HomeMy WebLinkAboutAddendum 1 - BID - 10196 URA Asbestos Abatement and Demolition of Budget Host Inn
Addendum # 1
10196 ITB FCURA Asbestos Abatement and Demolition of Budget Host Inn
ADDENDUM NO. 1
Description of ITB 10196: FCURA Asbestos Abatement and Demolition of Budget Host Inn
ITB DUE DATE: 3:00 PM (Mountain Time) August 12, 2025
To all prospective Bidders under the Invitation to Bid documents described above, the following
changes/additions are hereby made and detailed in the following sections of this addendum:
Exhibit 1 - Questions and Answers
Exhibit 2 – ALTA/ NSPS Land Title Survey
Please contact Adam Hill, Senior Buyer, at 970-221-6777 or adhill@fcgov.com with any questions
regarding this addendum.
RECEIPT OF THIS ADDENDUM MUST BE ACKNOWLEDGED BY A WRITTEN STATEMENT
ENCLOSED WITH THE ITB STATING THAT THIS ADDENDUM HAS BEEN RECEIVED.
nd Floor
970.221.6775
970.221.6707
fcgov.com/purchasing
Addendum # 1
10196 ITB FCURA Asbestos Abatement and Demolition of Budget Host Inn
Exhibit 1 – Questions and Answers
1. Will a 3rd party Project Manager be required for this project and will this contract need to
be included by the Bidder or the Owner?
Response: A project manager must be used on all asbestos abatement projects in
which the amount of friable asbestos-containing material to be abated exceeds 1,000
linear feet on pipes, or 3,000 square feet on other surfaces. The Owner will contract out
the Project Manager independently of this RFP, thus this does not need to be included
in the BID.
2. What is the anticipated start date for the project?
Response: FCURA is anticipating closing on the property by August 26, 2025. Once this
occurs the awarded Contractor can start with an executed contract and notice to
proceed. FCURA would like this work to be completed by the end of October 2025.
3. Who will be responsible to procure the water meter and the costs?
Response: This will be the responsibility of the awarded Contractor.
4. How many water and sewer disconnects will be required and where are they to be
capped at the main or a different location on site?
Response: There are two water disconnects along the east side of the property, and one
sewer disconnect at the southwest corner of the property. Additionally, there is a storm
drainage pipe that must be maintained along the south property line.
5. Are there any known spills in the units?
Response:
Page 22 of the Foothills Environmental Asbestos Inspection Report notes, “The
damaged ACM drywall surface texture compound (areas of the unit 29 Bedroom and
Bathroom ceilings) is less than 160 square feet. This condition is defined as a “Minor
Asbestos Spill” according to the CDPHE Regulation No. 8.” The owner restricted access
to this unit. No additional response actions were taken.
Note the following limitation on page 42 of the Foothills Environmental Asbestos
Inspection Report, “It should be noted that multiple layers of flooring were present
throughout the property. FE made a concerted effort to perform intrusive investigation
of the flooring materials in order to determine the location and quantity of the flooring
layers; however, significant disturbance of the flooring materials was avoided in order
to avoid creating an asbestos spill at the property. In addition, in many instances, it was
apparent that some ACM sheet vinyl flooring had previously been removed, and that
remnant ACM fibrous backing and adhesive were still present in some areas. Once
abatement activities are initiated and containments are established, further intrusive
examination may be required to determine the exact location and quantity of the ACM
vinyl sheet flooring, ACM remnant fibrous backing and remnant associated mastics.”
Addendum # 1
10196 ITB FCURA Asbestos Abatement and Demolition of Budget Host Inn
6. Is there any meth lab equipment in the units?
Response: None that we are aware of. Please refer to full Preliminary Assessment.
7. Can the awarded Contractor utilize a temporary electrical panel on the site during the
asbestos abatement period as this will require significant electrical usage for 24 hour
periods during this process?
Response: Yes
8. Can the scope of this project be broken out into multiple contracts?
Response: No, we want to handle this under one contract.
ALTA/NSPS LAND TITLE SURVEY
Know what's below.
before you dig.Call
R
OF
REVISIONS
DESIGNER / DRAFTER
PROJECT NUMBER
DATE
SHEET
BOOK AND PAGE
LAMPRYNEARSON.COM
OMAHA, NEBRASKA
14710 W. DODGE RD, STE. 100 (402) 496.2498
NE AUTHORIZATION NO.: CA0130
FORT COLLINS, COLORADO
4715 INNOVATION DR., STE. 100 (970) 226.0342
KANSAS CITY, MISSOURI
9001 STATE LINE RD., STE. 200 (816) 361.0440
MO AUTH. NO.: E-2013011903 | LS-2019043127
COLORADO L ICENSED
P R O F E S SI O N A L L A N D S U R V E Y O R
LA
INE A . LANDAU31159
5/16/2025
STOP
STOP
ALTA/NSPS LAND TITLE SURVEY
Know what's below.
before you dig.Call
R
OF
REVISIONS
DESIGNER / DRAFTER
PROJECT NUMBER
DATE
SHEET
BOOK AND PAGE
LAMPRYNEARSON.COM
OMAHA, NEBRASKA
14710 W. DODGE RD, STE. 100 (402) 496.2498
NE AUTHORIZATION NO.: CA0130
FORT COLLINS, COLORADO
4715 INNOVATION DR., STE. 100 (970) 226.0342
KANSAS CITY, MISSOURI
9001 STATE LINE RD., STE. 200 (816) 361.0440
MO AUTH. NO.: E-2013011903 | LS-2019043127
COLORADO L ICENSED
P R O F E S SI O N A L L A N D S U R V E Y O R
LA
INE A . LANDAU31159
5/16/2025