HomeMy WebLinkAboutCHANGE ORDER - REQUISITION - 29585SECTION 00950
CHANGE ORDER NO. 1
PROJECT TITLE: Old Sand/Salt Building Roof
CONTRACTOR: ACC Roofing LLC
DESCRIPTION: The re -roofing of the Old Sand/Salt Building as part of the renovation for conversion to a
VehiGe Parking Garage.
1. Reason for change: Replacement of the very deteriorated 5" fluted downspouts around the entire
building.
2. Description of change: Removal of existing deteriorated downspout and installation of new downspout
3. Change in Contract Cost: $9,534.00
4. Change in Contract Time: 0 Days
ORIGINAL CONTRACT COST $92,400.00
TOTAL APPROVED CHANGE ORDERS 0.00
TOTAL PENDING CHANGE ORDERS 0.00
TOTAL THIS CHANGE ORDER 9,534.00
ADJUSTED CONTRACT COST $101,934.00
ACCEPTED BY:
r__--Contractor's
REVIEWED BY:
Facilities Project
cc: Pdrelra*V
Contractor
Project File
3'1/,')-07
Date
311 o
Date