Loading...
HomeMy WebLinkAboutBID - 5512 DOWNTWON STREETSCAPE PHASE IDOWNTOWN STREETSCAPF PHASE I D j BID OPENING: PURCHASING DIVISION 256 WEST MOUNTAIN AVE., FORT COLLINS JUNE 26, 2000 - 3:OOP.M. (Our Clock) No Text No Text TABLE OF CONTENTS OF GENERAL CONDITIONS Article or Paragraph Page Article or Paragraph Number & Title Number Number & Title DEFINITIONS 1 1 Addenda 1 12 Agreement 1 1 3 Application for Payment I 14 Asbestos _ 1 1 5 Bid _ _ 1 1 6 Bidding Documents I 1 7 Bidding Requirements_ „ I 18 Bonds 1 19 Change Order 1 1 10 Contract Documents, _ 1 1 11 Contract Price 1 1 12 Contract Times _ 1 113 CONTRACTOR ,. 1 114 defective I 115 Drawings I 1 16 Effective Date of the Agreement l 117 ENGINEER 1 1 18 ENGINEER's Consultant I 1 19 Field Order I 1.20 General Requirements .2 1 21 Hazardous Waste 2 1 22 a Laws and Regulations, Laws or Regulations _ 2 1 22 b Legal Holidays 2 123 Liens 2 1 24 Milestone. 2 1 25 Notice of Award „ 2 1 26 Notice to Proceed „ 2 127 OWNER , , 2 1 28 Partial Utilization . .. .... ... 2 129 PCBs „ 2 L30 Petroleum , , „ 2 1 31 Project , , „ _ „ 2 1 32 a Radioactive Material ,2 1 32 b Regular Working Hours 2 133 Resident Project Representative, 2 134 Samples „ 2 1.35 Shop Drawings „ .2 136 Specifications,_, .. _ 2 1 37 Subcontractor ,., , .2 1 38 Substantial Completion, 2 1 39 Supplementary Conditions 2 1 40 Supplier _ _2 1 41 Underground Facilities 2-3 1 42 Unit Price Work 3 143 Work 3 1.44 Work Change Directive 3 1 45 Written Amendment 3 Page Number 2 PRELIMINARY MATTERS. _ , ,,,, „ , „3 21 Delivery of Bonds. 2.2 Copies of Documents 23 Commencement of Contract Times, Notice to Proceed 3 24 Starting the Work 3 2 5-2 7 Before Starting Construction, CONTR.ACTOR's Responsibility to Report, Preliminary Schediles, Delivery of Certificates of Insurance ,_ _ ___„ 3-4 2 8 Preconstruction Conference , 4 29 Initially Acceptable Schedules ,4 3. CONTRACT DOCUMENTS INTENT, AMENDING, REUSE „ 4 3 1-3.2 Intent „ 4 33 Reference to Standards and Speci- fications of Technical Societies, Reporting and Resolving Dis- crepancies , 4-5 34 Intent of Certain Terms or Adjectives 5 3 5 Amending; Contract Documents 5 3 6 Supplementing Contract Documents „ .5 37 Reuse of Documents 5 4. AVAILABILITY OF LANDS, SUBSURFACE AND PHYSICAL CONDITIONS, REFERENCE POINTS „ 5 41 Availability of Lands „5-6 42 Subsurface and Physical Conditions„ 6 42 1 Reports and Drawings, , 6 4 2 2 Limited Reliance by CONTRAC- TOR Authorized, Technical Data 6 4 2 3 Notice of Differing Subsurface or Physical Conditions, 6 424 ENGINEER's Review „ , 6 4 2 5 Possible Contract Documents Change ,6 4 2 6 Possible Price and Times Adjustments_ _ , , 6-7 43 Physical Conditions --Underground Facilities „ 7 43 1 Shown or Indicated, 7 4 3 2 Not Shown or Indicated 44 Reference Points. „ 7 u EJCDC GENERAL CONDITIONS 1910-8 (1990 EDITION) w/ CiTY OF FORT COLLINS MODIFICATIONS (REV 9/99) Article or Paragraph Page Article or Paragraph Page Number & Title Number Number & Title Number 45 Asbestos, PCBs, Petroleum, 625 Submittal Proceedures, CON - Hazardous Waste or TRACTOR'S Review Prior Radioactive Material 7-8 to Shop Drawing or Sample Submittal. .16 5 BONDS AND INSURANCE 8 626 Shop Drawing & Sample Submit- 5 1-5 2 Performance, Payment and Other tals Review by ENGINEER 16-17 Bonds 8 627 Responsibility for Variations 5 3 Licensed Sureties and Insurers, From Contract Documents -.... , 17 Certificates of Insurance .8 628 Related Work Performed Prior 5 4 CONTRACTOR'S Liability to ENGINEER's Review and Insurance 9 Approval of Required 5 5 OWNER's Liability Insurance 9 Submittals ,-, .17 5 6 Property Insurance . 9-10 629 Continuing the Work 17 5 7 Boiler and Machinery or Addi- 630 CONTRACTOR's General tional Property Insurance. 10 Warranty and Guarantee, , 17 5 8 Notice of Cancellation Promsion 10 6 31-6 33 Indemnification „ - 17-18 5 9 CONTRACTOR's Responsibility 634 Survival of Obligations 18 for Deductible Amounts 10 5 10 Other Special Insurance 10 7. OTHER WORK ..18 5 11 Waiver of Rights 11 7 1-7 3 Related Work at Site 18 5 12-5 13 Receipt and Application of 7 4 Coordination 18 Insurance Proceeds 10-11 5 14 Acceptance of Bonds and Insu- 8 OWNER'S RESPONSIBILITIES 18 ance, Option to Replace 11 8 1 Communications to CON- 5 15 Partial Utilization --Property TRACTOR ,..18 Insurance ,„ 11 8 2 Replacement of ENGINEER 18 8 3 Furnish Data andPay Promptly 6 CONTRACTOR'S RESPONSIBILITIES 11 When Due 18 6 1-6 2 Supervision and Superintendence 11 8 4 Lands and Easements, Reports 6 3-6 5 Labor, Materials and Equipment 11-12 and Tests .18-19 6 6 Progress Schedule 12 8 5 Insurance, 19 6 7 Substitutes and "Or -Equal" Items, 8 6 Change Orders -„ „ ,..19 CONTRACTOR'S Expense, 8 7 Inspections, Tests and Substitute Construction Approvals 19 Methods or Procedures; 8 8 Stop or Suspend Work; ENGINEER's Evaluation 12-13 Terminate CONTRACTOR's 6 8-6.11 Concerning Subcontractors, Services 19 Suppliers and Others, 8 9 Limitations on OWNER'S Waiver of Rights . . , , . J3-14 Responsibilities „ „ 19 6 12 Patent Fees and Royalties 14 8 10 Asbestos, PCBs, Petroleum, 6 13 Permits 14 Hazardous Waste or 6 14 Laws and Regulations 14 Radioactive Material, , „ 19 6 15 Taxes 14-15 8 11 Evidence of Financial 6 16 Use of Premises „ 15 Arrangements ... . ..... „ 19 6 17 Site Cleanliness 15 6 18 Safe Structural Loading 15 9 ENGINEER'S STATUS DURING 6.19 Record Documents - 15 CONSTRUCTION ...... .... 19 620 Safety and Protection 15-16 9 1 OWNER's Representative , -. -.. 19 6.21 Safety Representative 16 9 2 Visits to Site 19 622 Hazard Communication Programs 16 9 3 Project Representative, 19-21 623 Emergencies 16 9 4 Clarifications and Interpre- 6 24 Shop Drawings and Samples 16 tations , 21 9 5 Authorized Variations in Rork 21 u EJCDC GENERAL CONDITIONS 1910-8 (1990 EDITION) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 9/99)r_� U Article or Paragraph Page Article or Paragraph Page Number & Title Number Number & Title Number 96 Rejecting Defective Work .21 13 8-13 9 Uncovering Work at ENGI- 9 7-9 9 Shop Drawings, Change Orders and Payments ,,,, 21 13.10 NEER's Request OWNER May Stop the Work, , 27-28 „ , 28 9 10 Determinatims for Unit Prices _, 21-22 13,11 Correction or Removal of 9 11-9 12 Decisions on Disputes, ENGI- Defective Work„ 28 NEER as Initial Interpreter 22 13 12 , Correction Period „ , „ , „ , , ,,, , „ ,28 913 Limitations on ENGINEER's 13.13 Acceptance of Defective Work„ ,28 Authority and Responsibilities,,, 22-23 13 14 OWNER May Correct Defective Work CHANGES IN THE WORK 23 10 1 OWNER's Ordered Change _23 14 PAYMENTS TO CONTRACTOR AND 102 103 Claim for Adjustment Work Not Required by Contract 23 COMPLETION _ , , . . .:...:.. .. . 141 Schedule of Values 29 29 Documents 23 142 Application for Progress 104 Change Orders_ _ ..... 23 Payment _ 10 5 Notification of Surety 23 143 CONTRACTOR's Warranty of ,29 Title „ ,,.29 CHANGE OF CONTRACT PRICE 23 14 4-14 7 Review of Applications for 11 1-11 3 Contract Price, Claim for Progress Payments . , ,,, 29-30 Adjustment, Value of 14 8-14 9 Substantial Completion,,, , 30 the Work „ 23-24 14 10 Partial Utilization 30-31 114 11 5 Cost of the Work Exclusions to Cost of the Work 24-25 25 1411 14 12 Final Inspection , „ Final Application for Payment _31 31 11 6 CONTRACTOR's Fee 25 14 13-14 14 Final Payment and Acceptance, . ,,, 31 11 7 Cost Records,,, 14 15 Waiver of Claims, 11 8 „ , „ _ _ ,,,,,25-26 Cash Allowances 26 , „ , , ,31-32 11.9 Unit Price Work„ ­.,26 15 SUSPENSION OF WORK AND TERMINATION _ _ 32 CHANGE OF CONTRACT TIMES _ 12 1 Claim for Adjustment „ 26 26 15 1 15 2-15 4 OWNER May Suspend Work„ OWNER May Terminate 32 32 122 Time of the Essence „ 26 15 5 CONTRACTOR May Stop 123 Delays Beyond CONTRACTOR'S Control 26-27 Work or Terminate, 32-33 124 Delays Beyond OWNER's and 16 DISPUTE RESOLUTION , , „ „ , , 33 CONTRACTOR's Control _ 27 , , 17 MISCELLANEOUS „ , .33 TESTS AND INSPECTIONS, CORRECTION, 171 Giving Nolice, „ _ „ 33 REMOVAL OR ACCEPTANCE OF 172 Computation of Times ,..,,, ..... 33 DEFECTIVE WORK „ . „ , 13 1 Notice of Defects , , 27 ,27 17.3 174 Notice of Claim , „ , „ „ , ,: Cumulative Remedies„ , , , 33 .33 112 Access to the Work_. , , 27 17 5 Professional Fees and Court 13 3 Tests and Inspections, CONTRACTOR's Cooperation „ 27 176 Costs Included ,. Applicable State Laws, „ „ .33 33-34 134 OWNER's Responsibilities, Intentionally left blank , „ , , „35 Independent Testing Laboratory, _ 27 13 5 CONTRACTOR's EXHIBIT GC -A (Optional) Responsibilities 27 Dispute Resolution Agreement _ , , „,GC -Al 13 6-13 7 Covering Work Prior to Inspec- 16 1-16 6 Arbitration , , , „ GC -Al tion, Testing or Approval. , _ , 27 167 Mediation „ . GC -Al IV EJCDC GENERAL. CONDITIONS 1910-8 (1990 EDITION) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 9199) INDEX TO GENERAL CONDITIONS City of Fort Collins modifications to the General Conditions of the Construction Contract are not shown in this index Article or Paragraph Number Acceptance of -- Bonds and Insurance, _ _ „ 5.14 defective Work , , 10 4 1, 13 5, 13 13 final payment 9 12, 14 15 insurance 5 14 other Work, by CONTRACTOR _ 73 Substitutes and "Or -Equal" Items 67 1 Work by OWNER ,2 5, 6 30, 6 34 Access to the -- Lands, OWNER and CONTRACTOR responsibilities 41 site, related Work „ 72 Work, 132, 13 14, 149 Acts or Omissions--, Acts and Omissions -- CONTRACTOR 69 1,9 13 3 ENGINEER 6 20, 9 133 OWNER _ 620, 89 Addenda --definition of (also see definition of Specifications) (1 6, 1 10,6 19), 1 1 Additional Property Insurances 5 7 Adjustments— Contract Price or Contract Times 1 5, 3 5, 4 1, 4 3 2, 4 5 2, 4 5 3, 9 4, 9 5, 10 2-10 4, - 11, 12, 14 8, 15 1 progress schedule 66 Agreement -- definition of , , „ 1 2 "All -Risk" Insurance, policy form 5 62 Allowances, Cash , _ _ 11 8 Amending Contract Documents „ „ 3 5 Amendment, Written -- in general 1 10, 1 45, 3 5, 5 10, 5 12, 6 6 2 6 8 2, 6 19, 10 1, 10 4, 112 121, 13 12.2, 1472 Appeal, OWNER or CONTRACTOR intent to _ 9.10, 9 11, 10 4, 16 2, 16 5 Application for Payment -- definition of 13 ENGINEER's Responsibility .99 final payment „ 9 13 4, 9 13 5, 14 12-14 15 in general 2 8, 2.9, 5 6 4, 9 10, 15.5 progress payment 14.1-14 7 review of 14 4-14 7 Arbitration ....16 1-16 6 Asbestos -- claims pursuant thereto _ 452, 45.3 CONTRACTOR authorized to stop Work 4 5 2 definition of, 1.4 Article or Paragraph Number OWNER responsibility for . , . , , 4 5 1, 8 10 possible price and times change , „ , 4 5 2 Authorized Variations in Work , 3 6, 6 25, 6 27, 9 5 Availability of Lands „ _ ,4 1, 84 Award, Notice of --defined , 125 Before Starting Construction „ , ,2 5-2 8 Bid --definition of _ 1 5 (1.1, 1 10, 2 3, 33, 4264,613,1143,1191) Bidding Documents --definition of 1 6 (6 8 2) Bidding Requirements --definition of 17(11,4262) Bonds -- acceptance of 5 14 additional bonds „ 105, 114 5 9 Cost of the Work 11 5 4 definition of 1.8 delivery of ... „ 2 1, 5 1 final Application for Payment _,,, , , , 14 12-14 14 general .1 10, 5.1-5 3, 5 13, ...... „ 9.13, 10 5, 14 7 6 Performance, Payment and Other. $ I-5 2 Bonds and Insurance --in general_ _ 5 Builder's risk "all-risk" policy form .562 Cancellation Provisions, Insurance_ 5 4 11, 5 8, 5 15 Cash Allowances ,_11 8 Certificate of Substantial Completion, ,1 38, 63023, 148, 14.10 Certificates of Inspection 13.4, 13 5, 14 12 Certificates of Insurance „ 2.7, 5 3, 5 4 11, 5 4.13, 5 6 5, 5 8, 5 14, 9 13 4, 14 12 Change in Contract Price -- Cash Allowances „ 118 claim for price adjustment 4 1, 4 2 6, 4 5, 5 15, 6 8 2, 9 4 9 5, 9 11, 10 2, 10 5, 11 2, 13 9, „13.13,1314,147,15.1,155 CONTRACTOR's fee „ 116 Cost of the Work general „ 11.4-117 Exclusions to, 115 Cost Records . ..... „ 117 in general 1 19, 1 44,9 11, 10 4 2, 10.4 3, 11 Lump Sum Pricing 11.32 Notification of Surety _ 105 Scope of, 10 3-10 4 Testing and Inspection, Uncovering the Work „ 139 EJCDC GENERAL CONDITIONS 1910-8 (1990 EDITION) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 9/9S' u Unit Price Work „ „ „ 119 Article or Paragraph Number Value of Work 11 3 Change in Contract Times -- Claim for times adjustment, _ 4 1, 4 2 6, 4 5, 5 15, 6 9 2, 9 4, 9 5, 9 11, 10 2, 10 5, 121, 139,13.13, 1314, 147, 15 1, 15 5 Contractual time limits „ „ 12.2 Delays beyond CONTRACTOR's control 123 Delays beyond OWNER's and CONTRACTOR's control 124 Notification of surety 10 5 Scope of change 10 3-10 4 Change Orders -- Acceptance ofDefectrve Work 13 13 Amending Contract Documents 3 5 Cash Allowances Change of Contract Price „ , 11 8 11 Change of Contract Times „ 12 Changes in the Work 10 CONTRACTOR's fee 11 6 Cost of the Work „ .11 4-11 7 Cost Records 11 7 definition of 1.9 emergencies 623 ENGINEER's responsibility 98, 104, 11 2, 12 1 execution of 10.4 Indemnifiction 6.12, 6 16, 6 31-6 33 Insurance, Bonds and 5 10, 5 13, 105 OWNER may terminate _ _ 15 2-15 4 OWNER's Responsibility 86, 104 Physical Conditions -- Subsurface and, , _ _ 42 Underground Facilities-- ... 4 3 2 Record Documents _ 6 19 Scope of Change 10 3-10 4 Substitutes Unit Price Work _ :, 673, 6 8 2 119 value of Work, covered by _ „ 113 Changes in the Work, Notification of surety, „ _10 „ 105 OWNER's and CONTRACTOR's responsibilities , , , .104 Right to an adjustment 102 Scope of change, 10 3-10 4 Claims -- against CONTRACTOR 6 16 against ENGINEER 632 against OWNER. , 632 Change of Contract Price _ 9 4, 11 2 Change of Contract Times 94, 12 1 CONTRACTOR's 4, 7 1, 9 4, 9 5, 9 11, 10 2, 11 2, 11 9, 12 1, 13 9, 148, 151,155,173 CONTRACTOR's Fee „ ., _ .116 Article or Paragraph Number CONTRACTOWs liability „ , , 5 4, 6 12, 6 16, 6.31 Cost of the Work , _ „ .11.4, 11 5 Decisions on Disputes .....9 11, 9.12 Dispute Resolution „ , „ ....... , 16.1 Dispute Resolution Agreement „ , 16 1-16 6 ENGINEER as initial mterpretor .911 Lump Sum Pricing „ , ..It 32 Notice of , 173 OWNER's, 9 4, 9 5, 9 11, 10 2, 112, 119 12 1, 13 9, 13.13, 13 14, 173 OWNER's liability .55 OWNER may refuse to make payment „ 147 Professional Fees and Court Costs Included , „ 17.5 request for formal decision on 9 11 Substitute Items 67 1.2 Time Extension .121 Time requirements „ 911, 121 Unit Price Work 1193 Value of . .... . 11 3 .. .. .. . Waiver of --on Final Payment 14 14, 14 15 Work Change Directive, 102 written notice required 9 11, 11 2, 12 1 Clarifications and Interpretations _„ 3 6 3, 9A, 9.11 Clean Site 6 17 Codes of Technical Society, Organization or Association_ „ 3 3 Commencement of Contract Times _ „ „ ... 7.3 Communications -- general „ 62,692, 8 1 Hazard Communication Programs , , „ , 622 Completion -- Final Application for Payment_ 14 12 Final Inspection „ ..14.11 Final Payment and Acceptance „ _ 14 13-14.14 Partial Utilization _ 14.10 Substantial Completion 1 38, 14 8-14.9 Waiver of Claims „ _ .14.15 Computation of Times „ „17.2 1-17 2 2 Concerning Subcontractors, Suppliers and Others „ 6 8-6.11 Conferences -- initially acceptable schedules 2 9 preconstruction 28 Conflict, Error, Ambiguity, Discrepancy -- CONTRACTOR to Report .2 5, 3.3 2 Construction, before starting by CONTRACTOR _ 2 5-2 7 Construction Machinery, Equipment, etc _ _, 6 4 Continuing the Work 6 29, 10 4 Contract Documents -- Amending 1 5 Bonds 5.1 EJCDC GENERAL CONDITIONS 1910-8 (1990 EDITION) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 9/99) Cash Allowances - 11 8 Stop Work requirements- - - 4 5 2 CONTRACTOR's— Article or Paragraph Number Change of Contract Price „ -, .11 Change of Contract Times , 12 Changes in the Work , , „ ,- 10 4-10 5 check and verify - - -,--. .25 Clarifications and Interpretations 3 2, 3 6, 9.4, 9.11 definition of . . , -- „ , I'10 ENGINEER as initial interpreter of , , ,-, 9 11 ENGINEER as OWNER's representative .91 general3 Insurance .. 5 3 Intent 3 1-3 4 minor variations in the World , „ 3 6 OWNER'S responsibility to furnish data 8 3 OWNER's responsibility to make prompt payment $ 3, 14 4, 1413 precedence - 3 1, 3 3 3 Record Documents . 6 19 Reference to Standards and Specifications of Technical Societies, „ 3 3 Related Work 7 2 Reporting and Resolving Discrepancies 2 5, 3 3 Reuse of 3 7 Supplementing „ 3 6 Termination of ENGINEER's Employment 8 2 Unit Price Work „ .11 9 variations - 3 6,623, 627 Visits to Site, ENGINEER's ...92 Contract Price -- adjustment of - 3 5, 4.1, 9 4, 10 3, 11 2-11 3 Change of .11 Decision on Disputes „ , 9 11 definition of „ 1.11 Contract Times -- adjustment of - 3 5, 4.1, 9 4, 10.3, 12 Change of „ 12 1-12 4 Commencement of , -- .•-- 2 3 definition of.. , , 1.12 CONTRACTOR -- Acceptance of Insurance, 5.14 Communications , , -, „ - .... , - 6 2, 6 9 2 Continue Work .... 6.29, 104 coordination and scheduling - .692 definition of - 1 13 Limited Reliance on Technical Data Authorized, „ .422 May Stop Work or Terminate - 155 provide site access to others,- 72, 132 Safety and Protection 43 1 2,6 16,6 18, ,-----6.21-6 23, 7 2, 13 2 Shop Drawing and Sample Review Prior to Submittal- ... 025 NO Article or Paragraph Number Compensation „ I1.1-112 Continuing Obligation 14.15 Defective Work , 9 6, 13 10-13.14 Duty to correct defective Work, 13.11 Duty to Report -- Changes in the Work caused by Emergency „ ,- „ 6.23 Defects in Work of Others- , , „ 73 Differing conditions 4 2 3 Discrepancy in Documents. , , 2 5, 3 3 2, 6 14 2 Underground Facilities not indicated 4 3 2 Emergencies 623 Equipment and Machinery Rental, Cost of the Work 11 4 5 3 Fee --Cost Plus 11 4 5 6, 11 5.1, 116 General Warranty and Guarantee 630 Hazard Communication Programs- 6.22 Indemnification ( 12, 6 16, 6 31-6 33 Inspection of the Work ..73, 134 Labor, Materials and Equipment 6 3-6 5 Laws and Regulations, Compliance by 6 141 Liability Insurance „ 54 Notice of Intent to Appeal , „ „ 9 10, 104 obligation to perform and complete the Work 630 Patent Fees and Royalties, paid for by 6.12 Performance and Other Bonds 51 Permits, obtained and paid for by 6 13 Progress Schedule- 2 6, 2 8, 2.9, 6 6, 629, 104, 152.1 Request for formal decisionon disputes, 911 Responsibilities -- Changes in the Work .. -„ , , , ,,,,,, 101 Concerning Subcontractors, Suppliers and Others „ , 6 8-6 11 Continuing the Work , , , , , , 629, 104 CONTRACTOR's expense. 6 7 1 CONTRACTOR's General Warranty and Guarantee 630 CONTRACTOR's review prior to Shop Drawing or Sample submittal .625 Coordination of Work „ , „ 6 9 2 Emergencies - .623 ENGINEER's evaluation, Substitutes or "Or -Equal" Items 6 7 3 For Acts and Omissions of Others 69 1-6 9 2, 9 13 for deductible amounts, insurance , 59 general „ , , 6, 7.2, 7 3, 8 9 Hazardous Communication Programs 622 Indemnification 6 31-6 33 u EJCDC GENERAL CONDITIONS 1910-8 (1990 EDITION) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 9/99)"•_� u X Labor, Materials and Equipment 6 3-6 S Laws and Regulations -- „ „ „ 6 14 Liability Insurance-- 5 4 Article or Paragraph Number Notice of variation from Contract Documents 627 Patent Fees and Royalties -- , 6 12 Permits 6 13 Progress Schedule 66 :_ Record Documents 6 19 related Work performed prior to ENGINEER's approval of required submittals 628 safe structural loading 6 18 Safety and Protection 6 20, Safety Representative 7 2, 13 2 621 Scheduling the Work „ 6 9 2 Shop Drawings and Samples 624 Shop Drawings and Samples Review by ENGINEER 626 Site Cleanliness 6 17 Submittal Procedures 625 Substitute Construction Methods and Procedures 6 7 2 Substitutes and "Or -Equal" Items Superintendence 6 7 1 6 2 Supervision „ - 61 Survival of Obligations .-6 34 Taxes 6 15 Tests and Inspections „ 13 5 To Report „ 2 5 Use of Premises 6 16-6.18, 6 30 2 4 Review Prior to Shop Drawing or Sample Submittal „ 625 Right to adjustment for changes in the Work 10 2 right to claim 4, 7 1, 9 4, 9 5, 9 11, 10 2,11 2, 11 9, 12 1, 13 9, 14 8, 15 1, 15.5, 17 3 Safety and Protection --- 6 20-6.22, 7 2, 13 2 Safety Representative ,-, 621 Shop Drawings and Samples Submittals 6 24-6 28 Special Consultants , 114.4 Substitute Construction Methods and Procedures,6 7 Substitutes and "Or -Equal" Items, Expense , , , -,- - , 6 7 1, 6 7 2 Subcontractors, Suppliers and Others, 6 8-6 11 j Supervision and Superintendence 6 1, 6 2, 621 1�f1 Taxes, Payment by 6 15 Use of Premises 6 16-6 18 Warranties and guarantees 6 5, 630 Warranty of Title - 143 Written Notice Required-- CONTRACTOR stop Work or terminate , 155 �nJJI Reports of Differing Subsurface and Physical Conditions 4 2 3 Substantial Completion -, - 8 „14 CONTRACTORS --other, , , , 7 Contractual Liability Insurance, ... 5 4 10 .. ..- . . Contractual Time Limits ,,,,,, „ •„ „ ,12.2 Article or Paragraph Number Coordination— CONTRACTOR's responsibility „ 6.9.2 Copies of Documents, , , , 2 2 Correction Period- , „ , „ ,,,, 13.12 Correction, Removal or Acceptance of Defective Work-- in general 10.4 1, 13 10-13 14 Acceptance of Defective Work, - , 13 13 Correction or Removal of Defective Work „ ,,,630, 13.11 Correction Period 13 12 OWNER May Correct Defective Work-, 13 14 OWNER May Stop Work - „• -- „ 13 10 Cost -- of Tests and Inspections „ - 13.4 Recordsll 7 Cost of the Work -- Bonds and insurance, additional - 11 4 5 9 Cash Discounts 11.4-2 CONTRACTOR's Fee 11 6 Employee Expenses 11 4 5 1 Exclusions to „ 11-5 Generalll 4-I1 5 Home office and overhead expenses „ 11 5 Losses and damages . .-......- 11 4 5 6 Materials and equipment „ 1142 Minor expenses „ - 11.4 5.8 Payroll costs on changes _ _ 114 1 performed by Subcontractors „ , , -, „ J.143 Records ll 7 Rentals of construction equipment and machinery , -, _ ,,,,I 1 4 5 3 Royalty payments, permits and license fees ,11 4.5 5 Site office and temporary facilities, „ 11 4.5 2 Special Consultants, CON'TRACTOR's , 11 4.4 Supplemental 11.45 Taxes related to the Work , , , - „ „ ,11 4 5 4 Tests and Inspection 13 4 Trade Discounts- 1142 Utilities, fuel and sanitary facilities 11.4,5 7 Work after regular hours 114.1 Covering Work , , ,,,,, „ „•, ,13.6-13 7 Cumulative Remedies 17 4-17.5 Cutting, fitting and patching, 72 Data, to be furnished by OWNER, , , , , „ , $-3 Day --definition of „17 2 2 Decisions on Disputes „ , 9.11, 9 12 defective --definition of-- -- 1 14 defective Work -- Acceptance of 10.4 1, 13.13 EJCDC GENERAL, CONDITIONS 1910-8 (1990 EDITION) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 9/99) Correction or Removal of 10 4.1, 13 11 Correction Period „ , 13 12 in general „ , 13, 14 7, 14 11 Article or Paragraph Number Observation by ENGINEER, ._ ,. 9 2 OWNER May Stop Work 13 10 Prompt Notice of Defects 131 Rejecting , , , , .96 Uncovering the Work , „ , ,. 13 8 Definitions _ .-. 1 Delays 4 1, 629, 12 3-12 4 Delivery of Bonds 2 1 Delivery of certificates of insurance, 27 Determinations for Unit Price$ „ 910 Differing Subsurface or Physical Conditions -- Notice of _ 4 2 3 ENGINEER's Review „ .424 Possible Contract Documents Change 4 2 5 Possible Price and Times Adjustments 4 2 6 Discrepancies -Reporting and Resolving „2 5, 3 3 2, 6 14 2 Dispute Resolution -- Agreement „ _ 16 1-16 6 Arbitration 16 1-16 5 genera116 Mediation „ 166 Dispute Resolution Agreement 16 1-16 6 Disputes, Decisions by ENGINEER 9 11-9 12 Documents -- Copies of 22 Record 6 19 Reuse of „ 37 Drawings --definition of 1 15 Easements „ 41 Effective date of Agreement -- definition of. 1 16 Emergencies .623 ENGINEER -- as initial interpreter on disputes 9 11-9 12 definition of _ „ 1 17 Limitations on authority and responsibilities 913 Replacement of, „ „ 82 Resident Project Representative 93 ENGINEER's Consultant -- definition of 1 18 ENGINEER's-- authority and responsibility, limitations orl. 9 13 Authorized Variations in the Work „ „ 95 Change Orders, responsibility for .97, 10, 11, 12 Clarifications and Interpretations 36 3,94 Decisions on Disputes 9 11-9 12 defective Work, notice of 13 1 Evaluation of Substitute Items „ , , 673 Liability, , 6 32, 9 12 Notice Work is Acceptable ,14,13 Observations , _ 6 30 2, 92 OWNER's Representative„ 91 Payments to the CONTRACTOR, Responsibility for _ 99, 14 Recommendation of Payment„ , ,,,, „ , 14 4, 14 13 Article or Paragraph Number Responsibilities --Limitations on, ,,, , , ,9 11-9 13 Review of Reports on Differing Subsurface and Physical Conditions, ,,, ,,,,,, ,,,,, , 4.2.4 Shop Drawings and Samples, review responsibility „ „ .....626 Status During Construction -- authorized variations in the Work „ ,,,, „ ,,, 9.5 Clarifications and Interpretations , , ,,,, „ PA Decisions on Disputes , , , „ „ „ ....9 11-9 12 Determinations on Unit Price,,, 9 10 ENGINEER as Initial Interpreter ,_, „ 9 11-9 12 ENGINEER's Responsibilities.. „9 1-9 12 Limitations on ENGINEER's Authority and Responsibilities _ , ....9 13 OWNER's Representative 9.1 Project Representative „ , , , , 93 Rejecting Defective Work . , „ , .96 Shop Drawings, Change Orders and Payments ,,,,,, 9.7-9.9 Visits to Site „ _ , , „ 9.2 Unit Price determinations „ „ , 910 Visits to Site „ , 9.2 Written consent required „ , 7.2, 9 1 Equipment, Labor, Materials and, ,,, „6.3-6 5 Equipment rental, Cost of the Work,,,_ 1145.3 Equivalent Materials and Equipment„ „ 6.7 error or omissions „ „ , ,,, 633 Evidence of Financial Arrangement$_ „ , .8 11 Explorations of physical conditions_ „ 42.1 Fee, CONTRACTOR's--Costs Plus „ „ „ 11 6 Field Order -- definition of , „ 1 19 issued by ENGINEER ...3 6 1,95 Final Application for Payment, , „ „ , ,14.12 Final Inspection 1411 Final Payment -- and Acceptance , ,14 13-14 14 Prior to, for cash allowances , , ,,,, ,,,,,, , , 11.8 General Provisions 17 3-17 4 General Requirements -- definition of „ „ „ ,,, ,,, , ,,,,,,,,,,, 1.20 principal references tq,,, , , „ , 6, 6 4, 6 6-6 7, 6 24 Giving Notice „ , . , , , , . 171 Guarantee of Work --by CONTRACTOR, 6.30, 14 12 Hazard Communication Programs , „ , „ .022 Hazardous Waste -- definition of „ „ „ _1 21 general „ , ,,,,,,.. ,4 5 OWNER's responsibility for, 8 10 ix E1CDC GENERAL CONDITIONS 1910-8 (1990 EDITION) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 9/9'� u Indemnification 112, 116, Initially Acceptable Schedules 6 11-111 .2.9 Inspection -- Certificates of, - - - 9 13 4, 13 5, 14 12 Final 1411 Article or Paragraph Number Special, required by ENGINEER„ „9 6 Tests and Approval 8 7, 13 3-13 4 , , Insurance -- Acceptance of, by OWNER, --, - , 5 14 Additional, required by changes in the Work. , 11459 Before starting the Work .27 Bonds and --in general „ 5 Cancellation Provisions 5 8 Certificates of. 2 7, 5, 5.3, 5 4 11, 54 13, 5 65, 5 8, 5 14, 9 13 4, 14 12 completed operations 54 13 CONTRACTOR's Liability - 54 CONTRACTOR's objection to coverage 5 14 Contractual Liability 54 10 deductible amounts, CONTRACTOR's responsibility , ., -, - 5 9 Final Application for Payment. 14 12 Licensed Insurers 5 3 Notice requirements, material changes 5 81 10 5 Option to Replace ... 5 14 other special insurances „- 5 10 OWNER as fiduciary for insureds 5 12-5 13 OWNER's Liability-- , 5 5 OWNER's Responsibility. 8 5 Partial Utilization, Property Insurance 5 15 Property 5 6-5 10 Receipt and Application of Insurance Proceeds Special Insurance . „ „ - . , .5 12-5 13 5 10 Waiver of Rights 5 11 Intent of Contract Documents,. 3.1-3 4 , , Interpretations and Clarifications „ 3 63, 94 Investigations of physical conditions , 42 Labor, Materials and Equipment 6 3-6 5 Lands -- and Easements . 8 4 Availability of . „ „ ,4.1, 8 4 Reports and Tests , , ....8 4 Laws and Regulations --Laws or Regulations— ���111 Bonds 5 1-5 2 Changes in the Work 114 Contract Documents :- 3 1 CONTRACTOR's Responsibilities 6.14 Correction Period, defective Work - 13 12 Cost of the Work, taxes 11 4 5 4 definition of : 122 general6 14 Indemnification - - - -- - x 6 31-6.33 Insurance, 5 3 Precedence .3-1, 3 3.3 Reference to - „ 3.3 1 Safety and Protection ,.6.20, 132 Subcontractors, Suppliers and Others „ 6 8-6 11 Article or Paragraph Number Tests and Inspections . , 13 5 Use of Premises 6.16 Visits to Site 9 2 Liability Insurance-- CONTRACTOR's 54 OWNER's - .. 5 5 Licensed Sureties and Insurei s. 5 3 Liens -- Application for Progress Payment -, .... , 142 CONTRACTOR's Warranty of Title, .143 Final Application for Payment 1412 definition of 1 23 Waiver of Claims 14 15 Limitations on ENGINEER's authority and responsibilities 9.13 Limited Reliance by CONTRACTOR Authorized , 422 Maintenance and Operating Manuals -- Final Application for Payment 14 12 Manuals (of others) -- Precedence 3 3.3 1 Reference to in Contract Documents , 3 3 1 Materials and equipment -- furnished by CONTRACTOR. 63 not incorporated in Work 14 2 Materials or equipment --equivalent .07 Mediation (Optional),. •, 167 Milestones --definition of „ .124 Miscellaneous -- Computation of Times„ 172 Cumulative Remedies ,- „ , 174 Giving Notice , . 171 Notice of Claim ,17 3 Professional Fees and Court Costs Included .175 Multi -prime contracts, • 7 Not Shown or Indicated „ , „ ,432 Notice of -- Acceptability of Project. „ „ „ 14.13 Award, definition of „ , „ .1 25 Claim .173 Defects,l3 1 Differing Subsurface or Physical Conditions .423 Giving 17 1 Tests and Inspections. „ - ,,, 13 3 Variation, Shop Drawing and Sample .627 Notice to Proceed -- definition of ) 26 giving of 23 E1CDC GENERAL. CONDITIONS 1910-8 (1990 EDITION) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 9/99) 712 45 degree bend 18" PVC C-900 3 EA 202 Remove asphalt and concrete street pavement 4329 SF 202 Remove and replace concrete sidewalk near type 16 inlet 85 SF 403 Asphalt Patching - 6" 20 TN 412 Concrete Pavement - 6" 1600 SF Sub Total - Stormwater Improvements JGrand Total Grand 'Dotal in writing 9. PRICES Dollars The foregoing prices shall include all labor, materials, transportation, shoring, removal, dewatering, overhead, profit, insurance, etc., to cover the complete Work in place of the several kinds called for. Bidder acknowledges that the OWNER has the right to delete items in the Bid or change quantities at his sole discretion without affecting the Agreement or prices of any item so long as the deletion or change does not exceed twenty-five percent (25%) of the total Agreement Price. RESPECTFULLY SUBMITTED: Signature Title (Seal - if Bid is by corporation) Attest: Address Telephone Date License Number (If Applicable) 7/96 Section 00300 Page 4 Notification to Surety .105 Observations, by ENGINEER _ 630, 92 Occupancy of the Work. , 5 15, 6 30 2 4, 14 10 Omissions or acts by CONTRACTOR, 6 9, 9 13 Open Peril policy form, Insurance 5 6 2 Option to Replace .5 14 Article or Paragraph Number "Or Equal" Items .67 Other work 7 Overtime Work --prohibition of, 63 OWNER -- Acceptance ofdefective Work 13 13 appoint an ENGINEER .82 as fiduciary 5 12-5 13 Availability of Lands, responsibility 41 definition of 1 27 data, furnish 8 3 May Correct Defective Work 13 14 May refuse to make payment 147 May Stop the Work 13 10 May Suspend Work, Terminate 8 8, 13 10, 15 1-15 4 Payment, make prompt 8 3, 14 4, 14 13 performance of other work ­7 1 permits and licenses, requirements ¢ 13 purchased insurance requirements 5 6-5 10 OWNER's-- Acceptance of the Work .63025 Change Orders, obligation to execute 86, 104 Communications 8 1 Coordination of the Work 74 Disputes, request for decision 9 I 1 Inspections, tests and approvals 8 7, 134 Liability Insurance 5 5 Notice of Defects 13 1 Representative— During Construction, ENGINEER's Status 91 Responsibilities -- Asbestos, PCBs, Petroleum, Hazardous Waste or Radioactive Material _ ,8 10 Change Orders .86 Changes in the Work 10.1 communications 8 1 CONTRACTOR's responsibilities 89 evidence of financial arrangements 8 11 inspections, tests and approvals 87 insurance 8 5 lands and easements 8 4 prompt payment by 8 3 replacement of ENGINEER .82 reports and tests 8 4 stop or suspend Work 8 81 13 10, 15 1 terminate CONTRACTOR's services 8 8, 15 2 separate representative at site . 93 testing, independent _ , . , ............13.4 use or occupancy of the Work , ....... $ 15, 6 30 2 4, 14 10 written consent or approval required „ 9 1, 6 3, 11.4 E1CDC GENERAL CONDITIONS 1910-8 (1990 EDITION) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 9/99_-) Article or Paragraph Number Article or Paragraph Number written notice required , 7 1, 9 4, 9.11, Shown or Indicated . .. .. ............ . . 4 3 1 r „ 11 2, 11.9, 14 7, 154 Technical Data , , . 42.2 PCBs-- Preconstruction Conference „ „ „ , „ 2 8 definition of. 1 29 Preliminary Matters , „ 2 general , OWNER's responsibility for, , _ „4 5 8 10 Preliminary Schedules . ......... Premises, Use of,,,,, ,,,,,,,, .26 6 16-6 18 Partial Utilization-- Price, Change of Contract „ , , definition of _ general 6 30 2 4, 14 10 „ 128 Price, Contract --definition of _ „ , , Progress Payment, Applications for , , , , „ , , 1 11 .142 Property Insurance „ , 5 15 Progress Payment--retainage_ „ 142 Patent Fees and Royalties _ _ Payment Bonds „ _ .612 5 1-5 2 Progress schedule, CONTRACTOR's .2.6, 2 8, 2 9, , 6 6, 6 29, 10 4, 15 2.1 Payments, Recommendation of 14.4-14 7, 14 13 Project --definition of : ::,, 131 Payments to CONTRACTOR and Completion-- Project Representative-- Application for ProgressPayments CONTRACTOR's Warranty of Title, J4 2 143 ENGINEER's Status During Construction„ ,- .93 Project Representative, Resident --definition of, 133 Final Application for Payment 14 12 prompt payment by OWNER , , , , -..8.3 Final Inspection Final Payment and Acceptance 1411 14 13-14 14 Property Insurance -- Additional 5 7 general $ 3, 14 general5 6-5.10 Partial Utilization 14 10 Partial Utilization ,. „ 5 15, 14 10 2 Retainage „ 142 receipt and application of proceeds ... 5 12-5 13 Review of Applications for Protection, Safety and 6 20-6 21, 13 2 Progress Payments_ .14 4-14 7 Punch list „ . „ , ,. 14 11 prompt payment Schedule of Values .83 141 Radioactive Material -- defintion of ..... ...1 32 Substantial Completion 14 8-14 9 general4 5 Waiver of Claims when payments due ., , 14 15 ,__ 144, 14 13 OWNER's responsibility for „ 8 10 Recommendation of Payment, 14.4, 145, 14.13 withholding payment „ „ 14 7 Record Documents „ 6 19, 1412 Performance Bonds 5 1-5 2 Records, procedures for maintaining ... ... „ .28 Permits 6 13 Reference Points 4.4 Petroleum-- Reference to Standards and Specifications definition of , , 130 of Technical Societies 33 general _ „4 5 Regulations, Laws and (or)_ „ _ _ Rejecting Defective Work. „ „ ....6.14 , „ , .96 OWNER's responsibility for _8 10 Related Work -- Physical Conditions-- Drawings of, in or relating to 4 2 1 2 at Site „ , ... ... . .... Performed prior to Shop Drawings ... .7.1-7.3 ENGINEER's review , , 42.4 and Samples submittals review„ 6.28 existing structures 4 2 2 Remedies, cumulative , , , , , ,,,, „ 17.4, 17.5 general 4 2 12 Removal or Correction ofDefec•tive Work, , ,,, , „.,13 11 Notice of Differing Subsurface or, , 423 rental agreements, OWNER approval required „ 114 5 3 Possible Contract Documents Change „ , 4 2 5 replacement of ENGINEER, by OWNER, ... „ .... , 8 2 Possible Price and Times Adjustments Reports and Drawings 4 2 6 .421 Reporting and Resolving Discrepancies 2 5, 3 3 2, 6 14 2 Subsurface and,. , 42 Reports -- Subsurface Conditions , „ , Technical Data, Limited Reliance by 42 11 and Drawings ... and Tests, OWNER's responsibility„ , „ „ „ 42.1 - , , .......8 4 CONTRACTOR Authorized 4 2 2 Resident and Project Representative -- Underground Facilities-- definition of _ 133 general 43 Not Shown or Indicded 432 Protection of _. 43,620 provision for „ , „ „ „ 9.3 xu E3CDC GENERAL CONDITIONS 1910-8 (1990 EDITION) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 9/99) Article or Paragraph Number Resident Superintendent, CONTRACTOR'$ 62 Responsibilities— CONTRACTOR's-m general 6 ENGINEER's-m general .9 Limitations on --- 9 13 OWNER'S-m general 8 Retamage 142 Reuse of Documents 3 7 Review by CONTRACTOR Shop Drawings and Samples Prior to Submittal 6-25 Review of Applications for Progress Payments - 14 4-14 7 Right to an adjustment 102 Rights of Way 4.1 Royalties, Patent Fees and 6 12 Safe Structural Loading 6 18 Safety -- and Protection 4 3 2, 6 16,6 18, 6 20-6 21, 72, 132 general 6 20-6 23 Representative, CONTRACTOR's 621 Samples -- definition of 1 34 general 6 24-6 28 Review by CONTRACTOR 6 25 Review by ENGINEER 626,627 related Work 6.28 submittal of - 6 24 2 submittal procedures 625 Schedule of progress 2 6, 2 8-2 9, 6 6, 6 29, 10 4, 15 2 1 Schedule of Shop Drawing and Sample Submittals 2 6, 2 8-2 9, 6 24-6 28 Schedule of Values ..2 6, 2 8-2 9, 14 1 Schedules -- Adherence to 152 1 Adjusting - 66 Change of Contract Times 104 Initially Acceptable 2 8, 2.9 Preliminary 26 Scope of Changes 10.3-10 4 Subsurface Conditions 42 11 Shop Drawings -- and Samples, general 6 24-6 28 Change Orders & Applications for Payments, and. . . . . . 9 7-9 S definition of 135 ENGINEER's approval of , -- 3 62 ENGINEER's responsibility for review 97, 6 24-6 28 related Work 628 review procedures - ..2 8, 6 24-6 28 Article or Paragraph Number submittal required ., _ ... 6.24 1 Submittal Procedures .. -, .... .625 use to approve substitutions .6 7.3 Shown or Indicated . 4 3.1 Site Access 72, 132 Site Cleanliness , ......... „ . . „ •¢ 17 Site, Visits to -- by ENGINEER , ...... 92, 132 by others ...... . . , 132 "special causes of loss" policy form, insurance .562 definition of ,. . . . 1.36 Specifications-- defination of. 1 36 of Technical Societies, reference to 3 3 1 precedence 3 3 3 Standards and Specifications of Technical Societies. 3 3 Starting Construction, Before .2 5-2 8 Starting the Work...- ,- 24 Stop or Suspend Work -- by CONTRACTOR 15.5 by OWNER 8 8, 13.10, 15 1 Storage of materials and equipment. . 4 1, 7 2 Structural Loading, Safety 6 18 Subcontractor -- Concerning, .6.8-6 11 definition of 1 37 delays „-• .... 12 3 waiver of rights 6.11 Subcontractors --in general .... 6 8-6 11 Subcontracts --required provision$ 5 11, 6 11, 1143 Submittals -- Applications for Payment 14 2 Maintenance and Operation Manuals „ 14 12 Procedures .625 Progress Schedules 2 6, 2.9 Samples - „ , „- .¢ 24-6.28 Schedule of Values , , „ ,.2 6, 14 1 Schedule of Shop Drawings and Samples Submissions - .2 6, 2 8-2 9 Shop Drawings 6 24-6 28 Substantial Completion -- certification of 63023, 14 8-14 9 definition of 1.38 Substitute Construction Methods or Procedures 6 7 2 Substitutes and "Or Equal" Item$•. ,• , . , ,- 6 7 CONTRACTOR's Expense. 67.1 3 ENGINEER's Evaluation , 6 7 3 "Or -Equal" 67 1.1 Substitute Construction Methods xm EJCDC GENERAL CONDITIONS 1910-8 (1990 EDITION) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 9/9�1 1 Article or Paragraph Number or Procedures „ •„ 6 7 2 Substitute Items 6 7.1 2 Subsurface and Physical Conditions -- Drawings of, in or relatng to 42 12 ENGINEER's Review .424 general - „- 42 Limited Reliance by CONTRACTOR Authorized 4 2 2 Notice of Differing Subsurface or Physical Conditions 42.3 Physical Conditions 42 12 Possible Contract Documents Change 4 2 5 Possible Price and Times Adjustments 4 2 6 Reports and Drawings - „ 42 1 Subsurface and, 42 Subsurface Conditions at the Site 4 2 1 1 Technical Data 4 2 2 Supervision— CONTRACTOR's responsibility 6 1 OWNER shall not supervise 89 ENGINEER shall not supervise 9 Z, 9 132 Superintendence 62 Superintendent, CONTRACTOR's resident 62 Supplemental costs 11 4 5 Supplementary Conditions -- definition of. 139 principal references to 1 10, 1 18, 2 2, 2 7, 4 2, 4 3, 5 1, 5 3, 5 4, 5 6-5 9, 5 11, 6 8, 6 13, 7 4, 8 11, 93,9 10 Supplementing Contract Documents 3 6 Supplier -- definition of 140 principal references to 3 7, 6 5, 6.8-6 11, 6 20, 6 24, 9 13, 14 12 Waiver of Rights , 6 11 Surety -- consent to final payment 14 12, 14 14 ENGINEER has no duty to - 9 13 Notification of - 10 1, 105, 15 2 qualification of , „ ,- 5 1-5 3 Survival of Obligations „ 634 Suspend Work, OWNER May - 13 10, 15 1 Suspension of Work and Termination-- 15 CONTRACTOR May Stop Work or Terminate 15 5 OWNER May Suspend Work 15 1 OWNER May Terminate , - 15.2-15 4 Taxes --Payment by CONTRACTOR, , , 6 15 Technical Data -- Limited Reliance by CONTRACTOR 4 2 2 Possible Price and Times Adjustments 4 2 6 Reports of Differing Subsurface and Physical Conditions 423 Temporary construction facilities . . .... ........ 41 Article or Paragraph Number Termination -- by CONTRACTOR - , , 15.5 by OWNER ,8.8, 15 1-15.4 of ENGINEER's employment „ , „ , , 8.2 Suspension of Work-in general . . . . ..........15 Terms and Adjectives , .. .... .. .. .... , . ...3 4 Tests and Inspections -- Access to the Work, by others ......... 13.2 CONTRACTOR's responsibilities , , , 135 cost of 13 4 covering Work prior to , , , Laws and Regulations (or) , ... 13 5 Notice of Defects - ,,, , , 13 1 OWNER May Stop Work ,__,13.10 OWNER's independent testing. 134 special, required by ENGINEER , „ , , „ , , 96 timely notice required ,,,_ „ 134 Uncovering the Work, at ENGINEER's request „ , 13.8-13 9 Times -- Adjusting - 66 Change of Contract „ „ „ ., 12 Computation of , „ .172 Contract Times --definition of - „ , „ , 1 12 day „ - „ ,- 1722 Milestones 12 Requirements -- appeals , , ,,, 9 10 16 clarifications, claims and disputes „- _9 11, 112, 12 Commencement of Contract Time$ . , , 23 Preconstruction Conference „ 28 schedules ,_„ „ , 2 6, 2 9, 6 6 Starting the Work. „ , , , , , .24 Title, Warranty of. - „ , - - .143 Uncovering Work „ .13.8-13 9 Underground Facilities, Physical Conditions -- definition of 1.41 Not Shown or Indicated ...... , 4.32 protection of -- 43, 620 Shown or Indicated ...... 43 1 Unit Price Work -- claims „ 1.1 9 3 definition of , „1 42 general 11 9, 14 1, 14 5 Unit Prices-- general113 1 Determination for „ 9 10 Use of Premises „6 16, 6 18, 6.30 2 4 Utility owners 6 13, 6 20, 7 1-7 3, 13 2 Utilization, Partial 1 28, 5 15, 6 30.2 4, 14.10 Value of the Work -- „ „ 11.3 Values, Schedule of 2 6, 2 8-2 9, 14 1 xtv EJCDC GENERAL CONDITIONS 1910-8 (1990 EDITION w/ CITY OF FORT COLLINS MODIFICATIONS (REV 9/99) Variations in Work--Mmor Authorized , , 6 25, 6 27, 9 5 Article or Paragraph Number Visits to Site --by ENGINEER 92 Waiver of Claims --on Final Payment .14 15 Waiver of Rights by insured parties , „ , $ 11,6 11 Warranty and Guarantee, General --by CONTRACTOR „ ., .630 Warranty of Title, CONTRACTOR's 143 Work -- Access to 132 by others, .. 7 Changes in the 10 Continuing the, _ 629 CONTRACTOR May Stop Work or Terminate „ „ , , 15 5 Coordination of 74 Cost of the,, _ „ 11 4-11 5 definition of 143 neglected by CONTRACTOR_ , , , 13 14 other Work „ 7 OWNER May Stop Work „ 13 10 OWNER May Suspend Work 13 10, 15 1 Related, Work at Site „ , , „ 7 1-7 3 Starting the,. 24 Stopping by CONTRACTOR _ , 15 5 Stopping by OWNER _._ -, 15 1-15 4 Variation and deviation authorized, minor 3 6 Work Change Directive -- claims pursuant to a0 2 definition of 144 principal references to _ 35 3, 10 1-10 2 Written Amendment -- definition of 145 principal references to „ , , 1 10, 3 5, 5 10,15 12, 662,682,619, 101, 104, 112, 12.1, 13 12 2, 14 7 2 Written Clarifications and Interpretations , . „ 3 6.3, 9 4, 9 11 Written Notice Required -- by CONTRACTOR 7 1, 9 10-9 11, 10 4, 112, 12 1 by OWNER 9 10-9.11, 10 4, 112, 13 14 xv u EJCDC GENERAL CONDITIONS 1910-8 (1990 EDITION), w/ CITY OF FORT COLLINS MODIFICATIONS (REV 9/991 u N 0 4. 0 e, 1 I Pill i (This page left blank intentionally) xw EJCDC GENERAL, CONDITIONS 1910-8 (1990 EDITION) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 9/99) No Text 0 ko 0 �1 14 GENERAL CONDITIONS ARTICLE 1--DEFINITIONS Wherever used in these General Conditions or in the other Contract Documents the following terms have the meanings indicated which are applicable to both the singular and plural thereof 1 1. Addenda —Written or graphic instruments issued prior to the opening of Bids which clarify, correct or change the Bidding Requirements or the Contract Documents 12. Agreement --The written contract between OWNER and CONTRACTOR covering the Work to be performed, other Contract Documents are attached to the Agreement and made a part thereof as provided therein 13 Application for Payment --The form accepted by ENGINEER which is to be used by CONTRACTOR in requesting progress or final payments and which is to be accompanied by such supporting documentation as is required by the Contract Documents. 1 4 Asbestos --Any material that contains more than one percent asbestos and is friable or is releasing asbestos fibers into the air above current action levels established by the United States Occupational Safety and Health Administration 15 Bid --The offer or proposal of the bidder submitted on the prescribed form setting forth the prices for the Work to be performed 16 Bidding Documents —The advertisement or invitation to Bid, instructions to bidders, the Bid form, and the proposed Contract Documents (including all Addenda issued prior to receipt of Bids) 17 Bidding Requirements --The advertisement or invitation to Bid, instructions to bidders, and the Bid form 1.8 Bonds —Performance and Payment bonds and other instruments of security 19. Change Order —A document recommended by ENGINEER, which is signed by CONTRACTOR and OWNER and authorizes an addition, deletion or revision in the Work, or an adjustment in the Contract Price or the Contract Times, issued on or after the Effective Date of the Agreement. 1 10 Contract Documents --The Agreement, Addenda (which pertain to the Contract Documents), CONTRACTOR'S Bid (including documentation accompanying the Bid and any post Bid documentation submitted prior to the Notice of Award) when attached as an exhibit to the Agreement, the Notice to Proceed, the Bonds, these General Conditions, the Supplementary Conditions, the Specifications and the Drawings as the same are more specifically Identified in the Agreement, together with all Written Amendments, Change Orders, Work Change Directives, Field Orders and ENGINEER's written interpretations and clarifications Issued pursuant to paragraphs 3 5, 3 6 1 and 3 6 3 on or after the Effective Date of the Agreement Shop Drawing submittals approved pursuant to paragraphs 6 26 and 6.27 and the reports and drawings referred to in paragraphs 4 2 1 and 4 2 2 are not Contract Documents 111 Contract Price --The moneys payable by OWNER to CONTRACTOR for completion of the Work in accordance with the Contract Documents as stated in the Agreement (subject to the provisions of paragraph 119 1 in the case of Unit Price Work) 1 12. Contract Times --The numbers of days or the dates stated in the Agreement (1) to achieve Substantial Completion, and (ii) to complete the Work so that it is ready for final payment as evidenced by ENGINEER's written recommendation of final payment in accordance with paragraph 14 13 1 13 CONTRACTOR --The person, firm or corporation with whom OWNER has entered into the Agreement 1 14 defective --An adjective which when modifying the word Work refers to Work that is unsatisfactory, faulty or deficient in that it does not conform to the Contract Documents, or does not meet the requirements of any inspection, reference standard, test or approval referred to in the Contract Documents, or has been damaged prior to ENGINEER's recommendation of final payment (unless responsibility for the protection thereof has been assumed by OWNER at Substantial Completion in accordance with paragraph 14 8 or 1410) 1 15 Drawings --The drawings which show the scope, extent and character of the Work to be furnished and performed by CONTRACTOR and which have been prepared or approved by ENGINEER and are referred to in the Contract Documents Shop drawings are not Drawings as so defined 116. Effective Date of the Agreement --The date indicated in the Agreement on which it becomes effective, but if no such date is indicated it means the date on which the Agreement is signed and delivered by the last of the two parties to sign and deliver 117 ENGINEER --The person, firm or corporation named as such in the Agi eement. 118 ENGINEER's Consultant --A person, firm or corporation having a contract with ENGINEER to fumish services as ENGINEER's independent professional associate or consultant with respect to the Project and who is identified as such in the Supplementary Conditions 119 Field Order —A, written order issued by ENGINEER which orders minor changes in the Work in accordance with paragraph 9.5 but which does not involve a change in the Contract Price or the Contract Times X EJCDC GENERAL, CONDITIONS 191M (1990 Edition) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000) 120 General Requirements --Sections of Division I of the Specifications 1954 (42 USC Section 2011 et seq) as amended from time to time. 121 Hazardous Waste --The term Hazardous Waste shall have the meaning provided in Section 1004 of the Solid Waste Disposal Act (42 USC Section 6903) as amended from time to time 122 a Laws and Regulations, Laws or Regulations --Any and all applicable laws, rules, regulations, ordinances, codes and orders of any and all governmental bodies, agencies, authorities and courts having jurisdiction 122 b Legal Hohdays--shall be those holidays observed by the City of Fort Collins. 123. Liens --Liens, charges, security interests or encumbrances upon real property or personal property 124. Milestone —A principal event specified in the Contract Documents relating to an intermediate completion date or time prior to Substantial Completion of all the Work. 125. Notice of Award --A written notice by OWNER to the apparent successful bidder stating that upon compliance by the apparent successful bidder with the conditions precedent enumerated therein, within the time specified, OWNER will sign and deliver the Agreement 126 Notice to Proceed --A written notice given by OWNER to CONTRACTOR (with a copy to ENGINEER) fixing the date on which the Contract Times will commence to run and on which CONTRACTOR shall start to perform CONTRACTOR'S obligations under the Contract Documents 127 OWNER --The public body or authority, corporation, association, firm or person with whom CONTRACTOR has entered into the Agreement and for whom the Work is to be provided 128. Partial Utilization --Use by OWNER of a substantially completed part of the Work for the purpose for which it is intended (or a related purpose) prior to Substantial Completion of all the Work 129 PCBs —Polychlorinated biphenyls. 130. Petroleum —Petroleum, including crude oil or any fraction thereof which is liquid at standard conditions of temperature and pressure (60 degrees Fahrenheit and 14 7 pounds per square inch absolute), such as oil, petroleum, fuel oil, oil sludge, oil refuse, gasoline, kerosene and oil mixed with other non -Hazardous Wastes and crude oils 131 Project --The total construction of which the Work to be provided under the Contract Documents may be the whole, or a part as indicated elsewhere in the Contract Documents 132 a. Radioactive Material --Source, special nuclear, or byproduct material as defined by the Atomic Energy Act of 2 FJCDC GENERAL CONDITIONS 1910-8 (1990 EcLnon) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000) 132 b Regular Working Hours —Regular working hours are defined as 7 OOam to 6 OOpm unless otherwise specified in the General Requirements. 133 Resident Project Representative --The authorized representative of ENGINEER who may be assigned to the site or any part thereof 134 Samples --Physical examples of materials, equipment, or workmanship that are representative of some portion of the Work and which establish the standards by which such portion of the Work will be judged 135 Shop Drawings --All drawings, diagrams, illustrations, schedules and other data or information which are specifically prepared or assembled by or for CONTRACTOR and submitted by CONTRACTOR to illustrate some portion of the Work 136 Specifications --Those portions of the Contract Documents consisting of written technical descriptions of materials, equipment, construction systems, standards and workmanship as applied to the Work and certain administrative details applicable thereto 1 37 Subcontractor --An individual, firm or corporation having a direct contract with CONTRACTOR or with any other Subcontractor for the performance of a part of the Work at the site 138 Substantial Completion --The Work (or a specified part thereof) has progressed to the point where, in the opinion of ENGINEER as evidenced by ENGINEER's definitive certificate of Substantial Completion, it is sufficiently complete, in accordance with the Contract Documents, so that the Work (or specified part) can be utilized for the purposes for which it is intended, or if no such certificate is issued, when the Work is complete and ready for final payment as evidenced by ENGINEER's written recommendation of final payment in accordance with paragraph 14 13 The terms "substantially complete" and "substantially completed" as applied to all or part of the Work refer to Substantial Completion thereof 139 Supplementary Conditions --The part of the Contract Documents which amends or supplements these General Conditions 1,40 Supplier --A manufacturer, fabricator, supplier, distributor, materialman or vendor having a direct contract with CONTRACTOR or with any Subcontractor to furnish materials or equipment to be incorporated in the Work by CONTRACTOR or any Subcontractor 141 Underground Facilities --All pipelines, conduits, ducts, cables, wires, manholes, vaults, tanks, tunnels or other such facilities or attachments, and any encasements containing such facilities which have been installed underground to furnish any of the following services or eta A I t i� U�w 0 0 materials: electricity, gases, steam, liquid petroleum products, telephone I or other communications, cable television, sewage and drainage removal, traffic or other control systems or water 142 Unit Price Work --Work to be paid for on the basis of unit prices. 143 Work --The entire completed construction or the various separately identifiable parts thereof required to be furnished under the Contract Documents. Work includes and is the result of I performing or furnishing labor and furnishing and incorporating materials and equipment into the construction, and performing or furnishing services and furnishing documents, all as required by the Contract Documents 144 Work Change Directive --A written directive to CONTRACTOR, issued on or after the Effective Date of the Agreement and signed by OWNER and recommended by ENGINEER, ordering an addition, deletion or revision in the Work, or responding to differing or unforeseen physical conditions (under which the Work is to be performed as provided in paragraph 4 2 or 43 or to emergencies under paragraph 6 23 A Work Change Directive will not change the Contract Price or the Contract Times, but is evidence that the parties expect that the change directed or � documented by a Work Change Directive will be incorporated in a subsequently issued Change Order following negotiations by the parties as to its effect, if any, on the `Contract Price or Contract Times as provided in paragraph 1 102. 145 Written Amendment --A written amendment of the Contract Documents, signed by OWNER and CONTRACTOR on ` or after the Effective Date of the Agreement and normally dealing with the nonengineering or nontechnical rather than strictly construction -related aspects of the Contract Documents ARTICLE 2—PRELYMINARY MATTERS Delivery of Bonds: 21 When CONTRACTOR delivers the executed Agreements to OWNER, CONTRACTOR shall also deliver to OWNER such Bonds as CONTRACTOR may be required to furnish Im accordance with paragraph 5 1. Copies of Documents: 22 OWNER shall furnish to CONTRACTOR up to ten copies (unless otherwise specified in the Supplementary Conditions) of the Contract Documents as are reasonably necessary for the execution ofthe Work Additional copies will be furnished, upon request, at the cost of reproduction Commencement of Contract Times; Notice to Proceed: 23 The Contract Times will commence to run on the thirtieth day after the Effective Date of the Agreement, or, 1 EJCDC GENERAL CONDITIONS 1910-8 (1990 Edition) w/ CITY OF FORT COLLIINS MODIFICATIONS (REV 42000) if a Notice to Proceed is given, on the day indicated in the Notice to Proceed. A Notice to Proceed may be given at any time within thirty days after the Effective Date of the Agreement in no event ill the Caritraet Time . the thirtieth day after the E ff „ t., a D t 9��y� opening ^.. .. thirtieth ..j .. �. � � . � � Mary e -the- nt, iele •'cvcr-vase-is earlier_ Starting the Work: 24 CONTRACTOR shall start to perform the Work on the date when the Contract Times commence to run, but no Work shall be done at the site prior to the date on which the Contract Times commence to run Before Starting Construction: 25 Before undertaking each part of the Work, CONTRACTOR shall carefully study and compare the Contract Documents and check and verify pertinent figures shown thereon and all applicable field measurements CONTRACTOR shall promptly report in writing to ENGINEER any conflict, error, ambiguity or discrepancy which CONTRACTOR may discover and shall obtain a written interpretation or clarification from ENGINEER before proceeding with any Work affected thereby, however, CONTRACTOR shall not be liable to OWNER or ENGINEER for failure to report any conflict, error, ambiguity or discrepancy in the Contract Documents, unless CONTRACTOR knew or reasonably should have known thereof 26 Within ten days after the Effective Date of the Agreement (unless otherwise specified in the General Requirements), CONTRACTOR shall submit to ENGINEER for review: 2 6 1 a preliminary progress schedule indicating the times (numbers of days or dates) for starting and completing the various stages of the Work, including any Milestones specified in the Contract Documents; 2 6 2 a preliminary schedule of Shop Drawing and Sample submittals which will list each required submittal and the times for submitting, reviewing and piocessmg such submittal, 262 1 In no case will a schedule be acceptable which allows less than 21 calendar days for each review by Engineer. 2 6 3 A preliminary schedule of values for all of the Work which will include quantities and prices of items aggregating the Contract Price and will subdivide the Work into component parts in sufficient detail to serve as the basis for progress payments during construction Such prices will include an appropriate amount of overhead and profit applicable to each item of Work 27 Before any Work at the site is started, CONTRACTOR arid OWNER shall eaeh deliver to the ether OWNER, with copies to eaeh , dditieri.' Insurea ideeti led in the Supplementary Ce art.,.. ENGINEER No Text certificates of insurance (and other evidence of insurance reasonably request requested by OWNER) which CONTRACTOR and 03AW D respeetively are is required to purchase and maintain in accordance with paragraphs 5 ^, `�T Preconstruction Conference: 28. Within twenty days after the Contract Times start to run, but before any Work at the site is started, a conference attended by CONTRACTOR, ENGINEER and others as appropriate will be held to establish a working understanding among the parties as to the Work and to discuss the schedules referred to in paragraph 2 6, procedures for handling Shop Drawings and other submittals processing Applications for Payment and maintaining required records Initially Acceptable Schedules: 29 Unless otherwise provided in the Contract Documents, at ,east ten days bef re submission of !he fir t A ppi Rio: ibr Dajrient before any work at the site begins, a conference attended by CONTRACTOR, ENGINEER and others as appropriate designated by OWNER, will be held to review for acceptability to ENGINEER as provided below the schedules submitted in accordance with paragraph 2 6 and Division 1 - General Requirements CONTRACTOR shall have an additional ten days to make corrections and adjustments and to complete and resubmit the schedules. No progress payment shall be made to CONTRACTOR until the schedules are submitted to and acceptable to ENGINEER as provided below The progress schedule will be acceptable to ENGINEER as providing an orderly progression of the Work to completion within any specified Milestones and the Contract Times, but such acceptance will neither impose on ENGINEER responsibility for the sequencing, scheduling or progress of the Work nor interfere with or relieve CONTRACTOR from CONTRACTOR's full responsibility therefor. CONTRACTOR's schedule of Shop Drawing and Sample submissions will be acceptable to ENGINEER as providing a workable arrangement for reviewing and processing the required submittals CONTRACTOR's schedule of values will be acceptable to ENGINEER as to form and substance ARTICLE 3--CONTRACT DOCUMENTS: INTENT, AMENDING, REUSE Intent: 31. The Contract Documents comprise the entire agreement between OWNER and CONTRACTOR concerning the Work The Contract Documents are complementary, what is called for by one is as binding as if called for by all The Contract Documents will be construed in accordance with the law of the place of the Project 32. It is the intent of the Contract Documents to EJCDC GENERAL CONDITIONS 1910-8 (1990 Edition) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000) describe a functionally complete Project (or part thereof) to be constructed in accordance with the Contract Documents Any Work, materials or equipment that may reasonably be inferred from the Contract Documents or from prevailing custom or trade usage as being required to produce the intended result will be furnished and performed whether or not specifically called for. When words or phrases which have a well-known technical or construction industry or trade meaning are used to describe Work, materials or equipment, such words or phrases shall be interpreted in accordance with that meaning Clarifications and interpretations of the Contract Documents shall be issued by ENGINEER as provided in paragraph 9 4 3.3. Reference to Standards and Specifications of Technical Societies; Reporting and Resolving Discrepancies: 3 3 1 Reference to standards, specifications, manuals or codes of any technical society, organization or association, or to the Laws or Regulations of any governmental authority, whether such reference be specific or by implication, shall mean the latest standard, specification, manual, code or Laws or Regulations in effect at the time of opening of Bids (or, on the Effective Date of the Agreement if there were no Bids), except as may be otherwise specifically stated in the Contract Documents 3 3 2 If, during the performance of the Work, CONTRACTOR discovers any conflict, error, ambiguity or discrepancy within the Contract Documents or between the Contract Documents and any provision of any such Law or Regulation applicable to the performance of the Work or of any such standard, specification, manual or code or of any instruction of any Supplier referred to in paragraph 6.5, CONTRACTOR shall report it to ENGINEER in writing at once, and, CONTRACTOR shall not proceed with the Work affected thereby (except in an emergency as authorized by paragraph 6 23) until an amendment or supplement to the Contract Documents has been issued by one of the methods indicated in paragraph 3 5 or 3 6, provided, however, that CONTRACTOR shall not be liable to OWNER or ENGINEER for failure to report any such conflict, error, ambiguity or discrepancy unless CONTRACTOR knew or reasonably should have known thereof 3 3 3 Except as otherwise specifically stated in the Contract Documents or as may be provided by amendment or supplement thereto issued by one of the methods indicated in paragraph 3 5 or 3 6, the provisions of the Contract Documents shall take precedence in resolving any conflict, error, ambiguity or discrepancy between the provisions of the Contract Documents and 3 3 3 1 the provisions of any such standard, specification, manual, code or instruction (whether or not specifically incorporated by reference in the Contract Documents), or I 0 C L41 1 0 d i, C 6 0 1 3.3.3 2 the�,plivclaliole prosns of any such Laws or Regulations to the performance of the Work (unless such an interpretation of the provisions of the Contract Documents would result in violation of such Law or Regulation) 3 3 4 In the event of conflicting or ambiguous No provision of any' such standard, specification, manual, code or instruction shall be effective to change the duties and responsibilities ` of OWNER, CONTRACTOR or ENGINEER, or any of their subcontractors, consultants, agents or employees, from those set forth in the Contract Documents, nor shall it be effective to assign to OWNER, ENGINEER or any of ENGINEER's Consultants, agents or employees any duty or authority to supervise or direct the furnishing or performance of the Work or any duty or authority to undertake responsibility inconsistent with the provisions of paragraph 9 13 or any other provision of the Contract Documents � 34 Whenever in the Contract Documents the terms "as ordered", "as directed", "as required", "as allowed", "as approved" or terms of like effect or import are used, or the adjectives "reasonable", "suitable", "acceptable", "proper" or "satisfactory" or adlecuves of like effect or import are used to describe a requirement, direction, review or judgment of ENGINEER as to the Work, it is intended that such requirement, direction, review or judgment will be solely to evaluate, in general, the completed Work for compliance with the requirements of and information in the Contract Documents and conformance with the design concept of the completed Project as a functioning whole as shown or indicated in the Contract Documents (unless there is a specific statement indicating otherwise) The use of any such term or adjective shall not be effective to assign to ENGINEER any duty or authority to supervise or direct the furnishing or performance of the Work or any duty or authority to undertake responsibility contrary to the provisions of paragraph 9 13 or any other provision of the Contract Documents � Amending and Supplementing Contract Documents: 3.5 The Contract Documents may be amended to provide for additions; deletions and revisions in the Work or to modify the terms and conditions thereof in one or more of the following ways 35 1 a formal Written Amendment, 3 5 2 a Change Order (pursuant to paragraph 10 4), or 3 5 3, a Work Change Directive (pursuant to paragraph 10 1). 3 6 In addition, the requirements of the Contract Documents may be supplemented, and minor variations and deviations in the Work may be authorized, in one or more of the following ways- 3 6.1. A Field Order (pursuant to paragraph 9 5), 3 62 ENGINEER's approval of a Shop Drawing or Sample (pursuant to paragraphs 6 26 and 6 27), or 3 63 ENGINEER's written interpretation or clarification (pursuant to paragraph 9 4) Reuse of Documents: 37 CONTRACTOR, and any Subcontractor or Supplier or other person or organization performing or furnishing any of the Work under a direct or indirect contract with OWNER (I) shall not have or acquire any title to or ownership rights in any of the Drawings, Specifications or other documents (or copies of any thereof) prepared by or bearing the seal of ENGINEER or ENGINEER's Consultant, and (u) shall not reuse any of such Drawings, Specifications, other documents or copies on extensions of the Project or any other project without written consent of OWNER and ENGINEER and specific written verification or adaptation by ENGINEER ARTICLE 4--AVAILABILITY OF LANDS; SUBSURFACE AND PHYSICAL CONDITIONS; REFERENCE POINTS Availability of Lands III OWNER shall furnish, as indicated in the Contract Documents, the lands upon which the Work is to be perfoimed, rights -of -way and easements for access thereto, and such other lands which are designated for the use of CONTRACTOR r_,..en reasonable wfiften4equest Ian& upon -Nhieh the Work is te be perRiffned an b E —9r fit: a etip e's l: against i ui:va wga uch r-cs zcx aeeef . OWNER shall identify any encumbrances or restrictions not oI'general application but specifically related to use of lands so furnished with which CONTRACTOR will have to comply in performing the Work. Easements for permanent structures or permanent changes in existing facilities will be obtained and paid for by OWNER, unless otherwise provided in the Contract Documents. If CONTRACTOR and OWNER are unable to agree on entitlement to or the amount or extent of any adjustments in the Contract Price or the Contract Times as a result of any delay in OWNER's furnishing these lands, rights -of - way or easements, CONTRACTOR may make a claim therefor as provided in Articles 11 and 12. 0 EJCDC GENERAL CONDITIONS 1910-8 (1990 E&non) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000) 1 CONTRACTOR shall provide for all additional lands and access thereto that may be required for temporary construction facilities or storage of materials and equipment 4.2. Subsurface and Physical Conditions: 4 2 1 Reports and Drawings Reference is made to the Supplementary Conditions for Identification of 4 2.1 1. Subsurface Conditions Those reports of explorations and tests of subsurface conditions at or contiguous to the site that have been utilized by ENGINEER in preparing the Contract Documents, and 4 2 12. Physical Conditions Those drawings of physical conditions in or relating to existing surface or subsurface structures at or contiguous to the site (except Underground Facilities) that have been utilized by ENGINEER in preparing the Contract Documents. 4 2 2 Limited Reliance by CONTRACTOR Authorized, Technical Data CONTRACTOR may rely upon the general accuracy of the "technical data" contained in such reports and drawings, but such reports and drawings are not Contract Documents Such "technical data" is identified in the Supplementary Conditions Except for such reliance on such "technical data", CONTRACTOR may not rely upon or make any claim against OWNER, ENGINEER or any of ENGINEER's Consultants with respect to 422 1 the completeness of such reports and drawings for CONTRACTOR's purposes, including, but not limited to, any aspects of the means, methods, techniques, sequences and procedures of construction to be employed by CONTRACTOR and safety precautions and programs incident thereto, or 4222 other data, interpretations, opinions and information contained in such reports or shown or indicated in such drawings, or 4223. any CONTRACTOR interpretation of or conclusion drawn from any "technical data" or any such data, interpretations, opinions or information 4 2 3 Notice of Differing Subsurface or Physical Conditions If CONTRACTOR believes that any subsurface or physical condition at or contiguous to the site that is uncovered or revealed either 423 1 is of such a nature as to establish that any "technical data" on which CONTRACTOR is entitled to rely as provided in paragraphs 4 2 1 and 4 2 2 is materially inaccurate, or 4232 is of such a nature as to require a change in the Contract Documents, or 423.3 differs materially from that shown or 6 EJCDC GENERAL CONDITIONS 1910-8 (1990 Edition) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000) indicated in the Contract Documents, or 4 2.3 4 is of an unusual nature, and differs materially from conditions ordinarily encountered and generally recognized as Inherent in work of the character provided for in the Contract Documents, then CONTRACTOR shall, prerr4* immediately after becoming aware thereof and before further disturbing conditions affected thereby or performing any Work in connection therewith (except in an emergency as permitted by paragraph 6 23), notify OWNER and ENGINEER in writing about such condition CONTRACTOR shall not further disturb such conditions or perform any Work in connection therewith (except as aforesaid) until receipt of written order to do so 4 2 4 ENGINEER's Review ENGINEER will promptly review the pertinent conditions, determine the necessity of OWNER's obtaining additional exploration or tests with respect thereto and advise OWNER in writing (with a copy to CONTRACTOR) of ENGINEER's findings and conclusions 4 2 5 Possible Contract Documents Change If ENGINEER concludes that a change in the Contract Documents is required as a result of a condition that meets one or more of the categories in paragraph 4 2 3, a Work Change Directive or a Change Order will be issued as provided in Article 10 to reflect and document the consequences of such change 4 2 6 Possible Price and Times Adjustments An equitable adjustment in the Contract Price or in the Contract Times, or both, will be allowed to the extent that the existence of such uncovered or revealed condition causes an increase or decrease in CONTRACTOR's cost of, or time required for performance of, the Work, subject, however, to the following 426 1 such condition must meet any one or more of the categories described in paragraphs 4 2 3 1 through 4 2 3 4, inclusive, 4262 a change in the Contract Documents pursuant to paragraph 4 2 5 will not be an automatic authorization of nor a condition precedent to entitlement to any such adjustment, 426.3 with respect to Work that is paid for on a Unit Price Basis, any adjustment in Contract Price will be subject to the provisions of paragraphs 9 10 and 119, and 4 2 6 4 CONTRACTOR shall not be entitled to any adjustment in the Contract Price or Times if, 4 2 6 4 1 CONTRACTOR knew of the existence of such conditions at the time CONTRACTOR made a final commitment to OWNER in respect of Contract Price and Contract Times by the iL submission of a bid or becoming bound under a negotiated contract, or I 426 42 the existence of such condition could reasonably have been discovered or revealed as a result of any examination, investigation, exploration, test or study of the site and contiguous areas required by the Bidding Requirements or Contract Documents to be conducted by or for CONTRACTOR prior to CONTRACTOR's making such final commitment, or 4 2 6 43 CONTRACTOR failed to glve�the written notice within the time and as rel uired by paragraph 4.23 If OWNER and CONTRACTOR are unable to agree on entitlement to or alto the amount or length of any such equitable adjustment in the Contract Price or Contract Times, a claim may be made therefor as provided in Articles I I and 12 I However, OWNER, ENGINEER and ENGINEER's Consultants shall not be liable to CONTRACTOR for' any claims, costs, losses or damages sustained by CONTRACTOR on or in connection with any other project or anticipated project 4.3. Physical Conditions— Underground Facilities: 43 1 Shown or Indicated The information and data shown or indicated in the Contract Documents with respect to existing Underground Facilities at or contiguous to the site is based on information and data furnished to OWNER or ENGINEER by the owners of such Underground Facilities or by others Unless it is otherwise expressly provided in the Supplementary Conditions 43 11 OWNER and ENGINEER shall not be responsible for the accuracy or completeness of any such information or data, and 43 12 The cost of all of the following will be included in the Contract Price and CONTRACTOR shall have full responsibility for (I) reviewing and checking all such information and data, (ii) locating all Underground Facilities shown or indicated in the Contract Documents,(iii) coordination of the Work with the owners of such Underground Facilities during construction, and (iv) the safety and protection of all such Underground Facilities as provided in! paragraph 6 20 and repairing any damage thereto resulting from the Work 4 3 2 Not Shown or Indicated If an Underground Facility is uncovered or revealed at or contiguous to the site which Iwas not shown or indicated in the Contract Documents, CONTRACTOR shall, prernptly immediately after becoming aware thereof and before further disturbing conditions affected thereby or performing any (Work in connection therewith (except in an emergency as required by paragraph 6 23), identify the owner of such Underground Facility and EJCDC GENERAL CONDITIONS 1910-8 (1990 Edam) w/ CITY OF FORT COL1dNS MODIFICATIONS (REV 4/2000) 1 give written notice to that owner and to OWNER and ENGINEER. ENGINEER will promptly review the Underground Facility and determine the extent, if any, to which a change is required in the Contract Documents to reflect and document the consequences of the existence of the Underground Facility. If ENGINEER concludes that a change in the Contract Documents is required, a Work Change Directive or a Change Order will be issued as provided in Article 10 to reflect and document such consequences During such time, CONTRACTOR shall be responsible for the safety and protection of such Underground Facility as provided in paragraph 6.20. CONTRACTOR shall may be allowed an increase in the Contract Price or an extension of the Contract Times, or both, to the extent that they are attributable io the existence of any Underground Facility that was not shown or indicated in the Contract Documents and that CONTRACTOR did not know of and could not reasonably have been expected to be aware of or to have anticipated If OWNER and CONTRACTOR are unable to agree on entitlement to or the amount or length of any such adjustment in Contract Price or Contract Times, CONTRACTOR may make a claim therefor as provided in Articles I I and 12 However, OWNER, ENGINEER and ENGINEER's Consultants shall not be liable to CONTRACTOR for any claims, costs, losses or damages incurred or sustained by CONTRACTOR on or in connection with any other project or anticipated project. Reference Points: 44 OWNER shall provide engineering surveys to establish reference points for construction which in ENGINEER's judgment are necessary to enable CONTRACTOR to proceed with the Work CONTRACTOR shall be responsible for laying out the Wort:, shall protect and preserve the established reference points and shall make no changes or relocations without the prior written approval of OWNER CONTRACTOR shall report to ENGINEER whenever any reference point is lost or destroyed or requires relocation because of necessary changes in grades or locations, and shall be responsible for the accurate replacement or relocation of such reference points by professionally qualified personnel 4.5. Asbestos, PCBs, Petroleum, Hazardous Waste or Radioactive Material: 4 5 1 OWNER shall be responsible for any Asbestos, PCBs, Petroleum, Hazardous Waste or Radioactive Material uncovered or revealed at the site which was not shown or indicated in Drawings or Specifications or identified in the Contract Documents to be within the scope of the Work and which may present a substantial danger to persons or property exposed thereto in connection with the Work at the site OWNER shall not be responsible for any such materials brought to the site by CONTRACTOR, Subcontractors, Suppliers or anyone else for whom CONTRACTOR is responsible - • ... . ; Now s - • ... .. .. •. .. •. " .... WON • ... .. • ... Offil Fiat -intended -m-apply , Hazardous Waste or Radieaetive Material uneevefe OF vied of the &A, EJCDC GENERAL CONDITIONS 1910-8 (1990 Echnon) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 42000) ARTICLE 5--BONDS AND INSURANCE Performance, Payment and Other Bonds: 5 1 CONTRACTOR shall furnish Performance and Payment Bonds, each in an amount at least equal to the Contract Price as security for the faithful performance and payment of all CONTRACTOR's obligations under the Contract Documents These Bonds shall remain in effect at least until one year after the date when final payment becomes due, except as provided otherwise by Laws or Regulations or by the Contract Documents CONTRACTOR shall also furnish such other Bonds as are required by the Supplementary Conditions All Bonds shall be in the form prescribed by the Contract Documents except as provided otherwise by Laws or Regulations and shall be executed by such sureties as are named in the current list of "Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and as Acceptable Remsuring Companies" as published in Circular 570 (amended) by the Audit Staff, Bureau of Government Financial Operations, U.S Treasury Department All Bonds signed by an agent must be accompanied by a certified copy of such agent's authority to act 52 If the surety on any Bond furnished by CONTRACTOR is declared a bankrupt or becomes insolvent or its right to do business is terminated in any state where any part of the Project is located or it ceases to meet the requirements of paragraph 5 1, CONTRACTOR shall within ten days thereafter substitute another Bond and surety, both of which must be acceptable to OWNER 5.3. Licensed Sureties and Insurers; Certificates of Insurance: 5 3 1 All Bonds and insurance required by the Contract Documents to be purchased and maintained by OWNER or CONTRACTOR shall be obtained from surety or insurance companies that are duly licensed or authorized in the jurisdiction in which the Project is located to issue Bonds or insurance policies for the limits and coverages so required Such surety and insurance companies shall also meet such additional requirements and qualifications as may be provided in the Supplementary Conditions. 5 3.2 CONTRACTOR shall deliver to OWNER, with copies to each additional insured identified in the Supplementary Conditions, certificates of insurance (and other evidence of insurance requested by OWNER or any other additional insured) which CONTRACTOR is required to purchase and maintain in accordance with paragraph 5 4. ^""` ER shall addifienal insured tdentjfied in the Supple b [ CONTRACTOR's Liaibility Insurance: 54 CONTRACTOR shall purchase and maintain such liability and other insurance as is appropriate for the Work being performed and furnished and as will provide protection from claims set forth below which may arise out of or result from CONTRACTOR's performance and furnishing of the Work and CONTRACTOR's other obligations under the Contract Documents, whether it is to be performed or furnished by CONTRACTOR, any Subcontractor or Supplier, or by anyone directly or indirectly employed by any of them to perform or furnish any of the Work, or by anyone for whose acts any of them may be liable: 5 4 1 claims under workers' compensation, disability benefits and otheri similar employee benefit acts, 5 4 2 claims for[ damages because of bodily injury, occupational sickness or disease, or death of CONTRACTOR's employees, 5 4 3. claims for damages because of bodily injury, sickness or disease, or death of any person other than CONTRACTOR's employees, A 4 eln..„n f [. damages insufed 1. .ntemaFy hieh are sustained as /.\ i.. a ..It of an offense .7 Fe efl e'Fto.l to the employment e f n sh b GONTR ACTOR ... L.\ 1... n Dili o. „ „nfn.„n , „.. e.n..r�--co,--airTS e&r'.;e;im - 5 4 5 claims for damages, other than to the Work itself, because ofi injury to or destruction of tangible property wherever located, including loss of use resulting therefrom, and 5.46 claims forldamages because of bodily injury or death of any person or property damage arising out of the ownership, maintenance or use of any motor vehicle The policies of insurance so required by this paragraph 5 4 to be purchased and maintained shall 5 4 7. with respect to insurance required by paragraphs 5 4 3! through 5.4 6 inclusive and 5 4 9, include as additional insureds (subject to any customary exclusion in respect of professional liability), OWNER, ENGINEER, ENGINEER's Consultants and any other persons or entities identified in the Supplementary Conditions, all of whom shall be listed as additional insureds, and include coverage for the respective officers and employees of all such additional insureds, 5.4 8 include the specific coverages and be written for not less than the limits of liability provided in the Supplementary Conditions or required by Laws or Regulations, whichever is greater, I 5 4 9 include completed operations insurance, EJCDC GENERAL_ CONDITIONS 1910-8 (1990 Edition) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000) 5 4 10. include contractual liability insurance covering CONTRACTOR's indemnity obligations under paragraphs 6.12, 6 16 and 6 31 through 6.33; 5 4 11 contain a provision or endorsement that the coverage afforded will not be cancelled, materially changed or renewal refused until at least thirty days' prior written notice has been given to OWNER and CONTRACTOR and to each other additional insured identified in the Supplementary Conditions to whom a certificate of insurance has been issued (and the certificates of insurance furnished by the CONTRACTOR pursuant to paragraph 5 3 2 will so provide), 5 4 12 remain in effect at least until final payment and at all times thereafter when CONTRACTOR may be correcting, removing or replacing defective Work in accordance with paragraph 13.12;and 5 4 13 with respect to completed operations insurance, and any insurance coverage written on a claims -made basis, remain in effect for at least two years after final payment (and CONTRACTOR shall furnish OWNER and each other additional insured identified in the Supplementary Conditions to whom a certificate of insurance has been issued evidence satisfactory to OWNER and any such additional msured of continuation of such insurance at final payment and one year thereafter) 0WNIER's Liability Insurance: 5 5 In addition to insurance required to be provided by CONTRACTOR under paragraph 5.4, OWNER, at O WNER's option, may purchase and maintain at OWNER's expense OWNER's own liability insurance as will protect OWNER against claims which may arise from operations under the Contract Documents. Property Insurance: '74 1 include the interests e€ ^o`,'r"�TNED, 03NTRACTOR, Subeentraeter,, 1 N PiE R,, enwjes identified . the a leme * Condit. eaeh of . he deemed to have at and shall be listed .... as ...........d ainsurable a ..d..al .r insured; 3-45 2 beaten an a Builder's Risk—"Fill-rsk" eF shall at least melude insuran , v li..nieal J less- or �„. ge to the Work temperafy buildings, F 1 in n'�'�` 1 . and �zh_i, na' and nl.nn^ nsure against the feAewing—perils fire, ligrtntrt thek dalism a F eeverage, earthquake, debris makeieus mis6hie .nl�al, de; eellapse, —re.,.e elitte damage, ether rile he watef and stieh as Fnay speetfioally required by the 0upplementa.., Conditions, tfeT•f!1fslRy.. .. j� al . lt100 W�� M•j11 : _ _ • ;T ••. 1. •64 •. r ••r I. •� •71-<I<tI!T.!!T.�lPylR�F71l:l�ITt7!TT�{C�jPj.R1lf: j�jRl/S FIR T'J.�! ----------------- • •. • •• 59 OWNER shall not be responsible for purchasing and maintaining any property insurance to protect the interests of CONTRACTOR, Subcontractors or others in the Work to the extent eF any deduc4.hle n ..its that are identified in the Supplementary Gendnions T om€ inns within such identified deduet.hle amount, ....II he baFna by CONTRACTOR, Subeentraeter of ethers suffering any ah le and if afty of the wish a ..yeE)vee-—'�'sRrai,�e .n within the 1,..,,ts eF eh .,ts each ... ay purehase and maintain it at the pttfehaser's rrr-expense. • 4 •. 2.1 m;; •_ . • •_ 1 O EJCDC GENERAL CONDITIONS 1910-8 (1990 Edition) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000) 01.1 • • ON01150" . ,, • • - - - - -'.�.lii!!. NO INN Lii�ii=r:ISJ:11FIr :t!11f9!!7TS7 7 _ UNWI •1 - 1. �. :.....•,:,:,_,:_I . `�!�� .�!��.-�. 7!f!tif<V7S!III .i .• WIN 6> Al I 0 0 J Receipt and Application of Insurance Proceeds: 5 12 Any insured loss under the policies of insurance required by paragraphs 5.6 and 5.7 will be adjusted with OWNER and made payable to OWNER as fiduciary for the insureds, as their interests may appear, subject to the requirements of any lapplicable mortgage clause and of paragraph 5.13 OWNER shall deposit in a separate account any money so received, and shall distribute it in accordance with suchl agreement as the parties in interest may reach If no other special agreement is reached the damaged Work shall be repaired or replaced, the moneys so received applied on account thereof and the Work and the cost thereof covered by an appropriate Change Order or Written Amendment 5 13 OWNER as fiduciary shall have power to adjust and settle any loss with the insurers unless one of the parties in interest shall object in writing within fifteen days after the occurrence of loss to OWNER's exercise of this power If such objection be made, OWNER as fiduciary shall make settlement lwrth the insurers in accordance with such agreement as the parties in interest may reach If no such agreement among the parties in interest is reached, OWNER as fiduciaryl shall adjust and settle the loss with the insurers and if . red in writine by . party I Acceptance of Bonds (land Insurance; Option to Replace: 5 14 If �• inian.TvnANER eF CONTRACTOR) OWNER has any objection to the coverage afforded by or other provisions of the Bends er insurance required to be purchased and maintained by the ether pares _CONTRACTOR in accordance with Article 5 on the basis of non-conformance with the Contract Documents, the �, �, A -a se „,..44 .x Oho ,..I . „.. . OWNER will notify, CONTRACTOR in writing within ten fifteen days after receipt delivery of the certificates r,._ OtheF evideneee requested) to OWNER as required by paragraph 2.7. Partial Utilization —Property Insurance: 515 If OWNER finds it necessary to occupy or use a portion or portions of the Work prior to Substantial Completion of all the Work, such use or occupancy may be accomplished in accordance with paragraph 14 10; provided that no such use or occupancy shall commence before the insurers providing the property insurance have acknowledged notice thereof and in writing effected any changes in coverage necessitated thereby The insurers providing the property insurance shall consent by endorsement on the policy or policies, but the property insurance shall not be cancelled or permitted to lapse on account of any such partial use or occupancy ARTICLE 6—CONTRACTOR'S RESPONSIBILITIES Supervision and Superintendence: 61 CONTRACTOR shall supervise, inspect and direct the Work competently and efficiently, devoting such attention thereto and applying such skills and expertise as may be necessary to perform the Work in accordance with the Contract Documents CONTRACTOR shall be solely responsible for the means, methods, techniques, sequences and procedures of construction, but CONTRACTOR shall not be responsible for the negligence of others in the design or specification of a specific means, method, technique, sequence or procedure of construction which is shown or indicated in and expressly required by the Contract Documents CONTRACTOR shall be responsible to see that the completed Work complies accurately with the Contract Documents 62 CONTRACTOR shall keep on the Work at all times during its progress a competent resident superintendent, who shall not be replaced without written notice to OWNER and ENGINEER except under extraordinary circumstances The superintendent will be CONTRACTOR's representative at the site and shall have authority to act on behalf of CONTRACTOR All communications to the superintendent shall be as binding as if given to CONTRACTOR Labor, Materials and Equipment: 63. CONTRACTOR shall provide competent, suitably qualified personnel to survey, lay out and construct the Work as required by the Contract Documents CONTRACTOR shall at all times maintain good discipline and order at the site. Except as otherwise required for the safety or protection of persons or the Work or property at the site or adjacent thereto, and except as otherwise indicated in the Contract Documents, all Work at the site shall be performed during regular working hours and CONTRACTOR will not permit overtime work or the performance of Work on Saturday, Sunday or any legal holiday without OWNER's written consent given after prior written notice to ENGINEER CONTRACTOR shall submit requests to the ENGINEER no lest; than 48 hours in advance of any Work to be egfomied on Saturday, Sunday. Holidays or outside the Regular Working Hours E.ICDCIGENERAL CONDITIONS 1910-8 (1990 Edition) ] j w/ CITY OF FORT COLLWS MODIFICATIONS (REV 4/2000) 64 Unless otherwise specified in the General Requirements, CONTRACTOR shall furnish and assume full responsibility for all materials, equipment, labor, transportation, construction equipment and machinery, tools, appliances, fuel, power, light, heat, telephone, water, sanitary facilities, temporary facilities and all other facilities and incidentals necessary for the furnishing, performance, testing, start-up and completion of the Work 64 1 Purchasing Restrictions CONTRACTOR must comply with the City's purchasing restrictions A copy of the resolutions are available for review in the offices of the Purchasing and Risk Managemen_ t Division or the City Clerk's office 642 Cement Restrictions City of Fort Collins Resolution 91-121 requires that suppliers and producers of cement or products containing cement to certify that the cement was not made in cement kilns that burn hazardous waste as a fuel 6 5 All materials and equipment shall be of good quality and new, except as otherwise provided in the Contract Documents All warranties and guarantees specifically called for by the Specifications shall expressly run to the benefit of OWNER If required by ENGINEER, CONTRACTOR shall furnish satisfactory evidence (including reports of required tests) as to the kind and quality of materials and equipment All materials and equipment shall be applied, installed, connected, erected, used, cleaned and conditioned in accordance with instructions of the applicable Supplier, except as otherwise provided in the Contract Documents Progress Schedule: 66 CONTRACTOR shall adhere to the progress schedule established in accordance with paragraph 2 9 as it may be adjusted from time to time as provided below 6 6 1 CONTRACTOR shall submit to ENGINEER for acceptance (to the extent indicated in paragraph 2 9) proposed adjustments in the progress schedule that will not change the Contract Times (or Milestones). Such adjustments will conform generally to the progress schedule then in effect and additionally will comply with any provisions of the General Requirements applicable thereto 662 Proposed adjustments in the progress schedule that will change the Contract Times (or Milestones) shall be submitted in accordance with the requirements of paragraph 12 1 Such adjustments may only be made by a Change Order or Written Amendment in accordance with Article 12 6.7. Substitutes and "Or -Equal" Items: 6 7 1 Whenever an item of material or equipment is specified or described in the Contract Documents by using the name of a proprietary item or the name of a particular Supplier, the specification or description is intended to establish the type, function and quality required Unless the specification or description EJCDC GENERAL CONDITIONS 1910-8 (1990 Edition) 12 w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000) contains or is followed by words reading that no like, equivalent or "or -equal" item or no substitution is permitted, other items of material or equipment or _ material or equipment of other Suppliers may be accepted by ENGINEER under the following circumstances 6 7 1 1 "Or -Equal" If in ENGINEER's sole discretion an item of material or equipment proposed by CONTRACTOR is functionally equal to that named and sufficiently, similar so that - no change in related Work will be required, it may be considered by ENGINEER as an "or -equal" item, in which case review and approval of the proposed item may, in ENGINEER's sole - discretion, be accomplished without compliance with some or all of the requirements for acceptance of proposed substitute items. 6 7 12 Substitute Items If in ENGINEER's sole discretion an item of material or equipment proposed by CONTRACTOR does not qualify as an "or -equal" item under subparagraph 6 7 1 1, it will be considered a proposed substitute item -� CONTRACTOR shall submit sufficient information as provided below to allow ENGINEER to determine that the item of material or equipment proposed is essentially equivalent to that named and an acceptable substitute therefor. The procedure for review by the ENGINEER will include the following as supplemented in the General Requirements and as ENGINEER may decide is appropriate under the circumstances Requests for review of proposed substitute items of material or equipment will not be accepted by ENGINEER from anyone other than CONTRACTOR If CONTRACTOR wishes to furnish or use a substitute item of material or equipment, CONTRACTOR shall first make written application to ENGINEER for acceptance thereof, certifying that the proposed substitute will perform adequately the functions and achieve the results called for by the general design, be similar in substance to that specified and be suited to the same use as that specified The application will state the extent, if any, to which the evaluation and acceptance of the proposed substitute will prejudice CONTRACTOR's achievement of Substantial Completion on time, whether or not acceptance of the substitute for use in the Work will require a change in any of the Contract Documents (or in the provisions of any other direct contract with OWNER for work on the Project) to adapt the design to the proposed substitute and whether or not incorporation or use -, of the substitute in connection with the Work is subject to payment of any license fee or royalty All variations of the proposed substitute from that specified will be identified in the application and available maintenance, repair and replacement service will be indicated The application will also contain an itemized estimate of all costs or credits that will result directly or indirectly from acceptance of such substitute, including costs of redesign and claims of other contractors affected U L_J r r7 e Lf� 0 `� i<� by the resulting change, all of which will be considered by ENGINEER in evaluating the proposed substitute ENGINEER may require CONTRACTOR to furnish additional data about the proposed substitute 6 7 1 3 CONTRACTOR's Expense All data to be provided by CONTRACTOR in support of any proposed "or equal" or substitute item will be at CONTRACTOR's expense 672 Substitute' Construction Methods or Procedures If a specific means, method, technique, sequence or procedure of construction is shown or indicated in and lexpressly required by the Contract Documents, CONTRACTOR may furnish or utilize a substitute means ,I method, technique, sequence or procedure of construction acceptable to ENGINEER CONTRACTOR shall submit sufficient information to allow ENGINEER, in ENGINEER's sole discretion, to determine that the substitute proposed is equivalent to that expressly called for by the Contract Documents The procedure for review by ENGINEER will be similar to that provided in subparagraph 6 7 12 673 Engineer's Evaluation ENGINEER will be allowed a reasonable time within which to evaluate each proposal) or submittal made pursuant to paragraphs 6 7 12 and 6 7 2 ENGINEER will be the sole judge of acceptability No "or -equal" or substitute will be ordered, installed or utilized without ENGINEER's prior written acceptance which will be evidenced by either a Change Order or an approved Shop Drawing OWNER may require CONTRACTOR to furnish at CONTRACTOR's expense a special performance guarantee or other surety with respect to any "or -equal" or substitute ENGINEER 'will record time required by ENGINEER and ENGINEER's Consultants in evaluating substitutes proposed or submitted by CONTRACTOR pursuant to paragraphs 6 7 12 and 6 7 2 and in I making changes in the Contract Documents (or !in the provisions of any other direct contract with OWNER for work on the Project) occasioned thereby Whether or not ENGINEER accepts a substitute item so proposed or submitted by CONTRACTOR, CONTRACTOR shall reimburse OWNER for )the charges of ENGINEER and ENGINEER's Consultants for evaluating each such proposed substitute item 68. Concerning I Subcontractors, Suppliers and Others: 6 8 1 CONTRACTOR shall not employ any Subcontractor, Supplier or other person or organization (including those acceptable to OWNER and ENGINEER as indicated in paragraph 6 8 2), whether initially or as a substitute, against whom OWNER or ENGINEER may have reasonable objection CONTRACTORI shall not be required to employ any Subcontractor, Supplier or other person or organization to furnish or perform any of the Work against whom CONTRACTOR has reasonable objection 6.9. CONTRACTOR shall perform not less than 20 percent of the Work with its own forces (that is without subcontracting) The 20 percent requirement shall be understood to refer to the Work the value of which totals not less than 20 percent of the Contract Price 6 8 2. If the S...,..1,,.. ent ty Condition Bi_ dding Documents require the identity of certain Subcontractors, Suppliers or other persons or of ganizations (including those who are to furnish the pi mcipal items of materials or equipment) to be submitted to OWNER in advanee of the speeified date prior to the Effective Date of the Agreement for acceptance by OWNER and ENGINEER; ap if CONTRACTOR CTO_D h b a list H vc ccv cc .... aceerdanee h the c. pl OWNER's or ENGINEER's acceptance (either in writing or by failing to make written objection thereto by the date indicated for acceptance or objection in the bidding documents or the Contract Documents) of any eiganizatieR SO -H-PBtffiR�_ may be revoked -A th-- to ..a ieh ease GONTD A CT -OD shall b -- - ai7eeptable—substitute, the CentCentraet Price ill adjusted st will be issued oF W rit4eft A .] « v=.«==ib.,«d will constitute a condition of the Contract requiring the use of the named subcontractors suppliers or other persons or organization on the Work unless prior written approval is obtained from OWNER and ENGINEER No acceptance by OWNER or ENGINEER of any such Subcontractor, Supplier or other person or organization shall constitute a waiver of any right of OWNER or ENGINEER to reject df feetive Work. 6 9 1 CONTRACTOR shall be fully responsible to OWNER and ENGINEER for all acts and omissions of the Subcontractors, Suppliers and other persons and organizations performing or furnishing any of the Work under a direct or indirect contract with CONTRACTOR just as CONTRACTOR is responsible for CONTRACTOR's own acts and omissions Nothing in the Contract Documents shall create for the benefit of any such Subcontractor, Supplier or other person or organization any contractual relationship between OWNER or ENGINEER and any such Subcontractor, Supplier or other person or organization, nor shall it create any obligation on the part of OWNER or ENGINEER to pay or to see to the payment of any moneys due any such Subcontractor, Supplier or other person or organization except as may otherwise be required by Laws and Regulations. OWNER or ENGINEER may furnish to any subcontractor, supplier or other person or organization evidence of amounts paid to CONTRACTOR in accordance with CONTRACTOR'S "Applications for Payment" EJCDC GENERAL CONDITIONS 1910-8 (1990 Edition) 13 w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000) SECTION 00400 SUPPLEMENTS TO BID FORMS 00410Bid Bond 00420Statement of Bidder's Qualifications 00430 Schedule of Subcontractors 692 CONTRACTOR shall be solely responsible for scheduling and coordinating the Work of Subcontractors, Suppliers and other persons and organizations performing or furnishing any of the Work under a direct or indirect contract with CONTRACTOR CONTRACTOR shall require all Subcontractors, Suppliers and such other persons and organizations performing or furnishing any of the Work to communicate with the ENGINEER through CONTRACTOR 610 The divisions and sections of the Specifications and the identifications of any Drawings shall not control CONTRACTOR in dividing the Work among Subcontractors or Suppliers or delineating the Work to be performed by any specific trade. 611 All Work performed for CONTRACTOR by a Subcontractor or Supplier will be pursuant to an appropriate agreement between CONTRACTOR and the Subcontractor or Supplier which specifically binds the Subcontractor or Supplier to the applicable terms and conditions of the Contract Documents for the benefit of OWNER and ENGINEER Whenever a eh agFeemen is with a Subeenti--aeter er Supplier whe is listed as -an addit.. nal Insured n the property insuranee provided , a�. paragraphs 5 6 or 5 7, the agreement between the CONTRACTOR and the Sub6ontFaeter or Supplier ....Il «tain previsiens whereby tha_Subeent...eter e^ Supple. waives all rights against OWNER, , ENGP* EE IITi!'PIEER'S Gees. Itants d II the. , ouod-ttavar$na au vn,cr additional insureds for All I___es and damages _ ^ed b.- arising ..ut of or resulting iafn .. e f the perils e red by theWedE iif cline—i,i3'cifers on any sueh pa ieies requifce signedseparate waiver forms te be c. ppiter,CONTRACTORwill obtain thesafnc Patent Fees and Royalties: 6.12 CONTRACTOR shall pay all license fees and royalties and assume all costs incident to the use in the performance of the Work or the incorporation in the Work of any invention, design, process, product or device which is the subject of patent rights or copyrights held by others If a particular invention, design, process, product or device is specified in the Contract Documents for use in the performance of the Work and if to the actual knowledge of OWNER or ENGINEER its use is subject to patent rights or copyrights calling for the payment of any license fee or royalty to others, the existence of such rights shall be disclosed by OWNER in the Contract Documents. To the fullest extent permitted by Laws and Regulations, CONTRACTOR shall indemnify and hold harmless OWNER, ENGINEER, ENGINEER's Consultants and the officers, directors, employees, agents and other consultants of each and any of them from and against all claims, costs, losses and damages arising out of or resulting from any infringement of patent rights or copyrights incident to the use in the performance of the Work or resulting from the incorporation in the Work of any invention, design, process, product or device not specified in the Contract Documents EJCDC GENERAL CONDITIONS 1910-8 (1990 Edition) 14 w/ C= OF FORT COLLINS MODIFICATIONS (REV 4R000) Permits: 6 13 Unless otherwise provided in the Supplementary Conditions, CONTRACTOR shall obtain and pay for all construction permits and licenses OWNER shall assist CONTRACTOR, when necessary, in obtaining such permits and licenses CONTRACTOR shall pay all governmental charges and inspection fees necessary for the prosecution of the Work, which are applicable at the time of opening of Bids, or, if there are no Bids, on the Effective Date of the Agreement CONTRACTOR shall pay all charges of utility owners for connections to the Work, and OWNER shall pay all charges of such utility owners for capital costs related thereto such as plant investment fees 6.14. Laws and Regulations: 6 14 1 CONTRACTOR shall give all notices and comply with all Laws and Regulations applicable to furnishing and performance of the Work Except where otherwise expressly required by applicable Laws and Regulations, neither OWNER nor ENGINEER shall be responsible for monitoring CONTRACTOR's compliance with any Laws or Regulations 6 14 2 If CONTRACTOR performs any Work knowing or having reason to know that it is contrary to Laws or Regulations, CONTRACTOR shall bear all claims, costs, losses and damages caused by, arising out of or resulting therefrom; however, it shall not be CONTRACTOR's primary responsibility to make certain that the Specifications and Drawings are in accordance with Laws and Regulations, but this shall not relieve CONTRACTOR of CONTRACTOR's obligations under paragraph 3 3 2 Taxes: 6 15 CONTRACTOR shall pay all sales, consumer, use and other similar taxes required to be paid by CONTRACTOR in accordance with the Laws and Regulations of the place of the Protect which are applicable during the performance of the Work 6 15 1 OWNER is exempt from Colorado State and local sales and use taxes on materials to be permanently incorporated into the protect Said taxes shall not be included in the Contract Price CONTRACTOR must apply for, and receive, a Address Colorado Department of Revenue State Capital Annex 0 It] Ht Fk y`1 3: 1375 Sherman Street Denver, Colorado, 80261 Sales and Use I Taxes for the State of Colorado Regional Transportation District (RTD) and certain Colorado counties are collected by the State of Colorado and are included in the Certification of Exemption All applicable Sales and Use Taxes (including State collected taxes), 'on any Items other than construction and building materials physically Incorporated into the protect are to bel paid by CONTRACTOR and are to be included in appropriate bid Items Use of Premises: 616. CONTRACTOR shall confine construction equipment, the storage of materials and equipment and the operations of workers to the site and land and areas identified in and permitted by the Contract Documents and other land and areas permitted by Laws and Regulations, rights -of -way, permits and easements, and shall not unreasonably encumber the premises with construction equipment or other materials or equipment CONTRACTOR shall assume full responsibility for any damage to any such land or area, or to the owner or occupant thereof or of any adjacent land or areas, resulting from the performance of the Work Should any claim be made by any such owner or occupant because of the performance of the Work, CONTRACTOR shall promptly settle with such other party by negotiation or otherwise resolve the claim by arbitration or other dispute resolution proceeding or at law CONTRACTOR shall, to the fullest extent permitted by Laws and Regulations, indemnify and hold harmless OWNER, ENGINEER, ENGINEER's Consultant and anyone directly or indirectly employed by any of them from and against all claims, costs, losses and damages arising out I of or resulting from any claim or action, legal or equitable, brought by any such owner or occupant against OWNER, ENGINEER or any other party indemnified hereunder to the extent caused by or based upon CONTRACTOR's performance of the Work 6 17 During the progress of the Work, CONTRACTOR shall keep the premises free from accumulations of waste materials, rubbish and other debris resulting from the Work At the completion of the Work CONTRACTOR shall remove all waste materials, rubbish and debris from and about the premises as well as all tools, appliances, construction equipment and machinery and surplus materials. CONTRACTOR shall leave the site clean and ready for occupancy by OWNER at Substantial Completion of the Work CONTRACTOR shall restore to original condition all property not designated for alteration by the Contract Documents 6.18. CONTRACTOR shall not load nor permit any part of any structure to be loaded in any manner that will endanger the structure, nor shall CONTRACTOR subject any part of the Work or adjacent property to stresses or pressures that will endanger it Record Documents: 619 CONTRACTOR shall maintain in a safe place at the site one record copy of all Drawings, Specifications, Addenda, Written Amendments, Change Orders, Work Change Directives, Field Orders and written interpretations and clarifications (issued pursuant to paragraph 9 4) in good order and annotated to show all changes made during construction These record documents together with all approved Samples and a counterpart of all approved Shop Drawings will be available to ENGINEER for reference. Upon completion of the Work, and prior to release of final payment, these record documents, Samples and Shop Drawings will be delivered to ENGINEER for OWNER. Safety and Protection: 620 CONTRACTOR shall be responsible for initiating, maintaining and supervising all safety precautions and programs in connection with the Work. CONTRACTOR shall take all necessary precautions for the sa Fety of, and shall provide the necessary protection to prevent damage, injury or loss to 6 20 1 all persons on the Work site or who may be affected by the Work, 6 20 2 all the Work and materials and equipment to be incorporated therein, whether in storage on or off the site, and 6 20 3 other property at the site or adjacent thereto, including trees, shrubs, lawns, walks, pavements, roadways, structures, utilities and Underground Facilities not designated for removal, relocation or replacement in the course of construction CONTRACTOR shall comply with all applicable Laws and Regulations of any public body having jurisdiction for safety of persons or property or to protect them from damage, injury or loss, and shall erect and maintain all necessary safeguards for such safety and protection CONTRACTOR shall notify owners of adjacent property and of Underground Facilities and utility owners when prosecution of the Work may affect them, and shall cooperate with them in the protection, removal, relocation and replacement of their property All damage, injury or loss to any property referred to in paragraphs 6.20.2 or 6 20 3 caused, directly or indirectly, in whole or in part, by CONTRACTOR, any Subcontractor, Supplier or any other person or organization directly or indirectly employed by any of them to perform or furnish any of the Work or anyone for whose acts any of them may be liable, shall be remedied by CONTRACTOR (except damage or loss abributable to the fault of Drawings or Specifications or to the acts or omissions of OWNER or ENGINEER or ENGEgEER's Consultant or anyone employed by any of them or anyone for whose acts any of them may be liable, and not attributable, directly or indirectly, in whole or in part, to the fault or negligence of CONTRACTOR or any Subcontractor, Supplier or other person or organization directly or indirectly employed by any of them) CONTRACTOR's duties and responsibilities for the safety and protection of the Work shall continue until such time as all tie Work is completed and ENGINEER has issued a EICDC GENERAL. CONDITIONS 1910-8 (1990Edition) 15 w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000) notice to OWNER and CONTRACTOR in accordance with paragraph 14.13 that the Work is acceptable (except as otherwise expressly provided in connection with Substantial Completion). 6.21. Safety Representative: CONTRACTOR shall designate a qualified and experienced safety representative at the site whose duties and responsibilities shall be the prevention of accidents and the maintaining and supervising of safety precautions and programs Hazard Communication Programs: 622 CONTRACTOR shall be responsible for coordinating any exchange of material safety data sheets or other hazard communication information required to be made available to or exchanged between or among employers at the site in accordance with Laws or Regulations Emergencies: 623 In emergencies affecting the safety or protection of persons or the Work or property at the site or adjacent thereto, CONTRACTOR, without special instruction or authorization from OWNER or ENGINEER, is obligated to act to prevent threatened damage, injury or loss CONTRACTOR shall give ENGINEER prompt written notice if CONTRACTOR believes that any significant changes in the Work or variations from the Contract Documents have been caused thereby If ENGINEER determines that a change in the Contract Documents is required because of the action taken by CONTRACTOR in response to such an emergency, a Work Change Directive or Change Order will be issued to document the consequences of such action 6.24. Shop Drawings and Samples: 6 24 1 CONTRACTOR shall submit Shop Drawings to ENGINEER for review and approval in accordance with the accepted schedule of Shop Drawings and Sample submittals (see paragraph 2 9). All submittals will be identified as ENGINEER may require and in the number of copies specified in the General Requirements. The data shown on the Shop Drawings will be complete with respect to quantities, dimensions, specified performance and design criteria, materials and similar data to show ENGINEER the materials and equipment CONTRACTOR proposes to provide and to enable ENGINEER to review the information for the limited purposes required by paragraph 6 26 6 24 2 CONTRACTOR shall also submit Samples to ENGINEER for review and approval in accordance with said accepted schedule of Shop Drawings and Sample submittals Each Sample will be identified clearly as to material, Supplier, pertinent data such as catalog numbers and the use for which intended and otherwise as ENGINEER may require to enable ENGINEER to review the submittal for the limited EJCDC GENERAL CONDITIONS 1910-8 (1990 Edition) 16 w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000) purposes required by paragraph 6 26. The numbers of each Sample to be submitted will be as specified in the Specifications 6.25. Submittal Procedures: 6 25 1 Before submitting each Shop Drawing or Sample, CONTRACTOR shall have determined and verified 625 1 1 all field measurements, quantities, dimensions, specified performance criteria, installation requirements, materials, catalog numbers and similar information with respect thereto, 6.25 12 all materials with respect to intended use, fabrication, shipping, handling, storage, assembly and installation pertaining to the performance of the Work, and 625 13 all information relative to CONTRACTOR's sole responsibilities in respect of means, methods, techniques, sequences and procedures of construction and safety precautions and programs incident thereto CONTRACTOR shall also have reviewed and coordinated each Shop Drawing or Sample with other Shop Drawings and Samples and with the requirements of the Work and the Contract Documents 6 25 2 Each submittal will bear a stamp or specific written indication that CONTRACTOR has satisfied CONTRACTOR's obligations under the Contract Documents with respect to CONTRACTOR's review and approval of that submittal 6 25.3. At the time of each submission, CONTRACTOR shall give ENGINEER specific written notice of such variations, if any, that the Shop Drawing or Sample submitted may have from the requirements of the Contract Documents, such notice to be in a written communication separate from the submittal; and, in addition, shall cause a specific notation to be made on each Shop Drawing and Sample submitted to ENGINEER for review and approval of each such variation. 626. ENGINEER will review and approve Shop Drawings and Samples in accordance with the schedule of Shop Drawings and Sample submittals accepted by ENGINEER as required by paragraph 2 9. ENGINEER's review and approval will be only to determine if the items covered by the submittals will, after installation or incorporation in the Work, conform to the information given in the Contract Documents and be compatible with the design concept of the completed Project as a functioning whole as indicated by the Contract Documents ENGINEER's review and approval will not extend to means, methods, techniques, sequences or procedures of construction (except where a particular means, method, technique, sequence or procedure of It i� �a 0 go Elt. construction is specifically and expressly called for by the Contract Documents)' or to safety precautions or programs incident thereto Thie review and approval of a separate item as such will not indicate approval of the assembly in which the item functions CONTRACTOR shall make corrections required by ENGINEER, and shall return the required number of corrected copies of Shop Drawings and submit as required new Samples for review and approval CONTRACTOR shall direct specific attention in writing to revisions other than the corrections called for by ENGINEER on previous submittals 6.27 ENGINEER's review and approval of Shop Drawings or Samples shall not relieve CONTRACTOR from responsibility for any variation from the requirements of the Contract Documents unless CONTRACTOR has in writing called ENGINEER's attention to each such variation at the time of submission as required by paragraph 6 25 3 and ENGINEER has given written approval of each such variation by a specific written notation thereof incorporated in or accompanying the Shop Drawing or Sample iapproval, nor will any approval by ENGINEER relieve CONTRACTOR from responsibility for complying with thi e requirements of paragraph 6 25 1 628 Where a Shop Drawing or Sample is required by the Contract Documents or the schedule of Shop Drawing and Sample submissions accepted by ENGINEER as required by paragraph 2 9, any related Work performed prior to ENGINEER's review and approval of the pertinent submittal will be at the sole expense and responsibility of CONTRACTOR. Continuing the Work: 6 29 CONTRACTOR shall carry on the Work and adhere to the progress schedule during all disputes or disagreements with OWNER. No Work shall be delayed or postponed pending resolution of any disputes or disagreements, except as permitted by paragraph 15 5 or as OWNER and CONTRACTOR may otherwise agree in writing 6.30. CONTRACTOR's General Warranty and Guarantee: 630.1 CONTRACTOR warrants and guarantees to OWNER, ENGINEER and ENGINEER's Consultants that all Work will be in accordance with the Contract Documents and will not be defective CONTRACTOR's warranty and guarantee hereunder excludes defects or damage caused by- 6 30 1 1 abuse, modification or Improper maintenance l or operation by persons other than CONTRACTOR, Subcontractors or Suppliers; or 6.3012 normal wear and tear under normal usage. 6.30 2 CONTRACTOR's obligation to perform and complete the Work in accordance with the Contract Documents shall be absolute None of the following will constitute an I acceptance of Work that is not in accordance with the Contract Documents or a release of CONTRACTOR's obligation to perform the Work in accordance with the Contract Documents• 6 30 2 1 observations by ENGINEER, 6 30 2.2. recommendation of any progress or final payment by ENGINEER, 63023 the issuance of a certificate of Substantial Completion or any payment by OWNER to CONTRACTOR under the Contract Documents, 63024 use or occupancy of the Work or any part thereof by OWNER, 63025 any acceptance by OWNER or any failure to do so, 63026 any review and approval of a Shop Drawing or Sample submittal or the issuance of a notice of acceptability by ENGINEER pursuant to paragraph 14 13, 63027 any inspection, test or approval by others, or 6 30.2 8_ any correction of defective Work by OWNER. Indeninrftcation: 631 To the fullest extent permitted by Laws and Regulations, CONTRACTOR shall indemnify and hold harmless OWNER, ENGINEER, ENGINEER's Consultants and the officers, directors, employees, agents and other consultants of each and any of them from and against all claims, costs, losses and damages (including, but not limited to, all fees and charges of engineers, architects, attorneys and other professionals and all court or arbitration or other dispute resolution costs) caused by, arsine, out of or resulting from the performance of the Work, provided that any such claim, cost, loss or damage (i) is attributable to bodily injury, sickness, disease or death, or to injury to or destruction of tangible property (other than the Work itself), including the loss of use resulting therefrom, and (ii) is caused in whole or in part by any negligent act or omission of CONTRACTOR, any Subcontractor, any Supplier, any person or organization directly or indirectly employed by any of them to perform or furnish any of the Work or anyone for whose acts any of them may be liable, regardless of whether or not caused in part by any negligence or omission of a person or entity indemnified hereunder or whether liability is Imposed upon such indemnified party by Laws and Regulations regardless of the negligence of any such person or entity 632 In any and all claims against OWNER or ENGINEER or any of then respective consultants, agents, officers, directors or employees by any employee (or the survivor or personal representative of such employee) of CONTRACTOR, any Subcontractor, any Supplier, any person or organization directly or indirectly employed by EJCDC GENERAL, CONDITIONS 1910-8 (1990 Edition) 17 w( CITY OF FORT COLLINS MODIFICATIONS (REV 412000) any of them to perform or furnish any of the Work or anyone for whose acts any of them may be liable, the indemnification obligation under paragraph 6 31 shall not be limited in any way by any limitation on the amount or type of damages, compensation or benefits payable by or for CONTRACTOR or any such Subcontractor, Supplier or other person or organization under workers' compensation acts, disability benefit acts or other employee benefit acts 6 33. The indemnification obligations of CONTRACTOR under paragraph 6 31 shall not extend to the liability of ENGINEER and ENGINEER's Consultants, officers, directors, employees or agents caused by the professional negligence, errors or omissions of any of them. Survival of Obligations: 634 All representations, indemnifications, warranties and guarantees made in, required by or given in accordance with the Contract Documents, as well as all continuing obligations indicated in the Contract Documents, will survive final payment, completion and acceptance of the Work and termination or completion of the Agreement ARTICLE 7--OTHER WORK Related Work at Site: 7 1 OWNER may perform other work related to the Project at the site by OWNER's own forces, or let other direct contracts therefor which shall contain General Conditions similar to these, or have other work performed by utility owners If the fact that such other work is to be performed was not noted in the Contract Documents, then (i) written notice thereof will be given to CONTRACTOR prior to starting any such other work and (it) CONTRACTOR may make a claim therefor as provided in Articles I I and 12 if CONTRACTOR believes that such performance will involve additional expense to CONTRACTOR or requires additional time and the parties are unable to agree as to the amount or extent thereof 72 CONTRACTOR shall afford each other contractor who is a party to such a direct contract and each utility owner (and OWNER, if OWNER is performing the additional work with OWNER's employees) proper and safe access to the site and a reasonable opportunity for the introduction and storage of materials and equipment and the execution of such other work and shall properly connect and coordinate the Work with theirs Unless otherwise provided in the Contract Documents, CONTRACTOR shall do all cutting, fitting and patching of the Work that may be required to make its several parts come together properly and integrate with such other work CONTRACTOR shall not endanger any work of others by cutting, excavating or otherwise altering their work and will only cut or alter their work with the written consent of ENGINEER and the others whose work will be affected The duties and responsibilities of CONTRACTOR under this paragraph are for the benefit of such utility owners and other contractors to the extent that there are comparable EJCDC GENERAL CONDITIONS 1910-8 (1990 Edition) 18 w/ CITY OF FORT COLLINS MODIFICATIONS (REV 42000) provisions for the benefit of CONTRACTOR in said direct contracts between OWNER and such utility owners and other contractors. 73 If the proper execution or results of any part of CONTRACTOR's Work depends upon work performed by others under this Article 7, CONTRACTOR shall inspect such other work and promptly report to ENGINEER in writing any delays, defects or deficiencies in such other work that render it unavailable or unsuitable for the proper execution and results of CONTRACTOR'S Work. CONTRACTOR's failure so to report will constitute an acceptance of such other work as fit and proper for integration with CONTRACTOR's Work except for latent or nonapparent defects and deficiencies in such other work Coordination: 74 If OWNER contracts with others for the performance of other work on the Project at the site, the following will be set forth in Supplementary Conditions: 7 4 L the person, firm or corporation who will have authority and responsibility for coordination of the activities among the various prime contractors will be identified, 742 the specific matters to be covered by such authority and responsibility will be itemized; and 7 4 3 the extent of such authority and responsibilities will be provided Unless otherwise provided in the Supplementary Conditions, OWNER shall have sole authority and responsibility in respect of such coordination ARTICLE 8—OWNER'S RESPONSIBILITIES 8 1. Except as otherwise provided in these General Conditions, OWNER shall issue all communications to CONTRACTOR through ENGINEER. 82 In case of termination of the employment of ENGINEER, OWNER shall appoint an engineer against whose status under the Contract Documents shall be that of the former ENGINEER 83. OWNER shall furnish the data required of OWNER under the Contract Documents promptly and shall make payments to CONTRACTOR promptly when they are due as provided in paragraphs 14 4 and 14 13 84 OWNER's duties in respect of providing lands and easements and providing engineering surveys to establish reference points are set forth in paragraphs 4.1 and 4 4 Paragraph 4 2 refers to OWNER's identifying and making available to CONTRACTOR copies of reports of explorations and tests of subsurface conditions at the site and drawings of physical conditions in existing Nr I ro C` r �• .t 49 Kli u� 0 uk- i i H t« structures at or contiguous to the site that have been utilized by ENGINEER in priepanng the Contract Documents .. .. ....,per. V ......,. »...... are setf ..thin pa aphs c [ through agr 86 OWNER is obligated to execute Change Orders as indicated in paragrapIh 10 4 87. OWNER's responsibility in respect of certain inspections, tests and approvals is set forth in paragraph 13 4. 8 8 In connection with OWNER's right to stop Work or suspend Work, see paragraphs 13 10 and 15 1 Paragraph 15 2 deals with OWNER's right to terminate services of CONTRACTOR under certain circumstances 8 9 The OWNER shall not supervise, direct or have control or authority over, nor be responsible for, CONTRACTOR's means, methods, techniques, sequences or procedures of construction or the safety precautions and programs incident thereto, or for any failure of CONTRACTOR to comply with Laws and Regulations applicable to the furnishing or performance of the Work OWNER will not be responsible for CONTRACTOR's failure to perform or, furnish the Work in accordance with the Contract Documents �._�cr.�tt�l•�rerrs!rearnrRresr.�+.ssa�s.:rna�r_,ar. :e�rru!w�e!,l+.zf rsr.�s�rsn>t.�css. M. RAW mi ARTICLE 9—ENGINEER'S STATUS DURING CONSTRUCTION i OWNER's Representative: 91. ENGINEER will be OWNER's representative during the construction period The duties and responsibilities andl the limitations of authority of ENGINEER as OWNER's representative during construction are set forth in the Contract Documents and shall not be extended without written consent of OWNER and ENGINEER. Visits to Site: 92 ENGINEER' will make visits to the site at intervals appropriate to the various stages of construction as ENGINEER deems necessary in order to observe as an experienced and qualified design professional the progress that has been made and the quality of the various aspects of CONTRACTOR's executed Work Based on mformation obtained during such visits and observations, ENGINEER will endeavor for the benefit of OWNER to deterinme, in general, if the Work is proceeding in accordance with the Contract Documents ENGINEER will not be required to make exhaustive or continuous on - site inspections to check the quality or quantity of the Work ENGINEER's efforts will be directed toward providing for OWNER a greater degree of confidence that the completed Work will conform generally to the Contract Documents On the basis of such visits and on - site observations, ENGINEER will keep OWNER informed of the progress of the Work and will endeavor to guard OWNER against defective Work ENGINEER' visits and on -site observations are subject to all the limitations on ENGINEER's authority and responsibility set forth in paragraph 9 13, and particularly, but without limitation, during or as a result of ENGINEER's on -site visits or observations of CONTRACTOR's Work ENGINEER will not supervise, direct, control or have authority over or be responsible for CONTRACTOR's means, methods, techniques, sequences or procedures of construction, or the safety precautions and programs incident thereto, or for any failure of CONTRACTOR to comply with Laws and Regulations applicable to the furnishing or performance of the Work Project Representative: 93 If OWNER and ENGINEER agree, ENGINEER will wrnish a Resident Project Representative to assist ENGINEER in providing more continuous observation of the Work The responsibilities and authority and limitations thereon of any such Resident Project Representative and assistants will be as provided in paragraphs93 and 9.13 and in the Supplementary Gendrtieas of these General Conditions If OWNER designates another representative or agent to represent OWNER at the site who is not ENGINEER's Consultant, agent or employee, the responsibilities and authority and limitations thereon of such other person will be as provided in the Supp',,..,entaF Conditions paragraph 9.3 of these General Conditions If the ENGINEER furnishes a Resident Project Representative (RPR) or other assistants, or if the OWNER designates a Representative gr a rnt, all as provided in paragraph 9 3 of the General Conditions, these Representatives shall have the authority and limitations as provided in paragraph 9 13 of the General Conditions and shall be subiect to the following 93 1 The Representative's dealings in matters pertaining to the on -site work will, in general, be with the ENGINEER and CONTRACTOR But, the Representative will keep the OWNER properly advised about such matters The Representative's dealings with subcontractors will only be through or with the full knowledge and approval of the CONTRACTOR 9 3 2 Duties and Responsibilities Representative will 9 3 2 1 Schedules - Review the progress EJCDC GENERAL CONDITIONS 1910-8 (1990 E&lion) 19 w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000) I schedule and other schedules prepared by the CONTRACTOR and consult with the ENGINEER concerning acceptability 9 3 2 2. Conferences and Meeting - Attend meeting with the CONTRACTOR such as preconstruction conferences, progress meetings and other iob conferences and prepare and circulate copies of minutes of meetings. 9 3 2 3 Liaison 9323 1 Serve as ENGINEER'S liaison with CONTRACTOR, working principally through CONTRACTOR'S superintendent to assist the CONTRACTOR in understanding the Contract Documents 9 3 2 3 2 Assist in obtaining from OWNER additional details or information, when required for proper execution of the Work 9 3 2 3 3 Advise the ENGINEER and CONTRACTOR of the commencement of any Work requiring a Shop Drawing or sample submission if the submission has not been approved by the ENGINEER 9 3 2 4 Review of Work, Rejection of Defective Work, Inspections and Tests - 9 3 2 4 1 Conduct on -site observations of the Work in progress to assist the ENGINEER in determining that the Work is proceeding in accordance with the Contract Documents for observation, or requires special testing, inspection or approval. 9 3 2 4 3 Accompany visiting inspectors representing public or other agencies having jurisdiction over the Project, record the results of these inspections and report to the ENGINEER 9 3.2 5 Interpretation of Contract Documents Report to ENGINEER when clarifications and interpretations of the Contract Documents are needed and transmit to CONTRACTOR clarification and interpretation of the Contract Documents as issued by the ENGINEER 9326 Modifications Consider and evaluate CONTRACTOR'S suggestions for EJCDC GENERAL CONDITIONS 1910-8 (1990 Edition) 20 w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000) modification in Drawings or Specifications and report these recommendations to ENGINEER Accurately transmit to CONTRACTOR decisions issued by the ENGINEER 9 3 2 7 Records 9 3 2 7 1 Maintain at the Representative's office orderly files concerning 9 3 2 7 2 Keep a diary, daily report form, or log book, recording hours on the job site, weather conditions, data relative to questions of work directive changes, Change Orders, or changed conditions, list of iob site visitors, daily activities, decisions, observations in general and specific observations in more detail as in the case of observing test procedures; send copies to the ENGINEER 9 3 2 7 3 Record names, addresses and telephone numbers of all CONTRACTORS, subcontractors and major suppliers of equipment and materials 9 3 2 8 Reports 9 3 2 8 1 Furnish ENGINEER venodic reports, as required, of the progress of the Work and of the CONTRACTOR'S compliance with the progress schedule and schedule of shop Drawing and sample submittals 9 3 2 8 2 Consult with ENGINEER in advance of scheduling major tests, inspections or start of important phases of the Work 9 3 2 8 3 Draft proposed Change Orders and Work Directive Changes, obtaining backup material from the CONTRACTOR and recommend to ENGINEER Change Orders. Work Directive Chanties and field orders 93.284 Report immediately to ENGINEER and OWNER the occurrence of any accident. 9 3 2 9 Payment Requests Review applications for payment with CONTRACTOR for compliance with the established procedure for their submission and forward with recommendation to ENGINEER, noting particularly the relationship of the payment requested to the schedule of values, ® work completed and materials and equipment delivered A the site but not incorporated in the Work 9 3 2 10. Completion 932101 Before ENGINEER issues a Certificate of Substantial Completion, submit to CONTRACTOR a list of observed items requiring correction or completion 932102 Conduct final inspection in the company of the ENGINEER, OWNER and CONTRACTOR and prepare a final list of items to be corrected or completed. 932103 Observe that all items on the final list have been corrected or completed and make recommendations to ENGINEER concerning acceptance. 9 3 3 Limitation of Authority- The Representative shall not ® 9 3 3 1 Authorize any deviations from the Contract Documents or accept any substitute materials or equipment, unless authorized by the ENGINEER 93 3 2 Exceed limitations of ENGINEER'S authority as set forth in the Contract Documents 93 3 3 Undertake any of the responsibilities of the CONTRACTOR, Subcontractors, or CONTRACTOR'S superintendent ® 9 3 3 4 Advise on, or issue directions relative to, or assume control over any aspect of the means, methods, techniques, sequences or procedures for construction unless such is specifically called for in the Contract Documents 9 3 3 5 Advise on or issue directions regarding or assume control over safety precautions and programs in connections with the Work M 9 3 3 6 Accept Shop Drawings or sample submittals from anyone other than the CONTRACTOR. 9 3 3 7 Authorize OWNER to occupy the ® Work in whole or in part 9 3 3 8 Participate in specialized field or ®� laboratory tests or inspections conducted by others except as I specifically authorized by the ENGINEER'- Clarifications and Interpretations: 94 ENGINEER will issue with reasonable promptness such written clarifications or interpretations of the EJCDC GENERAL CONDITIONS 1910-8 (1990 Edition) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000) requirements of the Contract Documents (m the form of Drawings or otherwise) as ENGINEER may determine necessary, which shall be consistent with the intent of and reasonably inferable from the Contract Documents. Such written clarifications and interpretations will be binding on OWNER and CONTRACTOR If OWNER or CONTRACTOR believes that a written clarification or interpretation justifies an adjustment in the Contract Price or the Contract Times and the parties are unable to agree to the; amount or extent thereof, if any, OWNER or CONTRACTOR may make a written claim therefor as provided in Article 11 or Article 12. Authorized Variations in Work: 95 ENGINEER may authorize minor variations in the Work from the requirements of the Contract Documents which do not involve an adjustment in the Contract Price or the Contract Times and are compatible with the design concept of the completed Project as a functioning whole as indicated by the Contract Documents These may be accomplished by a Field Order and will be binding on OWNER and also on CONTRACTOR who shall perform the Work involved promptly If OWNER or CONTRACTOR believes that a Field Order justifies an adjustment in the Contract Price or the Contract Times and the parties are unable to agree as to the amount or extent thereof, OWNER or CONTRACTOR may make a written claim therefor as provided in Article i 1 or 12 Rejecting Defective Work: 96. ENGINEER will have authority to disapprove or reject Work which ENGINEER believes to be defective, or that ENGINEER believes will not produce a completed Project that conforms to the Contract Documents or that will prejudice the integrity of the design concept of the completed Project as a functioning whole as indicated by the Contract Documents. ENGINEER will also have authority to require special inspection or testing of the Work as provided in paragraph 13.9, whether or not the Work is fabricated, installed or completed. Shop .Drawings, Change Orders and Payments: 97 In connection with ENGINEER's authority as to Shop Drawings and Samples, see paragraphs 6 24 through 6 28 inclusive 98 In connection with ENGINEER's authority as to Change Orders, see Articles 10, 11, and 12 99 In connection with ENGINEER's authority as to Applications for Payment, see Article 14. Determinations for Unit Prices: 910 ENGINEER will determine the actual quantities and classifications of Unit Price Work performed by CONTRACTOR ENGINEER will review with CONTRACTOR the ENGINEER's preliminary determinations on such matters before rendering a written decision thereon (by recommendation of an Application 21 paragraphs 11.9 1 through 11 9 3, inclusive), 113 2 where the Work involved is not covered by unit prices contained in the Contract Documents, by a mutually agreed payment basis, including lump sum (which may include an allowance for overhead and profit not necessarily in accordance with paragraph 116 2), 113.3 where the Work involved is not covered by unit prices contained in the Contract Documents and agreement to a lump sum is not reached under paragraph 113 2, on the basis of the Cost of the Work (determined as provided in paragraphs 114 and 11.5) plus a CONTRACTOR's fee for overhead and profit (determined as provided in paragraph 11 6) Cost of the Work: 114 The term Cost of the Work means the sum of all costs necessarily incurred and paid by CONTRACTOR in the proper performance of the Work Except as otherwise may be agreed to in writing by OWNER, such costs shall be in amounts no higher than those prevailing in the locality of the Project, shall include only the following items and shall not include any of the costs itemized in paragraph 11 5 114 1 Payroll costs for employees in the direct employ of CONTRACTOR in the performance of the Work under schedules of job classifications agreed upon by OWNER and CONTRACTOR Such employees shall include without limitation superintendents, foremen and other personnel employed full-time at the site Payroll costs for employees not employed full-time on the Work shall be apportioned on the basis of their time spent on the Work Payroll costs shall tnelude, but no be limited to-, salaries and wages plus the cost of fringe benefits which shall include social security contributions, unemployment, excise and payroll taxes, workers' compensation, health and -ant benefits, —bonuses; ek leave, eation and heliday pay applicable thereto The expenses of performing Work after regular working hours, on Saturday, Sunday or legal holidays, shall be included in the above to the extent authorized by OWNER 114 2. Cost of all materials and equipment furnished and incorporated in the Work, including costs of transportation and storage thereof, and Suppliers' field services required in connection therewith All cash discounts shall accrue to CONTRACTOR unless OWNER deposits funds with CONTRACTOR with which to make payments, in which case the cash discounts shall accrue to OWNER All trade discounts, rebates and refunds and returns from sale of surplus materials and equipment shall accrue to OWNER, and CONTRACTOR shall make provisions so that they may be obtained I 1 4 3 Payments made by CONTRACTOR to the Subcontractors for Work performed or furnished by Subcontractors If required by OWNER, EJCDC GENERAL CONDITIONS 1910-8 (1990 Edition) 24 w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000) CONTRACTOR shall obtain competitive bids from Subcontractors acceptable to OWNER and CONTRACTOR and shall deliver such bids to OWNER who will then determine, with the advice of ENGINEER, which bids, if any, will be accepted. If any subcontract provides that the Subcontractor is to be paid on the basis of Cost of the Work plus a fee, the Subcontractor's Cost of the Work and fee shall be determined in the same manner as CONTRACTOR's Cost of the Work and fee as provided in paragraphs 114, 115, 11.6 and 117. All subcontracts shall be subject to the other provisions of the Contract Documents insofar as applicable 1144 Costs of special consultants (including but not limited to engineers, architects, testing laboratories, surveyors, attorneys and accountants) employed for services specifically related to the Work 114 5 Supplemental costs including the following 1145 1 The proportion of necessary transportation, travel and subsistence expenses of CONTRACTOR's employees incurred in discharge of duties connected with the Work. 11452, Cost, including transportation and maintenance, of all materials, supplies, equipment, machinery, appliances, office and temporary facilities at the site and hand tools not owned by the workers, which are consumed in the performance of the Work, and cost less market value of such items used but not consumed which remain the property of CONTRACTOR. 11453 Rentals of all construction equipment and machinery and the parts thereof whether rented from CONTRACTOR or others in accordance with rental agreements approved by OWNER with the advice of ENGINEER, and the costs of transportation, loading, unloading, installation, dismantling and removal thereof --all in accordance with terms of said rental agreements The rental of any such equipment, machinery or parts shall cease when the use thereof is no longer necessary for the Work 11454 Sales, consumer, use or similar taxes related to the Work, and for which CONTRACTOR is liable, imposed by Laws and Regulations 11 4 5 5. Deposits lost for causes other than negligence of CONTRACTOR, any Subcontractor or anyone directly or indirectly employed by any of them or for whose acts any of them may be liable, and royalty payments and fees for permits and licenses 11456 Losses and damages (and related expenses) caused by damage to the Work, not compensated by insurance or otherwise, sustained by CONTRACTOR in connection with the performance and furnishing of the Work (except 115 5 Costs due to the negligence of losses and damages within the deductible amounts CONTRACTOR, any Subcontractor, or anyone of property insurance established by OWNER in directly or indirectly employed by any of them or for accordance with paragraph 5 9), provided they whose acts any of them may be liable, including but have resulted from causes other than the net limited to, the correction of defective Work, negligence � of CONTRACTOR, any disposal of materials or equipment wrongly supplied Subcontractor, or anyone directly or indirectly and making good any damage to property employed bye any of them or for whose acts any of them may be liable. Such losses shall include I 1 5 6 Other overhead or general expense costs of settlements made with the written consent and any kind and the costs of any item not specifically and approval of OWNER No such losses, damages expressly included in paragraph 114. and expenses shall be included in the Cost of the Work for the purpose of determining 116 The CONTRACTOR's fee allowed to CONTRACTOR's fee If, however, any such loss CONTRACTOR for overhead and profit shall be or damage requires reconstruction and determined as follows CONTRACTOR is placed in charge thereof, CONTRACTOR shall be paid for services a fee 116 1 a mutually acceptable fixed fee, or its proportionate to that stated in paragraph 116 2 116 2 if a fixed fee is not agreed upon, then a fee 11457 The cost of utilities, fuel and sanitary based on the following percentages of the various facilities at the site portions of the Cost of the Work 1 1 4 5 K Minor expenses such as telegrams, 1162 1 for costs incurred under long distance telephone calls, telephone service at paragraphs 114.1 and 1142, the the site, expressage and similar petty cash items in CONTRACTOR's fee shall be fifteen percent, connection width the Work 11622 for costs incurred under 11 4 5 9 Cost of premiums for additional Bonds paragraph 114 3, the CONTRACTOR's fee shall and insurance required because of changes in the be five percent; Work. 11 5 The term Cost of the Work shall not include any of 11623 where one or more tiers of subcontracts are on the basis of Cost of the Work the following plus a fee and no fixed fee is agreed upon, the intent of paragraphs 114 1, 114 2, 114 3 and 11 5 1 Payroll costs and other compensation of 11 6 2 is that the Subcontractor who actually CONTRACTOR's officers, executives, principals (of performs or furnishes the Work, at whatever tier, partnership and sole proprietorships), general managers, will be paid a fee of fifteen percent of the costs engineers, architects, estimators, attorneys, auditors, incurred by such Subcontractor under paragraphs accountants, purichasing and contracting agents, 114 1 and 114 2 and that any higher tier expediters, timekeepers, clerks and other personnel Subcontractor and CONTRACTOR will each be employed by CONTRACTOR whether at the site or in paid a fee ef five pereent of the amount paid to CONTRACTOR's principal or a branch office for the next l^.. of tief c•.i.,.entr..eter to be negotiated general administration of the Work and not specifically in good faith with the OWNER but not to exceed included in the, agreed upon schedule of job five percent of the amount paid to the next lower classifications referred to in paragraph 11.4 1 or tier Subcontractor, specifically covered by paragraph I 1 4 4--all of which are to be considered administrative costs covered by the 1 l 6 2 4 no fee shall be payable on the basis CONTRACTOR's fee of costs itemized under paragraphs 11 4.4, 114.5 and 11.5, I 1 5 2 Expenses of CONTRACTOR's principal and branch offices other than CONTRACTOR's office at 11625. the amount of credit to be allowed the site by CONTRACTOR to OWNER for any change which results in a net decrease in cost will be the 115 3 Any part of CONTRACTOR's capital amount of the actual net decrease in cost plus a expenses, including interest on CONTRACTOR'S deduction in CONTRACTOR's fee by an amount capital employed Ifor the Work and charges against equal to five percent of such net decrease, and 1 CONTRACTOR for delinquent payments 11626 when both additions and credits are 11 5 4 Cost of premiums for all Bonds and for all involved in any one change, the adjustment in insurance whether) or not CONTRACTOR is required CONTRACTOR's fee shall be computed on the all by the Contract Documents to purchase and maintain basis of the net change in accordance with the same (except for the cost of premiums covered by paragraphs 116 2 1 through 11.6 2 5, inclusive subparagraph 11 4I5 9 above) 117 Whenever the cost of any Work is to be EJCDC GENERAL CONDITIONS 1910-3 (1990 Edition) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000) 25 No Text determined pursuant to paragraphs 114 and 115, CONTRACTOR will establish and maintain records thereof in accordance with generally accepted accounting practices and submit in form acceptable to ENGINEER an itemized cost breakdown together with supporting data. Cash Allowances: 11 8 It is understood that CONTRACTOR has included in the Contract Price all allowances so named in the Contract Documents and shall cause the Work so covered to be furnished and performed for such sums as may be acceptable to OWNER and ENGINEER CONTRACTOR agrees that 1181. the allowances include the cost to CONTRACTOR (less any applicable trade discounts) of materials and equipment required by the allowances to be delivered at the site, and all applicable taxes, and 11 8 2 CONTRACTOR's costs for unloading and handling on the site, labor, installation costs, overhead, profit and other expenses contemplated for the allowances have been included in the Contract Price and not in the allowances and no demand for additional payment on account of any of the foregoing will be valid Prior to final payment, an appropriate Change Order will be issued as recommended by ENGINEER to reflect actual amounts due CONTRACTOR on account of Work covered by allowances, and the Contract Price shall be correspondingly adjusted 11.9. Unit Price Work: 11 9 1 Where the Contract Documents provide that all or part of the Work is to be Unit Price Work, initially the Contract Price will be deemed to include for all Unit Price Work an amount equal to the sum of the established unit prices for each separately identified item of Unit Price Work times the estimated quantity of each item as indicated in the Agreement The estimated quantities of items of Unit Price Work are not guaranteed and are solely for the purpose of comparison of Bids and determining an initial Contract Price Determinations of the actual quantities and classifications of Unit Price Work performed by CONTRACTOR will be made by ENGINEER in accordance with paragraph 9 10 119.2 Each unit price will be deemed to include an amount considered by CONTRACTOR to be adequate to cover CONTRACTOR's overhead and profit for each separately identified item 119 3 OWNER or CONTRACTOR may make a claim for an adjustment in the Contract Price in accordance with Article 11 if I 1 9 3 1 the quantity of any item of Unit Price Work performed by CONTRACTOR differs materially and significantly from the estimated quantity of such item indicated in the Agreement; E1CDC GENERAL CONDITIONS 1910-8 (1990 E(hition) 26 w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000) and � J 11932. there is no corresponding adjustment r with respect to any other item of Work; and 11933 if CONTRACTOR believes that LJ CONTRACTOR is entitled to an increase in r_ Contract Price as a result of having incurred additional expense or OWNER believes that OWNER is entitled to a decrease in Contract Price and the parties are unable to agree as to the _ amount of any such increase or decrease. J 11934 CONTRACTOR acknowledges that the OWNER has the right to add or delete items in the Bid or change quantities at OWNER'S sole discretion without affecting the Contract Price of any remaining item so long as the deletion or addition does not exceed twenty-five percent of — the original total Contract Price. u ARTICLE 12--CHANGE OF CONTRACT TIMES 121 The Contract Times (or Milestones) may only be changed by a Change Order or a Written Amendment Any claim for an adjustment of the Contract Times (or Milestones) shall be based on written notice delivered by the party making the claim to the other party and to ENGINEER promptly (but in no event later than thirty days) after the occurrence of the event giving rise to the claim and stating the general nature of the claim Notice of the extent of the claim with supporting data shall be delivered within sixty days after such occurrence (unless ENGINEER allows additional time to ascertain more accurate data in support of the claim) and shall be accompanied by the claimant's written statement that the adjustment claimed is the entire adjustment to which the claimant has reason to believe it is entitled as a result of the occurrence of said event. All claims for adjustment in the Contract Times (or Milestones) shall be determined by ENGINEER in accordance with paragraph 9.11 if J OWNER and CONTRACTOR cannot otherwise agree No claim for an adjustment in the Contract Times (or Milestones) will be valid if not submitted in accordance with the requirements of this paragraph 12.1 12.2. All time limits stated in the Contract Documents r are of the essence of the Agreement 123 Where CONTRACTOR is prevented from completing any part of the Work within the Contract r� Times (or Milestones) due to delay beyond the control of CONTRACTOR, the Contract Times (or Milestones) will be extended in an amount equal to time lost due to such delay if a claim is made therefor as provided in paragraph 12 1 Delays beyond the control of CONTRACTOR shall include, but not be limited to, acts or neglect by OWNER, acts or neglect of utility owners or other contractors performing other work as contemplated ^ by Article 7, fires, floods, epidemics, abnormal weather conditions or acts of God Delays attributable to and u C-J H P, r Lv d R a El 7 #14 within the control of a Subcontractor or Supplier shall be deemed to be delays within the control of CONTRACTOR 124 Where CONTRACTOR is prevented from completing any part of the Work within the Contract Times (or Milestones) due to delay beyond the control of both OWNER and CONTRACTOR, an extension of the Contract Times (or Milestones) in an amount equal to the time lost due to such delay shall be CONTRACTOR's sole and exclusive remedy for such delay In no event shall OWNER be liable to CONTRACTOR, any Subcontractor, any Supplier, any other person or organization, or to any surety for or employee or agent of any of them, for damages arising out of or resulting from (i) delays caused by or within the control of the CONTRACTOR, or (it) delays beyond the ,control of both parties including, but not limited to, fires, floods, epidemics, abnormal weather conditions, acts of God or acts or neglect by utility owners or other contractors performing other work as contemplated by Article 7 ARTICLE 13--TESTS AND INSPECTIONS; CORRECTION, REMOVAL OR ACCEPTANCE OF DEFECTIVE WORK 13.1. Notice of Defects: Prompt notice of all defective Work of which OWNER or ENGINEER have actual knowledge will be given to CONTRACTOR Alll defective Work may be rejected, corrected or accepted as provided in this Article 13 Access to Work: 13 2 OWNER, ENGINEER, ENGINEER's Consultants, other representatives and personnel of OWNER, independent testing laboratories and governmental agencies with jurisdictional interests will have access to the Work at reasonable time forl their observation, inspecting and testing CONTRACTOR shall provide them proper and safe conditions for such access and advise them of CONTRACTOR's site safety procedures and programs so that they may comply therewith as applicable Tests and Inspections: 13 3 CONTRACTOR shall give ENGINEER timely notice of readiness of the Work for all required inspections, tests or approvals, and shall cooperate with inspection and testing personnel to facilitate required inspections or tests 134 OWNER shall' employ and pay for the services of an independent testing laboratory to perform all inspections, tests, or approvals required by the Contract Documents except. 1341 for inspections, tests or approvals covered by paragraph 13 5I below, 1342 that costs incurred in connection with tests or inspections conducted pursuant to paragraph 13 9 below shall be paid as provided in said paragraph 13 9, and 13 4 3 as otherwise specifically provided in the Contract Documents 13 5 If Laws or Regulations of any public body having jurisdiction require any Work (or part thereof) specifically to be inspected, tested or approved by an employee or other representative of such public body, CONTRACTOR shall assume full responsibility for arranging and obtaimng such inspections, tests or approvals, pay all costs in connection therewith, and furnish ENGINEER the required certificates of inspection, or approval. CONTRACTOR shall also be responsible for arranging and obtaining and shall pay all costs in connection with any Inspections, tests or approvals required for OWNER's and ENGINEER's acceptance of materials or equipment to be incorporated in the Work, or of materials, mix designs, or equipment submitted for approval prior to CONTRACTOR's purchase thereof for incorporation in the Work 136 If any Work (or the work of others) that is to be inspecled, tested or approved is covered by CONTRACTOR without written concurrence of ENGINEER, it must, if requested by ENGINEER, be uncovered for observation 13 7 Uncovering Work as provided in paragraph 13.6 shall be at CONTRACTOR's expense unless CONTRACTOR has given ENGINEER timely notice of CONTRACTOR's intention to cover the same and ENGINEER has not acted with reasonable promptness in respon3e to such notice Uncovering Work: 13 8 If any Work is covered contrary to the written request of ENGINEER, it must, if requested by ENGINEER, be uncovered for ENGINEER's observation and replaced at CONTRACTOR's expense 13 9 If ENGINEER considers it necessary or advisable that covered Work be observed by ENGINEER or inspected or tested by others, CONTRACTOR, at ENGINEER's request, shall uncover, expose or otherwise make available for observation, inspection or testing as ENGINEER may require, that portion of the Work in question, furnishing all necessary labor, material and equipment If it is found that such Work is defective, CONTRACTOR shall pay all claims, costs, losses and damages caused by, arising out of or resulting from such uncovering, exposure, observation, inspection and testing and cf satisfactory replacement or reconstruction, (including but not limited to all costs of repair or replacement of work of others), and OWNER shall be entitled to an appropriate decrease in the Contract Price, and, if the parties are unable to agree as to the amount thereof, may make a claim therefor as provided in Article I 1 If, however, such Work is not found to be defective, CONTRACTOR shall be allowed an increase in the Contract Price or an extension of the Contract Times (or Milestones), or both, directly attributable to such EJCDC GENERAL CONDITIONS 1910-8 (1990 Edition) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000) 27 uncovering, exposure, observation, inspection, testing, replacement and reconstruction, and, if the parties are unable to agree as to the amount or extent thereof, CONTRACTOR may make a claim therefor as provided in Articles 11 and 12 OWNER May Stop the Work: 13 10 If the Work is defective, or CONTRACTOR fails to supply sufficient skilled workers or suitable materials or equipment, or fails to furnish or perform the Work in such a way that the completed Work will conform to the Contract Documents, OWNER may order CONTRACTOR to stop the Work, or any portion thereof, until the cause for such order has been eliminated; however, this right of OWNER to stop the Work shall not give rise to any duty on the part of OWNER to exercise this right for the benefit of CONTRACTOR or any surety or other party Correction or Removal of Defective Work: 13 11 If required by ENGINEER, CONTRACTOR shall promptly, as directed, either correct all defective Work, whether or not fabricated, installed or completed, or, if the Work has been rejected by ENGINEER, remove it from the site and replace it with Work that is not defective CONTRACTOR shall pay all claims, costs, losses and damages caused by or resulting from such correction or removal (including but not limited to all costs of repair or replacement of work of others) 13.12. Correction Period: 13 12 1 If within one-year two year after the date of Substantial Completion or such longer period of time as may be prescribed by Laws or Regulations or by the terms of any applicable special guarantee required by the Contract Documents or by any specific provision of the Contract Documents, any Work is found to be defective, CONTRACTOR shall promptly, without cost to OWNER and in accordance with OWNER's written instructions (i) correct such defective Work, or, if it has been rejected by OWNER, remove it from the site and replace it with Work that is not defective, and (it) satisfactorily correct or remove and replace any damage to other Work or the work of others resulting therefrom If CONTRACTOR does not promptly comply with the terms of such instructions, or in an emergency where delay would cause serious risk of loss or damage, OWNER may have the defective Work corrected or the rejected Work removed and replaced, and all claims, costs, losses and damages caused by or resulting from such removal and replacement (including but not limited to all costs of repair or replacement of work of others) will be paid by CONTRACTOR 13 12 2 In special circumstances where a particular item of equipment is placed in continuous service before Substantial Completion of all the Work, the correction period for that item may start to run from an earlier date if so provided in the Specifications or by Written Amendment 13 12 3 Where defective Work (and damage to other EJCDC GENERAL CONDITIONS 1910-8 (1990 Edition) 28 w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000) Work resulting therefrom) has been corrected, removed or replaced under this paragraph 13 12, the correction period hereunder with respect to such Work will be extended for an additional period of ene yeae two year after such correction or removal and replacement has been satisfactorily completed Acceptance of Defective Work: 13 13. If, instead of requiring correction or removal and replacement of defective Work, OWNER (and, prior to ENGINEER's recommendation of final payment, also ENGINEER) prefers to accept it, OWNER may do so. CONTRACTOR shall pay all claims, costs, losses and damages attributable to OWNER's evaluation of and determination to accept such defective Work (such costs to be approved by ENGINEER as to reasonableness) If any such acceptance occurs prior to ENGINEER's recommendation of final payment, a Change Order will be issued incorporating the necessary revisions in the Contract Documents with respect to the Work, and OWNER shall be entitled to an appropriate decrease in the Contract Price, and, if the parties are unable to agree as to the amount thereof, OWNER may make a claim therefor as provided in Article 11. If the acceptance occurs after such recommendation, an appropriate amount will be paid by CONTRACTOR to OWNER OWNER May Correct Defective Work: 13 14 If CONTRACTOR fails within a reasonable time after written notice from ENGINEER to correct defective Work or to remove and replace rejected Work as required by ENGINEER in accordance with paragraph 13.11, or if CONTRACTOR fails to perform the Work in accordance with the Contract Documents, or if CONTRACTOR fails to comply with any other provision of the Contract Documents, OWNER may, after seven days' written notice to CONTRACTOR, correct and remedy any such deficiency In exercising the rights and remedies under this paragraph OWNER shall proceed expeditiously. In connection with such corrective and remedial action, OWNER may exclude CONTRACTOR from all or part of the site, take possession of all or part of the Work, and suspend CONTRACTOR's services related thereto, take possession of CONTRACTOR's tools, appliances, construction equipment and machinery at the site and incorporate in the Work all materials and equipment stored at the site or for which OWNER has paid CONTRACTOR but which are stored elsewhere. CONTRACTOR shall allow OWNER, OWNER's representatives, agents and employees, OWNER's other contractors and ENGINEER and ENGINEER's Consultants access to the site to enable OWNER to exercise the rights and remedies under this paragraph All claims, costs, losses and damages incurred or sustained by OWNER in exercising such rights and remedies will be charged against CONTRACTOR and a Change Order will be issued incorporating the necessary revisions in the Contract Documents with respect to the Work; and OWNER shall be entitled to an appropriate decrease in the Contract Price, and, if the parties are unable to agree as to the amount thereof, OWNER may make a claim therefor as provided in Article 11 Such claims, costs, losses and N ;t 0 j T"] it 14 n 0 I F td damages will include but not be limited to all costs of repair or replacement of work of others destroyed or damaged by correction, removal or replacement of CONTRACTOR'S defective Work CONTRACTOR shall not be allowed an extension of the Contract Times (or Milestones) because of any delay in performance of the Work attributable to the exercise by OWNER of OWNER's rights and remedies hereunder ARTICLE 14—PAYMENTS TO CONTRACTOR AND COMPLETION Schedule of Values: 141 The schedule of values established as provided in paragraph 2 9 will serve as the basis for progress payments and will be incorporated into a form of Application for Payment acceptable to ENGINEER. Progress payments on account of Unit Price Work will be based on the number of units completed Application for Progress Payment. 142 At least twenty days before the date established for each progress payment (but not more often than once a month), CONTRACTOR shall submit to ENGINEER for review an Application for Payment filled out and signed by CONTRACTOR covering the Work completed as of the date of the Application and accompanied by such supporting, documentation as is required by the Contract Documents If payment is requested on the basis of materials and equipment not incorporated in the Work but delivered and suitably stored at the site or at another location agreed to in writing, the Application for Payment shall also be accompanied by a bill of sale, invoice or other documentation warranting that OWNER has received the materials and equipment free and clear of all Liens and evidence that the materials and equipment are covered by appropriate property insurance and other arrangements to protect O WNER's interest therein, all of which will be satisfactory to OWNER The amount of retainage with respect to progress payments will be as stipulated in the Agreement Any funds that are withheld by the OWNER shall not be subject to substitution by the CONTRACTOR with securities or any arrangements involving an escrow or custodianship By executing the application for payment form the CONTRACTOR expressly waives his right to the benefits of Colorado Revised Statutes, Section 24-91-101, et seq CONTRACTOR's WarraniT of Title: 143 CONTRACTOR warrants and guarantees that title to all Work, materials and equipment covered by any Application for Payment, whether incorporated in the Project or not, will pass to OWNER no later than the time of payment free and clear of all Liens Review of Applicationsfor Progress Payment: 144 ENGINEER will, within ten days after receipt of each Application for Payment, either indicate in writing a recommendation of payment and present the Application to OWNER, or return the Application to CONTRACTOR indicating in writing ENGINEER's reasons for refusing to recommend payment In the latter case, CONTRACTOR may make the necessary corrections and resubmit the Application Ten days after presentation of the Application for Payment to OWNER with ENGINEER's recommendation, the amount recommended will (subject to the, provisions of the last sentence of paragraph 14 7) become due and when due will be paid by OWNER to CONTRACTOR 145. ENGINEER's recommendation of any payment requested in an Application for Payment will constitute a representation by ENGINEER to OWNER, based on ENGINEER'S on -site observations of the executed Work as an experienced and qualified design professional and on ENGINEER's review of the Application for Payment and the accompanying data and schedules, that to the best of ENGINEER's knowledge, information and belief 14 5 1 the Work has progressed to the point indicated, 14 5 2. the quality of the Work is generally in accordance with the Contract Documents (subject to an evaluation of the Work as a functioning whole prior to or upon Substantial Completion, to the results of any subsequent tests called for in the Contract Documents, to a final determination of quantities and classifications for Unit Price Work under paragraph 9 10, and to any other qualifications stated in the recommendation), and 14 5 3 the conditions precedent to CONTRACTOR's being entitled to such payment appear to have been fulfilled insofar as it is ENGINEER's lesponsibdity to observe the Work However, by recommending any such payment ENGINEER will not thereby be deemed to have represented that (i) exhaustive or continuous on -site inspections have been made to check the quality or the quantity of the Work beyond the responsibilities specifically assigned to ENGINEER in the Contract Documents or (it) that there may not be other matters or issues between the parties that might entitle CONTRACTOR to be paid additionally by OWNER or entitle OWNER to withhold payment to CONTRACTOR. 146 ENGINEER's recommendation of any payment, including final payment, shall not mean that ENGINEER is responsible for CONTRACTOR's means, methods, techniques, sequences or procedures of construction, or the safety precautions and programs incident thereto, or for any failure of CONTRACTOR to comply with Laws and Regulations applicable to the furnishing or performance of Work, or for any failure of CONTRACTOR to perform or furnish Work in accordance with the Contract Documents. 147 ENGINEER may refuse to recommend the whole or any part of any payment if, in ENGINEER's opinion, it would be incorrect to make the representations to FJCDC GENERAL CONDITIONS 1910-8 (1990 Edition) 29 w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000) OWNER referred to in paragraph 14 5 ENGINEER may also refuse to recommend any such payment, or, because of subsequently discovered evidence or the results of subsequent inspections or tests, nullify any such payment previously recommended, to such extent as may be necessary in ENGINEER's opinion to protect OWNER from loss because 1471 the Work is defective, or completed Work has been damaged requiring correction or replacement, 1472 the Contract Price has been reduced by Written Amendment or Change Order, 1473 OWNER has been required to correct defective Work or complete Work in accordance with paragraph 13 14, or 14 7.4 ENGINEER has actual knowledge of the occurrence of any of the events enumerated in paragraphs 15 2 1 through 15 2 4 inclusive OWNER may refuse to make payment of the full amount recommended by ENGINEER because 14.7 5 claims have been made against OWNER on account of CONTRACTOR's performance or furnishing of the Work, 14 7 6 Liens have been filed in connection with the Work, except where CONTRACTOR has delivered a specific Bond satisfactory to OWNER to secure the satisfaction and discharge of such Liens, 14 7 7. there are other items entitling OWNER to a set- off against the amount recommended, or 14 7 8 OWNER has actual knowledge of the occurrence of any of the events enumerated in paragraphs 14 7 1 through 14 7 3 or paragraphs 15 2 1 through 15 2 4 inclusive, but OWNER must give CONTRACTOR immediate written notice (with a copy to ENGINEER) stating the reasons for such action and promptly pay CONTRACTOR the amount so withheld, or any adjustment thereto agreed to by OWNER and CONTRACTOR, when CONTRACTOR corrects to OWNER's satisfaction the reasons for such action Substantial Completion: 148 When CONTRACTOR considers the entire Work ready for its intended use CONTRACTOR shall notify OWNER and ENGINEER in writing that the entire Work is substantially complete (except for items specifically listed by CONTRACTOR as incomplete) and request that ENGINEER issue a certificate of Substantial Completion. Within a reasonable time thereafter, OWNER, CONTRACTOR and ENGINEER shall make an inspection of the Work to determine the status of completion If ENGINEER does not consider the Work substantially complete, ENGINEER will notify CONTRACTOR in writing giving the reasons therefor If ENGINEER FJCDC GENERAL CONDITIONS 1910-8 (1990 Edition) 30 w/ CITY OF FORT COLLINS MODIFICATIONS (REV 42000) considers the Work substantially complete, ENGINEER will prepare and deliver to OWNER a tentative certificate of Substantial Completion which shall fix the date of Substantial Completion. There shall be attached to the certificate a tentative list of items to be completed or corrected before final payment. OWNER shall have seven days after receipt of the tentative certificate during which to make written objection to ENGINEER as to any provisions of the certificate or attached list If, after considering such objections, ENGINEER concludes that the Work is not substantially complete, ENGINEER will within fourteen days after submission of the tentative certificate to OWNER notify CONTRACTOR in writing, stating the reasons therefor. If, after consideration of OWNER's objections, ENGINEER considers the Work substantially complete, ENGINEER will within said fourteen days execute and deliver to OWNER and CONTRACTOR a definitive certificate of Substantial Completion (with a revised tentative list of items to be completed or corrected) reflecting such changes from the tentative certificate as ENGINEER believes justified after consideration of any objections from OWNER At the time of delivery of the tentative certificate of Substantial Completion ENGINEER will deliver to OWNER and CONTRACTOR a written recommendation as to division of responsibilities pending final payment between OWNER and CONTRACTOR with respect to security, operation, safety, maintenance, heat, utilities, insurance and warranties and guarantees Unless OWNER and CONTRACTOR agree otherwise in writing and so inform ENGINEER in writing prior to ENGINEER's issuing the definitive certificate of Substantial Completion, ENGINEER's aforesaid recommendation will be binding on OWNER and CONTRACTOR until final payment 149 OWNER shall have the right to exclude CONTRACTOR from the Work after the date of Substantial Completion, but OWNER shall allow CONTRACTOR reasonable access to complete or correct items on the tentative list Partial Utilization: 1410. Use by OWNER at OWNER's option of any substantially completed part of the Work, which (i) has specifically been identified in the Contract Documents, or (n) OWNER, ENGINEER and CONTRACTOR agree constitutes a separately functioning and usable part of the Work that can be used by OWNER for its intended purpose without significant interference with CONTRACTOR's performance of the remainder of the Work, may be accomplished prior to Substantial Completion of all the Work subject to the following. 14 10 1 OWNER at any time may request CONTRACTOR in writing to permit OWNER to use any such part of the Work which OWNER believes to be ready for its intended use and substantially complete If CONTRACTOR agrees that such part of the Work is substantially complete, CONTRACTOR will certify to OWNER and ENGINEER that such part of the Work is substantially complete and request ENGINEER to issue a certificate of Substantial Completion for that part of the Work. !,1 771 Ci 0 I n 0 0 1 0 CONTRACTOR at any time may notify OWNER and ENGINEER in writing that CONTRACTOR considers any such part of the Work ready for its intended use and substantially complete and request ENGINEER to issue a certificate of Substantial Completion for that part of the Work Within a reasonable time after either such request, OWNER, CONTRACTOR and ENGINEER shall make an inspection of that part of the Work to determine its status of completion If ENGINEER does not consider that part of the Work to be substantially complete, ENGINEER will notify OWNER and CONTRACTOR in writing giving the reasons therefor If ENGINEER considers that part of the Work to be substantially complete, the provisions of paragraphs 14 8 and 14 9 will apply with respect to certification of Substantial Completion of that part of the Work and the division of responsibility in respect thereof and access thereto. 14 10 2. No occupancy or separate operation of part of the Work will be accomplished prior to compliance with the requirements of paragraph 5 15 in respect of property insurance Final Inspection: 14 11 Upon written notice from CONTRACTOR that the entire Work or an agreed portion thereof is complete, ENGINEER will make a final inspection with OWNER and CONTRACTOR and will notify CONTRACTOR in writing of all particulars in which this inspection reveals that the Work is incomplete or defective CONTRACTOR shall immediately take such measures as are necessary to complete such work or remedy such deficiencies Final Application for Payment: 1412. Afler CONTRACTOR has completed all such corrections to the satisfaction of ENGINEER and delivered in accordance with the Contract Documents all maintenance and operating instructions, schedules, guarantees, Bonds, certificates or other evidence of insurance required by paragraph 5 4, certificates of inspection, marked -up record documents (as provided in paragraph 6 19) and other documents, CONTRACTOR may make application foi final payment following the procedure foi progress payments The final Application for Payment shall be accompanied (except as previously delivered) by (i) all documentation called for in the Contract Documents, including but not limited to the evidence of insurance required by subparagraph 5 4 13, (ii) consent of the surety, if any, to final payment, and (ili) complete and legally effective releases or waivers (satisfactory to OWNER) ofall Liens arising out of or filed in connection with the Work In lieu of such releases or waivers of Liens and as approved by OWNER, CONTRACTOR may furnish receipts or releases in full and affidavit of CONTRACTOR that- (i) the releases and receipts include all labor, services, material and equipment for which a Lien could be filed, and (ii) all payrolls, material and equipment bills, and other indebtedness connected with the Work for which OWNER or OWNERSs property might in any way be responsible have been paid or otherwise satisfied If any Subcontractor or Supplier fails to furnish such a release or receipt in full, CONTRACTOR may firrnish a Bond or other collateral satisfactory to OWNER to indemnify OWNER against any Lien Releases or waivers of liens and the consent of the surety to finalize payment are to be submitted on forms conforming to the format of the OWNER'S standard forms bound in the Project manual. Final Payment and Acceptance: 14 13 If, on the basis of ENGINEER's observation of the Work during construction and final inspection, and ENGINEER's review of the final Application for Payment and accompanying documentation as required by the Contract Documents, ENGINEER is satisfied that the Work has been completed and CONTRACTOR's other obligations under the Contract Documents have been fulfilled, ENGINEER will, within ten days after receipt of the final Application for Payment, indicate in writing ENGINEER's recommendation of payment and present the Application to OWNER for payment At the same time ENGINEER will also give written notice to OWNER and CONTRACTOR that the Work is acceptable subject to the provisions of paragraph 14 15 Otherwise, ENGINEER will return the Application to CONTRACTOR, indicating in writing the reasons for refusing to recommend final payment, in which case CONTRACTOR shall make the necessary corrections and resubmit the Application Thirty days after presentation to OWNER of the Application and accompanying documentation, in appropriate form and substance and with ENGINEER's recommendation and notice of acceplability, the amount recommended by ENGINEER will become due and will be paid by OWNER to CONTRACTOR sub ect to paragraph 176,2 of these General Conditions 14 14 If, through no fault of CONTRACTOR, final completion of the Work: is significantly delayed and if ENGINEER so confirms, OWNER shall, upon receipt of CONCRACTOR's final Application for Payment and recommendation of ENGINEER, and without terminating the Agreement, make payment of the balance due for that portion of the Work fully completed and accepted. If the remaining balance to be held by OWNER for Work not fully completed or corrected is less than the retainage stipulated in the Agreement, and if Bonds have been furnished as required in paragraph 5 1, the written consent of the surety to the payment of the balance due for that portion of the Work fully completed and accepted shall be submitted by CONTRACTOR to ENGINEER with the Application for such payment Such payment shall be made under the terms and conditions governing final payment, except that it shall not constitute a waiver of claims Waiver of Claims: 14 15 The making, and acceptance of final payment will constitute 14 15 1 a waiver of all claims by OWNER against CONTRACTOR, except claims arising from unsettled Liens, from defective Work appearing after EJCDC GENERAL CONDITIONS 1910-8 (1990 Edition) 31 wl CITY OF FORT COLLINS MODIFICATIONS (REV 412000) final inspection pursuant to paragraph 1411, from failure to comply with the Contract Documents or the terms of any special guarantees specified therein, or from CONTRACTOR's continuing obligations under the Contract Documents, and 14 15.2 A waiver of all claims by CONTRACTOR against OWNER other than those previously made in writing and still unsettled. ARTICLE 15--SUSPENSION OF WORK AND TERMINATION OWNER May Suspend Work: 151 At any time and without cause, OWNER may suspend the Work or any portion thereof for a period of not more than ninety days by notice in writing to CONTRACTOR and ENGINEER which will fix the date on which Work will be resumed CONTRACTOR shall resume the Work on the date so fixed CONTRACTOR shall be allowed an adjustment in the Contract Price or an extension of the Contract Times, or both, directly attributable to any such suspension if CONTRACTOR makes an approved claim therefor as provided in Articles 11 and 12 OWNER May Terminate: 15 2. Upon the occurrence of any one or more of the following events 15 2 1 if CONTRACTOR persistently fads to perform the Work in accordance with the Contract Documents (including, but not limited to, failure to supply sufficient skilled workers or suitable materials or equipment or failure to adhere to the progress schedule established under paragraph 2 9 as adjusted from time to time pursuant to paragraph 6 6), 15.2 2. if CONTRACTOR disregards Laws or Regulations of any public body having jurisdiction, 15 2 3. if CONTRACTOR disregards the authority of ENGINEER, or 15.2.4 if CONTRACTOR otherwise violates in any substantial way any provisions of the Contract Documents, OWNER may, after giving CONTRACTOR (and the surety, if any) seven days' written notice and to the extent permitted by Laws and Regulations, terminate the services of CONTRACTOR, exclude CONTRACTOR from the site and take possession of the Work and of all CONTRACTOR's tools, appliances, construction equipment and machinery at the site and use the same to the full extent they could be used by CONTRACTOR (without liability to CONTRACTOR for trespass or conversion), incorporate in the Work all materials and equipment stored at the site or for which OWNER has paid EJCDC GENERAL CONDITIONS 1910-8 (1990 Edition) 32 w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000) CONTRACTOR but which are stored elsewhere, and finish the Work as OWNER may deem expedient. In such case CONTRACTOR shall not be entitled to receive any further payment until the Work is finished If the unpaid balance of the Contract Price exceeds all claims, costs, losses and damages sustained by OWNER arising out of or resulting from completing the Work such excess will be paid to CONTRACTOR If such claims, costs, losses and damages exceed such unpaid balance, CONTRACTOR shall pay the difference to OWNER Such claims, costs, losses and damages incurred by OWNER will be reviewed by ENGINEER as to their reasonableness and when so approved by ENGINEER incorporated in a Change Order, provided that when exercising any rights or remedies under this paragraph OWNER shall not be required to obtain the lowest price for the Work performed 153 Where CONTRACTOR's services have been so terminated by OWNER, the termination will not affect any rights or remedies of OWNER against CONTRACTOR then existing or which may thereafter accrue. Any retention or payment of moneys due CONTRACTOR by OWNER will not release CONTRACTOR from liability. 154 Upon seven days' written notice to CONTRACTOR and ENGINEER, OWNER may, without cause and without prejudice to any other right or remedy of OWNER, elect to terminate the Agreement In such case, CONTRACTOR shall be paid (without duplication of any items) 15 4 1 for completed and acceptable Work executed in accordance with the Contract Documents prior to the effective date of termination, including fair and reasonable sums for overhead and profit on such Work, 15 4 2, for expenses sustained prior to the effective date of termination in performing services and furnishing labor, materials or equipment as required by the Contract Documents in connection with uncompleted Work, plus fair and reasonable sums for overhead and profit on such expenses, 15 4 3 for all claims, costs, losses and damages incurred in settlement of terminated contracts with Subcontractors, Suppliers and others; and 15 4 4 for reasonable expenses directly attributable to termination CONTRACTOR shall not be paid on account of loss of anticipated profits or revenue or other economic loss arising out of or resulting from such termination CONTRACTOR May Stop Work or Terminate: 15 5 If, through no act or fault of CONTRACTOR, the Work is suspended for a period of more than ninety days by OWNER or under an order of court or other public authority, or ENGINEER fails to act on any Application for Payment within thirty days after it is submitted or OWNER fails for thirty days to pay CONTRACTOR any i p�} Hi T C Y T f. f T to R J sum finally determined to be due, then CONTRACTOR may, upon seven days' written notice to OWNER and ENGINEER, and provided OWNER or ENGINEER do not remedy such suspension or failure within that time, terminate the Agreement and recover from OWNER payment on the same terms as provided in paragraph 15 4 In lieu of terminating the Agreement and without prejudice to any other right or remedy, if ENGINEER has failed to act on an Application for Payment within thirty days after it is submitted, or OWNER has failed for thirty days to pay CONTRACTOR any sum finally determined to be due, CONTRACTOR may upon seven days' written notice to OWNER and ENGINEER stop the Work until payment of all such amounts due CONTRACTOR, including interest thereon The provisions of this paragraph 15 5 are not intended to preclude CONTRACTOR from making claim under Articles 11 and 12 for an increase in Contract Price or Contract Times or otherwise for expenses or damage directly attributable to CONTRACTOR's stopping Work as permitted by this paragraph ARTICLE; 16--DISPUTE RESOLUTION If and to the extent that OWNER and CONTRACTOR have agreed on the method and procedure for resolving disputes between them that may arise under this Agreement, such dispute resolution method and procedure, if any, shall be as set forth in Exhibit GC -A, "Dispute Resolution Agreement", to be attached hereto and made a part hereof If no such agreement on the method and procedure for resolving such disputes has been reached, and subject to the provisions of paragraphs 9 10, 9 11 and 9 12, OWNER and CONTRACTOR may exercise such rights or remedies as either may otherwise have under the Contract Documents or by Laws or Regulations in respect of any dispute. ARTICLE; 17—MISCELLANEOUS Giving Notice: 171 Whenever any provision of the Contract Documents requires the giving of written notice, it will be deemed to have been validly given if delivered in person to the individual or to a member of the firm, or to an officer of the corporation for whom it is intended, or if delivered at or sent by registered or certified mail, postage prepaid, to the last business address known to the giver of the notice 17.2. Computation of Time: 17 2 1 When any period of time is referred to in the Contract Documents by days, it will be computed to exclude the first and include the last day of such period. If the last day of any such period falls on a Saturday or Sunday or on a day made a legal holiday by the law of the applicable jurisdiction, such day will be omitted from the computation 17 2 2 A calendar day of twenty-four hours measured from midnight to the next midnight will constitute a day Notice of Claim: 17 3. Should OWNER or CONTRACTOR suffer injury or damage to person or property because of any error, omission or act of the other party or of any of the other parry's employees or agents or others for whose acts the other party is legally liable, claim will be made in writing to the other party within a reasonable time of the first observance of such injury or damage The provisions of this paragraph 17 3 shall not be construed as a substitute for or a waiver of the provisions of any applicable statute of limitations or repose Cumulative Remedies: 174 The duties and obligations imposed by these General Conditions and the rights and remedies available hereunder to the parties hereto, and, in particular but without limitation, the warranties, guarantees and obligations imposed upon CONTRACTOR by paragraphs 6 12, 6 16, 6 30, 6 31, 6 32, 13 1, 13 12, 13 14, 14 3 and 15 2 and all of the rights and remedies available to OWNER and ENGINEER thereunder, are in addition to, and are not to be construed in any way as a limitation of, any rights and remedies available to any or all of them which are otherwise imposed or available by Laws or Regulations by special warranty or guarantee or by other provisions of the Contract Documents, and the provisions of this paragraph will be as effective as if repeated specifically in the Contract Documents in connection with each particular duty, obligation, right and remedy to which they apply Professional Fees and Court Costs Included: 175 Whenever reference is made to "claims, costs, losses and damages", it shall include in each case, but not be limited to, all fees and charges of engineers, architects, attorneys and other professionals and all court or arbitration or other dispute resolution costs 176 The laws of the State of Colorado apply to this Agreement Reference to two pertinent Colorado statutes are as follows, 1761 Colorado Revised Statutes (CRS 8-17-101) require that Colorado labor be employed to perform the Work to the extent of not less than 80 percent LI%) of each type or class of labor in the several classifications of skilled and common labor employed on the proiect Colorado labor means any Person who is a bona fide resident of the State of Colorado at the time of employment, without discrimination as to race color, creed, age, religion or sex 1762 If a claim is filed, OWNER is required by law (CRS 38-26-107) to withhold from all payments to CONTRACTOR sufficient funds to insure the P�+merit of all claim:; for labor, materials, team hire, sustenance, provisions, provender, or other supplies used or consumed by CONTRACTOR or his EJCDC GENERAL CONDITIONS 1910-8 (1990 Edition) 33 w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000) ninety (90) day period, OWNER shall pay to CONTRACTOR such moneys and funds as are not the subject of suit and Its pendens notices, and shall retain only sufficient funds to insure the payment of Judgements which may result from the suit 34 E1CDC GENERAL. CONDITIONS 1910-8 (1990 Edition) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000) El Eli, .z IJ �I m T �F P ?F of, 0 a, �I I I M4 4,l R 0 (This page left blank intentionally ) EJCDC GENERAL CONDITIONS 1910-8 (1990 Edition) 35 w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000) SECTION 00410 I:lii7 T�7�1�] KNOW ALL MEN BY THESE PRESENTS: that we, the undersigned as Principal, and as Surety, are hereby held and firmly bound unto the City of Fort Collins, Colorado, as OWNER, in the sum of $ for the payment of which, well and truly to be made, we hereby jointly and severally bind ourselves, successors, and assigns. THE CONDITION of this obligation is such that whereas the Principal has submitted to the City of Fort Collins, Colorado the accompanying Bid and hereby made a part hereof to enter into a Construction Agreement for the construction of Fort Collins Project, Downtown Streetscape - Phase I; Bid #5512. NOW THEREFORE, (a) If said Bid shall be rejected, or (b) If said Bid shall be accepted and the Principal shall execute and deliver a Contract in the form of Contract attached hereto (properly completed in accordance with said Bid) and shall furnish a BOND for his faithful performance of said Contract, and for payment of all persons performing labor or furnishing materials in connection therewith, and shall in all other respects perform the Agreement created by the acceptance of said Bid, then this obligation shall be void; otherwise the same shall remain in force and effect, it being expressly understood and agreed that the liability of the Surety for any and all claims hereunder shall, in no event, exceed the penal amount of this obligation as herein stated. The Surety, for value received, hereby stipulates and agrees that the obligations of said Surety and its BOND shall be in no way impaired or affected by any extension of the time within which the OWNER may accept such Bid; and said Surety does hereby waive notice of any such extension. Surety Companies executing bonds must be authorized to transact business in the State of Colorado and be accepted by the OWNER. 7/96 Section 00410 Page 1 EJCDC GENERAL CONDITIONS 1910-8 (1990 Edition) 36 w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000) R �'��X L] 0 r'1 0 N] 0 I 0 0 EXHIBIT GC -A to General Conditions of the Construction Contract Between OWNER and CONTRACTOR DISPUTE RESOLUTION AGREEMENT OWNER and CONTRACTOR hereby agree that Article 16 of the General Conditions of the Construction Contract between OWNER and CONTRACTOR is amended to include the following agreement of the parties 161 All claims, disputes and other matters in question between OWNER and CONTRACTOR arising out of or relating to the Contract Documents or the breach thereof (except for claims which have been waived by the making or acceptance of final payment as provided by paragraph 1415) will be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association then obtaining, subject to the limitations of the Article 16 This agreement so to arbitrate and any other agreement or consent to arbitrate entered into in accordance herewith as provided in this Article 16 will be specifically enforceable under the prevailing law of any court having jurisdiction 162. No demand for arbitration of any claim, dispute or other matter that is required to be referred to ENGINEER initially for decision in accordance with paragraph 9 11 will be made; until the earlier of (a) the date on which ENGINEER has rendered a written decision or (b) the thirty-first day after 1he parties have presented their evidence to ENGINEER if a written decision has not been rendered by ENGINEER before that date. No demand for arbitration of any such claim, dispute or other matter will be made later than thirty days after the date on which ENGINEER has rendered a written decision in respect thereof in accordance with paragraph 9 11, and the failure to demand arbitration within said thirty days' period will result in ENGINEER's decision being final and binding upon OWNER and CONTRACTOR If ENGINEER renders a decision after arbitration proceedings have been initiated, such decision may be entered as evidence but will not supersede the arbitration proceedings, except where the decision is acceptable to the parties concerned No demand for arbitration of any written decision of ENGINEER rendered in accordance with paragraph 9.10 will be made later than ten days after the party making such demand has delivered written notice of intention to appeal as provided in paragraph 9 10 163 Notice of the demand for arbitration will be filed in writing with the other party to the Agreement and with the American Arbitration Association, and a copy will be sent to ENGINEER for information. The demand for arbitration will be made within the thirty -day or ten-day period specified in paragraph 16 2 as applicable, and in all other cases within a reasonable time after the claim, dispute or other matter in question has arisen, and in no event shall any such demand be made after the date when institution of legal or equitable proceedings based on such claim, dispute or other matter in question would be barred by the applicable statute of limitations EJCDC GENERAL CONDITIONS 1910-8 (1990 Edition) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 9/99) 164 Except as provided in paragraph 16.5 below, no arbitration arising out of or relating to the Contract Documents shall include by consolidation, joinder or in any other manner any other person or entity (including ENGINEER, ENGINEER's Consultant and the officers, directors, agents, employees or consultants of any of them) who is not a party to this contract unless. 16 4 1 the inclusion of such other person or entity is necessary if complete relief is to be afforded among those who are already parties to the arbitration, and 16 4.2. such other person or entity is substantially involved in a question of law or fact which is common to those who are already parties to the arbitration and which will arise in such proceedings, and 16 4 3 the written consent of the other person or entity sought to be included and of OWNER and CONTRACTOR has been obtained for such inclusion, which consent shall make specific reference to this paragraph, but no such consent shall constitute consent to arbitration of any dispute not specifically described in such consent or to arbitration with any party not specifically identified in such consent. 165 Notwithstanding paragraph 16 4, if a claim, dispute or other matter in question between OWNER and CONTRACTOR involves the Work of a Subcontractor, either OWNER of CONTRACTOR may join such Subcontractor as a party to the arbitration between OWNER and CONTRACTOR hereunder CONTRACTOR shall include in all subcontracts required by paragraph 6 11 a specific provision whereby the Subcontractor consents to being joined in an arbitration between OWNER and CONTRACTOR involving the Work of such Subcontractor Nothing in this paragraph 16 5 nor in the provision of such subcontract consenting to joinder shall create any claim, right or cause of action in favor of Subcontractor and against OWNER, ENGINEER or ENGINEER's Consultants that does not otherwise exist 166 The award rendered by the arbitrators will be final, judgment may be entered upon it in any court having jurisdiction thereof, and it will not be subject to modification or appeal 167 OWNER and CONTRACTOR agree that they shall first submit any and all unsettled claims, counterclaims, disputes and other matters in question between them arising out of or relating to the Contract Documents or the breach thereof ("disputes"), to mediation by the American Arbitration Association under the Construction Industry Mediation Rules of the American Arbitration Association prior to either of them initiating against the other a demand for arbitration pursuant to paragraphs 16 1 through 16 6, unless delay in initiating arbitration would irrevocably prejudice one of the parties The respective thirty and ten day time limits within which to file a demand for arbitration as provided in paragraphs 16 2 and 16 3 above shall be suspended with respect to a dispute submitted to mediation within those same applicable time limits and shall remain suspended until ten days after the termination of the mediation The mediator of any dispute submitted to mediation under this Agreement shall not serve as arbitrator of such dispute unless otherwise agreed GC -Al EJCDC GENERAL CONDITIONS 1910-8 (1990 Edition) GC -Al w/ CITY OF FORT COLLINS MODIFICATIONS (REV 9/94) N p 0 mi �Y IMF 0 1 m 0 i^ Ho I SECTION 00800 SUPPLEMENTARY CONDITIONS 109 No Text I SECTION 00800 SUPPLEMENTARY CONDITIONS Conditions of the Contract These Supplementary Conditions amend or supplement the General Conditions of the Construction Contract (EJCDC General Conditions 1910-8, 1990 edition with City of Fort Collins modifications) and other provisions of the Contract Documents as indicated below. SC-5.4.8 Limits of Liability A. Add the following language at the end of paragraph 5.4.8. The limits of liability for the insurance required by the paragraph numbers of the General Conditions listed below are as follows: 5.4.1 and 5.4 2 Coverage A - Statutory Limits ( Coverage B - $100,000/$100,000/$500,000 5.4.3 and 5.4.5 Commercial General Liability policy will have limits of $1,000,000 combined single limits (CSL). This policy will include coverage for Explosion, Collapse, and Underground coverage unless waived by the Owner. 5.4.6The Comprehensive Automobile Liability Insurance policy will have limits of $1,000,000 combined single limits (CSL). 5.4.9This policy will include completed operations coverage/product liability coverage with limits of $1,000,000 combined single limits (CSL). SC-12.3 Add the following language to the end of paragraph 12.3. Contractor will include in the project schedule '7 days lost due to abnormal weather conditions. 41 01 no d NO No Text �s SECTION 00900 ADDENDA, MODIFICATIONS AND PAYMENT 00950Contract Change Order 00960Application for Payment I Lf Mlrei 0 C'� 02 0 IL fli U �� LJ r� v V SECTION 00950 CHANGE ORDER NO. PROJECT TITLE: Downtown Streetscape - Phase I; Bid No. 5512 CONTRACTOR: PROJECT NUMBER: DESCRIPTION: 1. Reason for change. 2. Description of Change: 3. Change in Contract Cost 4 Change in Contract Time ORIGINAL CONTRACT COST $ 00 TOTAL APPROVED CHANGE ORDER 0 00 TOTAL PENDING CHANGE ORDER 0 00 TOTAL THIS CHANGE ORDER 0 00 TOTAL % OF THIS CHANGE ORDER TOTAL C 0.% OF ORIGNINAL CONTRACT ADJUSTED CONTRACT COST $ 0.00 Assuming all change orders approved) ACCEPTED BY DATE: Contractor's Representative ACCEPTED BY DATE Project Manager REVIEWED BY. DATE: Title. APPROVED BY DATE - Title. APPROVED BY DATE Purchasing Agent over $30,000 CC: City Clerk Contractor Project File Architect Engineer Purchasing 9/99 Section 00950 Page 1 No Text No Text 0 R RR Insert pages 1 - 4 ICJ 0 141 S 0 M Ali Section 00960 Application for Payment No Text go WR --I= am ow - ® -_6 go - age - OWNER: City of Fat Collins IGINEER: CHANOR ORDERS UMBER DATE I 3 3 I Chnge by Change Order APPLICATION FOR PAYMENT PROJECT: CONTRACTOR: APPEcalim Is mdp for Payment as shown below in camneetim wtth Contract AMOUNT I The Present status of the account for this Contract is ►s fw ws: OtUku l Contract Amo nL Net Qunge by Change Order: QmrcaL Contract Amount: TOW Completed And Stored to Date: Less Previow Apphcatlpos: Amount Due this Application - Eeforc Retunage Less Reuainage: $0 00 I AMOUNT DUE THIS APPLICATION: IRTUgCATION: e todusiped CONTRACTOR certifies that all obligations of CONTRACTOR incurred In connection with i Wok have been sYuficd As regW" in Pangrapb 14.3. of the General Conditions of the Contract. it Above Amount Due Ibis Application Is tequcskd by the CONTRACTOR. yntmi of the Above Amosd Due Tbis Application L «commended by the ENOINEER. ate: By: nyakot of oho Above Ammw Due This Application hat boa seviewcd by the OWNER'S Project Manager. ate: By: tymeat of tlu above Amount Due This Application la Approved by the OWNER. ate: By: APPLICATION NUMBII.R. APPLICA I ION DATH PERIOD IIEOINNING. PERIOD INDINU PROJECT NUMBER $0 110 $0 00 $0 aI PAOE 1 Of 4 CONTRACT AMOUNTS lid tam Unit `lumber Description QU-10y Units Prue Amount Work Completd Th4 Mould Qty. Amount "I'LICATION FOR PAYMENT Work Compldd Work Complcted Pmviotu Penode To Usle Qty. Amount Qly. Amami Slorvl lvtot,.rlulo Ilns Peno11 PAIiE 2 OI� 4 Tow "11% A 70 Ilute Pu.' m I1111.d $O.oa $0 a0 $0.00 $0 00 $0 W I Rik $0 00 $0 00 $0.00 $0 00 $lt On 1 IM $0 00 $0 00 $0.00 $o W $0 W lilt( $0.W $0 00 $0 00 $0 00 $0 00 I_IW $0 W $0 00 $0.00 sono $0 00 Jill? $u)o $0 00 $0 00 $0 00 $0 UO 1 lilt $0 DO $0 00 $0 00 $0 00 $0 00 1 Ith $0 00 $0 00 $0 00 $0 W $It oo 1 lilt $0 00 $0 00 $0 00 $000 $11110 I lilt $0 00 10.00 $0 00 _ $D DO $O W I.Rk $0.00 $0 00 $0 00 $000 $1) W LIt It $0 00 $0 00 $0 00 $0 00 $0 W Hilt $0 00 $0 00 $0.00 $0 00 $0 110 1 lilt $0 00 $0.00 $0 00 Stl W $0 oo 1 kit $0.00 $0 DO $0 DO $0 00 $0 00 1 kll $0,00 $0 00 $0.00 $0 00 SOW I Ili? $000 $0.00 $000 $000 $0 W LIM $O.W $O.DO . $000 $0 W 10 W I IM $0 00 $o o0 $0 W $0 W $0 Oil lilt( $000 $0 00 $0.00 $0 Olt $O W 1_kIt $000 $0 00 $000 $000 $O oO I Rk $0 00 $0,00 $0 W $O W $0 Oil 1 kk $0 00 $0 00 to oa $0 no $0 W I RR $000 $000 $0 W $000 SOW 114k $0,00 low $0 W $000 $0 Oil 1 III, $000 $0.00 $000 $000 $0 W 1 lilt $000 $0.00 $0.00 $0.00 $0,04) I lilt $0 00 $0 00 $000 $o Do $0 oo 1 lilt $0 00 $0 00 SO OD $000 $0,00 1 lilt $0 00 $0 00 $0 W $000 $0 W I Rik $000 $0.00 $O.W $000 $0 W I (IR $0 DO $0.00 $0 W $0 W $0 W I III, $0 00 $0 00 $0.00 $000 $0 00 1 14It TOTALS $0 00 $OW $000 SO OO $0 OO $0 Oo 1 lilt / C) C 1 [) C l [ 1 1-1 C 1 I C 1 [ 1 C 1 [) C l C 1 ( l C I [ 1 C 1( I CHANGE ORDERS APPLICATION FOR PAYMENT PACE I OF 4 Work CompleUd Work Comp Wed Work Completed Storcd U6 Month Pmioua Pcdoda To Date Matcnal, 7u1+1 (Sa Inr Unit Ib" Eamcd I'cna ui sub" De "Wdoa Qurdicy Unite Price Amount Qty. Amount Qty. Amount Qty. Amount PcnW To Datc Ild('d $0.00 $0 00 $0 00 i0 00 iO 00 1 tilt j0.00 >V, Ml ►v W i0 OG i0 00 I tilt _ . _ - - - _ - - - - - - - - - j0 W j0 W f0 00 SOW sti W lilt - $0.00 j0 00 $0.00 i0 00 f0 00 I IM $0.00 SO 00 SO 00 $0 W $0 00 I:NIt $0 00 j0 00 SO 00 $OW $0 0() 1 Itl( $0 W $0 00 $0 00 tow $0 00 1 lilt j0 00 $0m $0 00 $0.00 s0 W 1.I41t j0 W $0.00 $0 00 $0.00 i0 ()0 I.Itlt $0.00 $0 00 $0 00 $OW $OW 1 1<IL $O.W j0 W $0 W f0 W $OW 1 lilt $0.00 $0 W $0 W $OW i0 (10 I.Itlt jo.W $0 W so W $0 W $0 00 1 kit j0 W $0 W $0 00 $0 00 $0 00 1 Hit j0 W so W i0 W $0 W $0 00 Itidt 7IAI. CHANGE ORDERS $0 W $0 W i0 W i0 00 j0 W $OW Hilt kwwr TOTAIS $0.00 $OW $0.00 $OW SO 00 $0 W l.l(It STORED MATERIAL SUMMARY Item lavorce Number Numb" Descriptioq 0o H"A Rccievcd Previous Ibis Applic4iou Period hutnllal Thu Period PACE a 01: a Un lluu.l I hi- Applanu.w Su llu Sti till $ti till $u till $u Jill Sri w t $ri till ' Su nu $u tut Su till Sa tin Su tin Sti nn _ SU ou Sti tin $u rill Sri till $ri till TOTALS $0 00 30.00 50.00 Sri au C I C I C 1 C I C .I [ I [ 1 C- I ( 1 [ J C 1 f I C I [ I C I C 1 r i r I r I 0 J IL 111 r C l" J H I L No Text SPECIAL PROVISIONS COLLEGE AVENUE GID SIDEWALK IMPROVEMENTS — PHASE 1 The City of Fort Collins Design Criteria and Standards for Streets, revised July 1996, control construction of this project Also applicable to this project are The City of Fort Collins Storm Drainage Design Criteria and Construction Standards. The CDOT Standard Specifications for Road and Bridge Construction, dated 1991, are also considered minimum standards for compliance on this project. The following Special Provisions supplement or modify the Standard Specifications and take precedence over the Standard Specifications and plans. SPECIAL PROVISIONS Revision of Section 107 — Protection and Restoration of Property Revision of Section 202 — Removals Revision of Section 202 — Sawcutting - Special Revision of Section 203 — Excavation / Embankment Revision of Section 210 — Adjust manholes & valves Revision of Section 306 — Reconditioning Revision of Section 403 — Asphalt Patching . Revision of Section 608 — Colored Concrete Revision of Section 610 — Concrete Sandblasting I Lettering Traffic Control Plan - General Utilities Concrete Paving Aggregate Base Course Stone Pavers Concrete Pavers . Imgation Specifications Miscellaneous Site Furnishings 0 0 0 i 1 2 3 5 7 9 12 13 14 15 Section 02000 Section 02231 Section 02517 Section 02518 Section 02810 Section 02870 IN WITNESS WHEREOF, the Principal and the Surety have hereunto set their hands and seals this day of 20 and such of them as are corporations have caused their corporate seals to be hereto affixed and these presents to b;e signed by their proper officers, the day and year first set forth above. PRINCIPAL Name: Address: By SURETY Title: Title: ATTEST: By: (SEAL) (SEAL) 7/96 Section 00410 Page 2 REVISION OF SECTION 107 PROTECTION AND RESTORATION OF PROPERTY Section 107 of the Standard Specifications is hereby revised for this project to include the following The limits of construction are shown on the plans and represent the maximum extent of disturbance for measurement and payment for any contract items Disturbance beyond these limits may result in costly repairs to existing buildings, sidewalks, and landscaping Any damages to property caused by the Contractor's operations shall be repaired by the Contractor at no cost to The City of Fort Collins The Contractor shall prepare a schedule prior to construction that shows specific measures that will be employed to project private property and existing landscaping from damage during construction The Contractor shall avoid disturbance to existing tree roots during demolition and construction Any exposed tree roots must be inspected by the City Forester prior to burying, cutting, or any other activity in the vicinity of the exposed roots Excavation within the drip line of existing trees shall be minimized If excavation in such areas is required, the Contractor shall consult with the City Forester (221-6361) before beginning the excavation Tree Protection Specifications. A Within the drip line of any protected existing tree, there shall be no cut or fill over a four inch (4") depth unless the City Forester has evaluated and approved the disturbance B Prior to and during construction, barriers shall be erected around all protected existing trees with such barriers to be of orange fencing a minimum of four foot (4') height, secured with metal t- posts, no closer than six feet (6') from the trunk or one-half (1/2) of the drip line, whichever is greater There shall be no storage or movement of equipment, material, debris, or fill within the fenced tree protection zone C The Contractor shall prevent the cleaning of equipment or material or the storage and disposal of _ waste material such as paints, oils, solvents, asphalt, concrete, motor oil or any other material harmful to the life of a tree within the drip line of any protected tree or group of trees D No damaging attachments, wires, signs, or permits shall be fastened to any protected tree E The installation of utilities, irrigation lines, or any underground fixture requiring excavation deeper than six inches shall be accomplished by boring under the root system of protected existing trees at a minimum depth of 24 inches The auger distance is established from the face of the tree (outer back) and is scaled from tree diameter at breast height as described in the chart below u Tree Diameter at Breast Height (Inches) Auger Distance From Face of Tree (Feet) 0-2 1 3-4 2 5-9 5 10-14 10 15-19 12 Over 19 15 END OF SECTION 2 it; �, REVISION OF SECTION 202 REMOVALS Section 202 of the Standard Specifications is hereby revised for this project a, follows Subsection 202 01 is revised to include the following The Contractor shall remove and dispose of all concrete sidewalk, curb and gutter, cross pans, driveways, asphalt pavement, inlets, irrigation structures, pipe, fence, structures, foundations, retaining walls, and any other obstructions that are designated for removal All such removals will be measured in the field and quantities agreed to by the Contractor and the Engineer will be paid for by the square foot at the contract unit price for Remove Highback Curb & Gutter, 4" Concrete Sidewalk, Concrete Pavement, Asphalt Pavement, Brick Pavers. Existing signs, benches, tree grates and bicycle racks designated for removal are to be salvaged, stockpiled on the project site, and reinstalled or surrendered to the City as shown on the plans The Contractor shall protect the tree grates and bicycle racks from damage of any sort until they are reinstalled under the terms of the contract Subsection 202 02 is revised to include the following Disposal Site — Materials designated for removal shalt become property of the Contractor, unless noted on the plans or specifications to be salvaged, stockpiled, or surrendered Iit shall be the Contractor's aresponsibility to obtain a disposal site for all unusable material that is removed Subsection 202 07 is revised to include the following Prior to removal, concrete shall be saw cut full depth to a clean and straight vertical line Pieces of concrete which, due to the Contractor's operations, crack or break beyond the limits of construction shall be saw cut or removed to the nearest joint and removed and replaced at the Contractor's expense The Engineer will determine the limit of the repair Removal of concrete or obstructions as described in section 202 01 beyond the limits designated by the Engineer will be the responsibility of the Contractor and will not be paid for under this section Subsection 202 11 is revised to include the following The Contractor and the Engineer shall field measure and agree upon the quantity to be removed before the work commences Should the Contractor fail to request the Engineer to measure any work, the Contractor shall not be compensated for materials that were not measured by the Engineer The accepted quantities will be paid for at the contract unit price Haul, disposal, and stockpiling of materials will not be measured and paid for separately The contract unit prices and payments shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals for doing all work involved in removals, including haul and disposal as shown on the plans and as specified in these specifications, and as directed by the Engineer END OF SECTION 3 i� REVISION OF SECTION 202 SAWCUTTING - SPECIAL Section 202 02 of the Standard Specifications is hereby revised for this project to include the following Prior to removal, concrete shall be saw cut full depth to a clean and straight vertical line Pieces of concrete which, due to the Contractor's operations, crack or break beyond the limits of construction shall be saw cut or removed to the nearest joint and removed and replaced at the Contractor's expense The Engineer will determine the limit of the repair All sawcutting will be considered incidental to the work and will not be paid for separately The contract unit prices and payments shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals for doing all work involved in removals, including haul and disposal as shown on the plans and as specified in these specifications, and as directed by the Engineer END OF SECTION 4 REVISION OF SECTION 203 EXCAVATION AND EMBANKMENT Section 203 of the Standard Specifications is hereby revised as follows Subsection 203 01 is revised to include the following Excavation — This shall consist of excavation of 2 inches of subgrade material from beneath areas presently covered by 4 inch thick sidewalk or to a depth of 6 inch below proposed grade Tlus section also covers over -excavation and backfill of any locations on the site determined by the Engineer to contain unsuitable material Excavation includes separating the suitable fill material, hauling and disposing of any excess material or unsuitable fill material This item shall be paid only for those areas where additional excavation is required to result in the grades specified on the plans or for cases in which the Contractor originally encounters unsuitable material Over -excavation of material from ram or weather damage will not be paid for and is entirely the Contractor's responsibility Any required excavation is considered incidental to the construction and will not be paid for as a separate item Haul will not be paid for separately, but shall be included in the work for all applicable contract items Embankment — If unsuitable material is encountered and excavated as specified above then aggregate base course shall be placed and compacted according to these specifications This item will be considered incidental to the construction and will not be paid for as a separate item At the discretion of the Engineer on site excavated material may be used as embankment Embankment and subgrade material shall be compacted to 95% of maximum density +/- 2% optimum moisture Maximum density shall be determined by ASTM 698-78 This will apply under the roadway, curb and gutter, sidewalk, and driveways Topsoil shall be compacted to 90% of maximum density at +/- 2% optunum moisture If unsuitable subgrade is encountered and the Engineer directs the Contractor to over excavate the material, the Contractor shall use Aggregate Base Courses (Class 5 or Class 6) to backfill the over excavated area if there is not any acceptable material onsite The proposed material shall meet the following minimum requirements- LL Maximum 30 PI Maximum 6 "R" Value 78 The minimum strength coefficient of the Class 5 Aggregate Base shall be 0 12 Section 203 13 is revised to include the following 9 5 W. The excavations and embankments shall be finished to smooth and uniform surfaces conforming to the 4 typical sections specified Variations from the subgrade plan elevations specified shall not be more that 0 08 feet END OF SECTION REVISION OF SECTION 210 ADJUST MANHOLES, VALVE BOXES, METER BOXES Section 210 of the Standard Specifications is hereby revised as follows Subsection 210 02 is revised to include the following The Contractor shall protect existing manholes, water valves and stop boxes located within the limits of construction from damage When adjustment is required, the existing manholes, valves and stop boxes shall be adjusted to final grade by the Contractor prior to paver and/or concrete placement All work associated with the adjustment of water valves and appurtenances shall be inspected by the engineering inspector and/or the appropriate utility END OF SECTION 7 REVISION OF SECTION 306 RECONDITIONING Section 306 of the Standard Specifications is hereby revised as follows Subsection 306 02 is revised to include the following The top 6" of the entire subgrade shall be reconditioned by scarifying and recompactmg Sufficient water shall be added to meet the density requirements as specified The subgrade shall be thoroughly mixed and moistened to full depth and compacted as specified in Section 203 The reconditioned surface shall not vary above or below the lines and grades as staked by more than 0 04 foot under asphalt, concrete pavement, or pavers The surface shall be tested prior to application of any base course or pavement All defective work shall be corrected as directed The surface shall be satisfactorily maintained until base course or pavement has been placed Subsection 306 04 is revised to include the following The cost to do the required reconditioning shall be incidental to construction No separate payment will be made for reconditioning END OF SECTION 8 ri k i., REVISION OF SECTION 403 HOT BITUMINOUS PAVEMENT - PATCHING Section 403 of the Standard Specifications is hereby revised as follows Subsection 403 01 is revised to include the following This work shall consist of placing the specified depth of Hot Bituminous Pavement (Grading C) over existing pavement or subgrade previously prepared by the Contractor in reasonably close conformity with the lines, grades, thicknesses and typical cross sections shown on the plans or established Subsection 403 02 is revised to include the following Patching shall be performed using a job mix formula approved by the City of Fort Collins for 2000 If not previously approved, the job mix shall be determined by the Contractor and submitted to the Engineer for approval a minimum of one week prior to the beginning of construction The Contractor shall provide the Engineer with a report from an independent testing laboratory acceptable to the Engineer The report shall state the job mix formula, optimum oil content, and recommended mixing and placing temperatures Subsection 403 03 is revised to include the following Patching will be accomplished in the following manner A straight vertical cut shall be made through the pavement to provide a square or rectangular opening, such that each edge of the finished patch will be parallel or at right angles to the direction of traffic Wheel cutting shall not be allowed All patches placed in pavement not to be overlaid shall be sawcut If, in the opinion of the Engineer, the subgrade material for the patch is unsuitable, it shall be removed to the limits and depths designated If asphalt is to be placed in the extra depth, the Contract Unit Price for Patching shall be used for measurement and ,payment If the deepened section is to be filled with Borrow, the excavation will be measured and paid for under Revision of Section 203 - Excavation and the material paid for under the appropriate item found herein The Contractor shall be responsible for the protection of the subgrade/base course until subsequent courses have been placed After the excavation has been completed, the Contractor shall prepare the subgrade by utilizing a vibratory plate, roller, or other compaction device approved by the Engineer After the area to be patched is prepared, the Contractor shall place an emulsified asphalt tack coat on all pavement cut surfaces and on the lip of exposed gutter and crosspan faces that abut these paving areas 9 Emulsified Asphalt for tack coat shall be grade CSS-lh The tack coat shall consist of a 1 1 dilution (one (1) part emulsified asphalt to one (1) part water) The application rate for tack coat shall be approximately 0 1 gallons per square yard Plant Mix Bituminous Base shall be used in all locations except in locations where patching takes place and no overlay is scheduled Plant Mix Bituminous Base shall be placed in the bottom of the patches and shall be left one (1) J to one and one-half (1'/z) inches below the existing street surface to allow the patch to be "topped" with a surface course material The "topping" material shall be Hot Bituminous Pavement (Grading CX) Hot Bituminous Pavement used for "topping" material will be measured and paid for at the Contract Unit Price for Patching In locations where concrete repairs take place in an area of a large patch or in grind areas and the grind operation does not immediately follow the concrete repair (three (3) days), the Contractor _ shall remove no more than six (6) inches of pavement The pavement areas shall be temporarily patched with a minimum of two (2) inches of asphalt These locations shall be paid under the Contract Unit Price for Patching Regardless of the delivery temperature, the mixture shall not be placed for use on the roadway at a temperature lower than 225 ❑ F Pavement areas to be replaced adjacent to concrete repairs shall be completed within three (3) working days of said concrete work Areas requiring reduction in the quantity for Patching shall be deducted from the pay quantity using the following formula Deduct 0 054 Tons Per Square Yard Inch Subsection 403 04 is revised to include the following Patching will be measured by the ton Pavement cutting, excavation, subgrade preparation, haul, disposal, and bituminous materials will not be measured or paid for separately, but shall be included in the contract price for Patching v Load slips shall be consecutively numbered for each day and shall include the batch time Subsection 403 05 is revised to include the following u The accepted quantities for Patching will be paid for at the Contract Unit Price per Ton Payment will be made under Pay Item Pay Unit u Asphalt Patching Ton 10 l The above prices and payments shall include full compensation for furmshing all labor, materials, tools, equipment, and incidentals and for doing all the work involved in Patching, including pavement cutting, excavation, haul, disposal, surface preparation, and bituminous materials, complete -in -place, as shown on these plans, as specified in these specifications, and as directed by the Engineer END OF SECTION r 0 �I 0 0 No Text REVISION OF SECTION 608 COLORED CONCRETE Section 608 of the Standard Specifications is hereby revised for this project to include the following Subsection 608 02 is revised to include the following Proportioning shall conform to the requirements for Class `B" concrete as described in Section 601 for the concrete used in the construction of the sidewalks, access ramps, and curb and gutter Colored concrete for the 4" thick sidewalk will be colored with 1 % lbs per sack of cement using the following pigment Davis No 5237, San Diego Buff, or approved equal After finishing and before the surface of the concrete has dried it shall be protected by the application of a thin coat of Davis W-1000 Clear Cure & Seal or approved equal END OF SECTION 12 REVISION OF SECTION 610 CONCRETE SANDBLASTING — LETTERING Section 610 of the Standard Specifications is hereby revised for this project to include the following Subsection 610 02 shall be modified to include the following Concrete Stain shall be Lith7chrome Grey, manufactured by Cleveland Lithichrome 1024 E Wall Ft Scott, KS 66701 (316) 223-3210 or approved equal Subsection 610 03 shall be modified to include the following • Stencil and lettering shall be Times New Roman font, eight (8) inches high, placed as shown on the plans Pattern and placement shall be approved by the Engineer prior to sandblasting G • Depth of sandblasting shall be a minimum of 3/32 inches and a maximum of 5/32 inches • Sandblasting shall be performed using a fine grained sand • After sandblasting is complete, all sandblasted surfaces shall be thoroughly cleaned All sand particles, loose concrete particles, and foreign debris shall be removed Engineer shall inspect and approve final sandblasted surface prior to application of the stain Stain shall be applied according to the manufacturers specifications and instructions END OF SECTION E 7 H 1 13 TRAFFIC CONTROL PLAN — GENERAL Traffic Control for this project will include significant amounts of pedestrian traffic due to it's location The Contractor's traffic control plan shall specifically include methods of handling pedestrian traffic during the construction Access to all businesses shall remain usable at all times during business hours The bid item for lump sum traffic control shall include the cost of construction and maintenance of a temporary pedestrian walkway to be used during the construction to maintain pedestrian access throughout the duration of the construction END OF SECTION 14 I1 UTILTIES In addition to typical utilities that may exist in and adjacent to this project, electrical services are in place beneath the existing sidewalk on College Avenue These existing services are to remain in their present location beneath the pavement It will be the Contractor's responsibility to protect all existing utilities from damage during the all construction END OF SECTION fl 15 R SECTION 02000 CONCRETE PAVING PART 1 GENERAL 1 1 Description PART 2 PRODUCTS 2 1 Matenal PART 3 EXECUTION 3.1 Sample 3.2 Subgrade for Concrete Paving F SECTION 02000 CONCRETE PAVING PART 1 - GENERAL 1.1 DESCRIPTION A. This section incorporates in its entirety the City of Fort Collins Standard ` Specifications for Streets and Roads with the following revisions: PART 2- PRODUCTS 2.1 MATERIAL A. Imported fill material, if required, shall have a minimum R value of 9. B. Concrete Pavement: 1. Modulus of rupture at 28 days. 700 psi minimum 2 Cement- Type I 3 Maximum water content- 0.49 lb/lb of cement C Forms: 1. Masonite for curved surfaces. 2 2" x 6" Fir for sidewalk and rectangular surface framing D Color Agent. "San Diego Buff' manufactured by Davis Colors �i PART 3 - EXECUTION 3.1 SAMPLE Provide a 4' X 4' sample of proposed concrete walk surface for review by the Owner prior to placement of sidewalks Obtain written authorization to proceed prior to placing remaining walk The sample may become a part of the permanent work if approved by the Owner. If the sample is not approved, the Contractor shall remove the test section from the site and shall place another sample for approval. 32 SUBGRADE FOR CONCRETE PAVING A. ASTM D698, Mimmum Percent Compaction- 95 END OF SECTION COLLEGE AVENUE IMPROVEMENTS CONCRETE PAVING Apn128, 2000 ' 02000 -1 P1 SECTION 02231 AGGREGATE BASE COURSE PART 1 GENERAL 1 1 Section Includes 12 Related Sections 13 Testing 1 4 Protection PART 2 PRODUCTS 2 1 Materials PART 3 EXECUTION 3 1 Examination 3 2 Preparation 3 3 Soil Separator fabric 3 4 Aggregate Placement 3 5 Tolerances 3.6 Field Quality Control SECTION 02231 AGGREGATE BASE COURSE PART 1 - GENERAL 1.1 SECTION INCLUDES A. Aggregate base course B. Subgrade Compaction 12 RELATED SECTIONS A. Section 02000- Concrete Paving B. Section 02517 - Stone Pavers Sand setting bed and Interlocking pavers over base course . C. Section 02518 -Concrete Pavers Sand setting bed and Interlocking pavers over base course 13 TESTING A , R-Value test for moisture stability of base course aggregate. 14 PROTECTION A. Protect all subsurface sleeving and conduit PART 2-PRODUCTS 2,1 MATERIALS A. Aggregate Fill Type. Provide aggregate base course in quantities necessary to conform with the drawings Materials shall be sound, durable particle, free from clay,silt or organic materials. Material shall be 100% crushed with fines graded to the following limits Sieve Size 1" 3/4" 3/8" %Passing 100 70-100 50-80 COLLEGE AVENUE IMPROVEMENTS AGGREGATE BASE COURSE Apn128, 2000 02231 -1 No 4 35-65 No.10 25-50 No.40 15-30 No 200 5-12 B. Soil Separator Fabric. Typar3341, Mirafi 140 or approved equal PART 3 - EXECUTION 3.1 EXAMINATION A Verify subgrade has been inspected, gradients and elevations are correct, and subgrade is dry. 3.2 PREPARATION A. Establish a consistent subgrade depth in conformance with the dimensions shown on the drawings B. Compact subgrade to 95%Standard Proctor Density (ASTM D698) within a moisture content range of 2 percent below to 2 percent above optimum C Determine moisture stability: Moisture stability is determined by R-value testing which shows a maximum 12 point difference in R-values between exudation pressures of 300psi and 100 psi Aggregate base course material shall be tested to determine compliance with these specifications pnor to importation to the site. D. Correct irregularities in substrate gradient and elevation by scarifying, reshaping, and re -compacting. E. Do not place fill, grade or compact on soft, muddy, or frozen surfaces 3.3 SOIL SEPARATOR FABRIC A. Install soil separator fabric over all compacted subgrade areas to receive aggregate base course material Maintain clean edges that do not extend above the final surface of the aggregate base course. Do not disturb once the separator fabric is in place. 3 4 AGGREGATE PLACEMENT A. Spread aggregate over prepared subggrade to the total compacted thickness shown on the drawings. COLLEGE AVENUE IMPROVEMENTS AGGREGATE BASE COURSE April 28, 2000 02231 -2 B. Place aggregate in maximum 6 inch lifts and compact to 98% SPD (ASTM D698) C. Level and contour surfaces to elevations and gradients required to attain the specified finished surface elevations as shown on the drawings. D. Add small quantities of fine aggregate to coarse aggregate as appropriate to assist compaction E Use mechanical tamping equipment in areas inaccessible to compaction equipment 3.5 TOLERANCES A Flatness: Maximum variation of 1/21nch measured with 10 foot straight edge. B. Variation From Design Elevation. Withal 1/2 inch 36 FIELD QUALITY CONTROL A. Compaction testing will be performed m accordance with ASTM D698. B If tests indicate Work does not meet specified requirements, remove Work, replace and retest. C. Frequency of Tests- 1 per 1,000 SF END OF SECTION COLLEGE AVENUE IMPROVEMENTS AGGREGATE BASE COURSE April 28, 2000 02231 -3 SECTION 00420 STATEMENT OF BIDDER'S QUALIFICATIONS All questions must be answered and the data given must be clear and comprehensive. This statement must be notarized. If necessary, questions may be answered on separate attached sheets. The Bidder may submit any additional information he desires. 1. Name oflBidder: _ 2. Permanent main office address: 3. When organized: 4. If a corporation, where incorporated: 5. How many years have you been engaged in the contracting business under your presentlfirm or trade name? 6. Contracts on hand: (Schedule these, showing the amount of each contract and the appropriate anticipated dates of completion.) I 7. Generalicharacter of Work performed by your company: 0 0 10 Have you ever failed to complete any Work awarded to you? If so, where and why? Have your ever defaulted on a contract:'_ If so, iwhere and why? Are you debarred by any government agency? If yes'hist agency name. 7/96 1 Section 00420 Page 1 SECTION 02517 STONE PAVERS PART 1 GENERAL 1.1 Description 1 2 Related Sections 1.3 Submittals 1.4 Submittals for Information 1 5 Mock Ups 1 6 Environmental Requirements PART 2 PRODUCTS 2 1 Paver Materials 2 2 Sand Bed materials 2 3 Accessories 2 4 Source Quality Control 2 5 protection PART 3 EXECUTION 3 1 Examination 3 2 Sand Setting Bed 3 3 New Sandstone Pavers 3 4 Cleaning 3 5 Protection of Finished Work SECTION 02517 STONE PAVERS PART 1 - GENERAL 1.1 DESCRIPTION A. Furnishing and installation of new sandstone pavers B. Furnishing and installation of sand setting; bed. 1.2 RELATED SECTIONS A. Section 02518 - Concrete Pavers B. Section 02231 Aggregate base course Prepared subbase for pavers. 1.3 SUBMITTALS FOR REVIEW A Samples. 1 Submit two l' X 1' samples of each new paver type, illustrating style, size, color range and surface texture of units being provided 1.4 MOCK-UPS A. New sandstone Pavers - Provide paver mockup, 6 feet long by 6 feet wide, which includes setting bed, pavers, joints, and concrete banding Sample may be retained as part of final installation if approved by Engineer. Remove and restore setting bed and reinstall mock up if not acceptable B. Mockups may remain as part of the Work if acceptable to the Engineer. 1 5 ENVIRONMENTAL REQUIREMENTS A At end of working day or during rainy or snowy weather, cover work exposed to weather with waterproof coverings, securely anchored. PART PRODUCTS 21 PAVER MATERIALS COLLEGE AVENUE IMPROVEMENTS STONE PAVERS Apnl 28, 2000 02517-1 A. New Sandstone Pavers: Stone Quarry: Arkin Park, Loveland, Colorado Color- Loveland Buff Dimensions: 3" thick, width and length shall be per the plans and details. Finishes- Saw -cut edges, natural cleft top and bottom surfaces Lips or abrupt changes in the exposed surface of the stone shall not exceed 1/8-inch 2.2 SAND BED MATERIALS A. Sand for Setting Bed and Joints: Clean, washed concrete sand to conform with the following gradation. Sieve Size %Passim 3/8" 100 No 4 90-96 No 100 10-30 23 ACCESSORIES A Cleaning Solution Water at ambient air temperature with a mild detergent Submit sample. 24 SOURCE QUALITY CONTROL A Fabrication Tolerances For Stone Units Within 1/4 inch of actual dimensions 25 PROTECTION A. Protect all stone faces from damage. Use folded blankets, foam rubber etc. to protect stone faces from damage by cables, chains or other abrasive materials to be used for placing stone. B Use only experienced stone masons with a minimum of 5 years experience. Masons shall be experienced in historic renovation work and be familiar with the requirements of handling, cutting ,placing and cleaning historic stones PART 3 EXECUTION 3.1 EXAMINATION COLLEGE AVENUE IMPROVEMENTS STONE PAVERS April 28, 2000 02517-2 A. Verify substrate conditions under provisions of Section 02231 Aggregate Sub base course B. Verify that substrate is smooth, and capable of supporting new sandstone pavers and imposed loads, and ready to receive work of this section. C. Verify gradients and elevations of substrate are correct. Do not proceed if subbase course is not installed per drawings and specifications. 32 SAND SETTING BED A. Screed sand evenly over prepared substrate; surface to a maximum thickness of 1 to 1 1/2 inches. B. Do not disturb or pre -compact sand setting surface after screeding.Regrade sand as required after placement of individual stones 3 3 SANDSTONE PAVERS A. Place new sandstone paver units in pattern as shown on layout plan, from straight reference edge. Form tight joints with no greater than a 1/8" joint dimension. B. Move sandstone pavers with a mechanical or manual hoist, fork lift, block and tackle or similar means Protect sandstone from damage. Handle carefully. C Establish finish grades in conformance with the drawings Place stones with no vertical difference in plane between stones that would create a possible trip surface. D Sprinkle sand over surface. Sweep into joints. Recover with additional sand until firm joints are achieved. Sand shall be filled until flush with the top of stones. i Remove excess sand E Tamp and level paver units with mechanical vibrator until units are firmly bedded, level, and to correct elevation and gradients. 3.4 CLEANING A. Clean sandstone surfaces using cleaning solution prior to sweeping sand into joints. Allow cleaning solution to dry prior to installation of sand. COLLEGE AVENUE IMPROVEMENTS STONE PAVERS ' Apn128, 2000 02517-3 B Use non-metallic tools in cleaning operations. C. Rinse surfaces with clean water. D. Broom clean paving surfaces after final sand operations 3.5 PROTECTION OF FINISHED WORK A. Section 01700 - Contract Closeout: Protecting installed work. B. Do not permit traffic over unprotected paver surface. END OF SECTION COLLEGE AVENUE IMPROVEMENTS STONE PAVERS April 28, 2000 02517-4 0 in PART 1 GENERAL 1.1 Description 1.2 Related Sections 1.3 References 1.4 Submittals for Review 1.5 Submittals for Information PART 2 PRODUCTS 2.1 Manufacturers 2 2 Materials PART 3 EXECUTION 3.1 Examination 3 2 Installation 0 F,J 11: I��s hs'1 I 0 SECTION 02518 CONCRETE PAVERS SECTION 02518 CONCRETE PAVERS PART1- GENERAL 11 DESCRIPTION A Concrete paver units. B. Sand bed and sand joint filler 1.2 RELATED SECTIONS A Section 02000- Concrete Paving B. Section 02231- Aggregate Base Course 13 REFERENCES A. ASTM C936 - Solid Concrete Interlocking Paving Units. 14 SUBMITTALS FOR REVIEW A Section 01300 - Submittals. Procedures for submittals. B Product Data Provide characteristics of paver unit, dimensions, and special shapes C. Samples Submit four samples of each paver size, illustrating style, size, color range and surface texture of units being provided. Construct test panel four feet by four feet for review by Engineer Test panel may become a part of installation if approved by Engineer. 15 SUBMITTALS FOR INFORMATION A Section 01300 - Submittals: Procedures for submittals. B. Manufacturer's Installation Instructions: Submit manufacturer's installation instructions. Indicate substrate requirements, installation methods, and paver thicknesses PART 2-PRODUCTS COLLEGE AVENUE IMPROVEMENTS CONCRETE PAVERS April 28, 2000 02518-1 21 di G 0 L 0 n .I 0 MANUFACTURER A. Manufacturer: 1. Pavestone Company, 9401 E 96`h Avenue, Henderson, Colorado 80640, (303)287-3700. 2 Substitutions. Not permitted 2.2 MATERIALS A. Pavers. Conforming to the following 1 Type. ASTM C936-82 Hydraulically pressed concrete of 8,000 psi minimum, 28 day strength. 2 Freeze/Thaw- Section 8 of ASTM C-67-73 3 Air Entrained: 5 to 7 percent. 4 Moisture Content: 7 percent 5 Moisture Absorption Maximum of 5% 6 Model Holland and Double Holland 7 Nominal Size• a Type 1 Pavers. Holland 2 3/8"H x 4"Wx 8"L b Type 2 Pavers- Double Holland, 2 3/8"H X 8"W X 8"L. c Type 3 Pavers Double Holland, 2 3/8"H X 8"W X 8"L 7. Pattern As Shown on Plans 8 Color Oaks Blend B. Sand Setting Bed and Joints: Clean, washed concrete sand to conform with the following gradation: Sieve Size %Passing 3/8" 100 No 4 90-96 No 100 10-30 PART 3 - EXECUTION 3.1 EXAMINATION A Verify that substrate is level or to correct gradient, smooth, capable of supporting pavers and imposed loads, and ready to receive work of this Section B. Verify gradients and elevations of substrate are correct. 32 INSTALLATION COLLEGE AVENUE IMPROVEMENTS CONCRETE PAVERS April 28, 2000 02518-2 A. Use only experienced installers with 5 years prior experience and training in the installation of concrete pavers B. Screed sand evenly over prepared substrate surface to a maximum thickness of 1 to 1 1/2 inches C. Do not disturb or pre -compact sand setting surface after screeding D. Place paver units in pattern as shown on the plans and details, from straight reference edge. Pavers shall be laid hand tight with care taken to maintain straight and true lines. Joints of pavers in bands shall be aligned with joints of pavers in the fields. E Cutting, where necessary, shall be accomplished with a double bladed splatter or a masonry saw Maintain tight spaced joints F After stones have been installed and the cutting has been completed, the stones shall then be compacted into the loose sand with a plate type vibrating compactor One pass on all areas. G Sweep sand into the joints Vibrate with a plate type compactor until joints are full Joints must be filled all the way to the bottom of the chamfer on the pavers. Sweep off excess sand and remove from the site END OF SECTION COLLEGE AVENUE IMPROVEMENTS CONCRETE PAVERS Apn1 28, 2000 02518-3 SECTION 02810 IRRIGATION SPECIFICATIONS SECTION 02810-IRRIGATION PART 1 • GENERAL 1.01 SCOPE 102 SUBMITTALS 103 RULES AND REGULATIONS 104 TESTING 1 05 106 CONSTRUCTION REVIEW GUARANTEE/WARRANTY AND REPLACEMENT PART 2 MATERIALS 2.01 QUALITY 202 SUBSTITUTIONS 2.03 IRRIGATION TAP AND WATER METER 204 SLEEVING 2.05 PIPE AND FITTINGS 206 MAINLINE COMPONENTS 2.07 SPRINKLER AND BUBBLER IRRIGATION COMPONENTS 208 209 CONTROL SYSTEM COMPONENTS OTHER COMPONENTS PART 3. EXECUTION 3.01 INSPECTIONS AND REVIEWS 3.02 LAYOUT OF WORK 3.03 EXCAVATION, TRENCHING, AND BACKFILLING 3.04 IRRIGATION TAP AND WATER METER 3.05 SLEEVING AND BORING 306 ASSEMBLING PIPE AND FITTINGS 307 INSTALLATION OF MAINLINE COMPONENTS 308 INSTALLATION OF SPRINKLER AND BUBBLER IRRIGATION COMPONENTS 3.09 INSTALLATION OF CONTROL SYSTEM COMPONENTS 3.10 311 INSTALLATION OF OTHER COMPONENTS PROJECT RECORD (AS -BUILT) DRAWINGS 3.12 WINTERIZATION AND SPRING START-UP 3.13 MAINTENANCE 314 CLEANUP E� ,� 1.� .� �� �J K� No Text DIVISION 2-SITE WORK SECTION 02810-IRRIGATION PART 1: GENERAL 1. 01 SCOPE: Furnish all labor, materials, supplies, equipment, tools, and transportation, and perform all operations in connection with and reasonably incidental to the complete installation of the irrigation system, and guarantee/warranty as shown on the drawings, the installation details, and as specified herein Items of work specifically included are: A. Procurement of all applicable licenses, permits. B Coordination of Utility Locates ("Call Before You Dig"). C Excavation, installation, and backfill of tap into municipal water line D Excavation, installation, and backfill of water meter and vault E Maintenance period F Sleeving for irrigation pipe and wire. 1.02 SUBMITTALS A. Refer to Section 01300 - SUBMITTALS for procedures and quantities. B Materials List: Include pipe, fittings, mainline components, water emission components, control system components Coordinate tap, curbstop, water meter, and vault with the City of Fort Collins Water Department. C. Manufacturers' Data- Submit manufacturers' catalog cuts, specifications, and operating instructions for equipment shown on the materials list. D Shop Drawings. Submit shop drawings called for in the installation details Show products required for proper installation, their relative locations, and critical dimensions Note modifications to the installation detail. 1 03 RULES AND REGULATIONS A. Work and materials shall be in accordance with the latest edition of the National Electric Code, the Uniform Plumbing Code as published by the Western t� IJ u 0 H E� NJ Plumbing Officials Association, and applicable laws and regulations of the governing authorities. B. When the contract documents call for materials or construction of a better quality or larger size than required by the above -mentioned rules and regulations, provide the quality and size required by the contract documents C. If quantities are provided either in these specifications or on the drawings, these quantities are provided for information only It is the Contractor's responsibility to determine the actual quantities of all material, equipment, and supplies required by the project and to complete an independent estimate of quantities and wastage 104 TESTING: A. Notify the Owner's Representative three days in advance of testing B. Pipelines jointed with rubber gaskets or threaded connections may be subjected to a pressure test at anytime after partial completion of backfill Pipelines jointed with solvent -welded PVC joints shall be allowed to cure at least 24 hours before testing C W E. e COLLEGE Dec, 1999 Subsections of mainline pipe may be tested independently, subject to the review of the Owner's Representative. Furnish clean, clear water, pumps, labor, fittings, and equipment necessary to conduct tests or retests Hydrostatic Pressure Test 1. Subject mainline pipe to a hydrostatic pressure equal an anticipated operating pressure of 100 PSI for two hours Test with mainline components installed. 2. Backfill to prevent pipe from moving under pressure. Expose couplings and fittings 3. Leakage will be detected by visual inspection Replace defective pipe, fitting, joint, valve, or appurtenance. Repeat the test until the pipe passes test. 4. Cement or caulking to seal leaks is prohibited AVENUEIMPROVEMENTS IRRIGATION 02810 - 1 F Operational Test. 1 Activate each remote control valve in sequence from controller. The Owner's Representative will visually observe operation, water application patterns, and leakage. 2 Replace defective remote control valve, solenoid, wiring, or appurtenance to correct operational deficiencies 3 Replace, adjust, or move water emission devices to correct operational or coverage deficiencies. 4 Replace defective pipe, fitting, joint, valve, sprinkler, or appurtenance to correct leakage problems Cement or caulking to seal leaks is prohibited. 5 Repeat test(s) until each lateral passes all tests. Repeat tests, replace components, and correct deficiencies at no additional cost to the Owner 1 05 CONSTRUCTION REVIEW The purpose of on -site reviews by the Owner's Representative is to periodically observe the work in progress, the Contractor's interpretation of the construction documents, and to address questions with regard to the installation. A. Scheduled reviews such as those for irrigation system layout or testing must be scheduled with the Owner's Representative as required by these specifications B Impromptu reviews may occur at any time during the project C A review will occur at the completion of the irrigation system installation and Project Record (As -Built) Drawing submittal. 1.06 GUARANTEE/WARRANTY AND REPLACEMENT The purpose of this guarantee/warranty is to insure that the Owner receives irrigation materials of prime quality, installed and maintained in a thorough and careful manner. A. For a period of one year from commencement of the formal maintenance period, guarantee/warranty irrigation materials, equipment, and workmanship against defects Fill and repair depressions. Restore landscape or structural features damaged by the settlement of irrigation trenches or excavations. Repair damage to the premises caused by a defective item. Make repairs within seven days of COLLEGE AVENUE IMPROVEMENTS IRRIGATION Dec, 1999 02810 - 2 notification from the Owner's Representative. B Contract documents govern replacements identically as with new work. Make replacements at no additional cost to the contract price. C. Guarantee/warranty applies to originally installed materials and equipment and replacements made during the guarantee/warranty period. PART 2: MATERIALS 2.01 QUALITY. Use materials which are new and without flaws or defects of any type, and which are the best of their class and kind 2.02 SUBSTITUTIONS - Pipe sizes referenced in the construction documents are minimum sizes, and may be increased at the option of the Contractor. 2.03 IRRIGATION TAP AND WATER METER• A Provide materials required by local codes for installation of the murucipal water tap and associated piping. Coordinate with City of Ft Collins Water Department B Provide materials required by local code for installation of the water meter and vault and associated piping. 2 04 SLEEVING. A. Install separate sleeve beneath paved areas to route each run of irrigation pipe or wiring bundle. B. Sleeving material beneath pedestrian pavements shall be PVC Class 200 pipe with solvent welded joints C. Sleeving beneath drives and streets shall be PVC Class 200 pipe with solvent welded J oints. D. Sleeving diameter: as indicated on the drawings and installation details COLLEGE AVENUE IMPROVEMENTS Dec, 1999 IRRIGATION 02810 - 3 2.05 PIPE AND FITTINGS: A. Mainline Pipe and Fittings- Use rigid, unplasticized polyvinyl chloride (PVC) 1120, 1220 National Sanitation Foundation (NSF) approved pipe, extruded from material -- meeting the requirements of Cell Classification 12454-A or 12454-13, v ASTM Standard D1784, with an integral belled end 2. Use Class 200, SDR-21, rated at 200 PSI, conforming to the dimensions and tolerances established by ASTM Standard D2241. Use PVC pipe rated at higher pressures than Class 200 in the case of small nominal diameters which are not manufactured in Class 200 3. Use solvent weld pipe for mainline pipe with a nominal diameter less than 4-inches or where a pipe connection occurs in a sleeve. Use Schedule 40, Type 1, PVC solvent weld fittings conforming to ASTM Standards D2466 and D1784 Use primer approved by the pipe manufacturer Solvent cement to conform to ASTM Standard D2564 B Lateral Pipe and Fittings: Use rigid, unplastimzed polyvinyl chloride (PVC) 1120, 1220 National Sanitation Foundation (NSF) approved pipe, extruded from material meeting the requirements of Cell Classification 12454-A or 12454-13, ASTM Standard D1784, with an integral belled end suitable for solvent welding. `J 2 Use Class 160, SDR-26, rated at 160 PSI, conforming to the dimensions and tolerances established by ASTM Standard D2241 Use solvent weld pipe for lateral pipe. Use primer approved by the pipe u manufacturer. Solvent cement to conform to ASTM Standard D2564, of a type approved by the pipe manufacturer. ^ u C. Specialized Pipe and Fittings. 1 Copper pipe- Use Type "K" rigid conforming to ASTM Standard B88. Use wrought copper or cast bronze fittings, soldered or threaded per the installation details. Use a 95% tin and 5% antimony solder. COLLEGE AVENUE IMPROVEMENTS IRRIGATION Dec, 1999 02810 - 4 v v 2. Ductile iron pipe. Use Class 50 conforming to ANSI A21.51 (AWWA C151). Use mechanical joints conforming to ANSI A 21 10 (AWWA C110) and ANSI A21.11 (AWWA C111) or flanged fittings conforming to ANSI/AWWA C110 and ANSI B16 1 (1259). 3 Use a dielectric union wherever a copper -based metal (copper, brass, bronze) is joined to an iron -based metal (iron, galvanized steel, stainless steel) 4. Low Density Polyethylene Hose- a. Use pipe specifically intended for use as a flexible swing joint. Inside diameter 0.490+0 010 inch. Wall thickness- 0 100±0.010 inch. Color Black. b. Use spiral barb fittings supplied by the same manufacturer as the hose. 5 Assemblies calling for threaded pipe connections shall utilize PVC Schedule 80 nipples and PVC Schedule 80 threaded fittings 6. Joint sealant: Use only teflon-type tape or teflon based paste pipe joint sealant on plastic threads. Use nonhardening, nontoxic pipe joint sealant formulated for use on water -carrying pipes on metal threaded connections. 2 06 MAINLINE COMPONENTS: A. Winterization Assembly: as per local practice and in compliance with local code. B. Backflow Prevention Assembly as presented in the installation details. C. Isolation Gate Valve Assembly as presented in the installation details. Install a separate valve box over a 3-inch depth of 3/4-inch gravel for each assembly D. Quick Coupling Valve Assembly double swing joint arrangement as presented in the installation details. 2 07 SPRINKLER AND BUBBLER IRRIGATION COMPONENTS: COLLEGE AVENUE IMPROVEMENTS IRRIGATION Dec, 1999 02810 - 5 A. Remote Control Valve (RCV) Assembly for Sprinkler and Bubbler Laterals: as presented in the installation details. Use wire connectors and waterproofing sealant to join control wires to solenoid valves Use standard Chn sty I.D. tags with hot -stamped black letters on a yellow background. Install a separate valve box over a 3-inch depth of 3/4-inch gravel for each assembly B Sprinkler Assembly: as presented in the drawings and installation details. Use the sprinkler manufacturer's pressure compensating screens (Rain Bird PCS) to achieve 30 PSI operating conditions on each sprinkler and to control excessive operating pressures. C. Bubbler Assembly: as presented in the drawings and installation details 2.08 CONTROL SYSTEM COMPONENTS. A. Imgation Controller Unit: 1. As presented in the drawings and installation details 2 Primary surge protection arrestors* As recommended by the manufacturer 3 Valve output surge protection arrestors As recommended by the manufacturer. 4 Lightning protection. Provide as recommended by the manufacturer 5. Wire markers: Prenumbered or labeled with indelible nonfading ink, made of permanent, nonfading material B Control Wire: 1. Use American Wire Gauge (AWG) No. 14 solid copper, Type OF or PE cable, UL approved for direct underground burial from the controller unit to each remote control valve. 2 Color: Use white for common ground wire. Use easily distinguished colors for other control wires. Spare control wires shall be of a color different from that of the active control wire Wire color shall be continuous over its entire length. COLLEGE AVENUE IMPROVEMENTS IRRIGATION Dec, 1999 02810 - 6 f 3. Splices. Use wire connector with waterproof sealant. Wire connector to be of plastic construction consisting of two (2) pieces, one piece which snap locks into the other. A copper crimp sleeve to be provided with connector. 4 Warning tape: Inert plastic film highly resistant to alkalis, acids, or other destructive chemical components likely to be encountered in soils. Three inches wide, colored yellow, and imprinted with "CAUTION: BURIED ELECTRIC LINE BELOW" ffm Ell C Instrumentation. 1. Ram Sensor- Provide Mmi-Clik II as manufactured by Glen -Hilton Products, Inc. 2.09 OTHER COMPONENTS A Tools and Spare Parts: Provide operating keys, servicing tools, test equipment, spare parts and other items indicated in the General Notes of the drawings PART 3. EXECUTION 3 01 INSPECTIONS AND REVIEWS A Site Inspections: 1. Verify construction site conditions and note irregularities affecting work of this section. Report irregularities to the Owner's Representative prior to beginning work. 2 Beginning work of this section implies acceptance of existing conditions B Utility Locates ("Call Before You Dig"). 1. Arrange for and coordinate with local authorities the location of all underground utilities 2 Repair any underground utilities damaged during construction. Make repairs at no additional cost to the contract price, C. Imgation System Layout Review: Imgation system layout review will occur after COLLEGE AVENUE IMPROVEMENTS IRRIGATION Dec, 1999 02810 - 7 0 the staking has been completed. Notify the Owner's Representative one week in advance of review. Modifications will be identified by the Owner's Representative at this review 3.02 LAYOUT OF WORK: A Stake out the irrigation system. Items staked include- sprinklers, pipe, control valves, manual drains, controller, and isolation valves. B. Install all mainline pipe and mainline components inside of project property lines. 3.03 EXCAVATION, TRENCHING, AND BACKFILLING- A. Excavate to permit the pipes to be laid at the intended elevations and to permit work space for installing connections and fittings. B Minimum cover (distance from top of pipe or control wire to finish grade): 1. 14-inch over mainline pipe and over electrical conduit. 2 16-inch over control wire. 3 10-inch over lateral pipe to sprinklers and bubblers C PVC or PE lateral pipes may be pulled into the soil utilizing a vibratory plow device specifically manufactured for pipe pulling. Minimum burial depths equals minimum cover listed above D Backfill only after lines have been reviewed and tested. E. Excavated material is generally satisfactory for backfill. Backfill shall be free from rubbish, vegetable matter, frozen materials, and stones larger than 2-inches in maximum dimension. Remove material not suitable for backfill Backfill placed next to pipe shall be free of sharp objects which may damage the pipe. F. Backfill unsleeved pipe in either of the following manners: 1. Backfill and puddle the lower half of the trench. Allow to dry 24 hours. Backfill the remainder of the trench in 6-inch layers. Compact to density of surrounding soil. COLLEGE AVENUE IMPROVEMENTS IRRIGATION Dec, 1999 02810 - 8 ^ LJ rn u CJ 0 It J f., F 4 2. Backfill the trench by depositing the backfill material equally on both sides of the pipe in 6-inch layers and compacting to the density of surrounding soil 3. Enclose pipe and wiring beneath roadways, walks, curbs, etc, in sleeves Minimum compaction of backfill for sleeves shall be 95% Standard Proctor Density, ASTM D698-78 Conduct one compaction test for each sleeved crossing less than 50 feet long. Conduct two compaction tests for each sleeved crossing greater than 50 feet long. Costs for such testing and any necessary retesting shall be borne by the Contractor Use of water for compaction around sleeves, "puddling", will not be permitted. G. Dress backfilled areas to original grade. Dispose of excess backfill off site H Where utilities conflict with irrigation trenching and pipe work, contact the Owner's Representative for trench depth adjustments 3.04 IRRIGATION TAP AND WATER METER A Install the municipal water tap and associated piping materials in conformance with local regulations. B. Install the water meter and vault and associated piping in conformance with local regulations C Coordinate installation with the City of Fort Collins Water Department. 1 3.05 SLEEVING AND BORING: A. Install sleeving at a depth which permits the encased pipe or wiring to remain at the specified burial depth. B. Extend sleeve ends six inches beyond the edge of the paved surface Cover pipe ends and mark with stakes. Mark concrete with a chiseled "x" at sleeve end locations. C Bore for sleeves under obstructions which cannot be removed. Employ equipment and methods designed for horizontal boring 3 06 ASSEMBLING PIPE AND FITTINGS: A. General- TECOLLEGE AVENUE IMPROVEMENTS IRRIGATION Dec, 1999 02810 - 9 11. List the lmore important projects recently completed by your company, stating the approximate cost of each, and the month and year completed, location and type of construction. 12. List your major equipment available for this contract. 13. Experience in construction Work similar in importance to this project': i 14. Background and experience of the principal members of your organization, including officers: 15. Credit available: $ _ 1 16. Bank reference: 17. Will you, upon request, fill out a detailed financial statement and furnish any other information that may be required by the OWNER? 18 19. Are you licensed as a General CONTRACTOR? If yes,i in what city, county and state? class, ilicense and numbers? Do you anticipate subcontracting Work under this Contract? If yes,'what percent of total contract? and to whom? 20. Are any lawsuits pending against you or your firm at this time? If DETAIL 7/96 Section 00420 Page 2 What yes, 1. Keep pipe free from dirt and pipe scale Cut pipe ends square and debur. Clean pipe ends. 2. Keep ends of assembled pipe capped. Remove caps only when necessary to continue assembly. 3. Trenches may be curved to change direction or avoid obstructions within the limits of the curvature of the pipe Minimum radii of curvature is 25 feet for 2-inch diameter pipe, 100 feet for 3- and 4-inch diameter pipe, and 150 feet for 6-inch diameter pipe. All curvature results from the bending of the pipe lengths. No deflection will be allowed at a pipe joint. B Mainline Pipe and Fittings. 1 Use only strap -type fraction wrenches for threaded plastic pipe 2. PVC Rubber-Gasketed Pipe a. Use pipe lubricant. Joni pipe in the manner recommended by manufacturer and in accordance with accepted industry practices 3. PVC Solvent Weld Pipe a Use primer and solvent cement Join pipe in a manner recommended by the manufacturer and in accordance with accepted industry practices b Cure for 30 minutes before handling and 24 hours before allowing water in pipe c Snake pipe from side to side within the trench. 4. Fittings: The use of cross type fittings is not permitted C Lateral Pipe and Fittings- 1 Use only strap -type friction wrenches for threaded plastic pipe. 2 PVC Solvent Weld Pipe a Use primer and solvent cement Join pipe in the manner recommended by the manufacturer and in accordance with COLLEGE AVENUE IMPROVEMENTS IRRIGATION Dec, 1999 02810 - 10 3( C accepted industry practices. b Cure for 30 minutes before handling and 24 hours before allowing water to the pipe. i C. Snake pipe from side to side within the trench. 3. Fittings. The use of cross type fittings is not permitted Specialized Pipe and Fittings: 1 Copper Pipe: a. Buff surfaces to be joined to a bright finish. Coat with solder flux. b Solder so that a continuous bead shows around thejoint circumference 2 Insert a dielectric union wherever a copper -based metal (copper, brass, bronze) and an iron -based metal (iron, galvanized steel, stainless steel) are joined. 3 Low Density Polyethylene Hose. Install per manufacturer's recommendations. 4. PVC Threaded Connections: a. Use only factory -formed threads. Field -cut threads permitted. b. Use only Teflon -type tape or teflon based paste. C. When connection is plastic -to -metal, the plastic car have male threads and the metal component shall h threads 5 Make metal -to -metal, threaded connections with Teflon-ty joint compound applied to the male threads only. INSTALLATION OF MAINLINE COMPONENTS• .LEGE AVENUE IMPROVEMENTS , 1999 are not iponent shall ,ve female ie tape or pipe 02810 — 11 A. Winterization Assembly Install where indicated on the drawings. B Backflow Prevention Assembly. Install where indicated on the drawings Install assembly so that its elevation, orientation, access, and drainage conform to the manufacturer's recommendations and applicable health codes. C Isolation Gate Valve Assembly 1 Install where indicated on the drawings. 2 Locate at least 12-inches from and align with adjacent walls or edges of paved areas D Quick Coupling Valve Assembly Install where indicated on the drawings. 3 08 INSTALLATION OF SPRINKLER AND BUBBLER IRRIGATION COMPONENTS. A Remote Control Valve (RCV) Assembly for Sprinkler and Bubbler Laterals: 1 Flush mainline prior to installation of assembly. 2. Install where indicated on the drawings. Wire connectors and waterproof sealant shall be used to connect control wires to remote control valve wires. Install connectors and sealant per the manufacturer's recommendations 3 Install only one RCV to a valve box Locate valve box at least 12-inches from and align with nearby walls or edges of paved areas Group RCV assemblies together where practical Arrange grouped valve boxes in rectangular patterns Allow at least 12-inches between valve boxes. 4 Adjust RCV to regulate the downstream operating pressure. 5. Attach ID tag with controller station number to control wiring. B. Sprinkler Assembly- 1 Flush lateral pipe before installing sprinkler assembly 2 Install per the installation details at locations shown on the drawings COLLEGE AVENUE IMPROVEMENTS IRRIGATION Dec , 1999 02810 - 12 3C 91 0 W, 31 Locate spray sprinklers 3-inches from adjacent walls, fences, or edges of paved areas Install sprinklers perpendicular to the finish grade. Supply appropriate nozzle or adjust arc of coverage of best performance. Adjust the radius of throw of each sprinkler for best C Bubbler Assembly 1 Flush lateral pipe before installing bubbler assembly. 2 Install bubbler assembly per the installation details at the drawings. INSTALLATION OF CONTROL SYSTEM COMPONENTS. A. Irrigation Controller Unit 1 The location of the controller unit as depicted on the draw approximate, the Owner's Representative will determine tl location upon commencement of contract. sprinkler for shown on ngs is e exact site 2. Lightning protection Drive 8-foot copper -clad grounding 'rod into the soil. If rock prevents driving, bury at least four feet deep Use one rod for each controller. Connect controller to grounding rod with AWG No. 10 solid conductor copper wire. Secure wire to grounding rod with brass or bronze clamp. Locate the connection in a separate valve box. 3. Install primary surge protection arrestors on incoming power lines. 4. Install one valve output surge protection arrestor on each control wire and one for the common wire 5. Attach wire markers to the ends of control wires inside the 'controller unit housing. Label wires with the identification number (see drawings) of the remote control valve to which the control wire is connected. 6. Connect control wires to the corresponding controller terminal .EUE AVENUE IMPROVEMENTS 1999 1RF 16A'11UN 02810 - 13 B. Control Wire• v 1. Bundle control wires where two or more are in the same trench Bundle with pipe wrapping tape spaced at 10-foot intervals. 2 Control wiring may be chiseled into the soil utilizing a vibratory plow device specifically manufactured for pipe pulling and wire installation. u Appropriate chisel must be used so that wire is fed into a chute on the chisel, and wire is not subject to pulling tension Minimum burial depth must equal minimum cover previously listed 3. Provide a 24-inch excess length of wire in an 8-mch diameter loop at each 90 degree change of direction, at both ends of sleeves, and at 100-foot intervals along continuous runs of wiring. Do not tie wiring loop Coil 24-inch length of wire within each remote control valve box 4. Install common ground wire and one control wire for each remote control valve Multiple valves on a single control wire are not permitted. 5 If a control wire must be spliced, make splice with wire connectors and waterproof sealant, installed per the manufacturer's instructions Locate splice in a valve box which contains an irrigation valve assembly, or in a separate 6-inch round valve box. Use same procedure for connection to valves as for in -line splices. 6 Unless noted on plans, install wire parallel with and below PVC mainline pipe. 7. Encase wire not installed with PVC mainline pipe in electrical conduit. C. Instrumentation: 1 Provide Rain Sensor to the Owner for future installation. 3 10 INSTALLATION OF OTHER COMPONENTS. 1. Tools and Spare Parts: 2. Prior to the Review at completion of construction, supply to the Owner operating keys, servicing tools, spare parts, test equipment, and any other items indicated in the General Notes on the drawings COLLEGE AVENUE IMPROVEMENTS IRRIGATION Dec, 1999 02810 - 14 1 1 3 1 1 e 3 3 A. Other Materials- Install other materials or equipment shown on the drawings or installation details to be part of the irrigation system, even though such items may not have been referenced in these specifications. I 1 PROJECT RECORD (AS -BUILT) DRAWINGS• A Maintain on -site and separate from documents used for construction, one complete set of contract documents as Project Documents Keep documents current Do not permanently cover work until as -built information is recorded. B. Record pipe and wiring network alterations. Record work which is installed differently than shown on the construction drawings Record accurate reference dimensions, measured from at least two permanent reference points, of each irrigation system valve, each backflow prevention device, each controller or control unit, each sleeve end, each stub -out for future pipe or wiring connections, and other irrigation components enclosed within a valve box C. Prior to construction completion, obtain from the Owner's Representative a reproducible mylar copy of the drawings. Mylars or CAD data files compatible with AutoCAD software, can be purchased from the Engineer. Cost of mylar reproducible drawings is $25 per sheet and the cost of AutoCAD data files on diskette is $25 per file Using technical drafting pen or CAD, duplicate information contained on the project drawings maintained on site 1 Label each sheet "Record Drawing". Completion of the Record Drawings will be a prerequisite for the Review at the completion of the irrigation system installation WINTERIZATION AND SPRING START-UP: A. Winterize the irrigation system in the fall of 1994 and start-up the�irrigation system in the spring of 1995. Repair any damage caused in improper winterization at no additional cost to the Owner. Coordinate the interization and start-up with the landscape maintenance personnel MAINTENANCE: A. Upon completion of construction and Review by the Owner's Representative, maintain irrigation system for a duration of 30 calendar days Make periodic examinations and adjustments to irrigation system components so i s to achieve the most desirable application of water B. Following completion of the Contractor's maintenance period, the Owner will be responsible for maintaining the system in working order during the remainder of CO�LEGE AVENUE Dec., 1999 IMUA'I WN 02810 - 15 the guarantee/warranty period, for performing necessary minor maintenance, for trimming around sprinklers, for protecting against vandalism, and for preventing damage after the landscape maintenance operation. 3 14 CLEANUP A. Upon completion of work, remove from the site all machinery, tools, excess materials, and rubbish. END OF SECTION COLLEGE AVENUE IMPROVEMENTS IRRIGATION Dec, 1999 02810 - 16 SECTION 02870 MISCELLANEOUS SITE FURNISHINGS PART 1 GENERAL 1 A Section Includes 1.2 Related Section 1.3 Submittals for Review PART 2 MATERIALS 2.1 Existing Bench 2.2 Existing Trash Receptacles 2.3 Existing Bike Rack 2 4 Existing Tree Grate 2 5 Drain Inlet Grate 2.6 Existing Bollard 2 7 Miscellaneous Hardware 2 8 Protection PART 3 EXECUTION 3.1 Existing Trash Receptacle 3 2 Existing Bike Rack 3.3 Existing Tree Grate 3 4 Dram Inlet Grate 3.5 Existing Bollard PART 4 GUARANTY/WARRANTY SECTION 02870 MISCELLANEOUS SITE FURNISHINGS PART 1 -GENERAL A. SECTION INCLUDES A Existing Bench B Existing Trash Receptacle C. Existing Bike Rack D Existing Tree Grate E Dram Inlet F Existing Bollards G. Miscellaneous Hardware H. Samples B RELATED SECTIONS A Section 02000- Concrete Paving B Section 02518 - Concrete Pavers. C SUBMITTALS FOR REVIEW A Shop drawings, technical literature from the manufacturer for each of the following• A Dram Inlet Grate PART 2 - MATERIALS 2 1 EXISTING BENCH Manufacturer• Not Applicable, existing benches to be removed protected in place. See layout plan for locations of existing benches. ` 22 EXISTING TRASH RECEPTACLE Manufacturer- Not Applicable, existing trash receptacles to be removed and — reinstalled after pavement is in place See layout plan for locations. Mounting: Surface mount Fastening hardware shall be approved by the City Representative. COLLEGE AVENUE IMPROVEMENTS SITE FURNISHINGS April 28, 2000 02870 -1 _ u �J 2 2 2.: 2 2 A A 1 EXISTING BIKE RACK Manufacturer. Not Applicable, existing bicycle racks to be removed and ri after pavement is in place. See layout plan for locations Mounting Surface mount. Fastening hardware shall be approved by Representative. EXISTING TREE GRATE Manufacturer- Not Applicable, existing tree grates to be removed and i after pavement and tree grate supports are in place. See layout plan for Mounting: Per plans and details. I7:7_\10ih71DTIlKe :7_VY�1 Manufacturer: Urban Accessories, 20004 144" Avenue NE, W1 (206)487-0488 Model: STD Size 24" square Mounting Per plans and details. Manufacturer. Not Applicable, existing bollards to be removed and re after pavement are in place See layout plan for locations Mounting. Install bollards per the bollard manufacturer's instructions MISCELLANEOUS HARDWARE A. Hardware: All hardware including nuts, bolts, and washers, shall be an shall conform to ASTM A307. B. ExpansionBolts- Expansion bolts and anchors shall be galvanized. bolts are to fasten to concrete, they shall be Hilti "KWIK BOLT" c Where expansion bolts are used to fasten to concrete block c construction, they shall be "RAWLY anchors or approved equal. PROTECTION A. Protect all painted surfaces from cracking or chipping during i installation Use blankets, tarps etc. to protect paint surfaces the City WA 98072, plated, here expansion pproved equal. other masonry ,EGE AVENUE IMPROVEMENTS SITE 28, 2000 1, storage and handling and 02870 -2 No Text storing — B. Do not accept materials damaged during shipping. Damaged parts shall not be accepted. If minor repairs are required it shall be at the discretion of the Engineer whether the items are acceptable. C Verify proper operation of all equipment prior to acceptance. Contractor shall be ^ responsible for proper operation of all materials. PART 3 - EXECUTION 3 1 Existing Trash Receptacles Fasten in place per the manufacturers instructions or as approved by the City Representative Install in locations shown on the plans and details The City's representative shall approve the final location of the trash receptacles prior to fastening them in place. The contractor shall notify the City's Representative a minimum of twenty-four (24) hours in advance of mounting the trash receptacles 3 2 Existing Bike Racks Fasten in place per the manufacturers instructions or as approved by ^ the City Representative Install bike racks in locations shown on the layout plans The City's representative shall approve the final location of the bike racks prior to fastening them in place The contractor shall notify the City's Representative a minimum of twenty-four (24) hours in advance of fastening the bike racks 3 3 Existing Tree Grates Install tree grates in locations shown on the layout plans Tree grates shall be installed so that the top surface of the tree grate is no more than 1/8" above or below adjacent surfaces at any point 34 Drain Inlet Grate Install drain inlet grate per the details and the manufacturer's instructions Install in locations shown on the plans and details Drain inlet grates shall be installed so that the top surface of the grate is no more than 1/8" above or below adjacent surfaces at any point. 3 5 Existing Bollard. Fasten in place per the manufacturers instructions or as approved by the City Representative. Install bollards in locations shown on the layout plans The City's representative shall approve the final location of the bollards prior to fastening them in place u The contractor shall notify the City's Representative a minimum of twenty-four (24) hours in advance of fastening the bollards. PART 4-GUARANTY[WARRANTY D. Guaranty/Warranty all new products under this section for a period of one year from •� the date of Substantial Completion. In addition to the manufacturer's product ^ u COLLEGE AVENUE IMPROVEMENTS SITE FURNISHINGS Apnl 28, 2000 02870 -3 v J N 0 0 0 Guaranty/ Warranty, the Contractor shall Guaranty/Warranty the installation of all new and re -installed products in this section exclusive of normal wear and tear and damage caused out of the Control of the Contractor. This Guaranty/Warranty shall extend to removal and replacement of any defective materials or damaged products ansmg out of the failure of the product or improper installation of jthe Contractor. .EGE AVENUE 28, 2000 END OF SECTION 02870 -4 No Text 21 22 What are the limits of your public liability? DETAIL what company? What are your company's bonding limitations? 23. The undersigned hereby authorizes and requests any person, firm or corporation to furnish any information requested by the OWNER in verification of the recital comprising this Statement of Bidder's Qualifications. Dated at this day of 20_ Name of Bi By: Title: State of_ County Of being duly sworn deposes and says that he is of and that (name of organization) the answers to the foregoing questions and all statements therein contained are true and correct. Subscribed and sworn to before me this day of 20 . NotarylPublic My commission expires 7/96 Section 00420 Page 3 No Text SECTION 00430 SCHEDULE OF SUBCONTRACTORS List all subcontractors for the work items listed below and all subcontractors performing over 100 of the contract. ITEM SUBCONTRACTOR 7/96 Section 00430 Page 1 No Text 0 r �J l K, L� 'Lill R P CONTRACT DOCUMENTS TABLE OF CONTENTS Section BID INFORMATION 00020 Notice Inviting Bids 00100 Instruction to Bidders 00300 Bid Form 00400 Supplements to Bid Forms 00410 Bid Bond 00420 Statements of Bidders Qualifications 00430 Schedule of Major Subcontractors CONTRACT DOCUMENTS 00500 Agreement Forms 00510 Notice of Award 00520 Agreement 00530 Notice to Proceed 00600 Bonds and Certificates 00610 Performance Bond 00615 Payment Bond 00630 Certificate of Insurance 00635 Certificate of Substantial Completion 00640 Certificate of Final Acceptance 00650 Lien Waiver Release(Contractor) 00660 Consent of Surety 00670 Application for Exemption Certificate CONDITIONS OF THE CONTRACT 00700 General Conditions Exhibit GC -A 00800 Supplementary Conditions 00900 Addenda, Modifications, and Payment 00950 Contract Change Order 00960 Application for Payment SPECIFICATIONS Pages 00020-1 - 00020-2 00100-1 - 00100-9 00300-1 - 00300-3 00400-1 00410-1 - 00410-2 00420-1 - 00420-3 00430-1 00500-1 00510-0 00520-1 - 00520-6 00530-1 00600-1 00610-1 - 00610-2 00615-1 - 00615-2 00630-1 00635-1 00640-1 00650-1 - 00650-2 00660-1 00670-1 - 00670-2 00700-1 - 00700-34 GC -Al - GC-A2 00800-1 - 00800-2 00900-1 00950-1 - 00950-2 00960-1 - 00960-2 No Text M, E 7;� 0 0 SECTION 00020 INVITATION TO BID SECTION 00300 BID FORM No Text E R ru- K SECTION 00020 INVITATION TO BID Date: May 22, 2000 Sealed Bids will be received by the City of Fort Collins (hereinafter referred to as OWNER), at the office of the Purchasing Division, 256 West Mountain Avenue, Fort Collins, Colorado until 3:00 P.M., our clock, on Monday, June 26, 2000, for r the Downtown Streetscape, Bid No. 5512. c° At said place and time, and promptly thereafter, all Bids that have been duly received will be publicly opened and read aloud. The Contract Documents provide for replacing the existing tile pavers in the pedestrian bulbs/sidewalks in the following areas: Mountain Avenue and College Avenue (SE corner only), and Olive and College (primarily the two north corners, and a smaller amount of work on the south corners). The work will include removing the existing tile pavers and underlying concrete, establishing new grades to improve surface drainage in the bulbs, installing new concrete pavers on a compacted aggregate/sand base, and replacement of selected curb and gutter with required street repairs. Also included is removal and replacement of storm drainage systems at the corners including storm drain pipe, inlets, and manholes. Also included is installation and extension of irrigation systems. All Bids must be in accordance with the Contract Documents on file with The City of Fort Collins, 256 West Mountain Avenue, Fort Collins, Colorado 80521. Contract Documents will be available Friday, May 26, 2000. Copies of the Contract Documents, complete with Construction Specifications and Drawings, may be obtained from Purchasing Division at 256 West Mountain Avenue, Fort Collins, Colorado, 80521 upon payment of a refundable fee of Fifty dollars ($50.00) per set. No partial sets will be issued. The Contract Documents and Construction Drawings may be examined at: 1. City of Fort Collins, Purchasing Division. 2. The Daily Journal, 2000 S. Colorado Blvd. Suite 2000, Denver, Colorado. 3. CMD Denver Plan Room, 9250 E Costilla Ave, STE 400, Englewood, CO 4. Builders Exchange, 223 South Link Lane, Fort Collins, Colorado. 5. The Plan Room, 2176 South Jasmine St. Door "Ell/Suite 219, Denver, Colorado. A prebid conference and job walk with representatives of prospective Bidders will be held at 10:00 a.m. on Tuesday, June 6, 2000, in the Engineering Conference room at 281 N. College Avenue, Fort Collins, Colorado. 7/96 Section 00020 Page 1 RR i, Prospective Bidders are invited to present their questions relative to this Bid proposal at this meeting. Bids will be received as set forth in the Bidding Documents. The Work is expected to be commenced within the time as required by Section 2.3 of General Conditions. Substantial Completion of the Work is required as specified in the Agreement. �. The successful Bidder will be required to furnish a Performance Bond and a Payment Bond guaranteeing faithful performance and the payment of all bills and obligations arising from the performance of the Contract. No Bid may be withdrawn within a period of forty-five (45) days after the date fixed for opening Bids. The OWNER reserves the right to reject any and all Bids, and to waive any informalities and irregularities therein. Bid security in the amount of not less than 50 of the total Bid must accompany each Bid in the form specified in the Instructions to Bidders. Sales Prohibited/Conflict of Interest: No officer, employee, or member of City Council, shall have a financial interest in the sale to the City of any real or personal property, equipment, material, supplies or services where such officer or employee exercises directly or indirectly any decision -making authority concerning such sale or any supervisory authority over the services to be rendered. This rule also applies to subcontracts with the City. Soliciting or accepting any gift, gratuity favor, entertainment, kickback or any items of monetary value from any person who has or is seeking to do business with the City of Fort Collins is prohibited City of Fort Collins B TP m s B. O'Neill, II, CPPO hasing/Risk Management Director 1< 7/96 Section 00020 Page 2 U m e, MU R N R a �� No Text 10 E Fil 0 m '� 0 2;.� Y P, k �'y SECTION 00100 INSTRUCTIONS TO BIDDERS u LJ u SECTION 00100 INSTRUCTIONS TO BIDDERS 1.0 DEFINED TERMS Terms used in these Instructions to Bidders which are defined in the Standard General Conditions of the Construction Contract (No. 1910-8, 1990 ed.) have the meanings assigned to them in the General Conditions. The term "Bidder" means one who submits a Bid to OWNER, as distinct from a sub - bidder, who submits a Bid to Bidder. The terms "Successful Bidder" means the lowest, qualified, responsible and responsive Bidder to whom OWNER (on basis of OWNER's evaluation as hereinafter provided) makes an award. The term "Bidding Documents" includes the Advertisement or Invitation to Bid, Instructions to Bidders, the Bid Form, and the proposed Contract Documents (including all Addenda issued prior to receipt of Bids). 2.0 COPIES OF BIDDING DOCUMENTS 2.1. Complete sets of Bidding Documents may be obtained as stated in the Invitation to Bid. No partial sets will be issued. The Bidding Documents may be examined at the locations identified in the Invitation to Bid. 2.2. Complete sets of Bidding Documents shall be used in preparing Bids; neither OWNER nor Engineer assumes any responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents. y 2.3. The submitted Bid proposal shall include Sections 00300, 00410, 00420, and 00430 fully executed. 2.4. OWNER and Engineer, in making copies of Bidding Documents available on the above terms, do so only for the purpose of obtaining Bids on the Work and do not confer a license or grant for any other use. 3.0 QUALIFICATION OF BIDDERS 3.1 To demonstrate qualifications to perform the Work, each Bidder must submit at the time of the Bid opening, a written statement of qualifications including financial data, a summary of previous experience, previous commitments and evidence of authority to conduct business in the jurisdiction where the Project is located. Each Bid must contain evidence of Bidder's qualification to do business in the state where the Project is located or covenant to obtain such qualification prior to award of the contract. The Statement of Qualifications shall be prepared on the form provided in Section 00420. Section 001.00 Page 1 3.2. In accordance with Section 8-159 of the Code of the City of Fort `J Collins in determining whether a bidder is responsible, the following shall be considered: (1) The ability, capacity and skill of the bidder to perform the contract or provide the services required, (2) whether the bidder can perform the contract or provide the service promptly and within the time specified without delay or interference, (3) the character, integrity, reputation, judgment, experience and efficiency of the bidder, (4) the quality of the bidder's performance of previous contracts or services, (5) the previous and existing compliance by the bidder with laws and ordinances relating to the contract or service, (6) the sufficiency of the financial resources and ability of the bidder to perform the contract or provide the service, (7) the quality, availability and adaptability of the materials and services to the particular use required, (8) the ability of the bidder to provide future maintenance and service for the use of the subject of the contract, and (9) any other circumstances which will affect the bidder's performance of the contract. 3.3. Each Bidder may be required to show that he has handled former Work so that no just claims are pending against such Work. No Bid will be accepted from a Bidder who is engaged on any other Work which would impair his ability to perform or finance this Work. u 3.4 No Bidder shall be in default on the performance of any other contract with the City or in the payment of any taxes, licenses or other monies due to the City. 4.0 EXAMINATION OF CONTRACT DOCUMENTS AND SITE v 4.1. It is the responsibility of each Bidder, before submitting a Bid, to (a) examine the Contract Documents thoroughly, (b) visit the site to familiarize himself with local conditions that may in any manner affect cost, progress or performance of the Work, (c) familiarize himself with federal, state and local laws, ordinances, rules and regulations that may in any manner affect cost, progress or performance of the Work, (d) study and carefully correlate Bidder's observations with the Contract Documents, and (e) notify Engineer of all conflicts, errors or discrepancies in the Contract Documents. 4.2. Reference is made to the Supplementary Conditions for identification of: Subsurface and Physical Conditions SC-4.2. 4.3. The submission of a Bid will constitute an incontrovertible , representation by Bidder that Bidder has complied with every requirement of this Article 4, that without exception the Bid is premised upon performing and furnishing the Work required by the Contract Documents and such means, methods, techniques, sequences or procedures of construction as may be 7/96 Section 00100 Page 2 "" M indicated in or required by the Contract Documents, and that the Contract Documents are sufficient in scope and detail to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work. 5.0 INTERPRETATIONS AND ADDENDA. 5.1. All questions about the meaning or intent of the Bidding Documents are to be submitted in writing to the Engineer and the OWNER. Interpretation or clarifications considered necessary in response to such questions will be issued only by Addenda. Questions received less than seven days prior to the date for opening of the Bids may not be answered. Only questions answered by formal written Addenda will be binding. Oral and other interpretations or clarifications will be without legal effect. 5.2. All questions concerning the scope of this project should be directed to the Engineer. Questions regarding submittal of bids should be directed to the City of Fort Collins' Purchasing Division. 5.3. Addenda may also be issued to modify the Bidding Documents as deemed advisable by OWNER or Engineer. 5.4. Addenda will be mailed or delivered to all parties recorded by the OWNER as having received the Bidding documents. 6.0 BID SECURITY a6.1. Each Bid must be accompanied by Bid Security made payable to OWNER in the amount stated in the Invitation to Bid. The required security must be in the form of a certified or bank cashier's check payable to OWNER or a Bid Bond on the form enclosed herewith. The Bid Bond must be executed by a surety meeting the requirements of the General Conditions for surety bonds. 6.2. The Bid Security of the successful Bidder will be retained until such Bidder has executed the Agreement and furnished the required contract security, whereupon Bid Security will be returned. If the successful Bidder fails to execute and deliver the Agreement and furnish the required contract security within 15 days of the Notice of Award, OWNER may annul the Notice of Award and the Bid Security of that Bidder will be forfeited. The Bid Security of other Bidders whom OWNER believes to have reasonable chance receiving the award may be retained by OWNER until the earlier of the seventh day after the effective date of the Agreement or the thirty- first day after the Bid Opening, whereupon Bid Security furnished by such Bidders will be returned. Bid Security with Bids which are not competitive will be returned within seven days after the Bid opening. Section 00100 Page 3 No Text 7.0 CONTRACT TIME. The number of days within which, or the date by which the Work is to be substantially complete and also completed and ready for Final Payment (the Contract Times) are set forth in the Agreement. 8.0 LIQUIDATED DAMAGES. Provisions for liquidated damages are set forth in the Agreement. 9.0 SUBSTITUTE ("OR EQUAL") MATERIAL AND EQUIPMENT The Contract, if awarded, will be on the basis of material and equipment described on the Drawings or specified in the Specifications without v consideration of possible substitute or "or equal" items. Whenever it is indicated on the Drawings or specified in the Specifications that a substitute or "or equal" item of material or equipment may be furnished or used by CONTRACTOR if acceptable to Engineer, application for such acceptance will not be considered by Engineer until after the "effective date of the Agreement". The procedure for submittal of any such application by CONTRACTOR and consideration by Engineer is set forth in the General Conditions which may be supplemented in the General Requirements. ^ 10.0 SUBCONTRACTORS, SUPPLIERS AND OTHERS -*n 10.1. Each Bidder shall submit at the Bid opening to OWNER a list of principal subcontractors he proposes to use in the Work. Refer to Section ~ 00430 contained within these Documents. 10.2. If OWNER or Engineer after due investigation has reasonable 4 objection to any proposed Subcontractor, either may, before the Notice of Award is given, request the apparent successful Bidder to submit an acceptable substitute without an increase in Bid price. If the apparent successful Bidder declines to make any substitution, OWNER may award the contract to the next lowest responsive and responsible Bidder that proposes to use acceptable subcontractors. Subcontractors, suppliers, other persons ` or organization listed and to whom OWNER or Engineer does not make written objection prior to the giving of the Notice of Award will be deemed acceptable to OWNER and ENGINEER subject to revocation of such acceptance after the effective date of the Agreement as provided in the General _ Conditions. 10.3. CONTRACTOR shall not be required to employ any subcontractor, supplier or other persons or organizations against whom he has reasonable objection. The use of subcontractors listed by the Bidder and accepted by OWNER prior to the Notice of Award will be required in the performance of the Work. 7/96 Section 00100 Page 4 ® 11. BID FORM. �7 11.1. A copy of the Bid Form is bound in the Contract Documents which may be retained by the Bidder. A separate unbound copy is enclosed for submission with the Bid. 11.2. Bid Forms must be complete in ink or typed. All lump sum prices on the form must be stated in words and numerals; in case of conflict, words will take precedence. Unit prices shall govern over extensions of sums. 11.3. Bids by corporations must be executed in the corporate name by the president or a vice-president (or other appropriate officer accompanied by evidence of authority to sign) and the corporate seal shall be affixed and attested by the secretary or an assistant secretary. The corporate address and state of incorporation shall be shown below the corporate name. 11.4. Bids by partnerships must be executed in the paltnership name and signed by a partner, his title must appear under his signature and the official address of the partnership must be shown below the signature. 11.5. Bids by joint venture shall be signed by each participant in the joint venture or by an authorized agent of each participant. The full name of each person or company interested in the Bid shall be`listed on the Bid Form. 11.6. The Bid shall contain an acknowledgement of receipt of all Addenda (the numbers of which must be filled in on the Bid Form)I. 11.7. No alterations in Bids, or in the printed forms therefore, by erasures, interpolations, or otherwise will be acceptable unless each such alteration is signed or initialed by the Bidder; if initialed, OWNER may require the Bidder to identify any alteration so initialled. 11.8. The address and telephone number for communications regarding the Bid shall be shown. 12.0 BID PRICING. Bids must be priced as set forth in the Bid Schedule or Schedules. i 13.0 SUBMISSION OF BIDS. i 13.1. Bids shall be submitted at the time and place (indicated in the Invitation to Bid and shall be enclosed in an opaque sealed envelope marked with the Project title, Bid No., and name and address of the Bidder and accompanied by the Bid Security, Bid Form, Bid Bond, Statement of Bidders 7/ 6 Section 00100 Page 5 Qualifications, and Schedule of Subcontractors as required in Section 00430. If the Bid is sent through the mail or other delivery system, the sealed envelope shall be enclosed in a separate envelope with the notation "BID ENCLOSED" on the face of it. 13.2. Bids shall be deposited at the designated location prior to the time and date for receipt of Bids indicated in the Invitation to Bid, or any extension thereof made by addendum. Bids received after the time and date for receipt of Bids will be returned unopened. Bidder shall assume full responsibility for timely delivery at the location designated for receipt of Bids. 13.3. Oral, telephonic, telegraphic, or facsimile Bids are invalid and v will not receive consideration. 13.4. No Bidder may submit more than one Bid. Multiple Bids under different names will not be accepted from one firm or association. 14.0 MODIFICATION AND WITHDRAWAL OF BIDS. 14.1. Bids may be modified or withdrawn by an appropriate document duly executed (in a manner that a Bid must be executed) and delivered to the place where Bids are to be submitted at any time prior to the opening of Bids. 14.2. Bids may also be modified or withdrawn in person by the Bidder or an authorized representative provided he can prove his identity and authority at any time prior to the opening of Bids. 14.3. Withdrawn Bids may be resubmitted up to the time designated for the -- receipt of Bids provided that they are then fully in conformance with these Instructions to Bidders. 15.0 OPENINGS OF BIDS. M Bids will be opened and (unless obviously non -responsive) read aloud r publicly as indicated in the Invitation to Bid. An abstract of the amounts of the Base Bids and major alternates (if any) will be made available after the opening of Bids. 16.0 BIDS TO REMAIN OPEN SUBJECT TO ACCEPTANCE. All Bids shall remain open for forty-five (45) days after the day of the Bid Opening, but OWNER may, in his sole discretion, release any Bid and return the Bid Security prior to that date. 7/96 Section 00100 Page 6 u i 17. AWARD OF CONTRACT. 17.1. OWNER reserves the right to reject any and all lids, to waive any and all informalities not involving price, time or changes in the Work, to negotiate contract terms with the Successful Bidder, and the right to disregard all nonconforming, nonresponsive, unbalanced of conditional Bids. Also, OWNER reserves the right to reject the Bid of any Bidder if OWNER believes that it would not be in the best interest of the Project to make an award to that Bidder, whether because the Bid is not responsive or the Bidder is unqualified or of doubtful financial ability or fails to meet any other pertinent standard or criteria established by OWNER. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum. 17.2. In evaluating Bids, OWNER will consider the qualifications of the Bidders, whether or not the Bids comply with the prescribed requirements, and such alternates, unit prices and other data, as may be requested in the Bid Form or prior to the Notice of Award. 17.3. OWNER may consider the qualification and experience of Subcontractors, Suppliers, and other persons and organizations proposed for those portions of the Work as to which the identity of Subcontractors, Suppliers, and other persons and organizations is submitted as requested by OWNER. OWNER also may consider the operating costs, maintenance requirements, performance data and guarantees of major items of materials and equipment proposed for incorporation in the Work when such data is required to be submitted prior to the Notice of Award. 17.4. OWNER may conduct such investigations as OWNER deems necessary to assist in the evaluation of any Bid and to establish the responsibility, qualifications and financial ability of the Bidder's proposed Subcontractors, Suppliers and other persons and organizations to do the Work in accordance with the Contract Documents to OWNER's satisfaction within the prescribed time. 17.5. If the Contract is to be awarded, it will be awarded to the lowest responsive and responsible Bidder whose evaluation by OWNER indicates to OWNER that the award will be in the best interest of the OWNER. Award shall be made on the evaluated lowest base bid excluding alternates. The basis for award shall be the lowest Bid total for the Schedule or, in the case of more than one schedule, for sum of all schedules. Only one contract will be awarded. 17.6. If the Contract is to be awarded, OWNER will give the Successful Bidder a Notice of Award within forty-five (45) days after the date of the Bid opening. i 7f 6 Section 00100 Page 7 i u 18.0 CONTRACT SECURITY. The General Conditions and the Supplementary Conditions set forth OWNER's requirements as to performance and other Bonds. When the Successful Bidder ~ delivers the executed Agreement to the OWNER, it shall be accompanied by the required Contract Security. 19.0 SIGNING OF AGREEMENT. 4 When OWNER gives a Notice of Award to the Successful Bidder, it will be accompanied by the required number of unsigned counterparts of the Agreement with all other written Contract Documents attached. Within fifteen (15) days thereafter, CONTRACTOR shall sign and deliver the -' required number of counterparts of the Agreement and attached documents to OWNER with the required Bonds. Within ten (10) days thereafter, OWNER shall deliver one fully signed counterpart to CONTRACTOR. Each counterpart is to be accompanied by a complete set of the Drawings with appropriate identification. 20.0 TAXES. OWNER is exempt from Colorado State Sales and Use Taxes on materials and equipment to be incorporated in the Work. Said taxes shall not be included in the Contract Price. Reference is made to the General and Supplementary Conditions. 21.0 RETAINAGE. Provisions concerning retainage are set forth in the Agreement. 22.0 PURCHASING RESTRICTIONS. Purchasing restrictions: The Bidder's authorized signature of this Bid assures the Bidder's compliance with the City's purchasing restrictions. A copy of the resolutions are available for review in the Purchasing and Risk Management Division or the City Clerk's office. A. Cement Restrictions: City of Fort Collins Resolution 91-121 requires that suppliers and producers of cement or products containing cement to certify that the cement was not made in cement kilns that burn hazardous waste as a fuel. 23.0 COLLUSIVE OR SHAM BIDS. Any Bid deemed by the City in its sole discretion to be a collusive or sham Bid will be rejected and reported to authorities as such. Your authorized 7/96 w Section 00100 Page 8 1 u 24.0 7/9 I I I I I signature of this Bid assures that such Bid is genuine and is not a collusive or sham Bid. i BID RESULTS. For information regarding results for individual Bids send a self- addressed, self -stamped envelope and a Bid tally will be mailed to you. Bid results will be posted in the Purchasing office seven (7) days after the Bid Opening. END OF SECTION I I I I Section 00100 Page 9 I I No Text SECTION 00300 BID FORM v u i i i i I SECTION 00300 ` BID FORM i PROJECT: Downtown Streetscape, Bid No. 5512 i Place Date 1. In compliance with your Invitation to Bid dated and subject to all conditions thereof, the undersigned, a **(Corporation, Limited Liability Company, Partnership, Joint Venture, or Sole Proprietor)* authorized to do business in the State of Colorado hereby proposes to furnish and do everything required by the Contract Documents to which this refers for the construction of all items listed on the following Bid Schedule or Bid Schedules. 2. The undersigned Bidder does hereby declare and stipulate that this proposal is made in good faith, without collusion or connection with any other person or persons Bidding for the same Work, and that it is made in pursuance of and subject to all the terms and conditions) of the Invitation to Bid and Instructions to Bidders, the Agreement, the detailed Specifications, and the Drawings pertaining to the Work 'to be done, all of which have been examined by the undersigned. 3. Accompanying this Bid is a certified or cashier's check or standard Bid bond in the sum of 1 ($ ) in accordance with the Invitaition To Bid and aInstructions to Bidders. 4. The undersigned Bidder agrees to execute the Agreement land a Performance Bond and a Payment Bond for the amount of the total of this Bid within fifteen (15) calendar days from the date when the written notice of the award of the contract is delivered to him at the address given on this Bid. The name and address of the corporate surety with (which the Bidder proposes to furnish the specified performance and payment bonds is as follows: S. All the various phases of Work enumerated in the Contract Documents with their individual jobs and overhead, whether specifically mentioned, included by implication or appurtenant thereto, are to be performed by the CONTRACTOR under one of the items listed in the Bid Schedule, irrespective of whether it is named in said list. 6. I Payment for Work performed will be in accordance with the Bid Schedule or 7/96 Section 00300 Page 1 SECTION 00300 BID FORM PROJECT: Downtown Streetscape, Bid No. 5512 Date 1. In compliance with your Invitation to Bid dated and subject to all conditions thereof, the undersigned a **(Corporation, Limited Liability Company, Partnership, Joint Venture, or Sole Proprietor)** authorized to do business in the State of Colorado hereby proposes to furnish and do everything required by the Contract Documents to which this refers for the construction of all items listed on the following Bid Schedule or Bid Schedules. 2. The undersigned Bidder does hereby declare and stipulate that this proposal is made in good faith, without collusion or connection with any other person or persons Bidding for the same Work, and that it is made in pursuance of and subject to all the terns and conditions of the Invitation to Bid and Instructions to Bidders, the Agreement, the detailed Specifications, and the Drawings pertaining to the Work to be done, all of which have been examined by the undersigned. 3. Accompanying this Bid is a certified or cashier's check or standard Bid bond 2n the sum of ($ ) in accordance with the Invitation To Bid and Instructions to Bidders. 4. The undersigned Bidder agrees to execute the Agreement and a Performance Bond and a Payment Bond for the amount of the total of this Bid within fifteen (15) calendar days from the date when the written notice of the award of the contract is delivered to him at the address given on this Bid. The name and address of the corporate surety with which the Bidder proposes to furnish the specified performance and payment bonds is as follows: 5. All the various phases of Work enumerated in the Contract Documents with their ind-ividual jobs and overhead, whether specifically mentioned, included by implication or appurtenant thereto, are to be performed by the CONTRACTOR under one of the items :Listed in the Bid Schedule, _irrespective of whether it is named in said list. 6. Payment for Work performed will be in accordance with the Bid Schedule or 7/96 Section 00300 Page 1 Bid Schedules subject to changes as provided in the Contract Documents 7. The undersigned Bidder hereby acknowledges receipt of Addenda No. through CONTRACTOR BY: ADDRESS: B. BID SCHEDULE (Base Bid) Downtown Streetscaping - Phase I Olive and College (4 corners) and Moutam and College (NE corner only) Bid Schedules Spec/Item Description Total Unit Unit Price Item Total Number Est Quantity 626 Mobilization 1 LS 212 Tree Protection 17 EA 202 Remove Highback Curb & Gutter, 4" Concrete Sidewalk, Concrete Pavement, Asphalt Pavement, Brick Pavers 11700 SF 210 Remove, store and reset signs 1 EA 210 Remove and dispose of aggregate wall 60 LF 210 Remove, store, and reset fencing 194 LF 210 Remove, store, and reset mail boxes 2 EA 210 Remove, store, and reset tree grates and frames 16 EA 210 Adjust Manhole 1 EA 210 Adjust Valve Box 4 EA 7/96 Section 00300 Page 2 1 210 Bicycle Rack (Remove and Reset) 9 EA I 10 Bollards (Remove and Reset) 4 EA 04 24" x 24" Catch Basins - Urban Accessories Model STD 13 EA 608 Colored Concrete 4" (Davis color #544) 5745 SF I 609 Vertical Curb and Gutter - special 215 LF 6 8 Concrete Banding - 6" (gray) 305 LF I 608 Concrete Banding - 18" (gray) 240 LF 610 Brick Pavers - Type I (bands) 1400 SF 6 0 Brick Pavers - Type II (fields) 3230 SF I 610 Sandstone Inset 15 SF I 4 3 Asphalt Patching - 6" 20 TN I 4 2 Concrete Pavement - 6" 1600 SF it 6 8 Concrete Lettering - sandblasting (6 locations) 1 L$ 6 3 Irrigation System 1 LS 630 Traffic Control 1 LS I Sub Total - Streetscapmg Improvements I 20 Removal of structures and obstructions 1 LS I 71 18 -inch PVC C-900 321 LF 706 18 - inch Gass III RCP 34 LF 70q 24 - inch class III RCP 23 LF 604 Type 16 combination inlet 2 EA 6041 Double type 16 combination inlet 2 EA 6041 5' dia manhole 3 EA 604 4' dia manhole i EA I 6091 Vertical curb and gutter- Special 92 LF 7/96 Section 00300 Page 3 712 45 degree bend 18" PVC C-900 3 EA 202 Remove asphalt and concrete street pavement 4329 SF 202 Remove and replace concrete sidewalk near type 16 inlet 85 SF 403 Asphalt Patching - 6" 20 TN 412 Concrete Pavement - 6" 1600 SF Sub Total - Stormwater Improvements [Grand Total Grand Total in writing 9. PRICES Dollars The foregoing prices shall include all labor, materials, transportation, shoring, removal, dewatering, overhead, profit, insurance, etc., to cover the complete Work in place of the several kinds called for. Bidder acknowledges that the OWNER has the right to delete items in the Bid or change quantities at his sole discretion without affecting the Agreement or prices of any item so long as the deletion or change does not exceed twenty-five percent (25%) of the total Agreement Price. RESPECTFULLY SUBMITTED: Signature Date Title (Seal - if Bid is by corporation) Attest: Address Telephone License Number (If Applicable) 7/96 Section 00300 Page 4 SECTION 00400 SUPPLEMENTS TO BID FORMS 00410 Bid Bond 00420 Statement of Bidder's Qualifications i 00430Schedule of Subcontractors No Text SECTION 00410 BID BOND KNO ALL MEN BY THESE PRESENTS: that we, the undersigned _ _ as Principal, and Sur tNER, y, are hereby held and firmly bound unto the City of Fort as in the sum of $ for the payment tru y to be made, we hereby jointly and severally bind ourselv ass'gns. THE I CONDITION of this obligation is such that whereas t sub itted to the City of Fort Collins. Colorado the accompany mad a part hereof to enter into a Construction Agreement foi of rt Collins Pro3ect, Downtown Streetscape - Phase I; Bidl NOW THEREFORE, (a) 0 If said Bid shall be rejected, or If said Bid shall be accepted and the Principal shall e: a Contract in the form of Contract attached hereto (pro. accordance with said Bid) and shall furnish a BOND performance of said Contract, and for payment of all labor or furnishing materials in connection therewith, other respects perform the Agreement created by the accex then this obligation shall be void; otherwise the sam force and effect, it being expressly understood and liability of the Surety for any and all claims hereu: event, exceed the penal amount of this obligation as he: The urety, for value received, hereby stipulates and agrees th of s tid Surety and its BOND shall be in no way impaired of exte sion of the time within which the OWNER may accept such Bi does hereby waive notice of any such extension. Sure y Companies executing bonds must be authorized to trans Stat of Colorado and be accepted by the OWNER. 7/�6 as )f which, well and s, successors, and he Principal has ng Bid and hereby the construction M512 . ecute and deliver 5erly completed in Ifor his faithful Jersons performing and shall in all tance of said Bid, shall remain in agreed that the ider shall, in no Mein stated. t the obligations affected by any and said Surety business in the Section OOi410 Page 1 IN WITNESS WHEREOF, the Principal and the Surety have hereunto set their hands " and seals this day of , 20 , and such of them as are corporations have caused their corporate seals to be hereto affixed and these presents to be signed by their proper officers, the day and year first set forth above. _ PRINCIPAL SURETY Name: Address• By: By: Title: Title: ATTEST: By: (SEAL) (SEAL) 7/96 Section 00410 Page 2 All compr be a info i 1. 2. 3. 4. 5. V. 7. 0 0 10 7/c SECTION 00420 STATEMENT OF BIDDER'S QUALIFICATIONS questions must be answered and the data given must shensive. This statement must be notarized. If necessary, >wered on separate attached sheets. The Bidder may submit nation he desires. Name of Bidder: Permanent main office address: When organized: If a corporation, where incorporated: How many years have you been engaged in the contracting business present firm or trade name? Contracts on hand: (Schedule these, showing the amount of the appropriate anticipated dates of completion.) be cl quest any ad ur each cont General character of Work performed by your company: Have you ever failed to complete any Work awarded to you? If so, where and why? Have your ever defaulted on a contract? If so, where and why? 4 re you debarred by any government agency? If yes list agency name. Section 00420 Page gar and Lons may 3itional der your ract and u 11. List the more important projects recently completed by your company, stating ^ the approximate cost of each, and the month and year completed, location and type of construction. _ 12. List your major equipment available for this contract. 13. Experience in construction Work similar in importance to this project: u 14. Background and experience of the principal members of your organization, including officers: 15. Credit available: $ 16. Bank reference: 17. Will you, upon request, fill out a detailed financial statement and furnish any other information that may be required by the OWNER? _ 18. Are you licensed as a General CONTRACTOR?_ If yes, in what city, county and state? class, license and numbers? 19. Do you anticipate subcontracting Work under this Contract? If yes, what percent of total contract? and to whom? 20. Are any lawsuits pending against you or your firm at this time? If DETAIL 7/96 Section 00420 Page 2 What 21. 22. 23. Dal What are the limits of your public liability? DETAIL What company? What are your company's bonding limitations? I The undersigned hereby authorizes and requests any person, firm or corporation to furnish any information requested by the OWNER in verification of the recital comprising this Statement of Bidder's Qualifications. Id at this day of 20_ Nam of Bidder By: _ Titl Stat of Coun y of__ being duly sworn deposes of and t (nam of organization) the nswers to the foregoing questions and all statements t true and correct. Subs ribed and sworn to before me this day of 20 Notary Public My cc 7/�6 ssion expires says that he is ein contained are Section 00;420 Page 3 No Text SECTION 00430 SCHEDULE OF SUBCONTRACTORS List all subcontractors for the work items listed below and all subcontractors — performing over 10% of the contract. ITEM SUBCONTRACTOR 7/96 Section 00430 Page 1 0 0 0 I h 0 I 0 0 1 0 I 1 1 1 No Text 0 I r I 0 N 0 0 0 0 ,1 a" I h I'JI SECTION 00500 AGREEMENT FORMS 00510 Notice of Award 00520Agreement 00530 Notice to Proceed u No Text Date: TO: SECTION 00510 NOTICE OF AWARD :7T: Downtown Streetscape - Phase I; Bid 45512 CITY OF FORT COLLINS (hereinafter referred to as "the OWNER") You are hereby notified that your Bid dated 20_ for the above pro3 ct has been considered. You are the apparent successful Bidder and have been awar ed an Agreement for Downtown Streetscape - Phase I; Bid 45512. The rice of your Agreement is Four (4) copies of each of the proposed Contract Documents (except Drawings) acco pany this Notice of Award Four (4) sets of the Drawings will be delivered sepa ately or otherwise made available to you immediately. You ust comply with the following conditions precedent within fifteen (15) days of t e date of this Notice of Award, that is by , 20_ 1 2 Fai. your With you atta 7/< You must deliver to the OWNER four (4) fully executed Agreement including all the Contract Documents. Ea Documents must bear your signature on the cover of the You must deliver with the executed Agreement the Contr as specified in the Instructions to Bidders, General 5.1) and Supplementary Conditions. nterparts of the of the Contract Security (Bonds) ditions (Article e to comply with these conditions within the time specilfied will entitle to consider your Bid abandoned, to annul this Notice of Award and to declare id Security forfeited. ten (10) days after you comply with those conditions, OWNER will return to e (1) Cully -signed counterpart of the Agreement with the Contract Documents 11 By: OWNER James B. O'Neill II, CPPO Title Section 00510 Page 1 No Text 10 �J 11 SECTION 00520 AGREEMENT THIS AGREEMENT is dated as of the day of year of 20 and shall be effective on the date this ItCity. III in the is signed by the The City of Fort Collins (hereinafter called OWNER) and (hereinafter called CONTRACTOR) i OWNEZ and CONTRACTOR, in consideration of the mutual covenants hereinafter set afort , agree as follows: ARTI LE 1. WORK OCONTRACTOR shall complete all Work as specified or indicated in the Contract Documents. The Project for which the Work under the Contract Documents may be the Stre whole or only a part is defined as the construction) tscape - Phase I; Bid #5512, is described of the Downtown and generally in Section 01010. ARTICLE 2. ENGINEER The Project has been, designed by City of Fort Collins Engineering, who is j� hereinafter called ENGINEER and who will assume all duties and responsibilities and aill have the rights and authority assigned to ENGINEER in the Contract �1 Documents in connection with completion of the Work in accordance with the Cont act Documents. ARTI LE 3. CONTRACT TIMES 3.1 The Work for the Northeast corner of Olive and College shall be Substantially Complete within 21 calendar days after the date (when the Contract TimeE commence to run as provided in the General Conditions and completed and read for Final Payment and Acceptance in accordance with the General Conditions within 35 calendar days after the date when the Contract Times commence to run. The Work for the Northwest corner of Olive and College shall be l Substantially Complete within 21 calendar days after the Final Completion of the Northeast corner of Olive and College and completed and ready for Final Payment and Acceptance in accordance with the General Conditions within 35 calendar days aftez beginning work on the Northwest corner. The Work for the Northeast corner of Mountain and College shall begin on ox after September 5, 2000 and be Substantially Complete within 28 calendar days after the work on Mountain and College begins and completed and ready for 7/6 Section 00520 Page 1 Final Payment and Acceptance in accordance with the General Conditions within 42 calendar days after beginning work on the corner of Mountain and College. 3.2. Liquidated Damages. OWNER and CONTRACTOR recognize that time is of the essence of this Agreement and that OWNER will suffer financial loss if the Work is not completed within the times specified in paragraph 3.1. above, plus any extensions thereof allowed in accordance with Article 12 of the General u Conditions. They also recognize the delays, expenses and difficulties involved in proving in a legal proceeding the actual loss suffered by OWNER if the Work is not completed on time. Accordingly, instead of requiring any such proof, OWNER and CONTRACTOR agree that as liquidated damages for delay (but not as penalty) CONTRACTOR shall pay OWNER the amounts set forth hereafter. 1) Substantial Completion: Northeast corner of Olive and College. Two Hundred Fifty_ Dollars ($250.00) for each calendar day or fraction thereof that expires after the Twenty-one (21) calendar day period for Substantial Completion of the Work until the Work is Substantially Complete. 2) Substantial Completion: Northwest corner of Olive and College. Two Hundred Fifty Dollars ($250.00) for each calendar day or fraction thereof that expires after the Twenty-one (21) calendar day period for Substantial Completion of the Work until the Work is Substantially Complete. 3) Substantial Completion: Northeast corner of Mountain and College, this work shall not begin until on or after September 5, 2000. Two Hundred Fifty Dollars ($250 00) for each calendar day or fraction thereof that expires after the Twenty-eight (28) calendar day period for Substantial Completion of the Work until the Work is Substantially Complete. r, 4) Final Acceptance: (for each of the above mentioned stages of the project) After Substantial Completion, One Hundred Fifty ($150.00) for each calendar day or fraction thereof that expires after the Fourteen (14) calendar day period for Final Payment and Acceptance until the Work is ready for Final Payment and Acceptance. ARTICLE 4. CONTRACT PRICE 4.1. OWNER shall pay CONTRACTOR for performance of the Work in accordance with the Contract Documents in current funds as follows: ($ Dollars, in accordance with Section 00300, attached and incorporated herein by this reference. 7/96 Section 00520 Page 2 I u L n p1 ARTIC'LE 5. PAYMENT PROCEDURES CONTRACTOR shall submit Applications for Payment in accordance with Article 14 of the General Conditions. Applications for Payment will be processed by ENGINEER as provided in the General Conditions. 5.1. PROGRESS PAYMENTS. OWNER shall make progress payments on account of the Contract Price on the basis of CONTRACTOR's Application for Payment as recommended by ENGINEER, once each month during construction as provided below. All progress payments will be on the basis of the progress of the Work measured by the schedule of values established in paragraph 2.6 of the General Conditions and in the case of Unit Price Work based on the number of units completed, and in accordance with the General Requirements concerning Unit Price Work. 5.1.1. Prior to Substantial Completion, progress payments will be in the amount equal to the percentage indicated below, but, in each case, less the aggregate of payments previously made and less such amounts as ENGINEER shall determine, or OWNER may withhold, in accordance with paragraph 14.7 of the General Conditions. 90% of the value of Work completed until the Work has been 50% completed as determined by ENGINEER, when the retainage equals 5% of the Contract Price, and if the character and progress of the Work have been satisfactory to OWNER and ENGINEER, OWNER on recommendation of ENGINEER, may determine that as long as the character and progress of the Work remain satisfactory to them, there will be no additional retainage on account of Work completed in which case the remaining progress payments prior to Substantial Completion will be in an amount equal to 100% of the Work completed. 90% of materials and equipment not incorporated in the Work (but delivered, suitably stored and accompanied by documentation satisfactory to OWNER as provided in paragraph 14.2 of the General Conditions) may be included in the application for payment. 5.1.2. Upon Substantial Completion payment will be made in an amount sufficient to increase total payments to CONTRACTOR to 95% of the Contract Price, less such amounts as ENGINEER shall determine or OWNER may withhold in accordance with paragraph 14.7 of the General Conditions or as provided by law. 5.2. FINAL PAYMENT. Upon Final Completion and Acceptance of the Work in accordance with paragraph 14.13 of the General Conditions, OWNER shall pay the remainder of the Contract Price as recommended by ENGINEER as provided in said i paragraph 14.13. ARTICLE 6. CONTRACTOR'S REPRESENTATION in order to induce OWNER to enter into this Agreement, CONTRACTOR makes the following representations: 7/96 Section 00520 Page 3 Bid Schedules subject to changes as provided in the Contract Documents. 7. The undersigned Bidder hereby acknowledges receipt of Addenda No. through - CONTRACTOR I IA ADDRESS: 8. BID SCHEDULE (Base Bid) Downtown Streetscapmg - Phase I Olive and College (4 corners) and Moutain and College (NE corner only) Bid Schedules Spec/Item Description Total Unit Unit Price Item Total Number Est Quantity 626 Mobilization 1 LS 212 Tree Protection 17 EA J 202 Remove Highback Curb & Gutter, 4" Concrete Sidewalk, Concrete Pavement, Asphalt Pavement, Brick Pavers 11700 SF 210 Remove, store and reset signs 1 EA 210 Remove and dispose of aggregate wall 60 LF 210 Remove, store, and reset fencing 194 LF 210 Remove, store, and reset mail boxes 2 EA 210 Remove, store, and reset tree grates and frames 16 EA 210 Adjust Manhole 1 EA 210 Adjust Valve Box 4 EA 7/96 Section 00300 Page 2 6.1. CONTRACTOR has familiarized himself with the nature and extent of the Contract Documents, Work, site, locality, and with all local conditions and Laws and Regulations that in any manner may affect cost, progress, performance or furnishing of the Work. 6.2. CONTRACTOR has studied carefully all reports of explorations and tests of subsurface conditions and drawings of physical conditions which are identified in the Supplementary Conditions as provided in paragraph 4.2 of the General Conditions. 6.3. CONTRACTOR has obtained and carefully studied (or assumes responsibility for obtaining and carefully studying) all such examinations, investigations, explorations, tests, reports, and studies (in addition to or to supplement those referred to in paragraph 6.2 above) which pertain to the subsurface or physical condition at or contiguous to the site or otherwise may affect the cost, progress, performance or furnishing of the Work as CONTRACTOR considers necessary for the performance or furnishing of the Work at the Contract Price, within the Contract Times and in accordance with the other terms and conditions of the Contract Documents, including specifically the provisions of paragraph 4.2 of the General Conditions; and no additional examinations, investigations, explorations, tests, reports, studies or similar information or data are or will be required by CONTRACTOR for such purposes. 6.4. CONTRACTOR has reviewed and checked all information and data shown or indicated on the Contract Documents with respect to existing Underground Facilities at or contiguous to the site and assumes responsibility for the accurate location of said Underground Facilities. No additional examinations, investigations, explorations, tests, reports, studies or similar information or data in respect of said Underground Facilities are or will be required by CONTRACTOR in order to perform and furnish the Work at the Contract Price, within the Contract Times and in accordance with the other terms and conditions of the Contract Documents, including specifically the provision of paragraph 4.3. of the General Conditions. 6.5. CONTRACTOR has correlated the results of all such observations, examinations, investigations, tests, reports and data with the terms and conditions of the Contract Documents. 6.6. CONTRACTOR has given ENGINEER written notice of all conflicts, errors or discrepancies that he has discovered in the Contract Documents and the written ~ resolution thereof by ENGINEER is acceptable to CONTRACTOR. ARTICLE 7. CONTRACT DOCUMENTS 7.1 The Contract Documents which comprise the entire Agreement between 7/96 Section 00520 Page 4 .i 4J I dk OWNER and CONTRACTOR concerning the Work consist of the General Conditions, Supplementary Conditions, those items included in the definition of "Contract Documents" in Article 1.10 of the General Conditions, and such other items as are referenced in this Article 7, all of which are incorporated herein by this reference. 7.2 Forms for use by CONTRACTOR in performing the Work and related actions in carrying out the terms of this Agreement are deemed Contract Documents and incorporated herein by this reference, and include, but are not limited to, the following, 7.2.1Certificate of Substantial Completion 7.2.2Certificate of Final Acceptance 7.2.3 Lien Waiver Releases 7.2.4 Consent of Surety 7.2.5Application for Exemption Certificate 7.2.6Application for Payment 7.3 Drawings, consisting of a cover sheet and sheets numbered CS-1, N-1, D-1, D-2, L-1, L-2, G-1, G-2, C-1 TO C-4, I-1, AND I-2 inclusive with the ' following general title. College Avenue Sidewalk Improvements The Contract Drawings shall be stamped "Final for Construction" and dated. Any revisions made shall be clearly identified and dated. 7.4. Addenda Numbers to , inclusive. 7.5. The Contract Documents also include all written amendments and other documents amending, modifying, or supplementing the Contract Documents pursuant to paragraphs 3.5 and 3.6 of the General Conditions. 7.6. There are no Contract Documents other than those listed or incorporated by reference in this Article 7. The Contract Documents may only be amended, modified or supplemented as provided in paragraphs 3.5 and 3.6 of the General Conditions. ARTICLE 8. MISCELLANEOUS 8.1. Terms used in this Agreement which are defined in Article I of the J General Conditions shall have the meanings indicated in the General Conditions. 8.2. No assignment by a party hereto of any rights under or interests in the Contract Documents will be binding on another party hereto without the written consent of the party sought to be bound; and specifically but not without 7/96 Section 00520 Page 5 limitations, moneys that may become due and moneys that are due may not be u assigned without such consent (except to the extent that the effect of this restriction may be limited by law), and unless specifically stated to the contrary in any written consent to an assignment no assignment will release or discharge that assignor from any duty or responsibility under the Contract Document. 8.3. OWNER and CONTRACTOR each binds itself, its partners, successors, _ assigns and legal representatives to the other party hereto, its partners, successors, assigns and legal representatives in respect to all covenants, Agreement and obligations contained in the Contract Document. OWNER: CITY OF FORT COLLINS CONTRACTOR: By: By: JOHN F. FISCHBACH, CITY MANAGER BY: JAMES B. O'NEILL II, CPPO DIRECTOR OF PURCHASING Title: AND RISK MANAGEMENT Date: Date: (CORPORATE SEAL) Attest: Attest: City Clerk Address for giving notices: Address for giving notices: P. O. Box 580 Fort Collins, CO 80522 LICENSE NO.: Approved as to Form Assistant City Attorney 7/96 Section 00520 Page 6 a SECTION 00530 NOTICE TO PROCEED Description of Work: Downtown Streetscape - Phase I; Bid No. 5512 To: This notice is to advise you: That the contract covering the above described Work has been fully executed by the CONTRACTOR and the OWNER. That the required CONTRACTOR's Performance Bond and Payment Bond have been received by the OWNER. That the OWNER has approved the said Contract Documents. Therefore, as the CONTRACTOR for the above described Work, you are hereby authorized and directed to proceed within _ (_ ) calendar days from receipt of this notice as required by the Agreement. Dated this day of 20 The dates for Substantial Completion and F1rLal Acceptance shall be and , 20__, respectively. City of Fort Collins OWNER By: Title: ACKNOWLEDGMENT OF NOTICE Receipt of the above Notice to Proceed is hereby acknowledged this of , 20 CONTRACTOR By: Title: 7/96 Section 00530 Page 1 day No Text Pt fl SECTION 00600 BONDS AND CERTIFICATES i f 00610 Performance Bond 00615 Payment Bond 00630 Certificate of Insurance 00635 Certificate of Substantial Completion 00640 Certificate of Final Acceptance 00650 Lien Waiver Release (CONTRACTOR) 00660 Consent of Surety 00670Application for Exemption Certificate No Text 0 SECTION 00610 PERFORMANCE BOND � Bond No. KNOW ALL MEN BY THESE PRESENTS: that (Firm) (Address) (an Individual), (a Partnership), (a Corporation), hereinafter referred to as the "Principal" and (Firm) _ (Address) hereinafter referred to as "the Surety", are held and firmly bound unto City of Fort Collins. 300 LaQorte Ave, Fort Collins. Colorado 80522 a (Municipal Corporation) hereinafter referred to as the "OWNER", in the penal sum of in lawful money of the United States, for the payment of which sum well and truly to be made, we bind ourselves, successors and assigns, jointly and severally, firmly by these presents. THE CONDITIONS OF THIS OBLIGATION are such that whereas the Principal entered into a,certain Agreement with the OWNER, dated the _ day of , 20 , a copy of which is hereto attached and made a part hereof for the performance of The City of Fort Collins project, Downtown Streetscape - Phase I; Bid No. 5512. NOW, THEREFORE, if the Principal shall well, truly and faithfully perform its duties, all the undertakings, covenants, terms, conditions and agreements of said Agreement during the original term thereof, and any extensions thereof which may be granted by the OWNER, with or without Notice to the Surety and during the life of the guaranty period, and if the Principal shall satisfy all claims and demands incurred under such Agreement, and shall fully indemnify and save harmless the OWNER from all cost and damages which it may suffer by reason of failure to do so, and shall reimburse and repay the OWNER all outlay and expense which the OWNER may incur in making good any default then this obligation shall be void; otherwise to remain in full force and effect. i� 7/96 Section 00610 Page 1 LJ PROVIDED, FURTHER, that the said Surety, for value received, hereby stipulates and agrees that no change, extension of time, alteration or addition to the terms of the Agreement or to the Work to be performed thereunder or the Specifications accompanying the same shall in any way affect its obligation on this bond; and it does hereby waive notice of any such change, extension of time, alteration or i_e addition to the terms of the Agreement or to the Work or to the Specifications. PROVIDED, FURTHER, that no final settlement between the OWNER and the CONTRACTOR shall abridge the right of any beneficiary hereunder, whose claim may be unsatisfied. PROVIDED, FURTHER, that the Surety Company must be authorized to transact business in the State of Colorado and be acceptable to the OWNER. IN WITNESS WHEREOF, this instrument is executed in four (4) counterparts, each one of which shall be deemed an original, this day of 20 IN PRESENCE OF: (Corporate Seal) IN PRESENCE OF: IN PRESENCE OF: (Surety Seal) Principal (Title) (Address) Other Partners By: By: Surety By: By: (Address) NOTE: Date of Bond must not be prior to date of Agreement. If CONTRACTOR is Partnership, all partners should execute Bond. 7/96 Section 00610 Page 2 _ SECTION 00615 PAYMENT BOND Bond No. KNOW ALL MEN BY THESE PRESENTS: that (Firm) (Address) (an Individual), (a Partnership), (a Corporation), hereinafter referred to as the "Principal" and (Firm) (Address) hereinafter referred to as "the Surety", are held and firmly bound unto the City of Fort Collins. 300 Laporte Ave.. Fort Collins. Colorado 80522 a (Municipal Corporation) hereinafter referred to as "the OWNER", in the penal sum of in lawful money of the United States, for the payment of wizich sum well and truly to be made, we bind ourselves, successors and assigns, jointly and severally, firmly by these presents. THE CONDITIONS OF THIS OBLIGATION are such that whereas the Principal entered into a certain Agreement with the OWNER, dated the day of , 20_, a copy of which is hereto attached and made a part hereof for the performance of The City of Fort Collins project, Downtown Streetscape - Phase I; Bid No. 5512. NOW, THEREFORE, if the Principal shall make payment to all persons, firms, subcontractors, and corporations furnishing materials for or performing labor in the prosecution of the Work provided for in such Agreement and any authorized extension or modification thereof, including all amounts due for materials, lubricants, repairs on machinery, equipment and tools, consumed, rented or used in connection with the construction of such Work, and all insurance premiums on said Work, and for all labor, performed in such Work whether by subcontractor or otherwise, then this obligation shall be void; otherwise to remain in full force and effect. 7/96 Section 00615 Page 1 0 No Text PROVIDED, FURTHER, that the said Surety, for value received, hereby stipulates and agrees that no change, extension of time, alteration or addition to the terms of the Agreement or to the Work to be performed thereunder or the Specifications accompanying the same shall in any way affect its obligation on this bond; and it does hereby waive notice of any such change, extension of time, alteration or addition to the terms of the Agreement or to the Work or to the Specifications. PROVIDED, FURTHER, that no final settlement between the OWNER and the CONTRACTOR shall abridge the right of any beneficiary hereunder, whose claim may be _ unsatisfied. PROVIDED, FURTHER, that the Surety Company must be authorized to transact business in the State of Colorado and be acceptable to the OWNER. IN WITNESS WHEREOF, this instrument is executed in four (4) counterparts, each one of which shall be deemed an original, this day of 20 IN PRESENCE OF: Principal By: (Title) U (Address) (Corporate Seal) Y V IN PRESENCE OF: Other Partners n IN PRESENCE OF: Surety By: By: (Address) (Surety Seal) NOTE: Date of Bond must not be prior to date of Agreement. If CONTRACTOR is Partnership, all partners should execute Bond. ~ 7/96 Section 00615 Page 2 k. Hj SECTION 00630 CERTIFICATE OF INSURANCE CONTRACTOR sha1L insert his own standard form for Certificate of Insurance. 4 I M No Text SECTION 00635 CERTIFICATE OF SUBSTANTIAL COMPLETION TO: CITY OF FORT COLLINS I (OWNER) DATE OF SUBSTANTIAL COMPLETION: PROJECT TITLE: Downtown Streetscape - Phase I; Bid No. 5512 PROJECT OR SPECIFIED PART SHALL LOCATION: _Fort Collins. Colorado INCLUDE: OWNER- _City of For: Collins CONTRACTOR: CONTRACT DATE: The Work performed under this contract has been inspected by authorized representatives of the OWNER, CONTRACTOR, and the ENGINEER and the project (or specified part of the project, as indicated above) is hereby declared to be substantially completed on the above date A tentative list of items to be completed or corrected is appended hereto. This list may not be exhaustive, and the failure to include an item on it does not a' alter the responsibility of the CONTRACTOR to complete all the Work in accordance with the Contract Documents. ENGINEER AUTHORIZED REPRESENTATIVE DATE The CONTRACTOR accepts the above Certificate of Substantial Completion and agrees to complete and correct the items on the tentative list within the time indicated. By: _ CONTRACTOR AUTHORIZED REPRESENTATIVE DATE The OWNER accepts the project or specified area of the project as substan- tially complete and will assume full possession of the project or specified area / of the project at 12:01 a.m., on The responsibility for heat, utilities, security, and insurance under the Contract Documents shall be as set forth under "Remarks" below. CITY OF FORT COLLINS, COLORADO By: OWNER REMARKS: 7/96 l AUTHORIZED REPRESENTATIVE Section 00635 Page 1 DATE HI No Text r4. SECTION 00640 CERTIFICATE OF FINAL ACCEPTANCE TO: Gentlemen: 2 0_ You are hereby notified that on the _ day of , 20_, the City of Fort Collins, Colorado, has accepted the Work completed by for the City of Fort Collins project Downtown Streetscape - Phase I; Bid No. 5512. A check is attached hereto in the amount of $ __ as Final Payment for all Work done, sub]ect to the terms of the Contract Documents which are dated In conformance with the Contract Documents for this project, your obligations and guarantees will continue for the specified time from the following date: Sincerely, OWNER: City of Fort Collins By: _ Title: AATTEST: Title: 7/96 Section 00640 Page 1 No Text 0 SECTION 00650 LIEN WAIVER RELEASE (CONTRACTOR) TO: City of Fort Collins, Colorado (OWNER) FROM: (CONTRACTOR) UPROJECT: Downtown Streetscape - Phase I; Bid No. 5512 1. The CONTRACTOR acknowledges having received payment, except retainage from the OWNER for all work, labor, skill and material furnished, delivered and performed by the CONTRACTOR for the OWNER or for anyone in the construction, design, improvement, alteration, addition or repair of the above described project. 2. In consideration of such payment and other good and valuable consideration, the receipt and adequacy of which are hereby acknowledged, the CONTRACTOR voluntarily waives all rights, claims and liens, including but not limited to, mechanic's liens, Miller Act claims (40 t3.S.C.A. 270 a and b), stop notices, equitable liens and labor and material bond rights which the CONTRACTOR may now or may afterward have, claim or assert for all and any work, labcr, skill or materials furnished, delivered or performed for the construction, design, improvement, alteration, addition or repair of the above described project, against the OWNER or its officers, agents, employees or assigns, against any fund of or in the possession or control of the OWNER, against the pro3ect or against all land and the buildings on and appurtenances to the land improved by the project. 3. The CONTRACTOR affirms that all worth:, labor and materials, furnished, delivered or performed to or for the construction, design, improvement, alteration, addition or repair of the project were furnished, delivered or performed by the CONTRACTOR or its agents, employees, and servants, or by and through the CONTRACTOR by various Subcontractors or materialmen or their agents, employees and servants and further affirms the same have been paid in full and have released in full any and all existing or possible future mechanic's liens or rights or claims against the project or any funds in the OWNER'S possession or control concerning the project or against the OWNER or its officers, agents, employees or assigns arising out of the project. 4. The CONTRACTOR agrees to defend and hold harmless the OWNER, the lender, if any, and the Surety on the pro3ect against and from any claim hereinafter made by the CONTRACTOR'S Subcontractors, materialmen, employees, servants, agents or assigns against the project or against the OWNER or its officers, 7/96 Section 00650 Page 1 employees, agents or assigns arising out of the project for all loss, damage and costs, including reasonable attorneys fees, incurred as a result of such claims. - 5. The parties acknowledge that the description of the project set forth above U constitutes and adequate description of the property and improvements to which this Lien Waiver Release pertains. It is further acknowledged that this Lien Waiver Release is for the benefit of and may be relied upon by u the OWNER, the lender, if any, and Surety on any labor and material bonds for the project. Signed this day of 20_ U CONTRACTOR By: Title: w ATTEST: �r Secretary n STATE OF COLORADO ) u )ss. COUNTY OF LARIMER ) u Subscribed and sworn to before me this day of 20_, by Witness my hand and official seal. My Commission Expires: Notary Public 7/96 Section 00650 Page 2 SECTION 00660 CONSENT OF SURETY TO: City of Fort Collins. Colorado (hereinafter referred to as the "OWNER") CONTRACTOR: PROJECT: Downtown Streetscape - Phase I; Bid No. 5512 CONTRACT DATE: In accordance with the provisions of the Contract between the OWNER and the CONTRACTOR as indicated above, for b d f on on o (Surety) 11CLCUy aPPLVJCb VL 111C PLlla1 1' YL C11L LV L11C l.V1V 11Ct11..1VR, allU ayleeS L11aL i'lnal Payment to the CONTRACTOR shall not relieve the Surety Company of any of its obligations to the OWNER, as set forth in the said Surety Company's Bond. IN WITNESS WHEREOF, the Surety Company has hereunto set its hand this day of , (Surety Company) By ATTACH: Power of Attorney and Certificate of Authority of Attorney(s)-in-Fact. 7/96 Section 00660 Page 1 210 Bicycle Rack (Remove and Reset) 9 EA 210 Bollards (Remove and Reset) 4 EA 604 24" x 24" Catch Basins - Urban Accessories Model STD 13 EA 608 Colored Concrete 4" (Davis color #544) 5745 SF 609 Vertical Curb and Gutter - special 215 LF 608 Concrete Banding - 6" (gray) 305 LF 608 Concrete Banding - 18" (gray) 240 LF 610 Brick Pavers - Type I (bands) 1400 SF 610 Brick Pavers - Type II (fields) 3230 SF 610 Sandstone Inset 15 SF 403 Asphalt Patching - 6" 20 TN 412 Concrete Paverrient - 6" 1600 SF 608 Concrete Lettering - sandblasting (6 locations) 1 LS 623 Irrigation System 1 LS 630 Traffic Control 1 LS Sub Total - Streetscapmg Improvements 202 Removal of structures and obstructions 1 LS 712 18 - inch PVC C-900 321 LF 706 18 - inch class III RCP 34 LF 706 24 - inch class III RCP 23 LF 16 combination inlet 2 EA q04Type Double type 16 combination inlet 2 EA 5' dia manhole 3 EA 604 4' dia manhole 1 EA 609 Vertical curb and gutter - Special 92 LF 7/96 Section 00300 Page 3 No Text SECTION 00670 APPLICATION FOR EXEMPTION CERTIFICATE 9 Insert State certificate here. a' 0 No Text DR 0172 (12198) COLORADO DEPARTMENT OF REVENUE DENVER CO 110261 (303)232.2416 0 E 0 tt� I a n M CONTRACTOR APPLICATION FOR EXEMPTION CERTIFICATE Pursuant to Statute Section 39-26.114(1)(a)(M) DO NOT WRITE IN THIS SPACE The exemption certificate for which you are applying must be used only for the purpose of purchasing construction and building materials for the exempt project described below. This exemption does not include or apply to the purchase or rental of equipment, supplies, and materials which are purchased, rented, or consumed by the contractor and which do not become a part of the structure, highway, road, street, or other public works owned and used by the exempt organization Any unauthorized use of the exemption certificate will result In revocation of your exemption certificate and other penalties provided by law. A separate certificate is required for each contract. Subcontractors will not be Issued Certificates of Exemption by the Department of Revenue It Is the responsibility of the prime contractor to Issue certificates to each of the subcontractors (See reverse side ) FAILURE TO ACCURATELY COMPLETE ALL BOXES WILL CAUSE THE APPLICATION TO BE DENIED. Aegistratlon7Accouni No (to be assigned by DOR) Period 0170-750 (999) $0.00 89 - iF nl��i n'.Y� AShIF SV; 1i t CONTRACTORNE CO Trade name/DBA Owner, partner, or corporate name Mailing address (City, State, Zip). Contact Person E-Mail address Federal Employer's Identification Number Bid amount for your contract cS Fax number Business telephone number Colorado withholding tax account number I "e ti tCopiesofcontractoGagreementpages:(1};identify"ingth6iuiritractingpartiesl EXEMPI;TION'INFQ,RMATIO.N��' ,-,,- - M..y >H ._- - N•:- Yr. ;�- be.attachecl:r. ,. -,,and:(2).contatningxsignatu�esof6"caniracting°jiarties;mus Name of exempt organization (as shown on contract) Exempt organization's number 98 - Address of exempt organization (City, State, Zipp Principal contact at exempt organization Principal contacts telephone number Physical location of project site (give actual address when applicable and Cities and/or County (ies) where project is located) Scheduled Month Day Year Estimated Month Day Year construction start date completion date ^^S�u4,-a �♦it .F' rD'v..i+uY:eJNS l.' /f — lhT-.+W'-1 �l.{i —S o�,' 1 declare under penalty of penury In the second degree that the statements made in this application are true and complete to the best of my knowledge. Signature of owner, partner or corporate officer Title of corporate officer Date DO NOT WRITE BELOW THI5 LINE Special Notice - Contractors who have completed this application in the past, please note the following changes in procedure - The Department will no longer issue individual Certificates of exemption to subcontractors. Only prime contrac- tors will receive a Contractor's Exemption Certificate on exempt projects `J Upon receipt of the Certificate, the prime contractor should make a copy for each subcontractor involved in the ^ protect and complete it by filling in the subcontractor's name and address and signing it. The original Certificate should always be retained by the prime contractor. Copies of all Certificates that the prime contractor issued to subcontractors should be kept at the prime contractor's place of business for a `J minimum of three years and be available for inspection in the event of an audit. Once an 89# has been assigned to you, please use the next five numbers following it for any applications submitted for future projects. This should be your permanent number. For instance, if you were assigned 89- 12345-0001, every application submitted thereafter should contain 89-12345 on the application. The succeed- ing numbers will be issued by the Department of Revenue. DO NOT enter what you believe to be the next in f sequence as this may delay processing of your application. — k n m 0 w F-+ ME e r No Text 0 SECTION 00700 ® GENERAL CONDITIONS �7 LJ 7,1 t� 5"'; 0 s,' lyd P 0 rll No Text D11 0 P Ni U 0 N GENERAL CONDITIONS OF THE CONSTRUCTION CONTRACT These GENERAL CONDITIONS have been developed by using the STANDARD GENERAL CONDITIONS OF THE CONSTRUCTION CONTRACT prepared by the Engineers Joint Contract Documents Committee, EJCDC No 1910-8 (1990 Edition), as a base. Changes to that document are shown by underlining text that has been added and striking through text that has been deleted EJCDC GENERAL CONDITIONS 1910-8 (1990 ]EDITION) WITH CITY OF FORT COLLINS MODIFICATIONS (REV 9/99)