1. Pre-Bid Attendance Record
2. Pre-Bid Meeting Presentation
3. Updated Bid Schedule-This Bid Schedule replaces the original Bid Schedule supplied in
the Solicitation. Please use this Bid Schedule in your response to the City.
Please contact JD McCune, Senior Buyer, at jmccune@fcgov.com with any questions regarding
this addendum.
RECEIPT OF THIS ADDENDUM MUST BE ACKNOWLEDGED BY A WRITTEN STATEMENT
ENCLOSED WITH THE RFP STATING THAT THIS ADDENDUM HAS BEEN RECEIVED.
Financial Services
Purchasing Division
215 N. Mason St. 2nd Floor
PO Box 580
Fort Collins, CO 80522
970.221.6775
970.221.6707
fcgov.com/purchasing
NAME FIRM NAME EMAIL ADDRESS
Brandon Koehler Coyote Ridge Construction bkoehler@crc.co.net
Nick Ritschard Gerrad Excavating nritschard@gerrardinc.com
Kobi Salinas Custom Water Connections ksali@customwaterconnections.com
ATTENDANCE RECORD - PRE-BID MEETING
TIME: 10:00 AM MT DATE: MARCH 27, 2024
LOCATION: MICROSOFT TEAMS
PROJECT: 9961 2023-2024 COLLECTION REPLACEMENT PROJECT
1
Pre-Bid Meeting
March 27, 2024
‘23-’24 Collections Replacement Project
Bid #9961
AGENDA
1.Introductions
2.Virtual Meeting Requests
3.BID Process & Schedule
4.Contract Times & Schedule
5.Bid Form Highlights
6.Contract Highlights
7.Project Background and Objectives
8.Scope of Services
9.Easements – Beaver’s Alley
10.Questions
2
INTRODUCTIONS
J.D. McCune-CoFC
Senior Buyer, Purchasing
Jason Stutzman, P.E.-CoFC
PM, Utilities Capital Projects
Matt Fater-CoFC
Director of Civil Engineering
Dan Egger, P.E. – Ditesco
Services
Design Consultant
3
VIRTUAL MEETING REQUESTS
•Please put your Name, Company and email in the Chat.
•A copy of this presentation will be provided as part of
the Addendum
•City will provide Q&A’s with an Addendum only if
additional clarification or additional information is
needed
•Submit additional questions in writing via e-mail to J.D.
McCune (Jmccune@fcgov.com) after pre-bid meeting.
4
BID PROCESS AND SCHEDULE
•Submit Bids online via RMEPS
•All questions submitted in writing via email to J.D. McCune
(Jmccune@fcgov.com)
•Anticipated Schedule (Section 100-24.0)
5We encourage you to ask questions prior to the question deadline
Schedule Date & Time (MST)
Bid Issue Date March 14, 2024
Pre-Bid Meeting (10:00 AM MT) on March 27
Question Deadline April 1, 2024 (3:00 PM)
Final Addendum Issued April 5,2023
Bids Due April 12, 2024 (3:00 PM)
Target Start Date June 3, 2024
CONTRACT TIMES & SCHEDULE
6
NOTICE OF AWARD
•sent out with AGREEMENT
PRE-CONSTRUCTION
MEETING
•Mandatory prior to NOTICE
TO PROCEED
•Construction Schedule
approved prior to meeting
•Target Construction Start –
June 3, 2024
MILESTONE DATE (SUBJECT TO CHANGE)
Notice of Award (tentative):Week of 4/15/24
Contract / Agreement
Completed (tentative):
Week of 5/13/24
Pre-Construction Meeting
(tentative):
Week of 5/20/24
Construction Start (Target):June 3, 2024
Phase 1 Milestone -
North Meldrum
(Section 520, Article 4)
August 2, 2024
Phase 2 Milestone -
Beaver’s Alley
(Section 520, Article 4)
October 2, 2024
Substantial Completion December 27, 2024
Final Acceptance 30 days after Substantial
Completion
BID FORM
Highlights in the bid form (Section 300):
Bid Form
Electronic Bid Bond (Item 3 above and Section 00410) for five (5)
percent of the base Bid amount
Acknowledgement of Bid Addenda
Preliminary Schedule (Item 10)
Statement of Bidder's Qualifications (Section 00420, item 16)
Schedule of Subcontractors (Section 00430)
Safety Form (Section 00440)
7
CONTRACT
Key items to the project bid:
Critical schedule for North Meldrum (school) and Beaver’s Alley (TCE)
Contractor is responsible for traffic control permitting and coordination
Contractor is responsible for excavation permitting and Engineering
department inspection
Surface restoration will be limited to the extents shown on the drawings.
Payment for additional full depth asphalt/concrete restoration will not be
made
Note the technical specifications for the project, a new format vs. past
City projects
Provide the preliminary schedule
8
BACKGROUND AND OBJECTIVES
Collections Replacement Program
•Replacement Priorities:
•All V. Clay
•6-inch Mainlines
•100 yr. old life cycle
•Backyard mains
•Collaborative/Opportunity
•Project locations prioritized by
condition and opportunity.
9
SCOPE OF SERVICES
10
•Replacement & rehabilitation of
sanitary sewer mains in Old Town
Fort Collins
•Comprised of traditional open-cut
installation
•In-kind replacement where possible.
•5 different locations
•3,000 lf. of PVC SDR35 mainline
(approx.)
SCOPE OF SERVICES
11
Highlights for scope of services
•The work will require all services/sanitary sewer lines remain active
during construction.
•…Complete all utility replacement work within a phase before
starting work in the next phase, unless multiple crews are working
simultaneously.
•Prepare detailed traffic control plans for each part of the project
…Section 01 32 16
•extensive public outreach and accommodation including property
owners, tenants, commercial properties, and public entities.
SCOPE OF SERVICES
12
Community Engagement
•Assist City staff in outreach to impacted residents and
businesses during construction activities.
•Distribution of outreach materials to residents and businesses.
•Attendance at individual meetings with local businesses and
residents as needed.
•Assist with preparation of communication materials as needed.
BEAVER’S ALLEY
13
Easements for Beaver’s Alley have been provided by owner.
BEAVER’S ALLEY
14
Easements for Beaver’s Alley have been provided by owner.
BEAVER’S ALLEY
15
Easements for Beaver’s Alley have been provided by owner.
BEAVER’S ALLEY
16
Easements for Beaver’s Alley have been provided by owner.
Email J.D McCune questions before April 1st at 3:00 PM MT
pjohnson@fcgov.com
17
THANK YOU FOR ATTENDING
QUESTIONS & THANK YOU
No. ITEM QTY UNIT UNIT COST EXTENDED COST
1 Mobilization 1 LS
2 Excavation Permit Fees 1 ALLOW 16,500.00$
3 Erosion Control 1 LS
4 Traffic Control Management 40 DAY
5 Traffic Control Flagging 160 HR
6 Variable Message Sign (VMS) 2 EA
7 Traffic Control Signage and Devices 1 LS
8 Asphalt Pavement Removal 499 SY
9 Asphalt Milling 665 SY
10 Concrete Pan Removal 5 SY
11 Remove Manhole 5 EA
12 Unsuitable Materials Mitigation 150 CY
13 Sanitary Sewer Installation - 8" SDR 35 715 LF
14 Sanitary Sewer Service Connection 11 EA
15 Manhole Installation 5 EA
16 Aggregate Base Course 343 TON
17 Asphalt Pavement 375 TON
18 Concrete Pan 5 SY
19 Pavement Markings 1 LS
Cherry-Maple-Shields Subtotal
9961 2023-2024 COLLECTION SYSTEM REPLACEMENT PROJECT
BID SCHEDULE
CHERRY-MAPLE-SHIELDS
Bid Schedule 1 of 5 2023-2024 COLLECTION SYSTEM REPLACEMENT PROJECT
9961 2023-2024 COLLECTION SYSTEM REPLACEMENT PROJECT
BID SCHEDULE
CHERRY-MAPLE-SHIELDS
No. ITEM QTY UNIT UNIT COST EXTENDED COST
1 Mobilization 1 LS
2 Erosion Control 1 LS
3 Traffic Control Management 28 DAY
4 Traffic Control Flagging 20 HR
5 Traffic Control Signage and Devices 1 LS
6 Asphalt Pavement Removal 147 SY
7 Asphalt Milling 440 SY
8 Abandon Manhole 1 EA
9 Fence Removal 180 LF
10 Unsuitable Materials Mitigation 60 CY
11 Sanitary Sewer Installation - 8" SDR 35 315 LF
12 Sanitary Sewer Service Connection 8 EA
13 Manhole Installation 3 EA
14 Aggregate Base Course 300 TON
15 Asphalt Pavement 104 TON
16 Landscape Repair 1 LS
Beaver's Alley Total
BEAVER'S ALLEY (Phase 2)
Bid Schedule 2 of 5 2023-2024 COLLECTION SYSTEM REPLACEMENT PROJECT
9961 2023-2024 COLLECTION SYSTEM REPLACEMENT PROJECT
BID SCHEDULE
CHERRY-MAPLE-SHIELDS
No. ITEM QTY UNIT UNIT COST EXTENDED COST
1 Mobilization 1 LS
2 Excavation Permit Fees 1 ALLOW 11,500.00$
3 Erosion Control 1 LS
4 Traffic Control Management 28 DAY
5 Traffic Control Flagging 30 HR
6 Traffic Control Signage and Devices 1 LS
7 Asphalt Pavement Removal 301 SY
8 Asphalt Milling 401 SY
9 Concrete Pavement Removal 342 SY
10 Remove Manhole 1 EA
11 Unsuitable Materials Mitigation 100 CY
12 Sanitary Sewer Installation - 8" SDR 35 505 LF
13 Sanitary Sewer Service Connection 11 EA
14 Manhole Installation 1 EA
15 Aggregate Base Course 242 TON
16 Asphalt Pavement 190 TON
17 Concrete Pavement 342 SY
18 Pavement Markings 1 LS
South Loomis Total
SOUTH LOOMIS
Bid Schedule 3 of 5 2023-2024 COLLECTION SYSTEM REPLACEMENT PROJECT
9961 2023-2024 COLLECTION SYSTEM REPLACEMENT PROJECT
BID SCHEDULE
CHERRY-MAPLE-SHIELDS
No. ITEM QTY UNIT UNIT COST EXTENDED COST
1 Mobilization 1 LS
2 Excavation Permit Fees 1 ALLOW 30,000.00$
3 Erosion Control 1 LS
4 Traffic Control Management 60 DAY
5 Traffic Control Flagging 120 HR
6 Variable Message Sign (VMS) 2 EA
7 Traffic Control Signage and Devices 1 LS
8 Asphalt Pavement Removal 770 SY
9 Asphalt Milling 2035 SY
10 Concrete Pavement Removal 379 SY
11 Remove Manhole 2 EA
12 Storm Manhole Repair 1 LS
13 Unsuitable Materials Mitigation 230 CY
14 Sanitary Sewer Installation - 8" SDR 35 550 LF
15 Sanitary Sewer Installation - 10" SDR 35 715 LF
16 Sanitary Sewer Service Connection 26 EA
17 Manhole Installation 6 EA
18 Aggregate Base Course 605 TON
19 Asphalt Pavement 609 TON
20 Concrete Pavement 379 SY
21 Pavement Markings 1 LS
North Meldrum Total
NORTH MELDRUM (Phase 1)
Bid Schedule 4 of 5 2023-2024 COLLECTION SYSTEM REPLACEMENT PROJECT
9961 2023-2024 COLLECTION SYSTEM REPLACEMENT PROJECT
BID SCHEDULE
CHERRY-MAPLE-SHIELDS
No.ITEM QTY UNIT UNIT COST EXTENDED COST
1 Mobilization 1 LS
2 Excavation Permit Fees 1 ALLOW 9,500.00$
3 Erosion Control 1 LS
4 Traffic Control Management 20 DAY
5 Traffic Control Flagging 20 HR
6 Traffic Control Signage and Devices 1 LS
7 Asphalt Pavement Removal 279 SY
8 Asphalt Milling 372 SY
9 Remove Manhole 1 EA
10 Unsuitable Materials Mitigation 75 CY
11 Sanitary Sewer Installation - 8" SDR 35 400 LF
12 Sanitary Sewer Service Connection 2 EA
13 Manhole Installation 1 EA
14 Aggregate Base Course 128 TON
15 Asphalt Pavement 177 TON
16 Pavement Markings 1 LS
South Meldrum Total
Project Total (All Locations)
SOUTH MELDRUM
Bid Schedule 5 of 5 2023-2024 COLLECTION SYSTEM REPLACEMENT PROJECT