HomeMy WebLinkAboutCHANGE ORDER - BID - 5300 CARPET MAINTENANCE PROJECT (7)CHANGE ORDER
PROJECT TITLE - Carpet Maintenance
PROJECT NUMBER 5300
CHANGE ORDER NUMBER-2-2003
DESCRIPTION In preparing change orders show in order as separate numbered paragraphs the following
1 Reason for change 2 Description of change 3 Change in contract cost 4 Change in contract
time
1 New building added
2 Nix Farm Office — 2,297SF carpet
3 Start 1-03-12-31-03 - Total cost - $430 41
4 No change in contract time
ORIGINAL CONTRACT COST
$44,583 89
APPROVED CHANGE ORDERS
4,56900
TOTAL PENDING CHANGE ORDERS
-00-,
TOTAL THIS CHANGE ORDER
43041
(Assuming all change orders approved)
$49,583 30
ACCEPTED BY
SUBMITTED BY
REVIEWED BY
APPROVED BY
cc Contractor, Contract Administrator, Dept File, City Clerk, Purchasing