HomeMy WebLinkAbout109445 CONNELL RESOURCES INC - CONTRACT - BID - 5482 ASPHALT OVERLAY PROJECT 2000 (23)1.20. General Requirements --Sections of Division 1 of
the Specifications.
of 1954 (42 USC Section 2011 et seq) as amended from
time to time
1.21. Hazardous Waste --ThetermHazardousWaste shall
have the meaning provided in Section 1004 of the Solid
Waste Disposal Act (42 USC Section 6903) as amended
from time to time.
1 22 a Laws and Regulations; Laws orRegulations--Any
and all applicable laws, rules, regulations, ordinances,
codes and orders of any and all governmental bodies,
agencies, authorities and courts havinS jurisdiction.
I1 22 b Legal Holidays --shall be those holidays
observed by the City of Fort Collins.
1.23. Liens --Liens, charges, security interests or
encumbrances upon real property or personal property
1.24. Milestone --A principal event specified in the
Contract Documents relating to an intermediate
completion date or time prior to Substantial Completion
of all the Work
1.25 Notice of A ward --A written notice by OWNER to
the apparent successful bidder stating that upon
compliance by the apparent successful bidder with the
conditions precedent enurr-rated therein, within the time
specified, OWNER will sign and deliver the Agreement
1.26. Notice to Proceed --A written notice given by
OWNER to CONTRACTOR (with a copy to ENGINEER)
fixing the date on which the Contract Times will
commence to run and on which CONTRACTOR shall
start to perform CONTRACTOR'S obligations under the
Contract Documents
1.27. OWNER --The public body or authority,
corporation, association, firm or person with whom
CONTRACTOR has entered into the Agreement and for
whom the Work is to be provided
1.28. Partial Utilization --Use by OWNER of a
substantially completed part of the Work for the purpose
for which it is intended (or a related purpose) prior to
Substantial Completion of all the Work.
1.29. PCBs --Polychlorinated biphenyls.
1.30 Petroleum --Petroleum, including crude oil or any
fraction thereof which is liquid at standard conditions of
temperature and pressure (60 degrees Fahrenheit and
14 7 pounds per square inch absolute), such as oil,
petroleum, fuel oil, oil sludge, oil refuse, gasoline,
kerosene and oil mixed with other non -Hazardous Wastes
and crude oils.
1.31. Project --The total construction of which the Work
to be provided under the Contract Documents may be the
whole, or a part as indicated elsewhere in the Contract
Documents
j 1.32 a. Radioactive Materfal--Source, special nuclear, or
byproduct material as defined by the Atomic Energy Act
1 32 b Reeular Workine Hours--Reuular working hours
are defined as 7 OOam to 6 OOpm unless otherwise
specified in the General Requirements.
133 Resident Project Representative --The authorized
representative of ENGINEER who may be assigned to the
site or any part thereof.
1.34 Samples --Physical examples of materials,
equipment, or workmanship that are representative of some
portion of the Work and which establish the standards by
which such portion of the Work will be judged.
135. Shop Drawings --All drawings, diagrams,
illustrations, schedules and other data or information
which are specifically prepared or assembled by or for
CONTRACTOR and submitted by CONTRACTOR to
illustrate some portion of the Work
136 Specifications --Those portions of the Contract
Documents consisting of written technical descriptions of
materials, equipment, construction systems, standards and
workmanship as applied to the Work and certain
administrative details applicable thereto
I 37 Subcontractor --An individual, firm or corporation
having a direct contract with CONTRACTOR or with any
other Subcontractor for the performance of a part of the
Work at the site
1 38 Substantial Completion --The Work (or a specified
part thereof) has progressed to the point where, in the
opinion of ENGINEER as evidenced by ENGINEER's
definitive certificate of Substantial Completion, it is
sufficiently complete, in accordance with the Contract
Documents, so that the Work (or specified part) can be
utilized for the purposes for which it -is intended; or if no
such certificate is issued, when the Work is complete and
ready for final payment as evidenced by ENGINEER's
written recommendation of final payment in accordance
with paragraph 14 13 The terms "substantially complete"
and "substantially completed" as applied to all or part of
the Work refer to Substantial Completion thereof.
139. Supplementary Conditions --The part of the
Contract Documents which amends or supplements these
General Conditions
140 Suppher--A manufacturer, fabricator, supplier,
distributor, materialman or vendor having a direct contract
with CONTRACTOR or with any Subcontractor to furnish
materials or equipment to be incorporated in the Work by
CONTRACTOR or any Subcontractor.
1.41. Underground Facilities —All pipelines, conduits,
ducts, cables, wires, manholes, vaults, tanks, tunnels or
other such facilities or attachments, and any encasements
containing such facilities which have been installed
underground to furnish any of the following services or
materials: electricity, gases, steam, liquid petroleum
products, telephone or other communications, cable
EJCDC GENERAL CONDITIONS I910.8 (1990 Edition)
w/ CITY OF FORT COLLINS MODIFICATIONS (REV 9/94)