HomeMy WebLinkAbout113275 ALLER-LINGLE-MASSEY ARCHITECTS PC - CONTRACT - CONTRACT - 29904PROFESSIONAL SERVICES AGREEMENT
THIS AGREEMENT made and entered into the day and year set forth below, by and
between THE CITY OF FORT COLLINS, COLORADO, a Municipal Corporation, hereinafter referred
to as the "City" and Aller-Lingle Architects. P.C., hereinafter referred to as "Professional'.
W ITNESSETH:
In consideration of the mutual covenants and obligations herein expressed, it is agreed by
and between the parties hereto as follows:
1. Scope of Services. The Professional agrees to provide services in accordance with
the scope of services attached hereto as Exhibit "A", consisting of four (4) pages, and incorporated
herein by this reference.
2. The Work Schedule. The services to be performed pursuant to this Agreement shall
be performed in accordance with the Work Schedule attached hereto as Exhibit "B", consisting of
one (1) page, and incorporated herein by this reference.
3. Contract Period, This Agreement shall commence within five (5) days of signing and
shall continue in full force and effect until June 30, 2008, unless sooner terminated as herein
provided.
4. Early Termination by City. Notwithstanding the time periods contained herein, the
City may terminate this Agreement at any time without cause by providing written notice of
termination to the Professional. Such notice shall be delivered at least fifteen (15) days prior to the
termination date contained in said notice unless otherwise agreed in writing by the parties.
All notices provided under this Agreement shall be effective when mailed, postage prepaid and sent
to the following addresses:
Professional: City: With Copy to:
Aller-Lingle Architects City of Fort Collins, OPSVS City of Fort Collins, Purchasing
Attn: Dave Lingle Attn: Steve White PO Box 580
712 Whalers Way ste B100 117 N. Mason Fort Collins, CO 80522
Fort Collins, Co 80525 Fort Collins, CO 80524
In the event of any such early termination by the City, the Professional shall be paid for services
Standard Professional Services Agreement- rev 09/01 /06
4. Record Documents: Preparation of record documents upon the completion of construction
of this project.
Work Not Included
1. Design or construction documents for core and shell of the building. This will be provided by
Bayer Properties. We will coordinate our work with theirs as necessary.
2. Structural engineering for core and shell elements related to the library design, including
increase in floor loading, cantilevers beyond the exterior walls, clerestory "lantern" framing,
elevator shafts, structural components of the main and secondary exit stair, etc. This will be
provided by Bayer Properties. We will coordinate with their work as necessary.
3. Civil engineering and landscape architecture design for any related on -site improvements,
including parking lot and common entry plaza improvements, grading and drainage, and site
utilites. The design does not include a curbside book return.
4. Interior design services beyond specifications for painting, carpeting and other hard
surfaces. Selection of fabrics, upholstery, window coverings and moveable equipment is not
included. Studiotrope will coordinate with the City -approved vendor for furnishings and
shelving systems specifications, as described above.
5. Fire sprinkler system design, engineering and flow calculations. This system will be
design/build by the selected Subcontractor, based upon a performance specification
provided by the Mechanical Engineer, if not part of the core and shell work.
6. 3-Dimensional CAD renderings, models or other presentation documents. See additional
Services.
7. Specialty consultants for audio/visual and/or data/video/telecommunications systems shall
be provided as Additional Services, and are not a part of the Scope of Basic Services.
8. Blueprinting and copying of bid documents, and distribution to Contractors for bidding will be
provided by the City; we will furnish vellum plots of our original drawings and originals of the
appropriate technical specification sections.
Owner -Provided Information
1. CAD drawings in AutoCAD 2006 format of the proposed building's core and shell floor plans,
elevations, building cross sections, structural framing, and core and shell mechanical,
plumbing and electrical systems.
2. Design criteria for HVAC, plumbing and electrical systems and other specialty systems and
equipment for the library tenant finish.
3. Copies of all applicable standard documents, forms, specifications or other information from
the City of Fort Collins to be a part of the bidding documents.
4. Coordination with telephone, electric, natural gas, propane or other independent utility
and/or building services providers for infrastructure and equipment installation.
5. Enhanced or additional building commissioning, as required for LEED certification.
Standard Professional Services Agreement- rev 09/01/06 10
Consultants
The following consultants will be used on this project:
Library Design Consultant
Studitrope
Joseph Montalbano
2942 Welton Street
Denver, CO 80205
(303) 308-1144
Civil Engineering
KL&A Inc.
Doug Rutledge
4412 W. Eisenhower Blvd., Suite 200
Loveland, CO 80537
(970) 667-2426
Mechanical Engineering
Abrahamson Engineering
Roger Abrahamson, P.E.
3101 Kintzley Court, Unit D
LaPorte, CO 80535
(970) 221-2569
Cost Consultant
Moore Construction Consulting Services
Don Moore
1215 Crestway Court
Fort Collins, CO 80526
(970) 222-5030
LEED Consultant
Design Balance
Kelly Karmel
P. O. Box 7214
Missoula, MT 59807
(406)721-7077
Energy Modeling Consultant
Ambient Energy
Renee Azerbegi, CEM LEED-AP
4392 Ulysses Way
Golden, CO 80403
(303) 278-1532
Electrical Engineering
Electrical Systems Consultants
Kate Hodgson
212 W. Mulberry
Fort Collins, CO 80521
(970) 224-9100
Standard Professional Services Agreement- rev 09/01/06 11
EXHIBIT B
Schedule
Phases 2 and 3 Scope of Basic Services shall be performed in accordance with the following
proposed schedule, subject to the design schedule of the core and shell by Bayer Properties:
Phase 1:
Completion of Programming and Conceptual Design:
Late February 2007
Phase 2:
Complete 100% Design Development:
May 14, 2007
City Review Complete:
May 28, 2007
Complete 95% Construction Documents:
August 17, 2007
City Review Complete:
August 31, 2007
Complete 100% Construction Documents:
September 10, 2007
Phase 3:
Bidding/Negotiation Phase: Approx. November 1-December 31, 2007
Construction Administration Phase: Approx. January 1-June 30, 2008
Adjustments to this schedule may be made if Bayer Properties' schedule shifts.
Standard Professional Services Agreement- rev 09/01/06 12
EXHIBIT C
Fees
Aller•Lingle Architects P.C. and our team of consultants propose to complete the project for fees on
an hourly basis as follows:
Phase 1: Complete.
Phase 2:
Studiotrope (Interior Architecture):
Hourly not -to -exceed: $
29,050.00
Studiotrope (Graphic Design for Interior Signage):
Hourly not -to -exceed: $
3,750.00
Aller•Lingle Architects P.C.:
Hourly not -to -exceed: $
27,300.00
LEED Consultant:
Hourly not -to -exceed: $
10,800.00
Energy Modeling:
Hourly not -to -exceed: $
24,000.00
Daylighting Study:
Hourly not -to -exceed: $
4,500.00
KL&A Inc.:
Hourly not -to -exceed: $
1,800.00
Abrahamson Engineering Inc.:
Hourly not -to -exceed: $
20,600.00
Electrical Systems Consultants:
Hourly not -to -exceed: $
15,600.00
Design Balance (LEED On-line Submittal):
Hourly not -to -exceed: $
2,200.00
Cost Consultant:
Hourly not -to -exceed: $
1,800.00
Reimbursable Expenses Allowance:
Not -to -exceed: $
4,800.00
Total:
Not -to -exceed: $146,200.00
Phase 3:
Studiotrope: Hourly not -to -exceed: $ 7,300.00
Aller-Lingle Architects P.C.: Hourly not -to -exceed: $15,500.00
Design Balance: Hourly not -to -exceed: $ 6,300.00
Abrahamson Engineering Inc: Hourly not -to -exceed: $ 4,900.00
Electrical Systems Consultants: Hourly not -to -exceed: $ 3,800.00
Design Balance (LEED On-line Submittal): Hourly not -to -exceed: $ 3,200.00
Reimbursable Expenses Allowance: Not -to -exceed: $ 2,000.00
USGBC Certification Fees: Not -to -exceed: $ 2,100.00
Total: Not -to -exceed: $45,100.00
Reimbursable Expenses
In addition to Basic Services, the following expenses in connection with this project shall be
reimbursable in accordance with our master contract, as itemized by the allowance above:
1. Blueprinting
2. Copying
3. Long distance telephone/FAX
4. Mileage and related travel expenses
5. Postage
Photography or other miscellaneous expenses
Plotting of CAD -generated drawings for City reviews and presentations
LEED registration and submittal fees
These allowances do not include blueprinting and copying for bid/constructions sets.
Additional Services
If the city requests additional services beyond those set forth in this Proposal, or for additional
services as described elsewhere in this Proposal, such services shall be agreed to in writing
between the City and the Architect and the fees adjusted accordingly per the following, current
hourly rates:
Standard Professional Services Agreement- rev 09/01/06 13
Studiotrope
Principal:
$110/hour
Project Manager:
$95/hour
Graphic Designer:
$85/hour
Project Architect/Project Coordinator:
$80/hour
Project Team Member Level II:
$65/hour
Project Team Member Level I:
$55/hour
Administrative:
$40/hour
Aller•Lingle Architects P.C.
Principal:
$105/hour
Associate Architect:
$92/hour
Sr. Project Manager/Architect:
$84/hour
Project Manager/Architect:
$75/hour
Architectural Intern/CAD Tech.2:
$58/hour
Draftsperson/CAD Tech.1:
$50/hour
Clerical/Administrative:
$36/hour
Design Balance
Principal: $125/hour
KL&A
Principal
$130/hour
Project Engineer
$100/hour
Design Engineer
$82/hour
Engineering Intern
$69/hour
Senior CAD Drafter
$69/hour
Steel Detailer
$69/hour
CAD Drafter
$54/hour
Clerical
$36/hour
Abrahamson Engineering Inc.
Principal/Project Engineer: $90/hour
Professional Engineer: $75/hour
Mechanical Engineer/Senior Designer: $65/hour
Draftsperson: $42/hour
Clerical: $42/hour
Electrical Systems Consultants Inc.
Project Manager:
$70/hour
Project Engineer:
$66/hour
Electrical Designer:
$50/hour
CAD Technician 1:
$40/hour
Clerical:
$30/hour
Moore Construction Consulting Services
Detailed Architectural Project Cost Estimating:
$65/hour
Mechanical/Plumbing/Electrical Estimating:
$65/hour
Plan Interpretation and Consultation Services:
$55/hour
Standard Professional Services Agreement- rev 09/01/06 14
From: Valerie Mathiason At: Front Range Insurance Group FaxID: 970-225-6596 To: Purchasing Dept
Date: 4/3/2007 10:35 AM Page: 2 of 3
ACORD CERTIFICATE OF LIABILITY INSURANCE OP ID
DATE(MMIDD/YYW)
ALLER-1
04/03/07
PRODUCER
THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION
ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE
Front Range Insurance Group
HOLDER. THIS CERTIFICATE DOES NOT AMEND, EXTEND OR
1109 Oak Park Drive Suite 101
ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW.
Fort Collins CO 80525
Phone : 97 0 -22 3 -1804
INSURERS AFFORDING COVERAGE
NAIC #
INSURED
INSURER AThe Hartford
Aller-INSURER
Architects PC
B: Uw Hampshire Aourance Co.
INSURER
Michael
Michael L Allen, AIA
Al
712 WhalQrs Flay Suite B-100
NsuRERD
Ft. Collins CO $0525
INSURER E'.
THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTWITHSTANDING
ANY REOUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR
MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH
POLICIES. AGGREGATE LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS.
LTR
NSR
TYPE OF SJSURANCE
POLICY NUMBER
DATE (MMIDD/YY
14
DATE MMIDD/YY)
LIMITS
GENERAL LIABILRY
EACH OCCURRENCE
$ 1,000,000
A
X
X COMMERCIAL GENERAL LIABILITY
34 SBA KJ7716 DX
04/09/06
04/09/07
PREMISES(Eeoccurence)
$300,000
CLAIMS MADE E OCCUR
MED EXP (Any one Person)
$ 10,000
PERSONAL & ADV INJURY
$ 1,000,000
X
Hired & nonowned
GENERAL AGGREGATE
$2,000,000
GEN'L AGGREGATE LIMIT APPLIES PER:
PRODUCTS - COMP/OP AGG
$ 2 , 000 , 0 00
POLICY X PRIjECT LOC
AUTOMOBILE
LIABILITY
A
X
ANY AUTO
34UECIQ8390
10/12/06
04/09/07
COMBINED SINGLE LIMIT
(Ea accident
$1,000,000
ALL OWNED AUTOS
BODILY INJURY
$
SCHEDULED AUTOS
(Per person)
A
X
HIRED AUTOS
34UECIQ8390
10/12/06
04/09/07
A
X
NON -OWNED AUTOS
34UECIQ8390
10/12/06
04/09/07
BODILY INJURY
(Per accident)
$
PROPERTY DAMAGE
$
(Per accidert)
GARAGE LIABILITY*
AUTO ONLY - EA ACCIDENT
$
ANY AUrTO
EA ACC
OTHER THAN
$
AUTO ONLY'. AGG
$
EXCESSIUMBRELLA UABILrrY
EACH OCCURRENCE
$1,000,000
A
X OCCUR F-1CLAIMSMADE
34SBAKJ7716DX
10/12/06
04/09/07
AGGREGATE
$1,000,000
DEDUCTIBLE
RETENTION $10000
$
WORKERS COMPENSATION AND
EMPLOYERS'LUIBRRY
I TORY LIMITS ER
E.L. EACH ACCIDENT
$
ANY PROPRIETORUPARTNERIEXECUTIVE
OFFICER(MEMIBER EXCLUDED?
E.L. DISEASE - EA EMPLOYEE
$
If yea, describe under
E.L. DISEASE -POLICY LIMIT
$
SPECIAL PROVISIONS below
OTHER
B Pro. Liability 468611701 12/14/06 F12/14/07 E60 $1,000,000
$2,000000
,
DESCRIPTION OF OPERATIONS / LOCATIONS I VEHICLES /EXCLUSIONS ADDED BY ENDORSEMENT! SPECIAL PROVISIONS
The City of Fort Collins is named as additional insured with regards to
general liabitity.
l`COTIGI/�AT! rJ/�� nr•n _
City of Fort Collins
Purchasing Department
FAX 221-6707
PO Box 580
Fort Collins CO 80522
CITY OF SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE THE EXPIRATION
DATE THEREOF, THE ISSUING INSURER WILL ENDEAVOR TO MAL 10 DAYS WRITTEN
NOTICE TO THE CERTIFICATE HOLDER NAMED TO THE LEFT, BUT FAILURE TO DO SO SHALL
IMPOSE NO OBLIGATION OR LIABILITY OF ANY KIND UPON THE INSURER, ITS AGENTS OR
REPRESENTATIVES.
From: Valerie Mathiason At: Front Range Insurance Group FaxID: 970-225-6596 To: Purchasing Dept Date: 4f3l2007 10:35 AM Page: 3 of 3
04/03/2007 10:31AM Pinnacol Assurance PAGE 2 OF 3
ACORD .
CERTIFICATE OF LIABILITY INSURANCE
DATE04M�IP //D007Y
PRODUCER
Pimaool Assurance
7501 E Lowry Blvd
DENVER CO 80230-7006
THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY
AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS
CERTIFICATE DOES NOT AMEND, EXTEND OR ALTER THE COVERAGE
AFFORDED BY THE POLICIES BELOW.
INSURERS AFFORDING COVERAGE NAIC #
INSURED
ALLER • LINGLE ARCHITECTS PC
712 WHALERS WAY B•100
FORT COLLINS CO B0525
INSURER A: PmnaGol Assurance
41190
INSURER E,
INSURER C:
INSURER D:
INSURER E',
COVERAGES
THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTWITHSTANDING
ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR
MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH
POLICIES. LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS.
INSR
LTR
ADD'L
IN9O
TYPE OF INSURANCE
POLICY NUMBER
POLICY EFFECTIVE
DATEIMMOO/YYYYI
POLICY EXRRAnON
OATE(MMOD/YYYYI
OMITS
GENERAL LIABILITY
COMMERCIAL GENERAL LIABILITY
CLAIMS MADi ❑ OCCUR
EACH OCCURRENCE
DAMAGE TO RENTED
FREMISES (E..«unncJ
MED EXP (Am ... ... .nl
PERSONAL E ADV INJURY
GII AGGRGATE UNIT M77S PER:
POUCY PROJECT lAC
GENERAL AOGREGATE
PRODUCTS. COMPMP AGG
AUTOMOBILE LIABILITY
ANY AUTO
ALL OWNED AUTOS
SCHEDULED AUTOS
HERO AUTOS
NONOWNED AUTOS
COMBINED ANGLE LIMIT
M..«id. tl
BODILY INJURY
IP. P...nl
BODILY INJURY
IF..c dnU
PROPERTY DAMAGE
IPr •cdd.n0
GARAGE LIABILITY
ANY AUTO
AUTO ONLY - EA ACCIDENT
OTHER THAN EA ACC
AUTO ONLY: AGO
ERCEEEAIMBRELLA LULGLIrT
OCCUR CLAIMSMAOE
DEDUCTIBLE
RETENTION t
EACH OCCURRENCE
AGGREGATE
A
WORKERS COMPENSATION AND
EMPLOYERS, IIABIUTY
ANY PROPRIETOPUPAWNER.EXECUTIVE
OFFBCEWMEMBER EXCLUDEDT
H v.., 0..c. dwrb.—d. SPECIAL PROVISIONS 6J6.
1951272
-
04/01/2007
04101 /2008
X WC STATU. Lj OTHER
TORY UNITS
E.L. EACH ACCIDENT
8500 OOO
E.L DISEASE. EAEMFLOYEE
SSOO DOD
E.L. DISEASE - POLICY UNIT
s 5OO OOO
OTHER
OEWBIIr10N OF OPERATON6 / LOCATIONS / VEHICLES I EXCW61GN6 ADDED BT ENDORNMENT / 6PECW. PROVIBION6
SEE BACK OF CERTIFICATE FOR CLASS COVERAGE AND OWNERSHIP COVERAGE DETAIL
CERTIFICATE HOLDER
CANCELLATION
S79147
City of Fort Collins
Attn: Purchasing
PO Box 580
Fort Collins CO 80522
ACORD 25 (2001108)
SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE THE
EXPIRATION DATE THEREOF, THE ISSUING COMPANY WILL ENDEAVOR TO MAIL
DAYS WRITTEN NOTICE TO THE CERTIFICATE HOLDER NAMED TO THE LEFT,
BUT FAILURE TO MAIL SUCH NOTICE SHALL IMPOSE NO OBLIGATION OR
LIABILITY OF ANY KIND UPON THE COMPANY, ITS AGENTS OR REPRESENTATIV
AUTHORIZED REPRESENTATIVE
Rodney Postillion
Underwriter ACORD CORPORATION 1988
PINNAWEBE.t.nd/EMPR.«rdO* 06/03/07 30:27:55 1951272 U.d.t.d: 12ASA99612:00:00 UW135
04/03/2007 10:31AM Pinnacol Assurance PAGE 3 OF 3
CERTIFICATE HOLDER COPY
IMPORTANT
If the certificate holder is an ADDITIONAL INSURED,
the policy(ies) must be endorsed. A statement on
this certificate does not confer rights to the
certificate holder in lieu of such endorsement(s).
If SUBROGATION IS WAIVED, subject to the terms and
conditions of the policy, certian policies may
require an endorsemem. A statement on this
certificate does not confer rights to the
certificate holder in lieu of such endorsemem(s).
DISCLAIMER
City of Fort Collins
The Certificate of Insurance on the reverse side
Attn: Purchasing
of this form does not constitute a contract between
the issuing insurer(s), authorized representative
PO Box 680
Fort Collins CO 80522
or producer, and the certificate holder, nor does it
affirmatively or negatively amend, extend or alter
the coverage afforded by the policies listed thereon.
POLICY NUMBER: 1951272
BUSINESS LOCATION: ALLER- LINGLE ARCHITECTS PC
CLASSIFICATION OF OPERATION
COVERAGE COVERAGE
RATI
CLASS DESCRIPTION
EFFECTIVE EXPIRES
TYPE
Affiliate Coverage:DAVID LINGLE
860105ENGINEERS OR ARCHITECTS
04/01/2007 04/01/2008
CO
Affiliate Coverage:MICHAEL ALLER
860105ENGINEERS OR ARCHITECTS
04/01/2007 04/01/2008
CO
Affiliate Coveragge:BRADLEY MASSEY
86010BENGINEERS OR ARCHITECTS
04/01/2007 04/01/2008
CO
86010SENGINEERS OR ARCHITECTS
04/01/2007 04/01/2008
EM
881005EXCLUSIVELY OFFICE
04/01/2007 04/01/2008
EM
AGENDA ITEM SUMMARY
FORT COLLINS CITY COUNCIL
SUBJECT
Items Relating to the Southeast Branch Library.
RECOMMENDATION
ITEM NUMBER: 26 A-C
DATE: March 6, 2007
STAFF: Marty Heffernan
Staff recommends adoption of the Resolutions and the Ordinance on First Reading.
FINANCIAL IMPACT
Approximately $5.8 million is available from library capital improvement expansion fees collected
from new residential construction in Fort Collins since 1996. These fees are collected to pay for the
impact of growth on the quality of library services. Funds must be spent within a reasonable time
of collection (approximately 10 years) to provide library materials or facilities. Staff anticipates
construction and furnishings, including the library's collection, will cost about $5.5 million.
Recent ballot language authorized the newly formed library district to operate a southeast branch
library once it is constructed. The annual operating budget would be approximately $750,000 -
$1,200,000 depending on the level of staffing needed.
EXECUTIVE SUMMARY
A. Resolution 2007-020 Authorizing an Exemption to the Competitive Process for the City to
Enter into a Contract with Bayer Properties for the Construction of the Southeast Branch
Library.
B. Resolution 2007-021 Authorizing an Exemption to the Competitive Process for the City to
Enter into a Contract with Aller-Lingle Architects to Complete Architectural Services of the
Design and Construction Phases of the Southeast Branch Library.
C. First Reading of Ordinance No. 037, 2007, Appropriating Prior Year Reserves Designated
for Library Improvements in the Capital Improvement Expansion Fund for Transfer to the
City's Capital Projects Fund to Construct a Southeast Branch Library and the General Fund
to Purchase Library Books and Materials.
Resolution 2007-020 will allow the City to coordinate construction of the Southeast Branch Library
at Front Range Village with Bayer Properties.
rendered prior to the date of termination, subject only to the satisfactory performance of the
Professional's obligations under this Agreement. Such payment shall be the Professional's sole right
and remedy for such termination.
5. Design, Project Indemnity and Insurance Responsibility. The Professional shall be
responsible for the professional quality, technical accuracy, timely completion and the coordination
of all services rendered by the Professional, including but not limited to designs, plans, reports,
specifications, and drawings and shall, without additional compensation, promptly remedy and
correct any errors, omissions, or other deficiencies. The Professional shall indemnify, save and hold
harmless the City, its officers and employees in accordance with Colorado law, from all damages
whatsoever claimed by third parties against the City; and for the City's costs and reasonable
attorneys fees, arising directly or indirectly out of the Professional's performance of any of the
services furnished under this Agreement. The Professional shall maintain commercial general
liability insurance in the amount of $500,000 combined single limits and errors and omissions
insurance in the amount of $ N/A.
6. Compensation. In consideration of the services to be performed pursuant to this
Agreement, the City agrees to pay Professional on a time and reimbursable direct cost basis
according to the following schedule and Exhibit C consisting of two (2) pages and incorporated
herein by this reference:
Hourly billing rates:
Principal:
$105/hour
Associate Architect:
$92/hour
Sr. Project Manager/Architect:
$84/hour
Project Manager/Architect:
$75/hour
Architectural Intern/CAD Tech.2:
$58/hour
Draftsperson/CAD Tech.1:
$50/hour
Clerical/Administrative:
$36/hour
Reimbursable direct costs: as billed
with maximum compensation (for both Professional's time and reimbursable direct costs) not to
exceed One Hundred Ninety One Thousand Three Hundred Dollars ($191,300). Monthly partial
Standard Professional Services Agreement- rev 09/01/06 2
March 6, 2007 -2- Item No. 26 A-C
Resolution 2007-021 authorizes a contract with Alter -Lingle Architects, already under a City
purchasing contract, to provide comprehensive architectural services through the design and
construction phases of the project.
Ordinance No. 037, 2007, appropriates available library impact fees to pay for the design and
construction of the Library and the collection.
BACKGROUND
The City is working with Bayer Properties to include a 16,000 square -foot library in the Front Range
Village development. The library will be located on the second floor of an attractive, centrally
located building. The library will be owned by the City and will provide convenient and much
needed library services for the community.
Area voters recently approved the new library district, including new funds to pay for the operation
of the SE Branch Library. Existing funds collected from impact fees are sufficient to pay for the
construction and furnishing of a 16,000 square -foot branch. This branch will help meet the goals
identified in the Library Capital Improvement Plan of four books per capita and .7 square feet per
capita of library space by 2015. The library is currently at 2.56 books per capita and .4 square feet
per capita.
Resolution 2007-020
Bayer Properties has retained a construction contractor for all the buildings in the Front Range
Village development, including the core and shell of the building the library will occupy. By
coordinating the construction of the library core and shell through Bayer, the City will realize
efficiencies, benefit from economies of scale and expedite the completion of the library. The core
and shell includes the foundation, walls, roof and associated elements of the building. Because
Bayer's contractor will be constructing the first floor core and shell, it would be difficult and
inefficient to bring in a separate contractor to build the core and shell for the second floor. Having
two contractors working on the structure of the same building would also create significant
coordination issues and cause confusion regarding responsibility for warranty work. The cost ofthe
library's portion of the core and shell will be determined by the final design of the library space but
is not anticipated to exceed $1.5 million. Under the City's agreement with Bayer, the City must
approve the design and all costs associated with construction of the core and shell on a line item
basis. The City has hired an independent estimator to verify the reasonableness of all costs.
Staff intends to utilize a competitive process to select a contractor to finish the library space. The
finish work includes the entire interior space of the library, everything from drywall and electrical
to carpeting, lighting and shelving.
Partnering with Bayer on the Library project maximizes use of the impact fees designated
for library services and materials. Bayer's contribution to the library project is substantial.
Bayer is providing the land for the library building and paying for the infrastructure costs
associated with bringing necessary utilities and streets to the development and to the library
building itself.
March 6, 2007 -3- Item No. 26 A-C
Bayer is also providing the adjacent parking lots and paying the associated offsite
development costs and fees.
Operation Services has estimated that the cost savings to the City by partnering with Bayer
is approximately 2.2 million dollars compared to the cost of the City building a stand alone
branch library.
Resolution 2007-021
Because the City is under extreme time pressures to complete the construction of the library in
conjunction with the construction of the Front Range Village, City Purchasing has made a
determination per Section 8-161(d)(1)(b) of the Code of the Cityof Fort Collins, that although there
exists more than one (1) responsible source, a competitive process cannot reasonably be used or, if
used, will result in a substantially higher cost to the City, will otherwise injure the City's financial
interests or will substantially impede the City's administrative functions or the delivery of services
to the public. The Purchasing Agent has submitted the requisite justification to the City Manager
for approval and the City Manager has reviewed and concurred in that determination for this
acquisition.
Section 8-161(d) (3) requires Council approval of all exceptions to the competitive process over One
Hundred Thousand Dollars ($100,000) prior to acquisition.
Bayer Properties intends to begin construction of its development next month and open the new retail
center in June of 2008. Due to the aggressive timeline for construction of the building that will
include the library, Aller-Lingle Architects, already under City of Fort Collins purchasing contract,
was consulted for preliminary plans required by Bayer to begin the core and shell design. Aller-
Lingle sub -contracted for librarydesign expertise from Joseph Montabano of Studiotrope in Denver.
Phase One was completed for $41,000 and allowed Bayer Properties architects to begin drawings
for the core and shell of the building.
To insure the integrity of the Southeast Branch Library project, from conceptual design through
completion, City staff is asking to hire Aller-Lingle to provide comprehensive architectural services
through the design and construction phases of the project, including mechanical, electrical and
library design. The estimated cost for these services is $191,300. Aller Lingle Architects P.C.'s
design team is the most appropriate for continuing the design work for the new Fort Collins branch
library because:
• The team of Aller Lingle Architects P.C. and Studiotrope has been working with the library
staff for the programming and conceptual design phases of the project, including
coordination with Bayer Properties, and has full knowledge and understanding of the
functional and aesthetic needs of this library branch.
Studiotrope was selected by the library staff as the library design consultant based upon its
experience and skill in library planning and design.
March 6, 2007 -4- Item No. 26 A-C
• Aller Lingle Architects P.C. has a 20-year working relationship with the City of Fort Collins,
including such major projects as the Downtown Transit Center and the Northside Aztlan
Community Center.
• Aller Lingle Architects P.C. has experience with LEED-accredited projects, including both
the Utilities Vehicle Storage facility and the Northside Aztlan Community Center for the
City.
• Aller-Lingle Architects P.C. has a working knowledge of the City's Design Standards
Manual, specifying the design and maintenance requirements of all city facilities.
• Aller-Lingle has retained the services of Joseph Montalbano, an award -winning architect
with ten years of experience designing libraries in Colorado and elsewhere. He has worked
on public libraries in Littleton, Aurora, and Walsenburg as well as Reno, Nevada. He spent
seven years working with the Denver firm Brendle AVP.
Ordinance No. 037, 2007
The City would use available library impact fees to pay for the design and construction of the library
and for the library collection.
• The City would own the library through a condominium deed Bayer is providing.
• All off -site development costs, parking, utility infrastructure to the building, streets, green
space and numerous site amenities will be provided by Bayer without cost to the library
project.
• The City will pay for construction of the second floor library space and related infrastructure,
including a first floor lobby, elevators, a stairway and book drops.
• The branch library will be operated by the new Fort Collins Regional Library District under
the terms worked out in the intergovernmental agreement.
It is anticipated that construction of the new library will be completed by June 2008 so it can be
opened at the same time the shopping center opens.
RESOLUTION 2007-020
OF THE COUNCIL OF THE CITY OF FORT COLLINS
AUTHORIZING AN EXEMPTION TO THE COMPETITIVE PROCESS FOR THE CITY
TO ENTER INTO A CONTRACT WITH BAYER PROPERTIES
FOR THE CONSTRUCTION OF THE SOUTHEAST BRANCH LIBRARY
WHEREAS, Bayer Properties has agreed to construct a branch library on the second floor of one of
the buildings at their Front Range Village Development; and
WHEREAS, City staff has determined that savings of approximately $2,200,000 will be realized by
partnering with Bayer Properties for the construction of a 16,000 square foot branch library located over retail
space planned for the Front Range Village, located near the intersection of Harmony and Ziegler Roads; and
WHEREAS, the Purchasing Agent has determined that Bayer Properties offers the best opportunity
to construct the Southeast Branch Library at a substantial savings; and
WHEREAS, if the City wishes to take advantage of the cost savings of partnering with Bayer
Properties there is not sufficient time to initiate and complete a new competitive selection process for the
construction of the exterior shell of the Southeast Branch Library; and
WHEREAS, the estimated cost to have Bayer Properties construct the exterior shell of the Southeast
Branch Library is approximately ONE MILLION FIVE HUNDRED THOUSAND DOLLARS ($1,500,000);
and
WHEREAS, pursuant to Section 8-161(d)(1)(b) of the Code of the City of Fort Collins authorizes
Council to approve an exemption to the competitive process when, although there exists more than one
responsible source, a competitive process cannot reasonably be used or, if used, will result in a substantially
higher cost to the City, will otherwise injure the City's financial interests or will substantially impede the
City's administrative functions or the delivery of services to the public; and
WHEREAS, the Purchasing Agent has submitted the required written justification to the City Manager
for approval; and
WHEREAS, the City Manager has reviewed and concurred in that determination for this procurement;
and
WHEREAS, Section 8-161(d)(3) required approval of this purchasing method by the City Council
for items costing more than ONE HUNDRED THOUSAND DOLLARS ($100,000).
NOW, THEREFORE, BE IT RESOLVED BY THE COUNCIL OF THE CITY OF FORT COLLINS
that the construction of the exterior shell of the Southeast Library at Front Range Village by Bayer Properties
in an amount up to ONE MILLION FIVE HUNDRED THOUSAND DOLLARS ($1,500,000) is approved
as an exemption to the City's competitive procurement requirements.
Passed and adopted at a regular meeting of the Council of the City of Fort Collins this 6th day of
March, A.D. 2007.
Mayor
ATTEST:
City Clerk
RESOLUTION 2007-021
OF THE COUNCIL OF THE CITY OF FORT COLLINS
AUTHORIZING AN EXEMPTION TO THE COMPETITIVE PROCESS FOR
THE CITY TO ENTER INTO A CONTRACT WITH ALLER-LINGLE ARCHITECTS
TO COMPLETE ARCHITECTURAL SERVICES OF THE DESIGN AND
CONSTRUCTION PHASES OF THE SOUTHEAST BRANCH LIBRARY
WHEREAS, Aller-Lingle Architects has an existing work order agreement with the City for
miscellaneous design services costing up to $50,000; and
WHEREAS, Aller-Lingle Architects has successfully completed the phase one design of the
Southeast Library Project; and
WHEREAS, the Purchasing Agent has determined that Aller-Lingle Architects has extensive
knowledge and direct experience on the Southeast Library Project and offers the best opportunity
for continuity and streamlining between the phase one design and completed construction; and
WHEREAS, City staff has determined that savings of approximately $2,200,000 will be
realized by partnering with Bayer Properties for the construction of a 16,000 square foot branch
library located over retail space planned for the Front Range Village, located near the intersection
of Harmony and Ziegler Roads; and
WHEREAS, if the City wishes to take advantage of the cost savings ofpartnering with Bayer
Properties there is not sufficient time to initiate and complete a new competitive selection process
fora design firm; and
WHEREAS, the cost to have Aller-Lingle Architects complete design services through
construction is ONE HUNDRED NINETY-ONE THOUSAND THREE HUNDRED DOLLARS
($191,300); and
WHEREAS, pursuant to Section 8-161(d)(1)(b) of the Code of the City of Fort Collins
authorizes Council to approve an exemption to the competitive process when, although there exists
more than one responsible source, a competitive process cannot reasonably be used or, if used, will
result in a substantially higher cost to the City, will otherwise injure the City's financial interests or
will substantially impede the City's administrative functions or the delivery of services to the public;
and
WHEREAS, the Purchasing Agent has submitted the required written justification to the City
Manager for approval; and
WHEREAS, the City Manager has reviewed and concurred in that determination for this
procurement; and
WHEREAS, Section 8-161(d)(3) requires approval of this purchasing method by the City
Council for items costing more than ONE HUNDRED THOUSAND DOLLARS ($100,000).
NOW, THEREFORE, BE IT RESOLVED BY THE COUNCIL OF THE CITY OF FORT
COLLINS that the purchase of design and construction services in the amount of ONE HUNDRED
NINETY-ONE THOUSAND THREE HUNDRED DOLLARS ($191,300) from Aller-Lingle
Architects for the construction of the Southeast Library Project as an exemption to the City's
competitive procurement requirements, is hereby approved:
Passed and adopted at a regular meeting of the Council of the City of Fort Collins this 6th
day of March, A.D. 2007.
Mayor
ATTEST:
City Clerk
ORDINANCE NO. 037, 2007
OF THE COUNCIL OF THE CITY OF FORT COLLINS
APPROPRIATING PRIOR YEAR RESERVES DESIGNATED FOR LIBRARY
IMPROVEMENTS IN THE CAPITAL IMPROVEMENT EXPANSION FUND
FOR TRANSFER TO THE CITY'S CAPITAL PROJECTS FUND TO CONSTRUCT A
SOUTHEAST BRANCH LIBRARY AND THE GENERAL FUND TO PURCHASE LIBRARY
BOOKS AND MATERIALS
WHEREAS, the City of Fort Collins has recognized and addressed the issue of requiring
future growth and new development to contribute its proportionate shareof the cost of providing new
capital facilities and infrastructure required to maintain the City's level of services to its residents;
and
WHEREAS, on May21,1996, the City Council adopted Ordinance No. 051,1996 amending
the City Code by adding a new article pertaining to the imposition of capital improvement expansion
fees to be used to fund capital improvements for the library, community parkland, police services,
fire services, and general governmental facility services; and
WHEREAS, the capital improvement expansion fees imposed under the provisions of the
aforementioned section of the City Code, including a Library Capital Improvement Expansion Fee,
went into effect on July 1, 1996, and the City has since been receiving those fees as a condition of
the issuance of building permits; and
WHEREAS, on July 21, 1998, the City Council adopted on second reading Ordinance No.
121,1998, increasing the library capital improvement expansion fee to reflect the increased level of
service resulting from the opening of the Harmony Library at Front Range Community College; and
WHEREAS, City Code Section 7.5-27(a) requires that library capital improvement expansion
fee funds be used only for capital improvements related to the provision of general library services,
as such improvements may be identified in the capital improvements plan for library services; and
WHEREAS, on May 19, 1998, the City Council adopted Resolution 1998-83 creating the
Capital Improvements Plan for the library, which plan recommends the library strive to provide 4.0
books per city resident and provide 0.7 square foot per capita; and
WHEREAS, the construction of a new southeast branch library and the purchase of books
and other library materials needed for the new branch library is consistent with the Capital
Improvements Plan; and
WHEREAS, Library staff has determined that savings of approximately $2,200,000 will be
realized by partnering with Bayer Properties for the construction of a 16,000 square foot branch
library located over retail space planned for the Front Range Village, located near the intersection
of Harmony and Ziegler Roads; and
WHEREAS, the estimated cost to construct a 16,000 square foot branch library including the
purchase of books and materials is $5.5 million; and
WHEREAS, library staffrecommends appropriating library capital improvement expansion
fee revenues, in the amount of $5.5 million, to be used to construct a 16,000 square foot branch
library including the purchase ofbooks and materials, located at the proposed Front Range Village;
and
WHEREAS, the request for appropriation of fees is consistent with the uses of the fees set
forth in Chapter 7.5 of the City Code; and
WHEREAS, Article V, Section 9, of the Charter of the City of Fort Collins permits the City
Council to appropriate by ordinance at any time during the fiscal year such funds for expenditure as
may be available from reserves accumulated in prior years, notwithstanding that such reserves were
not previously appropriated; and
WHEREAS, it is the desire of the City Council to appropriate the sum of $5.5 million from
prior year reserves designated for library capital improvements in the Capital Improvement
Expansion Fund for transfer as follows:
To the Capital Projects Fund for Construction of a Branch Library $ 4,500,000
To the General Fund for Books and Materials 1,000,000
Total $ 5,500,000
for appropriation therein, as set forth in the Library Capital Improvements Plan.
NOW, THEREFORE, BE IT ORDAINED BY THE COUNCIL OF THE CITY OF FORT
COLLINS as follows:
Section 1. That there is hereby appropriated from prior year reserves designated for library
capital improvements in the Capital Improvement Expansion Fund, the sum of FOUR MILLION
FIVE HUNDRED THOUSAND DOLLARS ($4,500,000), for transfer to the Capital Projects Fund -
Southeast Branch Library capital project, and appropriated therein, to be used to construct a 16,000
square foot branch library at the proposed Front Range Village.
Section 2. That there is hereby appropriated from prior year reserves designated for library
capital improvements in the Capital Improvement Expansion Fund, the sum of ONE MILLION
DOLLARS ($1,00,000), for transfer to the General Fund, and appropriated therein, to be used to
purchase books and materials for the new branch library at the proposed Front Range Village.
-2-
Introduced and considered favorably on first reading and ordered published this 6th day of
March, A.D. 2007, and to be presented for final passage on the 20th day of March, A.D. 2007.
Mayor
ATTEST:
City Clerk
Passed and adopted on final reading this 20th day of March, A.D. 2007.
ATTEST:
City Clerk
-3-
Mayor
payments based upon the Professional's billings and itemized statements of reimbursable direct
costs are permissible. The amounts of all such partial payments shall be based upon the
Professional's City -verified progress in completing the services to be performed pursuant hereto
and upon the City's approval of the Professional's reimbursable direct costs. The parties
acknowledge that the sub -contractors: Studiotrope, KL&A Inc., Abrahamson Engineering, Moore
Construction Consulting Services, Design Balance, Ambient Energy and Electrical Systems
Consultants are not parties to this agreement. However, the rates listed for services to be
provided by these subcontractors shall be the rate paid by the City to the Professional for these
services. If the amount charged by these subcontractors exceed the rates listed in Exhibit "C"
the excess amount shall not be paid or owed by the City. Final payment shall be made following
acceptance of the work by the City. Upon final payment, all designs, plans, reports,
specifications, drawings and other services rendered by the Professional shall become the sole
property of the City.
6. City Representative. The City will designate, prior to commencement of work, its
project representative who shall make, within the scope of his or her authority, all necessary and
proper decisions with reference to the project. All requests for contract interpretations, change
orders, and other clarification or instruction shall be directed to the City Representative.
7. Project Drawings. Upon conclusion of the project and before final payment, the
Professional shall provide the City with reproducible drawings of the project containing accurate
information on the project as constructed. Drawings shall be of archival, prepared on stable mylar
base material using a non -fading process to provide for long storage and high quality reproduction.
"CD" disc of the as -built drawings shall also be submitted to the owner in and AutoCAD version no
older then the established city standard.
8. Monthly Report. Commencing thirty (30) days after the date of execution of this
Agreement and every thirty (30) days thereafter, Professional is required to provide the City
Representative with a written report of the status of the work with respect to the Scope of Services,
Standard Professional Services Agreement- rev 09/01/06 3
Work Schedule, and other material information. Failure to provide any required monthly report may,
at the option of the City, suspend the processing of any partial payment request.
9. Independent Contractor. The services to be performed by Professional are those of
an independent contractor and not of an employee of the City of Fort Collins. The City shall not be
responsible for withholding any portion of Professional's compensation hereunder for the payment of
FICA, Workers' Compensation, other taxes or benefits or for any other purpose.
10. Personal Services. It is understood that the City enters into this Agreement based on
the special abilities of the Professional and that this Agreement shall be considered as an
agreement for personal services. Accordingly, the Professional shall neither assign any
responsibilities nor delegate any duties arising under this Agreement without the prior written
consent of the City.
11. Acceptance Not Waiver. The City's approval of drawings, designs, plans,
specifications, reports, and incidental work or materials furnished hereunder shall not in any way
relieve the Professional of responsibility for the quality or technical accuracy of the work. The City's
approval or acceptance of, or payment for, any of the services shall not be construed to operate as a
waiver of any rights or benefits provided to the City under this Agreement.
12. Default. Each and every term and condition hereof shall be deemed to be a material
element of this Agreement. In the event either parry should fail or refuse to perform according to the
terms of this agreement, such party may be declared in default.
13. Remedies. In the event a party has been declared in default, such defaulting party
shall be allowed a period of ten (10) days within which to cure said default. In the event the default
remains uncorrected, the party declaring default may elect to (a) terminate the Agreement and seek
damages; (b) treat the Agreement as continuing and require specific performance; or (c) avail
himself of any other remedy at law or equity. If the non -defaulting party commences legal or
equitable actions against the defaulting party, the defaulting party shall be liable to the
non -defaulting party for the non -defaulting party's reasonable attorney fees and costs incurred
Standard Professional Services Agreement- rev 09/01/06 4
because of the default.
14. Binding Effect. This writing, together with the exhibits hereto, constitutes the entire
agreement between the parties and shall be binding upon said parties, their officers, employees,
agents and assigns and shall inure to the benefit of the respective survivors, heirs, personal
representatives, successors and assigns of said parties.
15. Law/Severability. The laws of the State of Colorado shall govern the construction,
interpretation, execution and enforcement of this Agreement. In the event any provision of this
Agreement shall be held invalid or unenforceable by any court of competent jurisdiction, such
holding shall not invalidate or render unenforceable any other provision of this Agreement.
17. Prohibition Against Employing Illegal Aliens. This paragraph shall apply to all
Contractors whose performance of work under this Agreement does not involve the delivery of a
specific end product other than reports that are merely incidental to the performance of said work.
Pursuant to Section 8-17.5-101, C.R.S., et. seq., Contractor represents and agrees that:
A. As of the date of this Agreement:
1. Contractor does not knowingly employ or contract with an illegal alien; and
2. Contractor has participated or attempted to participate in the basic pilot
employment verification program created in Public Law 208, 104th
Congress, as amended, and expanded in Public Law 156, 108th
Congress, as amended, administered by the United States Department of
Homeland Security (the "Basic Pilot Program") in order to verify that
Contractor does not employ any illegal aliens.
B. Contractor shall not knowingly employ or contract with an illegal alien to
perform works under this Agreement or enter into a contract with a
subcontractor that fails to certify to Contractor that the subcontractor shall not
knowingly employ or contract with an illegal alien to perform work under this
Agreement.
C. Contractor shall continue to apply to participate in the Basic Pilot Program and
shall in writing verify same every three (3) calendar months thereafter, until
Contractor is accepted or the public contract for services has been completed,
whichever is earlier. The requirements of this section shall not be required or
effective if the Basic Pilot Program is discontinued.
D. Contractor is prohibited from using Basic Pilot Program procedures to
undertake pre -employment screening of job applicants while this Agreement is
being performed.
Standard Professional Services Agreement- rev 09/01/06 5
E. If Contractor obtains actual knowledge that a subcontractor performing work
under this Agreement knowingly employs or contracts with an illegal alien,
Contractor shall:
1. Notify such subcontractor and the City within three days that Contractor
has actual knowledge that the subcontractor is employing or contracting
with an illegal alien; and
2. Terminate the subcontract with the subcontractor if within three days of
receiving the notice required pursuant to this section the subcontractor
does not cease employing or contracting with the illegal alien; except that
Contractor shall not terminate the contract with the subcontractor if during
such three days the subcontractor provides information to establish that
the subcontractor has not knowingly employed or contracted with an illegal
alien.
Contractor shall comply with any reasonable request by the Colorado
Department of Labor and Employment (the "Department") made in the course
of an investigation that the Department undertakes or is undertaking pursuant
to the authority established in Subsection 8-17.5-102 (5), C.R.S.
G. If Contractor violates any provision of this Agreement pertaining to the duties
imposed by Subsection 8-17.5-102, C.R.S. the City may terminate this
Agreement. If this Agreement is so terminated, Contractor shall be liable for
actual and consequential damages to the City arising out of Contractor's
violation of Subsection 8-17.5-102, C.R.S. ,
H. The City will notify the Office of the Secretary of State if Contractor violates this
provision of this Agreement and the City terminates the Agreement for such
breach.
Standard Professional Services Agreement- rev 09/01/06
City Clerk
F VORTco THE CITY OF FORT COLLINS, COLORADO
C4:Z By:
SE A LN a es B. O'Neill II, CPPO, FNIGP
• DirectoW Purchasin & Risk Management
CORAOp DATE: (o D
Aller-Lingle
�Architects P.C.
Title: V I UG—! �1:5i�c��llst l
CORPORATE PRESIDENT OR VICE PRESIDENT
Date: �Aur d 3�7
ATTE T:
�l
(Corporate Seal)
o porate , re
Standard Professional Services Agreement- rev 09/01/06 7
EXHIBIT A
SCOPE OF WORK
Aller•Lingle Architects P.C. is pleased to provide you with this Proposal for design services for a
southeast branch library at Front Range Village in Fort Collins. In response to our Phase 1 work
and our meetings to date, we propose the following scope of services and associated fees:
Project Description
Phases 2 and 3 Design Development through Construction Administration phase services as
itemized below for a tenant finish of the second floor of a mixed -use building to be part of Front
Range Village in southeast Fort Collins. The scope of the tenant finish work will be approximately
16,000 sq. ft. on the second floor, including a public meeting room, and approximately 1,100 sq. ft.
on the main level for a public entry lobby, main stair, elevator and book return processing area with a
freight elevator. The stair elements and elevators will be designed as part of the core and shell
construction; however, the public restrooms will be considered part of the tenant finish work.
Plumbing, mechanical and electrical work will include complete engineering of these systems,
including selection of primary HVAC equipment. Only minor structural work is anticipated as part of
the tenant finish; structural aspects of the core and shell construction related to the library use will
be provided by Bayer Properties' structural engineer.
The City of Fort Collins has established a LEED goal of "Gold" certification for the project. As
requested, this Proposal includes LEED design consulting, energy modeling and a daylighting study.
It is our understanding that Bayer Properties is also pursuing LEED certification for the overall
development, but the level has not been determined. This will be critical for the library to attain
"Gold" certification.
Aller•Lingle Architects P.C. will be the Architect of Record for the project.
Scope of Basic Services
The Scope of Basic Services shall be as follows:
Phase 1:
Conceptual Design phase was covered by a separate work order.
Phase 2:
1. Design Development Phase: Expand upon and refine the approved conceptual design.
Submit floor plans, furnishings plan, reflected ceiling plan, building section and typical wall
sections, mechanical and electrical plans, and 80% technical specifications for review and
approval.
2. Library Design Consulting: Continued consulting by Studiotrope through 65% Design
Development, plus 100% Construction Documents for interior casework and graphic design
for interior signage systems (or coordination with City -approved signage vendor).
Studiotrope will coordinate with Scott Rice, OfficeScapes or other City -approved vendor for
furnishings and shelving systems specifications, including up to four (4) coordination
meetings.
3. LEED Consulting: Continued consulting by the LEED consultant as a continuation of
Phase 1 services, including up to two (2) meetings plus conference calls.
4. Energy Modeling: Energy modeling in support of LEED certification, including a "base
case" energy model in compliance with applicable ASHRAE 90.1-1999 Energy Standards,
modeling conceptual design solution(s) against the base model, and general consulting with
the design team for conformance with LEED criteria.
Standard Professional Services Agreement- rev 09/01/06
5. Daylighting Study: Daylighting model of conceptual design solution(s) for evaluation of
conformance with LEED criteria.
6. Tenant Finish: Prepare construction drawings and technical specifications for the interior
tenant finish, including architectural, interior architecture, graphics design for interior
signage, furnishings/shelving coordination, minor structural engineering, and complete
mechanical and electrical engineering. Extent of drawings is estimated as follows:
Title Sheet
Main Level Floor Plan of Lobby Core and Exit Stair Enclosure
Upper Level Floor Plan
Main and Upper Level Reflected Ceiling Plans
Wall Sections and Details
Room Finish Schedule
Door and Window Schedules, Door Types and Details
Casework and Interior Elevations
Furnishings Plan
Interior Graphics/Signage Plan
Structural Plan and Details (framing for overhead door, etc.)
Plumbing Plan and Details
HVAC Mechanical Plan and Details
Mechanical Schedules and Details
Fire Protection Plan and Details
Electric Power Plan and Details
Electrical Lighting Plan and Schedules
Electrical Communications/Special Systems Plan and Schedules
Electrical One -Line Diagram
7. Meetings: Meetings with Library and Operations Services staff as necessary for review and
approval of the design submittals. Meetings for Studiotrope are limited to two (2) plus
conference calls for this phase of work.
8. Presentations: Presentations of the design in progress to the new Library District Board
and City Council Study Session.
9. Cost Estimating: Prepare an estimate of probable construction costs at approximately 90%
completion of Construction Documents.
Phase 3:
1. Bidding/Negotiation Phase: Assistance to the Owner to acquire and review Contractor
bids, including attendance at Pre -Bid Conference, responding to Contractor questions and
issuing addenda, and assistance in reviewing bids. Plan distribution will be by the City.
2. Construction Administration Phase: Perform regular field observations of the work in
progress during construction with written reports to the Owner, attendance at Pre -
Construction Conference, attend regular site meetings with the Contractor and Owner's
representative (Consultants on an as -needed basis), review of shop drawings and
submittals, issuance of change orders, review of Contractor's pay requests, final punch list
inspection and assistance with project closeout. We anticipate up to 20 site meetings/field
observations by Aller•Lingle Architects P.C. in this phase of work. For purposes of this
Proposal, field observations by our Consultants are proposed as follows:
a. Studiotrope: 2 site visits.
b. Structural Engineering: None.
C. Mechanical Engineering: 3 site visits.
d. Electrical Engineering: 3 site visits.
3. LEED Consulting: Continued consulting during construction, including coordination with
the selected Contractor and documentation and submittal services forthe LEED certification
process.
Standard Professional Services Agreement- rev 09/01 /06 9