HomeMy WebLinkAboutCHANGE ORDER - CONTRACT - FORT COLLINS LOVELAND AIRPORT REHABILIATE RECONSTRUCT TAXIWAY A CHANGE ORDER 5Change Order
Number 5
March 8, 2007
PROJECT TITLE AND NUMBER: Rehabilitate and Reconstruct Taxiway A
PURCHASE ORDER NUMBER:
1 Reason for Change — Runway 6-24 pavement is cracked and deteriorated badly and is in need of
rehabilitation
2. Description of Change — Change order # 5 will add Schedule V Q to the project for rehabilitation
of Runway 6-24 Rehabilitation will involve crack repair by crack filling on smaller cracks and full
depth repair for larger cracks After crack repair, the runway will be paved with a 1 inch asphalt
leveling course to provide abase for the stress absorbing fabric After construction of the leveling
course, the runway will be covered with a stress absorbing fabric and over laid with a 2 5 inch
asphalt concrete surface course Change order #5 will add quantities to the project for crack repair,
asphalt cold planning to match existing asphalt, stress absorbing tabnc, asphalt, marking, and
shoulder grading
Change in Contract Cost—$301,976 00 (see attached table for breakdown of change order costs)
Unit process used to determine the cost of the work are from the existing contract prices from the
subject project
4 Change in Contract Time /Calendar Days
10 �J.t .0
Original Contract Cost: $4,908, t 17 50
Total Approved Change Orders: $ (92,192 45)
Total Pending Change Orders: $ 000
Total This Change Order: $ 301,976 00
Adjusted Contract Cost: $ 5,117,901 05
(assuming all changed orders are approved)
Submitted by Date
Project Man a ger
Reviewed/Approved by e // L� Date (21/i ZA 7
D ector
V
Approved by
City Manager (if applicable)
Date
Change Order
Number 5
March 8, 2007
This change order is accepted and the contract is amended to conform thereto, thi.%day
200
CITY OF LOVELAIID
l�l
by a 2 i�
0
JZ)/(l / .
Type or print name
CITCOL INS
I
by
�-ji^°1P�^-Nc�tt,as�na
TT pe or print name'
ApprovW aw Yo i ur+nr:
A-Wsitartt C4ty Attcww,
COULSON EXCAVATION
by
Type or print name (�/GE PREs/d�n/T
AppgOVED AS TO FORM
BY ASSI.,. `.T CIT ;ITTC INFY
Change Order #5
V H- Rnhand,tuh. Rnnwav 6.7d (Nnn_FMl roll
ITEM NO
DESCRIPTION
UNIT
Unit Price
Quantity
Amount
P-101-5 4
Asphalt Cold Planing (Variable Depth)
SY
$5 00
715
$ 3,57500
P-101-5 11
Type 1 Asphalt Crack Repair
LF
$1 50
2,500
$ 3,75000
P-101-5 12
Type 2 Asphalt Crack Repair
LF
$12 41
2,100
$ 28,541 00
P-152-42
Borrow Excavation
CY
$600
275
$ 1,65000
P-152-4 3
Shouldering with Topsoil
CY
$5 00
740
$ 3,70000
P-310-51
Stress Absorbing Fabric
SY
$300
17,500
$ 52,50000
P-401-8 1
Btummous Paveinan
TON
$35 00
3,480
$ 121,800 00
P-401-8 2
Bituminous Material
CON
$362 00
210
$ 76,020 00
P-603-5 I
Bituminous Tack Coal
CAL
$2 00
3,500
$ 7,00000
P-620-5 1
Permanent Pavement Marking
SF
$0 55
1,770
$ 97350
P-620-5 2
Temporary Pavement Marking
SF
$0 55
1,770
$ 973 50
T-901-5 1
Seeding with Hydromuleh
AC
$1,065 00
1
$ 1,49100
Total Schedule Vll $ 301,976.00