HomeMy WebLinkAbout109445 CONNELL RESOURCES INC - CONTRACT - BID - 5482 ASPHALT OVERLAY PROJECT 2000 (28)I
0
0
rN
0
1)
0
Contract Times by the submission of a bid or
becoming bound under a negotiated contract,
or
42.6.4.2. the existence of such condition
could reasonably have been discovered or
revealed as a result of any examination,
investigation, exploration, test or study of the
site and contiguous areas required by the
Bidding Requirements or Contract Documents
to be conducted by or for CONTRACTOR
prior to CONTRACTOR's making such final
commitment; or
426.4.3. CONTRACTOR failed to give the
written notice within the time and as required
by paragraph 4 2.3.
If OWNER and CONTRACTOR are unable to agree on
entitlement to or as to the amount or length of any such
equitable adjustment in the Contract Price or Contract
Times, a claim may be made therefor as provided in
Articles I and 12 However, OWNER, ENGINEER and
ENGP,1EER's Consultants shall not be liable to
CONTRACTOR for any claims, costs, losses or damages
sustained by CONTRACTOR on or in connection with
any olher project or anticipated project.
4.3. Physical Conditions —Underground Facilities:
4.3 1 Shown orindicated: The information and data
shown or indicated in the Contract Documents with
respect to existing Underground Facilities at or
contiguous to the site is based on information and data
furnished to OWNER or ENGINEER by the owners of
such Underground Facilities or by others. Unless it is
otherwise expressly provided in the Supplementary
Conditions.
4 3 1.1 OWNER and ENGINEER shall not be
responsible for the accuracy or completeness of
any such information or data, and
4 3.1.2 The cost of all of the following will be
included in the Contract Price and
CONTRACTOR shall have full responsibility for
(i) reviewing and checking all such information
and data, (ii) locating all Underground Facilities
shown or indicated in the Contract
Documents,(iii) coordination of the Work with the
owners of such Underground Facilities during
construction, and (iv) the safety and protection of
all such Underground Facilities as provided in
paragraph 6 20 and repairing any damage thereto
resulting from the Work.
4.3.2. Not Shown or Indicated: If an Underground
Facility is uncovered or revealed at or contiguous to
the site which was not shown or indicated in the
Contract Documents, CONTRACTOR shall, grexrptij
immediately after becoming aware thereof and before
further disturbing conditions affected thereby or
performing any Work in connection therewith (except
in an emergency as required by paragraph 6.23),
identify the owner of such Underground Facility and
give written notice to that owner and to OWNER and
ENGINEER. ENGINEER will promptly review the
Underground Facility and determine the extent, if any,
to which a change is required in the Contract
Documents to reflect and document the consequences
of the existence of the Underground Facility. If
ENGINEER concludes that a change in the Contract
Documents is required, a Work Change Directive or
a Change Order will be issued as provided in
Article 10 to reflect and document such consequences
During such time, CONTRACTOR shall be
responsible for the safety and protection of such
Underground Facility as provided in paragraph 6.20.
CONTRACTOR shall may be allowed an increase in
the Contract Price or an extension of the Contract
Times, or both, to the extent that they are attributable
to the existence of any Underground Facility that was
not shown or indicated in the Contract Documents and
that CONTRACTOR did not know of and could not
reasonably have been expected to be aware of or to
have anticipated If OWNER and CONTRACTOR are
unable to agree on entitlement to or the amount or
length of any such adjustment in Contract Price or
Contract Times, CONTRACTOR may make a claim
therefor as provided in Articles 11 and 12. However,
OWNER, ENGINEER and ENGINEER's Consultants
shall not be liable to CONTRACTOR for any claims,
costs, losses or damages incurred or sustained by
CONTRACTOR on or in connection with any other
project or anticipated project.
Reference Points:
44 OWNER shall provide engineering surveys to
establish reference points for construction which in
ENGINEER's judgment are necessary to enable
CONTRACTOR to proceed with the Work.
CONTRACTOR shall be responsible for laying out the
Work, shall protect and preserve the established reference
points and shall make no changes or relocations without
the prior written approval of OWNER. CONTRACTOR
shall report to ENGINEER -whenever any reference point
is lost or destroyed or requires relocation because of
necessary changes in grades of locations, and shall be
responsible for the accurate replacement or relocation of
such reference points by professionally qualified
personnel.
4.5. Asbestos, PCBs, Petroleum, Hazardous Waste or
Radioactive Material;
4 5 1 OWNER shall be responsible for any
Asbestos, PCBs, Petroleunn, Hazardous Waste or
Radioactive Material uncovered or revealed at the site
which was not shown or indicated in Drawings or
Specifications or identified in the Contract Documents
to be within the scope of the Work and which may
present a substantial danger to persons or property
exposed thereto in connection with the Work at the
site OWNER shall not be responsible for any such
materials brought to the site by CONTRACTOR,
Subcontractors, Suppliers or anyone else for whom
CONTRACTOR is responsible.
gi
EJCDC GENERAL CONDITIONS 1910-8 (1990 Edition)
w/ CITY OF FORT COLLINS MODIFICATIONS (REV 9/94)