HomeMy WebLinkAboutAddendum 1 - RFP - 10198 Utility Consulting Services - ArcFM XI MigrationAddendum # 1
10198 Page 1 of 7
ADDENDUM NO. 1
SPECIFICATIONS AND CONTRACT DOCUMENTS
Description of RFP 10198: Utility Consulting Services - ArcFM XI Migration
OPENING DATE: 3:00 PM (Our Clock) October 9, 2025
To all prospective bidders under the specifications and contract documents described above, the
following changes/additions are hereby made and detailed in the following sections of this
addendum:
Exhibit 1 – Questions and Answers
Please contact Jake Rector, Purchasing Manager, at (970) 221-6776 or jrector@fcgov.com with
any questions regarding this addendum.
RECEIPT OF THIS ADDENDUM MUST BE ACKNOWLEDGED BY A WRITTEN STATEMENT
ENCLOSED WITH THE PROPOSAL STATING THAT THIS ADDENDUM HAS BEEN
RECEIVED.
Financial Services
Purchasing Division
215 N. Mason St. 2nd Floor
PO Box 580
Fort Collins, CO 80522
970.221.6775
fcgov.com/purchasing
Addendum # 1
10198 Page 2 of 7
EXHIBIT 1
QUESTIONS AND ANSWERS
1
From the RFP section 2.0 Business Organization chart it appears to be a
single GIS team with GIS specialists by utility type (fiber, electric, water) -
is this a correct assessment?
A: That is correct.
2
Who makes GIS related decisions if it impacts multiple utilities?
A: The Utilities GIS Manager, with input from the Utilities GIS
Team and leadership stakeholders from each utility.
3
Do you have separate or consolidated GIS instances for each of the
utility type (fiber, electric, water or fiber in one and electric/water in
another)?
A: We have both separate and consolidated instances. We share
one Enterprise GIS Environment with separate database for
OneWater. Light & Power and Fiber currently share a database,
which will be separated as part of this project. Conduit is in a
shared structure network. between Light & Power and Fiber.
4
Do you have a unified geospatial database across all utilities (fiber,
electric, water)?
A: No
5
Will the team selected for this work also be allowed to work on future
Fort Collins GIS projects in the other utility areas (water, electric)?
A: The other utility areas will be awarded under a separate
solicitation. The awarded Professional will not be excluded from
eligibility.
6
Could winning and delivering this work successfully lead to a managed
service contract or place firm in favorable position for future GIS work
across all utilities?
A: Delivering a successful product would serve as a good
reference for future work with the City.
7
What is the timing of RFPs/actions for the rest of the GIS ecosystem?
(e.g. SE upgrade for electric, or UN migration for any of the utilities)
A: The solicitation will be posted on BidNet, anticipated in 2025.
8 Main document
On the cover page, it lists 10/8 as the due date. On page 10, it states
10/9. Please clarify.
A: October 9, 2025 at 3:00 PM MT. Proposals to be submitted through
BIDNET.
9 Main document
Due to the closeness of when responses to questions is to the due date.
Would you consider an extension?
A: No, the Evaluation Team feels that there is enough time for
prospective firms to prepare their proposals after the Q&A Addendum is
posted on October 1, 2025
10 DOW Training - Will training be expected to be performed on City data? Or a
demo / canned dataset?
Addendum # 1
10198 Page 3 of 7
A: City Data
11 DOW
Cleansing - It is our understanding that remediation and data cleansing
will be reported to the city, the city will be responsible for cleaning up
their own data? The (professional) will produce data reports of what
conflicts, errors and remediation items need to occur.
A: Yes, the City will perform data cleansing. The schema needs to be
cleaned up and we will seek advice from the Professional for best
practices. The data is relatively new and has been through rigorous
QAQC.
12 Scope
Mentions that the SQL environment is maintained by a 3rd party, is this a
vendor / firm that is maintaining the data, or is it a platform that is
maintaining the SQL environment (like GLDS or AWS)?
A: No, the 3rd party does not maintain the data. The 3rd Party provides a
managed service, not a platform (like GLDS or AWS).
13 Scope
Conduit is shared between telecom and electric, it is our understanding
that the conduit will be pulled from electric and placed in telecom for
future maintenance of the data, is there an attribute that designates
which conduit / vaults is shared vs electric only
A: Yes, at various states, but the data has not been well maintained.
Mostly built at parent level. Child relationships are not optimized.
14 DOW
GLDS is the OSS/BS platform and only needs a night push of data to the
GIS?
A:Yes
15 Scope
The RFP does not mention UN, but reads like a UN migration for Fiber, is
this a correct assumption?
A: This RFP is for a migration from ArcFM 10.8.1 to ArcFM XI (Schneider
Electric solution, based on Esri UN data model).
16 Scope
Are there any other systems (other than GLDS) integrated to the fiber
database, such as a CRM?
A: No
17 Scope
Database will be migrated to separate SQL server, is the system
integrator (professional) responsible for standing up the new instance of
SQL? Will the City supply all IT infrastructure?
A: The City will supply all IT Infrastructure
18 DOW
Will the test environment be on the City IT infrastructure or is the System
Integrator (professional) supplying this?
A: The City will supply the test environment
19 DOW
How many staff is anticipated to be trained for train the trainer? End user
training?
A: 4 train the trainers and up to 9 end users
20 DOW
What is the target infrastructure environment for this deployment (on-
premises VM environment, or cloud hosted(Azure/AWS/etc.)?
A: Target infrastructure will be an on-premise VM Environment.
21 DOW
What are the high-availability and disaster recovery requirements for this
migration including the ArcFM XI database?
A: Not defined at this point.
Addendum # 1
10198 Page 4 of 7
22
10198 Utility Consulting
Services - ArcFM XI
Migration(JR).pdf
What specific desktop infrastructure solution, if any, does the City of
Fort Collins anticipate being used by ArcFM XI / ArcGIS Pro users after
the upgrade (i.e., physical laptops/desktops with locally-installed
software, dedicated virtual desktop infrastructure using VMware
Horizon, virtualized applications using Citrix Virtual Apps, shared-
sessions using Citrix XenApp or some other Remote Desktop Session
Host technologies)?
A: Desktop solution will be physical laptops with locally installed
software and dedicated virtual desktops.
23 Scope
For GIS operation workflows in ArcFM XI, does the City have an
authoritative, maintained repository or standard for documenting end-
to-end processes and workflows?
A: No
24 Scope
Does the project include upgrading ArcGIS Enterprise and ArcGIS Pro? If
yes, what versions of ArcGIS Pro and ArcGIS Enterprise are targeted?
A: The project includes a migration from ArcMap to ArcGIS Pro, but not
an upgrade. At the time of migration implementation, the target version
will be the most current version of ArcGIS Pro and Enterprise that is
compatible with ArcFM XI, and supported by the City.
25
The RFP document and procurement website list due dates for the
proposal of October 8, 2025, and October 9, 2025, which is the correct
due date?
A: October 9, 2025 at 3:00 PM MT. Proposals to be submitted through
BIDNET.
26
How many end users are there for each of the Esri and Schneider Electric
applications?
a. ArcFM Fiber Manager
A: ~5
b. ArcFM Editor
A: ~20
c. ArcFM Conduit Manager
A: ~20
d. Wavepoint
A: ~30
27
How many environments (test, production, development, etc.) need to
be setup with software installed and configured?
A: Development, test and production.
28
Does the City of Fort Collins expect the supplier to perform all Esri and
Schneider Electric software installation tasks? Or will the City of Fort
Collins perform any of that work?
A: The City IT provides the installation of Software
29
Please provide detailed information on the GLDS Broadhub data feed
including integration technology, data mapping, etc.
A: No direct integration, 1 nightly data feed (email) that updates two
tables.
Addendum # 1
10198 Page 5 of 7
30
As it is an upgrade from ArcFM 10.8.1 to ArcFM XI; should we assume
that the data cleansing will be limited to any restructuring of existing
facilities in the source ArcFM 10.8.1 system, and any gaps that exist in
the source system will continue to exist, and the vendor is not expected
to perform any cleansing of the same? If data cleansing is expected as
part of the scope of work, can the City quantify the extent of such issues
that require data cleansing?
A: The RFP Includes a Data Readiness Assessment (Task 4.2). The
Professional is expected to complete the Data Readiness Assessment to
identify readiness to migrate to ArcFM XI. The City anticipates limited
topology errors in the current environment, however migration readiness
will remain unknown until the Data Readiness Assessment is completed.
Creation of new data and gaps in source system are out of scope.
31
Can the City provide the list of Feature/Object Classes along with their
record counts?
A: See Tables below
FiberDataset -Features Count
DivicePoint 5084
FDHBoundary 387
FiberDataset_Net_Junctions 30163
FiberOpticCable 66291
HutBoundary 4
NAPBoundary 1100
PatchLocation 28567
SplicePoint 11435
FiberOther
Fiber_FieldNID 86382
Tables Count
F_BACKSIDEPORT 92636
F_BUFFERTUBE 127060
F_CIRCUIT 57609
F_CIRCUITCOMPONENT 1283908
F_DEVICE 4771
F_DEVICEPORT 4747
F_FIBER 994874
F_FIBERCONNECTIONOBJECT 494459
F_FRONTSIDEPORT 94382
F_PATCHPANEL 28722
F_PATCHPANELCARD 30310
Addendum # 1
10198 Page 6 of 7
F_PortPositions 110112
F_Rack 28591
F_Splitter 34327
F_SplitterInputPort 3426
F_SplitterOutputPort 109576
WorkOrders 21879
CXN_GIS_HOMES_PASSED_LIST 23046
Relationship Name Orgin PKEY FKEY Destination
Fiber_NID_F_PortPositions Fiber_FieldNID GLOBALID NIDFIELGUID F_PortPostions
CXN_FIELD_NID CXN_GIS_HOMES_PASSED_LIST GIS_ADDR_ID ADDRESSID Fiber_FieldNID
WorkOrder_FieldNID WorkOrders ADDRESSID ADDRESSID Fiber_FieldNID
CXN_HomePassed_DropCables CXN_GIS_HOMES_PASSED_LIST GIS_ADDR_ID ADDRESSID FiberOpticCable
WorkOrders_FiberCables WorkOrders ADDRESSJOIN CABLENAME FiberOpticCable
CXN_SplicePoint CXN_GIS_HOMES_PASSED_LIST FDH SPLICENAME SplicePoint
F_SpliceNAP_F_PortPositions SplicePoint SpliceName SERVING_NAP F_PortPostions
F_SplicePoint_F_PortPositions SplicePoint SPLICENAME FDH F_PortPositions
* The remaining relationship classes are standard ArcFM Fiber Manager relationship/schema configurations
32
Are there additional legacy data sources to be considered during the
version upgrade?
A: No
33
Can we assume that the City will continue to utilize SQL Server as the
preferred Database post ArcFM version upgrade?
A: Yes
34
Please provide:
a. Number of Circuits
A: 57,609 Circuits built
b. Customer Counts
A: ~ 86,000 Potential Customers
35
Will landbase be migrated? If so, will it require standardization or will it
be migrated as-is? Please provide the feature class/count listing for the
same.
A: No, out of scope
36
Do we need to create Fiber Favorites?
A: Yes, we currently use Fiber Favorites and expect them to be created
and configured in the new ArcFM XI.
37 Do we need to create Symbol files?
A: No
38 Do you have any custom functionality or solutions that will need to be
carried forward into the new implementation?
Addendum # 1
10198 Page 7 of 7
A: No
39
Do you have any integrations to external applications that will need to be
implemented?
A: No, just the billing data feed.
40
Are there existing web maps / web applications that will need to persist?
If so, could you please list and provide descriptions?
A: Yes
• UView Web (Web Mapping App)
• An application utilized City wide as a viewer for all Utility Data.
• UView Web for Locates (Web Mapping App)
• A web app used by utility locates to view City utilities,
customized to locate specifications.
• Outside Plant “OSP” Network Audit Map (Web Map)
• Web Map for tracking construction inspection status for network
features. Similar to the Fiber Multi Dwelling Unit “MDU”
Inspections Map, but is not specific to MDU's.
• OSP MDU and Exclusion Area Statuses (Web Map)
• Project coordination application, providing statuses of buildout
and associated information.
• Fiber MDU Inspections (Web Map)
• App for OSP field engineers to record and note issues related to
construction.
• Fiber Premise Installation (Web Map)
• Web Map used to assign FDH splitter/splitter tail assignments
and OLT port assignments.
41
Does your organization currently maintain any coaxial infrastructure as
part of your network? If so, are you currently utilizing ArcFM Designer
Hybrid Fiber Coax (DHFC) software?
A: No
42
Are you currently using ArcFM Designer or Session Manager for your
design and editing workflows?
A: No
43
Is your team utilizing ArcFM Geodatabase Manager (GDBM) for work
order processing?
A: No
.