HomeMy WebLinkAboutCHANGE ORDER - BID - 5952 SPRING CANYON COMMUNITY PARK (12)08/02/2007 THU 09:05 FAX 970 221 6586 CITY OF FT COLLINS CLRS
Q 001/001
CHANGE ORDER NO. #43
PROJECT TITLE: SPRING CANYON COMMUNITY PARK
CONTRACTOR: ECI
PROJECT NUMBER: 5952
PURCHASE ORDER NO.: 6602274
DESCRIPTION: additional safety surfacing depth
1. Reason for change- for DOLA grant compliance, change the varying depth surfacing to 4" depth consistent
across the playground
2. Description of Change: additional rubber surfacing to achieve 4" depth surfacing throughout
playground
3. Change in Contract Cost: $28,000.00
4_ Change in Contract Time: 0
S•-) -off
UIHIUINAL CONTRACT COST
$11,514,8.18
84$869.154.93
TOTAL APPROVED CHANGE ORDER
TOTAL PENDING CHANGE ORDER
$23,020.42
TOTAL THIS CHANGE ORDER
$28,000.00
TOTAL % OF ORIGINAL CONTRACT, THIS C.O.
0 24%
TOTAL % OF ORIGINAL CONTRACT, ALL C.O.'S
7.99%
ADJUSTED CONTRACT COST
12,435,0 3. 3
(Assuming all change orders approved)
r
ACCEPTED BY:
DATE,
Contractors Representative
ACCEPTED BY:
DATE_ �. d
Project Manager
REVIEWED BY:
DATr=:
Title:
—
APPROVED BY: DATE:
Title: '
APPROVED BY: DATE:
Purchasing Agent over $30,000
cc: City Clerk Archiiect
Contractor Engineer
Project He Purchasing