HomeMy WebLinkAboutBID - 6006 STEWART CASE PARK IMPROVEMENTS (10)Bid Estimated Item Description Quantity Unit Unit Price Total 1 Mobilization 1 lump sum $ 2,000.00 $ 2,000.00 2 Surveying 1 lump sum $ 1,500.00 $ 1,500.00 3 Removal of 4 & 5-Inch Concrete 3,340 sf $ 1.00 $ 3,340.00 4 Removal of Planter Beds 142 sf $ 1.00 $ 142.00 5 Removal of Playground Header & Wall 76 lf $ 1.50 $ 114.00 6 Erosion Control 100 lf $ 5.00 $ 500.00 7 Concrete 6 Inch Flatwork 7,450 sf $ 3.50 $ 26,075.00 8 1,480 sf $ 4.50 $ 6,660.00 9 Concrete Basketball Court 5040 sf $ 4.00 $ 20,160.00 10 Basketball Court Striping 1 lump sum $ 500.00 $ 500.00 11 Exposed Aggregate Wall 15 lf $ 30.00 $ 450.00 12 Exposed Aggregate Playground Header 70 lf $ 25.00 $ 1,750.00 13 Engineered Wood Safety Surfacing 15 cy $ 10.00 $ 150.00 14 Prefabricated Picnic Shelter 1 lump sum $ 30,000.00 $ 30,000.00 15 Bench - Non-Backed 5 ea $ 890.00 $ 4,450.00 16 Bench - Backed 1 ea $ 1,060.00 $ 1,060.00 17 Bench - 6 Foot Swing 1 ea $ 800.00 $ 800.00 18 Picnic Table 2 ea $ 750.00 $ 1,500.00 19 Bicycle Rack 1 ea $ 800.00 $ 800.00 20 Basketball Equipment 1 lump sum $ 4,000.00 $ 4,000.00 21 Relocation of Drinking Fountain 1 lump sum $ 1,000.00 $ 1,000.00 22 Repainting Shelter 1 lump sum $ 1,500.00 $ 1,500.00 Project: STEWART CASE PARK - SITE IMPROVEMENTS BID SCHEDULE GENERAL REQUIREMENTS DEMOLITION EARTHWORK SIDEWALKS AND COURT Concrete 6 Inch Exposed Aggregate Flatwork PLAYGROUND AREAS SITE FURNISHINGS Page 1 of 3 Bid Estimated Item Description Quantity Unit Unit Price Total Project: STEWART CASE PARK - SITE IMPROVEMENTS BID SCHEDULE 23 2 Inch Caliper Deciduous Tree 25 ea $ 275.00 $ 6,875.00 24 6 Foot Evergreen Tree 6 ea $ 300.00 $ 1,800.00 25 Relocation of Existing Tree 2 ea $ 500.00 $ 1,000.00 26 Deciduous Shrub #5 42 ea $ 75.00 $ 3,150.00 27 Ornamental Grass #1 30 ea $ 30.00 $ 900.00 28 Irrigated Fescue Sod 7,572 sf $ 0.50 $ 3,786.00 29 Granite Turf Area Boulders 30 ea $ 275.00 $ 8,250.00 30 Granite Stepping Path Boulders 16 ea $ 300.00 $ 4,800.00 $ $ 139,012.00 Dollars (written) 7,572 sf $ $ work by others: tot play equipment - eddie 1.00 ea $ 2,685.00 $ 2,685.00 tot play equipment - rodeo 1.00 ea $ 7,700.00 $ 7,700.00 goric play equipment -board 1.00 ea $ 4,080.00 $ 4,080.00 goric play equipment -cat tail 1.00 ea $ 4,265.00 $ 4,265.00 poured in place safety surfacing 1,200.00 sf $ 12.00 $ 14,400.00 cliff boulder 1.00 ea $ 25,000.00 $ 25,000.00 subtotal $ 58,130.00 total $197,142.00 15% contingency $29,571.30 LANDSCAPING TOTAL Alternate Bid Items Alternate Bid Item #1 Irrigated Fescue Seed (add seed and deduct sod) playground improvements Figure Page 2 of 3 Bid Estimated Item Description Quantity Unit Unit Price Total Project: STEWART CASE PARK - SITE IMPROVEMENTS BID SCHEDULE total construction cost $226,713.30 Page 3 of 3