CHANGE ORDER NO. #42
PROJECT TITLE: SPRING CANYON COMMUNITY PARK
CONTRACTOR: ECI
PROJECT NUMBER: 5952
PURCHASE ORDER NO_: 6602274
DESCRIPTION: misc changes
1. Reason for change: revised dog park dock fence connection, temp irrigation by Olander, cone mowband at
creekside fence, cone storage bins at maint_ Bldg_, change seeding milestone 1 week for
pump station intake line work, 15 red oaks by contractor instead of forestry, remove walls
and free standing boulders at ballfield, add 12" ads pipe at north bridge
2. Description of Change: revised dog park dock fence connection, temp irrigation by Olander,
cone mowband at creekside fence, cone storage bins at maint_
Bldg., change seeding milestone 1 week for pump station intake
line work, 15 red oaks by contractor instead of forestry, remove
walls and free standing boulders at ballfield, add 12" ads pipe at
north bridge
3_ Change in Contract Cost: $23,020.42 iEs
4. Change in Contract Time: 0
e-c)--07
VR1V11VNL L.I,)N 1 r%M%.1 %.UQ t $11,514,848.18
TOTAL APPROVED CHANGE ORDER $869.154.93
TOTAL PENDING CHANGE ORDER $0.00
TOTAL THIS CHANGE ORDER $23,020.42
TOTAL % OF ORIGINAL CONTRACT, THIS C.O. 0.20%
TOTAL % OF ORIGINAL CONTRACT, ALL C.O.'S 7.75%
ADJUSTED CONTRACT COST 12,407,023.5
(Assuming all change orders approved)
ACCEPTED BY:
Contractor's Represent
ACCEPTED BY:
Project Manager
REVIEWED BY:
Title:
APPROVED BY:
Title:
DATE: r ~ 2 0 ` CT
DATE: 17• 1,0 - P -%
DATE'
DATE:
APPROVED BY: DATE:
purchasing Agent over $30,000
cc: City Clerk Architect
Contractor engineer
Project Re Purchasing