HomeMy WebLinkAboutBID - 6006 STEWART CASE PARK IMPROVEMENTS (50)City of Fort Collins Section 02870 – Site Furnishings
Park Planning & Development Division Page 1 of 3
DIVISION 2
SECTION 02870 - MISCELLANEOUS SITE FURNISHINGS
PART 1: GENERAL
Section Includes
A. Bike Rack
B. Site Benches
C. Basketball Equipment
D. Playground Safety Surfacing (Engineered Wood Fiber)
Submittals for Review
A. Submittals shall be directed to the Owners Representative and shall be approved in writing before
affected work commences.
B. Submit shop drawings and technical literature from manufacturer for all items specified in Section
1.01 above.
C. Submit all color swatches on finish metal colors for each of the above site furnishings at the same
time.
D. Submit warranty information at time of review.
Substitutions
A. Alternative bid proposals, which propose material substitutions, must be fully supported by
necessary documentation showing compatibility/comparability with specific materials.
Substitutions must be submitted to the Owners Representative prior to the bid opening.
Substitutions must also comply with the General Conditions. Some Materials may not be
substituted.
1.04 Warranty
E. Warranty all products under this section for a period of two years from the date of Substantial
Completion. In addition to the manufacturer’s product Warranty, Contractor shall warranty the
installation of all products in this section exclusive of normal wear and tear and damage caused
out of the Control of the Contractor. This Warranty shall extend to removal and replacement of
any defective materials or damaged products arising out of the failure of the product of improper
installation of the Contractor.
PART 2: MATERIALS
2.01 Bike Rack
One (1) Namesake Bike Rack.
Bicycle Capacity: 2-4
Mounting: Flanged Surface Mount.
Finish: Polyester Powder Coated.
Color: (To Be Determined). Submit Color Samples
Allow 8-10 weeks for delivery
Factory Representative: Creative Pipe, Inc., PO Box 2458, Rancho Mirage, California 92270-1087.
Toll Free (800) 644-8467. Web Site www.creativepipe.com.
City of Fort Collins Section 02870 – Site Furnishings
Park Planning & Development Division Page 2 of 3
2.02 Site Benches
One (1) Pullenium 3 Seat Modular with Back Curved, Surface Mount – Model #PL2MCU3
Four (4) Pullenium 3 Seat Modular Flat Curved, Surface Mount – Model #PL1MCU3
Color: (To Be Determined) Submit Color Sample.
Allow 10-12 weeks for delivery
Factory Representative: Keystone Ridge Designs, Inc. P.O. Box 2008, 670 Mercer Road, Butler,
Pennsylvania 16003-2008, 1-800-284-8208. Website www.keystoneridgedesigns.com
2.03 Bench Swing
One (1) WEBCOAT Inc., Visions Innovative Products; Model #B6WBCLASSSWING; 6 Ft. Bench
Swing with Contoured Back and Arms, In-ground Mount.
Finish: Black Powder Coat Metal, Webcoating
Color: (To Be Determined) Submit Color Sample.
Allow 8-12 weeks for delivery
Factory Representative: Ermold Park and Recreation Products, Eastlake, CO 1-877-880-5382.
Website www.ermoldpark.com
2.04 Picnic Tables
Two (2) WEBCOAT Inc., Visions Innovative Products; Model #T8RCHDCPALT; 8 Ft. Mesh Table, 2
Attached 6 Ft. Seats Centered, ¾’#9 Expanded Metal, 2 3/8” Legs, Portable.
Finish: Black Powder Coat Metal, Webcoating
Color: (To Be Determined) Submit Color Sample.
Allow 8-12 weeks for delivery
Factory Representative: Ermold Park and Recreation Products, Eastlake, CO 1-877-880-5382.
Website www.ermoldpark.com
2.05 Basketball Equipment
One Pair Gared Sports; Model #GNB45 4 ½” O.D. Gooseneck Post and Brace w/ 4’ Extension
One Pair Gared Sports; Model #1850B Premium Fan Aluminum Backboard w/ White Finish Target &
Border
One Pair Gared Sports; Model # 7550 Titan Playground Super Goal w/ Nylon Net
Factory Representative: Ermold Park and Recreation Products, Eastlake, CO 1-877-880-5382.
Website www.ermoldpark.com
2.06 Playground Safety Surfacing (Engineered Wood Fiber)
2.07 Miscellaneous Hardware
A. Hardware: All hardware including nuts, bolts, and washers, shall be cadmium plated, and shall
conform to ASTM A307.
B. Expansion Bolts: Expansion bolts and anchors shall be galvanized. Where expansion bolts are to
fasten to concrete, they shall be Hilti KWIK BOLT or approved equal.
D. Where expansion bolts are used to fasten to concrete block or other masonry construction, they
shall be RAWL3" anchors or approved equal.
City of Fort Collins Section 02870 – Site Furnishings
Park Planning & Development Division Page 3 of 3
E. Anchor picnic tables with a Pool Cup Anchor, Model #58290; 3” round CPB cup anchor with
cross bar; Spectrum Aquatic Catalog 1-800-776-5309 or local pool supply company.
PART 3: EXECUTION
3.01 Bike Rack
A. Install bike racks per manufacturer’s recommendations.
B. Set racks plumb with grade, as shown on plans, and parallel and perpendicular to building walls
and/or walks.
C. Provide all concrete footings and hardware necessary for installation per plans and manufacturer’s
recommendations.
D. Prior to completion of project, clean bike racks, as needed, to remove dust and dirt. Provide a
clean factory finish at time of final review. Touch up paint as needed.
3.02 Site Furniture
A. Locate picnic tables, benches on site for review by Engineer prior to installation. See plan for
dimensional locations.
B. Anchor picnic table and benches per plans and manufacturer’s recommendations.
C. Provide all concrete footings and hardware necessary for installation per plans and manufacturer’s
recommendations.
D. Prior to completion of project, clean all furniture, as needed, to remove any dust and dirt, and
provide a clean factory finish at time of final review. Touch up paint as needed.
3.03 Basketball Pole, Backboard, Ring and Net
A. Assemble and install Pole, backboard and ring as per drawings and manufacturer’s specifications.
3.04 Protection
A. Protect all painted surfaces from cracking or chipping during installation. Use blankets, tarps etc.,
to protect paint surfaces while handling.
B. Do not accept materials damaged during shipping. Damaged parts shall not be accepted. If minor
repairs are required, it shall be at the discretion of the Owners Representative whether the items
are acceptable.
C. Verify proper operation of all equipment prior to acceptance. Contractor shall be responsible for
proper operation of all materials.
END OF SECTION