HomeMy WebLinkAboutPrebid - BID - 5998 LPATH BERM EROSION PROTECTION MEASURES (2)Introduction
■ City of Ft. Collins
■ Jin Wang, Project Manager
■ Jeff Baldwin, Inspector
■ Rob Hintz & Bennie Salgado, Surveyors
■ John Lang, Project Oversight
■ Mark Sears, Natural Resources Coordinator
■ Rick Bachand, Restoration
■ John Stephen, Purchasing
Introduction
■ Consultant — Anderson Consulting Engineers
■ Gregory Koch, Project Manager
■ Mark Kempton, Project Engineer
■ Testing
■ CTL Thompson
Highlights from the Bid Schedule
# ITEM UNIT QUANTITY
14 Concrete Sill CY 170
(Complete In Place)
. 4,000 psi structural concrete (Section 03310)
. Form top 12" of sill minimum
Highlights from the Bid Schedule
# ITEM UNIT QUANTITY
1s Concrete Block Revetment SF 27,453
Mat — North Spill
16 Concrete Block Revetment SF 28,640
Mat (Including Drainage
Layer) — South Spill
. Different type of block
. South Spill has additional geotextile and drainage layer
Highlights from Specifications
and Contract Documents
. Regular Working Hours are Monday through
Friday, 7 A.M. to 6 P.M.
. Saturday work will be allowed with Engineer's
approval. 48 hours notice needed.
10
Highlights from Specifications
and Contract Documents
. Anticipated Calendar Days Lost to Adverse Weather
Conditions. Schedule will not be extended until days
shown below are exceeded.
NOV
DEC
]AN
I FEB
MAR
2
5
7
4
4
. 2-Year Correction Period after date of final acceptance.
Miscellaneous
. Riverbend Ponds Natural Area will be closed for
the duration of the project
. The City will be doing some minor grading on
the construction traffic path along the west bank
of Wiper Pond. Some materials from the Borrow
Site 1, south of Bluegill Pond, will be used. This
work is schedule to be completed before the
start of the LPATH project.
Thank You
for Attending ,the
Pre -Bid Meeting
Please Remember to Sign -In
11
QUESTIONS?
Field Visit
Meet at
North Parking
Lot of
Riverbend Ponds
Natural Area
12
Bid Opening
. October 191h, 2006
3:00 PM (our clock)
. 215 North Mason Street,
2"d Floor
Purchasing Department
Plans & Specifications
. Available for viewing at
. Purchasing Department
. Online at www.mercury-ldo.com
. Specifications available for download at
www.fcgov.com/purchasing
. Contractor can purchase plans and specs
from Mercury-LDO
Plans & Specifications
2
Contractor Qualifications
Must Show Proof of Completing
Three (3) Projects Involving
Dewatering or Concrete Block
Revetment Mat
Important Dates
. Anticipated Notice of Award
Week of November 6th, 2006
. Anticipated Notice to Proceed
Week of November 27th, 2006
Schedule
. Substantial Completion: March 23th, 2007
. Final Completion: March 30t", 2007
3
Summary of Work
. Removal of existing trees and concrete rubble
■ Installation of concrete sills
■ Excavation and transportation of fill material
from borrow sites
. Installation of concrete block revetment mat
systems
. Installation of buried rock riprap
. Ground preparation for revegetation
4
Project Overview
Remove 9 Existing Trees
Project Overview
• Remove 6 Existing Trees
• Clearing and Grubbing
• Install Concrete Sill
• Install Concrete Block Revetment Mat
System
5
No Text
Coordination of Work by Others
. City Survey crew will be providing the
survey for this project.
s 48 hours request prior to needing surveying.
a City Natural Resources will be
revegetating the disturbed area.
Highlights from the Bid Schedule
# ITEM UNIT QUANTITY
1 Mobilization LS 1
. Amount shall not exceed 5% of the total bid
Highlights from the Bid Schedule
# ITEM UNIT QUANTITY
2 Traffic I Access Control LS 1
. It is anticipated that Traffic Control will only be needed
for delivery of materials and other short duration
activity.
. Includes providing, installing and maintaining of all
required Type III barricades (17) and signs (20).
7
Highlights from the Bid Schedule
# ITEM UNIT QUANTITY
3 Clearing and Grubbing LS 1
. Vegetation and debris
. All trees <12" diameter included
. Scalping required
. Disposed off -site
Highlights from the Bid Schedule
# ITEM UNIT QUANTITY
4 Construction Dewatering LS 1
(North Spill and
River Riprap Location)
. Stormwater Management Permit required and included
. Construction Dewatering Permit required and included
Highlights from the Bid Schedule
# ITEM UNIT QUANTITY
4 Construction Dewatering LS 1
(North Spill and
River Riprap Location)
. Stormwater Management Permit required.
. Construction Dewatering Permit required.
Highlights from the Bid Schedule
# ITEM UNIT QUANTITY
4 Construction Dewatering LS 1
(North Spill and
River Riprap Location)
. Stonnwater Management Permit required and included
. Construction Dewatering Permit required and included
Highlights from the Bid Schedule
(Construction Dewatering)
t a u
� sa
Z. °
Highlights from the Bid Schedule
# ITEM UNIT QUANTITY
5 Remove Concrete Rubble SF 10,350
. Concrete Rubble is estimated at 3 foot thick (average).
. Can be reused at South Spill as 4" to 8" Crushed
Concrete Rubble, governed by Section 02376, Concrete
Rubble.
9