HomeMy WebLinkAboutADDENDA 1 - RFP - 9911 OWNER'S REPRESENTATIVE PROJECT MANAGEMENT SERVICES SOUTHEAST COMMUNITY CENTERAddendum # 1
RFP 9911 Owner's Representative Project Management Services SE Community Center
Page 1 of 7
ADDENDUM NO. 1
SPECIFICATIONS AND CONTRACT DOCUMENTS
Description of RFP 9911: Owner's Representative Project Management Services SE
Community Center
OPENING DATE: 3:00 PM (Our Clock) February 9, 2024
To all prospective bidders under the specifications and contract documents described above, the
following changes/additions are hereby made and detailed in the following sections of this
addendum:
Exhibit 1 – Questions and Answers
Exhibit 2 – Section III Item F Cost and Work Hours
Section III Item F is removed and replaced in its entirety by Exhibit 2 attached hereto.
Please contact Dennis Ralph, Senior Buyer, at 970-221-6281 or dralph@fcgov.com with any
questions regarding this addendum.
RECEIPT OF THIS ADDENDUM MUST BE ACKNOWLEDGED BY A WRITTEN STATEMENT
ENCLOSED WITH THE PROPOSAL STATING THAT THIS ADDENDUM HAS BEEN
RECEIVED.
Financial Services
Purchasing Division
215 N. Mason St. 2nd Floor
PO Box 580
Fort Collins, CO 80522
970.221.6775
970.221.6707
fcgov.com/purchasing
Addendum # 1
RFP 9911 Owner's Representative Project Management Services SE Community Center
Page 2 of 7
EXHIBIT 1 QUESTIONS AND ANSWERS
1. Does the City intend to solicit RFQ/RFPs for design (A/E) and construction
separately, or will you be seeking design/build services for the SE Community
Center? If so, what project delivery method is anticipated? If this is not
determined yet, at what point will you do so, given the intent to onboard
design and/or construction teams by EO Q2?
Answer: The city and stakeholder group have not made a final determination on
the project delivery approach. Both design/build and construction
manager/general contractor are being considered. We plan to have the Owner’s
Representative be part of further discussions, including helping determine which
is the most advantageous for this project. We anticipate these discussions to
occur soon after the Owners’ Representative is on board.
2. The RFP states, "The Professional will submit hourly rates by employee
classification and a not-to-exceed estimate for each task as detailed in
Section III." Can clarification be provided regarding which tasks the proposing
firm's "estimated price" should be related to? Is it solely for the two tasks
outlined in RFP Section III, Item F, or are the proposing firms required to
submit pricing for the entire project scope as outlined in Section II?
Answer: Refer to attached Exhibit 2 which replaces RFP Section III, Item F.
During this project, the Professional may also be required to provide costs for
various services on a work order basis as stated in the RFP.
3. Do the stakeholders have a minimum LEED Certification level they want
the project to meet?
Answer: The City’s ordinance requires projects over 5,000 SF to seek the highest
level LEED certification possible. We are targeting LEED Gold.
4. Does the City have staff in charge of reviewing certified payroll with whom
the Owner's Representative will be working?
Answer: The City of Fort Collins does have a few staff members who have
experience working with certified payroll for projects which have federal and
other specialty funding. However, we are anticipating the Owner’s
Representative taking the lead role for this task.
5. It is our understanding that the School District is not yet formalized as a
partner, but that they expect to provide the land and desire to have
scheduling priority for the swimming lanes. Please confirm the accuracy of
Addendum # 1
RFP 9911 Owner's Representative Project Management Services SE Community Center
Page 3 of 7
this understanding and elaborate as needed to clarify the role and interest of
the School District in the project.
Answer: Currently, Poudre School District has signed onto an IGA and the City
intends to acquire the property for the planned project. All stakeholder
involvement is planned to be further developed, including priorities for each
stakeholder, and documented in a project charter and guiding principles.
6. It is our understanding that the Library District is a separate entity from the
City of Fort Collins, with separate taxing authority and a Board of Directors?
Would a separate IGA be needed for the Library District and the City, as well
as the School District and the City? Or would one IGA govern the relationship
among all three?
Answer: Currently, the City of Fort Collins, Poudre Library District, and Poudre
School District have signed onto a high level IGA. The IGA is intended to govern
the overall relationship between the three entities. The plan is to process a more
detailed IGA for the partnership between the City and the Library and another
IGA between the City and Poudre School district which will provide more details
and cost sharing and responsibilities for the new facility.
7. The RFP mentions assisting in “coordination of facilitation of an IGA
between the Owners and end users of this new facility.” It is our
understanding that the “end users” in the context of this statement are the
City, the Library District, and the School District. Please confirm or clarify.
Answer: The City of Fort Collins, Poudre Library District, and Poudre School
District are separate entities. The three entities may have similar or different
priorities that relate to their end users. The plan is to process a more detailed
IGA for the partnerships between the City and the Library and another IGA
between the City and Poudre School district which will provide more details and
cost sharing and responsibilities for on-going maintenance of the new facility.
8. The RFP references “coordination with city real estate services for land
purchases, easements, right of way and potential private developments.”
What is meant by the inclusion of “potential private developments” in this
context?
Answer: The City of Fort Collins Real Estate Division is assisting with various
land acquisition duties. We are not aware of any private developments
currently.
Addendum # 1
RFP 9911 Owner's Representative Project Management Services SE Community Center
Page 4 of 7
9. What is the intended role of the selected Professional in “Certified Payroll
Management” for the project?
Answer: We are anticipating the Owner’s Representative taking the lead role for
any certified payroll. Depending on the project delivery approach, this could
include verification of contractor pay requests, wage rate verification (if tied to
grant or other special funding sources), etc.
10. In Section I.A. the potential size of the indoor space is listed at 50K-90K
SF; in an effort to homogenize proposals, would the Owner like submitters to
assume a square footage for bidding purposes?
Answer: Refer to question #2 response. Additionally for your cost response,
assume a 70K GSF facility.
11. Page 6, under Specific Responsibilities that might be required, it is noted
“Professional shall use a fully comprehensive project management software
program (Procore) to manage and document the project with powerful
features that track every task and aspect of a highly complicated project with
a challenging budget with funds from multiple sources.” It is typical that a
General Contractor will utilize Procore (or similar software) to manage
documentation but it’s less typical that the design phase requires a software
of this type. Please confirm you are requesting Procore (or similar software)
be utilized during the planning/programing & pre-construction/design phase
of the project and shall be provided by the Owner’s Rep.
Answer: The City of Fort Collins has invested significant time and resources into
hosting the use of Procore for certain projects. While this software is typically
used during bidding and construction phases of the project, it can also be used to
track design submittals and other correspondence during earlier phases. We
plan to further discuss the use with the successful Professional as a potential tool
to help manage correspondence and submittals. In any case, the City of Fort
Collins is planning to host the project and the Professional will be given
access. The Professional will not have to provide or host this
software. Additionally, refer to question #2 response.
12. Page 13, Section F asks for pricing of “the following tasks” and lists
Coordination of partnering/charrette with project Owners, and Review of IGA
between City & Library. Please confirm these are the only 2 tasks you are
requesting a not-to-exceed pricing for at this time. (Aside from hourly rates &
a per-meeting rate.)
Addendum # 1
RFP 9911 Owner's Representative Project Management Services SE Community Center
Page 5 of 7
Answer: Refer to question #2 response.
13. Will the City please confirm the requested estimated price (estimated
hours, cost for each task, etc.) is only for the tasks identified in the first two
bullets of section F (creation of partnering charter & review IGA)?
Answer: Refer to question #2 response.
14. Is the City considering a phased start-up of the Owner’s Representative
and Project Management Services? Is this the reason for the requested ‘not-
to-exceed estimate for each task’, in addition to the hourly rates by employee
classification?
Answer: Refer to question #2 response.
15. Please clarify the expectation for the OR/PM team office location be it on-
site, off-site, or a hybrid of the two.
Answer: The expectation is for the assigned personnel to be available when
needed which could require both in-person meetings and tasks being performed
off-site. As such, we see a hybrid depending on the needs and
requirements. For the initial tasks required to be priced, provide a clear
indication as to which is being provided. We will work with the successful
Professional to define expectations for all future tasks.
16. In the proposal, will the City permit firms to use fonts/sizes other than Arial
10pt for graphics and headers (non-body text)?
Answer: The city permits firms to use other Fonts/sizes as long as they exceed
the minimum requirements and does not exceed the maximum page limit.
17. Would the City consider revising the second to last sentence of Section
11(a) to the following: “…in such event the PROFESSIONAL shall not be held
responsible for the design to the extent the CITY utilizes the design for any
project other than the one specified under this Agreement or deviates from
the Project Instruments”?
Answer: The City may consider minor revisions to the Agreement and reserves
the right to negotiate the Agreement terms with the selected Professional. As
stated in the RFP, please state in the proposal any objections to the terms of the
Agreement and provide suggested revisions.
Addendum # 1
RFP 9911 Owner's Representative Project Management Services SE Community Center
Page 6 of 7
EXHIBIT 2 SECTION III ITEM F COST AND WORK HOURS
Schedule of Rates: Provide a separate schedule of hourly billing rates which includes labor,
overhead, and profit. This schedule of rates will be firm for at least one (1) year from the date of
the Agreement. The schedule will be used for all invoicing for time and material based
items. The proposal also needs to include a fee schedule(s) for subconsultants/subcontractors,
if used, with the same level of detail breakout.
Direct Costs: All direct costs (i.e., travel, printing, postage, etc.) specifically attributed to the
project and not included in the billing rates must be identified. All direct costs will be reimbursed
as per the current rates found at www.gsa.gov. The Professional will be required to provide
original receipts to the City for all travel expenses.
Provide estimated hours for each proposed task by job title and employee name. Estimated
hours should be based on your understanding and assumptions regarding each task of the
project.
Provide a breakout of scope, assumptions and clarifications for each task and work order to
support the estimated costs.
In your response to this proposal, please provide the following:
1. Work Order I (Pre-Construction) Services: (Anticipate ten months)
i. Lump sum cost for your team’s involvement to complete pre-construction services,
including, but not limited to, coordinating charrettes, and partnering charter, assisting
with IGA’s for stakeholders, assisting with RFP’s for design, construction and other
consultants, planning & development coordination. Meetings with owner
stakeholders, designers, contractors, consultants to collaborate and coordinate
project delivery, design development, sustainability, LEED coordination, cost
estimating, value engineering and other related tasks. Pre-construction ends once a
GMP has been established with a contractor for construction.
$________________________________________
ii. On a separate sheet, provide your schedule of rates by job title and estimated hours
by task utilized to establish the Pre-construction lump sum cost stated above.
iii. Lump sum cost for your required use of the City’s Procore account for project
management documentation from award through contractor GMP. This will be used
to coordinate design, development review, LEED, schedules, etc.
$________________________________________
Addendum # 1
RFP 9911 Owner's Representative Project Management Services SE Community Center
Page 7 of 7
iv. Provide your total estimated direct cost for any overhead expenses associated with
copies, vehicles, mileage, tolls, or other fees for pre-construction. Please list them on
your separate sheet for iv below.
$________________________________________
v. On a separate sheet, provide your schedule of rates for each direct cost expense
item.
2. Work Order II (Construction) Services: (Anticipate Eighteen months)
i. Total estimated cost for your firm’s involvement in managing the overall project and
represent the owner’s stakeholders during the construction phase as detailed in the
scope of work. This includes, but is not limited to, permitting, weekly OAC meetings,
budget meetings, LEED coordination, QA/QC coordination, 3rd party inspections,
submittal reviews/coordination, pay applications, certified payroll, site inspections,
punch list and project closeout.
$ ________________________________________/Month
ii. On a separate sheet, provide your schedule of rates by job title and estimated hours
by task for the monthly cost stated above.
iii. Total lump sum cost for your required use of the City’s Procore account for project
management documentation for construction beginning with the GMP through final
construction completion. This will be used to coordinate permitting activities,
submittals, RFI’s ASI’, proposal request, cost proposals, change orders, LEED
coordination, project schedules, pay applications, QA/QC documentation, punch list,
as-builts, record drawings, O & M’s, Owner training, etc.
$ ________________________________________
iv. Provide your estimated direct cost for any overhead expenses associated with
copies, vehicles, mileage, tolls, or other fees for the construction phase. Please list
them on a separate sheet if different from the Pre-construction phase.