Loading...
HomeMy WebLinkAboutCHANGE ORDER - REQUISITION - 30469vx Change Order Form City of Fort Collins PRO ft%V-!partmenc2007 Street Maintenance Program, Concrete Project PROJECT NUMBER: 3202000 (Bid No. 6046) CONTRACTOR: Vogel Concrete (PO #7704283) CHANGE ORDER NUMBER: 1 n preparing change orders show to order as separa a numbered paragraphs the o owing: 1. Reason for change. 2. Description of change. 3. Change in contract cost. 4. Change in contract time. 1.&2. See attached invoice for details 3. The contract cost will increase by $2,984.37 4. One (1) day will be added to the contract time. ORIGINAL CONTRACT COST $1,203,057.22 TOTAL APPROVED CHANGE ORDERS $0.00 TOTAL PENDING CHANGE ORDERS $0.00 TOTAL THIS CHANGE ORDER $2,984.37 TOTAL % OF THIS CHANGE ORDER 0.25% TOTAL C.O. % OF ORIGINAL CONTRACT 0.25% ADJUSTED CONTRACT COST $1,206,041.5.9 ACCEPTED BY: REVIEWED BY:` SUBMITTED BY: APPROVED BY APPROVED BY APPROVED BY cc: Accounting Purchasing Contractor Project File 6 - al- 0 DATE: C DATE: / " ' ^ 0 DATE: (Purchasing Agent over $30,000) $2,984.37 Stormwater 504 ✓rj044 (O(•-7 . 529 2rt p ,(,. Engineering Department - 281 North College Avenue • P.O. Box 580 • Fort Collins, CO 80522-0580 • (970) 221-6605 2006 Concrete Project Vogel Concrete Bid No. 5847 Change Order No.: 1 Date: 6/12/2007 1. Reason For Change: a. Additional concrete work was performed by Vogel Concrete for City Stormwater Utility on Parker St. & Peterson PI. 2. Description Of Change: a. Pay for additional concrete repairs at contract unit prices. b. Pay for additional concrete repairs at contract unit prices. c. Pay for additional concrete repairs at contract unit prices. d. Pay for additional concrete repairs at contract unit prices. e. Pay for additional concrete repairs at contract unit prices. 3. Change In Contract Amount: Item Qty Unit Unit Cost Total Cost a. 304.01 Aggregate Base Course 2 Ton $26.44 $52.88 b. 604.07 Modified Type 13 Curb Inlet - Remove & Replace 1 Each $1,710.58 $1,710.58 c. 604.07 Modified Type 13 Curb Inlet - material Only 1 Each $707.04 $707.04 d. 608.11 Hollywood Curb, Gutter & 6" Sidewalk - Remove & Replace 6.5 LF $34.20 $222.30 e. 608.12 Hollywood Curb & Gutter - No Sidewalk - Remove & Replace 11 LF $21.79 $239.69 f_ 608.24 Expansion & Caulking 12.5 LF $4.15 $51.88 TOTAL CHANGE IN CONTRACT AMOUNT 4. Change In Contract Time a. One day is added >o the contract. TOTAL CHANGE IN CONTRACT TIME $2,984.37 1 Days H:\p.m.p\PROJECTS\2007\Concrete\Pay Estimates\07 CONTRACTOR MONTHLY PAY ESTIMATE 1 of 1