CHANGE ORDER FORM
City of Fort Collins
PROJECT TITLE: Mason Transportation Corridor
PROJECT NUMBER: 30521900
CONTRACTOR: Felsburg Holt & Ullevig (PO #2206648)
CHANGE ORDER NUMBER: 5
In preparing change orders show in order as separate numbered paragraphs the following:
1. Reason for change. 2. Description of change.
3. Change in contract cost. 4. Change in contract time.
1. & 2. See attached for reason and description of change.
3. The contract cost will increase by $12,730.00
4. There will be no change in contract time.
ORIGINAL CONTRACT COST $1,642,542.00
TOTAL APPROVED CHANGE ORDERS $904,112.60
TOTAL PENDING CHANGE ORDERS
TOTAL THIS CHANGE ORDER
ADJUSTED CONTRACT COST
(Assuming all change
ACCEPTED BY:
SUBMITTED BY;
$0.00
$12, 730.00
$2,559,384.60
DATE: Jl s—o7
DATE: 5
/_�/O 7
REVIEWED BY: N t A- DATE:
(Engineer)
APPROVED BY: N i ✓k— DATE:
APPROVED BY:
APPROVED BY:
cc. City Clerk
Contractor
Purchasing
Project File
(Department Head)
DATE: s% J y A4
(Service Area
DATE:
(Purchasing Agent)
=So [forth i Ikon • 1?0. oox 580 • Fort C oilllls, L 0 80522-0580 • (97 0) 224-n058 • F_1X (,97o) 2_1-o239
MA
FELSBURG
(4HOLT &
ULLEVIG
engineering paths to transportation solutions
April 16, 2007
Ms. Kathleen Bracke, AICP
Senior Transportation Planner
City of Fort Collins
PO Box 580
Fort Collins, CO 80522
RE: Budget Addendum Request
FHU Reference No. 06-287
Dear Ms. Bracke:
A request has been made by City of Fort Collins staff to use our sub -consultant, Carter &
Burgess, for additional NEPA Environmental Assessment assistance. Attached is a proposal
from Carter & Burgess for the additional services. If this budget addendum is approved, our
contract budget for the BRT EA and PE should be revised as follows:
Total Contract co 3_ H
• Currently Contracted Amount = $536,215.00
• Requested Addendum = $ 12,730.00 Z=
• New Total = $548,945.00
If you have any questions regarding this information, please do not hesitate to call me at 303-
721-1440.
Sincerely,
FELSBURG HOLT & ULLEVIG
Richard R. Follmer, PE, PTOE
Senior Transportation Engineer
6300 South Syracuse Way, Suite 600 Centennial, CO 80111 tet 303.712 1. 1440 fax 303.72L0832
www.thuen,.com into@flzueng.com
Carter-Surgess
April 9, 2007
Mr. Rich Follmer
Felsburg Holt & Ullevig
6300 South Syracuse Way, Suite 600 D (�� �Y�!
Centennial, CO 80111 IE
AFR ± 2007
JJ I
RE: Mason Corridor BRT Additional Requested Services FELSBURG, HOLT& ULLEVIG
Dear Rich,
In a conversation I had last week, Kurt Ravenschlag with the City of Fort Collins requested that i provide an
'.'..itvliiuw %=v iii.; uc:U:iionui uCS. -�iiiia vlils niiitii .�Y: Biu gc,>s utiuu.�e-�....Cvilul"lvTiJ ucu �ioia Of theia:..0ii
BRT EA.
As part of the current scope, Carter & Burgess is preparing existing conditions sections for the following
resources: visual, noise and vibration, air quality and hazardous materials. Under this proposed scope Carter &
Burgess would update existing conditions for the following additional resources:
• Land use and zoning • Water resources and water quality
• Social • Floodplains
• Economic • Paleontological resources
• EJ • Parks and Recreation areas
• Wildlife & Fisheries • Trails
• Vegetation and noxious weeds
The estimate for the additional work is $12,730, including preparation of 8 graphics. This scope also assumes
the following:
• City is responsible for updating existing conditions for:
o Right-of-way
o Historic and archaeological resources
o Transportation (existing conditions and impacts)
• FHU is responsible for providing the necessary right -of --way information to the city and updating
'IT 0 -1 ..
o Threatened and endangered species
Thank you for your assistance and please let me know if you need any additional information.
Sincerely,
J11"4rd
Tracey MacDonald
Project Manager
Cc: Gina McAfee