CHANGE ORDER NO, I
PROJECT TITLE: Bobcat Ridge phase 11 design
CONTRACTOR: Arrowhead Trails, Inc
PROJECT NUMBER: 982
DESCRIPTION: Additional design of phase 11 trail
1. Reason for change: Addfdonal lineal footage added to trail.
2. Description of Change: Three additional days of field work Q $750.00/day plus
15% mobilization.
3. Change in Contract Cost: $2,587.50
4. Change in Contract Time: Finish 7127/07
ORIGINAL CONTRACT COST
TOTAL APPROVED CHANGE ORDER
TOTAL PENDING CHANGE ORDER
TOTAL THIS CHANGE ORDER
TOTAL % OF THIS CHANGE ORDER
TOTAL C.O.% OF ORIGNINAL CONTRACT
$ 19,115,28
2,687.50
0.00
2.687.60
13.5
ADJUSTED CONTRACT COST $ 21,702:78
(Assuming all change orders approved)