HomeMy WebLinkAboutCHANGE ORDER - PURCHASE ORDER - 5508213n
CITY OF FORT COLLINS
CHANGE ORDER
CONTRACTOR: HDR Engineering PROJECT TITLE: Downtown RiverDistrict
Project
ADDRESS:
PROJECT NUMBER:
PURCHASE ORDER NO.: 5508213 CHANGE ORDER NUMBER: 1
DESCRIPTION
1. Reason for change: Adding Utilities component to original project.
2. Description of change:
3. Change in Contract Cost: $37,900
4. Change in Contract Time: None
ORIGINAL CONTRACT COSTS $200,000.00
TOTAL APPROVED CHANGE ORDERS 0.00
TOTAL PENDING CHANGE ORDERS 0.00
TOTAL THIS CHANGE ORDER $37,900
TOTAL % OF ORIGINAL CONTRACT, THIS CO:
TOTAL % OF ORIGINAL CONTRACT, ALL CO'S:
ADJUSTED CONTRACT COST
(Assuming all change orders approved)
ACCEPTED BY:
SUBMITTED BY: I t 1 A
APPROVED BY
APPROVED BY:
Title:
$2379900.00
DATE: 77.,b 3� 7
DATE: /- Z 9-6
TE: / -23 v
DATE: L - 2 —0f
DATE: o)-/5-07
Agent if> $30,000)
cc: City Clerk Architect/Engineer
Finance Purchasing
Project Manager Contractor
\eng\forms\coform.d oc
Downtown River District Project
Utility Preliminary Design
Scope of Services
Background and Approach
The Downtown River District (DTRD) project has
developed several alternatives for transportation and
streetscape improvements within the project study area.
Through a series of stakeholder meetings and design
refinements, the project team has identified a preferred
alternative. This preferred alternative will be carried
forward to develop preliminary design drawings for
roadway improvements which will provide a 30% design
detail of roadway widths, curb alignments and vertical
profiles. This Utility Preliminary Design Scope of
Services presents the engineering activities and
deliverables needed to identify improvements to the
storm, water and sanitary utilities within the project area
and develop design drawings for the utility improvement
recommendations to a 30% level of detail.
The City has performed a planning level analysis of the existing storm drain system and has identified a
preferred approach to addressing capacity and stormwater quality issues within the study area.
Generally, the preferred approach is to reconstruct the existing system and alter the system alignment to
be located within the public right-of-way. In addition, water quality flows south of Willow Street will be
directed to the Udall regional stormwater quality facility via a storm drain southeast of Lincoln Avenue. It
is anticipated this preferred approach will serve as the framework for developing and analyzing additional
alternatives. Work performed to date that will be used as a starting point for this analysis includes
subbasin boundaries, hydrologic parameters, EPA-SWMM hydrologic and hydraulic model, mapping and
analysis documentation. HDR will refine the H✓£H analysis, evaluate additional alternatives, identify a
recommended plan and present that plan in the Utility Preliminary Design Drawings.
Conversations with City Water and Sewer staff note that the City will perform any needed engineering
analysis for the relocation and improvements within the water distribution and sewer collection system.
The City will prepare redlines of proposed water and sewer utility improvements based on the
recommended plan for roadway and streetscape improvements. However, HDR will transfer this design
information to the Utility Preliminary Design Drawings to complete the utility improvement
recommendations within the study area.
Task 1. Project Initiation
Objective: Collect existing storm drainage information and review with consideration of preferred
streetscape alternative design components.
1.1 Project Administration and QC
❑ Initiate project accounting, budget and resource management tools.
❑ Update the Project Guide to clearly identify the added work elements, deliverables, budget and
schedule.
❑ Perform and document quality control reviews of calculation and deliverables.
HDR Engineering, Inc. DTRD — Utility Predesign Services Amendment
Page 1
❑ Submit draft report for City review (1-copy, color). Meet with City staff to discuss review comments.
Address comments and submit final memo (1-copy, color and PDF).
Task 3. Utility Coordination
Objectives: Coordinate water and sewer utility improvements with roadway and storm drain
improvements. Coordinate private utility locations with respect to streetscape and roadway features.
3.1 Coordinate Water and Sewer Utility Improvements
❑ Meet with City staff to review proposed roadway and streetscape improvements. Provide hard copy
drawings of proposed plan view features for use in utility relocations and other system improvements.
❑ Meet with City staff to review proposed water and sewer improvements. Review proposed design
information with respect to roadway, streetscape and storm drain improvements. Discuss and
resolve improvement conflicts.
❑ Provide Utility Preliminary Design Drawings for review and comment. Meet to discuss review
comments in order to develop final Utility Preliminary Design Drawing package.
❑ Obtain estimates of capital construction cost for sewer and water improvements from City based on
final Utility Preliminary Design Drawings for incorporation into project cost estimate.
3.2 Coordinate Private Utility Infrastructure
❑ Meet with private utility companies to review infrastructure needs and desired improvements. It is
anticipated three 2-hour meetings will be held with utility company representatives at HDR offices to
assist in developing typical right-of-way sections showing locations of private utilities.
Task 4. Utility Preliminary Design Drawings and Capital Cost
Objective: Develop 30% design documents that define utility improvements to guide development plans
within the study area.
4.1 Prepare Overall Utility Plan Drawings
❑ Incorporate recommended storm drain features and BMP areas into a Utility Plan drawing(s). Show
inlet elevations and leader dimensions in plan view only.
❑ Incorporate water and sewer utility improvement redlines prepared by the City into the Utility Plan
drawing(s).
4.2 Prepare Storm Drain Plan and Profile Drawings
❑ Obtain profile data from the hydraulic model/project GIS. Develop plan and profile drawings for the
trunk lines. Show existing and proposed utility crossings in profile. Based on conceptual plan, 5200-
feet of storm drain plan and profiles are anticipated at a scale of 1"=50'.
4.3 Prepare Water and Sewer Profile Drawings
❑ Incorporate vertical redline information from the City's utility design work into profiles for water and
sanitary sewer improvements. It is assumed four plan and profile drawings at 1" = 50' scale will be
needed to show proposed water and sewer improvements.
4.4 Prepare Project Specific Details
❑ Prepare preliminary storm drain details of diversion manholes and outfall erosion protection.
❑ Prepare typical right-of-way sections showing locations of public and private utilities.
HDR Engineering, Inc. DTRD — Utility Pmdesign Services Amendment
Page 3
1/15/2007
Downtown River District Project
Utility Preliminary Design
Scope of Services
Background and Approach
The Downtown River District (DTRD) project has
developed several alternatives for transportation and
streetscape improvements within the project study area.
Through a series of stakeholder meetings and design
refinements, the project team has identified a preferred
alternative. This preferred alternative will be carried
forward to develop preliminary design drawings for
roadway improvements which will provide a 30% design
detail of roadway widths, curb alignments and vertical
profiles. This Utility Preliminary Design Scope of
Services presents the engineering activities and
deliverables needed to identify improvements to the
storm, water and sanitary utilities within the project area
and develop design drawings for the utility improvement
recommendations to a 30% level of detail.
The City has performed a planning level analysis of the existing storm drain system and has identified a
preferred approach to addressing capacity and stormwater quality issues within the study area.
Generally, the preferred approach is to reconstruct the existing system and alter the system alignment to
be located within the public right-of-way. In addition, water quality flows south of Willow Street will be
directed to the Udall regional stormwater quality facility via a storm drain southeast of Lincoln Avenue. It
is anticipated this preferred approach will serve as the framework for developing and analyzing additional
alternatives. Work performed to date that will be used as a starting point for this analysis includes
subbasin boundaries, hydrologic parameters, EPA-SWMM hydrologic and hydraulic model, mapping and
analysis documentation. HDR will refine the H&H analysis, evaluate additional alternatives, identify a
recommended plan and present that plan in the Utility Preliminary Design Drawings.
Conversations with City Water and Sewer staff note that the City will perform any needed engineering
analysis for the relocation and improvements within the water distribution and sewer collection system.
The City will prepare redlines of proposed water and sewer utility improvements based on the
recommended plan for roadway and streetscape improvements. However, HDR will transfer this design
information to the Utility Preliminary Design Drawings to complete the utility improvement
recommendations within the study area.
Task 1. Project Initiation
Objective: Collect existing storm drainage information and review with consideration of preferred
streetscape alternative design components.
1.1 Project Administration and QC
❑ Initiate project accounting, budget and resource management tools.
❑ Update the Project Guide to clearly identify the added work elements, deliverables, budget and
schedule.
❑ Perform and document quality control reviews of calculation and deliverables.
HDR Engineering, Inc. DTRD - Utility Predesign Services Amendment
Page 1
❑ Submit draft report for City review (I -copy, color). Meet with City staff to discuss review comments.
Address comments and submit final memo (1-copy, color and PDF).
Task 3. Utility Coordination
Objectives: Coordinate water and sewer utility improvements with roadway and storm drain
improvements. Coordinate private utility locations with respect to streetscape and roadway features.
3.1 Coordinate Water and Sewer Utility Improvements
❑ Meet with City staff to review proposed roadway and streetscape improvements. Provide hard copy
drawings of proposed plan view features for use in utility relocations and other system improvements.
❑ Meet with City staff to review proposed water and sewer improvements. Review proposed design
information with respect to roadway, streetscape and storm drain improvements. Discuss and
resolve improvement conflicts.
❑ Provide Utility Preliminary Design Drawings for review and comment. Meet to discuss review
comments in order to develop final Utility Preliminary Design Drawing package.
❑ Obtain estimates of capital construction cost for sewer and water improvements from City based on
final Utility Preliminary Design Drawings for incorporation into project cost estimate.
3.2 Coordinate Private Utility Infrastructure
❑ Meet with private utility companies to review infrastructure needs and desired improvements. It is
anticipated three 2-hour meetings will be held with utility company representatives at HDR offices to
assist in developing typical right-of-way sections showing locations of private utilities.
Task 4. Utility Preliminary Design Drawings and Capital Cost
Objective: Develop 30% design documents that define utility improvements to guide development plans
within the study area.
4.1 Prepare Overall Utility Plan Drawings
❑ Incorporate recommended storm drain features and BMP areas into a Utility Plan drawing(s). Show
inlet elevations and leader dimensions in plan view only.
❑ Incorporate water and sewer utility improvement redlines prepared by the City into the Utility Plan
drawing(s).
4.2 Prepare Storm Drain Plan and Profile Drawings
❑ Obtain profile data from the hydraulic model/project GIS. Develop plan and profile drawings for the
trunk lines. Show existing and proposed utility crossings in profile. Based on conceptual plan, 5200-
feet of storm drain plan and profiles are anticipated at a scale of 1"=50'.
4.3 Prepare Water and Sewer Profile Drawings
❑ Incorporate vertical redline information from the City's utility design work into profiles for water and
sanitary sewer improvements. It is assumed four plan and profile drawings at 1" = 50' scale will be
needed to show proposed water and sewer improvements.
4.4 Prepare Project Specific Details
❑ Prepare preliminary storm drain details of diversion manholes and outfall erosion protection.
❑ Prepare typical right-of-way sections showing locations of public and private utilities.
HDR Engineering, Inc.
DTRD — Utility Predesign Services Amendment
Page 3
1.1 Project Administration and QC
6
4
0
0
4
14
$
1,922
$
134
1.2 Review Hydrologic and Hydraulic Data
1
4
8
01
12
$
1,314
$
102
Sub -total
61
8
8
01
4
26
$
3.236
$
236
2.1 Develop Concept Alternatives
8
24
121
44
$
4,268
$
351
2.2 Refine Preferred Alternative
8
48
41
60
$
6,015
$
487
2.3 Prepare Summary Memorandum
21
4
12
41
22
$
2 349
$
184
Sub -total
21
201
84
201
0
126
$
12,633
1 $ 1,022
3.1 Coordinate Water and Sewer Utilitv Improvements
8
0
01
8
$
1,079
$
76
3.2 Coordinate Private Utility Infrastructure
12
0
01
12
$
1,619
$
114
Sub -total
0
20
0
0
0
20
$
2.699
$
190
4.1 Prepare Overall Utility Plan Drawings
8
24
16
48
$
4,557
$
379
4.2 Prepare Storm Drain Plan and Profile Drawings
4
16
24
44
$
3,819
$
333
4.3 Prepare Water and Sewer Plan and Profile Drawings
4
0
24
28
$
2,270
$
206
4.4 [Prepare Project Specific Details
21
8
8
18
$
1,621
$
139
4.5 1 Prepare Estimates of Capital Construction Cost
41
12
0
16
$
1,702
$
134
4.6 Submit Utility Predesi n Package
41
81
161
28
$
2,468
$
214
Sub-totall
01
261
681
881
81
1 R21
$
16,437 I
$ 1,404
1 /15/2007
A
CITY OF FORT COLLINS
CHANGE ORDER
CONTRACTOR:
ADDRESS:
HDR Engineering PROJECT TITLE:
Project
PROJECT NUMBER:
Downtown River District
PURCHASE ORDER NO.: 5508213 CHANGE ORDER NUMBER: 1
DESCRIPTION
1. Reason for change: Adding Utilities component to original project.
2. Description of change:
3. Change in Contract Cost: $37,900
4. Change in Contract Time: None
ORIGINAL CONTRACT COSTS $200,000.00
TOTAL APPROVED CHANGE ORDERS 0.00
TOTAL PENDING CHANGE ORDERS 0.00
TOTAL THIS CHANGE ORDER $37,900
TOTAL % OF ORIGINAL CONTRACT, THIS CO:
TOTAL % OF ORIGINAL CONTRACT, ALL CO'S:
ADJUSTED CONTRACT COST
(Assuming all change orders approved)
ACCEPTED BY:
SUBMITTED BY:
REVIEWED BY:
APPROVED BY
0g7Z91T/0-93O-r i
$237,900.00
*******************************************
Agent if> $30,000)
cc: City Clerk Architect/Engineer
Finance Purchasing
Project Manager Contractor
henglforms\coform.doc
DATE: L- Z 5-0 7
TE: ! -2-3 —v
DATE:
DATE: c� - /6-0'7
Downtown River District Project
Utility Preliminary Design
Scope of Services
Background and Approach
The Downtown River District (DTRD) project has
developed several alternatives for transportation and
streetscape improvements within the project study area.
Through a series of stakeholder meetings and design
refinements, the project team has identified a preferred
alternative. This preferred alternative will be carried
forward to develop preliminary design drawings for
roadway improvements which will provide a 30% design
detail of roadway widths, curb alignments and vertical
profiles. This Utility Preliminary Design Scope of
Services presents the engineering activities and
deliverables needed to identify improvements to the
storm, water and sanitary utilities within the project area
and develop design drawings for the utility improvement
recommendations to a 30% level of detail.
t Poortr
g,
N
Study Area .
E MoureaYr Ave
The City has performed a planning level analysis of the existing storm drain system and has identified a
preferred approach to addressing capacity and stormwater quality issues within the study area.
Generally, the preferred approach is to reconstruct the existing system and alter the system alignment to
be located within the public right-of-way. In addition, water quality flows south of Willow Street will be
directed to the Udall regional stormwater quality facility via a storm drain southeast of Lincoln Avenue. It
is anticipated this preferred approach will serve as the framework for developing and analyzing additional
alternatives. Work performed to date that will be used as a starting point for this analysis includes
subbasin boundaries, hydrologic parameters, EPA-SWMM hydrologic and hydraulic model, mapping and
analysis documentation. HDR will refine the H&H analysis, evaluate additional alternatives, identify a
recommended plan and present that plan in the Utility Preliminary Design Drawings.
Conversations with City Water and Sewer staff note that the City will perform any needed engineering
analysis for the relocation and improvements within the water distribution and sewer collection system.
The City will prepare redlines of proposed water and sewer utility improvements based on the
recommended plan for roadway and streetscape improvements. However, HDR will transfer this design
information to the Utility Preliminary Design Drawings to complete the utility improvement
recommendations within the study area.
Task 1. Project Initiation
Objective: Collect existing storm drainage information and review with consideration of preferred
streetscape alternative design components.
1.1 Project Administration and QC
❑ Initiate project accounting, budget and resource management tools.
❑ Update the Project Guide to clearly identify the added work elements, deliverables, budget and
schedule.
❑ Perform and document quality control reviews of calculation and deliverables.
HDR Engineering, Inc. DTRD — Utility Predesign Services Amendment
Page 1
❑ Submit draft report for City review (1-copy, color). Meet with City staff to discuss review comments.
Address comments and submit final memo (1-copy, color and PDF).
Task 3. Utility Coordination
Objectives: Coordinate water and sewer utility improvements with roadway and storm drain
improvements. Coordinate private utility locations with respect to streetscape and roadway features.
3.1 Coordinate Water and Sewer Utility Improvements
❑ Meet with City staff to review proposed roadway and streetscape improvements. Provide hard copy
drawings of proposed plan view features for use in utility relocations and other system improvements.
❑ Meet with City staff to review proposed water and sewer improvements. Review proposed design
information with respect to roadway, streetscape and storm drain improvements. Discuss and
resolve improvement conflicts.
❑ Provide Utility Preliminary Design Drawings for review and comment. Meet to discuss review
comments in order to develop final Utility Preliminary Design Drawing package.
❑ Obtain estimates of capital construction cost for sewer and water improvements from City based on
final Utility Preliminary Design Drawings for incorporation into project cost estimate.
3.2 Coordinate Private Utility Infrastructure
❑ Meet with private utility companies to review infrastructure needs and desired improvements. It is
anticipated three 2-hour meetings will be held with utility company representatives at HDR offices to
assist in developing typical right-of-way sections showing locations of private utilities.
Task 4. Utility Preliminary Design Drawings and Capital Cost
Objective: Develop 30% design documents that define utility improvements to guide development plans
within the study area.
4.1 Prepare Overall Utility Plan Drawings
❑ Incorporate recommended storm drain features and BMP areas into a Utility Plan drawing(s). Show
inlet elevations and leader dimensions in plan view only.
❑ Incorporate water and sewer utility improvement redlines prepared by the City into the Utility Plan
drawing(s).
4.2 Prepare Storm Drain Plan and Profile Drawings
❑ Obtain profile data from the hydraulic model/project GIS. Develop plan and profile drawings for the
trunk lines. Show existing and proposed utility crossings in profile. Based on conceptual plan, 5200-
feet of stone drain plan and profiles are anticipated at a scale of 1 "=50'.
4.3 Prepare Water and Sewer Profile Drawings
❑ Incorporate vertical redline information from the City's utility design work into profiles for water and
sanitary sewer improvements. It is assumed four plan and profile drawings at 1" = 50' scale will be
needed to show proposed water and sewer improvements.
4.4 Prepare Project Specific Details
❑ Prepare preliminary storm drain details of diversion manholes and outfall erosion protection.
❑ Prepare typical right-of-way sections showing locations of public and private utilities.
HDR Engineering, Inc. DTRD — Utility Predesign Services Amendment
Page 3
1/15/2007
CITY OF FORT COLLINS
CHANGE ORDER
• CONTRACTOR: HDR Engineering PROJECT TITLE: DowntownRiverDistrict
Project
PROJECT NUMBER:
PURCHASE ORDER NO.: 5508213 CHANGE ORDER NUMBER: 1
DESCRIPTION
1. Reason for change: Adding Utilities component to original project.
2. Description of change:
3. Change in Contract Cost: $37,900
4. Change in Contract Time: None
ORIGINAL CONTRACT COSTS $200,000.00
TOTAL APPROVED CHANGE ORDERS 0.00
TOTAL PENDING CHANGE ORDERS 0.00
TOTAL THIS CHANGE ORDER $37,900
TOTAL % OF ORIGINAL CONTRACT, THIS CO:
TOTAL % OF ORIGINAL CONTRACT, ALL CO'S:
ADJUSTED CONTRACT COST
(Assuming all change orders approved)
ACCEPTED BY:
SUBMITTED BY:
REVIEWED BY:
APPROVED BY:
APPROVED BY:
$237,900.00
Agent if> $30,000)
cc: City Clerk Architect/Engineer
Finance Purchasing
Project Manager Contractor
1 Aenglform s\coform.d oc
DATE:_-O, f
DATE:_ l- Z 9--0 7
TE: / -2-3 --0
DATE: L- 7-�01
DATE: c, - /S-0%