Pioneer Charter School - Fort Collins, Colorado
Prole( t Manager for an Outward Bound Expeditionary Learning (ELOB) Charter School
in Fort Collins The project is located on a tract of the Rigden Farm First Filing and is
bisected by a large drainage channelldetention facility The project included sustainable
design considerations and LEER Certification The site improvements included the
school building, associated parking, a pedestrian bridge and special onsite features such
as an amphitheatre built into the drainage channel
Wray School Additions - Wray, Colorado
Project Manager for multiple building additions located on the Wray School District site
The project entailed site civil design services for building additions to the Multi -Purpose
Room, Ag Building and High School The site improvements included utility, grading
and drainage designs associated with the building additions and the relocation of existing
playground equipment
Estes Park School Campus — Estes Park, Colorado
Project Manager for various building additions to the Estes Park School Campus The
project included separate additions to the Elementary, Intermediate, Aquatic Center and
High School buildings as well as various parking, and site improvements to the Stadium
and Campus Existing utilities were relocated around the additions and a new storm
drainage system was developed
Gateway Plaza - Greeley, Colorado
Project Manager for a 3-acre commercial subdivision in the City of Greeley The project
is comprised of a three lot subdivision including a carwash, liquor store and future pad
site Special design considerations include offsite utility extensions, significant grading
and retaining wall usage and incorporation of the onsite Greeley -Loveland Irrigation
Company overflow structure into the site layout
Downtown Enhancement Project - Fort Collins, Colorado
Project Manager providing engineering support to the City of Fort Collins for the design
of numerous intersection improvements in downtown Fort Collins The project included
upgrades to Mountain Ave, Mountain & Mason Intersection, left turn lane extension on
College Ave, addition of enhanced crosswalks at four major intersections on College
Ave, storm drainage improvements and adherence to new ADA Accessibility
Guidelines The project included State funding and coordination with officials with the
Colorado Department of Transportation
Foothills Community - Boulder, Colorado
Project Manager for this 12-acre affordable housing project in northwest Boulder,
developed by the Boulder Housing Authority Preliminary and Final design for
infrastructure of multifamily, townhouse and duplex units with a community building,
trails and open space Development constraints included the mapping and relocation of
an existing flood plain and incorporation of an existing open irrigation system through
the development The design incorporated new urbanistic architecture, alleys and
carriage units
G�qUff
5 ASS CIATE.5 INC
G L, T2jcL
55871b0,t i9th Street
C.realet, Cninndo 60634
RESUME
been in many areas of industrial, institutional,
waste water, and commercial design These areas
include; low voltage and high voltage distribution,
lighting, fire alarms, control, instrumentation,
energy management, and various special
systems
REPRESENTATIVE PROJECTS
RONALD J. McNUTT, P.E. Eaton Fire Station —Eaton, CO
Electrical Engineering Consultant
Designed the electrical system
Windsor/Severance Fire Station — Windsor, CO
EDUCATION Bachelor of Science/
Designed the electrical system
Electrical Engineering
Union Colony Fire Rescue Station #3 & #7 —
University of Colorado
Greeley, CO
Boulder, Colorado
Designed the electrical system
REGISTRATION Licensed Professional
Lafayette Fire Station — Lafayette, CO
Engineer
Designed the electrical system
States of Colorado,
Arizona, California,
Fire Station #5 — Loveland, CO
Connecticut, Maryland,
Designed the electrical system
Massachusetts, Michigan,
Nebraska,
Spring Canyon Fire Station —
New Mexico, New York,
Designed the electrical system
NCEES, Pennsylvania,
South Dakota,
North Metro Fire Rescue —
Texas, Utah, Virginia,
Designed the electrical system
Wyoming
Certified Consulting West Adams County Fire Protection 5 stations -
Engineer Adams County, Colorado
State of Colorado Designed the electrical systems
PROFESSIONAL R J McNutt &
Associates, Inc
Greeley, Colorado
President
PROFESSIONAL
ORGANIZATIONS Consulting Engineer's
Council
Illuminating Engineering
Society
SUMMARY OF EXPERIENCE
AND CAPABILITIES
Mr McNutt's specialty of study in engineering was
power distribution and computer control systems
He has been a design engineer in the construction
field for thirty-three years This experience has
Poudre Fire Authority 3 stations -
Fort Collins, Colorado
Designed the electrical systems
Bancroft Fire Station - Bancroft, Colorado
Designed the electrical system
Island Grove Community Center
Greeley, CO
Designed the electrical system
Island Grove Regional Treatment Facility
Greeley, CO
Designed the electrical system
South Park Ambulance — Fairplay, CO
Designed the electrical system
Loveland Police & Courts Facility
Loveland, CO
Designed the electrical system
I
AE AssoctAl I3S
ALICIA B THORPE, PE
PROJECT MANAGER
EDUCATION Bachelor of Science in Architectural Engineering, 1997
University of Wyoming
University of Wyoming Professional Advisory Board for
Civil and Architectural Engineering Department
(Term 2001-2006)
REGISTRATION Professional Engineer(PE)- Colorado
QUALIFICATIONS
RECENT
EXPERIENCE:
OTHER NOTABLE
PROJECTS
PROFESSIONAL
ASSOCIATIONS
Since joining AE Associates, Inc in 1997, Ms Thorpe has
worked as a Project Manager and designer in mechanical
HVAC design Her responsibilities include project design and
coordination of mechanical systems as well as on -site problem
solving As an engineer at AE Associates, she functions in
project management roles for various projects Alicia has expenence in design of both new construction
and remodel projects, and has been involved in start-up and operation through her work on
commissioning teams
LOVELAND POLICE AND COURTS Loveland, Colorado
Project Manager for this 96,000 at two-story ice budding that houses Police functions for the City of
Loveland, and Court functions for Lanmer County The mechanical systems were handled under a
Design -Build arrangementwith U S Engineering Company
LOVELAND MEDICAL CENTER Loveland, Colorado
Alicia functioned as project manager and lead HVAC designer for this 78,000 square foot medical office
building The functions of this building include medical office space, procedure areas, surgical suites,
overnight beds and imaging department (MR1, CT Scanning, X-Ray, mammography, ultrasound, etc)
NORTH COLORADO MEDICAL CENTER MOB I Greeley, Colorado
Alicia functioned as project managerfor the shell and core portion of this fourstory medical office building
(three above grade levels plus basement)
DENVER CONVENTION CENTER HOTEL Denver, Colorado
Project Manager for this $250 million, 38-story, Hyatt Hotel currently under construction at the cornerof
California and 15"' Street in downtown Denver Part of her responsibility included the high rise smoke
control systems The mechanical systems were handled under a Design -Assist arrangement
PORTOFINO TOWER Denver, Colorado
Alicia functioned as the Project Managerforth is 120,000 sf, fourteen story, luxury condominium with four
levels of underground parking Part of her responsibility included the high rise smoke control systems
Westin Hotel at Denver International Airport - Denver, Colorado
Summit View Medical Office Building - Greeley, Colorado
University School - Greeley, Colorado
O'Meara Ford - Northglen, Colorado
American Society of Heating, Refrigeration and Air Conditioning Engineers (ASHRAE)
A AssoclAII'S
GREGORY R MARTINO, PE
PRESIDENT
EDUCATION
REGISTRATIONS
QUALIFICATIONS
SIGNIFICANT
PROJECTS
Bachelor of Architectural Engineering, 1971
Pennsylvania State University
LEED' 2 0 Accredited Professional
California, Colorado, Nevada, and most other states
As Founder and President, Mr Martino mentors his staff to
listen to what the client wants, propose creative but cost
effective solutions, and accept feedback positively A firm
opponent of micro -management, he enables each staff
member to do their job as effectively and efficiently as they
can within his general guidelines His commitment tobuilding system commissioning not only ensures
owner satisfaction at the completion of the project, but also provides valuable feedback for staff
education and design improvement By maintaining this exceptional level of service most clients have
become repeat clients, and in some instances AE Associates has become a "sole -source' for
engineering services
POLICE and COURTS BUILDING Loveland, Colorado
Project Director for this 96,000 sf two-story office building that houses Police functions for the City of
Loveland, and Court functions for Lanmer County The mechanical systems were handled under a
Design -Build arrangement with U S Engineering Company
LOVELAND MEDICAL CENTER Loveland, Colorado
Project Director for this 78,000 sf, two-story, medial office budding that houses an Imaging Center, four
surgical suites, and extensive office space for doctors The mechanical systems were handled under
a Design -Assist arrangement with U S Engineering Company
GSA-NRRC Foil Collins, Colorado
Project Director for this 120,000 sf, three-story office building for several federal government offices
The mechanical systems were handled under a Design -Budd arrangement
D 0 T OFFICE BUILDING Lakewood, Colorado
Project Director for this 128,000 sf, three story office building for the federal Department of
Transportation The mechanical systems were handled under a Design -Build arrangement
MILLENIUM FINANCIAL Denver, Colorado
Project Director for this 140,000 sf, three story, Class A office building located in downtown Denver
The mechanical systems were handled under a Design -Build arrangement
SUMMIT VIEW MEDICAL OFFICE BUILDING Greeley, Colorado
Project Directorfor this 58,000 sf, two story, medical office building that houses an Imaging Center and
extensive office space for doctors The mechanical systems were handled under a Design -Build
arrangement
PROFESSIONAL American Society of Heating, Refrigeration and An -Conditioning Engineers
AFFILIATIONS American Consulting Engineers Council
International Code of Budding Officials
National Fire Protection Association
SECTION 2
®
Q
Proposed Approach
0
Q
Motivation
Belford Watkins Group is uniquely qualified for the Scope of Work
®
anticipated under this request for Architectural Services Not only has
Belford Watkins Group personnel been involved in new and prototypical
Q
station design, but also many remodel and addition protects to existing
stations In fact, our experience is extensive in the difficult venue of
renovation work ranging from addition / remodel protects for fire stations,
0
churches and schools, to small controlled maintenance protects for school
®
districts and municipalities The proposed) team for the Poudre Fire
'Watkins
Authority contract includes many firms that Belford has worked with
®
on fire stations and renovation protects, as well as consultants that have
worked successfully with the City of Fort Collins in the past
Naa
,r
Availability
Belford Watkins Group has the availability to start work at any time
Once Poudre Fire Authority's target dates are known, Belford
Watkins can recommend a schedule to accomplish the deadline with
0
written and/or graphic schedule matenal that will set milestones for
the entire Design / Owner Team Belford Watkins has been involved
in many public school protects that require: strict adherence to
t
schedules in order to accomplish construction within specified
windows This is exemplified by local projects for the Poudre School
District including the recent renovation to Blevins Junior High and
addition/remodels completed for Riffenburgh and Bennett
Elementary Schools The size of protects anticipated by Poudre Fire
Authority can be easily accommodated with existing staff and they
will be completed in Poudre Fire Authority's time frames Belford
®Watkins
'
presence in Fort Collins along with consultants from the
surrounding area allow easy access to and historywith local entities
Milt
This presence also affords the Owner easy access to design
®
personnel and quick response to protect issues especially during
construction
®
Attitude
These are your protects, not ours You will pay for it, use the facilities, and
maintain the buildings for the foreseeable futul e
®
We provide many good, creative choices and recommendations You make
all the decisions We believe the talent in this profession is to take the user
group's ideas and aspirations, and make a usable, attractive protect
®
We use a charrette process in which we present many alternatives
Together, we will discuss the pros and cons of the different options, and the
best ideas rise to the top
®
This technique allows Owners to drive the direction of the design and allows
for a natural consensus to be built among a potentially diverse group of
people, departments and interests
®
P O U D R E
FIRE R E AUTHORITY T Y ARCHITECTURAL T E C T U R A L & ENGINEERING
G I N E E R I N G
S E R V I C E S
8eUbrd Watkins Group, LLC
SECTION d
We find that people get more excited about a project when they are asked to
participate and give input
The photographs above show Mark Belford presenting options in atypical
charrette setting Please note the walls are filled with options
Cost Control Methods The following describes our philosophy and approach to project cost control
Set expectations during the programming phase The program provides
accurate detail about the quantities and types of space It also captures
the overall quality of construction that the city and fire authority expects
The time and effort spent on developing a realistic budget will pay
dividends as the project moves forward info design
We will work from a milestone design schedule At the first milestone,
our design team can develop a very useful tool — a cost model This
tool is nothing more than a baseline estimate broken down by building
systems It is then used as a measuring stick for subsequent design
decisions and estimates With this powerlul tool, out design team can
prioritize design decisions
Decisions will be acknowledged through meeting minutes, space
planning sheets and schematic design drawings and form the
foundation for subsequent construction document eflorts
Value engineering, if needed, will be based on items that minimally
affect the scope, aesthetics, or function of the facility
POUDRE FIRE AUTHORITY ARCHITECTURAL & ENGINEERING
S E R V I C E S
Belford Watkins Group LLC
SECTION
Different systems and materials will be analyzed for their Inclusion Into
this project
Use of alternates in the bidding process is an effective way to control
possible budget issues
Day to day attention to, understanding of, and designing in the current
market conditions
Deliverables As we move through the design process, early deliverables will Include a
written Programmatic document and Space Diagram Options with
associated Cost Models to investigate different approaches to the project
including site development options as needed
Once the budget has been arrived at and the approach to the project set,
final Schematic Design documents will be generated including a Site Plan,
Floor Plan, Building Elevations and a Cost Estimate
Finally, all of the design information will be summarized in a Schematic
Design Manual that will include a written executive summary including
conceptual systems for the building, findings for the site including survey,
utility and geotechnlcal findings, Data Sheets for each space within the
building and the above drawings and cost estimate
Following are examples of some of these deliverables and the design
process
POUDRE FIRE AUTHORITY ARCHITECTURAL & EMGINEERING
S E R V I C E S
Belford Watkins Group LLC
SECTION d
Programming
Each space required by the Fire Department will be analyzed by
need The rooms are given an appropriate square footage based on
usage, mechanical, electrical and architectural systems
UNION COLONY FIRE RESCUE STATION 3
Room Number
127
Room Name
Trammg/Commumty/EOC
Square Feet
1000 square feet
Functional Descnpuon
Emergency Operations Center/Training Room/Community Room
a Architectural
1
Separate entrance to the front of the site with a second means of secure access to the
fire station living quarters and an emergency exit
2
Window coverings for room darkening
3
ADA mens and women's bathrooms
4
Parking adequate for occupant load plus additional spaces for fire station personnel
(Consider separate public and fire station parking)
5
Parking for visiting fire apparatus
b Structural
1
9' ceding height
2
Carpeted floor
c Mechanical
d Electrical
I
Wall, floor and ceding outlets
2
Wired for Cable Television at each end of room
3
Muumum two duplex outlets at the wet bar
4
Adjustable lighting
5
Ceding Mounted Digital Light Projector wired) to media closet
6
Emergency generator capable of supplying the entire building
e Communications
I
Station communications speaker with adjustable volume
2
Telephone lines (20) preferable wireless
3
Modem Imes
4
Access to main frame computers (20) preferable wireless
5
Public Address system for the community, policy, and conference rooms only
f Fire Protection
I
Full sprinkler system with smoke detection that is not single station
g Special Considerations
I
White boards for presentations
2
Bulletin Boards
3
Facilities for two wall mounted TV's with appropnate backing
4
Separate entryway to have a secure bulletin board for scheduling calendar
5
Allow storage space for tables and chairs
6
Flip chart clip/pm strips on all walls
7
Wet bar to be equipped with a garbage disposal
8
Cupboards above the wet bar need to lugh enough for a commercial coffee maker
h Security 1 Programmable lock on main entrance
Example of a programming sheet — The sheets are used to analyzed and create cost model analysis
POUDRE FIRE AUTHORITY ARCHITECTURAL & ENGINEERING
S E R V I C E S
Be/ford Watkins Group LLC
0
SECTION d
Cost Models
After the programming
Is complete, the cost models are created to
®
help assist the Owner In making
decisions based on different
building systems
Cost Model #1
OuaBty Leval .Im11M m Station #r
Flat ROW at Apparatus Bey, 412 Hip Roofs Elsewhere
®
More Compact Footprint
No PrecastA amts
Thme Ba t000ma for EVIs Bunknoms
®
ApparaNs Bay
4,480
$123 73
$154,332
AW r-dus Am,.II ry
1,660 z
$I404J =
$241117
®Living
Quarters
2„924 x
$11134 =
$394,047
v
Sla'pjng Quancra
2,196 x
S20970
S460491
®
Training Room
612 x
$16089 =
$98,467
Bmldmg
11,872
$1,730,454 $146/ef
Srte
$473,000
®
Subtdal
$2,201,454 $186 fs I
®
lnFlanon to March 2006
$89,138 4%
b
3%Change Onict Conhngenoy
S68,748
Total
$2,360,340
®
Cost Model #4
®
M. Flmcu, Appa-mc cry a".
HVAC and Ebc to Bwment Space
Remove Ma rune morepe at Appenlus Bay
®
and Flat Root over Apparatus Anc,llary
®
1,p,vrnmsBay
4,480
$10357
— $464,002
Appsmlos Aacrllary
1271
$13916
— $175,579
®
m Lrvp Qan uan
1,911 a
$13ROfl
$264,172
skcpwp Qrwncra
Basmnmu
2,196 1
1200
$17996
$9572
— $395,194
— $114%8
Trarnmg Rwm
612 a
S14354
S87846
®
SubmtW
11 672
$1 501 662 S129 /n 1
®
Srte
$473 UW
Subeaal
$t 974 662 $169 1, r
®
InlUmm m March 2006
S78 986 4'%
®
34 Chnn, (TOer Commgeaoe
i61 609
®
total
52,115,357
®
Examples of 2 different Cost models
®
POUDRE FIRE
AUTHORITY
ARCHITECTURAL
& E PJ G I N E E R I N G
S E R V I C E S
Belford Watkins Group LLC
SECTION d
Charrette The Charette process is used to help the Owner make decisions
about the extenor look of a building or the arrangement of spaces
After the design is defined, the cost estimate is further refined
Design Option 1 Fire Station #3 — Union Colony- based off of Union Colony Station 7 floor plan
Design Option 2 Fire Station #3 — Union Colony — Based off of the Union Colony Station 7 prototypical Floor plan
and additional square footage for the new bays and training room
POUDRE FIRE AUTHORITY ARCHITECTURAL & ENGINEERING
S E R V I C E S
Belford Watkins Group LLC
TABLE OF CONTENTS
Cover Letter
Section One
Section Two
Statement of Qualifications
Capabilities of Finn
Assigned Personnel
Proposed Approach
Motivation
Availability
Attitude
Cost Control Methods
Deliverables
Section Three Fee Proposal
Section F o u r Relevant Experience & References
POIJORE FIRE AUTHORITY -ARCHITECTURAL & ENGINEERING
S E R V I C E S
Belford Watkins Group LLC
SECTION 2
Design Option 2 — Fire Station #3 — Floor Plan based off of Initial wish list of the Union Colony Fire District- and
Fire Station 7 as the prototypical plan that was to be re -used
Design Option 3 — Fire Station #3 — Union Colony — Owner groups request turn of the century style, remove
training room to meet budget constraints
POUDRE FIRE AUTHORITY ARCHITECTURAL & ENGINEERING
S E R V I C E S
Belford Watkins Group LLC
SECTION d
Design Option 4 Fire Station #3 — Union Colony — Owner Group request turn of the century style
Final Design product Fire Station #3— Union Colony— cost analysis and final construction budget based off of
this design concept
Schematic Design After final probable construction cost analysis, site plan, exterior
elevations and floor plans have been approved by the Owner, the
formal schematic design drawings are finalized MG can provide
the Owner Group with photographic renderings of the exterior
building sited correctly on the property
Photographic rendering of the Union Colony Model of Redeemer Lutheran Church -used
Station #7 project — Used for City Council Approval for fund raisers
POUDRE FIRE AUTHORITY ARCHITECTURAL & ENGINEERING
S E R V I C E S
Safford Watkins Group, LLC
SECTION 3
Fee Proposal
Fees would be based upon the following ranges
Basic A/E Services
Fees for basic architectural, structural, mechanical and electrical services would range from
5 5 - 6 5% for reuse of the prototypical station in the same configuration as Station #12 with
minor changes and re -siting the design (not including civil, planning and landscaping
services)
to
6 5- 7 5% for design of a new station type (not including civil, planning and landscaping
services)
Note Civil, planning and landscaping services can range from 15 to 2 percent of the
construction cost depending on the complexity of the site and the extent of the planning
review process required
8-11% for remodel work depending on the project size and the extent of mechanical and
plumbing revisions
Reimbursable Expenses
Anticipated reimbursable expenses would be 5 — 10% of design fees Fees would be towards the
lower end of the range if the city were responsible for printing costs for bid sets
It is assumed that security, surveying and geotechnical services would be contracted separately by
the City but, if necessary, could be provided as consultants of Belford Watkins
Hourly Rates Belford Watkins Group
Principal
Project Coordinator
Intern Architect
CAD Technician
Clencal
Reimbursables Reimbursable expenses would include
Travel
Long distance phone calls
Postage
Reproduction
$105 00/hr
S. 95 00/hr
$ 70 00/hr
$ 55 00/hr
$ 25 00/hr
POUDRE FIRE AUTHORITY —ARCHITECTURAL & E IV G I N E E R I N G
S E R V I C E S
Belford Watkins Group, LLC
CSE Consultants
4710 S College Ave
Ft Collins, CO 80525
phifax (970) 282-8005
e-mail Alcse@gwest net
CSE Consultants - Structural Engineering
Hourly Billing Rate Schedule
2007
CATEGORY RATE
Project Manager $100
Project Engineer $80
Design Engineer $70
CAD Drafting $70
Administrative $50
INTIRMOi CON:U LTING
GROIN
INTERWEST CONSULTING GROUP
PROFESSIONAL SERVICE RATES
2007
1
PERSONNEL
HOURL•( RA E
Principal
$120
Project Manager
$98
Sr Project Engineer
$88
Project Engineer
$83
Design Engineer
$75
CAD Technician
$60
Clerical
$45
Mileage $0 55/mile
Copies (8'/s" X 11") $0 18/copy
Prints (24" X 36") $2 00/sheet
Mylar Sepia (24" X 36") $13 00/sheet
Vellum (24" x 36") $7 00/sheet
Unless otherwise stated in the Agreement for Professional Services, reimbursable expenses such as
outside reproduction, deliveries, sub -consultant fees, and travel costs are in addition to the base contract
fees and are charged as listed above or at cost plus fifteen percent
These Professional Service Rates are considered Confidential and shall not be released to a
third party without written permission of Interwest Consulting Group, Inc Rates are subject to
change
ASSOC ATES INC
rLrCr2jCA1 UVtFrRs
55S7 We,t lyth Street
Greeley, Colorado 80634
Hourly Rates 2007
Principal
Engineer
Designer
AutoCad Operator
Clerical
G RW6R J.W2007 Mast.m H. dy rites d.
@ $110 00 per hour
@ $
95 00 per hour
@ $
80 00 per hour
@ $
60 00 per hour
@ $
45 00 per hour
AE Associates, Inc.
5587 West 19t' Street
Greeley, Colorado 80634
RATE SHEET 2007:
1
President
2
Principals
3
Project Managers
4
Engineers
5
Designers
6
CAD Drafters
7
Administrative
$175 00 per hour
$135 00 to $145 00 per hour
$125 00 to $135 00 per hour
$ 90 00 to $115 00 per hour
$ 65 00 to $105 00 per hour
$ 45 00 to $65 00 per hour
$ 35 00 to $45 00 per hour
SECTION 4
Relevant Experience
The following pages show selected protects that are representative of our experience
C l i e n t
Project Cost
R e l e v a n c e
C l i e n t
P r o I e c t Cost
R e I e v a n c e
Union Colony Fire Rescue - Station #7
Greeley, Colorado
$1,400,000
New Facility
Fire station #7 represented the development of the prototypical station
for Union Colony
Special attention was given to design of a facility that meets fundamental
requirements for the Authoi dy at any location, but allows flexibility to
adapt and expand based upon site specific requirements
Don Watkins -Project Architect
Union Colony Fire Rescue Fire Station #3
Greeley, Colorado
$1, 900, 000
New Facility
This fie station is currently completing construction and is based upon
the prototypical station for Union Colony noted above Escalation of
costs in the current construction environment provided a challenge to
maintain the much desired functionality of the prototypical Station #7
while increasing the number of apparatus bays and sleeping quarters
In depth cost models were investigated to value enE sneer systems and
materials and prioritize goals to bring this protect into budget
POUDRE FIRE AUTHORITY ARCH I T E C T U A L AND ENGINEERING
S E R V I C E S
Beh ord Watkins Group LLC
SECTION Ot
C l i e n t City of Loveland, Loveland Fire Department
Live Fire Training Prop
Loveland, Colorado
Protect Coat $660,000
R e l e v a n c e New Facility
The latest addition to the Loveland Fire Departments facilities is a live
fire training prop that is in the initial stages of construction This two
thousand square foot, two story, cast -in -place concrete structure will be
added to the city's training facility and will provide a realistic training
environment for the firefighters
C l i e n t North Metro Fire Rescue District #66
Broomfield, Colorado
Protect Cost $2,118,000
R e l e v a n c e New Facility
This latest fire station for North Metro Fire Rescue District provides
response to the growing area south of Lafayette, east of Louisville and
north of Broomfield immediately adjacent to the new Northwest Parkway
The building was designed with an agranan theme in keeping with the
concept for the surrounding community including a i adio tower disguised
as a water windmill and native grass plantings A longitudinal clearstory
provides exceptional daylighting at the Apparatus Bay
Don Watkins Prol act Architect
_Z7
L-1-AA
POUDRE
FIRE A U T H O R I T Y ARCHITECTUAL AND ENGINEERING
S E R V I C E S
Belford Watkins Group LLC
SECTION 4
C l i e n t Nederland Fire Station
Nederland, Colorado
Project Cost $2,100,000
R e l e v a n c e New Facility
The site for this budding was very tight and required a two story
� approach to accomplish the desired building program, the location of the
building is very prominent in the community, the budding accommodates
paid and volunteer personnel and administrative offices have also been
_ _ Incorporated in the facility
The building has two ambulance bays and three double loaded
Apparatus bays for six vehicles, storage space, and an area for bio-
Decontamination and turnout gear
It
,p�fp ii+130 The administration/ business area of the station has a large training
Room, officer's office, conference room, chief office and an
1--`--- Administration office
The second floor area above the administration area is the living
Quarters and support facilities for volunteer fire fighters and
Paid staff The extenoi of the facility was designed to serve as
A focal point for the community
II csF-ift c
Don WatkmsPro/eat Architect
POUDRE FIRE AUTHORITY ARCHITECTUAL AND ENG I NE ERING
S E R V I C E S
Bettwof Watkins Group, LLC
A' ` h ' ' e ` ` ° ' e August 14, 2007
Planning
Mr James B O'Neill, II
City of Fort Collins — Purchasing Division
I n t e r i o r s 215 North Mason Street
Fort Collins, CO 80521
RE Poudre Fire Authority — Architectural Services
Proposal No P-1080
Dear Mr O'Neill,
Please accept this proposal as an expression of our interest in being considered to work with
the City of Fort Collins and the Poudre Fire Authority
Our interest in this project stems not only from our experience with fire stations specifically,
but also because of our vast experience with remodel / addition projects, controlled
maintenance projects and feasibility studies Tins flexibility and experience is critical for the
diversity of services that will be required in the open-ended, architectural and engineering
services contract anticipated
We would welcome your contact with any of our Clients in tlus regard
Belford Watkins Group's extensive involvement with facilities where input from numerous
committees is required has facilitated our ability to listen to our Clients and incorporate their
ideas in our design solutions This ability, combined with our understanding of the design
elements that must be considered when constructing a fire station, results in a facilities that
are functional, efficient and durable
We pride ourselves on being responsive to our Clients throughout the design and construction
process Towards this end we provide a design team with a single manager who will be
involved throughout the project We also maintain rigorous commumcations to set goals and
document decisions We area local firm and easily accessible Additionally, we have a
proven track record of being able to work we] I with contractors to provide solutions and
feedback at the time in the design process when responsiveness is so critical
We look forward to an opportunity to further discuss now we can contribute to the success of
your project
Si cerely,
2121 MdymM Drive
Don Watkins
Suite 303
Fort Collins CO 80525
Ph 9704070070
Pm 970 40 71011
C l i e n t
P r o I e c t Cost
R e l e v a n c e
a
Client
P r o 1 e c t Cost
R e l e v a n c e
SECTION It
North Metro Fire Rescue District Station #64
Thorton, Colorado
$800,000
Renovation and Addition
An addition to and remodel of the existing building has provided updated
and enlarged dayroom, dining, kitchen, and office facilities, and also
Replaced dorm -style bunk I ooms
The addition also Includes separate office space for Fire Prevention
Don Watkins -Project Architect
Castle Pines North Metro District
Castle Pines, Colorado
$600, 000
New Facility
The Castle Pines Metropolitan District office and maintenance facility is
located near an upscale residential community To keep the massing of
the building residential in scale, the facility is divided into two buildings
The maintenance yard is screened from the surrounding roadways by
being located between two buildings
The design of the facility respects that of the exclusive Castle Pines
Subdivision
Don Watkins - Project Architect
POUD RE F 1 RE AUTHOR ITV ARCH ITECTUAL AND ENGI NEER ING
S E R V I C E S
Bellord Watkins Group LLC
SECTION 4
Other Relevant Fire Station/Municipal Projects
North Metro Fire Rescue District renovation of Stations #61, 63 and 65
City of Golden Fire Station #4
Bancroft Fire Department Station #3
Castlewood/South Metro Fue District renovation to Stations #35 and 36
Wheat Ridge Police Department addition and renovation
POUDRE FIRE AUTHORITY ARCH I T E C T U A L AND ENGINEERING
S E R V I C E S
Belford Watkins Group, LLC
SECTION 4
References
Client
City of Loveland Fire Department
Live Fire Training Prop
Loveland Colorado
Reference Ken Cooper — 970/962-2635
Chief Mike Charo — 970/962-2808
Client
Union Colony Fire/Rescue Authority
Fire Station #3 and #7
Greeley, Colorado
Reference Chief Doug Forsman— 970/350-9515
Lieutenant Ron Adams — 970/304-3433 (Pager)
Client
Poudre School District
Various remodels and additions
Fort Collins, Colorado
Reference Ed Holder — 970/490-3412
Client
North Metro Fire Rescue District
North Metro Fire Rescue District Stations #66, 63, 68, 6L 65 and 64
Broomfield and Northglenn, Colorado
Reference Fire Chief John O'Hayre — 303/452-9910
Client Nederland Fire Station
Nederland, Colorado
Reference Rick Dirr — 303/259-9161
Client Castlewood Fire Protection District
Castlewood Fire Stations #35, 36 and 37 Remodels
Littleton, Colorado
Reference Chief Frank Young — 303/773-8282
POUDRE FIRE AUTHORITY ARCHITECTUAL AND ENGINEERING
S E R V I C E S
Belford Watkins Group LLC
INTCRWEOi CON ULTING
GROUP
INTERWEST CONSULTING GROUP
REPRESENTATIVE PROJECT EXPERIENCE
Commercial Development
Fort Collins Police Services Facility* — Fort Collins, Colorado (Humphnes-Poli)
Seven Generations Office Park* — Fort Collins, Colorado (Seven Generations, LLC)
Pioneer Charter School* - Fort Collins, Colorado (Architecture West)
Huron Street Library* - Thornton, Colorado (Humphnes-Poll)
Wright Farm Library* - Thornton, Colorado (Humphries -Poll)
Preston Center - Fort Collins, Colorado (Western Property Advisors)
Harmony Technology Park - Fort Collins, Colorado (Hewlett Packard)
Timberline Center — Fort Collins, Colorado (Timberline Development, LLC)
The Village at St Michael's — Greeley, Colorado (Thorp Associates)
Thunder Mountain Harley Davidson Complex, Loveland, Colorado (Thorp Associate)
Residential Development
Rigden Farm - Fort Collins, Colorado (Wheeler Commercial)
Preston Center — Fort Collins, Colorado (Bnsben Development)
Seven Lakes Subdivision - Loveland, Colorado (Glen Properties)
T-Bone Ranch — Greeley, Colorado (Sovereign Homes)
3120 Broadway — Boulder, Colorado (Boulder Housing Partners)
Foothills Community - Boulder, Colorado (Boulder Housing Partners)
Transportation Design (Private)
Timberline/Drake Roadway Improvements at Rigden Farm - Fort Collins, Colorado
(Wheeler Commercial)
Ziegler Roadway Widening at Preston Center - Fort Collins, Colorado (Western
Property Advisors)
Municipal Services
Downtown Enhancement Project - Fort Collins, Colorado
Kechter — Ziegler Roundabout - Fort Collins, Colorado
Timberline Road - Fort Collins, Colorado
Eisenhower Boulevard (US Highway 34) - Loveland, Colorado
I-70 at Hidden Valley - East of Idaho Springs, Colorado (CDOT)
Walnut Street Improvements - Boulder, Colorado
Plan Review — Elk Grove and Livingston, California, Mead, Colorado
* Indicates LEED project
kNuff
LLccrwCc- E c cMe,
,5S7 West 19th SUcet
C,reeleN, Colo,ado 50634
FIRE STATION PROJECTS
UNION COLONY FIRE RESCUE STATION #3
2006
NORTH METRO FIRE STATION #66
2004
FIRE STATION #6, LOVELAND
2004
NEW EATON FIRE STATION
2003
FIRE STA FION NO I4, FT COLLINS
2002
WINDSOR/SEVERANCE FIRE STATION
2002
UNION COLONY FIRE RESCUE STATION #7
2002
LA SALLE FIRE STATION
200I
LAFAYETTE FIRE STATION
I999
FIRE STATION #5 LOVELAND
I998
FIRE STATION # I2 FT. COLLINS
I998
SPRING CANYON FIRE STATION
I997
NORTH METRO FIRE RESCUE AUTHORITY
I996
BANCROFT FIRE STATION #3
I994
FIRE STATION #I0 FT COLLINS
I993
WEST ADAMS CO FIRE PROTECTION DIST
I992
ADAMS COUNTY AIRPORT FIRE STATION
I990
ADAMS CO FIRE STATION
I990
do
AL Atisxx rA IF',
UNION COLONY FIRE STATION #3 - Greeley, CO
11,000 Total Square Feet
Forced Air HVAC System
Vehicle Exhaust System
Currently Under Construction
LOVELAND FIRE STATION #6 - Loveland, CO
10,000 Total Square Feet
Forced Air HVAC System
Vehicle Exhaust System
Garage Make -Up Air/Exhaust System
Completed in 2004
EA1 ON FIRE STATION #1 - Eaton, CO
16,000 Total Square Feet
Forced Air HVAC System
Vehicle Exhaust System
Garage Make -Up Air/Exhaust Syslem
Completed in 2003
BLACK FOREST FIRE STATION • Black Forest, CO
17,000 Total Square Feet
Forced Air HVAC System
Vehicle Exhaust System
Compressed Air Systems
Completed in 2003
LAFAYETTE FIRE STATION, Lafayette, CO TRI-LAKES FIRE STATION - Monument, CO
12,500 Total Square Feet 9,000 Total Square Feet
Forced An HVAC System Packaged Rooftop Units
Vehicle Exhaust System Vehicle Exhaust System
Garage Make -Up An/Exhaust System Garage Make -Up Air I Exhaust System
Completed in 1999 Completed in 1999
CASTLEWOOD FIRE STATION #35 -Arapahoe County, CO
Remodel of Existing Fire Station
Forced Air HVAC System
Completed in 1998
C UanUaMProllnfolMumcipal Prolectslfire stations Bishton wpd
do
A ASSOCIA I LS
UNION COLONY CIVIC CENTER
Greeley, Colorado
65,000 sf complex with two performing arts theaters
Monfort Concert Hall has 1,700 seats
Hensel PhelpsTheater has 250 seats
LOVELAND POLICE AND COURTS BUILDING
Loveland, Colorado
Two-story government office complex
96,000 sf plus partial basement
Lanmer County courtrooms
Medium secunty facility
GREELEY POLICE HEADQUARTERS
Greeley, Colorado
77,000 sf government complex
Gym, laboratory, evidence storage, narcotics
lock -down, interview rooms and offices
OTHER NOTABLE PROJECTS
Lanmer County Detention Facility, Ft Collins, Colorado
Island Grove Treatment Center, Greeley, Colorado
P B Roche Memorial Facility, Greeley, Colorado
Athletic Club, Ft Collins, Colorado
Eaton Fire Station, Eaton, Colorado
Pueblo County Public Works, Pueblo, Colorado
Department of Social Services, Pueblo, Colorado
Lanmer County Alternate Sentencing Unit, Ft. Collins, Colorado
C Uan\Jan\Projanfo\Municrpal Projects\Municipal Hauscr B&G Club
No Text
SECTION I
Statement of Qualifications
Capabilities of Firm Belford Watkins Group is a full -service architectural firm that brings
to your protect a wealth of experience and a team of professionals
who are committed to excellence in design solutions and superior
quality of service The professionals at Belford Watkins Group have
successfully completed over 130 projects locally and nationally As
former partners in large firms with offices in multiple states, we have
intentionally organized a smaller practice and limited the number of
projects we work on each year This has allowed us to be intimately
involved with each of our protects In the larger practices, we have
found that senior experienced persons become predominately
administrators and marketers
Almost all of our protects are public facilities including fire stations,
schools, community centers, university buildings, and churches
Five technical persons make up this office Both Mark Belford and
Don Watkins are licensed in Colorado and each have over 28 years
experience
Assigned Personnel Belford Watkins Group
Don Watkins will be the principal in charge and protect manager
for all new and renovation protects Don Watkins offers an in-
depth history with fire station protects
Mark Belford will assist in design for protects and be in charge of
quality control
Patti Watkins will be in charge of protect coordination and interior
design
Consistent with Belford Watkins Group's philosophy of client
satisfaction and quality control, this team would be in place from
earliest design efforts through the end of construction to provide
consistency and continuity
Consultants
Ron Lindburg-CSE Consultants - will be the principal structural
engineer
Robert Almirall — Interwest Consulting Group - will be the
principal civil engineer and assist with planning submittals
Ron Boone — RJ McNutt and Associates - will be the principal
electrical and lighting engineer
Alicia Thorpe — AE Associates — will be the principal mechanical
engineer
POUCRE FIRE AUTHORITY - ARCHITECTURAL8 ENGINEERING
S E R V I C E S
Belford watkms Group LLC
Education
Registration
Experience
SECTION I
Resumes
Don Watkins -Principal, Project Manager
BA Architecture, Arizona State University
Registered Architect in Colorado, AIIA Member
NCARB registration
With over 25 years experience, Don Watkins has developed a reputation for his multi-
discipline approach to project management, design and coordination in all phases of the built
environment As an architect, he has a wide range of experience with both publicly and
privately funded projects Don's experience includes a broad collection of different types
and sizes of projects which include renovations, additions and new facilities He has varied
experience in working with owners from programming through construction close-out Don
has recently left a partnership in a Denver based firm to establish a new practice in Fort
Collins Dons' career has been characterized by the ability to deliver complete, quality
projects on time and within budget
• Loveland Live Burn Prop, Loveland, Colorado
• Union Colony Fire Rescue Authority Station #3, Greeley,
Colorado
• Union Colony Fire Rescue Authority Station #7, Greeley,
Colorado
• NMFRD Station #66, Broomfield, Coloi ado
• Nederland Fire Station, Nederland, Colorado
• Jefferson County Airport Station, North Metro Fire Rescue District
(NMFRD), Jefferson County, Colorado
• NMFRD Station #64, Addition and Remodel, Broomfield,
Colorado
• Castlewood Fire Stations #35, #36 & #37, Englewood, Colorado
• Castle Pines Metropolitan District, Offices and Maintenance
Facility, Castle Rock, Colorado
• Wheat Ridge Police Department Addition and Remodel, Wheat
Ridge, Colorado
• Bancroft Fire Station #3, Jefferson County, Colorado
• Golden Fire Station #4, Golden, Colorado
• West Adams County Fire Protection District Station Remodels,
Northglenn and Broomfield, Colorado
• Werner Enterprises Phoenux Trucking Terminal, Phoenix, Arizona
• Northglenn Dodge Service Center, Northglenn, Colorado
• Werner Enterprises Denver Trucking Terminal, Adams County,
Colorado
• Grease Monkey, Broomfield, Colorado
POUDRE FIRE AUTHOR ITY -ARCHITECTURAL & ENGINEERING
S E R V I C E S
Belford Watkins Group, LLC
SECTION I
Mark S. Belford - Principal, Project Architect
Ed u c a t i o n Bachelor of Architecture, Kansas State University
R e g i s t r a t i o n Registered Architect in Colorado, AIA Member, NCARB Registration
E x p e r i e n c e Mark Belford has a great deal of experience with K-12 schools, university protects,
recreation centers and religious education protects Most of his work has been in
the public sector Mark recently left as partner in a practice in the
Lawrence/Kansas City area and has recently started a practice in Colorado
Projects Mark has been responsible include
• Fletcher Elementary School Addition & Renovation, Aurora, CO
• Our Lady Of Peace Church Renovation Master Plan, Greeley, CO
• Cherryvale High School Addition 8, Renovation, Cherryvale, KS
• Lincoln Elementary Addition & Renovation, Cherry vale, KS
• Pinckney Elementary Addition & Renovation, Lawrence, KS
• Free State High School Addition, Lawrence, KS
• Centennial Elementary Addition & Renovation, Lawrence, KS
• New York Elementary School Addition & Renovation, Lawrence,
KS
• Mesa County Courthouse Renovation, Grand Junction, CO
• Sunflower Elementary School, Lawrence, KS
• Bear Creek K-8 School, Lakewood, CO
• Kansas Memorial Union Renovation, University Of Kansas
• Dyche Museum Addition & Renovation, University of Kansas
• Willard Hall Renovation, Pittsburg State University
• Good Samaritan Addition & Renovation, Fort Collins, CO
• Corpus Christi Catholic Church & School, Lawrence, KS
• Saint John Church Addition & Renovation, Lawrence, KS
• Baldwin Junior High Addition & Renovation, Baldwin, KS
• Usher Mansion Renovation & Addition, Lawrence, KS
• Spahr Hall Addition & Renovation, University of Kansas
• Lawrence Chamber of Commerce Renovation, Lawrence, KS
• Broken Arrow Elementary School Addition & Renovation,
Lawrence, KS
• Bell Hall Renovation, Fort Leavenworth, Kansas
• Redeemer Lutheran Church & School, Fort Collins, CO
POUDRE FIRE AUTHORITY -ARCH ITECTURAL & ENGINEERING
S E R V I C E S
Belford Watkins Group LLC
RON L. LiNDBURG, P.E.
CSE Consultants • 817 E Lineolnway • Cheyenne, WY 82001 • Telephone 307-634-1701
CSE Consultants • 4710 S College Avenue • Fort Collins, CO 80525 • Telephone 970-282-8005
EDUCATION
UNIVhRSI I Y Of WYOMING
B S degree in Civil Engineering (Architectural option), I986
PROFESSIONAL EXPERIENCE
CSE Consultants - Structural Engineering, Cheyenne, Wyoming & Fort Collins, Colorado
Project Manager & Owner, 2003 - present
Structural Engineer - schematic design, design
development, contract documents and
contract administration for commercial construction
and custom residential construction
Engineer of Record for Projects including
United Way Housing Services Center
Fort'Collins, Colorado
UW Plaza - Buildings 3 &4
Laramie, Wyoming
Good Samaritan - Six Bed Addition
Fort Collins, Colorado
East High School Phase II
Cheyenne, Wyoming
Suncor Energy
Gurnsev & Cheyenne, Wyoming
Lundvall Office Building
Greeley, Colorado
Avanti Business Complex
Cheyenne, Wyoming
Clothes Pony Remodel
Fort Collins, Colorado
Odell Brewing Company Addition
Fort Collins, Colorado
WHIP Flex Warehouse
Windsor, Colorado
Livermore Elementary Addition
Livermore, Colorado
Shepardson Elementary Addition
Fort Collins, Colorado
Peterson Specialty Products
Loveland, Colorado
Heschel Street '16' Townhomes
Fort Collins, Colorado
Good Samaritan -Therapy Addition
Loveland, Colorado
Valley Steel & Wire Company
Fort Collins, Colorado
Jorgenson Laboratories Warehouse
Loveland, Colorado
Ballyneal Golf and Hunt Club
Yuma, Colorado
Milliken Housing Project
Milliken, Colorado
Dunn Elementary Addition
Fort Collins, Colorado
East High School Phase I & IIA
Cheyenne, Wyoming
WyeaTech Diesel Shop
Laramie, Wyoming
Arena Sports Indoor Soccer Arena
Windsor, Colorado
Blackstone C C Pump House
Aurora, Colorado
Lanterl Office Buildings
Fort Collins, Colorado
Timberline Terrace Office Building
Fort Collins, Colorado
Markley Motors Renovations
Fort Collins, Colorado
River Bend Business Park
Laramie, Wyoming
Sunstone Office Buildings
Fort Collins, Colorado
IVA, INC , Ft Collins, Colorado
Project Engineer, 1997 - 2004
Project structural engineer - schematic design, design development, contract documents
and contract administration for structures including schools, churches, theaters, hospitals,
offices and other commercial buildings Structural systems utilizing reinforced masonry,
steel framing, wood framing, structural insulated panels, insulated concrete forms and pre-
engineered metal buildings Multiplex theater projects in seismic zones 3 and 4
Engineer of Record or Project Engineer for Projects including
Coloradoan Office Building Fort Collins, Colorado
Skyline Center for Health Loveland, Colorado
Fossil Ridge High School Fort Collins, Colorado
The Winslow Retirement Village Fort Collins, Colorado
Palmer Design Center Fort Collins, Colorado
Loveland Good Samaritan Kitchen Loveland, Colorado
Resurrection Fellowship Church Loveland, Colorado
Cool River Wine & Spirits Cheyenne, Wyoming
Mountain View High School Loveland, Colorado
Centennial Bank
Bennett Elementary Addition
Rffenburgh Elementary Addition
Union Colony Fire Station #7
Our Saviours Lutheran Church
The Lodge at Miramont
National Wildlife Research Center
Norlarco Credit Union
Mountain View Swimming Pool
Park Meadows Medical Office
Planet Hyundai
"'heat Ridge High School Additions
McCovs Restaurant
Livermore Elementary Addition
Nrwot High School Addition
Rental Cite
St Johns United Church Addition
Buena Vista Elementary
Metro 12 Movie Theatre
Metro 16 Movie Theatre
Estes Park Birthing Suite
Fort Collins/Windsor, Colorado
Fort Collins, Colorado
Fort Collins, Colorado
Greeley, Colorado
Greeley, Colorado
Fort Collins, Colorado
Fort Collins, Colorado
Fort Collins, Colorado
Loveland, Colorado
Lone Tree, Colorado
Golden, Colorado
Wheat Ridge, Colorado
Fort Collins, Colorado
Livermore, Colorado
Niwot, Colorado
Longmont, Colorado
Greeley, Colorado
Buena Vista, Colorado
Calearco, California
Rancho Mirage, California
Estes Park, Colorado
TERRACON CONSULTANTS WESTERN, INC, Ft Collins, Colorado
Protect Engineer, 1993 - 1997
Responsible for the structural design of custom and multifamily residential, commercial
buildings, and earth retaining systems Field observation services for construction relating
to earthwork, foundation, concrete, timber, masonry and steel construction Prepared
geotechnrcal engineering reports for residential and commercial development
EMPIRE LABORATORIES, INC, Ft Collins, Colorado
Staff Engineer, 1986 - 1993
Staff engineer working in the disciplines of geotechnrcal, materials and structural
engineering Supervised subsurface drilling investigations, conducted geotechnral
laboratory tests, and developed asphaltic and Portland cement concrete mix designs Field
engineering work involving the observation of earthwork, utility and budding construction
Supervised drilled pier construction and conducted special inspection of masonry
construction for shopping centers, parking garages, hospitals, schools, and athletic facilities
Evaluated field and laboratory soils data and prepared geotechnrcal engineering reports for
residential and commercial development Structural design of custom homes, office
buildings and foundation systems for pre-engineered metal buildings
PROFESSIONAL REGISTRATION
Registered Professional Engineer Colorado, Wvommg
Licensed !teal Estate Broker Colorado
V
INTIRWRBT CO N Sb LTI NG GROUP
ROBERT ALMIRALL, PE
EDUCATION/REGISTRATIONS
BS / Civil Engineering / Virginia Tech / 1986
1999/Professional Engineer / Colorado, No 33441
1991 / Professional Engineer / Virginia, No 021882
PROFESSIONAL EXPERIENCE
Mr Pdmirall has 21 years of experience providing general civil engineering and client
support services His experience includes the design, project management and oversight
of public and private land development projects in Virginia, California and Colorado
These have included residential, commercial, and industrial site developments, roadway
designs, watershed analyses, grading and drainage plans, storm sewer and stormwater
management plans, erosion and sedimentation control plans, sanitary and water main
system design, flood plain studies, and site layouts
Prior to joining lnterwest Consulting Group, Pvlr Almirall was a Project Manager,
Division Manager and most recently the Director of Operations for a Fort Collins,
Colorado office of a statewide engineering firm, Director of Engineering for a 25 person
land development firm in Manassas, Virginia, a partner and Vice President in his own
firm in Fairfax, Virginia, and a Design Engineer for a statewide; engineering and planning
firm based out of Northern Virginia.
As a Project Manager, Mr Almirall has been responsible for the design, quality control
and processing of numerous entitlement and land development projects These have
included Annexation and Rezoning applications, Municipal projects and private land
development designs Mr Almirall is dedicated to client satisfaction through his
commitment to responsiveness, attention to detail, budget management and strong
communication skills
PROJECT EXPERIENCE
Fort Collins Police Services Facility — Fort Colliuis, Colorado
Project Manager for the City of Fort Collins Police Facility on Timberline Road This
project included the grading and utility design as well as the LEED certifications required
for the proposed site construction Through a sep.rrate contract with the City Engineering
Department, the design of rimberlme Road adjacent to the site was also integral to the