HomeMy WebLinkAboutCHANGE ORDER - REQUISITION - 27981NOV-08-2006 WED 09:01 AM CFO ENG. Eaglaeering nepartfnene FAX NO. 9702216378 Change Order Form PROJECT TITLE: 2006 Pedestrian Access - Pedestrian Bridges PROJECT NUMBER: 30621451.6 (Bid #5971) CONTRACTOR: 01, Hoff (PO #6602850) CHANGE ORDER NUMBER: 1 n preparing change orders s ow in order as separate numSered paragrap s t1le o owing: 1. Reason for change. 2. Description of change. 3. Change in contract cost, 4. Change in contract time. , 1 &2. See attached sheet for detail. 3. The contract cost will increase by $ 20,541.60 4. There will be no change in Contract time ORIGINAL CONTRACT COST $141,589.50 TOTAL APPROVED CHANGE ORDERS $0.00 TOTAL PENDING CHANGE ORDERS $0.00 TOTAL THIS CHANGE ORDER $20,641.60 TOTAL % OF THIS CHANGE ORDER 14.51%6 TOTAL C.O. % OF ORIGINAL CONTRACT 14.51% ADJUSTED CONTRACT COST $162,131.10 (Assuming all change orders approved) . ACCEPTED BY: REVIEWED BY: ACCEPTED BY: DATE: /lam ado DATE: DATE' (Project Mana(pr) ACCEPTED BY: _ lA +pch� ,.+i`DATE: (Department Head) APPROVED BY: DATE: (Purchasing Agent over $30,000) cc: Contractor 5 ray. so ,Tra rrv444A, ��� r1 Project File �B i'3 8U �LLLR.t/ Project File Fnain".rinv Deosrtment • 281 North College Montle • P.O. Box 590 • Fort Collins, CO 80522-0580 (970) 221-6605 NOV-08-2006 WED 09:01 AM CFC ENG. FAX N0, 9702216378 P. 02 Change Order No.: 1 Data: 111112006 Pedestrian Bridges G L Hoff Company Bid No. 5971 Reason For Change: e, Adds concrete quantlies for concrete sidewalks, curb, and gutters for the Mulberry Ped Bridge paid by Transportation Planning. b. Additional traffic control quanttics relating to added ccncrate work for the Mulberry Pad Bridge paid by Transportation Planning, c, Adds concrete quantities for concrete sidewalks, curb, and gutters for the Laporte Pod Bridges paid by Pod Access. d. Additional traffic control quantities relating to added concrete work for the Laporte Pod Bridges paid by Pod Access. e. Additional labor work was performed by Hoff Construction to modify the Laporte bridge abutnwnls due to utility conflicts. I. Additional labor work was performed Uy Hoff Construction to modify the Mulberry bridge abutments due to utility conflicts. 2. Description Of Change! a. Add items for Concrete Repairs. It. Increase the quantities in the contract for the specific Items. c. Add items for Concrete Repair$. d. increase the quantities in line Contract for the specific items. e. Lump Sum price for field moditicatlona to laporto bridge abutments. f, Lump Sum prine for Held modifications to Mulberry bridge abutments. 3. change In Contract Amount: a, Mulberry • Additional Concrete Repair Unit Quantity Unit Cast Total Cost 202.01 Remove Concrete SF 66 $ 1.60 $ 105.60 202.02 Remove Asphalt Paving SF 140 $ 1.20 S 168.00 304.01 Aggregate Base Course Ton 2.43 S 75.00 S 102.25 608.01 6" Concrete Flat Work SF 219 $ 6.90 S 1 1111A0 $ 1.966,94 b. Mulberry -Traffic Control Unit Quantity Unit Coat Total Coat 614.03 Channelizing Barrels ;or Day Per Esol 24 $1.30 $ 31.20 614.04 Type I Barricade Without Light Ter Day Per Ead 24 $1,30 S 31.20 614.07 Size A Sign With Stand Der Day Per Eacl 5 $3.85 $ 19.25 614,11 Cone with Reflective Strip 3er Day Per Ead 24 51,30 S 31.20 614.15 Advance Warning Flashing - or Sequencing Arrow Panel Der Day Per Eacl 3 $100.00 S 300.00 614.10 Traffic Control Supervisor Per Day 2 S490.00 $ 980.00 814.18 rlagging Per Hour 5 $29.00 S $ 1,53737..85 c. capons -Additional Concrete Repair Unit Quantity Unit Cost Total Cost 202,01 Remove Concrete 8F 343 $ 1.60 $ 446.80 202.02 Remove Asphalt Paving SF 340 S 1.20 $ 406.00 304.01 Aggregate Bass Course Ton 9.34 $ 75.00 $ 700.50 506.01 Type L(D50=9") Rlprep Ton 20 $ 64.00 S 1,280.00 608.01 6" connects Flat Work SF 541 $ 6.90 $ 3,732.90 608,02 Vertical Curb & Gutter LF 120 S 18.00 $ 2,160.00 $08.03 2-foot concrete channel LF 16 S 36.75 $ d8800 S ,418.20 d. Laporte -Traffic Control Unit Quantity Unit Cost Total Coat 614.03 Channelizing Barrels Ser Day Per Eacl 5o $1.30 $ 65.00 61404 Type 16arricado Without Light Der Day For fact 50 $1,30 $ 65.00 614.07 Size A Sign With Stand Der Day Per Eacl 14 $3.85 S 53.90 614,11 Cone With Reflective Strip Der Day Per Eacl 14 $1,30 S 18.20 614.15 Advance Warning Flashing - or Sequencing Arrow Panel 'Der Day Per Ead 5 S100.00 S 500.00 614.1a Traffic Control Supervisor Par Day 5 $490.00 $ 2,450,00 614.18 Flagging Per Hour 16 $29.00 S 464.00 $ 3,616.10 e. Lump Sum price for Laporte bridge abutments. LS 1 S 2,401,50 S 2,401.50 f. Lump sum price for Mulhorry, bridge abuterfents. LS 1 S 1,601.00 $ 1,001.00 H:\p.m.p\PEMPed Access\Ped Access 2004\Ped Bridges\Monthly Pay Estimate,xis 1 of 2 NOV-08-2006 WED 09:02 AM CFC ENG. FAX NO. 9702216378 P, 03 Pedestrian Bridges G L Hoff Company Bid No. 5971 TOTAL CHANGE. IN CONTRACT AMOUNT Mulberry PED Bridge Concrete Repair Trolfic Control Abutment Modifications Total paid by Transportation Planning Laporte PEP Bridge Concrete Repair Traffic Cbetrol Abutment Modifications Total paid by PEO Access 4, Chango In Contract Time a. Ten days are added to the contract TOTAL CHANGE IN CONTRACT TIME $ 20,541.60 $ 1,966.95 16 1,537.86 3 1,601.00 5 5,105.a0 $ 9,418.20 $ 3,616.10 5 2,40150 �$ 15,0.35.80 10 Days HAp.m.pTEMPed ACCessxPed Access 20041Ped BridgesWonthly Pay Estimate.xls 2 of 2