HomeMy WebLinkAboutCHANGE ORDER - RFP - P677 FUTURE SW W & WW FACILITY IMPROVEMENTSCITY OF FORT COLLINS
CHANGE ORDER
CONTRACTOR Rocky Mountain Consultants
ADDRESS 8301 E Prentice Ave Suite 101
Englewood, CO 80111
PURCHASE ORDER NO 9907330
DESCRIPTION
PROJECT TITLE Interconnect Pipeline
PROJECT NUMBER 50264327
CHANGE ORDER NUMBER D-2
1 Reason for change Pipeline construction lasted longer than time contracted with RMC for
resident services
2 Description of change See attached exhibit
3 Change in Contract Cost Add $13,764 00 to Contract Cost
4 Change in Contract Time No change in Contract Time
ORIGINAL CONTRACT COSTS
$121,710 00
TOTAL APPROVED CHANGE ORDERS
6,96000
TOTAL PENDING CHANGE ORDERS
000
TOTAL THIS CHANGE ORDER
13,764 00
TOTAL % OF ORIGINAL CONTRACT, THIS CO 11 3%
TOTAL % OF ORIGINAL CONTRACT, ALL CO' S 17 0%
ADJUSTED CONTRACT COST
$142,434.00
(Assuming all change orders approved)
ACCEPTED BY
's Representative
SUBMITTED BY
FlY.W1
DATE
REVIEWED BY '� DATE
Title Senior Utilit Ey ngmeer
APPROVED BY ����i DATE
Title Utilities General NTanager
cc City Clerk Architect/Engineer
Finance Purchasing
Project Manager Contractor
I \eng\forms\coform doc
ROCKY MOUNTAIN CONSULTANTS INC
April 10, 2000
Mr Dean Saye
City of Fort Collins
P O Box 580
Fort Collins, CO 80522-0580
Re Interconnect Pipeline, Metering and Flow Control Facility
Dear Mr Saye
8301 E Prentice Ave
Suite 101
Englewood CO 8011 1
(303)741-6000
FAX (303) 741-6106
The following additional costs have been incurred as a result of very slow construction
progress, thus substantially increasing the amount of project management and resident
engineering services for the City of Ft Collins and Tri-District interconnect pipeline protect
The resident engineering services as set forth in change order #1 totaled 120 hours @
$58 00/hr for a total amount of $6,960 00 Thus far, the total hours of resident engineering
services provided is 278 hours The total cost for these additional services is as follows
Resident Engineer - 158 hours @ $58 00/hr = $ 9,164 00
Project Manager - 40 hours @ $115 00/hr = $ 4,60000
Total Additional Costs $13,764 00
Rocky Mountain Consultations hereby requests that change order #2 to the original
contract for the Interconnect Pipeline Project be approved in the amount of $13,764 00
The terms and conditions of the existing agreement between the City of Ft Collins and
Rocky Mountain Consultants, Inc would remain unchanged
The opportunity to provide these services is greatly appreciated
questions, please do not hesitate to contact me at your convenience
Sincerely,
ROCKY MOUNTAIN CONSULTANTS, INC
William A Schuler, P E
Principal
O \FRONT OFFICE\Ene\Correspondence\DSaye_lnlerconnedPipeline RequesM2 wpd