HomeMy WebLinkAboutCHANGE ORDER - BID - 30324 6027 PRIMROSE ART STUDIOSECTION 00950
CHANGE ORDER NO. 01
PROJECT TITLE: Primrose Art Studio Remodel
CONTRACTOR: Construction Concepts, Inc.
PROJECT NUMBER: Bid No. 6027 "B"
DESCRIPTION: Remodel Work
In preparing change orders show In order as separate numbered paragraphs the following:
1. Reason for change: To reduce health hazards from mice and rat droppings and remove Crawl
Space debris.
2. Description of change: Replace existing ductwork with all new material and clear/rake Crawl
Space,
3. Change in contract cost: Add $1,068.00
4. Change in contract time: 0 days
(Attach additlonal sheets as required)
y' oD 3�1 0Zs4)
ORIGINAL CONTRACT COST
300,471.00
TOTAL APPROVED CHANGE ORDERS
00.00
TOTAL PENDING CHANGE ORDERS
00.00
TOTAL THIS CHANGE ORDER
1,068.00
TOTAL % OF THIS CHANGE ORDER Less than 10/6
TOTAL % OF ORIGINAL CONTRACT Less than 1%
ADJUSTED CONTRACT COST
301.539,00
!Assuming all change orders approved?
ACCEPTED BY: 5-25-07
;Construct n ncepts, [no. Date
ACCEPTED BY:GZ!/
teve White, Project Ma ager Date
t
REVIEWED BY:�
Aller-Lingle Date
APPROVED BY: rf/0 %
M k Sears, Natural Areas Date
cc: Project File, Contractor, Purchasing, Engineer
303acl