemed to have waived the nght to object
R 39 Extensions of Time
The parties may modify any period of time by mutual agreement The AAA or the arbitrator may for good cause extend any period of time
established by these rules except the time for making the recommendation The AAA shall notify the parties of any extension
R-41 Time of Recommendation
The recommendation shall be made promptly by the arbitrator and unless otherwise agreed by the parties or specified by law no later
than 30 days from the date of closing the hearing or if oral hearings have been waived from the date of the AAA s transmittal of the final
statements and proofs to the arbitrator
R 42 Form of Recommendation
The recommendation shall be in wnbng and shall be signed by a majority of the arbitrators The arbitrators shall provide a concise written
breakdown and explanation of the recommendation If the arbitrators do not agree the dissenting arbitrator shall also submit a written
recommendation
August 2005
6
REVISION OF SECTION 105
DISPUTES AND CLAIMS FOR CONTRACT ADJUSTMENTS
R-44 Modification of Recommendation
Within twenty (20) days after the transmittal of a recommendation any party upon notice to the other parbes may request the arbitrator to
correct any clerical typographical technical or computational errors in the recommendation The arbitrator is not empowered to re-
determine the ments of any claim already decided
The other parties shall be given ten (10) days to respond to the request The arbitrator shall dispose of the request within twenty (20) days
after transmittal by the AAA to the arbitrator of the request and any response thereto
If applicable law provides a different procedural time frame that procedure shall be followed
R-46 Delivery of Recommendation to Parties
Parties shall accept as legal delivery of the recommendation the placing of the recommendation or a true copy thereof in the mail
addressed to a party or its representative at the last known address personal service of the recommendation or filing of the
recommendation in any other manner that is permitted by law
R-47 Release of Documents for Judicial Proceedings
The AAA shall upon written request of a party furnish to the party at its expense certified copies of any papers in the AAA s possession
that may be required in judicial proceedings related to the arbitration
R-48 Applications to Court and Exclusion of Liability
(a) No judicial proceeding by a parry relating to the subject matter of the arbitration shall be deemed a waiver of the party s right to
arbitrate
(b) Neither the AAA nor any arbitrator in a proceeding under these rules is a necessary party in judicial proceedings relating to the
arbitration
(c) Neither the AAA nor any arbitrator shall be liable to any party for any act or omission in connection with any arbitration conducted under
these rules
R-49 Administrative Fees
As a not for profit organization the AAA shall prescribe filing and other administrative fees and service charges to compensate it for the
cost of providing administrative services The fees in effect when the fee or charge is incurred shall be applicable
R 50 Expenses
The expenses of witnesses for either side shall be paid by the party producing such witnesses All other expenses of the arbitration
including required travel and other expenses of the arbitrator AAA representatives and any witness and the cost of any proof produced at
the direct request of the arbitrator shall be bome equally by the parties unless they agree otherwise
R 51 Neutral Arbitrator's Compensation
Arbitrators shall charge a rate consistent with the arbitrator's stated rate of compensation beginning with the first day of hearing
If there is a disagreement concerning the terms of compensation an appropriate rate will be established with the arbitrator by the
Association and confirmed to the parties
Any arrangement for the compensation of a arbitrator shall be made through the AAA and not directly between the parties and the
arbitrator
August 1 2005
7
REVISION OF SECTION 105
DISPUTES AND CLAIMS FOR CONTRACT ADJUSTMENTS
R 52 Deposits
The AAA may require the parties to deposit in advance of any hearings such sums of money as it deems necessary to cover the expense
of the arbitration including the arbitrator's fee if any and shall render an accounting to the parties and return any unexpected balance at
the conclusion of the case
R 53 Interpretation and Application of Rules
The arbitrator shall interpret and apply these rules insofar as they relate to the arbitrator's powers and duties When there is more than one
arbitrator and a difference arises among them concerning the meaning or application of these rules il shall be decided by a majority vote
If that is not possible either an arbitrator or a party may refer the question to the AAA for final decision All other rules shall be interpreted
and applied by AAA
Administrative Fee Schedule
The administrative fees of the AAA are based on the amount of the claim Arbitrator compensation is not included in this schedule
Filing Fee
A nonrefundable filing fee is payable in full when a claim is filed The fee will be paid by CDOT and one half will be charged to the
contractor by them The filing fee rate schedule is as follows
Amount of Claim
Filing Fee
Hearing Fee
Postponement Fee
$20 000 to $50 000
$750
$150
$150
Above $50 000 to $100 000
$1 250
$150
$150
Above $100 000 to $250 000
$2 000
$150
$150
Above $250 000 to $500 000
$3 500
$250
$250
Above $500 000 to $1 000 000
$5 000
$250
$250
Above $1 000 000 to $5 000 000
$7 000
$250
$250
As indicated above when no amount can be stated at the time of filing the minimum filing fee is $2 000 subject to change when the claim
is disclosed
For any case having three or more arbitrator's the minimum filing fee is $2 000 the hearing fee is $250 per party and postponement fee is
$250
The administrative fee for claims in excess of $5 000 000 will be negotiated
When a claim is not for a monetary amount an appropriate filing fee will be determined by the AAA
PostponementlCancellation Fees
The postponement fees indicated above are payable by the party causing a postponement or cancellation of any schedule hearing
Hearing Room Rental
The Heanng Fees described above do not cover the rental of hearing rooms which are available on a rental basis Check with the
administrator for availability and rates
June 29 2006
REVISION OF SECTION 106
CERTIFICATES OF COMPLIANCE AND
CERTIFIED TEST REPORTS
Section 106 of the Standard Specifications is hereby revised for this project as follows
In subsection 106 12 delete item (11) of the list following the first paragraph and replace with the following
(11)The following certification signed by a person having legal authority to act for the Contractor
I hereby certify under penalty of perjury that the material listed in this Certificate of Compliance
represents (quantity and units) of pay item (pay item number and
Description) that will be installed on project number
Contractor Date
In subsection 106 12 delete the second paragraph and replace with the following
The original Certificate of Compliance shall include the Contractors original signature as directed above and the
original signature (including corporate title) under penalty of perjury of a person having legal authority to act for
the manufacturer It shall state that the product or assembly to be incorporated into the project has been sampled
and tested and the samples have passed all specified tests One copy or facsimile of the fully signed Certificate
of Compliance shall be furnished to the Engineer prior to installation of material The original shall be provided to
the Engineer before payment for the represented item will be made Failure to comply may result in delays to the
project or rejection of the materials
In subsection 106 13 delete item (11) of the list following the first paragraph and replace with the following
(11)The following certification signed by a person having legal authority to act for the Contractor
I hereby certify under penalty of perjury that the material listed in this Certified Test Report represents
(quantity and units) of pay item (pay item number and Description) that will
be installed on project number
Contractor
Date
In subsection 106 13 delete the second paragraph and replace with the following
The original Certified Test Report shall include the Contractors original signature as directed above and the
original signature (including corporate title) under penalty of perjury of a person having legal authority to act for
the manufacturer or the independent testing laboratory It shall state that the test results show that the product or
assembly to be incorporated into the project has been sampled and tested and the samples have passed all
specified tests One copy or facsimile of the fully signed Certified Test Report shall be furnished to the Engineer
prior to installation of material The original shall be provided to the Engineer before payment for the represented
item will be made Failure to comply may result in delays to the project or rejection of the materials
August 2005
1
REVISION OF SECTION 107
PROJECT SAFETY PLANNING
Section 107 of the Standard Specifications is hereby revised for this project as follows
Delete subsection 107 06 and replace with the following
107 06 Safety Health and Sanitation Provisions
(a) Contractor Responsibilities The Contractor shall ensure compliance with applicable Federal State and local
laws rules regulations and guidelines governing safety health and sanitation including but not limited to the
Project Safety Management Plan (Plan) described below the Occupational Safety and Health Act 29 CFR
1910 29 CFR 1926 Mine Safety and Health Administration (MSHA) Title 30 CFR the Colorado Work Zone
Best Practices Safety Guide national consensus standards and the Drug Free Workplace Act (Public Law
100 690 Title V subtitle D 41 USC 701 at seq ) The Contractor shall provide all safeguards safety devices
and protective equipment and shall take all other actions necessary to protect the life safety and health of
persons working at or visiting the project site and of the public and property in connection with the
performance of the work covered by the Contract In the case of conflicting requirements the more stringent
of the requirements shall apply The Contractor shall require that all operations and work practices by
Contractor subcontractors suppliers and Department personnel comply with the provisions of the Plan
(b) Safety Officer Prior to the start of construction the Contractor shall designate a Safety Officer and an
alternate who shall be responsible for the coordination of safety activities and preparation and
implementation of the Plan
(c) Competent Persons Prior to the start of construction the Contractor shall designate at least one competent
person for each of the construction activities being completed Construction activities and safety
considerations that must be addressed shall include but are not limited to lead abatement hearing
protection respiratory protection rigging assured grounding scaffolding fall protection cranes trenching
and excavating steel erection underground construction (including caissons and cofferdams) demolition
blasting and the use of explosives stairways and ladders asbestos and confined space The appropriate
competent persons shall be present on the project site at all times during construction activities A competent
person is an individual who by way of training experience or combination thereof is knowledgeable of
applicable standards is capable of identifying existing and predictable workplace hazards relating to a
specific construction activity is designated by the employer and has authority to take appropriate actions
(d) Project Safety Management Plan Prior to the start of construction the Contractor shall prepare a written
Project Safety Management Plan (Plan) which shall be specific to the project The Plan shall include
(1) Designation of a Safety Officer and an alternate and competent persons for each construction activity
as described above
(2) A list of all significant and/or high risk construction activities and safety considerations as described
above and a hazard assessment for each
(3) Direction as to whether engineering administrative personal protection measures training or a
combination thereof shall be implemented to address the hazards identified in (2) above
(4) Provisions for field safety meetings The Contractor shall conduct field safety meetings at the
frequency specified in the Plan once per week at a minimum The Contractor shall encourage
participation by all persons working at the project site Participants at these meetings shall discuss
specific construction activities for that work period results from safety inspections required personal
protective equipment and all other necessary safety precautions
(5) Provisions for project safety meetings The Contractor shall conduct project safety meetings to discuss
accidents incidents safety goals near misses and results of safety inspections The Contractor shall
notify the Engineer of the time date and location of these meetings shall require participation by all
persons (including Department personnel) working at the project site and shall track attendance
through sign up lists
(6) Procedures for assuring compliance by subcontractors suppliers and authorized visitors to the project
In addition the Plan shall specify the measures that will be taken to discourage unauthorized personnel
from entering the site
August 2005
2
REVISION OF SECTION 107
PROJECT SAFETY PLANNING
(7) Procedures to be followed in cases where workers are suspected of drug or alcohol impairment
(8) Provisions for project safety inspections The Contractor shall conduct regular project safety
inspections at the frequency specified in the Plan once per month at a minimum The Contractor shall
maintain documentation on the project site including the date of these inspections the findings and the
corrective measures taken to address the findings
(9) Procedures to be followed to correct violations of the Plan by any personnel
(10) The notification investigation and implementation procedures that the Contractor shall follow in the
case of a safety stand down
(11) The Contractor's certification as follows
By authorized signature below (Contractor name). hereinafter referred to as the Contractor' hereby
certifies that this Project Safety Management Plan (Plan) complies with and meets applicable Federal
State and local laws rules regulations and guidelines governing safety health and sanitation
including but not limited to the Occupational Safety and Health Act 29 CFR 1910 29 CFR 1926 Mine
Safety and Health Administration (MSHA) Title 30 CFR the Colorado Work Zone Best Practices
Safety Guide national consensus standards and the Drug Free Workplace Act (Public Law 100 690
Title V subtitle D 41 USC 701 at seq ) All operations and work practices of the Contractor will comply
with this Plan The Contractor requires that all subcontractors suppliers and Department personnel
comply with this Plan
(Signature of Contractor s Safety Officer or alternate)
The Contractor shall submit the Plan to the Engineer for the project records and shall provide updates to the
Plan as necessary An up to date copy of the Plan shall be on the project site in the Contractors possession
at all times
(e) Project Safety & Health Requirements All personnel on the project site shall wear the following personal
protective equipment (PPE) at all times when in the State Highway Right of Way except when in their
vehicles
(1) Head protection and high visibility apparel reflectorized for night use and footwear all of which shall
comply with the latest appropriate national consensus standards
(2) All other PPE that is stipulated by the Plan All PPE shall comply with the latest appropriate national
consensus standards
(f) Safety Stand Down The Engineer may immediately suspend all or part of any work in the case of an accident
(including property damage) or catastrophe (three or more persons hospitalized in a single incident) or other
situation presenting an imminent danger to life or health such as a near miss violation of the Plan and/or
presence of a hazardous situation In the case of a worksite fatality directly related to the Contractors or any
subcontractors work operations the safety stand down shall be mandatory In the case of a traffic fatality
unrelated to a work zone incident in the opinion of the Engineer the safety stand down will not be mandatory
During any mandatory safety stand down due to a fatality all work on the project shall cease except that
work deemed necessary by the Engineer to immediately correct unsafe conditions The Contractor shall be
allowed to resume operations only after providing documentation certified by the Safety Officer or alternate
regarding the corrective actions taken to prevent recurrence The Contractor may be granted a non
compensable excusable delay up to three days for the period of time during which no work was pursued
due to each safety stand down
For information regarding results for individual Bids send a self-
addressed self -stamped envelope and a Bid tally will be mailed to
you Bid results will be posted in the Purchasing office seven
(7) days after the Bid Opening
END OF SECTION
Rev 10/20/07 Section 00100 Page 9
August 1 2005
3
REVISION OF SECTION 107
PROJECT SAFETY PLANNING
(g) Regulatory Enforcement Actions The Contractor shall provide written notifications of all Regulatory agency
actions relating to safety to the Engineer
All costs associated with the preparation and implementation of the Plan and complying with all safety health
and sanitation provisions and requirements will not be measured and paid for separately but shall be included in
the work
August 2005
I
REVISION OF SECTION 107
RESPONSIBILITY FOR DAMAGE CLAIMS
INSURANCE TYPES AND COVERAGE LIMITS
Section 107 of the Standard Specifications is hereby revised for this project as follows
Delete subsection 107 15 and replace with the following
107 15 Responsibility for Damage Claims, Insurance Types and Coverage Limits The Contractor shall
indemnify and save harmless the Department its officers and employees from suits actions or claims of any
type or character brought because of any and all injuries or damage received or sustained by any person
persons or property on account of the operations of the Contractor or failure to comply with the provisions of the
Contract or on account of or in consequence of neglect of the Contractor in safeguarding the work or through
use of unacceptable materials in constructing the work or because of any act or omission neglect or misconduct
of the Contractor or because of any claims or amounts recovered from any infringements of patent trademark or
copyright unless the design device material or process involved is specifically required by the Contract or from
any claims or amounts arising or recovered under the Workers Compensation Act or other law ordinance order
or decree The Department may retain as much of any moneys due the Contractor under any Contract as may be
determined by the Department to be in the public interest
(a) The Contractor shall obtain and maintain at all times during the term of this Contract insurance in the
following kinds and amounts
(1) Workers Compensation Insurance as required by state statute and Employer's Liability Insurance
covering all of Contractors employees acting within the course and scope of their employment
(2) Commercial General Liability Insurance written on ISO occurrence form CG 00 01 10/93 or equivalent
covering premises operations fire damage independent Contractors products and completed
operations blanket contractual liability personal injury and advertising liability with minimum limits as
follows
(i) $1 000 000 each occurrence
(u) $2 000 000 general aggregate
(uQ $2 000 000 products and completed operations aggregate and
(iv) $50 000 any one fire
(v) Completed Operations coverage shall be provided for a minimum period of one year following final
acceptance of work
If any aggregate limit is reduced below $1 000 000 because of claims made or paid the Contractor shall
immediately obtain additional insurance to restore the full aggregate limit and furnish to CDOT a
certificate or other document satisfactory to CDOT showing compliance with this provision
(3) Automobile Liability Insurance covering any auto (including owned hired and non owned autos) with a
minimum limit as follows $1 000 000 each accident combined single limit
(4) Professional liability insurance with minimum limits of liability of not less than $1 000 000 Each Claim and
$1 000 000 Annual Aggregate for both the Contractor or any subcontractors when
(i) Contract items 625 629 or both are included in the Contract
(u) Plans specifications and submittals are required to be signed and sealed by the Contractors
Professional Engineer including but not limited to
(A) Shop drawings and working drawings as described in subsection 105 02
(B) Mix Designs
August 1 2005
2
REVISION OF SECTION 107
RESPONSIBILITY FOR DAMAGE CLAIMS
INSURANCE TYPES AND COVERAGE LIMITS
(C) Contractor performed design work as required by the plans and specifications
(D) Change Orders
(E) Approved Value Engineering Change Proposals
(w) The Contractor and any included subcontractor shall renew and maintain Professional Liability
Insurance as outlined above for a minimum of one year following final acceptance of work
(5) Umbrella or Excess Liability Insurance with minimum limits of $1 000 000 This policy shall become
primary (drop down) in the event the primary Liability Policy limits are impaired or exhausted The Policy
shall be written on an Occurrence form and shall be following form of the primary The following form
Excess Liability shall include CDOT as an additional insured
(b) CDOT shall be named as additional insured on the Commercial General Liability and Automobile Liability
Insurance policies Completed operations additional insured coverage shall be on endorsements CG 2010
11185 CG 2037 or equivalent Coverage required of the contract will be primary over any insurance or self
insurance program carried by the State of Colorado
(c) The Insurance shall include provisions preventing cancellation or non -renewal without at least 30 days prior
notice to CDOT by certified mad
(d) The Contractor will require all insurance policies in any way related to the contract and secured and
maintained by the Contractor to include clauses stating that each carner will waive all rights of recovery
under subrogation or otherwise against CDOT its agencies institutions organizations officers agents
employees and volunteers
(a) All policies evidencing the insurance coverages required hereunder shall be issued by insurance companies
satisfactory to CDOT
(f) The Contractor shall provide certificates showing insurance coverage required by this contract to CDOT prior
to execution of the contract No later than 15 days prior to the expiration date of any such coverage the
Contractor shall deliver CDOT certificates of insurance evidencing renewals thereof At any time during the
term of this contract CDOT may request in writing and the Contractor shall thereupon within ten days supply
to CDOT evidence satisfactory to CDOT of compliance with the provisions of this section
(g) Notwithstanding subsection 107 15(a) if the Contractor is a public entity within the meaning of the Colorado
Governmental Immunity Act CRS 24 10 101 at seq as amended ( Act) the Contractor shall at all times
during the term of this contract maintain only such liability insurance by commercial policy or self insurance
as is necessary to meet its liabilities under the Act Upon request by CDOT the Contractor shall show proof
of such insurance satisfactory to CDOT Public entity Contractors are not required to name CDOT as an
Additional Insured
(h) When the Contractor requires a subcontractor to obtain insurance coverage the types and minimum limits of
this coverage may be different than those required as stated above for the Contractor except for the
Commercial General Liability Additional Insured endorsement and those that qualify as needing Professional
Liability Insurance
Apnl12 2007
REVISION OF SECTION 107
TON MILE TAX
Section 107 of the Standard Specifications is hereby revised for this project as follows
In subsection 107 02 delete the third paragraph
November 30 2006
REVISION OF SECTION 109
FUEL COST ADJUSTMENT
Section 109 of the Standard Specifications is hereby revised for this project as follows
Subsection 109 06 shall include the following
(h) Fuel Cost Adjustments Contract price adjustments will be made to reflect increases or decreases in the
prices of gasoline diesel and other fuels from those in effect during the month in which bids were received for
the Contract When bidding the Contractor shall specify on the Form 85 whether the price adjustment will
apply to the Contract After bids are submitted the Contractor will not be given any other opportunity to
accept or reject this adjustment If the Contractor fails to indicate a choice on the Form 85 the price
adjustment will not apply to the Contract If the fuel cost adjustment is accepted by the Contractor the
adjustment will be made in accordance with the following criteria
1 Price adjustments will be based on the fuel price index established by the Department on the first working
day of each month The index will be the rate posted by the Oil Price Information Service (OPIS) on the
first working day of the month for Denver No 2 Diesel The rate used will be the OPIS Average taken
from the OPIS Standard Rack table for Ultra Low Sulfur w/Lubncity Gross Prices (ULS column)
expressed in dollars per gallon and rounded to two decimal places
2 Price adjustments will be paid on a monthly basis with the following conditions
A Payment will be based on the pay quantities on the monthly partial pay estimate for the following pay
items for which fuel factors have been established
202-Removal of Asphalt Mat (Planing)
0 006 Galt$Y/Inch depth
203 Excavation (muck unclassified) Embankment Borrow
0 29 Gal/CY
203-Excavation (rock)
0 39 Gal/CY
206 Structure Excavation and Backfill [applies only to quantities
0 29 Gal/CY
paid for by separate bid item no adjustment will be made for
pay items that include structure excavation & backfill such as
RCP(CIP)]
304 Aggregate Base Course (if ABC is paid for by the CY) (if
0 85 Gal/CY
ABC is paid for by the ton convert to CY by multiplying the
quantity in tons by 0 557)
307 Lime Treated Subgrade
0 12 Gal/SY
310 Full Depth Reclamation
0 06 Gal/SY
403 Hot Mix Asphalt (HMA)
2 47 Gal/Ton
403 Stone Mastic Asphalt
2 47 Gal/Ton
405 Heating and Scarifying Treatment
0 44 Gal/SY
406 Cold Bituminous Pavement Recycle
0 01 Gal/SY/Inch depth
412 Portland Cement Concrete Pavement
0 03 Gal/SY/Inch thickness
B A price adjustment will be made only when the current fuel price index varies by more than 5 percent
from the price index at the time of bid and only for that portion of the variance in excess of 5 percent
Price adjustments may be either positive or negative dollar amounts
C No fuel price adjustments will be made for any partial estimate falling wholly after the expiration of
contract time
November30 2006
2
REVISION OF SECTION 109
FUEL COST ADJUSTMENT
D Adjustment formula
EP greater than BP
FA = (EP — 1 05 BP)(Q)(FF)
EP less than BP
FA = (EP — 0 95 BP)(Q)(FF)
Where
BP = Fuel price index for the month in which bids are opened
EP = Fuel price index for the month in which the partial estimate pay penod ends
FA = Adjustment for fuel costs in dollars
FF = Fuel usage factor for the pay item
Q = Pay quantity for the pay item on the monthly partial pay estimate
Note When they pay item is based on area and the rate of fuel use varies with
thickness Q should be determined by multiplying the area by the thickness For
example for 1000 square yards of 8 inch concrete pavement Q should be 8000
E No adjustment will be allowed for the quantity of any item that is left in place at no pay
The fuel cost adjustment will be the sum of the individual adjustments for each of the pay items shown No
adjustment will be made for fuel costs on items other than those shown The factors shown are aggregate
adjustments for all types of fuels used including but not limited to gasoline diesel propane and burner fuel
No additional adjustments will be made for any type of fuel
Fuel cost adjustments resulting in an increased payment to the Contractor will be paid for under the planned
force account item Fuel Cost Adjustment Fuel cost adjustments resulting in a decreased payment to the
Contractor will be deducted from monies owed the Contractor
August 1 2005
REVISION OF SECTION 109
MEASUREMENT OF QUANTITIES
Section 109 of the Standard Specifications is hereby revised for this protect as follows
In subsection 109 01 following paragraph 15 add the following
The Engineer will randomly verify the accuracy of the certified weigher on every protect where the weights are
manually entered on the scale ticket This verification will consist of at least one comparison check on the protect
Additional verification checks maybe required as determined by the Engineer The Engineer will randomly select
a loaded truck after the truck has been issued a scale ticket by the certified weigher The loaded truck will then be
reweighed in the presence of the Engineer on the same scale and the weight compared with the weight on the
scale ticket Reweighed loads shall be within the tolerance of 200 pounds plus or minus
The Engineer will also verify the accuracy of computerized scales Computerized scales are scales that
automatically print weights on the scale ticket This verification will consist of at least one comparison check
when the protect requires more than 2500 tons of matenal to be weighed This comparison check shall be made
by reweighmg a loaded vehicle The Contractor shall either provide a second certified scale or select a second
certified scale in the vicinity to be used for the comparison check Comparison checks shall be performed using
the following procedures
(1) Hopper Scale A loaded truck will be randomly selected by the Engineer The loaded truck shall be weighed
on a certified platform scale to record the gross weight The truck shall be unloaded and weighed again on
the same scale to record the tare weight The tare weight shall be subtracted from the gross weight and
compared against the net weight recorded on the scale ticket
(2) Platform Scales A loaded truck will be randomly selected by the Engineer The loaded truck shall be
reweighed on a second certified scale and the gross weight shall be compared against the gross weight on
the first scale ticket
Should a comparison check reveal a weight difference of more than one percent a second comparison check
shall be performed immediately If the weight differences of both companson checks exceed the one percent
limit the Contractor shall immediately stop weighing and the scale shall be recertified and resealed at the
Contractors expense The necessary adjustments as indicated by the recertification will be made to all scale
tickets issued since the last certification or on the entire project whichever occurred later unless the Contractor
demonstrates to the satisfaction of the Engineer that the defect in the scale was present for a lesser penod of
time
If it is necessary to recertify a scale and more than 2500 tons of material remain to be weighed another scale
comparison check shall be made
All comparison checks shall be made at the Contractors expense
September 2 2005
REVISION OF SECTIONS 614 AND 630
RETROREFLECTIVE SIGN SHEETING
Sections 614 and 630 of the Standard Specifications are hereby revised for this project as follows
In subsection 614 04 first paragraph delete the second sentence and replace with the following
Retroreflective sheeting shall be Type III as defined in the CDOT Retroreflective Sheeting Materials Guide and
shall conform to subsections 713 04 and 713 06 when applicable
In subsection 614 04 delete the second paragraph and replace with the following
Retroreflective sheeting for all signs requiring a yellow background shall be Type Fluorescent
In subsection 630 02 delete the third and fourth paragraphs including Table 630 1 and replace with the
following
Retroreflective sign sheeting types shall be as defined in the CDOT Retroreflective Sheeting Materials Guide
Retroreflective sheeting shall be one of the types specified for the particular application in Table 630 1
Retroreflective sheeting for all signs requiring an orange or yellow background shall be Type Fluorescent
Table 630 1
RETROREFLECTIVE SHEETING TYPES
Apn17 2006
REVISION OF SECTION 630
CONSTRUCTION ZONE TRAFFIC CONTROL
Section 630 of the Standard Specifications is hereby revised for this project as follows
Subsection 630 10 shall include the following after the first paragraph
The Contractors Superintendent and all others serving in a similar supervisory capacity shall have completed a
CDOT approved two-day Traffic Control Supervisor training as offered by the CCA The one day ATSSA Traffic
Control Technician (TCT) training along with the two day ATSSA Traffic Control Supervisor training will serve as
an alternate If the alternate is chosen the Contractor shall provide written evidence that at least an 80 percent
score was achieved in both of the two training classes The certifications of completion or certifications of
achievement for all appropriate staff shall be submitted to the Engineer at the preconstruction conference
In subsection 630 15 delete the fifth paragraph and replace with the following
The Contractor shall agree to quantities for the following items on a weekly basis when signing the Form 7
Traffic Control Management Day
Flagging Hour
bNR��y� n 460 1 Z t k e r
Apn17 2006
REVISION OF SECTION 630
METHOD OF HANDLING TRAFFIC
Section 630 of the Standard Specifications is hereby revised for this project as follows
In subsection 630 09 (8) delete Table 630 2 and replace with the following
Table 630-2
VERTICAL CLEARANCES TO STRUCTURES
OUnderpasses
ighway Railway
Under asses Overhead Wires
Rural Arterial
Urban Arterial 6 Feet 23 Fee? 3
Freeways
Vertical clearance to sign trusses and pedestrian overpasses shall be 17 feet
2 Measured from top of rail to bottom of highway structure All railway clearances are subject to the individual railroad s
approval
3 Communication and power lines of
0 to 750 volts 18 Feet
750 to 22 000 volts 20 Feet
22 000 to 50 000 volts 22 Feet
For voltages over 50 000 volts increase clearance '/2 inch for each 1000 volts
SECTION 00300
BID FORM
August2 2007
REVISION OF SECTION 630
NCHRP 350 REQUIREMENTS
Section 630 of the Standard Specifications is hereby revised for this project as follows
In subsection 630 01 first paragraph delete the second sentence
In subsection 630 08 delete the second paragraph and replace with the following
Work zone devices designated by FHWA as Category 1 II or III shall meet NCHRP 350 requirements Devices
designated as Category IV including but not limited to portable or trader -mounted devices such as flashing arrow
panels temporary traffic signals area lighting supports and changeable message signs are not required to meet
NCHRP 350 requirements
Except for Category IV devices the Contractor shall obtain and present to the Engineer the manufacturers written
NCHRP 350 certification for each work zone device before it is first used on the project
June 7 2007
REVISION OF SECTION 630
PAYMENT FOR CONSTRUCTION TRAFFIC CONTROL DEVICES
Section 630 of the Standard Specifications is hereby revised for this project as follows
In subsection 630 15 delete the second paragraph and replace with the following
Construction traffic control devices as determined by the project Traffic Control Plan (TCP) will be paid for as
follows 50 percent of the accepted amount upon first utilization an additional 40 percent of the accepted amount
when 75 percent of the original contract amount has been earned and the final 10 percent when the project has
been completed in accordance with subsection 105 20 exclusive of any maintenance penods The percent of
original contract amount earned will be determined by comparing the amount earned for bid items other than
traffic control devices and mobilization with the original contract amount minus the amounts bid for traffic control
devices and mobilization
August 2005
REVISION OF SECTION 630
PORTABLE SIGN STORAGE
Section 630 of the Standard Specifications is hereby revised for this project as follows
In subsection 630 12 first paragraph delete the fifth sentence and replace with the following
When storing portable signs or supports within the protect they shall be removed beyond the clear zone and shall
not be visible to traffic All storage areas shall be approved The minimum clear zone distance shall be 18 feet
measured from the edge of traveled way If the signs cannot be stored at least 18 feet from the traveled way they
shall be removed Signs shall not be stored on the paved surface
August 2005
1
AFFIRMATIVE ACTION REQUIREMENTS
EQUAL EMPLOYMENT OPPORTUNITY
A AFFIRMATIVE ACTION REQUIREMENTS
Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity (Executive Order 11246)
The Bidders attention is called to the Equal Opportunity Clause and the Standard Federal Equal
Employment Opportunity Construction Contract Specifications set forth herein
The goals and timetables for minority and female participation expressed in percentage terms for the
Contractors aggregate workforce in each trade on all construction work in the covered area are as
follows
Goals and Timetable for Minority Utilization
Timetable Until
Further Notice
Economic
Standard Metropolitan
Counties
Goal
Area
Statistical Area SMSA
Involved
157
2080 Denver Boulder
Adams Arapahoe Boulder Denver
(Denver)
Douglas Gilpin Jefferson
13 8%
2670 Fort Collins
Larimer
6 9%
3060 Greeley
Weld
13 1 %
Non SMSA Counties
Cheyenne Clear Creek Elbert
Grand Kit Carson Logan Morgan
Park Phillips Sedgwick Summit
Washington & Yuma
12 8%
158
1720 Colorado Springs
El Paso Teller
10 9%
(Colo Spgs
6560 Pueblo
Pueblo
27 5%
Pueblo)
Non SMSA Counties
Alamosa Baca Bent Chaffee
Coneios Costilla Crowley Custer
Fremont Huerfano Kiowa Lake
Las Ammas Lincoln Mineral Otero
Prowers Rio Grande Sa uache
19 0%
159
Non SMSA
Archuleta Delta Dolores Eagle
(Grand Junction)
Garfield Gunnison Hinsdale
La Plata Mesa Moffat Montezuma
Montrose Ouray Pitkin Rio Blanco
Routt San Juan San Miguel
10 2%
156 (Cheyenne
Non SMSA
Jackson County Colorado
7 5%
Casper WY)
GOALS AND TIMETABLES FOR FEMALE UTILIZATION
Until Further Notice 6 9% Statewide
August 2005
2
AFFIRMATIVE ACTION REQUIREMENTS
EQUAL EMPLOYMENT OPPORTUNITY
These goals are applicable to all the Contractors construction work (whether or not it is Federal or
federally assisted) performed in the covered area If the Contractor performs construction work in a
geographical area located outside of the covered area it shall apply the goals established for such
geographical area where the work is actually performed With regard to this second area the Contractor
also is subject to the goals for both its federally involved and non -federally involved construction
The Contractors compliance with the Executive Order and the regulations in 41 CFR Part 60-4 shall be
based on its implementation of the Equal Opportunity Clause specific affirmative action obligations
required by the specifications set forth in 41 CFR 60-4 3(a) and its efforts meet the goals established for
the geographical area where the contract resulting form this solicitation is to be performed The hours of
minority and female employment and training must be substantially uniform throughout the length of the
contract and in each trade and the Contractor shall make a good faith effort to employ minorities and
women evenly on each of its protects The transfer of minority or female employees or trainees from
Contractor to Contractor or from protect to protect for the sole purpose of meeting the Contractors goals
shall be a violation of the contract the Executive Order and the regulations in 41 CFR Par 60 4
Compliance with the goals will be measured against the total work hours performed
The Contractor shall provide written notification to the Director of the Office of Federal Contract
Compliance Programs within 10 working days of award of any construction subcontract in excess
of $10 000 at any tier for construction work under the contract resulting from this solicitation The
notification shall list the name address and telephone number of the subcontractor employer
identification number estimated dollar amount of the subcontract estimated starting and
completion dates of the subcontract and the geographical area in which the contract is to be
performed
4 As used in this specification and in the contract resulting from this solicitation the covered area
is the county or counties shown on the Invitation for Bids and on the plans In cases where the
work is in two or more counties covered by differing percentage goals the highest percentage will
govern
August 2005
3
AFFIRMATIVE ACTION REQUIREMENTS
EQUAL EMPLOYMENT OPPORTUNITY
B STANDARD FEDERAL EQUAL EMPLOYMENT OPPORTUNITY CONSTRUCTION CONTRACT
SPECIFICATIONS
Standard Federal Equal Employment Opportunity Construction Contract Specifications (Executive Order 11246)
1 As used in these Specifications
a Covered area means the geographical area described in the solicitation from which this contract
resulted
b Director" means Director Office of Federal Contract Compliance Programs United States
Department of Labor or any person to whom the Director delegates authority
c Employer identification number means the Federal Social Security number used on the Employers
Quarterly Federal Tax Return U S Treasury Department Form 941
d Minority includes
(1) Black (all persons having ongins in any of the Black African racial groups not of Hispanic
origin)
(n) Hispanic (all persons of Mexican Puerto Rican Cuban Central or South American or other
Spanish Culture or origin regardless of race)
(ni) Asian and Pacific Islander (all persons having origins in any of the original peoples of the Far
East Southeast Asia the Indian Subcontinent or the Pacific Islands) and
(iv) American Indian or Alaskan Native (all persons having origins in any of the original peoples
of North America and maintaining identifiable tribal affiliations through membership and
participation or community identification)
2 Whenever the Contractor or any Subcontractor at any tier subcontracts a portion of the work involving
any construction trade it shall physically include in each subcontract in excess of $10 000 the provisions
of these specifications and the Notice which contains the applicable goals for minority and female
participation and which is set forth in the solicitations from which this contract resulted
If the Contractor is participating (pursuant to 41 CFR 60 4 5) in a Hometown Plan approved by the U S
Department of Labor in the covered area either individually or through an association its affirmative
action obligations on all work in the Plan area (including goals and timetables) shall be in accordance with
that Plan for those trades which have unions participating in the Plan Contractors must be able to
demonstrate their participation in and compliance with the provisions of any such Hometown Plan Each
Contractor or Subcontractor participating in an approved Plan is individually required to comply with its
obligations under the EEO clause and to make a good faith effort to achieve each goal under the Plan in
each trade in which it has employees The overall good faith performance by other Contractors or
Subcontractor toward a goal in an approved Plan does not excuse any covered Contractors or
Subcontractors failure to take good faith efforts to achieve the Plan goals and timetables
4 The Contractor shall implement the specific affirmative action standards provided in paragraphs 7a
through p of these specifications The goals set forth in the solicitation from which this contract resulted
are expressed as percentages of the total hours of employment and training of minority and female
utilization the Contractor should reasonably be able to achieve in each construction trade in which it has
employees in the covered area Covered Construction contractors performing construction work in
geographical areas where they do not have a Federal or federally assisted construction contract shall
apply the minority and female goals established for the geographical area where the work is being
performed Goals are published periodically in the Federal Register in notice form and such notices may
be obtained from any office of Federal Contract Compliance Programs Office or from Federal
procurement contracting officers The Contractor is expected to make substantially uniform progress in
meeting its goals in each craft during the period specified
August 2005
4
AFFIRMATIVE ACTION REQUIREMENTS
EQUAL EMPLOYMENT OPPORTUNITY
Neither the provisions of any collective bargaining agreement nor the failure by a union with whom the
Contractor has a collective bargaining agreement to refer either minorities or women shall excuse the
Contractors obligations under these specifications Executive Order 11246 or the regulations
promulgated pursuant thereto
6 In order for the nonworking training hours of apprentices and trainees to be counted in meeting the goals
such apprentices and trainees must be employed by the Contractor during the training period and the
Contractor must have made a commitment to employ the apprentices and trainees at the completion of
their training subject to the availability of employment opportunities Trainees must be trained pursuant
to training programs approved by the U S Department of Labor
7 The Contractor shall take specific affirmative actions to ensure equal employment opportunity The
evaluation of the Contractor's compliance with these specifications shall be based upon its effort to
achieve maximum results from its actions The Contractor shall document these efforts fully and shall
implement affirmative action steps at least as extensive as the following
a Ensure and maintain a working environment free of harassment intimidation and coercion at all
sites and in all facilities at which the Contractor's employees are assigned to work The Contractor
where possible will assign two or more women to each construction protect The Contractor shall
specifically ensure that all foremen superintendents and other on -site supervisory personnel are
aware of and carry out the Contractor's obligation to maintain such a working environment with
specific attention to minority or female individuals working at such sites or in such facilities
b Establish and maintain a current list of minority and female recruitment sources provide written
notification to minority and female recruitment sources and to community organizations when the
Contractor or its union have employment opportunities available and maintain a record of the
organization s responses
c Maintain a current file of the names addresses and telephone numbers of each minority and female
off -the street applicant and minority or female referral from a union a recruitment source of
community organization and of what action was taken with respect to each individual If such
individual was sent to the union hiring hall for referral and was not referred back to the Contractor by
the union or if referred not employed by the Contractor this shall be documented in the file with the
reason therefor along with whatever additional actions the Contractor may have taken
d Provide immediate written notification to the Director when the union with which the Contractor has a
collective bargaining agreement has not referred to the Contractor a minority person or woman sent
by the Contractor or when he Contractor has other information that the union referral process has
impeded the Contractors efforts to meet its obligations
e Develop on the job training opportunities and/or participate in training programs for the area which
expressly include minorities and women including upgrading programs and apprenticeship and
trainee programs relevant to the Contractors employment needs especially those programs funded
or approved by the Department of Labor The Contractor shall provide notice of these programs to
the sources compiled under 7b above
f Disseminate the Contractors EEO policy by providing notice of the policy to unions and training
programs and requesting their cooperation in assisting the Contractor in meeting its EEO obligations
by including it in any policy manual and collective bargaining agreement by publicizing it in the
company newspaper annual report etc by specific review of the policy with all management
personnel and with all minority and female employees at least once a year and by posting the
Contractors EEO policy on bulletin boards accessible to all employees at each location where
construction work is performed
August 2005
5
AFFIRMATIVE ACTION REQUIREMENTS
EQUAL EMPLOYMENT OPPORTUNITY
g Review at least annually the Contractors EEO policy and affirmative action obligations under these
specifications with all employees having any responsibility for hiring assignment layoff termination
or other employment decisions including specific review of these items with onsite supervisory
personnel such as Superintendents General Foreman etc prior to the initiation of construction work
at any job site A wntten record shall be made and maintained identifying the time and place of these
meetings persons attending subject matter discussed and disposition of the subject matter
h Disseminate the Contractors EEO policy externally by including it in any advertising in the news
media specifically including minority and female news media and providing written notification to and
discussing the Contractors and Subcontractors with whom the Contractor does or anticipates doing
business
i Direct its recruitment efforts both oral and written to minority female and community organizations
to schools with minority and female students and to minority and female recruitment and training
organizations serving the Contractor's recruitment area and employment needs Not later than one
month prior to the date for the acceptance of applications for apprenticeship or other training by any
recruitment source the Contractor shall send written notification to organizations such as the above
describing the openings screening procedures and tests to be used in the selection process
j Encourage present minority and female employees to recruit other minority persons and women and
where reasonable provide after school summer and vacation employment to minority and female
youth both on the site and in other areas of a Contractors workforce
k Validate all tests and other selection requirements where there is an obligation to do so under 41
CFR Part 60 3
1 Conduct at least annually an inventory and evaluation at least of all minority and female personnel
for promotional opportunities and encourage these employees to seek or to prepare for through
appropriate training etc such opportunities
m Ensure that seniority practices job classifications work assignments and other personnel practices
do not have a discriminatory effect by continually monitoring all personnel and employment related
activities to ensure that the EEO policy and the Contractors obligations under these specifications
are being carried out
n Ensure that all facilities and Contractors activities are nonsegregated except that separate or single
user toilet and necessary changing facilities shall be provided to assure privacy between the sexes
o Document and maintain a record of all solicitations of offers for subcontracts from minority and female
construction contractors and suppliers including circulation of solicitations to minority and female
contractor associations and other business associations
p Conduct a review at least annually of all supervisors adherence to and performance under the
Contractors EEO policies and affirmative action obligation
August 2005
6
AFFIRMATIVE ACTION REQUIREMENTS
EQUAL EMPLOYMENT OPPORTUNITY
Contractors are encouraged to participate in voluntary associations which assist in fulfilling one or more
of their affirmative action obligations (7a through p) The efforts of a contractor association joint
contractor union contractor community or other similar group of which the Contractor is a member and
participant may be asserted as fulfilling any one or more of its obligations under 7a through p of these
specifications provided that the Contractor actively participates in the group makes every effort to assure
that the group has a positive impact on the employment of minorities and women in the industry ensures
that the concrete benefits of the program are reflected in the Contractors minority and female workforce
participation makes a good faith effort to meet its individual goal and timetables and can provide access
to documentation which demonstrates the effectiveness of actions taken on behalf of the Contractor The
obligation to comply however is the Contractors and failure of such a group to fulfill an obligation shall
not be a defense for the Contractor's noncompliance
A single goal for minorities and a separate single goal for women have been established The
Contractor however is required to provide equal employment opportunity and to take affirmative action
for all minority groups both male and female and all women both minority and non minority
Consequently the Contractor may be in violation of the Executive Order if a particular group is employed
in a substantially disparate manner (for example even thought the Contractor has achieved its goals for
women generally the Contractor may be in violation of the Executive Order if a specific minority group of
women is underutilized)
10 The Contractor shall not use the goals and timetables or affirmative action standards to discriminate
against any person because of race color religion sex or national origin
11 The Contractor shall not enter into any Subcontract with any person or firm debarred from Government
contracts pursuant to Executive Order 11246
12 The Contractor shall carry out such sanctions and penalties for violation of these specifications and of the
Equal Opportunity Clause including suspension termination and cancellation of existing subcontracts as
may be imposed or ordered pursuant to Executive Order 11246 as amended and its implementing
regulations by the Office of Federal Contract Compliance Programs Any Contractor who fads to carry
out such sanctions and penalties shall be in violation of these specifications and Executive Order 11246
as amended
13 The Contractor in fulfilling its obligations under these specifications shall implement specific affirmative
action steps at least as extensive as those standards prescribed in paragraph 7 of these specifications
so as to achieve maximum results from its efforts to ensure equal employment opportunity If the
Contractor fails to comply with the requirements of the Executive Order the implementing regulations or
these specifications the Director shall proceed in accordance with 41 CFR 60-4 8
14 The Contractor shall designate a responsible official to monitor all employment related activity to ensure
that the company EEO policy is being carried out to submit reports relating to the provisions hereof as
may be required by the Government and to keep records Records shall at least include for each
employee the name address telephone numbers construction trade union affiliation if any employee
identification number when assigned social security number race sex status (e g mechanic
apprentice trainee helper or laborer) dates of changes in status hours worked per week in the
indicated trade rate of pay and locations at which the work was performed Records shall be maintained
in an easily understandable and retrievable form however to the degree that existing records satisfy this
requirement contractors shall not be required to maintain separate records
15 Nothing herein provided shall be construed as a limitation upon the application of other laws which
establish different standards of compliance or upon application of requirements for the hiring of local or
other area residents (e g those under the Public Works Employment Act of 1977 and the Community
Development Block Grant Program)
August 2005
7
AFFIRMATIVE ACTION REQUIREMENTS
EQUAL EMPLOYMENT OPPORTUNITY
C SPECIFIC EQUAL EMPLOYMENT OPPORTUNITY RESPONSIBILITIES
1 General
Equal employment opportunity requirements not to discriminate and to take affirmative action to
assure equal employment opportunity as required by Executive Order 11246 and Executive Order
11375 are set forth in Required Contract Provisions (Form FHWA 1273 or 1316 as appropriate) and
these Special Provisions which are imposed pursuant to Section 140 of Title 23 U S C as
established by Section 22 of the Federal -Aid highway Act of 1968 The requirements set forth in
these Special Provisions shall constitute the specific affirmative action requirements for project
activities under this contract and supplement the equal employment opportunity requirements set
forth in the Required Contract provisions
b The Contractor will work with the State highway agencies and the Federal Government in carrying out
equal employment opportunity obligations and in their review of his/her activities under the contract
The Contractor and all his/her subcontractors holding subcontracts not including material suppliers of
$10 000 or more will comply with the following minimum specific requirement activities of equal
employment opportunity (The equal employment opportunity requirements of Executive Order
11246 as set forth in Volume 6 Chapter 4 Section 1 Subsection 1 of the Federal Aid Highway
Program Manual are applicable to material suppliers as well as contractors and subcontractors )
The Contractor will include these requirements in every subcontract of $10 000 or more with such
modification of language as is necessary to make them binding on the subcontractor
2 Equal Employment Opportunity Policy The Contractor will accept as his operating policy the following
statement which is designed to further the provision of equal employment opportunity to all persons
without regard to their race color religion sex or national origin and to promote the full realization of
equal employment opportunity through a positive continuing program
It is the policy of this Company to assure that applicants are employed and that employees are treated
during employment without regard to their race religion sex color or national origin Such action shall
include employment upgrading demotion or transfer recruitment or recruitment advertising layoff or
termination rates of pay or other forms of compensation and selection for training including
apprenticeship preapprenticeship and/or on the job training
3 Equal Employment Opportunity Officer The Contractor will designate and make known to the State
highway agency contracting officers and equal employment opportunity officer (herein after referred to as
the EEO Officer) who will have the responsibility for an must be capable of effectively administering and
promoting an active contractor program of equal employment opportunity and who must be assigned
adequate authority and responsibility to do so
4 Dissemination of Policy
a All members of the Contractors staff who are authorized to hire supervise promote and discharge
employees or who recommend such action or who are substantially involved in such action will be
made fully cognizant of and will implement the Contractors equal employment opportunity policy
and contractual responsibilities to provide equal employment opportunity in each grade and
classification of employment To ensure that the above agreement will be met the following actions
will be taken as a minimum
(1) Periodic meetings of supervisory and personnel office employees will be conducted before the
start of work and then not less often than once every six months at which time the Contractors
equal employment opportunity policy and its implementation will be reviewed and explained The
meetings will be conducted by the EEO Officer or other knowledgeable company official
SECTION 00300
BID FORM
PROJECT 6075 Trolley Brick Restoration Project
Place GLH CQ'stLCtu)n, IM
Date
1 In compliance with your Invitation to Bid dated Nuvdmr 15 _, 2007 and
subject to all conditions thereof, the undersigned
a (Corporation, Limited Liability Company, Partnership, Joint Venture, or
Sole Proprietor) authorized to do business in the State of Colorado hereby
proposes to furnish and do everything required by the Contract Documents to
which this refers for the construction of all items listed on the following
Bid Schedule or Bid Schedules
2 The undersigned Bidder does hereby declare and stipulate that this proposal
is made in good faith, without collusion or connection with any other person
or persons Bidding for the same Work, and that it is made in pursuance of
and subject to all the terms and conditions of the Invitation to Bid and
Instructions to Bidders, the Agreement, the detailed Specifications, and the
Drawings pertaining to the Work to be done, all of which have been examined
by the undersigned
3 Accompanying this Bid is a certified or cashier's check or standard Bid bond
in the sum of Y/
($ ) in accordance with the Invitation To Bid and Instructions to
Bidders
4 The undersigned Bidder agrees to execute the Agreement and a Performance
Bond and a Payment Bond for the amount of the total of this Bid within
fifteen (15) calendar days from the date when the written notice of the
award of the contract is delivered to him at the address given on this Bid
The name and address of the corporate surety with which the Bidder proposes
to furnish the specified performance and payment bonds is as follows
hh�.s PrIrhno
5 All the various phases of Work enumerated in the Contract Documents with
their individual jobs and overhead, whether specifically mentioned, included
by implication or appurtenant thereto, are to be performed by the CONTRACTOR
under one of the items listed in the Bid Schedule, irrespective of whether
it is named in said list
6 Payment for Work performed will be in accordance with the Bid Schedule or
Bid Schedules subject to changes as provided in the Contract Documents
7 The undersigned Bidder hereby acknowledges receipt of Addenda No
1 through
Revlazo/07 Section 00300 Page 1
Augustl 2005
8
AFFIRMATIVE ACTION REQUIREMENTS
EQUAL EMPLOYMENT OPPORTUNITY
(2) All new supervisory or personnel office employees will be given a thorough indoctrination by the
EEO Officer or other knowledgeable company official covering all major aspects of the
Contractors equal employment opportunity obligations within thirty days following their reporting
for duty with the Contractor
(3) All personnel who are engaged in direct recruitment for the project will be instructed by the EEO
Officer or appropriate company official in the Contractors procedures for locating and hiring
minority group employees
In order to make the Contractor's equal employment opportunity policy known to all employees
prospective employees and potential sources of employees i e schools employment agencies
labor unions (where appropriate) college placement officers etc the Contractor will take the
following actions
(1) Notices and posters setting forth the Contractors equal employment opportunity policy will be
placed in areas readily accessible to employees applicants for employment and potential
employees
(2) The Contractor's equal employment opportunity policy and the procedures to implement such
policy will be brought to the attention of employees by means of meetings employee
handbooks or other appropriate means
5 Recruitment
a When advertising for employees the Contractor will include in all advertisements for employees
the notation An Equal Opportunity Employer All such advertisements will be published in
newspapers or other publications having a large circulation among minority groups in the area
from which the project work force would normally be derived
The Contractor will unless precluded by a valid bargaining agreement conduct systematic and
direct recruitment through public and private employee referral sources likely to yield qualified
minority group applicants including but not limited to State employment agencies schools
colleges and minority group organizations To meet this requirement the Contractor will through
his EEO Officer identify sources of potential minority group employees and establish with such
identified sources procedures whereby minority group applicants may be referred to the
Contractor for employment consideration
In the event the Contractor has a valid bargaining agreement providing for exclusive hiring hall
referrals he is expected to observe the provisions of that agreement to the extent that the system
permits the Contractors compliance with equal employment opportunity contract provisions
(The U S Department of Labor has held that where implementation of such agreements have the
effect of discriminating against minorities or women or obligates the Contractor to do the same
such implementation violates Executive Order 11246 as amended )
The Contractor will encourage his present employees to refer minority group applicants for
employment by posting appropriate notices or bulletins in areas accessible to all such
employees In addition information and procedures with regard to referring minority group
applicants will be discussed with employees
Personnel Actions Wages working conditions and employee benefits shall be established and
administered and personnel actions of every type including hiring upgrading promotion transfer
demotion layoff and termination shall be taken without regard to race color religion sex or
national origin The following procedures shall be followed
a The Contractor will conduct periodic inspections of project sites to insure that working conditions
and employee facilities do not indicate discriminatory treatment of project site personnel
August 1 2005
9
AFFIRMATIVE ACTION REQUIREMENTS
EQUAL EMPLOYMENT OPPORTUNITY
The Contractor will periodically evaluate the spread of wages paid within each classification to
determine any evidence of discriminatory wage practices
c The Contractor will periodically review selected personnel actions in depth to determine whether
there is evidence of discrimination Where evidence is found the Contractor will promptly take
corrective action If the review indicates that the discrimination may extend beyond the actions
reviewed such corrective action shall include all affected persons
d The Contract will promptly investigate all complaints of alleged discrimination made to the
Contractor in connection with his obligations under this contract will attempt to resolve such
complaints and will take appropriate corrective action within a reasonable time If the
investigation indicates that the discrimination may affect persons other than the complainant
such corrective action shall include such other persons Upon completion of each investigation
the Contractor will inform every complainant of all of his avenues of appeal
7 Training and Promotion
a The Contractor will assist in locating qualifying and increasing the skills of minority group and
women employees and applicants for employment
b Consistent with the Contractors work force requirements and as permissible under Federal and
State regulations the Contractor shall make full use of training programs i e apprenticeship
and on -the job training programs for the geographical area of contract performance Where
feasible 25 percent of apprentices or trainees in each occupation shall be in their first year of
apprenticeship or training
c The Contractor will advise employees and applicants for employment of available training
programs and entrance requirements for each
d The Contractor will periodically review the training and promotion potential of minority group and
women employees and will encourage eligible employees to apply for such training and
promotion
8 Unions If the Contractor relies in whole or in part upon unions as a source of employees the
Contractor will use his/her best efforts to obtain the cooperation of such unions to increase
opportunities for minority groups and women with the unions and to effect referrals by such unions of
minority and female employees Actions by the Contractor either directly or thorough a contractors
association acting as agent will include the procedures set forth below
The Contractor will use best efforts to develop in cooperation with the unions joint training
programs aimed toward qualifying more minority group members and women for membership in
the unions and increasing the skills of minority group employees and women so that they may
qualify for higher paying employment
b The Contractor will use best efforts to incorporate an equal employment opportunity clause into
each union agreement to the end that such union will be contractually bound to refer applicants
without regard to their race color religion sex or national origin
c The Contractor is to obtain information as to the referral practices and policies of the labor union
except that to the extent such information is within the exclusive possession of the labor union
and such labor union refuses to furnish such information to the Contractor the Contractor shall
so certify to the State highway department and shall set forth what efforts have been made to
obtain such information
August 2005
10
AFFIRMATIVE ACTION REQUIREMENTS
EQUAL EMPLOYMENT OPPORTUNITY
In the event the union is unable to provide the Contractor with a reasonable flow of minority and
women referrals within he time limit set forth in the collective bargaining agreement the Contractor
will through independent recruitment efforts fill the employment vacancies without regard to race
color religion sex or national origin making full efforts to obtain qualified and/or qualifiable minority
group persons and women (The U S Department of Labor has held that it shall be no excuse that
the union with which the Contractor has a collective bargaining agreement providing for exclusive
referral faded to refer minority employees ) In the event the union referral practice prevents the
Contractor from meeting the obligations pursuant to Executive Order 11246 as amended and these
special provisions such Contractor shall immediately notify the State highway agency
9 Subcontracting
a The Contractor will use his best efforts to solicit bids from and to utilize minority group subcontractors
or subcontractors with meaningful minority group and female representation among their employees
Contractors shall obtain lists of minority owned construction firms from State highway agency
personnel
The Contractor will use his best efforts to ensure subcontractor compliance with their equal
employment opportunity obligations
10 Records and Reports
The Contractor will keep such records as are necessary to determine compliance with the
Contractors equal employment opportunity obligations The records kept by the Contractor will be
designed to indicate
(1) The number of minority and nonmmonty group members and women employed in each work
classification on the project
(2) The Progress and efforts being made in cooperation with unions to increase employment
opportunities for minorities and women (applicable only to contractors who rely in whole or in part
on unions as a source of their work force)
(3) The progress and efforts being made in locating hiring training qualifying and upgrading
minority and female employees and
(4) The progress and efforts being made in securing the services of minority group subcontractors or
subcontractors with meaningful minority and female representation among their employees
b All such records must be retained for a period of three years following completion of the contract work
and shall be available at reasonable times and places for inspection by authorized representatives of
the State highway agency and the Federal Highway Administration
c The Contractors will submit an annual report to the State highway agency each July for the duration
of the project indicating the number of minority women and non minority group employees currently
engaged in each work classification required by the contract work This information is to be reported
on Form PR 1391
December 8 2005
1
DISADVANTAGED BUSINESS ENTERPRISE
DEFINITIONS AND REQUIREMENTS
(a) Definitions and Procedures
For this protect the following terms are defined
1 Disadvantaged Business Enterprise (DBE) A small business concern that is certified as being
A At least 51 percent owned by one or more socially and economically disadvantaged individuals or in
the case of any publicly owned business at least 51 percent of the stock of which is owned by one or
more socially and economically disadvantaged individuals and
B Whose management and daily business operations are controlled by one or more of the socially and
economically disadvantaged individuals who own it
C Socially and economically disadvantaged individual means any individual who is a citizen (or lawfully
admitted permanent resident) of the United States and who is
(1) Any individual whom the Colorado Department of Transportation Office of Certification or the City
and County of Denver Division of Small Business Opportunity (DSBO) finds to be a socially and
economically disadvantaged individual
(2) Any individual in the following groups members of which are rebuttably presumed to be socially
and economically disadvantaged
a Black Americans which includes persons having origins in any of the Black racial groups of
Africa
b Hispanic Americans which includes persons of Mexican Puerto Rican Cuban Dominican
Central or South American or other Spanish or Portuguese culture or origin regardless of
race
c Native Americans which includes persons who are American Indians Eskimos Aleuts or
Native Hawaiians
d Asian Pacific Americans which includes persons whose origins are from Japan China
Taiwan Korea Burma (Myanmar) Vietnam Laos Cambodia (Kampuchea) Thailand
Malaysia Indonesia the Philippines Brunei Samoa Guam the U S Trust Territories of the
Pacific Islands (Republic of Palau) the Commonwealth of the Northern Marianas Islands
Macao Fiji Tonga Kirbati Juvalu Nauru Federated States of Micronesia or Hong Kong
e Subcontinent Asian Americans which includes persons whose origins are from India
Pakistan Bangladesh Bhutan the Maldives Islands Nepal or Sri Lanka
f Women which means females of any ethnicity
g Other which means any additional groups whose members are designated as socially and
economically disadvantaged by the Small Business Administration (SBA) at such time as the
SBA designation becomes effective and/or individuals who have been determined to be
socially and economically disadvantaged based on the criteria for social and economic
disadvantage
2 Underutilized DBE (UDBE) A firm which meets the definition of DBE above and is eligible to meet the
contract goal as defined in the project special provision titled Contract Goal
3 DBE Joint Venture Joint venture means an association of a DBE firm and one or more other firms to
carry out a single for profit business enterprise for which the parties combine their property capital
efforts skills and knowledge and in which the DBE is responsible for a distinct clearly defined portion of
the work of the contract and whose share in the capital contribution control management risks and
profits of the joint venture are commensurate with its ownership interest
December 8 2005
2
DISADVANTAGED BUSINESS ENTERPRISE
DEFINITIONS AND REQUIREMENTS
A DBE joint venture must be certified as a joint venture by the Business Programs Office at CDOT
A For those projects set -aside for bidding by UDBEs only all of the partners in a joint venture must be
UDBEs and certification of the joint venture will not be required
B For all projects other than the set aside projects discussed in A above one of the partners in a joint
venture must be a DBE The DBE percentage of the joint venture will be determined at the time of
certification
4 Contract Goal The goal for UDBE participation that the Department determines should appropriately be
met by the successful bidder Contract goal will be the percentage stated in the invitation for bids and in
the project special provisions Successful bidders that are awarded a Contract based on good faith
efforts shall continue to make good faith efforts through the period of time that work on the project is in
process to provide for additional UDBE participation toward meeting the goal
Good Faith Efforts It is the obligation of the bidder to make good faith efforts to meet the contract goal
prior to the bid opening The bidder can demonstrate that it has done so either by meeting the contract
goal or by documenting good faith efforts made CDOT will evaluate only the good faith efforts made by
the contractor pnor to the bid opening Any UDBE Participation submitted on Form 715 that exceeds the
participation submitted on Form 714 will be accepted as additional UDBE participation but will not be
counted as Good Faith Efforts and will not exempt a contractor from fulfilling the Good Faith Efforts
requirements The apparent low bidder shall report all efforts made including but not limited to the efforts
required on Form 718 The efforts employed by the bidder should be those that one could reasonably
expect a bidder to take if the bidder were actively and aggressively trying to obtain UDBE participation
sufficient to meet the DBE contract goal In determining whether a bidder has made good faith efforts
CDOT may take into account the performance of other bidders in meeting the contract For example
when the apparent successful bidder fails to meet the contract goal but others meet it CDOT may
reasonably raise the question of whether with additional reasonable efforts the apparent successful
bidder could have met the goal If the apparent successful bidder fails to meet the goal but meets or
exceeds the average UDBE participation obtained by other bidders CDOT may view this in conjunction
with other factors as evidence of the apparent successful bidder having made good faith efforts
The Business Programs Office with the DBE Liaison s Approval will notify the apparent low bidder by fax
regarding any deficiencies in the documentation and effort demonstrated by the bidder This fax will
include the Business Programs Office s recommendation to the DBE Liaison Officer regarding whether
the good faith effort demonstrated was sufficient for the bidder to be regarded as responsible If the
bidder may be regarded as responsible but with minor deficiencies in its good faith effort the bidder will
be expected to correct any deficiencies noted prior to bidding on other CDOT projects
Within five working days of being informed by the Business Programs Office that it is not a responsible
bidder because it has not documented sufficient good faith efforts a bidder may request administrative
reconsideration from the Good Faith Efforts (GFE) Committee which will not have played any role in the
original determination that the bidder did not document sufficient good faith efforts The bidder should
make this request to
Good Faith Efforts Committee
Fax 303 757 9019
Phone 303 757 9234
As part of this reconsideration the bidder will have the opportunity to provide written documentation or
argument concerning the issue of whether it met the goal or made adequate good faith efforts prior to the
bid opening to do so The bidder will also have the opportunity to meet in person with CDOT s GFE
Committee to discuss the issue of whether it met the goal or made adequate good faith efforts prior to the
bid opening to do so The Business Programs Office with the DBE Liaisons Approval will send the
bidder a written decision on reconsideration explaining the basis for finding that the bidder did or did not
meet the goal or make adequate good faith efforts prior to the bid opening to do so
December 8 2005
3
DISADVANTAGED BUSINESS ENTERPRISE
DEFINITIONS AND REQUIREMENTS
The GFE Review Committee will make a recommendation to the DBE Liaison Officer The DBE Liaison
Officer will review the good faith efforts documentation and the recommendation of the GFE Review
Committee determine whether the required efforts are sufficient for award and notify the Chief Engineer
of this finding The Chief Engineer will make the final decision regarding award There will be no
administrative appeal of the Chief Engineers decision
If award of the Contract is made based on the Contractors good faith efforts the goal will not be waived
The Contractor will be expected to continue to make good faith efforts as described below throughout the
duration of the Contract
To demonstrate Good Faith Efforts to meet the contract goal throughout the performance of the Contract
the Contractor shall document to the CDOT Region Civil Rights Professional the steps taken on Form
205 For each subcontract item not identified for DBE participation on Form 718 steps the Contractor
must take include but are not limited to the following
A Seek out and consider UDBEs as potential subcontractors
(1) Contact all UDBEs for each category of work that is being subcontracted
(2) Affirmatively solicit their interest capability and price quotations
(3) Provide equal time for all prospective subcontractors to prepare their proposals
(4) Provide at least as much time to UDBEs in assisting them to prepare their bids for subcontract
work as to non UDBE subcontractors
(5) Award subcontracts to UDBEs where their quotations are reasonably competitive with other
quotations received
B Maintain documentation of UDBEs contacted and their responses
(1) Maintain a list of UDBEs contacted as prospective subcontractors
(2) Maintain thorough documentation of criteria used to select each subcontractor
(3) Where a UDBE expressed an interest in a subcontract and made a quotation and where the
work was not awarded to a UDBE furnish a detailed letter explaining the reasons
(b) Certification as a DBE by the Department
1 Any contractor may apply to the Colorado Department of Transportation Office of Certification or the City
and County of Denver Division of Small Business Opportunity (DSBO) for status as a DBE Application
shall be made on the USDOT s Uniform Certification Application Form as provided by these agencies for
certification of DBEs Application need not be made in connection with a particular bid Only work
contracted to UDBE contractors or subcontracted to UDBEs and independently performed by UDBEs
shall be considered toward contract goals as established elsewhere in these specifications
2 It shall be the Contractor's responsibility to submit applications so that the certifying agency has sufficient
time to render decisions The certifying agency will review applications in a timely manner but is not
committed to render decisions about a firm s DBE status within any given period of time
3 The Department will publish an online directory of DBE contractors vendors and suppliers for the
purpose of providing a reference source to assist any bidder in identifying DBEs and UDBEs Bidders will
be solely responsible for verifying the Certification of DBEs they intend to use prior to submitting a
proposal The directory is updated daily by the certifying agencies and is accessible online at
http //www dot state co us/app_ucp/
4 Bidders shall exercise their own judgments in selecting any subcontractor to perform any portion of the
work
5 Permission for a DBE/non DBE joint venture to bid on a specific project may be obtained from the
Business Programs Office based on information provided by the proposed joint venture on Form 893
Information For Determining DBE Participation When A Joint Venture Includes A DBE Joint
applications should be submitted well in advance of bid openings
4
DISADVANTAGED BUSINESS ENTERPRISE
DEFINITIONS AND REQUIREMENTS
(c) Bidding Requirements
December 8 2005
All bidders shall submit with their proposals a fully executed Form 714 including a list of the names of
their UDBE subcontractors to meet the contract goal The apparent low bidder shall submit a fully
executed Form 715 for each UDBE used to meet the contract goal (sample attached) no later than 4 00
p m on the third work day after the date of bid opening to the Business Programs Office in the Center for
Equal Opportunity Form 715 may be submitted by FAX at Fax number (303)757 9019 with an original
copy to follow If the contract goal is not met the apparent low bidder shall submit a completed Form 718
and corresponding evidence of good faith efforts no later than 4 00 on the day following the bid opening
to the Business Programs Office in the Center for Equal Opportunity CDOT Form No 718 may be
submitted by FAX at Fax number (303)757 9019 with an original copy to follow A copy of Form 718 is
incorporated into this specification
2 The award of Contract if awarded will be made to the lowest responsible bidder that will meet or exceed
the contract goal or if the goal will not be met is able to demonstrate that good faith efforts were made to
meet the goal Good faith efforts are explained in (a) of this special provision
3 The use of the UDBE firms named on Form 714 or on a Form 715 for the items of work described is a
condition of award The replacement of a named UDBE firm will be allowed only as provided for in (a) of
this special provision Failure to comply will constitute grounds for default and termination of the
Contract
4 Contractors DBE Obligation The prime Contractor bidding on construction projects advertised by the
Department agrees to ensure that Disadvantaged Business Enterprises (DBEs) as defined in this special
provision have equal opportunity to participate in the performance of contracts or subcontracts financed
in whole or in part with Federal or State funds The prime Contractor shall not discriminate on the basis
of race color national origin or sex in the bidding process or the performance of contracts
To ensure that UDBEs are offered equal opportunity to participate in the performance of contracts it is
the responsibility of the prime Contractor to offer and to provide assistance to UDBEs related to the
UDBE performance of the subcontract However the UDBE must independently perform a commercially
useful function on the project
(d) Counting DBE Participation Toward Contract Goals and CDOT s annual DBE goal
1 Once a firm has been certified as a DBE the total dollar amount of the contract awarded to the firm shall
be counted toward CDOT s annual DBE goal and the contract goal as explained below and as modified
for the project in the project special provisions titled Contract Goal
2 The actual dollar total of a proposed subcontract supply or service contract with any DBE firm shall be
reported to the Department using Form 713 A Form 713 for subcontracts is to be submitted with the
Form 205 and receipt will be a condition of approval The eligibility of a proposed DBE subcontractor will
be finally established based on the firm s status at the time of Form 205 approval
A Form 713 for a supply or service contract is to be submitted once a contract has been fully executed so
the Department will be able to report the DBE participation in a timely manner The eligibility of a DBE
supplier or service firm will be finally established as of the date the Form 713 is received by the
Department A Form 205 is not required for a supply or service contract
If a firm becomes certified as a DBE during performance under a fully executed contract with CDOT but
prior to the DBE performing any work then 100 percent of the work performed by the firm under that
contract may be claimed as eligible work
3 The Contractor may count toward its contract goal the percentage of the total dollar amount of a contract
with a Department certified joint venture that equals the percentage of the ownership and control of the
UDBE partner in a joint venture
December 8 2005
5
DISADVANTAGED BUSINESS ENTERPRISE
DEFINITIONS AND REQUIREMENTS
4 A The Contractor may count toward its contract goal only that percentage of expenditures to UDBEs
which independently perform a commercially useful function in the work of a contract A DBE is
considered to be performing a commercially useful function by actually performing managing and
supervising the work involved To determine whether a DBE is performing a commercially useful function
the Department will evaluate the amount of work subcontracted work performed solely by the DBE
industry practices and other relevant factors
B A DBE may enter into subcontracts consistent with normal industry practices If a DBE does not
perform or exercise responsibility for at least 30 percent of the total cost of its contract with its own work
force or the DBE subcontracts a greater portion of the work of a contract than would be expected on the
basis of normal industry practice for the type of work involved the DBE shall be presumed not to be
performing a commercially useful function The DBE may present evidence to rebut this presumption to
the Department
The Contractor may count toward its contract goal the percentage of expenditures for transportation
services obtained from UDBE trucking firms provided the UDBE controls the trucking operations for
which it seeks credit A UDBE trucking firm must have at least one truck and driver of its own but it can
lease trucks owned by others both DBEs and non -DBEs including owner operators For work done with
its own trucks and drivers and for work done with DBE lessees the UDBE trucking firm receives credit for
all transportation services provided For work done with non DBE lessees the UDBE trucking firm gets
credit only for the fees or commissions it receives for arranging the transportation services because the
services themselves are being performed by non DBEs
6 The Contractor may count toward its contract goal the percentage of expenditures for materials and
supplies obtained from UDBE suppliers (regular dealers) and manufacturers provided that the UDBEs
assume the actual and contractual responsibility for and actually provide the materials and supplies
A The Contractor may count 100 percent of its expenditures to a UDBE manufacturer A DBE
manufacturer is a certified firm that operates or maintains a factory or establishment that produces on
the premises the materials or supplies obtained by the Contractor
The Contractor may count 60 percent of its expenditures to UDBE suppliers (regular dealers) that are
not manufacturers provided that the DBE supplier performs a commercially useful function in the
supply process A DBE supplier (regular dealer) is a certified firm that owns operates or maintains a
store warehouse or other establishment in which the materials or supplies required for the
performance of the Contract are bought kept in stock and regularly sold to the public in the usual
course of business To be a supplier (regular dealer) the firm must engage in as its principal
business and in its own name the purchase and sale of the products in question A supplier in such
bulk items as steel cement gravel stone and petroleum products need not keep such products in
stock if it owns or operates distribution equipment Brokers and packagers shall not be regarded as
manufacturers or suppliers within the meaning of this section
C The Contractor may count toward its contract goal the following expenditures to UDBE firms that are
not manufacturers or suppliers (regular dealers)
(1) The fees or commissions charged for providing a bona fide service such as professional
technical consultant or managerial services and assistance in the procurement of essential
personnel facilities equipment materials or supplies required for performance of the Contract
provided that the fee or commission is determined by the Department to be reasonable and not
excessive as compared with fees customarily allowed for similar services
(2) The fees charged for delivery of materials and supplies required to a job site (but not the cost of
the materials and supplies themselves) when the hauler trucker or delivery service is not also
the manufacturer of or a supplier of the materials and supplies provided that the fee is
determined by the Department to be reasonable and not excessive as compared with fees
customarily allowed for similar services
December 8 2005
6
DISADVANTAGED BUSINESS ENTERPRISE
DEFINITIONS AND REQUIREMENTS
(3) The fees or commissions charged for providing any bonds or insurance specifically required for
the performance of the Contract provided that the fee or commission is determined by the
Department to be reasonable and not excessive as compared with fees customarily allowed for
similar services
To determine the goals achieved under this Contract the participation as described in (d) of this special
provision shall be divided by the original prime Contract amount and multiplied by 100 to determine the
percentage of performance The Contractor shall maintain records of payment that show amounts paid to
all DBEs Upon completion of the project the Contractor shall submit a Form 17 listing all DBEs that
participated In this Contract the subcontract tier number of each and the dollar amount paid to each
This dollar amount shall Include payments made by nonDBE subcontractors to DBE subcontractors The
Contractor shall certify the amount paid which may be audited by the Department When there Is no
participation by DBEs the Contractor shall submit a Form 17 that indicates no participation and gives
reasons why there was no participation CDOT will not count the participation of a DBE subcontractor
toward the prime contractors UDBE achievements or CDOT s overall DBE goal until the amount being
counted toward the goal has been paid to the DBE
(a) Replacement of UDBE Subcontractors used to meet the contract goal
Based upon a showing of good cause the Contractor may request that a UDBE named on Form 714 or on a
Form 715 be replaced with another UDBE pursuant to the terms and conditions of this special provision In
the event that the Contractor is able to both document the need and to offer a replacement UDBE who can
perform the work at a reasonable cost the CDOT Region Civil Rights Professional will approve the
replacement at no additional cost to the Department Replacements will be allowed only with prior written
approval of the Region Civil Rights Professional
1 If a replacement is to be requested prior to the time that the named UDBE has begun to effectively
prosecute the work under a fully executed subcontract the Contractor shall furnish to the Region Civil
Rights Professional the following
A Written permission of the named UDBE Written permission may be waived only if such permission
cannot be obtained for reasons beyond the control of the Contractor
B A full written disclosure of the circumstances making it impossible for the Contractor to comply with
the condition of award
C Documentation of the Contractors assistance to the UDBE named on Form 714 or on Form 715
D Copies of any pertinent correspondence and documented verbal communications between the
Contractor and the named UDBE
E Documentation of the Good Faith Efforts in finding a replacement UDBE subcontractor and the
results of the efforts It is within the control of the Contractor to locate prior to award DBEs that offer
reasonable prices and that could reasonably be expected to perform the work For this reason
increased cost shall not by itself be considered sufficient reason for not providing an in kind
replacement
2 In the event a UDBE subcontractor begins to prosecute the work and is unable to satisfactorily complete
performance of the work the Contractor shall furnish to the Region Civil Rights Professional the following
A Documentation that the subject UDBE subcontractor did not perform in a satisfactory manner
B Documentation of the Contractor s assistance to the UDBE subcontractor prior to finding the UDBE
subcontractor in default
C A copy of the certified letter finding the UDBE to be in default or a letter from the UDBE stating that it
cannot complete the work and it is turning the work back to the Contractor
December 8 2005
7
DISADVANTAGED BUSINESS ENTERPRISE
DEFINITIONS AND REQUIREMENTS
D Copy of the contract between the Contractor and the UDBE subcontractor plus any modifications
thereto
E Documentation of the Good Faith Efforts in finding a replacement UDBE subcontractor and the
results of the efforts
In the event the Contractor is able to locate a replacement UDBE who can perform work at a reasonable
cost to the Contractor and also demonstrates to the satisfaction of the Department that prior to bid it had
reason to believe that the named UDBE firm was responsible and not expected to default the
Department may modify or renegotiate the Contract to compensate the Contractor for any reasonable
extra costs because of a higher price in the proposal of the replacement UDBE subcontractor than that of
the original UDBE subcontractor who failed to perform
Provided however that the Department will not be obligated to participate in any increased cost to the
Contractor if the UDBE that fads to perform has a recent history of performance failure or default that was
either known or should have been known to the Contractor prior to award
3 If the Contractor is unable to locate a UDBE replacement that is both interested in and capable of
performing the work at a reasonable cost the Department may waive the requirement that the work be
performed by a UDBE and the Contractor shall provide for the satisfactory completion of the work at no
additional cost to the Department
(f) Sanctions
It is the obligation of the Contractor to provide DBE firms with equal opportunity to participate in the
performance of the work
It is the responsibility of DBE firms to perform their work in a responsible manner fully consistent with the
intent of the DBE program and in substantial compliance with the terms and conditions of these DBE
definitions and requirements
DBE firms which fail to perform a commercially useful function as described in subsection (d) of these DBE
definitions and requirements or operate in a manner which is not consistent with the intent of the DBE
program may be subject to revocation of certification
A finding by the Department that the Contractor has faded to comply with the terms and conditions of these
DBE definitions and requirements shall constitute sufficient grounds for default and termination of the
Contract in accordance with subsection 108 09 of the specifications
Attachments
Form 714
Form 715
Form 718
BID SCHEDULE (Base Bid)
]esarigtion
Xhut
contract
Quantity
cot]G'kxact Goat
unit
Puce
Tot
_move Concrete
SF
5265
$
$
o-move and Salvage Existing Bricks
SF
2625
$ 243
$ 6378 7
classified Excavation
CY
75
$ 76 59
$ 57442
3,ggregate Base Course (Class 5)
TON
185
$ 3831
$ 7087 3
pply New Trolley Bricks - Material Only
SF
6500
$ 5 34
$ 34710 0
Cnstall Brack Trolley Roadbed
SF
7890
$ 422
$ 33295 &(
balizataon
LS
1
$ 10273 24
$ 10273 2'
Craffac Control
LS
1
$ 7700 OD
$ w C(
7 TAL COST
1C9769 94
Dc
C e f xdmd ILne Iv send Sen Anhrod Sixty bhne a-d 94/10D
Bad Total in Words
Cndavadual Doing Business an Company Name CLH Cb sUmtam, Inc
rporation avgpry L Homes, President
-_rtnershap
w-7 Section 00300 Page 1
COLORADO DEPARTMENT OF TRANSPORTATION Project#
UNDERUTILIZED DBE (UDBE) BID
Location
CONDITIONS ASSURANCE
Instructions Contractor Complete and submit this form with your bid Report only Underubl¢ed DBE (UDBE) participation percentages which qualify under
me convaa goal specmcaoon Tor mis project it is important to review k:uu i rorm 9175 instructions tSthum: compienng this form
POLICY
It Is the policy of the Colorado Department of Transportation that underutilized disadvantaged business enterprises have
equal opportunity to participate In the performance of contracts financed with federal state or local entity funds
UNDERUTILIZED DBE PARTICIPATION COMMITMENT
1) Will your company s Underutilized DBE (UDBE) participation meet contract goals? ❑ yes J no
2) Total intended Underutilized DBE (UDBE) percentage amount from Box A below %
3) List the UDBE firms commited work items and eligible UDBE percent of your bid that you are commiting to each
UDBE firm name
Certification
Committed
Subcontract
Eligible
expiration date
work item(s)
category
UDBE %•
See Form #715
❑ Trucker
1
/ /
❑ Subcontractor
%
U Supplier ❑ Broker
❑ Trucker
2
/ /
❑ Subcontractor
%
U Supplier ❑ Broker
❑ Trucker
3
/ /
L1 Subcontractor
%
❑ Supplier ❑ Broker
❑ Trucker
4
/ /
❑ Subcontractor
%
U Supplier U Broker
❑ Trucker
5
/ /
❑Subcontractor
%
U Supplier U Broker
Box A Total eligible UDBE percentage amount
(Round percentage amounts to the nearest hundredth)
Additional instructions on how to calculate the actual eligible amounts and percentages forthe trucker subcontractor supplier and broker
categories are available on the COOT Form #715 and in the Counting DBE Participation Toward Contract Goals and COOT s annual DBE
goal section ofthe DBE Definitions and Requirements In the Standard Special Provisions
I understand that if my company is determined to be the low bidder for the contract on this project I must submit a completed CDOT Form
#715 CERTIFICATION OF UNDERUTILIZED DBE PARTICIPATION for each firm listed on this form to the Transportation Department by
4 00 pm on the third workday after the day bids are opened The actual amounts submitted on each COOT Form #715 must equal or exceed
the percentage commitments documented on this form In addition if my company does not meet the DBE/UDBE goal for this project I must
submit a completed CDOT Form #718 DBE GOOD FAITH EFFORT DOCUMENTATION before 4 00 pm on the day after bids are opened
CDOT Form #715s submitted for firms not included on this form OR for amounts exceeding those listed on this form will be accepted but
NOT counted as Good Faith Efforts Only efforts the contractor made prior to the bid opening will count as Good Faith Efforts
I understand my obligation to abide by the policy stated above I shall not discriminate on the basis of race color age sex national origin or
handicap in the bidding process or the performance of contracts
I DECLARE UNDER PENALITY OF PERJURY IN THE SECOND DEGREE AND ANY OTHER APPLICABLE STATE OR FEDERAL
LAWS THAT THE STATEMENTS MADE IN THIS DOCUMENT ARE TRUE AND COMPLETE TO THE BEST OF MY KNOWLEDGE
ompany name I Date
Company officer signature
rrevwus editions are obsmete and may not be used CDOT Form #714 1106
COLORADO DEPARTMENT OF TRANSPORTATION
CERTIFICATE OF PROPOSED
Project No
UNDERUTILIZED DBE (UDBE)
Project Code (SA#)
Location
Form# of
PARTICIPATION
Prime Contractor - Send completed/signed form to the Business Programs Office (Instructions on second page) The Eligible UDBE
Amounts submitted on this form must equal or exceed the commitment(s) documented on the CDOT Form 714 you submitted with your
bid For the complete list of certified DBE/UDBE firms and their DBE work codes go to htt//www dot state co us/a uc /
NOTE See 49 CFR part 26 55 and the DBE Definitions and Requirements in the Standard Special Provisions for further information concerning
counting DBE participation of truckers subcontractors suppliers and service providers toward the projects UDBE goal
PART I — TRUCKING CONTRACT
If the UDBE is being used as a trucker for one or more trucking DBE work codes (25500 25505 etc ) then
ACTUAL UDBE AMOUNT = Actual contract amount for the transportation services provided by the UDBE firm and any UDBE lessees
ELIGIBLE UDBE TRUCKING AMOUNT= L (ACTUAL UDBE AMOUNT) — (Any non UDBE lessee amounts in this contract)" I
For work done on this UDBE contract with non UDBE lessees credit toward the project UDBE goal is given only for the broker fees or commissions
the UDBE trucker receives for arranging the transportations services because the services themselves are being performed by non UDBEs
NAME OF UDBE FIRM
CERTIFICATION #
EXPIRATION DATE ELIGIBLE UDBE TRUCKING AMOUNT
/ / $
DBE WORK CODE NUMBER(S) THIS UDBE IS BEING USED FOR
Complete list of work codes is at hdp lAvww dot state co uslapp ucp/
t
PART 1 b — SUBCONTRACT o '
e
ELIGIBLE UDBE SUBCONTRACTAMOUNT= [ (Actual UDBE contract amoung tB a r amounts in this contract)'
' Work that a UDBE subcontracts to a lower tier non UDBE firm does not court t U pal
NAME OF UDBE FIRM
CERTIFICATION #
1 TI (i1 VELIGIBLE UDBE SUBCONTRACT AMOUNT
is
DBE WORK CODE NUMBER(S) THIS UDBE IS BE tj '�`
Complete list of work codes is at hrp lhvww dot sl p
PART 1c —SUPPLY CON �A 1�, � , V
If the supplier is a UDBE with'a"t 60 ram} facturer for the item(s)
ELIGIBLE UDBEAIaPP#.*AMO 9..JJ(0AId UDBE contract amount) X 100%
if the supplier is a "PE vvrth,a "TyOe* fib of Regular Dealer' for the dem(s)
ELIGIBLE UDB PP�'YA T = I (Actual UDBE contract amount) X 60%
NOTE If the supplier a with a Type field of Broke for the item(s) use PART I — BROKER I SERVICE CONTRACT
NAME OF UDBE FIRM
CERTIFICATION #
EXPIRATION DATE ELIGIBLE UDBE SUPPLY AMOUNT
$
Ll
DBE WORK CODE NUMBER(S) THIS UDBE IS BEING USED FOR
Complete list of work codes is at http bwww dot state co us/app_ucp/
PART 1 d — BROKER / SERVICE CONTRACT
If purchasing materials or supplies through a UDBE with a Type field of Broker count only the amount of brokerage commission
and/or delivery service fees included in the contract Other examples of services to include in this section are bonding brokering
consulting security guards and insurance etc
ELIGIBLE UDBE SERVICE FEE AMOUNT= Actual compensation retained by the UDBE brokerlagent for services rendered*
' The amounts that count toward UDBE goals are limited to the compensation retained by the UDBE broker/agent for services rendered provided the
fee/commission is determined by CDOT to be reasonable and not excessive as compared with fees customarily charged for similar services
NAME OF UDBE FIRM
CERTIFICATION #
EXPIRATION DATE I ELIGIBLE UDBE SERVICE FEE AMOUNT
/ / Is
DBE WORK CODE NUMBER(S) THIS UDBE IS BEING USED FOR
Complete list of work codes is at hftp //army dot state co uslapp_ucp/
Original — Business Programs Office Previous editions may not be used CDOT Form 715 — Page 1 of 2 1/06
PART 2 - UDBE PARTICIPATION SUMMARY
A) What is the total dollar value of this proposed trucking subcontract supply OR broker/service
contract that is eligible for counting toward contract goals?
A = [ TOTAL FROM 'ELIGIBLE COLUMNS IN PART 1 ]
A>
$
NOTE Provide in actual subcontractor dollars and not prime contract prices
B) What is the total dollar value of proposed subcontracts that are eligible for counting towards
B>
$
contract goals from prior sheets/forms?
C) What is the accumulative value of proposed subcontracts that are eligible for counting towards
contract goals?
C>
$
C=[A + B]
D) What is the original contract bid total?
D>
$
E) What is the accumulative percent of contract bid total subcontracted to all underutilized DBEs?
E=[(C - D) X 100]
E>
PART 3 - UDBE CONFIRMATION ' }
I confirm that my company is participating In this contract as documented in the Pri c nt(s) in PART 1
of this form Only the value of the work that my company is actually performing c t ortn
UDBE Firm Name
7
UDBE Representative Signature and Title r' ,, �\ '" N +
PART 4 - PRIME
• my company has met the clFropoc'sed
Kgoalsypr'has submitted a completed CDOT Forth #718
• my company has acmpe UDBE named above
• my company s n6SE of the contracted UDBE commitment
• my compa ) red UDBE has signed PART 3 of this form
• my comparly(s Use b)" o3`6d UDBE for the items of work listed above is a condition of the contract award
• my comp y�wdl it proposed UDBE to attend the preconstruction conference
• my compa use a substitute UDBE for the proposed UDBE s failure to perform under a fully executed subcontract
unless my c y complies with the definitions and requirements section of the DBE Special Provisions
• I understand that failure to comply with the information shown on this form will be considered grounds for contract termination
I declare under penalty of perjury in the second degree and any other applicable state or federal laws that the statements
made on this document are true and complete to the best of my knowledge
Prime Contractor Name
Officer Signature and Title
Date
Prime Contractor
1 An officer of the contractor(s) must complete this form
7 Retain a photocopy for your records
2 Include only DBE fines which meet the underutilized criteria in
g Send original to
Colorado Department of Transportation
the contract goal specification for this project (i a UDBE firms)
Business Programs Office
3 Complete only relevant section(s) for PART 1
4201 E Arkansas Ave
Ave
4 Ensure that the proposed UDBE has signed PART 3 of this form
Denver Colorado 80 222
5 Complete ALL sections of PART 2 and PART 4
FAX (757
6 Submit a separate CDOT Form #715 for EACH proposed UDBE
- Business
may not
COLORADO DEPARTMENT OF TRANSPORTATION
Project No
Project Code (SA#)
UNDERUTILIZED DBE (UDBE) GOOD FAITH
Location
EFFORT DOCUMENTATION
Date
No Of Sheets Attached To Forth
The Contractor who is the apparent low bidder on a CDOT construction project and has failed to meet the Undemblized DBE (UDBE) contract goal shall use this form to document all good faith efforts that
were made prior to bid opening by said Contractor to meet the goal FAILURE TO. FULLY I CLEARLY COMPLETE THIS FORM MAY RESULT IN REJECTION OF THE BID
Each portion of this form is to be addressed in the space provided or on supplemental sheets that follow the same tabular structure and format outlined below Attach supporting documentation as required
by CDOT This completed form and required attachments are to be submitted to the Business Programs Office in the Center for Equal Opportunity prior to 4 00 p m on the day after the day bids are
opened This form may be submitted by FAX (303 757 9019) with an original copy to follow An extension may be granted by the DBE Liaison Only the efforts the Contractor made prior to bid opening
will count as Good Faith Efforts consistent with the instructions on CDOT Form #714
Complete the following table to document sufficient bid items identified as subcontract work to be performed by UDBEs to achieve the contract goal This includes where appropriate breaking out
contract work items into economically feasibly units to facilitate DBE participation even when the Contractor might otherwise prefer to perform these work items with its own forces The total percentage of
11
subcontract items identified for UDBE participation must equal or exceed the percentage UDBE goal set by COOT
DBE DIRECTORY WORK CODES
� s
The DBE Directory can be found online at
http //www dot state co uslapp_ucp/
DBE work codes are 5 digit numbers where the 1st digit
corresponds to the overall section the code belongs to
The tat 3 digits of a DBE work code identify its category
DBE work codes ending in 00 represent certification for the
entire work code category
DBE work codes NOT ending in 00 represent certification in a
specific sub category only
UDBE CONTRACT GOAL °/ TOTAL CONTRACT °/
II Complete the following table to summarize all outreach efforts made to UDBE firths For each subcontract item identified contact by mail fax phone and/or email 100%of the Colorado certified
UDBEs whose DBE work codes match the type of work being solicited and who are marked as CDOT GFE Eligible on the DBE Directory The Contractor shall ensure that initial solicitations allow
UDBEs at least 10 calendar days to participate effectively in the bidding process In order to determine with certainty which UDBEs are interested the Contractor is also required to take appropriate steps
to follow up initial solicitations (e g regional follow up phone calls etc ) If soliciting by telephone attach a summary telephone log of calls including topic of discussion date time name of person
contacted and the response received If soliciting by mail fax and/or email attach one example copy of the letter fax and/or email sent to UDBEs along with a summary log that documents all dates and
responses received Letters faxes and/or emads must specifically identify the project the items to be subcontracted and the bid date Letters faxes and/or emails must also provide an address and
phone number where specific quantities or details will be available to bidders
DBE • 'UPDATES
Go to http Ilwww dotstate co us/app_ucp/ and use the
Directory Updates" button on the DBE Directory to submit any of
the following documented updates on UDBE firms
Contact information changes (e g phone and address etc )
CDOT GFE Eligibility" status changes (e g UDBE firth says they
don t want to be contacted via GFE solicitations etc)
Note In order to verify all updates submdtted CDOT may request
additional information from contractors and/or UDBE firms before
FEE posting requested changes to the Directory
Original Business Programs Office THIS FORM IS CONFIDENTIAL Previous editions may not be used CDOT Form 71S Page 1 of 2 1/06
III Complete the following table to show all subcontract bids received (non UDBE and UDBE) bid dollar amounts for each bid item and the name of the successful bidder Where bundled subcontract
bids were received break out quotes per bid item number If the UDBE bids were rejected give reasons for each case If the work is to be counted as a potential UDBE subcontract item the Contractor
cannot elect to perform that work itself when a UDBE bid is competitive or only UDBE bids are received Cost alone may not be adequate lusification for failure to use a UDBE bid When anon UDBE bid
is significantly lower than a UDBE bid the Contractor may choose to perform the item itself CDOT will determine whether a subcontractors bid is competitive based on factors such as the percentage
and dollar difference between quote(s) and/or the percentage the quote(s) represents of the overall contract
LJ
Li
Li
El
Li
IV The efforts required herein are not exhaustive or exclusive Other factors or types of efforts maybe relevant in appropnate cases In determining whether Good Faith Efforts have been made the
quantity and quality of the efforts made as well as kinds of efforts made maybe considered List any additional efforts to increase UDBE contract participation such as assisting UDBEs in obtaining
bondinglinsurance/lines of credit effectively using the services of community organizations/publications and/or requesting subcontractors to assist with providing UDBE participation Report the results of
such efforts Note Advertising in a publication with low UDBE subscription rates wig not be considered as quality efforts by CDOT
THE CONTRACTOR UNDERSTANDS THAT DEMONSTRATION OF GOOD FAITH EFFORTS IN ACHIEVING THE UDBE GOALS ESTABLISHED BY COOT IS REQUIRED THROUGHOUT THE
PERFORMANCE OF THE CONTRACT
Company Name
1Phone
Fax
Title
Printed Name
ISIgnature
Original Business Programs Office THIS FORM IS CONFIDENTIAL Previous editions may not be used COOT Forth 71S Page 2 of 2 1/06
I
U S DEPT OF LABOR DAVIS BACON MINIMUM WAGES COLORADO DATE 10 05 07
GENERAL DECISION NUMBERS CO20070014 AND CO20070015 HIGHWAY CONSTRUCTION
Decision Nos CO20070014 and CO20070015 dated February 09
Modifications
to
2007 supersedes Decision Nos C0030014 and C0030015 dated
MOD 1 04 06 07 Pages 15
1
June 13 2003
MOD 2 0601 07 Pages 1 2 5 & 6
MOD 3 08 03 07 Pages 1 5
2
3
When work within a project is located in two or more counties and
the minimum wages and fringe benefits are different for one or more
MOD 4 09 07 07 Pages 1 5
MOD 5 1005 07 Pages 12 4
4
5
job classifications the higher min man wages and fringe benefits
shall apply throughout the project
General Decision No CO20070014 applies to the following counties Adams Arapahoe Boulder Denver Douglas El
Paso Jefferson Latimer Mesa, Pueblo and Weld counties
General Decision No CO20070014
The wage and frtn a benefits listed below reflect ollectively bargained rates
Code
Classification
Basic Hourly
Fringe Benefits
Last
Rate
Mod
ELECTRICIANS
1200
Electrical work $150 000 or less (Pueblo county)
2214
8 85 + 3%
1201
Electrical work over $150 000 (Pueblo county)
2629
8 85 + 3%
1
1202
Electricians (Adams Arapahoe Boulder Denver Douglas
Jefferson Lanmer and Weld counties)
2g 91
10 33
1203
Electricians (El Paso county)
2680
12 00 + 3%
3
1204
Electricians (Mesa county)
2031
856
2
1205
Traffic Signal Installer (Zone 1)
2383
4 75 + 13 75%
4
1206
Traffic Signal Installer (Zone 2)
2683
4 75 + 13 75%
4
Traffic Installer Zone Definitions
Zone 1 — Within a 35 mile radius measured from the addresses
of the following cities
Colorado Springs Nevada & Bijou
Denver Ellsworth Avenue & Broadway
Ft Collins Prospect & College
Grand Junction 12th & North Avenue
Pueblo 125 & Highway 50
Zone 2 All work outside these areas
POWER EQUIPMENT OPERATORS
1300
Asphalt Screed
2167
822
2
1301
Bituminous or Asphalt Spreader/Laydown Machine
21 67
822
2
1302
Bulldozer
2167
822
2
2
U S DEPT OF LABOR DAVIS BACON MINIMUM WAGES COLORADO DATE 10 05 07
GENERAL DECISION NUMBERS CO20070014 AND CO20070015 HIGHWAY CONSTRUCTION
General Decision No CO20070014
The wage and fringe benefits listed below reflect collectively bargained rates
Code
Classification
Basic Hourly
Fringe Benefits
Last
Rate
Mod
POWER EQUIPMENT OPERATORS (cont)
Crane
1305
50 tons and under
2182
822
2
1306
51 to 90 tons
21 97
822
2
1307
91 to 140 tons
22 12
822
2
1308
141 tons and over
2288
822
2
Drill Operator
1309
William MF/Watson 2500 only
2197
822
2
Grader/Blade
1310
Rough
21 67
822
2
1311
Finish
2197
822
2
Loader
1312
Barber Green etc 6 cubic yards and under
2167
822
2
1313
Over 6 cubic yards
21 82
822
2
Mechanic and/or Welder (Includes heavy duty and combination
mechanic and welder)
1314
Mechanic and/or Welder
21 82
822
2
1315
Mechanic/Welder (Heavy duty)
2197
822
2
1316
Oiler
2097
822
2
Power Broom
1317
Under 70 HP
2097
822
2
1318
70 HP and over
21 67
822
2
Roller (excluding dirt and soil compaction)
1319
Self propelled rubber tires under 5 tons
21 32
822
2
1320
Self propelled all types over 5 tons
21 67
822
2
Scraper
1321
Single bowl under 40 cubic yards
21 82
822
2
1322
Single bowl including pups 40 cubic yards and tandem bowls
and over
2197
822
2
1323
Trackhoe
21 82
822
2
U S DEPT OF LABOR DAVIS BACON MINIMUM WAGES COLORADO DATE 10 05 07
GENERAL DECISION NUMBERS CO20070014 AND CO20070015 HIGHWAY CONSTRUCTION
General Decision No CO20070014
The wage and fringe benefits listed below reflect collectively bargained rates
Code
Classification
Basic Hourly
Fringe Benefits
Last
Rate
Mod
Laborers
Asphalt Laborer/Raker Common Laborer
1400
and Concrete Laborer/Mason Tender
1629
425
General Decision No CO20070014
The wage and fringe benefits listed below do not reflect collectively bargained rates
1500
Bricklayers
1555
2 85
Carpenters
1600
Form Work (Excluding curbs and gutters)
1654
390
1601
All other work
1661
3 88
1700
Concrete Finishers/Cement Masons
1605
300
Ironworkers
1900
Reinforcing
1669
545
1901
Bridge Rail (Excludes guardrail)
1822
601
Laborers
2001
Fence Erector (Includes fencing on bridges)
1302
320
2002
Form Work (Curbs and gutters only)
1185
345
2003
Guardrail Erector (Excludes bridgerail)
1289
320
2004
Landscape and Irrigation Laborer
1226
3 16
2005
Pipelayer
13 55
241
2006
Striping Laborer (Pre form layout and removal of pavement
markings)
12 62
3 21
2007
Traffic Director/Flagger
955
305
2008
Traffic and Sign Laborer (Sets up barricades and cones
and installs permanent signs)
12 43
3 22
PAINTERS
2100
Brush
1694
2 10
2101
Spray
1699
287
POWER EQUIPMENT OPERATORS
2200
Backhoes
1654
424
2201
Bobcat/Skid Loader
1537
4 28
2202
Concrete Pump Operator
1652
430
a
U S DEPT OF LABOR DAVIS BACON MINIMUM WAGES COLORADO DATE 10 05 07
GENERAL DECISION NUMBERS CO20070014 AND CO20070015 141aT4WAV C0WRTRn(`TTnM
General Decision No CO20070014
The wage and fringe benefits listed below do not reflect collectively bargained rates
Code
Classification
Basic Hourly
Fringe Benefits
Last
Rate
Mod
POWER EQUIPMENT OPERATORS (cont)
Drill Operator
2203
All except William MF/Watson 2500
1674
266
2204
Forklift
1591
409
2205
Rotomill Operator
1622
441
2206
Post Dnver/Punch Machine
1607
441
2207
Tractor
13 13
295
2208
Compactor (Dirt and sod only)
1670
3 30
Groundman (Traffic signalization)
2301
Class C
1144
325
Truck Drivers
2400
Floats Semi Truck
1486
308
2401
Multipurpose Truck — Specialty & Hoisting
1435
349
2402
Truck Mechanic
1691
301
2403
Pickup Truck (Includes Pilot and Sign/Barricade Truck)
1393
368
2405
Single Axle Truck
1424
377
2406
Distributor Truck
1580
527
2407
Dump Truck
2408
14 cubic yards and under
1493
527
2409
15 to 29 cubic yards
15 27
527
2410
30 to 79 cubic yards
1580
527
2411
80 cubic yards and over
1645
527
2412
Low Boy Truck
1725
527
2413
Water Truck
14 93
527
5
WELDERS Receive rate prescribed for craft performing operation to which welding is incidental
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award
only as provided in the labor standards contract clauses [29 CFR 5 5(a)(1)(n)]
END OF GENERAL DECISION NUMBER CO20070014
5
U S DEPT OF LABOR DAVIS BACON MINIMUM WAGES COLORADO DATE 10 05 07
GENERAL DECISION NUMBERS CO20070014 AND CO20070015 HIGHWAY CONSTRUCTION
General Decision No CO070015 applies to the following counties Alamosa Archuleta Baca Bent, Chaffee Cheyenne
Clear Creek, Conejos Costilla, Crowley Custer Delta Dolores Eagle Elbert Fremont Garfield Gilpin Grand
Gunnison Hinsdale Huerfano Jackson Kiowa Kit Carson La Plata Lake Las Aromas Lincoln Logan Mineral Moffat
Montezuma Montrose Morgan Otero Ouray Park Phillips Pitkin Prowers Rio Blanco Rio Grande Roun Saguache
San Juan San Miguel, Sedgwick Summit Teller Washington and Yuma counties
When work within a project is located in two or more counties and the rmmmum wages and fringe benefits are different
for one or more job classifications the higher mmimum wages and fringe benefits shall apply throughout the project
General Decision No CO20070015
The wage and fringe benefits listed below reflect collectively bargained rates
Code
Classification
Basic Hourly
Fringe Benefits
Last
Rate
Mod
ELECTRICIANS (Including traffic signal installation)
Electrical work $150 000 or less (Alamosa Archuleta Baca
3200
Bent Chaffee Conejos Costilla Crowley Custer Fremont
22 14
8 85 + 3%
Huerfano Kiowa Las Ammas Mineral Otero Prowers Rio
Grande and Saguache counties)
Electrical work over $150 000 (Alamosa Archuleta Baca
3201
Bent Chaffee Conejos Costilla Crowley Custer Fremont
Huerfano Kiowa Las Ammas Mineral Otero Prowers Rio
26 29
8 85 + 3%
1
Grande and Saguache counties)
Electricians (Clear Creek Eagle Gilpin Grand Jackson Lake
3202
Logan Morgan Phillips Sedgwick Summit Washington
2891
1033
and Yuma counties)
3203
Electricians (Cheyenne Elbert Kit Carson Lincoln Park
and Teller counties)
26 80
12 00+ 3%
3
Electricians (Dolores Garfield Gunnison Hinsdale La Plata
3204
Moffat Montezuma Ouray Pitkin Rio Blanco Routt San Juan
2806
876
2
and San Miguel counties)
3205
Electricians (Delta and Montrose counties)
2031
856
2
3206
Traffic Signal Installer (Zone 1)
23 83
4 75 + 13 75%
4
3207
Traffic Signal Installer (Zone 2)
2683
4 75 + 13 75%
4
Traffic Installer Zone Definitions
Zone 1 — Within a 35 mile radius measured from the addresses
of the following cities
Colorado Springs Nevada & Bijou
Denver Ellsworth Avenue & Broadway
Ft Collins Prospect & College
Grand Junction 12th & North Avenue
Pueblo 1 25 & Highway 50
Zone 2 All work outside these areas
a
ACCEPTANCE OF FUEL COST ADJUSTMENTS
Bidders have the option to accept Fuel Cost Adjustments in accordance with the
Revision of Section 109 - Fuel Cost Adjustment To accept this standard
special provision, the bidder must fill in an "X" next to "YES" below No
Fuel Cost Adjustment will be made due to fuel cost changes for bidders who
answer "NO" If neither line is marked, the Department will assume the bidder
rejects Fuel Cost Adjustments for this project After bids are submitted,
bidders will not be given any other opportunity to accept or reject this
adjustment
(Mark only one line with an "X")
X YES, I choose to accept Fuel Cost Adjustments for this project
NO, I choose NOT to accept Fuel Cost Adjustments for this project (if
neither line is marked, the default is "NO", I choose NOT to accept Fuel Cost
Adjustments for this project
9 PRICES
The foregoing prices shall include all labor, materials, transportation,
shoring, removal, dewatering, overhead, profit, insurance, etc , to cover
the complete Work in place of the several kinds called for
Bidder acknowledges that the OWNER has the right to delete items in the
Bid or change quantities at his sole discretion without affecting the
Agreement or prices of any item so long as the deletion or change does
not exceed twenty-five percent (25%) of the total Agreement Price
RESPECTFULLY SUBMITTED
• •'
r ��/a
0
Z
ignatu te
411
Lvsuknt
r�C�'0
Title
ON
"ollnNo`yl
License Number (If Applicable)
(Seal - if Bid is by c rporation)
Attest
Rev 10/20l07
Section 00410 Page 1
6
U S DEPT OF LABOR DAVIS BACON MINIMUM WAGES COLORADO DATE 10 05 07
GENERAL DECISION NUMBERS CO20070014 AND CO20070015 HIGHWAY CONSTRUCTION
General Decision No CO20070015
The wage and fringe benefits listed below reflect collectively bargained rates
Code
Classification
Basic Hourly
Fringe Benefits
Last
Rate
Mod
POWER EQUIPMENT OPERATORS
3300
Bituminous or Asphalt Spreader/Laydown Machine
2167
822
2
3301
Bulldozer
21 67
822
2
Crane
3302
50 tons and under
2182
822
2
3303
51 to 90 tons
2197
822
2
3304
91 to 140 tons
2212
822
2
3305
141 tons and over
2288
822
2
3306
Grade Checker
2182
822
2
Loader
3307
Barber Green etc 6 cubic yards and under
21 67
822
2
3308
Over 6 cubic yards
21 82
822
2
Roller (excluding dirt and soil compaction)
3309
Self propelled rubber tires under 5 tons
21 32
822
2
3310
Self propelled all types over 5 tons
21 67
822
2
3311
Trackhoe
21 82
822
2
3312
Oiler
2097
822
2
3313
Water Wagon
2182
822
2
General Decision No CO20070015
The wage and fringe benefits listed below do not reflect collectively bargained rates
Carpenters
3600
Form Building and Setting (Excluding curbs and gutters)
1592
538
3601
All other work
1630
3 71
3700
Concrete Finishers/Cement Masons
1555
2 85
3800
Groundman (Traffic signahzation)
1157
350
Ironworkers
3900
Reinforcing
1694
677
3901
Bridge Rail (Excluding guardrail)
1676
6 01
7
U S DEPT OF LABOR DAVIS BACON MINIMUM WAGES COLORADO DATE 10 05 07
GENERAL DECISION NUMBERS CO20070014 AND CO20070015 J41GT4w Av C0 NCTRT1rTrnN
General Decision No CO20070015
The wage and fringe benefits listed below do not reflect collectively bargained rates
Code
Classification
Basic Hourly
Fringe Benefits
Last
Rate
Mod
Laborers
4000
Asphalt Laborer/Raker
1240
292
4001
Common
1244
3 53
4002
Concrete Laborer/Mason Tender
1244
3 10
4003
Striping Paint Laborer (Pre form layout and removal of
pavement markings)
12 90
3 07
4004
Traffic Director/Flagger
942
3 21
4005
Traffic/Sign Laborer (Sets up barricades and cones
and installs permanent signs)
12 39
3 20
4007
Guardrail (Excludes bridgerail)
1278
3 31
4008
Formwork (Curbs and gutters only)
1292
454
4009
Landscape Laborer (Including irrigation work)
1221
3 16
Painters
4100
Spray
1754
352
POWER EQUIPMENT OPERATORS
4200
Asphalt Plant
1723
120
4201
Asphalt Screed
1621
376
4202
Backhoe
1642
442
4203
Compactor (Dirt and sod only)
1652
3 13
4204
Grader/Blade
1639
420
4205
Mechanic and or Welder (Includes heavy duty and combination
mechanic welder)
16 74
4 20
4206
Post Dnver/Punch Machine
1607
4 41
4207
Rotomill Operator
1628
441
4209
Scraper
1762
3 16
8
U S DEPT OF LABOR DAVIS BACON MINIMUM WAGES COLORADO DATE 10 05 07
GENERAL DECISION NUMBERS CO20070014 AND CO20070015 HIGHWAY CONSTRI ICTION
General Decision No CO20070015
The wage and fringe benefits listed below do not reflect collectively bargained rates
Code
Classification
Basic Hourly
Fringe Benefits
Last
Rate
Mod
Truck Dnvers
4400
Dump
1415
3 83
4401
Low Boy
1507
456
4402
Truck Mechanic
1597
461
4403
Multipurpose Truck Specialty and Hoisting
1460
349
4404
Pickup (Including pilot car)
1404
349
4405
Water Truck
1488
207
4406
Distributor
1580
527
WELDERS Receive rate prescribed for craft performing operation to which welding is incidental
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award
only as provided in the labor standards contract clauses [29 CFR 5 5(a)(1)(u)]
END OF GENERAL DECISION NUMBER CO20070015
Oversight / NHS
FHWA FULL OVERSIGHT? ■ NO 0 YES
NATIONAL HIGHWAY SYSTEMS ■ NO 0 YES
Other Project Information
Project Number STE M455-072
Project Code 15821
i5tructlon rrofeCT Narr
TROLLEY BRICK RESTORATION PROJECT
DEPARTMENT OF
STATE OF
As Constructed
No RQNBmns.
Reread
TRANSPORTATION
COLORADO
HIGHWAY CONSTRUCTION BID PLANS OF PROPOSED
FEDERAL AID PROJECT NO STE M455-072
TROLLEY BRICK RESTORATION PROJECT
EAST MOUNTAIN AVENUE — CITY OF FORT COLLINS — LARIMER COUNTY
CONSTRUCTION PROJECT CODE NO 15821
SHEET IDENTIFICATION SHEET NO
INDEX OF SHEETS
PROJECT LOCATION MAP 2
PROJECT DESCRIPTION 3
TYPICAL SECTIONS 4
SUMMARY OF APPROXIMATE QUANTITIES 5
TRAFFIC CONTROL PLAN 8-7
STORMWATER MANAGEMENT PLAN 8
Index of Sheets
Contractor
Protect En meer ERIKA KEETON
PROJECT 5gRTED ACCEPTED
Poth
DOCS
Imbols ERK
Imbols ERK
ENGUSH
Project No /I
STE M455-072
15821
Sheet 1
As Constructed
No Redekna
Revised
Vold
US
HIGHWAY 287
Q
—
o
Z END PROJECT STE M455-072 N
Z
W Vine Dr
a
0
E Vine Dr o
Laporte Ave
12
W Mulberry St
"�sy E Mulberry St
BEG N OJEC STE M4 -072
W Prospect Rd
E Prospect Rd
_
�
a
"'
N
W Drake Rd
V'
F.
N
Q
d
d
W Horsetooth
Rd U
E
Horsetooth Rd
W
LO
Harmony Rd
E Harmony Rd
PROJECT LOCATION MAP
Computer File Information
Project No /Code
Creation Date 06/05/07 Inhale ERK
Desgner ERK
l)
Regan 4
Last Modification Dote 10/26 07 Inhale ERK
STE M455-072
Detader ERK
Unh Leader Wr
Full Path I TROLLEY PROJEC BID DOGS
15821
Drawing File Nome: PROJECT LOCATION DWG
Aced Ver 2007 Scale NA Unite ENGLISH
Sheet 2
No Text
As Constructed
No Revisiom
Reereed
Void
TYPICAL SECTION
EXISTING RAILS AND
TIES TO REMAIN RESET NEW AND
& BE PROTECTED SALVAGED BRICK ON
1 SAND BED do
COMPACTED BASE
N + '
_ 4
EXISTING CONCRETE
PAVEMENT TO BE
PROTECTED
TYPICAL SECTION CreCom uter File Information Protect No /Code
ation Date 09/07/07 Initgls ERK
Desfgmr ERK O Region 4 Last Nodd'aation Date Inhale ERK STE M455-072
Detailer ERK Und Leader WF Full Path I \TROLLEY PROJE BID DOCS 15821
Qmwino Fie Nave TYPICAL SECTION DWG
Aced Ver 2007 Scale NA Units ENGUSH Sheet 4
As Constructed
No ReWeom
Rsvwd
Void
SUMMARY OF APPROXIMATE QUANTITIES
Contract
Item No
Contract Item
Unit
Contract
By Others
Proct Totals
Plan
As
Constructed
Plan
As
Cownwted
Plan
As
Comtracted
20201
Remove Corcretc
SF
5265
0
20202
Remove and Selvage Ex tug Bncks
SF
2625
0
20301
Umlassided Excavation
Cy
75
0
30401
Aggregate Base Course (Class 5)
TON
185
0
61001
Supply New Trolley Bncks Matenalonly
SF
6500
0
61002
Inetall Buck Troley Roadbed
SF
7890
0
62601
Mobdtzatnn
LS
I
0
630 01
Tm�c Control
LS
I
0
Force Account Items
700
F/A Mnor Contract Revnnns
FA
1
0
700
F/A On the Job Tranee
Hour
0
0
700
F/A OJT Colorado Trar ng Program
FA
1
0
SUMMARY OF APPROXIMATE QUANTITIES
Computer File Information
&;o *n Date 09/07/07 Imtmis ERK
Project No /Code
Designer ERK
oI,
Region 4
Lot Modification Dote 11 07 07 IndaM ERK
STE M455-072
Detader ERK
IM& Leader Nrr
Full Path I \TROLLEY PROJEC BID DOCS
15821
Drowsto file Name suawrty
of APPRoxiMAte GUArmns.DNG
Arad Var 2007 Scale NA Unds. ENGUSH
Sheet 5
tf�
I'
TRAFFIC CONTROL PLAN Computer File Information Project No /Ca
f:raatan Dote 09/07/07 inlab ERK
Designer ERK O Regan 4 Lost ModWoation Date Initials ERK STE M455-072
Detaler ERK Unit leader WT Full Path I \TROLLEY PROJEC BID DOGS 15821
Drava File Name TRAFFIC CONTROL PLAN DWG
Aood Ver 2007 Scale NA Units ENGLISH Sheet 6
As Constructed
No ReWsions
Revwd
Void
FOR INFORMATION ONLY
SCHEDULE OF CONSTRUCTION TRAFFIC CONTROL DEVICES
TRAFFIC CONTROL DEVICES Computer File Information Project No /Code
Croahon Dote 10/29/07 Inhale ERK
Designer ERK 07, Region 4 Lad Modd'ewhon Dote 11 07 07 Indiaie ERK STE M455-072
Detmkr ERK Und leader Wr Full Path. 1 \TROLLEY PROJECT\BID DOCS 15621
Draw File Nome r10 TFAFM co111rsOL alMN1111ES DWa
Aced Ver 2007 Scale NA Unit& ENGIJSH Sheet 7
SIGNS
CODE LEGEND SIGN PANEL SIZE UNIT PANEL SIZE A
W20-1 Road Work Ahead 36 x 36 Per Day Per 200
Each
W9-3 Left Lane Closed Ahead 36' x 36' Per Day Per 20
Each
R9-9 Sidewalk Closed 24' x 12 Per Day Per 200
Each
W20-7A Flagger Symbol 36 x 36 Per Day Per 200
Each
R3-2 No Left Turn 24 x 24 Per Day Per 120
Each
W4 1 5 Left or Right Transition 36' x 36 Per Day Per 80
ach
R8 3 No Parking Sign w/ Stand 24 x 24 Per Day Per 200
E
Each
SIGN TOTALS 1020
OTHER DEVICES
REM UNITS QUANTITY
Vertical Panel w/o Light Per Day Per Each 1000
Channellzing Drum w/o Light Per Day Per Each 500
Cone with Reflective Strip Per Day Per Each 1000
Light Per Day Per Each 400
Advance Warning Flashing or Sequencing Per Day Per Each 40
Arrow Panel
Traffic Control Supennsor Day 20
Flagging Hr 400
SIGNS
CODE LEGEND SIGN PANEL SIZE UNIT PANEL SIZE A
W20-1 Road Work Ahead 36 x 36 Per Day Per 200
Each
W9-3 Left Lane Closed Ahead 36' x 36' Per Day Per 20
Each
R9-9 Sidewalk Closed 24' x 12 Per Day Per 200
Each
W20-7A Flagger Symbol 36 x 36 Per Day Per 200
Each
R3-2 No Left Turn 24 x 24 Per Day Per 120
Each
W4 1 5 Left or Right Transition 36' x 36 Per Day Per 80
ach
R8 3 No Parking Sign w/ Stand 24 x 24 Per Day Per 200
E
Each
SIGN TOTALS 1020
OTHER DEVICES
REM UNITS QUANTITY
Vertical Panel w/o Light Per Day Per Each 1000
Channellzing Drum w/o Light Per Day Per Each 500
Cone with Reflective Strip Per Day Per Each 1000
Light Per Day Per Each 400
Advance Warning Flashing or Sequencing Per Day Per Each 40
Arrow Panel
Traffic Control Supennsor Day 20
Flagging Hr 400
OTHER DEVICES
REM UNITS QUANTITY
Vertical Panel w/o Light Per Day Per Each 1000
Channellzing Drum w/o Light Per Day Per Each 500
Cone with Reflective Strip Per Day Per Each 1000
Light Per Day Per Each 400
Advance Warning Flashing or Sequencing Per Day Per Each 40
Arrow Panel
Traffic Control Supennsor Day 20
Flagging Hr 400
SECTION 00420
STATEMENT OF BIDDER'S QUALIFICATIONS
All questions must be answered and the data given must be clear and
comprehensive This statement must be notarized If necessary, questions may
be answered on separate attached sheets The Bidder may submit any additional
information he desires
1 Name of Bidder (LH Consbictun. Inc
2 Permanent main office address
3 When organized
:1 .� .- i - •�. 11 :1I 1
4 If a corporation, where incorporated Colorado
5
N
7
e
0
10
How many years have you been engaged in the contracting business
under your present firm or trade names 11 vas
Contracts on hand (Schedule these, showing the amount of each
contract and the appropriate anticipated dates of completion )
General character of Work performed by your company
Tnfractn�tt.¢2/Lhdagu[rl Utilities
Have you ever failed to complete any Work awarded to you> No
If so, where and why)
Have your ever defaulted on a contracts Nb
If so, where and why9
Are you debarred by any government agency? ND
If yes list agency name
Rev 10/20/07 Section 00420 Page 1
As Constructed
No Redsbm
DURING CONSTRUCTION Rmsed
MATERIALS HANDLING Void
1 ) Material stockpile locations for projects in sensitive areas Any material stockpiles shall be located
away from sensitive areas and confined so that no material or their run—off will enter state waters
Locations shall be approved by the Engineer in consultation with the Region Environmental Unit
2 ) There shall be no stockpiling or side casting of waste materials including but not limited to paint
chips, asphalt and concrete adjacent to any state waters that could potentially result from project
activities
3) Containment and cleanup of equipment fuel oil and lubricant leaks
Contractor shall inspect and certify equipment and vehicles daily to ensure petroleum, oils and lubricants
(POL) are not leaking onto the soil or pavement Absorbent material or containers approved by the
Engineer shall be used to prevent leaking POL from reaching the soil or pavement Contractor shall have
ready approved absorbent material or containers of sufficient capacity to contain any leak POL that can
reasonably be foreseen All materials resulting from POL leakage control and cleanup shall be property of
the Contractor and removed from the site The cost for control and cleanup of POL leaks shall not be
paid for separately but shall be included in the cost of the work
STREET CLEANING
1 ) Whenever sediment is transported onto the roadway the road shall be cleaned as needed Street
washing will not be allowed Storm drain inlet protection shall be in place prior to shoveling or sweeping
Street cleaning will not be paid for separately
GENERAL SITE CONDITIONS
1 ) At the end of each day the Contractor shall be responsible for collecting all trash and disposing of it
in appropriate containers Containers shall be emptied as needed
CONCRETE WASHOUT
1 ) It is estimated that 0 concrete washout structures shall be required on this protect
2) Contractor is required to use an urban concrete washout for this project Urban concrete washout
examples are rigid plastic baby pools wooden boxes lined with heavy duty plastic or waterproof 55 gallon
drums Baby pools may be used a maximum of 3 times if not damaged during previous use After use
the Contractor shall remove the structure from the project at his own cost and dispose of properly off
site Cost of baby pools and maintenance of the baby pools will not be paid for separately, but shall be
included in the cost of the work
STORMWATER MANAGEMENT PLAN Computer File Information Project No /Code
Crwtwn Dot, 09/07/07 Indials ERK
Designer ERK b. Re"n 4 Lag Modiricotwn Dote 10/29/07 IndbM ERK STE M455-072
Full Polh I \TROLLEY PROEJ BID DOCS
DetaAer ERK Umt Lwder Wr 15821
Dram Fik Name STORMWATER MANAGEMENT DWG
Acad Ver 2007 Swie NA Units ENGLISH Sheet 8
11 List the more important projects recently completed by your company,
stating the approximate cost of each, and the month and year completed,
location and type of construction
12 List your major equipment available for this contract
Attad-ed
13 Experience in construction Work similar in importance to this
project
Attad-Ed
14 Background and experience of the principal members of your organization,
including officers
Attadlied
15 Credit available $ 10 nilim +
16 Bank reference Bak of Choice
17 Will you, upon request, fill out a detailed financial statement and
furnish any other information that may be required by the OWNER?
18 Are you licensed as a General CONTRACTOR'S yes
If yes, in what city, county and state? Q)JCA19d0, panajs QLtles What
class, license and numbers>
19 Do you anticipate subcontracting Work under this
Contract's Vx
If yes, what percent of total contract's
and to whom's NordOojcrado Mmffic Cmtml
20 Are any lawsuits pending against you or your firm at this time) Np
IF yes, DETAIL
Rev 10/20ro7 Section 00420 Page 2
COLORADO DEPARTMENT OF TRANSPORTATION
CERTIFICATION OF EEO COMPLIANCE
Instructions Bidders and subcontractors must complete and submit this form with bid proposals for federally funded contracts
greaterthan $10 000 This is required by the Equal Employment Opportunity Regulations [41 CFR 60 1 7(b) (1)] The regulation
also requires that if you have participated in a previous contractor subcontract and have not filed a Standard Form 100 (EEO
1) you cannot be awarded this contract You may file a report covering the delinquent period for consideration by the Federal
Highway Administration or the Director of the Office of Federal Contract Compliance U S Department of Labor
The Standard Form 100 (EEO-1) may be requested from the
Joint Reporting Committee
P O Box 779
Norfolk VA 23501
(757)461 1213
1 ❑ Yes ❑ No I have developed and have on file at each establishment an affirmative action program as
required by 41 CFR Chapter 60 Part 60 2
2 ❑ Yes ❑ No I have participated in a previous contract/subcontract subject to the equal opportunity
clause
3 ❑ Yes ❑ No I have filed with the Joint Reporting Committee the Director or the Equal Employment
Opportunity Commission all reports due under the applicable filing requirements
I declare under penalty of perjury in the second degree and any other applicable state or federal laws that the state
ments made in this document are true and complete to the best of my knowledge
Company
❑ bidder ❑ proposed subcontractor
By
Title
Date
COOT Form #U7 11/
21 What are the limits of your public liabilityP DETAIL
What company's
22 What are your company's bonding limitations?
23
The undersigned
hereby authorizes and
requests any person, firm or
corporation to
furnish any information
requested by the OWNER in
verification of
the recital comprising
this Statement of Bidder's
Qualifications
Dated
at
this 6th day of
DEcertEr 2007
CTH metnr.
imp Uh.
Name
of Bidders}�'
By
Title
p t
Kim €
MONAHAN �r
State
of Colar-adp
t
x
'bs
AhyC�
County of 'Abm
>
Gxgu L. Homes being duly sworn deposes and says that he
is president of G H Cmstncticn. Inc and that
(name of organization)
the answers to the foregoing questions and all statements therein contained
are true and correct
Subscribed and sworn to enfo^re me this 6th day of Liner 2007
Notary Public
My commission expires 06/28/10
Rev 10/20/07 Section 00420 Page 3
SECTION 00430
SCHEDULE OF SUBCONTRACTORS
List all subcontractors for the work items listed below and all subcontractors
performing over 15% of the contract
ITEM
SUBCONTRACTOR
Section 00430 Page 1
Bond Number COC49611
GLH Construction Inc & Merchants
KNOW ALL MEN BY THESE PRESENTS that we, the under-ig ned Bonding Company (Mutual)
as Principal, and as Surety, are hereby held and firmly bound unto the City of
Fort Collins, Colorado, as OWNER, in the sum of $ 5% of Attached Bid for the
payment of which, well and truly to be made, we hereby jointly and severally
bind ourselves, successors, and assigns
rHL CONDITION of this obligation is such that whereas the Principal has
submitted to the C.Lty of Fort Collins, Colorado the accompanying Bid and
hereby made a part hereof to enter into a Construction Agreement for the
construction of Fort Collins Project, 6075 Trolley Brick Restoration Project
NOW THEREFORE,
(a) If said Bad shall be rejected, or
(b) If said Bid shall be accepted and the Principal shall execute and deliver
a Contract in the form of Contract attached hereto (properly completed in
accordance with said Bad) and shall furnish a BOND for his faithful
performance of said Contract, and for payment of all persons performing
labor or furnishing materials in connection therewith, and shall in all
other respects perform the Agreement created by the acceptance of said
Bid, then this obligation shall be void otherwise the same shall remain
in force and effect, it being expressly understood and agreed that the
liability of the Surety for any and all claims hereunder shall, in no
event, exceed the penal amount of this obligation as herein stated
The Surety, for value received, hereby stipulates and agrees that the
obligations of said Surety and its BOND shall be in no way impaired or
affected by any extension of the time within which the OWNER may accept such
Bid, and said Surety does hereby waive notice of any such extension
Surety Companies executing bonds must be authorized to transact business in
the State of Colorado and be accepted by the OWNER
Rev Iormo7 Section 00410 Page 3
Bond Number COC49611
IN WTTNE33 WHEREOF, the Principal and the 3utety have hereunto bet their hands
and Seals this 5th day of December , 1007, and such of them ds are
corporations have caused their corporate seals to be hereto ai£ixed and these
presents to by signed by their proper officers, the day and year first set
forth above
PRINCIPAL
Name GLH Construction Inc
Address 780 E Garden Drive
Windsor CO 80550
Sy _
Title Gre ry L Hughes wner
ATTE
By
SURETY
Merchants Bonding Company (Mutual)
2100 Fleur Drive
Des Moines [A 50321
B 668E w
Title arole Peters AttorneyFm"r"`_a,..".�js1 i
a77 o- •"
^�daf Y, t
OZA a n [w T
f �.� ♦J �� f+jJ4nr9a^" 3 Ly. ^
(SEAL) x �
Rev 10120W7 Section 00410 Page 4
Merchants Bonding Company
(Mutual)
POWER OF ATTORNEY
Know All Persons By These Presents that the MERCHANTS BONDING COMPANY (MUTUAL) a corporation duly organized under
the laws of the State of Iowa and having its principal office in the City of Des Moines County of Polk State of Iowa hath made
constituted and appointed and does by these presents make constdute and appoint
Mike Schmitt Velene Schmitt Karole Peters
Of Greeley and State of Colorado its true and lawful Attorney In Fad with full power
and authority hereby conferred in its name place and stead to sign execute acknowledge and deliver In its behalf as surety any
and all bonds undertakings recegnizances or other written obligations in the nature thereof subject to the limitation that any such
instrument shall not exceed the amount of
FOUR MILLION ($ 4,000,000 00) DOLLARS
and to bind the MERCHANTS BONDING COMPANY (MUTUAL) thereby as fully and to the same extent as if such bond or
undertaking was signed by the duly authorized officers of the MERCHANTS BONDING COMPANY (MUTUAL) and all the acts of
said Attorney in Fact pursuant to the authority herein given are hereby ratified and confirmed
This Power -of Attorney is made and executed pursuant to and by authority of the following Amended Substituted and Restated By
Laws adopted by the Board of Directors of the MERCHANTS BONDING COMPANY (MUTUAL) on November 16 2002
ARTICLE II SECTION 8 The Chairman of the Board or President or any Vice President or Secretary shall have power and
authority, to appoint Attorneys in Fact and to authorize them to execute on behalf of the Company and attach the Seal of the
Company thereto bonds and undertakings recegnizances contracts of indemnity and other wrifings obligatory in the nature
thereof
ARTICLE If SECTION 9 The signature of any authorized officer and the Seal of the Company may be affixed by facsimile
to any Power of Attorney or Certification thereof authorizing the execution and delivery of any bond undertaking
recognizance or other suretyship obligations of the Company and such signature and seal when so used shall have the
same force and effect as though manually fixed
In Witness Whereof MERCHANTS BONDING COMPANY (MUTUAL) has caused these presents to be signed by its President and
its corporate seal to be hereto affixed this 16th day of January 2006
STATE OF IOWA
COUNTY OF POLK as
�014 co
• 0 G p%POq 9 .
4f y<
2 0- o
y 1933 c
JQq� � \1acti
MERCHANTS BONDING COMPANY (MUTUAL)
By /,e,,z7
7,7,,e-
President
On this i 6th day of January 2006 before me appeared Larry Taylor to me personally known who being by me duly sworn did say that
he is President of the MERCHANTS BONDING COMPANY (MUTUAL) the corporation described in the foregoing instrument and that the
Seal affixed to the said instrument is the Corporate Seal of the said Corporation and that the said Instrument was signed and sealed in behalf
of said Corporation by authority of Its Board of Directors
In Testimony Whereof I have hereunto set my hand and affixed my Official Seal at the City of Des Moines Iowa the day and year first
above written
CINDY 3MYTH
Commission Number 773604
MyComilon Ex
March 16Y008lna WWW^^^
Notary Public Polk County Iowa
STATE OF 10 WA
COUNTY OF POLK as
I William Warner Jr Secretary of the MERCHANTS BONDING COMPANY (MUTUAL) do hereby certify that the above and foregoing
is a true and correct copy of the POWER OF ATTORNEY executed by said MERCHANTS BONDING COMPANY (MUTUAL) which is
still in full force and effect and has not been amended or revoked
In Witness Whereof I have hereunto set my hand and affixed the seal of the Company on this 6th day of December 2007
. 013 Co*
,•�O�ppPOq
z 2 -O � ^:
a 1933 c secretary
POA 0001 (1/06) duly \1a
COLORADO DEPARTMENT OF TRANSPORTATION
CERTIFICATION OF EEO COMPLIANCE
Instructions Bidders and subcontractors must complete and submit this form with bid proposals for federally funded contracts
greater than $10 000 This is required by the Equal Employment Opportunity Regulations [41 CFR 60 1 7(b) (1)] The regulation
also requires that if you have participated in a previous contract or subcontract and have not filed a Standard Form 100 (EEO
1) you cannot be awarded this contract You may file a report covering the delinquent penod for consideration by the Federal
Highway Administration or the Director of the Office of Federal Contract Compliance U S Department of Labor
The Standard Form 100 (EEO 1) may be requested from the
Joint Reporting Committee
P O Box 779
Norfolk VA 23501
(757)461 1213
1 T1 Yes ❑ No I have developed and have on file at each establishment an affirmative action program as
required by 41 CFR Chapter 60 Part 60 2
2 ❑ Yes ❑ No I have participated in a previous contract/subcontract subject to the equal opportunity
clause
3 ❑ Yes ❑ No I have filed with the Joint Reporting Committee the Director or the Equal Employment
Opportunity Commission all reports due under the applicable filing requirements
I declare under penalty of perjury in the second degree and any other applicable state or federal laws that the state
ments made in this document are true and complete to the best of my knowledge
Company
CTH CQ'15tILCilOr1 EX bidder ❑ proposed subcontractor
By
Tiue
I Date
Secretary/Amets[Ker
17/2007
CDOT Form NJ47 III"
COLORADO DEPARTMENT OF TRANSPORTATION
PROJECT NO
ANTI -COLLUSION AFFIDAVIT
LOCATION
Fort Collam, O7
I hereby attest that I am the person responsible within my firm for the final decision as to the price(s) and amount of this
bid or if not that I have written authorization enclosed herewith from that person to make the statements set out below on
his or her behalf and on behalf of my firm
I further attest that
1 The price(s) and amount of this bid have been arrived at independently without consultation communication or
agreement for the purpose or with the effect of restricting competition with any other firm or person who is a bidder
or potential prime bidder
2A Neither the price(s) nor the amount of this bid have been disclosed to any other firm or person who is a bidder or
potential prime bidder on this project and will not be so disclosed prior to bid opening
2B Neither the prices nor the amount of the bid of any other firm or person who is a bidder or potential prime bidder on
this project have been disclosed to me or my firm
3A No attempt has been made to solicit cause or induce any firm or person who is a bidder or potential prime bidder to
refrain from bidding on this project or to submit a bid higher than the bid of this firm or any intentionally high or non
competitive bid or other form of complementary bid
3B No agreement has been promised or solicited for any other firm or person who is a bidder or potential prime bidder
on this project to submit an intentionally high noncompetitive or other form of complementary bid on this project
4 The bid of my firm is made in good faith and not pursuant to any consultation communication agreement or
discussion with or inducement or solicitation by or from any firm or person to submit any intentionally high noncom
petitive or other form of complementary bid
5 My firm has not offered or entered into a subcontract or agreement regarding the purchase or sale of materials or
services from any firm or person or offered promised or paid cash or anything of value to any firm or person
whether in connection with this or any other project in consideration for an agreement or promise by any firm or
person to refrain from bidding or to submit any intentionally high noncompetitive or other form of complementary bid
or agreeing or promising to do so on this project
6 My firm has not accepted or been promised any subcontract or agreement regarding the sale of materials or
services to any firm or person and has not been promised or paid cash or anything of value by any firm or person
whether in connection with this or any other project in consideration for my firms submitting any intentionally high
noncompetitive or other form of complementary bid or agreeing or promising to do so on this project
7 1 have made a diligent inquiry of all members officers employees and agents of my firm with responsibilities
relating to the preparation approval or submission of my firm s bid on this project and have been advised by each of
them that he or she has not participated in any communication consultation discussion agreement collusion or
other conduct inconsistent with any of the statements and representations made in this affidavit
8 1 understand and my firm understands that any misstatement in this affidavit is and shall be treated as a fraudulent
concealment from the Colorado Department of Transportation of the true facts relating to submission of bids for this
contract
I DECLARE UNDER PENALTY OF PERJURY IN THE SECOND DEGREE AND ANY OTHER APPLICABLE STATE OR
FEDERAL LAWS THAT THE STATEMENTS MADE ON THIS DOCUMENT ARE TRUE AND COMPLETE TO THE BEST
OF MY KNOWLEDGE
CCoordr{ractoes lion or company name
By
Deb
The
Vindsoic, (D WJJ✓ m[C0
cim
r1CJ1s.611t
2ntl corrtreeiors firm or company name (If ignt venture)
by
Date
Title
Sworn to before me this 6th day of 1 2007
r
No Lc
lam
e
My commimon exp res
06/28/10
i MONAHAN
NOTE This document must be signed in ink
�� •• ��y
•
;�� CDOT Form "N 1M
COLORADO DEPARTMENT OF TRANSPORTATION Project No
UNDERUTILIZED DBE (UDBE) BID Bid - 6075
CONDITIONS ASSURANCE Location
City of Fort OpUim
Instructions Contractor- Complete and submit this form with your bid Report only Underutilized DBE (UDBE) participation percentages which
qualify under the contract goal specification for this protect
POLICY
It is the policy of the Colorado Department of Transportation that underutilized disadvantaged business enterprises have maximum opportunity to
artia ate in the performance of contracts financed with federal state or local entity funds
UNDERUTILIZED DBE PARTICIPATION COMMITMENT
1) Will your company's Underublized DBE (UDBE) participation commitment meet contract goals? ® Yes ❑ No
2) Total eligible Underutilized DBE (UDBE) percentage amount from Box A below 7 0 %
3 List the UDBE firms committed work items and eli ibla UDBE percent of Your bid that ou are committing to each
UDBE FIRM NAME
CERTIFICATION
COMMITTED
SUBCONTRACT
ELIGIBLE
EXP DATE
WORK ITEM(S)
CATEGORY
UDBE %
Norti-Em Galoraio TYaffir-
KI Subcontractor
1 1712 1st
11 ).3) 09
U-affir- Cmtcol
❑ Supplier ❑ Broker
7 0 %
M
❑ Subcontractor
2
/ /
ElSupplier ❑Broker
%
❑ Subcontractor
3
/ j
❑ Supplier El Broker
%
❑ Subcontractor
4
' /
❑ Supplier El Broker
%
❑ Subcontractor
5
/ j
❑ Supplier ❑ Broker
o�
❑ Subcontractor
6
f /
❑ Supplier ❑ Broker
o�
BOX A TOTAL ELIGIBLE UDBE PERCENTAGE AMOUNT
Round percentage amounts to the nearest hundredth)
7
* Additional instructions on how to calculate the actual eligible amounts and percentages for the subcontractor supplier and broker categodes
are available on the CDOT Form #715 and in the Counting DBE Participation Toward Contract Goals and CDOT s annual DBE goal section of the
DBE - Definitions and Requirements in the Standard Special Provisions
I understand that if my company is determined to be the low bidder for the contract on this project I must submit a completed
CDOT Form #715 CERTIFICATION OF UNDERUTILIZED DBE PARTICIPATION for each firm listed on this form to the
Transportation Department by 4 00 pm the day after the bids are opened The actual amounts submitted on each CDOT Form
#715 must equal or exceed the percentage commitments documented on this form In addition if my company does not
meet the DBEIUDBE goal for this protect I must submit a completed CDOT Form #718 DBE GOOD FAITH EFFORT
DOCUMENTATION before the above stated deadline CDOT Form #715s submitted for firms not Included on this forth OR
for amounts exceeding those listed on this form will be accepted but NOT counted as Good Faith Efforts Only the efforts
the contractor made rpm to the bid opening will count as Good Faith Efforts
I understand my obligation to abide by the policy stated above I shall not discriminate on the basis of race color age sex national
origin or handicap In the bidding process or the performance of contracts
I DECLARE UNDER PENALITY OF PERJURY IN THE SECOND DEGREE AND ANY OTHER APPLICABLE STATE OR
FEDERAL LAWS THAT THE STATEMENTS MADE IN THIS DOCUMENT ARE TRUE AND COMPLETE TO THE BEST OF MY
KNOWLEDGE
Company Name Date
G LH Cc strmitim, IM 17 106 / 07
Company officer Signature _ / / Title
Previous etlitiyRs may not be used CDOT Form 714 08104
GLH CONSTRUCTION INC
12/5/2007ate
NUMBER
YEAR
MAKE/MODEL
1
2004
John Deere 330 Excavator (Justin)
2
2006
John Deere 644J Loader (Danny)
3
1986
Sakai SV91TF Roller
4
2006
Hillsboro Tuffloader 20 Trader
5
2004
Ford F-260 Pickup Justin
6
1958
Van Trader/TRL UT2 Dann
7
1997
Sakai SV50OTF Roller (Justin)
8
1993
John Deere 410 D Loader
9
2007
John Deere 722D Motor Grader (Hector)
10
2001
John Deere 644H Loader Dann
11
1998
Eager Beaver Trader
12
1993
A & W Water Truck (Ron)
13
1997
Dodge pickup Shop)
14
1982
GLH Construction Trailer (Justin)
15
2005
John Deere 200CLC Excavator (Hector)
16
2007
John Deere 750JX Dozer
17
2007
John Deere 644J Loader Dave
18
1994
Sakai SV70TF Roller (Ron)
20
2000
John Deere 330 Excavator (Extra)
21
2000
2000 Kenworth Tractor (Shop)
22
1996
John Deere 762B Scraper
23
2006
Interstate Trader (Hector)
24
1999
8 x 18 Flatbed Trader
25
1984
John Deere 762A Scr/Water Tanker
26
2001
Ford 350 (Danny s Field
28
1995
John Deere 410D Backhoe
29
2004
John Deere 624J Wheel Loader (Hector)
31
2004
4 Godwin Pump w/trader
33
2002
John Deere 450CLC Excavator Dann
34
1971
John Deere 510C Backhoe(Shop)
35
1975
1975 International Dump Truck (Shop)
36
2000
Dod a icku(Shop)
38
1999
John Deere 644H Loader Justin
39
1975
H ster Roller Hector
40
2001
Ford F250 Justin s Field
41
1999
John Deere 750C Dozer
42
2002
Ford F250 (Ron)
43
1976
1976 Fruehauf Trader (David)
44
2004
John Deere 330 CL Excavator (David)
NUMBER
YEAR
MAKE/MODEL
45
2001
John Deere 644H Loader (David)
46
1998
Sakai SV500T Roller David
47
1978
John Deere 762 ScrNNater Tanker
48
2002
Ford F250 4WD Ext Cab Hector
49
2002
Ford 350 4WD (David s Field)
50
2002
John Deere 644H Loader (David)
51
2002
John Deere 21OLE Landscape Ldr (Hector)
52
2002
John Deere 772CH II Motorgrader (Ron)
53
1997
Sakai SV70TF Roller Hector
54
2002
John Deere 200C LC Excavator (Ron)
55
2002
John Deere 624H Loader (Ron)
56
1999
John Deere 762B II Scraper (Ron)
57
1999
John Deere 310SE Backhoe
58
2003
Freight Liner Water Truck (Hector)
59
2007
Ford F350 4WD Crew Cab (Danny)
60
2003
Starlite Trader (Ron)
61
1999
Feted Dakota Lube Truck (Keith)
62
2005
Ford F 250 Pickup David
63
1943
International Model M Tractor
64
2001
Ford F550 Service Truck (Corey)
65
66
2004
210 Landscape Loader (Ron)
67
1996
Rosco Tru Pac 915 Compactor (Ron)
68
2001
MQ Power DCA 45 Generator
69
1999
Hitachi 750 Excavator (Danny)
70
71
2004
6 Godwin Pump w/trader
72
2005
Bob Cat S185 Skid Loader
73
1999
John Deere 762B Scraper (Hector)
74
2005
John Deere 644J Loader (Justin)
75
2005
Hillsboro Flatbed Trader
76
2003
HY-PAC C852-C Roller (Danny)
77
2005 1
Hitachi ZX45OLC Excavator (Justin)
78
2005 lJohn
Deere 762E Water Tanker
79
2006
Homemade Trailer (Sho
80
2006
Homemade Pi a Trader (Sho
81
2006
6 Godwin Pum w/trailer
82
2006
6 Godwin Pi w/trader
83
1997
John Deere 644G Loader
NSTRUCT ON INC
\
\pp
COLORADO DEPARTMENT OF TRANSPORTATION
PROJECT NO
ANTI -COLLUSION AFFIDAVIT
LOCATION
I hereby attest that I am the person responsible within my firm for the final decision as to the price(s) and amount of this
bid or if not that I have written authorization enclosed herewith from that person to make the statements set out below on
his or her behalf and on behalf of my firm
I further attest that
1 The price(s) and amount of this bid have been arrived at independently without consultation communication or
agreement for the purpose or with the effect of restricting competition with any other firm or person who is a bidder
or potential prime bidder
2A Neither the pnce(s) nor the amount of this bid have been disclosed to any other firm or person who Is a bidder or
potential prime bidder on this project and will not be so disclosed prior to bid opening
2B Neither the prices nor the amount of the bid of any other firm or person who is a bidder or potential bidder on
prime
this project have been disclosed to me or my firm
3A No attempt has been made to solicit cause or induce any firm or person who is a bidder or potential prime bidder to
refrain from bidding on this project or to submit a bid higher than the bid of this firm or any intentionally high or non
competitive bid or other form of complementary bid
3B No agreement has been promised or solicited for any other firm or person who is a bidder or potential prime bidder
on this project to submit an intentionally high noncompetitive or other form of complementary bid on this project
4 The bid of my firm is made in good faith and not pursuant to any consultation communication agreement or
discussion with or inducement or solicitation by or from any firm or person to submit any Intentionally high noncom
petitive or other form of complementary bid
5 My firm has not offered or entered into a subcontract or agreement regarding the purchase or sale of materials or
services from any firm or person or offered promised or paid cash or anything of value to any firm or person
whether in connection with this or any other project in consideration for an agreement or promise by any firm or
person to refrain from bidding or to submit any intentionally high noncompetitive or other form of complementary bid
or agreeing or promising to do so on this project
6 My firm has not accepted or been promised any subcontract or agreement regarding the sale of materials or
services to any firm or person and has not been promised or paid cash or anything of value by any firm or person
whether in connection with this or any other project in consideration for my firm s submitting any intentionally high
noncompetitive or other form of complementary bid or agreeing or promising to do so on this project
7 1 have made a diligent inquiry of all members officers employees and agents of my firm with responsibilities
relating to the preparation approval or submission of my firm s bid on this project and have been advised by each of
them that he or she has not participated in any communication consultation discussion agreement collusion or
other conduct inconsistent with any of the statements and representations made in this affidavit
8 1 understand and my firm understands that any misstatement in this affidavit is and shall be treated as a fraudulent
concealment from the Colorado Department of Transportation of the true facts relating to submission of bids for this
contract
I DECLARE UNDER PENALTY OF PERJURY IN THE SECOND DEGREE AND ANY OTHER APPLICABLE STATE OR
FEDERAL LAWS THAT THE STATEMENTS MADE ON THIS DOCUMENT ARE TRUE AND COMPLETE TO THE BEST
OF MY KNOWLEDGE
Contractors firm or company name
By
Date
Title
2nd contractors firm or company name (If Cant venture)
By
Dale
Title
Sworn to before me this day of 20
Notary Public
My commies on expires
NOTE This document must be signed in ink
CDOT some MOB 1/02
It is the goal of GLH Construction to provide infrastructure development and
�l improvement to the Northern Colorado area emphasizing quality and integrity
U
o Comply ONIF
7 Gregory L Hughes established GLH Construction in August of 1996 He brings
30 years experience in the pipeline and roadway construction industry GLH
7 Construction started as a company with 6 employees and has grown today to a
company of 37 employees Gary D Smith has been a managing partner since
August of 1996 He works as a general superintendent overseeing and
7 managing all field crews He also brings various superintendent experience to
the company Joseph A Schumacher has been with GLH Construction since
June of 1999 and a managing partner since January of 2000 Joe completed a
7 B S Civil Engineering degree from Colorado State University and an Associate of
Applied Science -Engineering Technology/Civil degree from Aims Community
College and is a Civil Engineer Joe also has a broad background ofJob
7 experience in the construction industry
-I I cloplyt#401t
L
L
11
GLH Construction is a company rooted in Windsor a Northern Colorado area As
such we have found that our costs are best minimized by operating within a specific
regional distance Typical parameters include the cities and towns of Ft. Collins
Loveland Berthoud Mead Longmont, Ene Dacono Fredrick, Firestone, Ft Lupton
Platteville Milliken Johnstown La Salle Kersey Greeley Eaton Evans Severance
Nunn Wellington Windsor and other areas within or nearby this boundary
to, Winner of a Mountain States BBB Torch Award for Business Ethics it
I
COP480*01
Our company specializes in infrastructure development which includes
• Subdivisions (Start to Finish)
• Construction Management
i I • Sanitary Sewer Water Line Storm Drainage Lines
�J • Backhoe & Loader Work
• Earth Work
J • Curb/Gutter/Sidewalk
• Streets
• GLH Construction also competitively bids city state and private projects
1 • Bonded and Insured
11
J jr"ALIL
Ckaft
J
J
J
f 00 Stiff j(2) Shop Mechamcs
Employee Cooidmahon
W
(3) Uhhty Crews (2) Street Crews
L
Estmiator Office Staff
11
l
!M
Agudars Corporation Aggregate Industries
Attn John Aguilar Attn Vern Trautman
Il JI 4301 Denver St P O Box 337231
Evans CO 80620 Greeley CO 80633
Phone (970) 330-7086 Phone (970) 353-2005
Dana Kepner Company Inc Foothills Concrete Pipe
Attn Dave Phillips Attn Mike Hoganson
3701 Canal Drive P O Box 838
Fort Collins CO 80524 Platteville CO 80651
JPhone (970) 482-331 1 Phone (970) 785-6066
Lafarge West Inc National Waterworks
Attn Keith Reichert Attn David Perry
925 N 35 h Avenue 1910 39a' St
Greeley CO 80631 Denver CO 80524
Phone (970) 378-2244 Phone (303) 292-1 1 12
Poudre Tech Aggregate T&T Concrete
Attn Martin Lind Attn Tony Arguello
1625 Pelican Lakes Point 3000 F Street
Windsor CO 80550 Greeley CO 80634
JPhone (970) 696-5828 Phone (970) 352-6721
LBank of Choice Advantage Bank
3635 23`0 Ave 4731 W 10'h St — Suite B
L Evans CO 80620 Greeley CO 80634
Phone (970) 506-1000 Phone (970) 353-0047
1 PinnacleB ank Signature Bank
` 1702 17 St 355 Eastman Park Dr
Cody WY 82414 Windsor CO 80550
1 Phone (307) 527-7186 Phone (970) 674-3600
3
i t1k,116"It"t
1 Sears Investment
(� Attn Brian Bartels
Il 711 10'St #200
Greeley CO 80634
Phone (970) 356-5500
Martin Lind
1625 Pelican Lakes Point Suite 201
Windsor CO 80550
Phone (970) 686-5828
Ashcroft Development, LLC
Attn David Calvin @ Bataa Oil
1
J
5801 W 1 it, St
Greeley CO 80634
Phone (970) 336-1000
Landings Development
Attn Bob Childers/Nick Francis/Adam Buna/Dale Boehner
1220 1 1 'h Ave
Greeley CO 80631
Phone (970) 353-2925
JCell
(970) 396-1031 (Dale Boehner)
Executive Homes
Attn Brian Boos
v
220 E Main St
Windsor CO 80550
Phone (970) 686-6233
L
Lumbermen s Investment Corp
Attn John Pierret
L
14755 Preston Road Suite 710
Dallas TX 75254
Phone (972) 702-8699
D-WP of Evans LLC
Attn Adam Buna
2423 Bluebells Drive
Evans CO 80620
Phone (303) 877-4766
4 4
Patriarch Development
Attn Mark Strauss
I4209
Idledale Drive
Ft Collins CO 80526
Phone (970) 226-0442
JRC Land Company LLC
J16977
Attn John Leffler
WCR 74
Eaton CO 80615
Phone (970) 454-2515
Double Eagle Construction Services Inc
Attn Gregg Seebohm
4026 Timberline Rd Suite 100
Ft Collins CO 80525
Phone (970) 223-3500
Summit Land Management Inc
Attn Andy Krill
8020 S CR 5 Suite 200
Windsor CO 80528
7
Phone (970)207-1511
Roche Constructors Inc
361 71 n Avenue
Greeley CO 80634
Phone (970) 356-361 1
J
LMajor Projects Completed
f Gateway Subdivision Ph 1 & II (Greeley CO)
l Owner Brian Boos
Contract Amount $2 356 491
LCompleted 09/ 1998
Cove @ The Landings (Evans CO)
r Owner Nick Francis/Adam Buna/Dale Boehner
t Contract Amount $658 871
Completed 09/ 1997
1
5
Water Valley Ph I & II (Windsor CO)
Owner Martin Lind
1
Contract Amount $3481863
Completed 0112001
1
Kelly Farms Ph 1 11 & III (Greeley CO)
Owner Brian Bartels
ContractAmount $3395106
Completed 0212001
Mt Vista Ph I & II/Mt Vista Center (Greeley CO)
Owner Vista Ventures
ContractAmount $4 337 024
Completed 0512002
Bay @ Landings (Evans CO)
Owner Nick Francis/Adam Buna/Dale Boehner
ContractAmount $1 581 261
Completed 05/ 1999
JPelican
Hills (Windsor CO)
Owner Martin Lind
J
Contract Amount $1 000 000
Completed 0112000
Baldndge Subdivision (Severance CO)
J
Owner IBC Dennis Egge
ContractAmount $2 470 088
JCompleted
09/2001
Willowbrook Ph I & II (Evans CO)
L
Owner Jeff Demaske
ContractAmount $4 494 640
Completed 06/2001
Diamond Valley Road (Windsor CO)
Windsor Development/Chris Ruff
Contract Amount $1 061 694
Completed 09/2001
Clearview Ph 1 II & III (Johnstown CO)
Clearview Development/Brian Boos
ContractAmount $6 404 884
LCompleted 08/2003
I
I
Boomerang (Greeley CO)
Adare Homes/Bill Purcell
1
Contract Amount $1 988 229
Completed 04/2002
Governors Ranch Ph I & II (Eaton CO)
JRC Land Co/John Leffler
Contract Amount $1 734 149
1
Completed 0712002
Highland Meadows/Lift Station (Ault, CO)
Clarkson Land
Contract Amount $1 333 096
7
Completed 1212002
Ashcroft Draw Sanitary Sewer Ph 1 & If (Greeley CO)
Ashcroft Development/David Calvin
Contract Amount $2 142 809
Completed 06/2002
St Michaels Dump Ditch/GLIC Realignment (Greeley CO)
Ashcroft Development/David Calvin
ContractAmount $718 736
Completed 1012002
Water Valley 7"' Filing (Windsor CO)
J
Dohn Construction
ContractAmount $1 666 043
Completed 09/2001
St Michaels Ph I & II (Greeley CO)
Ashcroft Development/David Calvin
L
ContractAmount $8 385 822
Completed 09/2003
LRidge @ Prairie View Ph I & II (Evans CO)
D-WP of Evans/Nick Francis & Adam Buna
L ContractAmount $ 2 009 543
Completed 12/2003
Waterford Place (Loveland CO)
Trammel Crow Residential
Contract Amount $1 319 842
LCompleted 09/2003
I
71 n Ave & 28"' St/GLIC Ditch Lining (Greeley CO)
Ashcroft Development/David Calvin
ContractAmount $990217
Completed 0812003
Summer Park Village (Greeley CO)
Highpointe Inc/Curt Karlen
ContractAmount $1 366 056
J
Completed 11/2003
Dove Hill (LaSalle CO)
JPatriarch
Builders/Mark Strauss
ContractAmount $1 378 440
Completed 0712003
Johnstown Farms (Johnstown CO)
Lumberman investment/John Pierret
ContractAmount $ 4 239 248
Completed 01/2004
Tuscany Development (Evans CO)
Tuscany Development LLC/John & Carl Ford
Contract Amount $1 357 295
Completed 01/2004
Baldndge Phase II
Jack & Beverly Schneider c/o Double Eagle Construction
Contract Amount $468 759
Completed 01/2004
Seeley Lake Improvements
Ogilvy Ditch Company
Contract Amount $268574
Completed 0212004
Town of Eaton 24" Waterline
Town of Eaton Colorado
ContractAmount $539976
Completed 01/2004
Habitat For Humanity
Greeley Colorado
Contract Amount $747 819
LCompleted 06/2004
Governors Ranch Ph III
JRC Land Company/John Leffler
Contract Amount $824 093
Completed 06/2004
J Clearview 2 Ph it
Clearwew Development/Bnan Boos
Contract Amount $300 848
Completed 07/2004
Water Valley South Trollco Ph I
Trollco/Martin Lind
Contract Amount- $4 856 782
JCompleted 1112004
Water Valley South -Metro Ph I
J Trollco/Martin Lind
Contract Amount $5 116 933
Completed I1/2004
Water Valley South -Metro Ph II
Trollco/Martin Lind
Contract Amount $2 684 692
Completed 11/2004
Barefoot Farms
Dave Barnett
Contract Amount $237 494
Completed 10/2004
.1 Winter Farm
Roche Constructors Ryan Strub
Contract Amount $4 180 00 00
u Completed 08/2005
Poudre River Ranch
{u
Double Eagle Construction Services Inc
Contract Amount $4 386 497 00
Completed 05/2006
Belmont Ridge
Belmont Ridge Development, LLC
Contract Amount $4 331 039 00
Completed 09/2005
f
fs
L
L
. ��. inn,
7430 E_ Garden Mrive Windsor, CO 80550
Phone (070) 674-0440 Fax (970) 074-0443
WWW.GLHConstraactl4Don.com
Current Projects
Project Name
Owner
Engineer
Location
Description
Contract Amt
Project dates
Belmont Ridge Ph 4 & 5
Belmont Ridge
Northern Engineenng
Windsor CO
Earthwork
5 547 398 79
Start 0512006
Development LLC
Services Inc
Sewer
Est Comp 12/2007
970-662-0600
970 221-4158
Water
Storm Sewer
Concrete
Streets
Good Samantan
Dohn Construction
TST Eng
Windsor CO
Sewer
595 000 00
Start 10/2006
970-490 1855
970 226 0204
Water
Est Comp 12/2007
Non Potable Water
Storm Sewer
Erosion Control
Timnath Ranch
Summit Land Mgmt
Northern Engmeenng
Timnath CO
Earthwork
4 300 000 00
Start 11/2006
(970) 207 1511
970 221-4158
Sewer
Fall 2007
Water
Storm Sewer
Aiadar/LCR 5
Umprop
Northern Engineering
Windsor CO
Earthwork
1 065 000 00
Start 04/2007
Sewer
Est Comp 11/2007
Water
Storm Sewer
Concrete
Streets
Touchstone/Westwood Village
013115112 LLC
Design One Consultants
Windsor CO
Erosion Control
1 465 000 00
Start 0612007
Earthwork
Est Comp 1212007
Sewer
Water
Storm Sewer
Concrete
Streets
Evans 23rd Avenue
City of Evans
City of Evans
Evans CO
Storm Sewer
8 44 000 00
Start 08/2007
Pinnacle Park
52 Highland Properties
Pickett Engineenng
Greeley CO
Streets
Earthwork
995 000 00
Est Comp 1212007
Start 0712007
Sewer
Est Comp Summer 2008
Water
Stone Sewer
Concrete
Streets
Current Projects 12/5/2007
STATE OF COLORADO
DEPARTMENT OF TRANSPORTATION
4201 E Arkansas Avenue, B404 OT
Denver, CO 80222
NOTICE
CHANGES TO CDOT'S GOOD FAITH EFFORT
AND UDBE COMMITMENT PROCESS
This letter contains important mfornation for you about a 6-month Pilot project that CDOT will
implement on all CDOT construction projects (including Local Agency projects) that are advertised after
September 1, 2004 and will apply to bid openings beginning September 23, 2004
Please read the information carefully If you have any questions about how this will apply to you and the
forms you submit to CDOT, please call the phone number listed below to discuss your questions with
someone from the Business Programs Office
The CDOT Form #714 (Underutilized DBE Bid Conditions Assurance), which is attached, has been
updated to require all Contractors bidding on CDOT Construction projects to list their UDBE
commitment information for the project at the time of bid opening This information includes the names
of the UDBE firms they will use, the items of work committed to them and their percent of the contract
Please take special note of the changes made in the text at the bottom of the form
"The actual amounts submitted on each CDOT Form #715 must equal or exceed the
percentage commitments documented on this form In addition, if my company does not
meet the DBE/UDBE goal for this project, I must submit a completed CDOT Form #718
(Underutilized DBE Good Faith Effort Documentation) before the above stated deadline
CDOT Form #715s submitted for firms not included on this form, OR for amounts
exceedin¢ those listed on this form will be accepted but NOT counted as Good Faith Efforts
Only the efforts the contractor made Prior to the bid opening will count as Good Faith
Efforts "
As always the low bidder must submit their CDOT Form #715's (Certificate of Proposed Underutilized
DBE Participation) by 4 00 pm the day after the bid opening During the Pilot project, if the low bidder
doesn't commit on the CDOT Form #714, enough UDBE participation to meet the UDBE goal for the
project, they will be required to submit their Good Faith Efforts by 4 00 pm the day after the bid opening
CDOT will evaluate only the good faith efforts made by the contractor prior to the bid opening Any
UDBE Participation submitted on CDOT Form #715's that exceeds the participation submitted on the
CDOT Form #714 will be accepted as additional UDBE participation, but will not be counted as Good
Faith Efforts and will not exempt a contractor from fulfilling the Good Faith Efforts requirements
CDOT will evaluate the results of this Pilot project after 6 months to determine whether CDOT will make
the pilot process or a similar process a permanent requirement
These changes are being communicated by letter to all Prequalified Contractors, all DBEs, all ESBs and
any other firm that has been used as a subcontractor on a CDOT project within the past year Also, a
Notice about the change and the new CDOT Form #714 will be placed in each plan set sold by CDOT's
plans room during the 6-month Pilot period, and the Business Programs Office will schedule
informational meetings for Contractors and subcontractors to discuss the process
Questions about the Pilot project should be directed to the Business Programs Office at (303) 757 9234
Project Name
Centerpiece North
Owner
Edgewood Companies
Engineer
KBN Engineering
Location
Greeley
Desch tlon
Contract Amt
Pro act dates
CO
Earthwork
940 000 00
Start 09/2007
Sewer
Est Comp Summer 2008
Water
Stone Sewer
Concrete
Evans 37th St
City of Evans
City of Evans
Evans CO
Streets
Sewer
1 005 000 00
Start 09/2007
Water
Est Comp Summer 2008
Midway
City of Ft Collins
City of Ft Collins
Ft Collins CO
Concrete
Water
8600000
Start 11/2007
Evans Town Ditch
City of Evans
C
City of Evans
Evans CO
Storm
Storm Sewer
830 000 00
Est Comp12/2007
Start 12/2007
Concrete
Est Comp Summer 2008
Current Protects 12/5/2007
GLI
s r
'k
4
780 E Garden Orlve Windsor C( 805507
Phone (970) 674-0440 Fax (970) 674-0443
www GLHConatruction com
Completed Projects
Location
Description
Contract Amt
Project dates
LindGreeley
CO
Earthwork
1 066 693 00
Completed 06/97
Sanitary Sewer
7PIaza
=LandingsDev
Water
Storm Sewer
Concrete
Sewer Main
Evans CO
Streets
Earthwork
266 419 00
Completed 66/97
Adam Buns
Sanitary Sewer
303 530-4766
Storm Sewer
Cottages @
The Landings
Fisbeck/Sheel
Bill Sheet
Evans CO
Earthwork
55 773 00
Completed 99/97
Sanitary Sewer
970-339-4525
Water
Storm Sewer
Concrete
Streets
Cove @
The Landings
Landings Dev,
Adam Buna
Evans CO
Earthwork
658 870 67
Completed 09/97
Sanitary Sewer
303 530-4766
Water
Storm Sewer
Concrete
Streets
City of Evans
11th Ave /
City of Evans
Evans CO
Sanitary Sewer
350 878 51
Completed 01/98
Earl Smith
Water
37th St
970 339-5344
Storm Sewer
Gateway
Phase II
Gateway Dev
Greeley CO
Streets
Earthwork
1 289 798 10
Completed 09/98
Brian Boos
Sanitary Sewer
970-686-6233
Water
Storm Sewer
Concrete
Streets
Completed Projects 12/5/2007
Project Name
Owner
Location
Description
Contract Amt
Proact dates
Water Valley
Martin Lind
Windsor CO
Earthwork
Phase I
Phase I & II
970-686 5828
Sanitary Sewer
1 459 467 81
Completed 09/99
Water
Storm Sewer
Phase II
Concrete
2 022 394 96
Completed 01/01
Streets
Kelly Farms
Kelly Farms
Greeley CO
Earthwork
1 041 088 24
Completed 09/98
Phase I
Development
Sanitary Sewer
Brian Bartels
Water
970 330-7700
Storm Sewer
Concrete
Streets
Mt Vista
Vista Ventures
Greeley CO
Earthwork
1 544 35122
Completed 06199
Phase I
Ken Crumb
Sanitary Sewer
970 304 1392
Water
Storm Sewer
Concrete
Streets
Pinnacle @
Sovereign Homes
Greeley CO
Earthwork
131 499 98
Completed 09/98
T Bone
Bob Leonetti
Sanitary Sewer
970 539 1941
Water
Storm Sewer
Concrete
Streets
Bay @
Landings Dev
Evans CO
Earthwork
1 581 260 92
Completed 05/99
Landings
Adam Buna
Sanitary Sewer
303 530-4766
Water
Storm Sewer
Concrete
Streets
Collages @
Fisbeck/Sheel
Evans CO
Earthwork
56 958 51
Completed 05/99
Landings
Bill Sheel
Sanitary Sewer
970-339-4525
Water
Storm Sewer
Concrete
Streets
Meadows @
Dale Boehner
Ft Collins CO
Earthwork
303 203 42
Completed 05/99
Fox Creek
970 396 1031
Sanitary Sewer
Water
Storm Sewer
Concrete
Streets
Completed Protects 12/512007
Pro ect Name
City of Evans
Owner
Location
Description
Contract Amt
Project dates
Pueblo St
Earl Smith
Evans CO
Water
336 000 00
Completed 08/99
970 339 5344
Storm Sewer
Streets
Loma Linda
Subdivision
UC Dev
Greeley
Earthwork
885 000 00
Completed 88/99
Stan Sessions
Sanitary Sewer
970 356-6082
Water
Storm Sewer
Concrete
Streets
Hilltop Estates
Martm Lind
Wmdsor CO
Earthwork
1 000 000 00
Completed 01/00
970-686 5828
Sanitary Sewer
Water
Storm Sewer
Concrete
Streets
Clubhouse @
Martm Lind
Windsor CO
Earthwork
400 000 00
Completed 07/00
Pelican Lakes
970-686 5828
Sanitary Sewer
Water
Storm Sewer
Concrete
Streets
Mt Vista
Vista Ventures
Greeley CO
Earthwork
1 861 889 20
Completed 09/00
Phase II
Ken Crumb
Sanitary Sewer
970 304 1392
Water
Storm Sewer
Concrete
Streets
Kelly Farms
Kelly Farms
Greeley CO
Earthwork
1 656 849 74
Completed 02/01
Phase II
Development
Sanitary Sewer
Brian Bartels
Water
970-330 7700
Storm Sewer
Concrete
Streets
Baldndge
IBC
Severance CO
Earthwork
2 470 087 96
Completed 99/01
Subdivision
Dennis Egge
Sanitary Sewer
970-686-0337
Water
Storm Sewer
Concrete
Streets
Town of
Town of Windsor
Windsor CO
Water
429 439 85
Completed 07/01
Windsor
1970-686-7180
Dennis Wagner
Streets
WL Replace
Completed Projects 12/5/2007
Pro act Name
Owner
Location
Description
Contract Amt
Project dates
State Farm
Hensel Phelps
Greeley CO
Earthwork
597 848 69
Completed 02/01
Budding
970 352-6565
Sanitary Sewer
Water
Storm Sewer
Willowbrook
J&J Enterprises
Evans CO
Earthwork
2 151 930 26
Completed 66/01
Phase I
Jeff Demaske
Sanitary Sewer
970 352 7072
Water
Storm Sewer
Concrete
Streets
Diamond
Windsor Dev —Windsor
CO
Earthwork
1 061 693 57
Completed 09/01
Valley Road
Group
Water
Chris Ruff
Storm Sewer
970-686-9552
Concrete
Streets
Diamond
Windsor Dev
Windsor CO
Earthwork
418 837 10
Completed 09/01
Valley 3rd Filing
Group
Sanitary Sewer
Chris Ruff
Water
970-686 9552
Storm Sewer
Concrete
Streets
Windsor
Windsor Dev
WindsorCO
Earthwork
121 815 87
Completed 09/01
Charter
Group-Chns Ruff
Concrete
Academy970-686
9552
Parking Lot
WV 4th Filing
Dohn Const
Windsor CO
Earthwork
152 043 45
Completed 10/01
Brett Brown
Sanitary Sewer
970-490 1855
Water
Willowbrook II
J&J Enterprises
Evans CO
Earthwork
1 669 634 93
Completed 09/01
Jeff Demaske
Sanitary Sewer
970 352 7072
Water
Storm Sewer
Concrete
Streets
Clearview
Clearview Dev
Johnstown CO
Earthwork
3 530 513 96
Completed 05/02
Bran Bartels
Sanitary Sewer
970 330-7700
Water
Storm Sewer
Concrete
Streets
Completed Projects 12/5/2007
Project Name
Owner
Location
Description
Contract Amt
Proect dates
Boomerang
Adare Homes
Greeley CO
Earthwork
1 988 228 59
Completed 04/02
Bill Purcell
Sanitary Sewer
303 220-5600
Water
Storm Sewer
Concrete
Streets
Willowbrook
J&J Enterprises
Evans CO
Earthwork
673 075 47
Completed 06/02
29th Ave
Jeff Demaske
Water
970-352 7072
Storm Sewer
Streets
Mountain Vista
Vista Ventures LLC
Greeley CO
Earthwork
930 784 25
Completed 05/02
Center
Ken Crumb
Sanitary Sewer
970 304 1392
Water
Storm Sewer
Concrete
Streets
Calvin Pond
David Calvin
Greeley CO
Earthwork
724 680 47
Completed 09/01
970-336 1000
WV 7th filing
Dohn Const
Windsor CO
Earthwork
1 666 043 31
Completed 09/01
Brett Brown
Sanitary Sewer
970-490 1855
Water
Governors Ranch
JRC Land Co LLC
Eaton CO
Earthwork
1 105 033 59
Completed 08/01
Phase
John Leffler
Sanitary Sewer
970-454 2515
Water
Storm Sewer
Concrete
Streets
Ashcroft Draw
Ashcroft Dev LLC
Greeley CO
Sanitary Sewer
1 055 895 09
Completed 06/02
Sanitary Sewer
David Calvin
970 336-1000
St Michaels Dump
Ashcroft Dev LLC
Greeley CO
Storm Sewer
328 590 70
Completed 06/02
Ditch
David Calvin
970-336 1000
St Michaels GLIC
Ashcroft Dev LLC
Greeley CO
Storm Sewer
390144 56
Completed 06/02
Realignment
David Calvin
970 336-1000
St Michaels
Ashcroft Dev LLC
Greeley CO
Earthwork
1 185 822 29
Completed 05/02
Subdivision
David Calvin
970-336 1000
Completed Projects 12/5/2007
Project Name
Owner
Location
Description
Contract Amt
Project dates
Highland
Clarkson Land
Ault CO
Earthwork
1 103 212 81
Completed 08/02
Meadows
Billy McDivitt
Sanitary Sewer
Ault
970-353 0802
Water
Storm Sewer
Concrete
Streets
Highland
W Windsor Dev
Windsor CO
Earthwork
958 849 15
Completed 07/02
Meadows
Brian Boos
Sanitary Sewer
Windsor
970-686-6233
Storm Sewer
DV 4th Filing
Dohn Const
Windsor CO
Earthwork
438 097 86
Completed 08/02
Brett Brown
Sanitary Sewer
970-490-1855
Water
Storm Sewer
Concrete
Streets
Governor's
JRC Land Co LLC
Eaton CO
Earthwork
629 114 74
Completed 07102
Ranch
John Leffler
Sanitary Sewer
Phase II
970-454 2515
Water
Storm Sewer
Concrete
Streets
Ridge @
D WP of Evans
Evans CO
Earthwork
968 906 55
Completed O1/03
Prairie View
Adam Buna
Sanitary Sewer
303-530-4766
Water
Storm Sewer
Concrete
Streets
North Weld
North Weld
Eaton CO
Earthwork
455 656 73
Completed O1/03
County Water
County Water
Water
District
District
Transmission
Allan Overton
Line
970-356-3020
Kelly Farms
Kelly Farms LLC
Greeley CO
Earthwork
697 167 67
Completed 12/02
Phase III
Brian Bartels
Sanitary Sewer
970 381 5166
Water
Storm Sewer
Concrete
Streets
Completed Projects 12/5/2007
Project Name
Owner
Location
Description
Contract Amt
Project dates
Clean raw
Clearview Dev LLC
Johnstown CO
Earthwork
2 945 663 72
Completed 03/03
Phase III
Brian Boos
Sanitary Sewer
970-686-6233
Water
Storm Sewer
Concrete
Streets
Ashcroft Draw
Meyer Farm
Greeley CO
Sanitary Sewer
1 086 914 30
Completed 10/2002
Sanitary Sewer
Development LLC
Phase II
David Calvin
970 336-1000
Highland Ault
Clarkson Land
Ault CO
Sanitary Sewer
229 883 27
Completed 12/02
Litt Station
Billy McDivitt
970-353-0802
City of Evans
City of Evans
Evans CO
Water
449 013 92
Completed 03/03
Waterline
Earl Smith
Project
970-339-5344
St Michaels
Ashcroft Dev LLC
Greeley CO
Earthwork
7 200 000 00
Completed 09/03
David Calvin
Sanitary Sewer
970 336 1000
Water
Storm Sewer
Concrete
Streets
Fossil Ridge
Executive Homes
Windsor CO
Earthwork
52 297 18
Completed 02/03
Sewer Crossing
Brian Boos
Sanitary Sewer
970-686-6233
Waterford Place
Trammel Crow
Loveland CO
Earthwork
1 319 842 29
Completed 09/03
Apartments
Residential
Sanitary Sewer
Water
Storm Sewer
Concrete
Streets
Longsview
Adare Homes
Greeley CO
Earthwork
383 335 10
Completed 08/03
Bill Purcell
Concrete
303-220 5600
Streets
71 st Ave/28th St
Ashcroft Dev LLC
Greeley CO
Earthwork
718 047 47
Completed 08/03
David Calvin
Streets
970-336-1000
Non Potable
Ashcroft Dev LLC
Greeley CO
Water
507 026 32
Completed 08103
Water
David Calvin
970 336 1000
Completed Projects 12/5/2007
Project Name
Owner
Location
Description
Contract Amt
Project dates
Dove Hill
Patriarch Developers
LaSalle CO
Earthwork
1 378 439 75
Completed 07/03
Mark Strauss
Sanitary Sewer
970 566-8880
Water
Storm Sewer
Concrete
Streets
GLIC Ditch Lining
Ashcroft Dev LLC
Greeley CO
Storm Sewer
272 169 75
Completed 08/03
David Calvin
970-336 1000
WV 11th Filing
Cotter Construction
Windsor CO
Earthwork
240 322 83
Completed 07/03
Dave Carlson
Sanitary Sewer
970 221-4621
Water
Storm Sewer
Concrete
Streets
High Pointe
Highpomte Inc
Greeley CO
Earthwork
252 264 55
Completed 08/03
Condos @
Curt Karlen
Sanitary Sewer
Kelly Farms
970-674 1299
Water
Storm Sewer
Concrete
Streets
Summer Park
Highpomte Inc
Greeley CO
Earthwork
1 366 056 34
Completed 11/03
Village
Curt Kaden
Sanitary Sewer
970-674 1299
Water
Storm Sewer
Concrete
Streets
Johnstown Farms
Lumberman s Investment
Johnstown CO
Earthwork
3 780 676 73
Completed 01/04
John Pierret
Sanitary Sewer
972 702 8699
Water
Storm Sewer
Concrete
Streets
Tuscany
Tuscany LLC
Evans CO
Earthwork
1 357 294 65
Completed 12/03
Carl Ford
Sanitary Sewer
970-405 3388
Water
Storm Sewer
Concrete
Streets
Completed Projects 12/5/2007
Pro ect Name
Owner
Location
Description
Contract Amt
Pro act dates
Baldridge Phase II
Jack & Beverly Schneider
Severance CO
Earthwork
468 758 95
Completed 01/04
% Double Eagle Const
Sanitary Sewer
970 223-3500
Water
Storm Sewer
Concrete
Streets
Johnstown Farms
Lumbermans
Johnstown CO
Earthwork
458 571 55
Completed 01/04
Phase IV
Investments
Sanitary Sewer
972 702-8372
Water
Storm Sewer
Concrete
Streets
Seeley Lake
Ogilvy Ddch Cc
Greeley CO
Storm Sewer
268 574 47
Completed 02/04
Improvements
970 352-4468
Town of Eaton
Town of Eaton
Eaton CO
Water
539 97616
Completed 01/04
24 Waterline
970-454 3338
Miscellaneous
Waterford Place
Kiewd Western Co
Loveland CO
Earthwork
74 479 17
Completed 03/04
303 979 9330
Habitat For
Habitat For
Greeley CO
Earthwork
747819 19
Completed 06/04
Humanity
Humanity
Sanitary Sewer
970 35M766
Water
Storm Sewer
Concrete
Streets
Governors Ranch
JRC Land Company
Eaton CO
Earthwork
824 092 90
Completed 06/04
Phase III
John Leffler
Sewer
970-454 2515
Water
Storm Sewer
Clearview 2 Ph II
Clearview Dev LLC
Johnstown CO
Earthwork
300 847 65
Completed 07/04
970-686-6233
Sewer
Water
Storm Sewer
Erosion Control
Concrete
Streets
Water Valley
Trollro Inc
Windsor CO
Earthwork
5 194 538 00
Completed 11/04
South Trollco Ph I
Martin Lind
Sewer
970-686 5828
Water
Storm Sewer
Conduit
Concrete
Streets
Completed Projects 12/5/2007
STATE OF COLORADO
DEPARTMENT OF TRANSPORTATION
4201 E Arkansas Avenue, B404 OT
Denver, CO 80222
APRIL 2005 NOTICE
CHANGES TO CDOT'S GOOD FAITH EFFORT (GFE)
AND UDBE COMMITMENT PROCESS
TO CONTINUE UNTIL FURTHER NOTICE
Last September, CDOT implemented a 6-month Pilot project on all construction projects (including Local
Agency projects) that were advertised after September 1, 2004 The Pilot made changes to CDOT's Good
Faith Efforts (GFE) and UDBE Commitment process and applied to bid openings beginning September
23, 2004
The purpose of this notice is to inform all firms budding on CDOT construction Proiects that
CDOT's Chief Engineer has directed CDOT to extend the GFE Pilot Protect as implemented in
September of 2004, until CDOT has the opportunity to assess the results of the Pilot and to issue
final emdehnes for the GFE and UDBE Commitment Process
Please read August 23, 2004 NOTICE for details on the Pilot process which Contractors should continue
to follow until further notice It is located on CDOT's "Project Bidding" page at
http //www dot state co us/bidding/Newsflash4 doc
When the final guidelines are issued, CDOT will send a mailed notification to all Prequalified
Contractors, all DBEs, all ESBs, and any other firm that has been used as a subcontractor on a CDOT
project in the past year
Any questions or input you may have about the continuation of the Pilot project should be directed to the
Business Programs Office at (303) 757-9234
Project Name
Owner
Location
Descn tion
Contract Amt
Project dates
Water Valley
Trollop Inc
Windsor CO
Earthwork
5 598 320 00
Completed 11104
South Metro Ph I
Martin Lind
Sewer
970-686-5828
Water
Storm Sewer
Conduit
Concrete
Streets
Water Valley
Trolloo Inc
Windsor CO
Earthwork
3 192 835 00
Completed 11/04
South Metro Ph 11
Martin Lind
Sewer
970-686 5828
Water
Storm Sewer
Conduit
Concrete
Streets
Barefoot Farms
Dave Barnett
Windsor CO
Earthwork
258 555 00
Completed 11/04
970-686-0525
Sewer
Water
Storm Sewer
Erosion Control
Concrete
Streets
Ridge @ Prairie
D WP of Evans LLC
Evans CO
Earthwork
663 460 18
Completed 05/05
View Ph 5
Nick Francis
Sewer
970-381 3591
Water
Adam Buna
Storm Sewer
303 877-4766
Erosion Control
Concrete
Streets
Town Centre @
Fisbeck/Sheel
Greeley CO
Earthwork
178 940 00
Completed 06/05
St Michaels
Winter Farm
Roche Constructors
Windsor CO
Earthwork
4 180 000 00
Completed 08/05
Ryan Strub
Sewer
970-356 3611
Water
Storm Sewer
Erosion Control
Concrete
Streets
Completed Projects 12/5/2007 10
Project Name
Owner
Location
Description
Contract Amt
Project dates
Belmont Ridge
Belmont Ridge
Windsor CO
Earthwork
4 331 03900
Completed 09/05
Development LLC
Sewer
970-662 0600
Water
Storm Sewer
Erosion Control
Concrete
Streets
Cimarron Pointe
Lockhart Consructors
Firestone CO
Earthwork
602 428 00
Completed 07/05
Sewer
Water
Storm Sewer
Erosion Control
Concrete
Streets
Terrace Green
Terrace Green LLC
Greeley CO
Earthwork
174 921 00
Completed 10/05
Nick Francis
Sewer
970 381 3591
Water
Storm Sewer
Concrete
Streets
Dove Hill Ph II
Patriarch Builders
LaSalle CO
Earthwork
711 276 00
Completed 10105
970-566-8880
Sewer
Water
Storm Sewer
Concrete
Streets
Parker Meadows
B & B Local
Evans CO
Earthwork
271 373 38
Completed 02/06
Construction LLC
Sewer
970 353 3141
Water
Storm Sewer
Concrete
Streets
Diamond Valley Bldg K
Dohn Construction Inc
Windsor CO
Sewer
39 094 64
Completed 12/05
970-490 1855
Water
King Surveyors Building
King Surveyors Inc
Windsor CO
Earthwork
910 018 46
Completed 08/05
970-686 5011
Sewer
Water
Concrete
Streets
Completed Projects 12/5/2007 11
Project Name
Owner
Location
Description
Contract Amt
Project dates
Chubbuck Ditch
Greeley Loveland
Loveland CO
Earthwork
44 235 63
Completed 07/05
Irrigation Company
Sewer
John Gauthne
Streets
970 330-0855
City of Evans
City of Evans
Evans CO
Earthwork
691 095 36
Completed 06/05
42nd Street
970 339-5344
Sewer
Water
Concrete
Streets
City of Evans
City of Evans
Evans CO
Earthwork
571 406 66
Completed 09/05
Riverside Parkway
970 339 5344
Concrete
Streets
Cedar Estates
Jewels Development
Pierce CO
Earthwork
117 712 26
Completed 07/05
970 206 1047
Concrete
Streets
State Hwy 257
Windsor CO
Earthwork
683 73129
Completed 02/06
Storm Sewer
Streets
WV South
Five Hole Investments
Windsor CO
Earthwork
1 956 459 66
Completed 12/05
Hillside & Trollco Ph III
Sewer
Water
Storm Sewer
Concrete
Streets
Poudre River Ranch
Double Eagle
Greeley CO
Earthwork
4 386 497 00
Completed 05/2006
Construction Sery Inc
Sewer
970-223 3500
Water
Storm Sewer
Concrete
Streets
S Gate Sewer
Trollco Inc
Windsor CO
Earthwork
1 346 415 72
Completed 05/2006
Interceptor
970-686 5828
Sewer
Water
Streets
Highpoint Vista
Double Eagle
Windsor CO
Sewer
3 826 565 44
Completed 0512006
Construction Sery Inc
970 223-3500
Storm Sewer
Water Valley Village
Dohn Construction Inc
Windsor CO
Earthwork
521 856 27
Completed 05/2006
970-490 1855
Sewer
Water
Storm Sewer
Concrete
Streets
Completed Projects 12/5/2007 12
Project Name
Owner
Location
Description
Contract Amt
Project dates
Lighthouse Bay
Landmark Construction
Windsor CO
Earthwork
574 183 15
Completed 05/2006
Condos
Solutions
Sewer
970-686-0824
Water
Storm Sewer
Concrete
Streets
Johnstown Farms Ph II
Lumbermen s Investment
Johnstown CO
Earthwork
614 300 37
Completed 04/2006
Corporation
Water
972 702-8699
Storm Sewer
Concrete
Streets
Faith Estates
National Vision
Eaton CO
Earthwork
407 778 25
Completed 05/2006
Development Inc
Water
970 396-6477
Storm Sewer
Streets
Center Park
Lou Cangdla
Greeley CO
Sewer
115 709 91
Completed 05/2006
970-356 3343
Water
Concrete
Streets
The Village @ St Michaels
Macrum Building Systems
Greeley CO
Sewer
194 208 00
Completed 03/2007
(970) 590 2200
Water
Non Potable Water
Storm Sewer
Concrete
Streets
Erosion Control
WV Village Storm
Water Valley
Windsor CO
Sewer
29 908 00
Completed 02/2007
970-686 5828
Water
Non Potable Water
Storm Sewer
Erosion Control
Southgate Business Park
Dohn Construction Inc
Windsor CO
Earthwork 4 131 167 00
Completed 12/06
970-490 1855
Sewer
and
Water
Windsor Southgate LLC
Storm Sewer
970-686 5828
Concrete
Streets
Windsor Commons
Ft Collins Paving
Windsor CO
Sewer
364 878 00
Completed 02/2007
(970) 686-0986
Water
Storm Sewer
Eagle Crossing
Eagle Crossing Dev Inc
Loveland CO
Earthwork
5 300 000 00
Completed 08/2007
970-686 5828
Sewer
water
Completed Projects 12/5/2007 13
Project Name
Owner
Location
Description
Contract Amt
Project dates
Storm Sewer
Concrete
Streets
Wyndham Hill
Ridge Development
Frederick CO
Earthwork
1 340 000 00
Completed08/2007
(970)663-0575
Sewer
Water
Storm Sewer
Concrete
Streets
McCloskey Commercial
Edgewood Companies
Greeley CO
Sewer
1 425 000 00
Completed 08/2007
(970)381 5166
Water
Storm Sewer
Erosion Control
River Run @ Poudre River
Snowdance Dev
Greeley CO
Sewer
1 166 064 00
Completed 09/2007
(970) 356 9787
Water
Non Potable Water
Storm Sewer
Erosion Control
Severance San Sewer
Town of Severance
Severence CO
Sewer
1 450 000 00
Completed 08/2007
Plaza Commercial
Herrick Garnsey
Greeley CO
Demo
652 498 00
Completed 11/2007
(970) 539-0010
Erosion Control
Sewer
Water
Storm Sewer
Condwds
Concrete
Streets
Completed Projects 12/5/2007
14
SECTION 00500
AGREEMENT FORMS
00510 Notice of Award
00520 Agreement
00530 Notice to Proceed
SECTION 00510
NOTICE OF AWARD
Date January 14, 2008
TO GLH Construction, Inc
PROJECT 6075 Trolley Brick Restoration Project
OWNER CITY OF FORT COLLINS
(hereinafter referred to as the OWNER )
You are hereby notified that your Bid dated December 6, 2007 for the above
project has been considered You are the apparent successful Bidder and have
been awarded an Agreement for 6075 Trolley Brick Restoration Project
Base Bid $109,769 94
Minor Contract Revisions + $8,000 00
OJT Colorado Training Program + $150 00
Total Agreement $117,919 94
The Price of your Agreement is One Hundred Seventeen Thousand Nine Hundred
Nineteen Dollars and Ninety Four Cents ($117 919 94)
Three (3) copies of each of the proposed Contract Documents (except Drawings)
accompany this Notice of Award Three (3) sets of the Drawings will be
delivered separately or otherwise made available to you immediately
You must comply with the following conditions precedent within fifteen (15)
days of the date of this Notice of Award that is by January 29, 2008
1 You must deliver to the OWNER three (3) fully executed counterparts of
the Agreement including all the Contract Documents Each of the Contract
Documents must bear your signature on the cover of the page
2 You must deliver with the executed Agreement the Contract Security
(Bonds) as specified in the Instructions to Bidders, General Conditions
(Article 5 1) and Supplementary Conditions
Failure to comply with these conditions within the time specified will entitle
OWNER to consider your Bid abandoned, to annul this Notice of Award and to
declare your Bid Security forfeited
Within ten (10) days after you comply with those conditions, OWNER will return
to you one (1) fully -signed counterpart of the Agreement with the Contract
Documents attached
City of Fort Collins
OWNER
By 6
J mes B O'Neill, II, CPPO, FNIGP
erector of Purchasing & Risk Management
Section 00510 Page 1
SECTION 00520
AGREEMENT
THIS AGREEMENT is dated as of the 14rd day of January in the year of 2008 and
shall be effective on the date this AGREEMENT is signed by the City
The City of Fort Collins (hereinafter called OWNER) and
GLH Construction, Inc (hereinafter called CONTRACTOR)
OWNER and CONTRACTOR, in consideration of the mutual covenants hereinafter set
forth, agree as follows
ARTICLE 1 WORK
CONTRACTOR shall complete all Work as specified or indicated in the Contract
Documents The Project for which the Work under the Contract Documents may be
the whole or only a part is defined as the construction of the 6075 Trolley
Brick Restoration Project and is generally described in Section 01010
ARTICLE 2 ENGINEER
The Project has been designed by City of
who is hereinafter called ENGINEER and
responsibilities and will have the rights
in the Contract Documents in connection
accordance with the Contract Documents
ARTICLE 3 CONTRACT TIMES
Fort Collins, Engineering Division,
who will assume all duties and
and authority assigned to ENGINEER
with completion of the Work in
3 1 The Work shall be Substantially Complete within Twenty (20) calendar
days after the date when the Contract Times commence to run as provided in the
General Conditions and completed and ready for Final Payment and Acceptance in
accordance with the General Conditions within Fifty (50) calendar days after
the date when the Contract Times commence to run
3 2 Liquidated Damages OWNER and CONTRACTOR recognize that time is of
the essence of this Agreement and that OWNER will suffer financial loss if the
Work is not completed within the times specified in paragraph 3 1 above, plus
any extensions thereof allowed in accordance with Article 12 of the General
Conditions
They also recognize the delays, expenses and difficulties involved in proving
in a legal proceeding the actual loss suffered by OWNER if the Work is not
completed on time Accordingly, instead of requiring any such proof, OWNER
and CONTRACTOR agree that as liquidated damages for delay (but not as penalty)
CONTRACTOR shall pay OWNER the amounts set forth hereafter
Section 00520 Page 1
1) Substantial Completion
One Thousand Dollars ($1000 00) for each calendar day or fraction
thereof that expires after the Twenty (20) calendar day period for
Substantial Completion of the Work until the Work is Substantially
Complete
2) Final Acceptance
After Substantial Completion, Five Hundred Dollars ($500 00) for
each calendar day or fraction thereof that expires after the Thirty
(30) calendar day period for Final Payment and Acceptance until the
Work is ready for Final Payment and Acceptance
ARTICLE 4 CONTRACT PRICE
4 1 OWNER shall pay CONTRACTOR for performance of the Work in
accordance with the Contract Documents in current funds as follows One
Hundred Seventeen Thousand Nine Hundred Nineteen Dollars and Ninety Four Cents
($117,919 94), in accordance with Section 00300, attached and incorporated
herein by this reference
ARTICLE 5 PAYMENT PROCEDURES
CONTRACTOR shall submit Applications for Payment in accordance with
Article 14 of the General Conditions Applications for Payment will be
processed by ENGINEER as provided in the General Conditions
5 1 PROGRESS PAYMENTS OWNER shall make progress payments on account
of the Contract Price on the basis of CONTRACTOR's Application for Payment as
recommended by ENGINEER, once each month during construction as provided
below All progress payments will be on the basis of the progress of the Work
measured by the schedule of values established in paragraph 2 6 of the General
Conditions and in the case of Unit Price Work based on the number of units
completed, and in accordance with the General Requirements concerning Unit
Price Work
5 1 1 Prior to Substantial Completion, progress payments will be in the
amount equal to the percentage indicated below, but, in each case, less the
aggregate of payments previously made and less such amounts as ENGINEER shall
determine, or OWNER may withhold, in accordance with paragraph 14 7 of the
General Conditions 90% of the value of Work completed until the Work has
been 50% completed as determined by ENGINEER, when the retainage equals 5% of
the Contract Price, and if the character and progress of the Work have been
satisfactory to OWNER and ENGINEER, OWNER on recommendation of ENGINEER, may
determine that as long as the character and progress of the Work remain
satisfactory to them, there will be no additional retainage on account of Work
completed in which case the remaining progress payments prior to Substantial
Completion will be in an amount equal to 100% of the Work completed 90- of
materials and equipment not incorporated in the Work (but delivered, suitably
stored and accompanied by documentation satisfactory to OWNER as provided in
Section 00520 Page 2
paragraph 14 2 of the General Conditions) may be included in the application
for payment
5 1 2 Upon Substantial Completion payment will be made in an amount
sufficient to increase total payments to CONTRACTOR to 95% of the Contract
Price, less such amounts as ENGINEER shall determine or OWNER may withhold in
accordance with paragraph 14 7 of the General Conditions or as provided by
law
5 2 FINAL PAYMENT Upon Final Completion and Acceptance of the Work in
accordance with paragraph 14 13 of the General Conditions, OWNER shall pay the
remainder of the Contract Price as recommended by ENGINEER as provided in said
paragraph 14 13
ARTICLE 6 CONTRACTOR'S REPRESENTATION
In order to induce OWNER to enter into this Agreement, CONTRACTOR makes
the following representations
6 1 CONTRACTOR has familiarized himself with the nature and extent of
the Contract Documents, Work, site, locality, and with all local conditions
and Laws and Regulations that in any manner may affect cost, progress,
performance or furnishing of the Work
6 2 CONTRACTOR has studied carefully all reports of explorations and
tests of subsurface conditions and drawings of physical conditions which are
identified in the Supplementary Conditions as provided in paragraph 4 2 of the
General Conditions
6 3 CONTRACTOR has obtained and carefully studied (or assumes
responsibility for obtaining and carefully studying) all such examinations,
investigations, explorations, tests, reports, and studies (in addition to or
to supplement those referred to in paragraph 6 2 above) which pertain to the
subsurface or physical condition at or contiguous to the site or otherwise may
affect the cost, progress, performance or furnishing of the Work as CONTRACTOR
considers necessary for the performance or furnishing of the Work at the
Contract Price, within the Contract Times and in accordance with the other
terms and conditions of the Contract Documents, including specifically the
provisions of paragraph 4 2 of the General Conditions and no additional
examinations, investigations, explorations, tests, reports, studies or similar
information or data are or will be required by CONTRACTOR for such purposes
6 4 CONTRACTOR has reviewed and checked all information and data shown
or indicated on the Contract Documents with respect to existing Underground
Facilities at or contiguous to the site and assumes responsibility for the
accurate location of said Underground Facilities No additional examinations
investigations, explorations, tests, reports studies or similar information
or data in respect of said Underground Facilities are or will be required by
CONTRACTOR in order to perform and furnish the Work at the Contract Price,
within the Contract Times and in accordance with the other terms and
Section 00520 Page 3
COLORADO DEPARTMENT OF TRANSPORTATION Project No
UNDERUTILIZED DBE (UDBE) BID
CONDITIONS ASSURANCE Location
Instructions Contractor - Complete and submit this form with your bid Report only Underutilized DBE (UDBE) participation percentages which
qualify under the contract goal specification for this project
POLICY
It is the policy of the Colorado Department of Transportation that underublized disadvantaged business enterpnses have maximum opportunity to
participate in the performance of contracts financed with federal state or local entity funds
UNDERUTILIZED DBE PARTICIPATION COMMITMENT
1) Will your companys Underutilized DBE (UDBE) participation commitment meet contract goalsv ❑ Yes ❑ No
2) Total eligible Underutilized DBE (UDBE) percentage amount from Box A below %
3 List the UDBE firms committed work items and eli ibis UDBE percent of your bid that ou are committing to each
UDBE FIRM NAME
CERTIFICATION
COMMITTED
SUBCONTRACT
ELIGIBLE
EXP DATE
WORK ITEM(S)
CATEGORY
UDBE %
❑ Subcontractor
❑ Supplier ❑ Broker
%
❑ Subcontractor
2
/ /
❑ Supplier ❑ Broker
❑ Subcontractor
3
/ /
❑ Supplier ❑ Broker
°
�O
❑ Subcontractor
4
/ /
❑ Supplier ❑ Broker
°
yO
❑ Subcontractor
5
/ /
❑ Supplier ❑ Broker
o
�O
❑ Subcontractor
L
❑ Supplier ❑ Broker
°
yO
BOX A TOTAL ELIGIBLE UDBE PERCENTAGE AMOUNT
Round percentage amounts to the nearest hundredth
Additional instructions on how to calculate the actual eligible amounts and percentages for the subcontractor supplier and broker mtegones
are available on the CDOT Form #715 and in the Counting DBE Participation Toward Contract Goals and CDOT s annual DBE goal section of the
DBE - Definitions and Requirements in the Standard Special Provisions
I understand that if my company is determined to be the low bidder for the contract on this project I must submit a completed
COOT Form #715 CERTIFICATION OF UNDERUTILIZED DBE PARTICIPATION for each firm listed on this form to the
Transportation Department by 4 00 pm the day after the bids are opened The actual amounts submitted on each CDOT Form
#715 must equal or exceed the percentage commitments documented on this form In addition if my company does not
meet the DBE/UDBE goal for this project I must submit a completed CDOT Form #718 DBE GOOD FAITH EFFORT
DOCUMENTATION before the above stated deadline CDOT Form #715s submitted for firms not Included on this form OR
for amounts exceeding those listed on this form will be accepted but NOT counted as Good Faith Efforts Only the efforts
the contractor made prior to the bid opening will count as Good Faith Efforts
I understand my obligation to abide by the policy stated above I shall not discriminate on the basis of race color age sex national
origin or handicap in the bidding process or the performance of contracts
I DECLARE UNDER PENALITY OF PERJURY IN THE SECOND DEGREE AND ANY OTHER APPLICABLE STATE OR
FEDERAL LAWS THAT THE STATEMENTS MADE IN THIS DOCUMENT ARE TRUE AND COMPLETE TO THE BEST OF MY
KNOWLEDGE
Company Name Date
Company Officer Signature Title
Previous editions may not be used CDOT Form 714 0&04
conditions of the Contract Documents, including specifically the provision of
paragraph 4 3 of the General Conditions
6 5 CONTRACTOR has correlated the results of all such observations,
examinations, investigations, tests, reports and data with the terms and
conditions of the Contract Documents
6 6 CONTRACTOR has given ENGINEER written notice of all conflicts,
errors or discrepancies that he has discovered in the Contract Documents and
the written resolution thereof by ENGINEER is acceptable to CONTRACTOR
ARTICLE 7 CONTRACT DOCUMENTS
7 1 The Contract Documents which comprise the entire Agreement between
OWNER and CONTRACTOR concerning the Work consist of the General Conditions,
Supplementary Conditions, those items included in the definition of Contract
Documents in Article 1 10 of the General Conditions, and such other items as
are referenced in this Article 7, all of which are incorporated herein by this
reference
7 2 Forms for use by CONTRACTOR in performing the Work and related
actions in carrying out the terms of this Agreement are deemed Contract
Documents and incorporated herein by this reference, and include, but are not
limited to, the following
7 2 1Certificate of Substantial Completion
7 2 2 Certificate of Final Acceptance
7 2 3 Lien Waiver Releases
7 2 4 Consent of Surety
7 2 5 Application for Exemption Certificate
7 2 6Application for Payment
7 3 Drawings, consisting of a cover sheet and sheets numbered as
follows
SHEET IDENTIFICATION SHEET NO
INDEX OF SHEETS I
PROJECT LOCATION MAP 2
PROJECT DESCRPTION 3
TYPICAL SECTIONS 4
SUMMARY OF APPROXIMATE QUANITTIES 5
TRAFFIC CONTROL PLAN 6-7
STORMWATER MANAGEMENT PLAN 8
The Contract Drawings shall be stamped "Final for Construction" and dated
Any revisions made shall be clearly identified and dated
7 4 Addenda Numbers 1 to 2, inclusive
7 5 The Contract Documents also include all written amendments and
other documents amending, modifying, or supplementing the Contract Documents
Section 00520 Page 4
pursuant to paragraphs 3 5 and 3 6 of the General Conditions
7 6 There are no Contract Documents other than those listed or
incorporated by reference in this Article 7 The Contract Documents may only
be amended, modified or supplemented as provided in paragraphs 3 5 and 3 6 of
the General Conditions
ARTICLE 8 MISCELLANEOUS
8 1 Terms used in this Agreement which are defined in Article I of the
General Conditions shall have the meanings indicated in the General
Conditions
8 2 No assignment by a party hereto of any rights under or interests in
the Contract Documents will be binding on another party hereto without the
written consent of the party sought to be bound and specifically but not
without limitations, moneys that may become due and moneys that are due may
not be assigned without such consent (except to the extent that the effect of
this restriction may be limited by law), and unless specifically stated to the
contrary in any written consent to an assignment no assignment will release or
discharge that assignor from any duty or responsibility under the Contract
Document
8 3 OWNER and CONTRACTOR each binds itself, its partners, successors,
assigns and legal representatives to the other party hereto, its partners,
successors, assigns and legal representatives in respect to all covenants,
Agreement and obligations contained in the Contract Document
Section 00520 Page 5
OWNER CITY OF FORT COLLINS
By
JAMES B O'NEILL II, CPPO, FNIGP
DI TOR OF PURCHASING
AND RISK MANAGEMENT
Date AIA
fy
V:
Attest
City Cle k
Address for giving notices
P 0 Box 580
Fort Collins, CO 80522
Approve to 4
AssijtantjCity Attorney
CONTRACTOR GLH Construction, Inc
BY
(CORPORATE
Address for given notices
J�
LICENSE NO
Section 00520 Page 6
SECTION 00530
NOTICE TO PROCEED
Description of Work 6075 Trolley Brick Restoration Project
To GLH Construction, Inc
This notice is to advise you
That the contract covering the above described Work has been fully executed by
the CONTRACTOR and the OWNER
That the required CONTRACTOR's Performance Bond and Payment Bond have been
received by the OWNER
That the OWNER has approved the said Contract Documents
Therefore, as the CONTRACTOR for the above described Work, you are hereby
authorized and directed to proceed within (_) calendar days from
receipt of this notice as required by the Agreement
Dated this day of , 20
The dates for Substantial Completion and Final Acceptance shall be
20 and 20_, respectively
City of Fort Collins
OWNER
By
Title
ACKNOWLEDGMENT OF NOTICE
Receipt of the above Notice to Proceed is hereby acknowledged this
day of 20
CONTRACTOR GLH Construction, Inc
By
Title
Section 00530 Page 1
SECTION 00600
BONDS AND CERTIFICATES
00610
Performance
Bond
00615
Payment Bond
00630
Certificate
of Insurance
00635
Certificate
of Substantial Completion
00640
Certificate
of Final Acceptance
00650
Lien Waiver
Release (CONTRACTOR)
00660
Consent of
Surety
00670
Application
for Exemption Certificate
SECTION 00610
PERFORMANCF BOND
Bond No COC49616
KNOW ALL MFN BY TIIF9F PRPSIN7s that
(Firm) GLH Construction Inc
(Address) 780 E Garden Drive Windsor CO 80550
(an Individual), (a Partnership) (a Corporation), hereinafter referred to as
the Principal and
(Farm) Merchants Bonding Company (Mutual)
(Address) 2100 Fleur Drive Des Moines IA 50321
hereinafter referred to as the surety', are held and firmly bound unto
City of Fort Collins 300 Laporte Ave, Fort Collins, Colorado 80522 a
(Mumc.ipal Corporation) hereinafter referred to as the OWNER", in the penal
gum of One Hundred Seventeen Thousand Nine Hundred Nineteen dollars and 94=01awful money of
the United States for the payment of which sum well and truly to be made, we
hind ourselves, successors and assigns, jointly and severally, firmly by these
presents
1HE CONDITIONS OF PHIS OBLIGATION are such that whereas Lhe Principal entered
into I certain Agreement with the OWNER dated the 197N day of Januaty 2008, a
ropy of Which hc,eto al.Ld,hed and made, a part hereoi for Lhe pErfurmanee 01
the Cj'y of Fort Collins project 6075 Trolley Briek itebt0r1t10n Prolert
NOW TPFREFORF, if the Principal shall well, truly and faithfully perform its
duLies all the undeiLakings covenant,, terms conditions and agreEments of
said Agreement duLing the original tcrm thereof, and any extension. thereof
which may be grantee by the OWNER, with or without Notice to the Surety and
during the life of the guarintl period, and if the Principal ,hall sati-fy all
e'arms end aenand- xn(urxed under such Agrewnient and shah fully (ndemn fy
inrl avr harnles3 the UWNFR from all r— and damages vh_(h it may siiff(r by
L(d,on )- iiliure LQ ao su anu atatl n.imLurs, nU .epay th_ O%N"R ati outlaj
.ii J —vl n a t'r cl tho OWNAP 0a/ .tnru, in making good any default then this
obi gatxon hall IhE void oUrrrwx sr to remain in full force and efteet
Rev 10/20/07 Section 00610 Page 1
PROVID[D, L'UR1HkR, that the said Surety, for value received, herfby stipulate
and agrees that no clang, extension of time, Uiteration or addition to the
terms of the Agreement or to the Work to be Performed thereurder of the
Specifications accompanying the same shall in any way affect its obligation on
this bond and it does hereby waive notice of any such change, extension of
time alteration or addition to the terms of the Agreement or to the Work or
to the Specifications
PP0VID1D FURTHER that no final settlement between the OWNFR and the
(NT1ACT01, shall abridge Lhe r,ght of my benaficlaty hereunder whose cl.im
may be unsatisfied
PROVIDED, FURTHER, that the Surety Company must be authorized to transact
business in the State of Colorado and be acceptable to the OWNER
IN WI1NESS WHEREOF this instrument is executed in three (3) counterparts,
each one of which shall be deemed an original, this 18thday of January _ 2008
IN PRESENCF Ok Princapal GLH Construction Inc
Greg C Hughes 0 ne
N$TJ C �O, - --(Tit 1 e )
Q Qp�0y''% 780 E Garden Drive Windsor CO 80550
:v to Z; (Address)
(Corposat@ SEAL :0= other Partners
IN PRE§BNCE OF
By - �/ - --- - -
iN PRESET E o suretyMerchants Bonding Company (Mutual)
Karole Peters Attor iey n Fact
__- ., _ By-
B , „2100 Fleur Drrv_e Des Moines IA 50321
(Address) — —
(",urety S(lal)
NOTE Date of Bond must not be prior to date of Agreement
if CONTRACTOR is partnership, all partners should execute Bond
Rey 1 MOW Section 00610 Page 2
Merchants Bonding Company
(Mutual)
POWER OF ATTORNEY
Know All Persons By These Presents that the MERCHANTS BONDING COMPANY (MUTUAL) a corporation duly organized under
the laws of the State of Iowa and having its principal office in the City of Des Moines County of Polk State of Iowa hath made
constituted and appointed and does by these presents make constitute and appoint
Mike Schmitt Valene Schmitt Karole Peters
of Greeley and Slate of Colorado its true and lawful Attorney in Fact with full power
and authority hereby conferred in its name place and stead to sign execute acknowledge and deliver in its behalf as surety any
and all bonds undertakings recognizances or other written obligations in the nature thereof subject to the limitation that any such
instrument shall not exceed the amount of
TEN MILLION ($10,000 000 00) DOLLARS
and to bind the MERCHANTS BONDING COMPANY (MUTUAL) thereby as fully and to the same extent as if such bond or
undertaking was signed by the duly authorized officers of the MERCHANTS BONDING COMPANY (MUTUAL) and all the acts of
said Attorney in Fact pursuant to the authority herein given are hereby ratified and confirmed
This Power of Attorney is made and executed pursuant to and by authority of the following Amended Substituted and Restated By
Laws adopted by the Board of Directors of the MERCHANTS BONDING COMPANY (MUTUAL) on November 16 2002
ARTICLE II SECTION 8 The Chairman of the Board or President or any Vice President or Secretary shall have power and
authority to appoint Attorneys in Fact and to authorize them to execute on behalf of the Company and attach the Seal of the
Company thereto bonds and undertakings recograzances contracts of indemnity and other writings obligatory in the nature
thereof
ARTICLE II SECTION 9 The signature of any authorized officer and the Seal of the Company may be affixed by facsimile
to any Power of Attorney or Certification thereof authorizing the execution and delivery of any bond undertaking
recognizance or other suretyship obligations of the Company and such signature and seal when so used shall have the
same force and effect as though manually fixed
In Witness Whereof MERCHANTS BONDING COMPANY (MUTUAL) has caused these presents to be signed by its President and
its corporate seal to be hereto affixed this 3rd day of January 2008
*00 CO*, MERCHANTS BONDING COMPANY (MUTUAL)
�O CO*,
c
1933 6y
Zvb�`V � \cacti
STATE OF IOWA President
COUNTY OF POLK ss
On this 3rd day of January 2008 before me appeared Larry Taylor to me personally known who being by me duly swom did say that
he is President of the MERCHANTS BONDING COMPANY (MUTUAL) the corporation described in the foregoing instrument and that the
Seal affixed to the said instrument is the Corporate Seal of the said Corporation and that the said instrument was signed and sealed in behalf
of said Corporation by authority of its Board of Directors
In Testimony Whereof I have hereunto set my hand and affixed my Official Seal at the City of Des Moines Iowa the day and year first
above written
fk Commission Number 1t73504
My Commission Expires V
March 16 2009 1 Notary Pubic Polk County Iowa
STATE OF IOWA
COUNTY OF POLK ss
I William Warner Jr Secretary of the MERCHANTS BONDING COMPANY (MUTUAL) do hereby certify that the above and foregoing
is a true and correct copy of the POWER OF ATTORNEY executed by said MERCHANTS BONDING COMPANY (MUTUAL) which is
still in full force and effect and has not been amended or revoked
In Witness Whereof I have hereunto set my hand and affixed the seal of the Company on this
18th day of January
2008
tip\NO m0 Co*, pPPO* 9
a, y�
1-- = O
s 1933 c
Secretary
POA 0001 (1/06)
'ICTION OQU 5
PAYMENT BOND Bond No COC49616
KNOW ALL MEN Be THESE PRE,SFNTS that
(Firm) GLH Construction Inc
(Andress) 780E Garden Drive Windsor CO80550
(In Individual) (a Partnership) la Coiporati.on), hereinafter referred to as
,hc Fiincipal' and
(Fi im) Merchants Bonding Company (Mutual)
(Address) 2100 Fleur Drive Des Moines IA 50321
hereinafter referred to as the Surety , are held and firmly bound unto the
City of Fort Collins 300 Laporte Ave Fort Collins Colorado 80522 a
(Municipal Corporation) hereinafter refexrPd to do llars & 9dY1t"the OWNER ful money penal of the
sum of One Hundred Seventeen Thousand Nine Hundred Nineteen do
United States for the payment of which sum well and truly to be made we bind
ourselves successors and assigns, jointly and severally, firmly by these
prPsentS
THE (OND11ION' OF THIS OBLICAPION are such that whereas the Principal entered
_nto a ctrtiin Agreement with the OWNEh, datc,d the 14TIl rlay of Januir 2008
a copy nt which _� hereto attachPd ind made a pdxt hereof for the performance
of The City of Eort collins prc3ect, 605 Trolley Brit_. Restoration Pio)eoL
NOW, THEREFORE, if the Principal shall make payment to all persons, firms,
inbother prosecution cofpcthei Work furnishingmaterials
mfor r in such cAgree Agreement performing labor and any
authorized extension or modification thereof, including all amounts due for
materials t^ b� is nntcornectairs on i ort w LI,tR the machinery,
equipment
of and suchuchools Work, consumed,
all
rentPd r �n much Work
nvi+ nrr= numiun on „d1d Work inj roi zj labor, per_ormed
y nnrnnt xaLtor or orherw Lse then tt .ia oc.ti q t awn 5hv 1 be ��id
Io +elf] n 1❑ 111 .UL( Ln(' t l
Section 00615 Page 1
Rev 10/20101
PROVlrh D, LURTHPR chat the said Surety, for value, rece,ved, hereby stipula}es
and agrees that no change, extension of time, alteration or addition to the
terms of the Agreement or to the alork to be pertormed therei.nder or the
Specifications accompanying the game shall _n any way afEect its obligation on
this bond and it does hereby waive notire of any such change, extension of
time, 37terdtian or addition to the trim of the Agreement or to the Work or
to the ,p(( Lfrcdtaons
EROb1)ED FURTHER that no final s(ttlemPnt between the OWNER and the
cONTRPCTOR shztl 3br_dge the n qht of any beneficiary nrxeundei, whuse claim
may be unsatisfied
PROVIDED FURTHER that the Surety Company must be authorized to transact
business in the State of Colorado and be acceptable to the OWNER
IN WITNESS WHERFOF, this instrument is executed in three (3) counterparts,
each one of which shall be deemed an original, this 18thday of January , 2008
IN ORESENCE OF
'fin --
V'Oki 10-1
(Corpora 9r' w ES AT cD'
IN PRESE$CE6
Principal GLH Construction Inc
By
Grego%LHughes Own r
(Title)
780 E Garden Drive Windsor CO 80550 _
__ -- (Address)
Other Partners
N PRL S EN( F OF Surety Merchants Bonding Company (Mutual)
— *AjaCj&arola Peters Artorne in Fact
By 2100 Fleur Drive Des Moines IA 50321 _
(Address)
(Surrty Seal)
NOTE Date of Bond must not be prior to date of Agreement
If CONTRACTOR is Partnership, all partners should execute Bond
Rev 10120/07 Section 00615 Page 2
ADDENDUM No 1
6075 Trolley Brick Restoration Project
SPECIFICATIONS AND CONTRACT DOCUMENTS
Description of Bid 6075 Trolley Brick Restoration Project
OPENING DATE 3 00 p in (Our Clock) December 6 2007
To all prospective bidders under the specifications and contract documents described above
the following changes are hereby made
QUESTIONS AND ANSWERS
1 For estimating purposes the quantity of salvable bricks is 50% of the existing brick surface
area
2 A salvable brick is defined as structurally sound with no more than 15% loss due to damage
or deterioration An inspector will be available during construction operations to evaluate the
suitability of the salvaged bricks
Please contact John D Stephen CPPO CPPB Senior Buyer at (970) 221-6777 with any
questions regarding this addendum
RECEIPT OF THIS ADDENDUM MUST BE ACKNOWLEDGED BY A WRITTEN STATEMENT
ENCLOSED WITH THE BID/QUOTE STATING THAT THIS ADDENDUM HAS BEEN
RECEIVED
where renewal Is a way of life
Merchants Bonding Company
(Mutual)
POWER OF ATTORNEY
Know All Persons By These Presents that the MERCHANTS BONDING COMPANY (MUTUAL) a corporation duly organized under
the laws of the State of Iowa and having its principal office in the City of Des Moines County of Polk State of Iowa hath made
constituted and appointed and does by these presents make constitute and appoint
Mike Schmitt Valerie Schmitt Karole Peters
of Greeley and State of Colorado its true and lawful Attorney in Fact with full power
and authority hereby conferred in its name place and stead to sign execute acknowledge and deliver in its behalf as surety any
and all bonds undertakings recognizances or other written obligations in the nature thereof subject to the limitation that any such
instrument shall not exceed the amount of
TEN MILLION ($10,000 000 00) DOLLARS
and to bind the MERCHANTS BONDING COMPANY (MUTUAL) thereby as fully and to the same extent as if such bond or
undertaking was signed by the duly authorized officers of the MERCHANTS BONDING COMPANY (MUTUAL) and all the acts of
said Attorney in Fact pursuant to the authority herein given are hereby ratified and confirmed
This Power of Attorney is made and executed pursuant to and by authority of the following Amended Substituted and Restated By
Laws adopted by the Board of Directors of the MERCHANTS BONDING COMPANY (MUTUAL) on November 16 2002
ARTICLE II SECTION 8 The Chairman of the Board or President or any Vice President or Secretary shall have power and
authority to appoint Attorneys in Fact and to authorize them to execute on behalf of the Company and attach the Seal of the
Company thereto bonds and undertakings recognizances contracts of indemnity and other writings obligatory in the nature
thereof
ARTICLE II SECTION 9 The signature of any authorized officer and the Seal of the Company may be affixed by facsimile
to any Power of Attorney or Certification thereof authorizing the execution and delivery of any bond undertaking
recognizance or other suretyship obligations of the Company and such signature and seal when so used shall have the
same force and effect as though manually fixed
In Witness Whereof MERCHANTS BONDING COMPANY (MUTUAL) has caused these presents to be signed by As President and
its corporate seal to be hereto affixed this 3rd day of January 2008
00 OpPOq 9
cl, 2 0 9m y<
Z 3
a 1933 c
ZJb�hr � `cacti
STATE OF IOWA
COUNTY OF POLK as
MERCHANTS BONDING COMPANY (MUTUAL)
By /—,.f,7 7,7x,
President
On this 3rd day of January 2008 before me appeared Larry Taylor to me personally known who being by me duly sworn did say that
he is President of the MERCHANTS BONDING COMPANY (MUTUAL) the corporation descnbed in the foregoing instrument and that the
Seal affixed to the said instrument is the Corporate Seal of the said Corporation and that the said instrument was signed and sealed in behalf
of said Corporation by authority of its Board of Directors
In Testimony Whereof I have hereunto set my hand and affixed my Official Seal at the City of Des Moines Iowa the day and year first
above written
fAN Commission NuNDY mfibe YT173504 `�" U ��� �'✓
My Commission Expires
March 16 2009 Notary Public Polk County Iowa
STATE OF IOWA
COUNTY OF POLK as
I William Warner Jr Secretary of the MERCHANTS BONDING COMPANY (MUTUAL) do hereby certify that the above and foregoing
is a true and correct copy of the POWER OF ATTORNEY executed by said MERCHANTS BONDING COMPANY (MUTUAL) which is
still in full force and effect and has not been amended or revoked
In Witness Whereof I have hereunto set my hand and affixed the seal of the Company on this
18th day of January
2008
a0,AG CO,H.a.
�O pPPOq 9
y 1933 ti
Secretary
POA 0001 (1/06)
SECTION 00630
CERTIFICATE OF INSURANCE
CONTRACTOR shall insert his own standard form for Certificate of Insurance
Rev 10/20/07 Section 00630 Page 1
ACORv CERTIFICATE OF LIABILITY
PRODUCER
Rich 6 Cartmill Insurance
If Colorado LLC
ID
INSURANCE GLHCO-
THIS CERTIFICATE IS ISSUED AS A MATTER f
ONLY AND CONFERS NO RIGHTS UPON THE
HOLDER. THIS CERTIFICATE DOES NOT AMI
ALTER THE COVERAGE AFFORDED BY THE
I O Box 336416
Greeley CO 80633
Phone: 970-356-6030 Fax:970-356-8032
V5URED
INSURERS AFFORDING COVERAGE
INSURER A: $l tuminOuB Insurance
INSURER B'. Pinnacol Assurance
INSURER C'.
GLH
780 E. GardQcn1Drive onnc
Windsor CO 90550
INSURER D:
INSURER E:
DATE (MM/DDIYYYY)
CERTIFICATE
'Nn. EXTEND OR
NAIC #
COVERAGES
OF INURANCE LISTED BELOW HAVE
BEEN ISSUED TO THE INSURED NAMED
PERIOD
CINDICATED, ATE MAY
THSTAN
BE ISSUED OR DING
POLICIES
THE
ANY
REQUIREMENTS
TERM OR CONDITION OF ANY
CONTRACT OR OTHER DOCUMENT WITH
IS SUBJECT
RESPECTT TO WH CH
TO ALL THE TERMS,
THIS CERIF
EXCLUSIONS AND CONDITIONS
OF SUCH
MAY
PERTAIN,
THE INSURANCE AFFORDED BY THE
POLICIES DESCRIBED HEREIN
POLICIES.
AGGREGATE LIMITS SHOWN MAY HAVE
BEEN REDUCED BY PAID CLAIMS.
TYPE OF INSURANCE
POLICY NUMBER
DATE MMIDDIVY
DATELIMITS
MM/DDIYY
LTR
NSR
EACH OCCURRENCE $ 1,000,000
GENERAL LIABILITY
CLP3225990
04/01/07
04/01/08
PREMISES (Ea occarence
$100,000
MED EXP (Any one person)
$ 5,000
A
X
X COMMERCIAL GENERALLIABILITY
— '-
CLAIMS MADE iX I OCCUR
PERSONAL SADVINJURY
$1,000 000
GENERAL AGGREGATE
$2 000,000
1 -_-,
PRODUCTS - COMP/OP AGG
$2,000 000
__. j___—.__—_.._-----
GENT. AGGREGATE LIMIT APPLIES PER'.
PRO- LOD
POLICY JECT
AUTOMOBILE LIABILITY
04/01/07
04/01/08
COMBINED SINGLE LIMIT
(Ea accident)
$ 1 , 000,000
X ANY AUTO
CAP3504416
IA
ALL OWNED AUTOS
BODILY INJURY
(Per person)
$
SCHEDULED AUTOS
HIRED AUTOS
BODILY INJURY
(Per accident)
$
NON -OWNED AUTOS
PROPERTY DAMAGE
$
(Per accident)
AUTO ONLY - EA ACCIDENT
$
GARAGE
LIABILITY
EA ACC
8
1 ANY AUTO
OTHER THAN
AUTO ONLY'. AGO
$
EACH OCCURRENCE
$5,000,000
EXCESS/UMBRELLA LIABILITY
CLAIMS MADE
CUP2577607
04/01/07
04/01/08
AGGREGATE
s 5,000 000
$
A
X OCCUR
DEDUCTIBLE
$
X RETENTION $10 000
X TORY LIMITS ER
WORXERS COMPENSATONAND
EMPLOYERS'LIABILITY 4028616 07/01/07 07/01/08 E.L.EACH ACCIDENT $1000000
B ANY PROPRIETOR/PARTNER/EXECUTIVE E.L. DISEASE - EA EMPLOYEE $ 1000000
O yFyFICERIMEMBER EXCLUDED?
describeE. L. DISEASE - POLICY LIMIT $1000000
SPas,
ECIAL below
OTHER
A (Leased / Rented CLP3225990 04/01/07 04/01/08 Limit $250,000
E i ment
DESCRIPTION OF OPERATIONS I LOCATIONS I VEHICLES I EXCLUSIONS ADDED BY ENDORSEMENT I SPECIAL PROVISIONS
but
'City of Fort Collins is an additional insured on the general liability,
only with respects to liability arising out of the insureds operations.
KPETERS SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE THE EXPIRATION
DATE THEREOF, THE ISSUING INSURER WILL ENDEAVOR TO MAIL 30 DAYS WRITTEN
City of Fort Collins NOTICE TO THE CERTIFICATE HOLDER NAMED TO THE LEFT, BUT FAILURE TO DO SO SHALL
Engineering Department IMPOSE NO OBLIGATION OR LIABILITY OF ANY KIND UPON THE INSURER, ITS AGENTS OR
PO BOX 580 REPRESENTATIVES.
Fort Collins CO 80522-0580 •„runo,�cn CCU. FCFMTATIVF
ACORD 25 42001/08)
IMPORTANT
If the certificate holder is an ADDITIONAL INSURED, the policy(ies) must be endorsed. A statement
on this certificate does not confer rights to the certificate holder in lieu of such endorsement(s).
If SUBROGATION IS WAIVED, subject to the terms and conditions of the policy, certain policies may
require an endorsement. A statement on this certificate does not confer rights to the certificate
holder in lieu of such endorsement(s).
DISCLAIMER
The Certificate of Insurance on the reverse side of this form does not constitute a contract between
the issuing insurer(s), authorized representative or producer, and the certificate holder, nor does it
affirmatively or negatively amend, extend or alter the coverage afforded by the policies listed thereon.
L
L
L
L
L
L
t
,L
SECTION 00635
CERTIFICATE OF SUBSTANTIAL COMPLETION
TO CITY OF FORT COLLINS
(OWNER)
DATE OF SUBSTANTIAL COMPLETION PROJECT TITLE 6075 Trolley Brick Restoration
Project
PROJECT OR SPECIFIED PART SHALL LOCATION Fort Collins, Colorado
INCLUDE
OWNER City of Fort Collins
CONTRACTOR GLH Construction, Inc
CONTRACT DATE January 14, 2008
The Work performed under this contract has been inspected by authorized
representatives of the OWNER, CONTRACTOR, and the ENGINEER and the project (or
specified part of the project, as indicated above) is hereby declared to be
substantially completed on the above date
A tentative list of items to be completed or corrected is appended hereto
This list may not be exhaustive, and the failure to include an item on it does
not alter the responsibility of the CONTRACTOR to complete all the Work in
accordance with the Contract Documents
ENGINEER
AUTHORIZED REPRESENTATIVE DATE
The CONTRACTOR accepts the above Certificate of Substantial Completion and
agrees to complete and correct the items on the tentative list within the time
indicated
0
CONTRACTOR
AUTHORIZED REPRESENTATIVE DATE
The OWNER accepts the project or specified area of the project as
substantially complete and will assume full possession of the project or
specified area of the project at 12 01 a m , on The
responsibility for heat, utilities, security, and insurance under the Contract
Documents shall be as set forth under 'Remarks' below
CITY OF FORT COLLINS, COLORADO By
OWNER
AUTHORIZED REPRESENTATIVE
REMARKS
DATE
Rev 10/20/07 Section 00635 Page 1
SECTION 00640
CERTIFICATE OF FINAL ACCEPTANCE
TO
Gentlemen
, 20
You are
hereby
notified that
on the
day of
20_, the City of
Fort
Collins,
Colorado,
has
accepted
the Work completed by
for the
City of
Fort Collins
proDect,
6075 Trolley
Brick Restoration Pro ect
A check is attached hereto in the amount of $
as Final Payment for all Work done, subject to the terms of the Contract
Documents which are dated , 20
In conformance with the Contract Documents for this project, your obligations
and guarantees will continue for the specified time from the following
date 20
Sincerely,
OWNER City of Fort Collins
By
Title
ATTEST
Title
Rev 10/20/07 Section 00640 Page 1
SECTION 00650
LIEN WAIVER RELEASE
(CONTRACTOR)
TO City of Fort Collins, Colorado (OWNER)
FROM GLH Construction, Inc (CONTRACTOR)
PROJECT 6075 Trolley Brick Restoration Project
1 The CONTRACTOR acknowledges having received payment, except retainage
from the OWNER for all work, labor, skill and material furnished,
delivered and performed by the CONTRACTOR for the OWNER or for anyone in
the construction, design, improvement, alteration, addition or repair of
the above described project
2 In consideration of such payment and other good and valuable
consideration, the receipt and adequacy of which are hereby acknowledged,
the CONTRACTOR voluntarily waives all rights, claims and liens, including
but not limited to, mechanic's liens, Miller Act claims (40 U S C A 270
a and b), stop notices, equitable liens and labor and material bond
rights which the CONTRACTOR may now or may afterward have, claim or
assert for all and any work, labor, skill or materials furnished,
delivered or performed for the construction, design, improvement,
alteration, addition or repair of the above described project, against
the OWNER or its officers, agents, employees or assigns, against any fund
of or in the possession or control of the OWNER, against the project or
against all land and the buildings on and appurtenances to the land
improved by the project
3 The CONTRACTOR affirms that all work, labor and materials, furnished,
delivered or performed to or for the construction, design, improvement,
alteration, addition or repair of the project were furnished, delivered
or performed by the CONTRACTOR or its agents, employees, and servants, or
by and through the CONTRACTOR by various Subcontractors or materialmen or
their agents, employees and servants and further affirms the same have
been paid in full and have released in full any and all existing or
possible future mechanic's liens or rights or claims against the project
or any funds in the OWNER'S possession or control concerning the project
or against the OWNER or its officers, agents, employees or assigns
arising out of the project
4 The CONTRACTOR agrees to defend and hold harmless the OWNER, the lender,
if any, and the Surety on the project against and from any claim
hereinafter made by the CONTRACTOR'S Subcontractors, materialmen,
employees, servants, agents or assigns against the project or against the
OWNER or its officers, employees, agents or assigns arising out of the
project for all loss, damage and costs, including reasonable attorneys
Rev 10/20/07 Section 00650 Page 1
fees, incurred as a result of such claims
5 The parties acknowledge that the description of the project set forth
above constitutes and adequate description of the property and
improvements to which this Lien Waiver Release pertains It is further
acknowledged that this Lien Waiver Release is for the benefit of and may
be relied upon by the OWNER, the lender, if any, and Surety on any labor
and material bonds for the project
Signed this day of , 20
CONTRACTOR GLH Construction, Inc
By
Title
ATTEST
Secretary
STATE OF COLORADO )
)ss
COUNTY OF LARIMER )
Subscribed and sworn to before me this day of
20_, by
Witness my hand and official seal
My Commission Expires
Notary Public
Rev 10/20/07 Section 00650 Page 2
SECTION 00660
CONSENT OF SURETY
TO City of Fort Collins Colorado
(hereinafter referred to as the "OWNER')
CONTRACTOR _GLH Construction, Inc
PROJECT 6075 Trolley Brick Restoration Pro]ect
CONTRACT DATE
In accordance with the provisions of the Contract between the
OWNER and the CONTRACTOR as indicated above, for
on bond of
(Surety)
hereby approves of the Final Payment to the CONTRACTOR, and
agrees that Final Payment to the CONTRACTOR shall not relieve the
Surety Company of any of its obligations to the OWNER, as set
forth in the said Surety Company's Bond
IN WITNESS WHEREOF, the Surety Company has hereunto set its hand
this day of ,
(Surety Company)
M
ATTACH Power of Attorney and Certificate of Authority of
Attorney(s)-in-Fact
Rev 10/20/07 Section 00660 Page 3
SECTION 00670
Section 00670 Page 1
SPECIFICATIONS
AND
CONTRACT DOCUMENTS
FOR
Trolley Brick Restoration Project
BID NO 6075
PURCHASING DIVISION
215 NORTH MASON STREET, 2ND FLOOR, FORT COLLINS
December 6, 2007 — 3 00 P M (OUR CLOCK)
where renewal is a way of life
DR 0172 (12/98)
COLORADO DEPARTMENT OF REVENUE
DENVER CO 80261
(303)232 2416
CONTRACTOR APPLICATION
FOR
EXEMPTION CERTIFICATE
Pursuant to Statute
Section 39-26 114(1)(a)(XIX)
0
uU NOT WRITE IN THIS SPACE
The exemption certificate for which you are applying must be used only for the purpose of purchasing construction and building materials
for the exempt project described below This exemption does not Include or apply to the purchase or rental of equipment supplies and
matenals which are purchased rented or consumed by the contractor and which do not become part of the structure highway road
street or other public works owned and used by the exempt organization
Any unauthorized use of the exemption certificate will result in revocation of your exemption certificate and other penalties provided by
law
A separate certificate is required for each contract
Subcontractors will not be issued Certificates of Exemption by the Department of Revenue It is the responsibility of the prime contractor
to issue certificates to each of the subcontractors (See reverse side)
FAILURE TO ACCURATELY COMPLETE ALL BOXES WILL CAUSE THE APPLICATION TO BE DENIED
Registration/Account No (to be assigned by DORI Period
89 - 0170-750 (999) $0 00
Trade name/DBA Owner partner or corporate name
Mailing address (City State Zip) Contact Person
E Mail address Federal Employers Identification Number Bid amount for your contract
Fax Number Business telephone number Colorado vnthholding tax account number
)
if 4 qY ry a iytad bq! b E P u
yX `
Name of exempt organization (as shown on contract) Exempt organizations number
9
of exempt organization (City State Zip)
Principal contact at exempt organization Principal contact s telephone number
Physical location of project site (give actual address when applicable and Cities and/or County ties) where protect is located)
Scheduled Month Day Year
construction start date
Estimated Month Day Vear
completion date
It
er
It 'r tin
if declare under penalty of perjury In the second degree that the statements made In this application are
true and complete to the best of my knowledge
Signature of owner partner or corporate officer Title of corporate officer Date
nn rTnT t1 D tTU OUT n117 TTrlI T
Section 00670 Page 2
Special Notice
Contractors who have completed this application in the past please note the following changes in
procedure
The Department will no longer issue individual Certificates of exemption to subcontractors Only
prime contractors will receive a Contractors Exemption Certificate on exempt projects
Upon receipt of the Certificate the prime contractor should make a copy for each subcontractor
involved in the protect and complete it by filling in the subcontractor s name and address and signing
it
The original Certificate should always be retained by the prime contractor Copies of all Certificates
that the prime contractor issued to subcontractors should be kept at the prime contractor's place of
business for a minimum of three years and be available for inspection in the event of an audit
Once an 89# has been assigned to you please use the next five numbers following it for any
applications submitted for future protects This should be your permanent number For instance if
you were assigned 89-12345-0001 every application submitted thereafter should contain 89-12345
on the application The succeeding numbers will be issued by the Department of Revenue DO NOT
enter what you believe to be the next in sequence as this may delay processing of your application
Section 00670 Page 3
SECTION 00700
GENERAL CONDITIONS
GENERAL CONDITIONS
M&
CONSTRUCTION CONTRACT
These GENERAL CONDITIONS have been developed by using the
STANDARD GENERAL CONDITIONS OF THE CONSTRUCTION
CONTRACT prepared by the Engineers Joint Contract Documents
Committee EJCDC No 1910 8 (1990 Edition) as a base Changes to
that document we shown by underlining text that has been added and
striking through text that has been deleted
EJCDC GENERAL CONDITIONS 1910-8 (1990 EDITION)
WITH CITY OF FORT COLLINS MODIFICATIONS (REV 9199)
TABLE OF CONTENTS OF GENERAL CONDITIONS
Article or Paragraph
Number & Title
DEFINITIONS
11
Addenda
12
Agreement
1 3
Application for payment
14
Asbestos
15
Bid
16
Bidding Documents
17
Bidding Requirements
18
Bonds
19
Change Order
1 10
Contract Documents
1 11
Contract Price
112
Contract Tim as
113
CONTRACTOR
114
defective
1 15
Drawings
1 16
Effective Date of the Agreement
117
ENGINEER
118
ENGINEERS Consultant
1 19
Field Order
120
General Requirements
121
Hazardous Waste
122 a
Laws and Regulations Laws or
Regulations
1 22 b
Legal Holidays
123
Liens
124
Milestone
1 25
Notice of Award
126
Nonce to Proceed
127
OWNER
129
Partial Utilization
129
PCBs
130
Petroleum
131
Project
1 32 a
Radioactive Material
1 32 b
Regular Working Hours
133
Resident Project Representative
134
Samples
135
Shop Drawings
136
Specifications
137
Subcontractor
138
Substantial Completion
1 39
Supplementary Conditions
140
Supplier
141
Underground Facilities
142
Unit Price Work
143
Work
144
Work Change Directive
1 45
Written Amendment
Page Article or Paragraph
Number Number & Title
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
7
23
3
3
3
3
Page
Number
PRELIMINARY MATTERS
3
21
Delivery of Bonds
3
22
Copies of Documents
3
23
Commencement of Contract
Tunes Notice to Proceed
3
24
Starting the Work
3
25 27
Betore Starting Construction
CONTRACTORS Responsibility
to Report Preliminary Schedues
Delivery of Certificates of
Insurance
34
28
Preconstruction Conference
4
29
Initially Acceptable Schedules
4
CONTRACT DOCUMENTS
AMENDING REUSE
4
3 1 32
Intent
4
33
Reference to Standards and Speci
ficatrcns of Technical Societies
Reporting and Resolving Dis
crepancies
45
34
Intent of Certain Terms or
Adjectives
5
35
Amending Contract Documents
5
36
Supplementing Contract
Documents
5
37
Reuse of Docum ents
j
AVAILABILITY OF LANDS
SUBSURFACE AND PHYSICAL CONDITIONS
REFERENCE POINTS
5
41
Availability of Lands
5-6
4 2
Subsurface and Physical
Conditions
6
42 1
Reports and Drawings
6
422
Limited Reliance by CONTRAC
TORAuthorized Technical
Data
6
4 2 3
Notice of Differing Subsurface
or Physical Conditions
6
42 4
ENGINEER s Review
6
42 5
Possible Contract Documents
Change
6
4 2 6
Possible Price and Times
Adjustments
67
43
Physical Conditions Underground
Facilities
7
43 1
Shown or Indicated
7
43 2
Not Shown or Indicated
7
44
Reference Points
7
EICD(, GENERAL CONDITIONS 1910 8 (1990 EDITION)
w/ CITY OF FORT COLLINS MODIFICATIONS (REV 9/99)
Article or Paragraph
Page
Article or Paragraph
Page
Number & Title
Number
Number &
Title
Number
45
Asbestos, PCBs Petroleum
625
Submittal Proceedures CON
Hazardous Waste or
TRACTOR Review Prior
Radioactive Material
7 8
to Shop Drawing or Sample
Submittal
16
5 13ONDS AND INSURANCE
8
626
Shop Drawing & Sample Submit
51 52
Performance Payment and Other
talc Review by ENGINEER
16-17
Bonds
8
627
Responsibility for Variations
53
Licensed Sureties and Insurers
From Contract Documents
17
Certificates of Insurance
8
628
Related Work Performed Prior
54
CONTRACTOR s Liability
to ENGINEER s Review and
Insurance
9
Approval of Required
55
OWNER s Liability Insurance
9
Submittals
17
56
Property Insurance
9 10
629
Contmmng the Work
17
57
Boiler and Machinery or Addi
630
CONTRACTORS General
tional Property Insurance
10
Warranty and Guarantee
17
58
Notice of Cancellation Prousion
10
631 633
Indemnification
17 18
59
CONTRACTOR s Responsibility
634
Survival of Obligations
18
for Deductible Amounts
10
510
Other Special Insurance
10
7 OTHER WORK
18
5 11
Waiver of Rights
11
71 73
Related Work at Site
18
5 12 5 13
Receipt and Application of
74
Coordmatiorl
18
Insurance Proceeds
10 11
514
Acceptance of Bonds and Insa
8 OWNER S
RESPONSIBILITIES
18
ance Option to Replace
11
8 1
Communications to CON
5 15
Partial Utilization Property
TRACTOR
18
Insurance
11
82
Replacement of ENGINEER
18
83
Furnish Data andPay Promptly
5 CONTRACTORS
RESPONSIBILITIES
11
When Due
18
6 1 6 2
Supervision and Superintendencg
11
84
Lands and Easements Reports
6 3 6 5
Labor Materials and Equipment
11 12
and Tests
18 19
66
Progress Schedule
12
85
Insurance
19
67
Substitutes and Or Equal Items
86
Change Orders
19
CONTRACTOR s Expense
87
Inspections Tests and
Substitute Construction
Approvals
19
Methods or Procedures
88
Stop or Suspend Work
ENGINEERS Evaluation
1213
Terminate CONTRACTORS
68611
Concerning Subcontractors
Services
19
Suppliers and Others
89
Limitations on OWNER S
Waiver of ILghts
13 14
Responsibilities
19
6 12
Patent Fees and Royalties
14
810
Asbestos PCBs Petroleum
613
Permits
14
Hazardous Waste or
614
Laws and Regulations
14
Radioactive Material
19
615
Taxes
14 15
8 11
Evidence of Financal
616
Use of Premises
15
Arrangements
19
617
Site Cleanliness
15
618
Safe Structural Loading
15
9 ENGINEERS STATUS DURING
619
Record Documents
15
CONSTRUCTION
19
620
Safety and Protection
15 16
91
OWNER s Representative
19
621
Safety Representative
16
92
Visits to Site
19
622
Hazard Communication Programs
16
93
Project Representative
19 21
623
Emergencies
16
94
Clarifications and Interpre
624
Shop Drawings and Samples
16
tations
21
95
Authorized Variations in Vbrk
21
ETCDC GENERAL CONDITIONS 1910 8 (1990 EDITION)
w/ CITY OF FORT COLLINS MODIFICATIONS (REV 9/99)
Article or Paragraph
Page
Article or Paragraph
Page
Number & Title
Number
Number & Title
Number
96
Rejecting Defective Work
21
138 139
Uncovering Work at ENGI
9799
Shop Dmwmgs, Change Orders
NEER s Request
2728
and Payments
21
1310
OWNER May Stop the Work
28
910
Determinatms for Unit Prices
21 22
1311
Correction or Removal of
911 912
Decisions on Disputes ENGI
Defective Work
28
NEER as Initial Interpreter
z2
13 12
Correction Period
28
913
Limitations on ENGINEER s
13 13
Acceptance of Defective Work
28
Authority and Responsibilities
2223
1314
OWNER May Correct Defective
Work
2829
CHANGES IN THE WORK
23
101
OWNERS Ordered Change
23
14 PAYMENTS TO CONTRACTOR AND
102
Claim for Adjustment
23
COMPLETION
29
103
Work Not Required by Contact
141
Schedule of Values
29
Documents
23
142
Application for Progress
104
Change Orders
23
Payment
29
10 5
Notification of Surety
23
143
CONTRACTORS Warranty of
Title
29
CHANGE OF CONTRACT PRICE
z3
144 147
Review of Applicatims, for
11 1 113
Contract Price Claim for
Progress Payments
2930
Adjustment Value of
148 149
Substantial Completion
30
the Work
23 24
1410
Partial Utilization
3031
11 4
Cost of the Work
2425
1411
Final Inspecticq
31
11 5
Exclusions to Cost of the Work
25
1412
Final Application for Payment
31
116
CONTRACTORS Fee
25
1413 14 14
Final Payment and Acceptance
31
11 7
Cost Records
2526
1415
Waiver of Claims
3132
11 8
Cash Allowances
26
119
Unit Price Work
26
15 SUSPENSION OF WORK AND
TERMINATION
32
CHANGE OF CONTRACT TIMES
26
151
OWNER May Suspend Work
32
121
Claim for Adjustment
26
152 154
OWNER May Terminate
32
122
Time of the Essence
26
155
CONTRACTOR May Stop
123
Delays Beyond CONTRACTORS
Work or Terminate
3233
Control
2627
124
Delays Beyond OWNERS and
16 DISPUTE RESOLUTION
33
CONTRACTORS Control
27
17 MISCELLANEOUS
33
TESTS AND
INSPECTIONS CORRECTION
171
Giving Notice
33
REMOVAL OR ACCFPTANCE OF
172
Computation of Times
33
DEFECTIVE
WORK
27
173
Notice of Clam
33
131
Notice of Defects
27
174
Cumulative Remedies
33
13 2
Access to the Work
27
175
Professional Fees and Court
133
Tests and Inspections
Costs Included
33
CONTRACTOR s Cooperation
27
176
Applicable State Laws
3334
13 4
OWNERS Responsibilities
Intentionally
left blank
35
Independent Testing Laboratory
27
135
CONTRACTORS
EXHIBIT GC A
(Optional)
Responsibilities
27
Dispute Resolution Agreement GC
Al
136 13 7
Covering Work Prior to Inspec
16 1 16 6
Arbitration GC
Al
tion Testing or Approval
27
167
Mediation GC
Al
EJCDC GENERAL CONDITIONS 1910 8 (1990 EDITION)
w/ CITY OF FORT COLLINS MODIFICATIONS (REV 9/99)
INDEX TO GENERAL CONDITIONS
City of Fort Collins modifications to the General Conditions of the Construction Contract are not shown in this index
Article or Paragraph
Number
Acceptance of
Bonds and Insurance
514
defective Work
1041 135 1313
final payment
912, 1415
insurance
5 14
other Work, by CONTRACTOR
73
Substitutes and Or Equal Items 6 7 1
Work by OWNER
25 630 634
Access to the
Lands OWNER and CONTRACTOR
responsibilities
41
site related Wok
72
Work,
132 1314 149
Acts or Omissions Acts and Omissions
CONTRACTOR
691 9133
ENGINEER
620 9 13 3
OWNER
020 89
Addenda definition of (also see
definition of Specifications)
(1 6 1 10 6 19) 1 1
Additional Property Insurances
57
Adjustments
Contract Price or Contract
Times 15
35 41 432 452
453 94 95 102104
11 12 148 15 1
progress schedule
66
Agreement
definition of
12
All Risk Insurance policy form
562
Allowances Cash
118
Amending Contract Documents
35
Amendment Written
in general 1 10 1 45
3 5 5 10 5 12 6 6 2
682 619 101 104 112
121 13122 1472
Appeal OWNER or CONTRACTOR
intent to 9 10 9 11 10 4 16 2 16 5
Application for Payment
definition of
13
ENGINEERS Responsibility
99
tnnal payment 9 13 4
9 13 5 14 12 14 15
in general 2 8 2 9 5 6 4 9 10 15 5
progress payment
141 147
review of
144 147
Arbitration
161 166
Asbestos
clams pursuant thereto
452 45 3
CONTRACTOR authorized to stop Work 4 52
definition of
14
Article or Paragraph
Number
OWNER responsibility for
451 810
possible price and times change
452
Authorized Variations in Work
36 625 627 95
Availability of Lands
41 84
Award, Notice of defined
125
Before Starting Construction
25 2 8
Bid —definition of 15 (1 1 110 2 3 3 3
4264 613 1143 1191)
Bidding Documents definition
of
1 6 (6 8 2)
Bidding Requirements definition
of
17(11 4262)
Bonds
acceptance of
5 14
additional bonds
105 11459
Cost of the Work
1154
definition of
) 8
delivery of
21 5 1
final Application for Payment
1412 1414
general
110 5 1 5 3 5 13
913 105 1476
Performance Payment and Other
5 1 5 2
Bonds and Insurance in general
5
Budder s risk all risk policy form
5 6 2
Cancellation Provisions Insurance
5411 58 5 15
(,ash Allowances
11 8
Certificate of Substantial Completion
138 63023
148 1410
Certificates of Inspection
9 134 135 1412
Certificates of Insurance 27
53 5 4 11 54 13
565 58
514 9 13 4 1412
Change in Contract Price
Cash Allowances
118
claim for price
adjustment 4 1 4 2 6
4 5 515 6 8 2 9 4
95 911 102
105 112 139
13 13 13
14 14 7 151 155
CONTRACTOR s fee
116
Cost of the Work
general
114 117
Exclusions to
115
Cost Records
117
in general 1 19 144 9 11
10 4 2 1043 11
Lump Sum Prncng
11 3 2
Notification of Surety
105
Scope of
103 104
Testing and Inspection
Uncovering the Work
139
ErCDC GENERA. CONDITIONS 1910 8 (1990 EDITION)
w/ CITY OF FORT COLLINS MODIFICATIONS (REV 9/99)
Unit Price Work
119
CONTRACTORS Fee
116
Article or Paragraph
Article or Paragraph
Number
Number
Value of Work
113
CONTRACTOR s liability 54
612,616 631
Change in Contract Times
Cost of the Work
114 115
Claim for tim es adlustm en1
41 426 45 5 15
Decisions on Disputes
911 912
6 8 2, 9 4 9 5 9
11 10 Z 10 5 121
Dispute Resolution
161
13 9 13 13 13 14 14 7 15 1 155
Dispute Resolution Agreement
16 116 6
Contractual time lmi its
122
ENGINEER as initial interpretol
911
Delays beyond CONTRACTORS
Lump Sum Pricing
1132
control
123
Notice of
173
Delays beyond OWNERS and
OWNERS 9 4 9 5 9 11
10 2 112 119
CONTRACTORS control
124
12 1 13 9 13
13 13 14 173
Notification of surely
105
OWNER s liability
55
Scope of change
103 104
OWNER may refuse to make payment
347
Change Orders
Professional Foes and Court Costs
Acceptance ofD%cave Work
13 13
Included
175
Amending Contract Documents
35
request for formal decision on
911
Cash AI lowances
118
Substitute Items
6 7 1 2
Change of Contract Price
11
Time Extension
121
Change of Contract Times
12
Time requirements
911 121
Changes in the Work
10
Unit Price Work
1193
CONTRACTORs Fee
116
Value of
113
Cost of the Work
114 11 7
Waiver of on Final Payment
1414 1415
Cost Records
117
Work Change Directive
102
definition of
1 9
written notice required
911 112 121
emergencies
023
Clarifications and Interpretations
363 94 911
ENGINEER s responsibility
98104 112 121
Clean Site
017
execution of
104
Codes of Technical Society Organization
Indemmfiction 612 616 631633
or Association
333
Insurance Bonds and
5 10 5 13 105
Commencement of Contract Times
23
OWNER may tennmate
152154
Communications
OWNER s Responsibility
86 104
general
6 2 692 81
Physical Conditions
Hazard Communication Programs
622
Subsurface and,
42
Completion
Underground Facilities
4 3 2
Final Application for Payment
1412
Record Documents
619
Final Inspection
1411
Scope of Change
103 104
Final Payment and Acceptance
1413 1414
Substitutes
673 6 8 2
Partial Utilization
1410
Unit Price Work
119
Substantial Completion
1 38 148 149
value of Work, covered by
113
Waiver of Claims
1415
Changes in the Work
10
Computation of Times
17211722
Notification of surety
105
Concerning Subcontractors Suppliers
OWNERS and CONTRACTOR,
and Others
68611
responsibilities
104
Conferences
Right to an adjustment
102
initially acceptable schedules
29
Scope of change
103 104
preconstruction
28
Claims
Conflict Error Ambiguity Discrepancy
against CONTRACTOR
616
CONTRACTOR to Report
25 3 32
against ENGINEER
632
Construction before starting by
against OWNER
632
CONTRACTOR
2 5 2 7
Change of Contract Price
94 112
Construction Machinery Equipment etc
64
Change of Contract Tunes
94 121
Continuing the Work
629 104
CONTRACTORS 4 71 94 95 911 102
Contract Documents
11 2 11
9 12 1 13 9 148
Amending
35
151 155 173
Bonds
51
EXEC GENERAL CONDITIONS
1910 S (1990 EDITION)
w/ CITY OF FORT COLLINS MODIFICATIONS (REV 9/99)
Cash Allowances ] 1 8 Stop Work requirements 452
CONTRACTORS —
Article or Paragraph
Number
Change of Contract Price 1 I
Change of Contract Times 12
Changes in the Work 104 105
check and verify 25
Clarifications and
Interpretations 32 36 94 911
definition of
1 10
ENGINEER as initial interpreter of
911
ENGINEER as OWNERS representative
91
general3
Insurance
53
Intent
31 34
minor variations in the Work
36
OWNERS responsibility to furnish data
83
OWNERS responsibility to make
prompt payment 83
144 1413
precedence
3 1 3 3 3
Record Documents
619
Reference to Standards and Specifications
of Technical Societies
33
Related Work
72
Reporting and Resolving Discrepancies
25 33
Reuse of
37
Supplementing
3 6
Termmation of ENGINEER s Employment
82
Unit Price Work
119
variations 36 623
627
Visits to Site ENGINEERS
92
Contract Price
adjustment of 35 41 94 103 112
113
Change of
I I
Decision on Disputes
911
definition of
1 11
Contract Times
adlustm ent of
3 5 4 1 9 4 10 3 12
Change of
121 124
Commencement of
23
definition of
1 12
CONTRACTOR
Acceptance of Insurance
5 14
Communications
62 6 9 2
Continue Work
629 104
coordination and scheduling
692
definition of
1 13
Limited Reliance on Technical
Data Authorized
4 2 2
May Stop Work or Term mate
155
provide site access to others
72 132
Safety and Protection
43 12 6 16 618
621 623 72 132
Shop Drawing and Sample Review
Prior to Submittal
vu
6 25
Article or Paragraph
Number
Compensation
11 1 112
Continuing Obligation
1415
Defective Work 96
13 10-13 14
Duty to correct defective Work
1311
Duty to Report
Changes in the Work caused by
Emergency
623
Defects in Work of Others
73
Differmg conditions
423
Discrepancy in Documents 25 332
6 14 2
Underground Facilities not indicated
432
Emergencies
623
Equipment and Machinery Rental Cost
of the Work
11453
Fee Cost Plus 114 5 6
115 1 116
General Warranty and Guarantee
630
Hazard Communication Programs
622
Indemnification 6 1 Z 616 631 633
Inspection of the Work
73 134
Labor Materials and Equipment
6 3 6 5
Laws and Regulations, Compliance by
6 14 1
Liability Insurance
54
Notice of Intent to Appeal
910 104
obligation to perform and complete
the Work
630
Patent Fees and Royalties paid for by
612
Performance and Other Bonds
5 1
Permits obtained and paid for by
4 13
Progress Schedule 26 28
29 66
629 104
1521
Request for formal decisionon disputes
911
Responsibilities
Changes in the Work
101
Concerning Subcontractors Suppliers
and Others
68611
Continuing the Work
629 104
CONTRACTOR s expense
67 1
CONTRACTOR s General Warranty
and Guarantee
630
CONTRACTOR s review prior to Shop
Drawing or Sample submittal
625
Coordination of Work
692
Emergencies
623
ENGINEERS evaluation Substitutes
or Or Equal Items
6 7 3
For Acts and Omissions
of Others 6 9 1 692 913
for deductible amounts insurance
59
general 6 72
73 89
Hazardous Communication Programs
622
Indemnification
631633
EJCDC GENERAL CONDITIONS 1910 8 (1990 EDITION)
w/ CITY OF FORT COLLINS MODIFICATIONS (REV 9/99)