HomeMy WebLinkAboutADDENDA 2 - RFP - 9808 CONSTRUCTION MANAGER/GENERAL CONTRACTOR (CM/GC) SERVICES FOR LAPORTE AVE IMPROVEMENTS - FISHBACK TO SUNSETAddendum 2 Page 1 of 2
ADDENDUM NO. 2
Description of RFP 9808: CMGC Laporte Ave Improvements - Fishback to Sunset
REQUEST FOR PROPOSAL
9808 RFP CMGC Laporte Ave Improvements - Fishback to Sunset
OPENING DATE: 3:00 PM (Our Clock) July 14, 2023
To all prospective proposers under documents described above, the following
changes/additions are hereby made and detailed in the following sections of this addendum:
Exhibit 1 – Questions & Answers
Please contact Adam Hill, Senior Buyer, at adhill@fcgov.com with any questions regarding this
addendum.
RECEIPT OF THIS ADDENDUM MUST BE ACKNOWLEDGED BY A WRITTEN STATEMENT
ENCLOSED WITH THE REQUEST FOR PROPOSAL STATING THAT THIS ADDENDUM HAS
BEEN RECEIVED.
Financial Services
Purchasing Division
215 N. Mason St. 2nd Floor
PO Box 580
Fort Collins, CO 80522
970.221.6775
970.221.6707
fcgov.com/purchasing
Addendum 2 Page 2 of 2
EXHIBIT 1 – QUESTIONS & ANSWERS
1. Will the City allow a full closure with detour like the one used for the bridge work? If not full,
would the city be open to directional closure(s)?
Response: As stated in the RFP we are not allowing full lane closures all
construction must be phased to maintain access throughout the project. A full
lane closure may be acceptable for certain short terms tasks if approved by the
Project Manager. Lane shifts and short-term directional closures will need to be
reviewed and approved by the Project Manager.