Loading...
HomeMy WebLinkAboutCHANGE ORDER - REQUISITION - 30842FROM : FAX NO. : Oct. 18 2006 12:03PM P2 CHANGE ORDER NO, I PROJECT TITLE: Bobcat Ridge phase 11 design CONTRACTOR: Arrowhead Trails, Inc PROJECT NUMBER: 982 DESCRIPTION: Additional design of phase 11 trail 1. Reason for change: Addfdonal lineal footage added to trail. 2. Description of Change: Three additional days of field work Q $750.00/day plus 15% mobilization. 3. Change in Contract Cost: $2,587.50 4. Change in Contract Time: Finish 7127/07 ORIGINAL CONTRACT COST TOTAL APPROVED CHANGE ORDER TOTAL PENDING CHANGE ORDER TOTAL THIS CHANGE ORDER TOTAL % OF THIS CHANGE ORDER TOTAL C.O.% OF ORIGNINAL CONTRACT $ 19,115,28 2,687.50 0.00 2.687.60 13.5 ADJUSTED CONTRACT COST $ 21,702:78 (Assuming all change orders approved) BY: BY: DATE: Purchasing Agent over $30,000 Contractor Project File Architect Engineer Purchasing