HomeMy WebLinkAboutBID - 9767 POUDRE FIRE AUTHORITY (PFA) TRAINING FACILITY PARKING LOT ADDITION
SPECIFICATIONS
AND
CONTRACT DOCUMENTS
FOR
POUDRE FIRE AUTHORITY (PFA) TRAINING
FACILITY PARKING LOT ADDITION
BID NO. 9767
PURCHASING DIVISION
MARCH 22, 2023 – 3:00 P.M. (OUR CLOCK)
Financial Services
Purchasing Division
215 N. Mason St. 2nd Floor
PO Box 580
Fort Collins, CO 80522
970.221.6775
970.221.6707
fcgov.com/purchasing
CONTRACT DOCUMENTS TABLE OF CONTENTS
BID INFORMATION
00020 Notice Inviting Bids
00100 Instruction to Bidders
00300 Bid Form
00400 Supplements to Bid Forms
00410 Bid Bond
00420 Statements of Bidders Qualifications
00430 Schedule of Major Subcontractors
CONTRACT DOCUMENTS
00500 Agreement Forms
00510 Notice of Award
00520 Agreement
00530 Notice to Proceed
00600 Bonds and Certificates
00610 Performance Bond
00615 Payment Bond
00630 Certificate of Insurance
00635 Certificate of Substantial Completion
00640 Certificate of Final Acceptance
00650 Lien Waiver Release (Contractor)
00660 Consent of Surety 00660-1
00670 Application for Exemption Certificate
CONDITIONS OF THE CONTRACT
00700 General Conditions
Exhibit GC-A GC-A1 - GC-A2
00800 Supplementary Conditions
00900 Addenda, Modifications, and Payment
00950 Contract Change Order
00960 Application for Payment
EXHIBIT A – 100% DESIGN PLANS DATED FEBRUARY 2023
EXHIBIT B – SPECIFICATIONS DATED FEBRUARY 7, 2023
EXHIBIT C – DRAINAGE MEMO JANUARY 2023
SECTION 00020
INVITATION TO BID
SECTION 00020
INVITATION TO BID
9767 PFA Training Facility Parking Lot Addition
BID DUE: 3:00 PM MT (MT our clock), March 22, 2023
As part of the City’s commitment to sustainability, sealed Bids must be submitted online through
the Rocky Mountain E-Purchasing System (RMEPS) at http://bidnetdirect.com/colorado/city-
of-fort-collins.
Public Bid Opening: The bid opening will be conducted by video conference per the following
information. At said place and time, and promptly thereafter, all Bids that have been duly
received will be publicly opened and read aloud. To access the public Bid opening, please
follow the link to join the Microsoft Teams meeting:
Click here to join the meeting
https://teams.microsoft.com/l/meetup-
join/19%3ameeting_YTgxZGViMzMtMDhiNy00NzUyLWFmYTItMWVkMjFmMzMxNTY4%
40thread.v2/0?context=%7b%22Tid%22%3a%2247fa2f5f-0d0a-4a68-b431-
6d1a27b66660%22%2c%22Oid%22%3a%2237299b31-8a43-4b66-8642-
b5358a21cda9%22%7d
Alternatively, the bid opening can be accessed via phone. This option will only allow you
to hear the audio presentation.
Call in #: 1 970-628-0892
Phone Conference ID: 496 481 015#
The Contract Documents provide for the construction of Bid 9767 PFA Training Facility Parking
Lot Addition. The work to be performed under this contract generally consists of the
construction of a new parking lot and associated access road at the Poudre Fire Authority
Training Center. Major construction items include construction surveying, erosion control,
earthwork, reinforced concrete pipe installation, aggregate base course construction, concrete
flatwork and curb/gutter, asphalt paving, signing and striping, seeding, mulching and final
stabilization.
This contract has a floating start date provision which allows the Contractor to choose the start
date between the period of July 10th, 2023, and July 24th, 2023. Substantial completion of the
Work shall occur within thirty (30) working days following the issuance of the Notice to Proceed.
The Contractor will be responsible for supplying all labor, materials, and equipment necessary
to complete the Work in accordance with the project plans and specifications. The total
quantities and type of work in the Bid Schedule is representative of the estimated quantities;
however, these quantities may be revised by the PFA to represent actual field conditions at the
time of construction.
The City encourages all disadvantaged business enterprises to submit bid in response to all
invitations and will not be discriminated against on the grounds of race, color, national origin.
A pre-bid meeting will be held at 2:00 PM Mountain Time on March 8, 2023. The pre-bid
meeting will be hosted on-line via Microsoft Teams. Select or copy/paste the below link
into your browser for access to the meeting. Please be prepared to record your name and
company in the chat window upon request and mute your microphone:
Click here to join the meeting
https://teams.microsoft.com/l/meetup-
join/19%3ameeting_ZGRhMmM1MWYtYzIwOC00N2FhLWJmZjctOWEyMTVmNzVjZDM1
%40thread.v2/0?context=%7b%22Tid%22%3a%2247fa2f5f-0d0a-4a68-b431-
6d1a27b66660%22%2c%22Oid%22%3a%2237299b31-8a43-4b66-8642-
b5358a21cda9%22%7d
Alternatively, the pre-bid meeting can be accessed via phone. This option will only allow
you to hear the audio presentation.
Call-in number: 1 970-628-0892
Conference ID: 152 308 415#
Prospective Bidders are invited to present their questions relative to this Bid proposal at this
meeting.
Questions concerning the scope of the bid should be directed to Tyson Barela, Project Manager,
at (970) 221-6244 or Tyson.barela@poudre-fire.org.
Questions regarding bid submittal or process should be directed to Adam Hill, Senior Buyer, at
(970) 221-6777 or adhill@fcgov.com.
All questions must be submitted in writing via email to Tyson Barela, with a copy to
Adam Hill, no later than 3:00 PM our clock on March 13, 2023. Questions received after this
deadline will not be answered.
The Contract Documents and Construction Drawings may be examined online at:
http://www.bidnetdirect.com/colorado/city-of-fort-collins
Bids will be received as set forth in the Bidding Documents.
The Work is expected to be commenced within the time as required by Section 2.3 of General
Conditions. Substantial Completion of the Work is required as specified in the Agreement.
The successful Bidder will be required to furnish a Performance Bond and a Payment Bond
guaranteeing faithful performance and the payment of all bills and obligations arising from the
performance of the Contract.
No Bid may be withdrawn within a period of forty-five (45) days after the date fixed for opening
Bids.
The OWNER reserves the right to reject any and all Bids, and to waive any informalities and
irregularities therein.
Bid security in the amount of not less than 5% of the total Bid must accompany each Bid in the
form specified in the Instructions to Bidders.
Sales Prohibited/Conflict of Interest: No officer, employee, or member of City Council, shall have
a financial interest in the sale to the City of any real or personal property, equipment, material,
supplies or services where such officer or employee exercises directly or indirectly any decision-
making authority concerning such sale or any supervisory authority over the services to be
rendered. This rule also applies to subcontracts with the City. Soliciting or accepting any gift,
gratuity favor, entertainment, kickback or any items of monetary value from any person who has
or is seeking to do business with the City of Fort Collins is prohibited.
City of Fort Collins
Gerry Paul
Purchasing Director
Bidder Name:
SECTION 00100
INSTRUCTIONS TO BIDDERS
Bidder Name:
SECTION 00100
INSTRUCTIONS TO BIDDERS
1.0 DEFINED TERMS
Terms used in these Instructions to Bidders which are defined in the Standard General Conditions of
the Construction Contract (No. 1910-8, 1990 ed.) have the meanings assigned to them in the General
Conditions. The term "Bidder" means one who submits a Bid to OWNER, as distinct from a sub-bidder,
who submits a Bid to Bidder. The terms "Successful Bidder" means the lowest, qualified, responsible
and responsive Bidder to whom OWNER (on basis of OWNER's evaluation as hereinafter provided)
makes an award. The term "Bidding Documents" includes the Advertisement or Invitation to Bid,
Instructions to Bidders, the Bid Form, and the proposed Contract Documents (including all Addenda
issued prior to receipt of Bids).
2.0 COPIES OF BIDDING DOCUMENTS
2.1. Complete sets of Bidding Documents may be obtained as stated in the Invitation to Bid. No partial
sets will be issued. The Bidding Documents may be examined at the locations identified in the
Invitation to Bid.
2.2. Complete sets of Bidding Documents shall be used in preparing Bids; neither OWNER nor
Engineer assumes any responsibility for errors or misinterpretations resulting from the use of
incomplete sets of Bidding Documents.
2.3. The submitted Bid proposal shall include Sections 00300, 00410, 00420, and 00430 fully
executed.
2.4. OWNER and Engineer, in making copies of Bidding Documents available on the above terms, do
so only for the purpose of obtaining Bids on the Work and do not confer a license or grant for any
other use.
3.0 QUALIFICATION OF BIDDERS
3.1 To demonstrate qualifications to perform the Work, each Bidder must submit at the time of the Bid
opening, a written statement of qualifications including financial data, a summary of previous
experience, previous commitments and evidence of authority to conduct business in the
jurisdiction where the Project is located. Each Bid must contain evidence of Bidder's qualification
to do business in the state where the Project is located or covenant to obtain such qualification
prior to award of the contract. The Statement of Qualifications shall be prepared on the form
provided in Section 00420.
3.2. In accordance with Section 8-160 of the Code of the City of Fort Collins in determining whether a
bidder is responsible, the following shall be considered: (1) The ability, capacity and skill of the
bidder to perform the contract or provide the services required, (2) whether the bidder can perform
the contract or provide the service promptly and within the time specified without delay or
interference, (3) the character, integrity, reputation, judgment, experience and efficiency of the
bidder, (4) the quality of the bidder's performance of previous contracts or services, (5) the
previous and existing compliance by the bidder with laws and ordinances relating to the contract
or service, (6) the sufficiency of the financial resources and ability of the bidder to perform the
contract or provide the service, (7) the quality, availability and adaptability of the materials and
services to the particular use required, (8) the ability of the bidder to provide future maintenance
and service for the use of the subject of the contract, and (9) any other circumstances which will
affect the bidder's performance of the contract.
3.3. Each Bidder may be required to show that he has handled former Work so that no just claims are
pending against such Work. No Bid will be accepted from a Bidder who is engaged on any other
Work which would impair his ability to perform or finance this Work.
3.4 No Bidder shall be in default on the performance of any other contract with the City or in the
payment of any taxes, licenses or other monies due to the City.
Bidder Name:
4.0 EXAMINATION OF CONTRACT DOCUMENTS AND SITE
4.1. It is the responsibility of each Bidder, before submitting a Bid, to (a) examine the Contract
Documents thoroughly, (b) visit the site to familiarize himself with local conditions that may in any
manner affect cost, progress or performance of the Work, (c) familiarize himself with federal, state
and local laws, ordinances, rules and regulations that may in any manner affect cost, progress or
performance of the Work, (d) study and carefully correlate Bidder's observations with the Contract
Documents, and (e) notify Engineer of all conflicts, errors or discrepancies in the Contract
Documents.
4.2. Reference is made to the Supplementary Conditions for identification of: Subsurface and Physical
Conditions SC-4.2.
4.3. The submission of a Bid will constitute an incontrovertible representation by Bidder that Bidder
has complied with every requirement of this Article 4, that without exception the Bid is premised
upon performing and furnishing the Work required by the Contract Documents and such means,
methods, techniques, sequences or procedures of construction as may be indicated in or required
by the Contract Documents, and that the Contract Documents are sufficient in scope and detail to
indicate and convey understanding of all terms and conditions for performance and furnishing of
the Work.
5.0 INTERPRETATIONS AND ADDENDA.
5.1. All questions about the meaning or intent of the Bidding Documents are to be submitted in writing
to the Engineer and the OWNER. Interpretation or clarifications considered necessary in response
to such questions will be issued only by Addenda. Questions received less than seven days prior
to the date for opening of the Bids may not be answered. Only questions answered by formal
written Addenda will be binding. Oral and other interpretations or clarifications will be without legal
effect.
5.2. All questions concerning the scope of this project should be directed to the Engineer. Questions
regarding submittal of bids should be directed to the City of Fort Collins' Purchasing Division.
5.3. Addenda may also be issued to modify the Bidding Documents as deemed advisable by OWNER
or Engineer.
5.4. Addenda will be mailed or delivered to all parties recorded by the OWNER as having received the
Bidding documents.
6.0 BID SECURITY
6.1. Each Bid must be accompanied by Bid Security made payable to OWNER in the amount stated in
the Invitation to Bid. The required security must be in the form of a certified or bank cashier's
check payable to OWNER or a Bid Bond on the form enclosed herewith. The Bid Bond must be
executed by a surety meeting the requirements of the General Conditions for surety bonds.
6.2. The Bid Security of the successful Bidder will be retained until such Bidder has executed the
Agreement and furnished the required contract security, whereupon Bid Security will be returned.
If the successful Bidder fails to execute and deliver the Agreement and furnish the required
contract security within 15 days of the Notice of Award, OWNER may annul the Notice of Award
and the Bid Security of that Bidder will be forfeited. The Bid Security of other Bidders whom
OWNER believes to have reasonable chance receiving the award may be retained by OWNER
until the earlier of the seventh day after the effective date of the Agreement or the thirty-first day
after the Bid Opening, whereupon Bid Security furnished by such Bidders will be returned. Bid
Security with Bids which are not competitive will be returned within seven days after the Bid
opening.
Bidder Name:
7.0 CONTRACT TIME.
The number of days within which, or the date by which the Work is to be substantially complete and
also completed and ready for Final Payment (the Contract Times) are set forth in the Agreement.
8.0 LIQUIDATED DAMAGES.
Provisions for liquidated damages are set forth in the Agreement.
9.0 SUBSTITUTE ("OR EQUAL") MATERIAL AND EQUIPMENT
The Contract, if awarded, will be on the basis of material and equipment described on the Drawings or
specified in the Specifications without consideration of possible substitute or "or equal" items.
Whenever it is indicated on the Drawings or specified in the Specifications that a substitute or "or
equal" item of material or equipment may be furnished or used by CONTRACTOR if acceptable to
Engineer, application for such acceptance will not be considered by Engineer until after the "effective
date of the Agreement". The procedure for submittal of any such application by CONTRACTOR and
consideration by Engineer is set forth in the General Conditions which may be supplemented in the
General Requirements.
10.0 SUBCONTRACTORS, SUPPLIERS AND OTHERS
10.1. Each Bidder shall submit at the Bid opening to OWNER a list of principal subcontractors he
proposes to use in the Work. Refer to Section 00430 contained within these Documents.
10.2. If OWNER or Engineer after due investigation has reasonable objection to any proposed
Subcontractor, either may, before the Notice of Award is given, request the apparent successful
Bidder to submit an acceptable substitute without an increase in Bid price. If the apparent
successful Bidder declines to make any substitution, OWNER may award the contract to the next
lowest responsive and responsible Bidder that proposes to use acceptable subcontractors.
Subcontractors, suppliers, other persons or organization listed and to whom OWNER or
Engineer does not make written objection prior to the giving of the Notice of Award will be
deemed acceptable to OWNER and ENGINEER subject to revocation of such acceptance after
the effective date of the Agreement as provided in the General Conditions.
10.3. CONTRACTOR shall not be required to employ any subcontractor, supplier or other persons or
organizations against whom he has reasonable objection. The use of subcontractors listed by the
Bidder and accepted by OWNER prior to the Notice of Award will be required in the performance
of the Work.
11.0 BID FORM.
11.1. A copy of the Bid Form is bound in the Contract Documents which may be retained by the
Bidder. A separate unbound copy is enclosed for submission with the Bid.
11.2. Bid Forms must be complete in ink or typed. All lump sum prices on the form must be stated in
words and numerals; in case of conflict, words will take precedence. Unit prices shall govern over
extensions of sums.
11.3. Bids by corporations must be executed in the corporate name by the president or a vice-
president (or other appropriate officer accompanied by evidence of authority to sign) and the
corporate seal shall be affixed and attested by the secretary or an assistant secretary. The
corporate address and state of incorporation shall be shown below the corporate name.
11.4. Bids by partnerships must be executed in the partnership name and signed by a partner, his title
must appear under his signature and the official address of the partnership must be shown below
the signature.
11.5. Bids by joint venture shall be signed by each participant in the joint venture or by an authorized
agent of each participant. The full name of each person or company interested in the Bid shall be
listed on the Bid Form.
Bidder Name:
11.6. The Bid shall contain an acknowledgement of receipt of all Addenda (the numbers of which must
be filled in on the Bid Form).
11.7. No alterations in Bids, or in the printed forms therefore, by erasures, interpolations, or otherwise
will be acceptable unless each such alteration is signed or initialed by the Bidder; if initialed,
OWNER may require the Bidder to identify any alteration so initialed.
11.8. The address and telephone number for communications regarding the Bid shall be shown.
12.0 BID PRICING.
Bids must be priced as set forth in the Bid Schedule or Schedules.
Bidder Name:
13.0 SUBMISSION OF BIDS.
13.1. Bids shall be submitted at the time and place indicated in the Invitation to Bid and shall be
enclosed in an opaque sealed envelope marked with the Project title, Bid No., and name and
address of the Bidder and accompanied by the Bid Security, Bid Form, Bid Bond, Statement of
Bidders Qualifications, and Schedule of Subcontractors as required in Section 00430. If the Bid is
sent through the mail or other delivery system, the sealed envelope shall be enclosed in a
separate envelope with the notation "BID ENCLOSED" on the face of it.
13.2. Bids shall be deposited at the designated location prior to the time and date for receipt of Bids
indicated in the Invitation to Bid, or any extension thereof made by addendum. Bids received
after the time and date for receipt of Bids will be returned unopened. Bidder shall assume full
responsibility for timely delivery at the location designated for receipt of Bids.
13.3. Oral, telephonic, telegraphic, or facsimile Bids are invalid and will not receive consideration.
13.4. No Bidder may submit more than one Bid. Multiple Bids under different names will not be
accepted from one firm or association.
14.0 MODIFICATION AND WITHDRAWAL OF BIDS.
14.1. Bids may be modified or withdrawn by an appropriate document duly executed (in a manner that
a Bid must be executed) and delivered to the place where Bids are to be submitted at any time
prior to the opening of Bids.
14.2. Bids may also be modified or withdrawn in person by the Bidder or an authorized representative
provided he can prove his identity and authority at any time prior to the opening of Bids.
14.3. Withdrawn Bids may be resubmitted up to the time designated for the receipt of Bids provided
that they are then fully in conformance with these Instructions to Bidders.
15.0 OPENINGS OF BIDS.
Bids will be opened and (unless obviously non-responsive) read aloud publicly as indicated in the
Invitation to Bid. An abstract of the amounts of the Base Bids and major alternates (if any) will be
made available after the opening of Bids.
16.0 BIDS TO REMAIN OPEN SUBJECT TO ACCEPTANCE.
All Bids shall remain open for forty-five (45) days after the day of the Bid Opening, but OWNER may,
in his sole discretion, release any Bid and return the Bid Security prior to that date.
17.0 AWARD OF CONTRACT.
17.1. OWNER reserves the right to reject any and all Bids, to waive any and all informalities not
involving price, time or changes in the Work, to negotiate contract terms with the Successful
Bidder, and the right to disregard all nonconforming, nonresponsive, unbalanced or conditional
Bids. Also, OWNER reserves the right to reject the Bid of any Bidder if OWNER believes that it
would not be in the best interest of the Project to make an award to that Bidder, whether because
the Bid is not responsive or the Bidder is unqualified or of doubtful financial ability or fails to meet
any other pertinent standard or criteria established by OWNER. Discrepancies between the
indicated sum of any column of figures and the correct sum thereof will be resolved in favor of
the correct sum.
17.2. In evaluating Bids, OWNER will consider the qualifications of the Bidders, whether or not the
Bids comply with the prescribed requirements, and such alternates, unit prices and other data, as
may be requested in the Bid Form or prior to the Notice of Award.
17.3. OWNER may consider the qualification and experience of Subcontractors, Suppliers, and other
persons and organizations proposed for those portions of the Work as to which the identity of
Subcontractors, Suppliers, and other persons and organizations is submitted as requested by
Bidder Name:
OWNER. OWNER also may consider the operating costs, maintenance requirements,
performance data and guarantees of major items of materials and equipment proposed for
incorporation in the Work when such data is required to be submitted prior to the Notice of
Award.
17.4. OWNER may conduct such investigations as OWNER deems necessary to assist in the
evaluation of any Bid and to establish the responsibility, qualifications and financial ability of the
Bidder's proposed Subcontractors, Suppliers and other persons and organizations to do the
Work in accordance with the Contract Documents to OWNER's satisfaction within the prescribed
time.
17.5. If the Contract is to be awarded, it will be awarded to the lowest responsive and responsible
Bidder whose evaluation by OWNER indicates to OWNER that the award will be in the best
interest of the OWNER. Award shall be made on the evaluated lowest base bid excluding
alternates. The basis for award shall be the lowest Bid total for the Schedule or, in the case of
more than one schedule, for sum of all schedules. Only one contract will be awarded.
17.6. If the Contract is to be awarded, OWNER will give the Successful Bidder a Notice of Award
within forty-five (45) days after the date of the Bid opening.
18.0 CONTRACT SECURITY.
The General Conditions and the Supplementary Conditions set forth OWNER's requirements as to
performance and other Bonds. When the Successful Bidder delivers the executed Agreement to the
OWNER, it shall be accompanied by the required Contract Security.
19.0 SIGNING OF AGREEMENT.
When OWNER gives a Notice of Award to the Successful Bidder, it will be accompanied by the
required number of unsigned counterparts of the Agreement with all other written Contract Documents
attached. Within fifteen (15) days thereafter, CONTRACTOR shall sign and deliver the required
number of counterparts of the Agreement and attached documents to OWNER with the required
Bonds. Within ten (10) days thereafter, OWNER hall deliver one fully signed counterpart to
CONTRACTOR. Each counterpart is to be accompanied by a complete set of the Drawings with
appropriate identification.
Bidder Name:
20.0 TAXES.
OWNER is exempt from Colorado State Sales and Use Taxes on materials and equipment to be
incorporated in the Work. Said taxes shall not be included in the Contract Price. Reference is made to
the General and Supplementary Conditions.
21.0 RETAINAGE.
Provisions concerning retainage are set forth in the Agreement.
22.0 PURCHASING RESTRICTIONS.
Purchasing restrictions: The Bidder's authorized signature of this Bid assures the Bidder's compliance
with the City's purchasing restrictions. A copy of the resolutions is available for review in the
Purchasing and Risk Management Division or the City Clerk's office.
A. Cement Restrictions: City of Fort Collins Resolution 91-121 requires that suppliers and
producers of cement or products containing cement to certify that the cement was not made
in cement kilns that burn hazardous waste as a fuel.
23.0 COLLUSIVE OR SHAM BIDS.
Any Bid deemed by the City in its sole discretion to be a collusive or sham Bid will be rejected and
reported to authorities as such. Your authorized signature of this Bid assures that such Bid is genuine
and is not a collusive or sham Bid.
24.0 BID RESULTS.
Bid results will be posted at http://www.bidnetdirect.com/colorado/city-of-fort-collins.
END OF SECTION
Bidder Name:
SECTION 00300
BID FORM
Bidder Name:
SECTION 00300
BID FORM
PROJECT: 9767 PFA Training Facility Parking Lot Addition
Place:
Date:
1. In compliance with your Invitation to Bid dated , 20 and subject to all conditions
thereof, the undersigned a (Corporation, Limited Liability Company, Partnership, Joint Venture, or Sole
Proprietor) authorized to do business in the State of Colorado hereby proposes to furnish and do
everything required by the Contract Documents to which this refers for the construction of all items
listed on the following Bid Schedule or Bid Schedules.
2. The undersigned Bidder does hereby declare and stipulate that this proposal is made in good faith,
without collusion or connection with any other person or persons Bidding for the same Work, and that
it is made in pursuance of and subject to all the terms and conditions of the Invitation to Bid and
Instructions to Bidders, the Agreement, the detailed Specifications, and the Drawings pertaining to the
Work to be done, all of which have been examined by the undersigned.
3. Accompanying this Bid is a certified or cashier's check or standard Bid bond in the sum of
($ ) in accordance with the Invitation To Bid and Instructions to Bidders.
4. The undersigned Bidder agrees to execute the Agreement and a Performance Bond and a Payment
Bond for the amount of the total of this Bid within fifteen (15) calendar days from the date when the
written notice of the award of the contract is delivered to him at the address given on this Bid. The
name and address of the corporate surety with which the Bidder proposes to furnish the specified
performance and payment Bonds is as follows:
.
5. All the various phases of Work enumerated in the Contract Documents with their individual jobs and
overhead, whether specifically mentioned, included by implication or appurtenant thereto, are to be
performed by the CONTRACTOR under one of the items listed in the Bid Schedule, irrespective of
whether it is named in said list.
6. Payment for Work performed will be in accordance with the Bid Schedule or Bid Schedules subject to
changes as provided in the Contract Documents.
7. The undersigned Bidder hereby acknowledges receipt of Addenda No. through .
8. BID SCHEDULE (Base Bid)
Bidder Name:
BID SCHEDULE
9767 POUDRE FIRE AUTHORITY TRAINING
CENTER PARKING LOT IMPROVEMENTS
All bids shall be submitted on this form. Submit your unit and total prices for the work listed below.
ITEM
NO.
CDOT
ITEM NO. BID
ITEM
UNIT QUANTITY UNIT
PRICE TOTAL ITEM
1 201-00000 Clearing & Grubbing LS 1
2 202-00010 Removal of Tree EACH 3
3 203-00060 Embankment Material (Complete in Place) CY 1,170
4 203-02330 Laborer HR 10
5 207-00205 Topsoil CY 150
6 208-00002 Erosion Log Type 1 (12 Inch) LF 125
7 208-00020 Silt Fence LF 1,500
8 208-00035 Aggregate Bag LF 50
9 208-00045 Concrete Washout Structure EACH 1
10 208-00070 Vehicle Tracking Pad EACH 1
11 208-00106 Sweeping (Sediment Removal) HR 10
12 208-00207 Erosion Control Management DAY 10
13 212-00006 Seeding (Native) ACRE 0.30
14 212-00032 Soil Conditioning ACRE 0.30
15 213-00002 Mulching (Weed Free Hay) ACRE 0.30
16 213-00061 Mulch Tackifier LB 60
17 216-00041 Soil Retention Blanket (Straw/Coconut)
(Biodegradable Class 1) SY 210
18 304-06000 Aggregate Base Course (Class 6) TON 1,053
19 304-09106 Aggregate Base Course (Crushed Concrete)
(Install Only) CY 145
20 306-01000 Reconditioning SY 3,935
21 403-34721 Hot Mix Asphalt (Grading SX) (75) (PG 58-28) TON 750
22 412-00600 Concrete Pavement (6 Inch) SY 34
23 506-00206 Riprap (6 Inch) CY 2
24 603-02185 23x14 Inch Reinforced Concrete Pipe
(Complete-In-Place) LF 32
25 603-05118 23x14 Inch Reinforced Concrete End Section
(Elliptical) EACH 2
Bidder Name:
BID SCHEDULE
POUDRE FIRE AUTHORITY TRAINING CENTER
PARKING LOT IMPROVEMENTS
All bids shall be submitted on this form. Submit your unit and total prices for the work listed below
ITEM
NO.
CDOT
ITEM NO. BID ITEM UNIT QUANTITY UNIT
PRICE TOTAL ITEM
26 607-11525 Fence (Plastic) LF 75
27 608-00010 Concrete Apron EACH 1
28 609-21010 Curb and Gutter (Vertical) (1 Foot) LF 245
29 614-00010 Sign Panel (Class I) SF 3
30 614-00216 Steel Sign Post (2x2 Inch Tubing) LF 10
31 614-00218 Steel Sign Post (2.25x2.25 Inch Tubing) LF 3
32 620-00020 Sanitary Facility EACH 1
33 623-09900 Sprinkler System (Reset) LS 1
34 625-00000 Construction Surveying LS 1
35 626-00000 Mobilization LS 1
36 627-00001 Pavement Marking Paint GAL 8
BASE BID TOTAL:
TOTAL IN WORDS:
FORCE ACCOUNTS TOTAL: $12,000.00
TOTAL BID (BASE + FORCE ACCOUNTS):
Force Accounts
700-70010 F/A Minor Contract Revisions F.A. 1 $10,000
700-70320 F/A Sprinklers F.A. 1 $2,000
Bidder Name:
9. PRICES
The foregoing prices shall include all labor, materials, transportation, shoring, removal,
dewatering, overhead, profit, insurance, etc., to cover the complete Work in place of the
several kinds called for.
Bidder acknowledges that the OWNER has the right to delete items in the Bid or change
quantities at his sole discretion without affecting the Agreement or prices of any item so
long as the deletion or change does not exceed twenty-five percent (25%) of the total
Agreement Price.
RESPECTFULLY SUBMITTED:
CONTRACTOR
BY:
Printed Date
Title
License Number (If Applicable)
(Seal - if Bid is by corporation)
Attest:
Address
Telephone
Email
Bidder Name:
SECTION 00400
SUPPLEMENTS TO BID FORMS
00410 Bid Bond
00420 Statement of Bidder's Qualifications
00430 Schedule of Subcontractors
Bidder Name:
SECTION 00410
BID BOND
KNOW ALL MEN BY THESE PRESENTS: that we, the undersigned
as Principal, and , as Surety, are hereby held and firmly bound
unto the Poudre Fire Authority, as OWNER, in the sum of $
for the payment of which, well and truly to be made, we hereby jointly and severally bind
ourselves, successors, and assigns.
THE CONDITION of this obligation is such that whereas the Principal has submitted to the
Poudre Fire Authority the accompanying Bid and hereby made a part hereof to enter into a
Construction Agreement for the construction of Project, 9767 PFA Training Facility Parking Lot
Addition.
NOW THEREFORE,
(a) If said Bid shall be rejected, or
(b) If said Bid shall be accepted and the Principal shall execute and deliver a Contract in the
form of Contract attached hereto (properly completed in accordance with said Bid) and
shall furnish a BOND for his faithful performance of said Contract, and for payment of all
persons performing labor or furnishing materials in connection therewith, and shall in all
other respects perform the Agreement created by the acceptance of said Bid, then this
obligation shall be void; otherwise the same shall remain in force and effect, it being
expressly understood and agreed that the liability of the Surety for any and all claims
hereunder shall, in no event, exceed the penal amount of this obligation as herein
stated.
The Surety, for value received, hereby stipulates and agrees that the obligations of said Surety
and its BOND shall be in no way impaired or affected by any extension of the time within which
the OWNER may accept such Bid; and said Surety does hereby waive notice of any such
extension.
Surety Companies executing bonds must be authorized to transact business in the State of
Colorado and be accepted by the OWNER.
Bidder Name:
IN WITNESS WHEREOF, the Principal and the Surety have hereunto set their hands and seals
this day of , 20__, and such of them as are corporations have caused
their corporate seals to be hereto affixed and these presents to be signed by their proper
officers, the day and year first set forth above.
PRINCIPAL SURETY
Name:
Address:
By: By:
Title: Title:
ATTEST:
By:
(SEAL) (SEAL)
Bidder Name:
SECTION 00420
STATEMENT OF BIDDER'S QUALIFICATIONS
All questions must be answered and the data given must be clear and comprehensive. This
statement must be notarized. If necessary, questions may be answered on separate attached
sheets. The Bidder may submit any additional information he desires.
1. Name of Bidder:
2. Permanent main office address:
3. When organized:
4. If a corporation, where incorporated:
5. How many years have you been engaged in the contracting business under your present
firm or trade name?
6. Contracts on hand: (Schedule these, showing the amount of each contract and the
appropriate anticipated dates of completion.)
7. General character of Work performed by your company:
8. Have you ever failed to complete any Work awarded to you?
If so, where and why?
9. Have you ever defaulted on a contract?
Bidder Name:
If so, where and why?
10. Are you debarred by any government agency?
If yes list agency name.
11. List the more important projects recently completed by your company, stating the
approximate cost of each, and the month and year completed, location and type of
construction.
12. List your major equipment available for this contract.
13. Experience in construction Work similar in importance to this project:
14. Background and experience of the principal members of your organization, including
officers:
Bidder Name:
15. Credit available: $
16. Bank Reference:
17. Will you, upon request, fill out a detailed financial statement and furnish any other
information that may be required by the OWNER?
18. Are you licensed as a General Contractor?
If yes, in what city, county and state?
What class, license and numbers?
19. Do you anticipate subcontracting Work under this Contract?
If yes, what percent of total contract?
And to whom?
20. Are any lawsuits pending against you or your firm at this time?
IF yes, DETAIL
21. What are the limits of your public liability? DETAIL
What company?
22. What are your company's bonding limitations?
Bidder Name:
23. The undersigned hereby authorizes and requests any person, firm or corporation to
furnish any information requested by the OWNER in verification of the recital comprising
this Statement of Bidder's Qualifications.
Dated at ________________ this ______ day of __________________, 20__.
Company:
By: Printed:
Title:
State of
County of
being duly sworn deposes and says that he
is of
(Name) (Organization)
and that the answers to the foregoing questions and all statements therein contained are true
and correct.
Subscribed and sworn to before me this _______ day of____________, 20__.
(Seal)
Notary Public
My commission expires: .
Bidder Name:
SECTION 00430
SCHEDULE OF SUBCONTRACTORS
List all subcontractors for the work items listed below and all subcontractors performing over
30% of the contract.
ITEM SUBCONTRACTOR
Bidder Name:
SECTION 00500
AGREEMENT FORMS
00510 Notice of Award
00520 Agreement
00530 Notice to Proceed
Bidder Name:
SECTION 00510
NOTICE OF AWARD
DATE: [Date]
TO: [Contractor]
PROJECT: 9767 PFA Training Facility Parking Lot Addition
OWNER: Poudre Fire Authority (PFA) (hereinafter referred to as "the OWNER")
You are hereby notified that your Bid dated [Contractor's Bid Date] for the above project has
been considered. You are the apparent successful Bidder and have been awarded an
Agreement for 9767 PFA Training Facility Parking Lot Addition.
The Price of your Agreement is ($ ).
Three (3) copies of each of the proposed Contract Documents (except Drawings) accompany
this Notice of Award. Three (3) sets of the Drawings will be delivered separately or otherwise
made available to you immediately.
You must comply with the following conditions precedent within fifteen (15) days of the date of
this Notice of Award, that is by [Date].
1. You must deliver to the OWNER three (3) fully executed counterparts of the Agreement
including all the Contract Documents. Each of the Contract Documents must bear your
signature on the cover of the page.
2. You must deliver with the executed Agreement the Contract Security (Bonds) as
specified in the Instructions to Bidders, General Conditions (Article 5.1) and
Supplementary Conditions.
Failure to comply with these conditions within the time specified will entitle OWNER to consider
your Bid abandoned, to annul this Notice of Award and to declare your Bid Security forfeited.
Within ten (10) days after you comply with those conditions, OWNER will return to you one (1)
fully-signed counterpart of the Agreement with the Contract Documents attached.
Poudre Fire Authority
OWNER
By:
Derek Bergsten, Fire Chief
Bidder Name:
SECTION 00520
AGREEMENT
THIS AGREEMENT is dated as of the [Day] day of [Month] in the year of 20[Year] and shall be
effective on the date this AGREEMENT is signed by the PFA.
Poudre Fire Authority (PFA) (hereinafter called OWNER) and
[Contractor] (hereinafter called CONTRACTOR)
OWNER and CONTRACTOR, in consideration of the mutual covenants hereinafter set forth,
agree as follows:
ARTICLE 1. WORK
CONTRACTOR shall complete all Work as specified or indicated in the Contract
Documents. The Project for which the Work under the Contract Documents may
be the whole or only a part is defined as the construction of the 9767 PFA
Training Facility Parking Lot Addition and is generally described in Section
01010.
ARTICLE 2. ENGINEER
The Project has been designed by J-U-B Engineers, Inc., who is hereinafter
called ENGINEER and who will assume all duties and responsibilities and will
have the rights and authority assigned to ENGINEER in the Contract Documents
in connection with completion of the Work in accordance with the Contract
Documents.
ARTICLE 3. CONTRACT TIMES
3.1 The Work shall be Substantially Complete within thirty (30) working days
after the date when the Contract Times commence to run as provided in the
General Conditions and completed and ready for Final Payment and
Acceptance in accordance with the General Conditions within five (5)
calendar days after the date when the Contract Times commence to run.
3.2. Liquidated Damages. OWNER and CONTRACTOR recognize that time is
of the essence of this Agreement and that OWNER will suffer financial loss
if the Work is not completed within the times specified in paragraph 3.1.
above, plus any extensions thereof allowed in accordance with Article 12 of
the General Conditions.
They also recognize the delays, expenses and difficulties involved in
proving in a legal preceding the actual loss suffered by OWNER if the Work
is not completed on time. Accordingly, instead of requiring any such proof,
OWNER and CONTRACTOR agree that as Liquidated damages for delay
(but not as penalty) CONTRACTOR shall pay OWNER the amounts set
forth hereafter.
1) Substantial Completion:
Two Hundred Fifty Dollars and Zero Cents ($250.00) for each calendar
day or fraction thereof that expires after the thirty (30) working day
Bidder Name:
period for Substantial Completion of the Work until the Work is
Substantially Complete.
2) Final Acceptance:
After Substantial Completion, Two Hundred Fifty Dollars and Zero
Cents ($250.00) for each calendar day or fraction thereof that expires
after the five (5) working day period for Final Payment and Acceptance
until the Work is ready for Final Payment and Acceptance.
ARTICLE 4. CONTRACT PRICE
4.1 OWNER shall pay CONTRACTOR for performance of the Work in
accordance with the Contract Documents in current funds as follows:
($ ), in accordance with Section 00300, attached and incorporated
herein by this reference.
ARTICLE 5. PAYMENT PROCEDURES
CONTRACTOR shall submit Applications for Payment in accordance with Article
14 of the General Conditions. Applications for Payment will be processed by
ENGINEER as provided in the General Conditions.
5.1. PROGRESS PAYMENTS. OWNER shall make progress payments on
account of the Contract Price on the basis of CONTRACTOR's Application
for Payment as recommended by ENGINEER, once each month during
construction as provided below. All progress payments will be on the basis
of the progress of the Work measured by the schedule of values
established in paragraph 2.6 of the General Conditions and in the case of
Unit Price Work based on the number of units completed, and in
accordance with the General Requirements concerning Unit Price Work.
5.1.1. Prior to Substantial Completion, Owner will be entitled to withhold as
contract retainage five percent (5%) of each progress payment, but, in each
case, less the aggregate of payments previously made and less such
amounts as ENGINEER shall determine, or OWNER may withhold, in
accordance with paragraph 14.7 of the General Conditions. If , in the sole
discretion of Owner, on recommendation of Engineer, Owner determines
that the character and progress of the Work have been satisfactory to
OWNER and ENGINEER, OWNER may determine that as long as the
character and progress of the Work remain satisfactory to them, there will
be no additional retainage on account of Work completed in which case the
remaining progress payments prior to Substantial Completion will be in an
amount equal to 100% of the Work completed. 95% of materials and
equipment not incorporated in the Work (but delivered, suitably stored and
accompanied by documentation satisfactory to OWNER as provided in
paragraph 14.2 of the General Conditions) may be included in the
application Section 00520 Page 3 for payment.
5.1.2. Upon Substantial Completion payment will be made in an amount
sufficient, if necessary, to increase total payments to CONTRACTOR to
95% of the Contract Price, less such amounts as ENGINEER shall
determine or OWNER may withhold in accordance with paragraph 14.7 of
the General Conditions or as provided by law.
Bidder Name:
5.2. FINAL PAYMENT. Upon Final Completion and Acceptance of the Work in
accordance with paragraph 14.13 of the General Conditions, OWNER shall
pay the remainder of the Contract Price as recommended by ENGINEER
as provided in said paragraph 14.13.
ARTICLE 6. CONTRACTOR'S REPRESENTATION
In order to induce OWNER to enter into this Agreement, CONTRACTOR makes
the following representations:
6.1. CONTRACTOR has familiarized himself with the nature and extent of the
Contract Documents, Work, site, locality, and with all local conditions and
Laws and Regulations that in any manner may affect cost, progress,
performance or furnishing of the Work.
6.2. CONTRACTOR has studied carefully all reports of explorations and tests of
subsurface conditions and drawings of physical conditions which are
identified in the Supplementary Conditions as provided in paragraph 4.2 of
the General Conditions.
6.3. CONTRACTOR has obtained and carefully studied (or assumes
responsibility for obtaining and carefully studying) all such examinations,
investigations, explorations, tests, reports, and studies (in addition to or to
supplement those referred to in paragraph 6.2 above) which pertain to the
subsurface or physical condition at or contiguous to the site or otherwise
may affect the cost, progress, performance or furnishing of the Work as
CONTRACTOR considers necessary for the performance or furnishing of
the Work at the Contract Price, within the Contract Times and in
accordance with the other terms and conditions of the Contract Documents,
including specifically the provisions of paragraph 4.2 of the General
Conditions; and no additional examinations, investigations, explorations,
tests, reports, studies or similar information or data are or will be required
by CONTRACTOR for such purposes.
6.4. CONTRACTOR has reviewed and checked all information and data shown
or indicated on the Contract Documents with respect to existing
Underground Facilities at or contiguous to the site and assumes
responsibility for the accurate location of said Underground Facilities. No
additional examinations, investigations, explorations, tests, reports, studies
or similar information or data in respect of said Underground Facilities are
or will be required by CONTRACTOR in order to perform and furnish the
Work at the Contract Price, within the Contract Times and in accordance
with the other terms and conditions of the Contract Documents, including
specifically the provision of paragraph 4.3. of the General Conditions.
6.5. CONTRACTOR has correlated the results of all such observations,
examinations, investigations, tests, reports and data with the terms and
conditions of the Contract Documents.
6.6. CONTRACTOR has given ENGINEER written notice of all conflicts, errors
or discrepancies that he has discovered in the Contract Documents and the
written resolution thereof by ENGINEER is acceptable to CONTRACTOR.
Bidder Name:
ARTICLE 7. CONTRACT DOCUMENTS
7.1 The Contract Documents which comprise the entire Agreement between
OWNER and CONTRACTOR concerning the Work consist of the General
Conditions, Supplementary Conditions, those items included in the
definition of “Contract Documents” in Article 1.10 of the General Conditions,
and such other items as are referenced in this Article 7, all of which are
incorporated herein by this reference.
7.2 Forms for use by CONTRACTOR in performing the Work and related
actions in carrying out the terms of this Agreement are deemed Contract
Documents and incorporated herein by this reference, and include, but are
not limited to, the following:
7.2.1 Certificate of Substantial Completion
7.2.2 Certificate of Final Acceptance
7.2.3 Lien Waiver Releases
7.2.4 Consent of Surety
7.2.5 Application for Exemption Certificate
7.2.6 Application for Payment
7.3 Drawings, consisting of a cover sheet and sheets numbered as follows:
100% Design Documents dated February 2023
The Contract Drawings shall be stamped "Final for Construction" and
dated. Any revisions made shall be clearly identified and dated.
7.4. Addenda Numbers to , inclusive.
7.5. The Contract Documents also include all written amendments and other
documents amending, modifying, or supplementing the Contract
Documents pursuant to paragraphs 3.5 and 3.6 of the General Conditions.
7.6. There are no Contract Documents other than those listed or incorporated
by reference in this Article 7. The Contract Documents may only be
amended, modified or supplemented as provided in paragraphs 3.5 and 3.6
of the General Conditions.
Bidder Name:
ARTICLE 8. MISCELLANEOUS
8.1. Terms used in this Agreement which are defined in Article I of the General
Conditions shall have the meanings indicated in the General Conditions.
8.2. No assignment by a party hereto of any rights under or interests in the
Contract Documents will be binding on another party hereto without the
written consent of the party sought to be bound; and specifically but not
without limitations, moneys that may become due and moneys that are due
may not be assigned without such consent (except to the extent that the
effect of this restriction may be limited by law), and unless specifically
stated to the contrary in any written consent to an assignment no
assignment will release or discharge that assignor from any duty or
responsibility under the Contract Document.
8.3. OWNER and CONTRACTOR each binds itself, its partners, successors,
assigns and legal representatives to the other party hereto, its partners,
successors, assigns and legal representatives in respect to all covenants,
Agreement and obligations contained in the Contract Document.
OWNER: POUDRE FIRE AUTHORITY (PFA) CONTRACTOR: [CONTRACTOR]
By: By:
Derek Bergsten, Fire Chief
Date:
PRINTED
CITY OF FORT COLLINS:
By:
GERRY PAUL Title:
PURCHASING DIRECTOR
Date: Date:
Attest: (CORPORATE SEAL)
City Clerk
Address for giving notices:
P. O. Box 580
Fort Collins, CO 80522 Attest:
Approved as to Form Address for giving notices:
Senior Assistant City Attorney
License No.:
Bidder Name:
SECTION 00530
NOTICE TO PROCEED
Description of Work: 9767 PFA Training Facility Parking Lot Addition
To: [Contractor]
This notice is to advise you:
That the contract covering the above described Work has been fully executed by the
CONTRACTOR and the OWNER.
That the required CONTRACTOR's Performance Bond and Payment Bond have been received
by the OWNER.
That the OWNER has approved the said Contract Documents.
Therefore, as the CONTRACTOR for the above described Work, you are hereby authorized and
directed to proceed within ( ) calendar days from receipt of this notice as
required by the Agreement.
Dated this day of , 20 .
The dates for Substantial Completion and Final Acceptance shall be , 20_ and
, 20__, respectively.
Poudre Fire Authority (PFA)
OWNER
By:
Title:
ACKNOWLEDGMENT OF NOTICE
Receipt of the above Notice to Proceed is hereby acknowledged this day of
, 20__.
CONTRACTOR: [Contractor]
By:
Title:
Bidder Name:
SECTION 00600
BONDS AND CERTIFICATES
00610 Performance Bond
00615 Payment Bond
00630 Certificate of Insurance
00635 Certificate of Substantial Completion
00640 Certificate of Final Acceptance
00650 Lien Waiver Release (CONTRACTOR)
00660 Consent of Surety
00670 Application for Exemption Certificate
Bidder Name:
SECTION 00610
PERFORMANCE BOND
Bond No.
KNOW ALL MEN BY THESE PRESENTS: that
(firm)
(address)
(an Individual), (a Partnership), (a Corporation), hereinafter referred to as the "Principal" and
(Firm)
(Address)
hereinafter referred to as "the Surety", are held and firmly bound unto Poudre Fire Authority,102
Remington St., Fort Collins, Colorado 80524 hereinafter referred to as the "OWNER", in the
penal sum of ($ ) in lawful money of the United States, for the payment of which
sum well and truly to be made, we bind ourselves, successors and assigns, jointly and
severally, firmly by these presents.
THE CONDITIONS OF THIS OBLIGATION are such that whereas the Principal entered into a
certain Agreement with the OWNER, dated the [Day] day of [Month] in the year of 20[Year], a
copy of which is hereto attached and made a part hereof for the performance of Poudre Fire
Authority Project, 9767 PFA Training Facility Parking Lot Addition.
NOW, THEREFORE, if the Principal shall well, truly and faithfully perform its duties, all the
undertakings, covenants, terms, conditions and agreements of said Agreement during the
original term thereof, and any extensions thereof which may be granted by the OWNER, with or
without Notice to the Surety and during the life of the guaranty period, and if the Principal shall
satisfy all claims and demands incurred under such Agreement, and shall fully indemnify and
save harmless the OWNER from all cost and damages which it may suffer by reason of failure
to do so, and shall reimburse and repay the OWNER all outlay and expense which the OWNER
may incur in making good any default then this obligation shall be void; otherwise to remain in
full force and effect.
PROVIDED, FURTHER, that the said Surety, for value received, hereby stipulates and agrees
that no change, extension of time, alteration or addition to the terms of the Agreement or to the
Work to be performed thereunder or the Specifications accompanying the same shall in any way
affect its obligation on this bond; and it does hereby waive notice of any such change, extension
of time, alteration or addition to the terms of the Agreement or to the Work or to the
Specifications.
PROVIDED, FURTHER, that no final settlement between the OWNER and the CONTRACTOR
shall abridge the right of any beneficiary hereunder, whose claim may be unsatisfied.
PROVIDED, FURTHER, that the Surety Company must be authorized to transact business in
the State of Colorado and be acceptable to the OWNER.
Bidder Name:
IN WITNESS WHEREOF, this instrument is executed in three (3) counterparts, each one of
which shall be deemed an original, this _____ day of _____ ____, 20__.
IN PRESENCE OF: Principal
(Title) (Title)
(Corporate Seal)
(Address)
IN PRESENCE OF: Other Partners
_____________________________ By:
_____________________________ By:
IN PRESENCE OF: Surety
_____________________________ By:_____________________________________
_____________________________
(Address)
(Surety Seal)
NOTE: Date of Bond must not be prior to date of Agreement. If CONTRACTOR is
Partnership, all partners should execute Bond.
Bidder Name:
SECTION 00615
PAYMENT BOND
Bond No.
KNOW ALL MEN BY THESE PRESENTS: that
(firm)
(address)
(an Individual), (a Partnership), (a Corporation), hereinafter referred to as the "Principal" and
(Firm)
(Address)
hereinafter referred to as "the Surety", are held and firmly bound unto Poudre Fire Authority,102
Remington St., Fort Collins, Colorado 80524 hereinafter referred to as the "OWNER", in the
penal sum of ($ ) in lawful money of the United States, for the payment of which
sum well and truly to be made, we bind ourselves, successors and assigns, jointly and
severally, firmly by these presents.
THE CONDITIONS OF THIS OBLIGATION are such that whereas the Principal entered into a
certain Agreement with the OWNER, dated the [Day] day of [Month] in the year of 20[Year], a
copy of which is hereto attached and made a part hereof for the performance of Poudre Fire
Authority Project, 9767 PFA Training Facility Parking Lot Addition.
NOW, THEREFORE, if the Principal shall make payment to all persons, firms, subcontractors,
and corporations furnishing materials for or performing labor in the prosecution of the Work
provided for in such Agreement and any authorized extension or modification thereof, including
all amounts due for materials, lubricants, repairs on machinery, equipment and tools,
consumed, rented or used in connection with the construction of such Work, and all insurance
premiums on said Work, and for all labor, performed in such Work whether by subcontractor or
otherwise, then this obligation shall be void; otherwise to remain in full force and effect.
PROVIDED, FURTHER, that the said Surety, for value received, hereby stipulates and agrees
that no change, extension of time, alteration or addition to the terms of the Agreement or to the
Work to be performed thereunder or the Specifications accompanying the same shall in any way
affect its obligation on this bond; and it does hereby waive notice of any such change, extension
of time, alteration or addition to the terms of the Agreement or to the Work or to the
Specifications.
PROVIDED, FURTHER, that no final settlement between the OWNER and the CONTRACTOR
shall abridge the right of any beneficiary hereunder, whose claim may be unsatisfied.
PROVIDED, FURTHER, that the Surety Company must be authorized to transact business in
the State of Colorado and be acceptable to the OWNER.
Bidder Name:
IN WITNESS WHEREOF, this instrument is executed in three (3) counterparts,
each one of which shall be deemed an original, this day of , 20__.
IN PRESENCE OF: Principal
(Title) (Title)
(Corporate Seal)
(Address)
IN PRESENCE OF: Other Partners
_____________________________ By:
_____________________________ By:
IN PRESENCE OF: Surety
_____________________________ By:_____________________________________
_____________________________
(Address)
(Surety Seal)
NOTE: Date of Bond must not be prior to date of Agreement. If CONTRACTOR is
Partnership, all partners should execute Bond.
Bidder Name:
SECTION 00630
CERTIFICATE OF INSURANCE
CONTRACTOR shall insert his own standard form for Certificate of Insurance in accordance
with the following requirements:
1. The Contractor will provide, from insurance companies acceptable to the PFA, the
insurance coverage designated hereinafter and pay all costs. Before commencing work
under this bid, the Contractor shall furnish the PFA with certificates of insurance showing
the type, amount, class of operations covered, effective dates and date of expiration of
policies, and containing substantially the following statement:
“The insurance evidenced by this Certificate will not reduce coverage or limits and
will not be cancelled, except after thirty (30) days written notice has been received
by the PFA.”
In case of the breach of any provision of the Insurance Requirements, the PFA, at its
option, may take out and maintain, at the expense of the Contractor, such insurance as
the PFA may deem proper and may deduct the cost of such insurance from any monies
which may be due or become due the Contractor under this Agreement. The PFA, its
officers, agents and employees shall be named as additional insureds on the Contractor
's general liability and automobile liability insurance policies for any claims arising out of
work performed under this Agreement.
Insurance certificates should show the certificate holder as follows:
City of Fort Collins AND Poudre Fire Authority
Purchasing Division 102 Remington Street
PO Box 580 Fort Collins, CO 80524
Fort Collins, CO 80522
The City and PFA, its officers, agents and employees shall be named as additional
insureds on the Service Provider 's general liability and automobile liability
insurance policies by marking the appropriate box or adding a statement to this
effect on the certificate, for any claims arising out of work performed under this
Agreement.
2. Insurance coverages shall be as follows:
A. Workers' Compensation & Employer's Liability. The Contractor shall maintain
during the life of this Agreement for all of the Contractor's employees engaged in
work performed under this agreement:
1. Workers' Compensation insurance with statutory limits as required by
Colorado law.
2. Employer's Liability insurance with limits of $100,000 per accident,
$500,000 disease aggregate, and $100,000 disease each employee.
B. Commercial General & Vehicle Liability. The Contractor shall maintain during the
life of this Agreement such commercial general liability and automobile liability
Bidder Name:
insurance as will provide coverage for damage claims of personal injury, including
accidental death, as well as for claims for property damage, which may arise
directly or indirectly from the performance of work under this Agreement.
Coverage for property damage shall be on a "broad form" basis. The amount of
insurance for each coverage, Commercial General and Vehicle, shall not be less
than $1,000,000 combined single limits for bodily injury and property damage.
In the event any work is performed by a subcontractor, the Contractor shall be responsible for
any liability directly or indirectly arising out of the work performed under this Agreement by a
subcontractor, which liability is not covered by the subcontractor's insurance
Bidder Name:
SECTION 00635
CERTIFICATE OF SUBSTANTIAL COMPLETION
TO: POUDRE FIRE AUTHORITY (PFA) (OWNER)
DATE OF SUBSTANTIAL COMPLETION: PROJECT TITLE: 9767 PFA Training
Facility Parking Lot Addition
PROJECT OR SPECIFIED PART SHALL LOCATION: Fort Collins, Colorado
INCLUDE:
OWNER: Poudre Fire Authority (PFA)
CONTRACTOR: [Contractor]
CONTRACT DATE: [Date]
The Work performed under this contract has been inspected by authorized representatives of
the OWNER, CONTRACTOR, and the ENGINEER and the project or specified part of the
project, as indicated above) is hereby declared to be substantially completed on the above date.
A tentative list of items to be completed or corrected is appended hereto. This list may not be
exhaustive, and the failure to include an item on it does not alter the responsibility of the
CONTRACTOR to complete all the Work in accordance with the Contract Documents.
ENGINEER AUTHORIZED REPRESENTATIVE
DATE
The CONTRACTOR accepts the above Certificate of Substantial Completion and agrees to
complete and correct the items on the tentative list within the time indicated.
CONTRACTOR AUTHORIZED REPRESENTATIVE
DATE
The OWNER accepts the project or specified area of the project as substantially complete and
will assume full possession of the project or specified area of the project at 12:01 a.m., on
. The responsibility for heat, utilities, security, and insurance under
the Contract Documents shall be as set forth under "Remarks" below.
POUDRE FIRE AUTHORITY (PFA) By:
OWNER AUTHORIZED REPRESENTATIVE
DATE
REMARKS:
Bidder Name:
SECTION 00640
CERTIFICATE OF FINAL ACCEPTANCE
, 20__
TO: [Contractor]
Gentlemen:
You are hereby notified that on the day of , 20__, Poudre Fire Authority,
has accepted the Work completed by [Contractor] for the Poudre Fire Authority project, 9767
PFA Training Facility Parking Lot Addition.
A check is attached hereto in the amount of $ as Final
Payment for all Work done, subject to the terms of the Contract Documents which are dated
[Contract Date].
In conformance with the Contract Documents for this project, your obligations and guarantees
will continue for the specified time from the following date:____________ _, 20__.
Sincerely,
OWNER: Poudre Fire Authority
By:
Title:
ATTEST:
Title:
Bidder Name:
SECTION 00650
LIEN WAIVER RELEASE
(CONTRACTOR)
TO: Poudre Fire Authority (OWNER)
FROM: [Contractor] (CONTRACTOR)
PROJECT: 9767 PFA Training Facility Parking Lot Addition
1. The CONTRACTOR acknowledges having received payment, except retainage from the
OWNER for all work, labor, skill and material furnished, delivered and performed by the
CONTRACTOR for the OWNER or for anyone in the construction, design, improvement,
alteration, addition or repair of the above described project.
2. In consideration of such payment and other good and valuable consideration, the receipt
and adequacy of which are hereby acknowledged, the CONTRACTOR voluntarily waives
all rights, claims and liens, including but not limited to, mechanic's liens, Miller Act claims
(40 U.S.C.A. 270 a and b), stop notices, equitable liens and labor and material bond rights
which the CONTRACTOR may now or may afterward have, claim or assert for all and any
work, labor, skill or materials furnished, delivered or performed for the construction,
design, improvement, alteration, addition or repair of the above described project, against
the OWNER or its officers, agents, employees or assigns, against any fund of or in the
possession or control of the OWNER, against the project or against all land and the
buildings on and appurtenances to the land improved by the project.
3. The CONTRACTOR affirms that all work, labor and materials, furnished, delivered or
performed to or for the construction, design, improvement, alteration, addition or repair of
the project were furnished, delivered or performed by the CONTRACTOR or its agents,
employees, and servants, or by and through the CONTRACTOR by various
Subcontractors or materialmen or their agents, employees and servants and further
affirms the same have been paid in full and have released in full any and all existing or
possible future mechanic's liens or rights or claims against the project or any funds in the
OWNER'S possession or control concerning the project or against the OWNER or its
officers, agents, employees or assigns arising out of the project.
4. The CONTRACTOR agrees to defend and hold harmless the OWNER, the lender, if any,
and the Surety on the project against and from any claim hereinafter made by the
CONTRACTOR'S Subcontractors, materialmen, employees, servants, agents or assigns
against the project or against the OWNER or its officers, employees, agents or assigns
arising out of the project for all loss, damage and costs, including reasonable attorneys
fees, incurred as a result of such claims.
5. The parties acknowledge that the description of the project set forth above constitutes and
adequate description of the property and improvements to which this Lien Waiver Release
pertains. It is further acknowledged that this Lien Waiver Release is for the benefit of and
may be relied upon by the OWNER, the lender, if any, and Surety on any labor and
material bonds for the project.
Bidder Name:
Signed this day of , 20__.
CONTRACTOR: [CONTRACTOR]
By:
Title:
ATTEST:
Secretary
STATE OF COLORADO )
)ss.
COUNTY OF LARIMER )
Subscribed and sworn to before me this day of 20__,
by .
Witness my hand and official seal.
Notary Public
My Commission Expires:
Bidder Name:
SECTION 00660
CONSENT OF SURETY
TO: Poudre Fire Authority (hereinafter referred to as the "OWNER")
CONTRACTOR: [Contractor]
PROJECT: 9767 PFA Training Facility Parking Lot Addition
CONTRACT DATE: [Date]
In accordance with the provisions of the Contract between the OWNER and the CONTRACTOR
as indicated above, for .
(Surety)
on bond of
hereby approves of the Final Payment to the CONTRACTOR, and agrees that Final Payment to
the CONTRACTOR shall not relieve the Surety Company of any of its obligations to the
OWNER, as set forth in the said Surety Company's Bond.
IN WITNESS WHEREOF, the Surety Company has hereunto set its hand this
day of , 20____ .
(Surety Company)
By:
ATTACH: Power of Attorney and Certificate of Authority of Attorney(s)-in-Fact.
SECTION 00670
APPLICATION FOR EXEMPTION CERTIFICATE
SECTION 00700
GENERAL CONDITIONS
SECTION 00800
SUPPLEMENTARY CONDITIONS
SECTION 00800
SUPPLEMENTARY CONDITIONS
Conditions of the Contract
These Supplementary Conditions amend or supplement the General Conditions of the
Construction Contract (EJCDC General Conditions 1910-8, 1990 edition with City of Fort Collins
modifications) and other provisions of the Contract Documents as indicated below.
SC-4.2 Subsurface and Physical Conditions:
A. Add the following language to paragraph 4.2.1 of the General Conditions.
4.2.1.1.1 The following report(s) of exploration and tests of subsurface conditions
at the site of the Work:
See contract exhibits A & C.
Contractor may rely upon the accuracy of the technical data contained in the
geotechnical documents, but not upon nontechnical data, interpretations or
opinions contained therein or upon the completeness of any information in the
report.
B. 4.2.1.2.1 No drawing of physical conditions in or relating to existing surface or
subsurface structures (except Underground Facilities referred to in Paragraph
4.3) which are at or contiguous to the site have been utilized by the Engineer in
preparation of the Contract Documents, except the following:
N/A
SC-5.4.8 Limits of Liability
A. Add the following language at the end of paragraph 5.4.8.
The limits of liability for the insurance required by the paragraph numbers of the
General Conditions listed below are as follows:
5.4.1 and 5.4.2
Coverage A - Statutory Limits
Coverage B - $100,000/$100,000/$500,000
5.4.3 and 5.4.5 Commercial General Liability policy will have limits of
$1,000,000 combined single limits (CSL). This policy will include coverage
for Explosion, Collapse, and Underground coverage unless waived by the
Owner.
5.4.6 The Comprehensive Automobile Liability Insurance policy will have
limits of $1,000,000 combined single limits (CSL).
5.4.9 This policy will include completed operations coverage/product
liability coverage with limits of $1,000,000 combined single limits (CSL).
SC-12.3 Add the following language to the end of paragraph 12.3.
Contractor will include in the project schedule zero (0) days lost due to abnormal
weather conditions. Contractor to provide written notification via email to Project
Manager Tyson Barela (Tyson.barela@poudre-fire.org ) within (48) hours for any
weather day claims including weather conditions of that day, site photos and a
description of critical activities impacted for the Projects Manager review and
approval.
SECTION 00900
ADDENDA, MODIFICATIONS AND PAYMENT
00950 Contract Change Order
00960 Application for Payment
SECTION 00950
CHANGE ORDER NO.
PROJECT TITLE: 9767 PFA Training Facility Parking Lot Addition
CONTRACTOR: [Contractor]
DESCRIPTION:
1. Reason for change:
2. Description of Change:
3. Change in Contract Cost:
4. Change in Contract Time:
ORIGINAL CONTRACT COST $ .00
TOTAL APPROVED CHANGE ORDER .00
TOTAL PENDING CHANGE ORDER .00
TOTAL THIS CHANGE ORDER .00
TOTAL % OF THIS CHANGE ORDER %
TOTAL C.O.% OF ORIGNINAL CONTRACT %
ADJUSTED CONTRACT COST $ .00
(Assuming all change orders approved)
ACCEPTED BY: DATE:
Contractor's Representative
ACCEPTED BY: DATE:
Project Manager
REVIEWED BY: DATE:
Title:
APPROVED BY: DATE:
Purchasing Agent over $60,000
cc: City Clerk Contractor Engineer
Project File Architect Purchasing
Section 00960
APPLICATION FOR PAYMENT PAGE 1 OF 4
OWNER: Poudre Fire Authority PROJECT: APPLICATION NUMBER:
APPLICATION DATE:
PERIOD BEGINNING:
ENGINEER: CONTRACTOR: PERIOD ENDING:
PROJECT NUMBER:
CHANGE ORDERS Application is made for Payment as shown below in connection with Contract
NUMBER DATE AMOUNT
The present status of the account for this Contract is as
follows:
1
2 Original Contract Amount:
3 Net Change by Change Order:
Current contract Amount: $0.00
Total Completed and Stored to Date:
Less Previous Applications:
Amount Due this Application - Before Retainage: $0.00
Less Retainage:
Net Change by Change Order $0.00 AMOUNT DUE THIS APPLICATION: $0.00
CERTIFICATION:
The undersigned CONTRACTOR certifies that all obligations of CONTRACTOR incurred in connection with
the Work have been satisfied as required in Paragraph 14.3. of the General Conditions of the Contract.
The above Amount Due This Application is requested by the CONTRACTOR.
Date: By:
Payment of the above Amount Due This Application is recommended by the ENGINEER.
Date: By:
Payment of the above Amount Due This Application has been reviewed by the OWNER'S Project Manager.
Date: By:
Payment of the above Amount Due This Application is approved by the OWNER.
Date: By:
CONTRACT AMOUNTS
APPLICATION FOR
PAYMENT PAGE 2 OF 4
Work
Completed
Work
Completed
Work
Completed Stored
Bid
This
Month
Previous
Periods
To
Date Materials Total
Item This Earned Percent
Number Description Quantity Units
Unit
Price Amount Qty. Amount Qty. Amount Qty. Amount Period
To
Date Billed
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
TOTALS $0.00 $0.00 $0.00 $0.00 $0.00
CHANGE ORDERS APPLICATION FOR PAYMENT PAGE 3 OF 4
Work
Completed
Work
Completed
Work
Completed Stored
Bid
This
Month
Previous
Periods
To
Date Materials Total
Item This Earned Percent
Number Description Quantity Units
Unit
Price Amount Qty. Amount Qty. Amount Qty. Amount Period
To
Date Billed
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
TOTALS CHANGE
ORDERS $0.00 $0.00 $0.00 $0.00 $0.00
PROJECT TOTALS $0.00 $0.00 $0.00 $0.00 $0.00
STORED MATERIALS
SUMMARY PAGE 4 OF 4
On Hand Received Installed On Hand
Item Invoice Previous This This This
Number Number Description Application Period Period Application
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
TOTALS $0.00 $0.00 $0.00 $0.00