HomeMy WebLinkAboutCORRESPONDENCE - RFP - P872 PFA GENERAL CONTRACTOR FOR FIRE STATION (2)August 15, 2005
John Stephen, CPPO, Senior Buyer
City of Fort Collins
Re: Station 5 Addition and Remodel
Dear John:
The following is the final proposal for the Station 5 Addition and Remodel
project. This proposal includes all materials,
labor, quipment, tools and supplies as
required and necessary to completely execute the work as provided in the contract
documents as issued by Vaught*Frye Architects, Bid/Permit set dated July 22, 2005.
The base bid pricing does include the door
#113
alternate.
This proposal is a base bid to be contracted as a total, however we are providing
the following breakdown of costs for your
information:
Surveying & Layout
$
5,260
Traffic & Pedestrian Control
$
1,026
Erosion Control
$
2,656
Demolition
$
27,134
Earthwork & Utilities
$
35,767
Asphalt Paving & Striping
$
23,263
Misc. Site Improvements
$
3,961
Landscape & Irrigation
$
16,325
Concrete - Building & Site
$
48,127
Masonry
$
27,700
Steel, Metals
'$
34,700
Carpentry
$
27,031
Interior Finish Carpentry
$
1,760
Dammproofing, Insulation
$
5,865
Stucco
$
3,300
Roofing & Sheet Metal
$
17,590
Caulking
$
3,062
Doors & Hardware
$
5,409
Overhead Sectional Doors
$
18,631
Aluminum Windows & Storefront
$
9,500
Vinyl Windows
$
1,700
Drywall & Metal Framing
$
9,351
Flooring
$
8,838
Acoustical Ceilings
$
2,381
Painting
$
6,830
FRP
$
1,800
Toilet Accessories
$
242
Casework & Countertops
$
690
(see continuation)
THE TEAM OF BUILDING PROFESSIONALS
General Contractors 0 Construction Management • Commercial & Industrial
4557 Denrose Court 4 P.O. Box 1969 0 Fort Collins, CO 80522 * (970) 493-1770 4 Fax (970) 482- 4537
( asGIN
VLRIFY Di
NOTE, rT &, EXIST, TREE L[R
U, ITY LASEftNr_FAAK10J& wagg
MOTE, C.C. SHALL FIELD
i 1 VERIFY ALL. LMAT134S 9F
r EXISTING U G. UTITILTIES
NW, 90. Il
T. TRtE
FI O
E CAN
D)
104S ---i
— iTE; REPLACE/REPA-IR SQ) D
IRRIGAIZON SYSTEM DISTURBED E�
PERM OF NEW PARKING AREA
ADDITONS
4i
P
Y
f CY
L..Bg
El
EXIST, aENERATOR
t�
€XI$T. LILC, GEAq
r �^
Z, kEy,a'T YPEE T.J a CHAIN
4
s
lV3 lofA
REMOVE ALL TMT, TRIES & LANSG'AF';;'G 14I114Y HEw
St'E1cH A
TO
RZKIvED 3 EXISt j iT.�"
ASPHALT PAVED E„ y."
{ � r PAVING-
19
..
I'
E � y
F
( P
ASP"PAL` ~CURS
I aFALVAGED &
.tsJ LOU 'r'"fi'�f 4JMir n-.•ERFSi, MASiI"Y S'.4.L
1r B tkp e
5 m"C',T..«ARSN114 �.�i9Y4'dH�r+�3Y��.x
� � e AkL u. " jai .ter - NER
DISCHARW uG, BRAIN i NC
✓t CX.C. 7 LflrE
TRC�C�
RE S+AVER_l
._! t .1. i "° ;q "•^ya n ,,y ExiST. PL+NTI #E.. ' . hF......
cr!n"5 ,rig. I �, A
f;: r xv",t+%7o-`,;"'L. E'zE .""a.0 & II 5= •-=�._..�; ! s $ "EN t"k" 'dF"K. j
,._ I hATICA SYSTEM ,� �,-' . 7 itP a
`IM1 .a NEW PAR
ITY iC3PE''Ts ,f C aFvn^i3 `r p"`Ei`, .VE S#rnia'PS '�` EiH INC ' EFoi3F. e4SF�t E.
'�• k EF 6C£ COW CCRB
a
1"IST E€r,=,Tsv
cr FEW
7 CNISY FL.nCaPCLE
Y
f v
I
i
y,"" ; ..
f iT
F'. mm
August 8, 2005
Vaught Frye Architects
401 West Mountain Avenue
Fort Collins, Colorado 80521
Attention: Mr. Gary Dennison
Subject: Exploratory Pit Observation
Fire Station #5
Fort Collins, Colorado
Project No. F003533-145
CTI_ ) Thompson was requested to observe the soils in an exploratory pit
to better determine the depth of fill present below proposed additions to the
fire station. Our Mr. John Boulden visited the site on August 3, 2005 to
observe conditions in the pit. The pit had been excavated to a depth of 9 feet
In the parking lot at the front of the living area of the existing fire station. The
pit was located about 30 feet west of boring TH-1. The following soils were
observed In the test pit: 6 inches of asphaltic concrete and 4 inches of
aggregate base coarse material over 1 to 1.5 feet of dark sandy clay fill over 6
feet of sandy clays with layers of silty to clean sands (less than 3 inches thick)
underlain by weathered claystone in the bottom of the excavation.
In our report (FC03533-125 dated July 7,2005) we suggested three
options for the building floor slab subgrade. Those options included placing
the slab on the fill, removing 2 feet of the existing fill to be replaced as
engineered fill, and complete removal and replacement of all existing fill. Our
boring (TH-1), with the greatest depth of unknown fill, was located in the
vicinity of a water line. It Is likely that the unknown fill in this boring is trench
backfill. Our other boring (TH-2) and the exploratory pit indicate 1 to 3 feet of
unknown fill. Based upon this new information and our observation that the
existing pavements are performing well in the area of the proposed addition,
we believe floor slab movement on the existing fill will be more tolerable.
Considering economy and performance, the slab may be placed on
grade in accordance with the first option in our report. At a minimum, the
subgrade should be scarified, moisture treated, and recompacted after
clearing and removal of existing pavements. Areas that will be subject to
truck traffic and parking within the building should at a minimum be prepared
and constructed using a pavement and base coarse section at least as thick
as currently exists at the site. We can provide a pavement design if desired
upon request.
The above recommendations are based upon our understanding of the
soils existing at the site and the proposed construction. Variations in the
subsurface conditions not indicated by our borings and the exploratory pit are
possible. This work was prepared to the standard of care exercised by other
engineers practicing in the area at this time. No warranty is expressed or
implied. if we can be of further assistance please do not hesitate to contact
US.
Very truly yours,
CTL I THOMPSOM INC
John J Bouiden, EIT
Staff Engineer
Reviewed By:
Howard Perko, Ph.D, PE
Division Manager
JJB:HAP:bly
VAUGHT FRYE ARCHITECTS 2
FIRE STATION #5
FORT COLLINS, COLORADO
GTL I T PROJECT NO. FC03653.146
Blinds & Shades
$
1,210
Fire Protection
$
20,995
Plumbing
$
17,074
HVAC
$
18,540
Electrical
$
67,750
General Conditions
$
68,750
Weather Protection/Temp. Heat
$
3,098
Builder's Risk Insurance
$
512
State Sales Tax
Exempt
Permits & Fees
BY OWNER
Bonds - Labor, Mat. & Performance
$
8,217
SBI Fee - Per Contract
$
22,242
BASE BID TOTAL
$
578,287
The following are the costs to add the fire protection system alternate to sprinkler the
remainder of the building. This alternate pricing does not include any costs for structural
improvements to support the system.
Drywall Repair $ 450
Painting $ 1,815
Fire Protection $ 13,400
Bonds, Insurance $ 314
SBI Fee, per contract $ 640
ALTERNATE $ 16,619 add to base bid
The following is the alternate pricing to delete the FRP in the Captain's Garage and
replace with the Fiberon Wall System
Delete FRP <$ 1,800>
Add Fiberon $ 8,252
Bond, Insurance $ 129
SBI Fee, per contract $ 264
TOTAL $ 6,845 add to base bid
Schedule:
This project is intended to start with SBI mobilizing to site to begin work Monday,
August 29, substantial completion on or about February 17th, 2006 and final completion
(including punchlist, etc.) by March 3, 2006.
Please review and advise of any question or comments.
Sincerely,
S' ett P
ers, Inc.
nett
Vice President, Project Manager
john@sinnettbuilders.com
cc: file, Scott Steel
THE TEAM OF BUILDING PROFESSIONALS
General Contractors 0 Construction Management 0 Commercial & Industrial
4557 Denrose Court • P.O. Box 1969 • Fort Collins, CO 80522 • (970) 493-1770 • Fax (970) 482- 4537
FIRE STATION #5 ADDITION
ADDENDUM I
August 9, 2005
1. Existing overhead doors on the Apparatus Bay are to be removed, salvaged &
delivered to the Owner at 3400 Vine Drive, Ft. Collins.
2. Re: Civil drawing C-4 Grading & Utility Plan. New water service is shown
coming into the SW corner of the Apparatus Bay Addition. This is incorrect. It is
to come into the SW corner of the Office/Bedroom Addition. The sprinkler valve
is located in the SW corner of the Garage in the Office/Bedroom Addition. See
attached sketch 1 of 1 Revised Water And Fire Lines
3. Re: Al.1 Room Finish Schedule: North and South walls of the Apparatus Bay are
noted to be painted. This refers only to the new (addition) portion of the
apparatus bay walls. The existing Apparatus Bay walls do not need to be re-
painted.
4. Re: Al.1 Alternates: Eliminate Alternate #3 (concrete filled steel piles). On -site
investigation of soil conditions has revealed that the spread footings, as shown on
the Structural drawings, are acceptable. See attached letter dated August 8, 2005
from CTL Thompson re Exploratory Pit Excavation (FC03533-145).
5. Overecavation & Fill below slabs on grade: Re: Systems Notes Floor Slabs F1 &
172: Remove the requirement to "scarify & recompact 18" below slab or below
vapor barrier." Replace with "Remove existing man -placed fill below slabs and
replace with compacted structural fill as directed by Soils Engineer".
For bidding purposes, assume that the depth of the man -placed fill and therefore
the required excavation and structural fill is 12" below the bottom surface of each
slab. (Note that slab F1 is 4" thick and F2 is 6" thick.) Provide unit costs for
additional excavation and structural fill beyond that depth. See attached letter
dated August 8, 2005 from CTL Thompson re Exploratory Pit Excavation
(FC03533-145).
6. Re: Re: Systems Notes Exterior CMU walls W2 & W2A: Add the following:
Fill all ungrouted cells with pourable masonry insulation (Perlite or approved
substitution).
7. Re: Sht. A7.2 detail 6 PVC Window Head Detail and detail 2 Exterior
Door/Window W/ Aluminum Frame in Stud Wall (Head). The soldier course and
projected rowlock courses shown above the window and door frames is incorrect.
Brick above the doors and windows will be flush running bond as shown on the
Elevations Sht. A2.1.
8. Add Sht. A01. Fire Separation/Sprinkler Scope Plan with plans 1: Base Bid —
Building Partially Sprinklered - Fire Separation/Sprinkler Scope Plan and 2:
Alternate #2 — Building Fully Sprinklered - Fire Separation/Sprinkler Scope Plan.
See attached drawings.
Note that the scope of new fire sprinkler coverage under the Base Bid includes all
of the Office/Bedroom Addition and extends into the eastern portion of existing
building where new ceilings are being installed as part of the addition. Note that
this extent of coverage is shown incorrectly on the Fire Suppression Plan on sht.
FP1 of the Mechanical/Plumbing Drawings, because it does not indicate this area
to be sprinklered as part of the Base Bid. $
Note that under the Base Bid a 1 hr. rated wall, door and frame are added to
separate the existing west wing from the rest of the building and thereby separate
the building into Fire Containment Areas that are less than 5,000 s.f. See
Addendum item 9 below.
9. Re: attached 1/Al.1 Partial Floor Plan & A7.1 Revised Door Schedule. Add new
1 hr. rated wall and Door & Frame 113 to separate the existing west wing from
the rest of the building. Note that this wall, door & frame are only required -under
the Base Bid, and are not to be included under Alternate #2 (Fully Sprinklered
Building).
10. Re: Attached A7.1 Revised Door Schedule. Add door type 5 (1 hr. rated flush
door w/ narrow clear wire glass light). Change door 107 to type 5.
11. The project will be constructed in two phases under two separate permits:
Phase 1: Apparatus Bay Addition and all Sitework
Phase 2: Office/Bedroom Addition
12. See sketches A and B attached with this addendum to clarify trees that are to be
removed, and new trees added to the landscape plan.
13. See sketch B for location of drain line, this includes heat tape by electrical
contractor. Landscape contractor to include irrigation and landscape repair for the
installation of this new line to the existing irrigation ditch on the north end of the
property.
14. The overhead doors are to be similar to the units existing. Pricing should also
include the stop/go light system when door are clear for trucks to leave. Provide a
specification / literature on the OH door unit you are proposing. Units at minimal
are insulated with light kits, and all are obviously electrically operated.
15. The asphalt paving section for the new parking lot is as follows: drive section is
(1) lift of grade S at 2" thick over (2) lifts grade SG at 3" thick each lift - total full
depth of the section is 8". The parking areas are to be (1) lift of grade S at 2"
thick over (1) lift of grade SG at 4" thick - total full depth of the section is 6".
This is similar to the paving section from Station 14.
16. Acoustical ceiling tiles are to be matched (if possible or as similar as possible) to
existing.
17. The fire sprinkler system must include dry or glycol anti -freeze systems in the
attics. The existing roof structure for the apparatus bay (base bid) and remaining
existing building (alternate) may not be able to support the additional weight of
the sprinkler piping system. Contractors are to bid running these lines on the
walls exposed, with side spray heads, or your best method to get the coverage not
being able to hang from the roof / ceiling structure.
18. For bidding purposes, painting contractors shall figure 470 feet of sprinkler pipe
to paint under the base bid (new living quarters area will be above ceiling) and
550 feet for the alternate, sizes vary between 1" and 3" in diameter.
No Text
No Text
17. 1 Partial Floor Plan
TOILETS
LAUNDRY
HALL
5HOWERS
NOTE: TNIS NEW I W RATEDFRAME ARE
11 T""ER5
BASE BID. ELIMINATE UNDE TOILETS
ALIERJATE 4 (WELT
EXIST. CM! W4
L- INR RATED OCCUPANCY:
MEGH/ELEG. R9 1 WALL.
EXIST. 3/4 MR RATED NM ow
EXIST. I NR CM OCG. SEP."
A7.1 Revised Door Schedule
DOOR SCHEDULE
DOOR
DOOR
mum
PM
Dumb
M
DOOR 0 1 w X N X T 1
WAT6ML
PAWN
TYPE
MATERIAL
P9l11
TYPE
RAT60
HEAD
w M
EEL
R@kVjm
101
12'-0' X 14'-0'
Sim
PREEN
4
-
-
-
4/A7.2 SIM
4/A7.2
NA
POWER OPERATED SECIIONAL OVERHEAD DOOOR
102
Ir-0' X ic_w
Sim
PREEN
4
_
_
_
/A7.2 SM
4/A1.2
NA
POWER OPERATED SECMONAL OVERHEAD OOOOR
103
Ir-0' X 14'-0'
Sim
PROM
4
-
-
-
/A7.2 ON
4/A1.2
NA
POWER OPERATED SECRONAL OVERHEAD DOOOR
104
3'-0' % r-O' X 1 3/4'
NN
PANT
2
HM
PAINT
HM2
/A1.2 SM
3/A73
TH
PAW HARDWARE
105
3'-0' X 7'-0' X 1 3/4'
ALIM
PREM
3
ALMA
PREM
Al
A7.2
2/0.2
TN
PANIC HARDWARE
106
10'-0' X E-o'
STEEL
PREEN
-
-
-
/A7.2 SIM
5/A7.2
MA
POWER OPERATED SE07IONAL OV064M DOOOR
107
3'-O' % 7'-O' X 1 3/4'
HM
PANT
5
HI (CALV.
PAINT
HMI
60 MN
/A7.2 SM
6/A1.2
-
FIRE RATED DOOR ! FRAME. CLOSER. NOTE WALL THICKNESS 9/16' RIOER UNDER ALWINAVE PI THAN LNOER BASE M.
106
3'-0' X 7--0' X 1 3/4'
WD
SaC
1
HIM
PAINT
NMI
1/A7.2 SM
1/A1.2
-
109
PR- S-0' X r-0' X 1 3/4'
WD
SAC
1
w
PANT
HMI
1/A7.2 SM
1/A7.2
-
110
3-0' % r-D' X 1 3/4'
WD
SAC
1
HM
PAINT
NMI
1/A1.2 SM
1/A1.2
-
III
Y-O' X 7'-D' X 1 3/4-
WD
SAC
1
HM
PANT
NMI
1/A1.2 SM
1/A7.2
-
11
SM7
1
HM
PAINT
/A1.2 SM
1/A7.2
-
113
S-O' X 7'-0' X 1 3/4'
WD
S6C
6
HM
PLAIT
MI
60 MN
1/0.2 SIM
1/A7.2
FIRE RATED DOOR ! FRAME M 050 NOTE TM DOOR ONLY RE" UNDER BABE M. ELIMINATE tMER ALTERNATE PL
41YL—.Y11'WKR
ABBF;�VIATi0N6
PI■#I—
FI■+rWP�
Wt IYAlAW Y■fAL WIC
— RAN CllIR 114R11
4^V.—OALVAe
N
AVAWM7 TMRTMR0.D
NO
90.ID MINE WQ I Q WOMEN
DOOR TYPES
VINYL WINDOW TYPES
1■fSMD n1R
r NKX_4LAPR
L
-L&L
wwrwL
K
DT.Hc
WI
w■oEWNxW
HIGHS
vRn'L NMI■ fJM■6 WIE011
1Waw■ ae.Plvo WWH66Hnn
6yM101)
aua■nRH WMHPNO TXPR!
§
1D!■HD
R
ML
f �6�RY1�i9DT
YAe
w
IRHWCRLRIWMmANDOM
M�
DO
M TYPE 1 V40M TYPE 2
M M 3
DOOR TYPE B
W l be=91i1 �M
RHawc
M.LWmW
ID
na■Hr AMR1N EIpM
Aue■4R4 DOow
M HALFLever W' a 1!■■gg, CM AZM
W MARROW LXMR
M HWL PA11110
0P1HeA
O, m;
Tcr AAL m NKIN O
PINMV
PAFK WIRpO AMOPMO
DOOR TYPE 4
IM AW SM MIMWMY.
OANGIMU w Kw Mr
r1W1MIs�
GF■wat"ReWe■aaLTKcm
N1IRL
HAU L
EXISTING
THIS
WATER
AREA
METER
)GATE
`� - ADDITION
POLE
AND
'ING —
WALK
HAUL
AND —
,RETE
Project:
PFA:
02/05
Scale:
1"-20'
Designed By:
a
PROPOSED 12x6 TAPPING TEE
W/ TB, 6" GATE VALVE
W _ W
5020- ,
FO F0,
REMOVE EXIST. CURB,
GUTTER AND WALK
UP TO EDGE OF RAMP.
W W
02 a NEW CURB, GUTTER
J AND 6.5' WALK
° REMOVE EXISTING
ASPHALT CURB
--,,_-,_..,;,,PROPOSED ._104 LF OF
i COPPER WATER SERVICE
60LF' OF
6" PVC FIRELI�E
90' BEND
W/ TB
10 'LF OF
6" PVC
FIRELINE
r
20 0 20 40 60 Feet
( IN FEET )
1 inch = 20 ft.
POUDRE FIRE AUTHORITY
STATION NO. 5
REVISED WATER
AND FIRE LINES
J
G of
CIVIL ENGINEERS4L*1;;o
1435 West 29th Street. Lovebnd, Colomdo, 60536
Phone: (970)461-2661, Fas: (970)461-2665
www.dmweivilengineem.com
1
Sheet
1
Sheete