HomeMy WebLinkAboutWORK ORDER - RFP - 8909 HVAC ON-CALL SERVICES 2019Work Order Form Official Purchasing Form
Last updated 10/2017
WORK ORDER FORM
PURSUANT TO A MASTER AGREEMENT BETWEEN
THE CITY OF FORT COLLINS
AND
TOLIN MECHANICAL SYSTEMS COMPANY
WORK ORDER NUMBER: 523914
PROJECT TITLE: IT Data Center East Unit – City Hall
ORIGINAL BID/RFP NUMBER & NAME: 8909 HVAC Contractors
MASTER AGREEMENT EFFECTIVE DATE: 7/26/2019
WORK ORDER COMMENCEMENT DATE: 12/11/2020
WORK ORDER COMPLETION DATE: 2/28/2021
MAXIMUM FEE: (time and reimbursable direct costs): $74860.00
PROJECT DESCRIPTION/SCOPE OF SERVICES: Replace the Liebert CRAC East unit serving
the IT Data Center at City Hall. Detail attached.
Service Provider agrees to perform the services identified above and on the attached forms in
accordance with the terms and conditions contained herein and in the Master Agreement between
the parties. In the event of a conflict between or ambiguity in the terms of the Master Agreement
and this Work Order (including the attached forms) the Master Agreement shall control.
The attached forms consisting of five (5) pages are hereby accepted and incorporated herein, by
this reference, and Notice to Proceed is hereby given after all parties have signed this document.
SERVICE PROVIDER: Date:
Ben Friesen, General Manager
ACCEPTANCE: Date:
Justin Huntley, Project Manager
REVIEWED: Date:
Jake Rector, Senior Buyer
ACCEPTANCE: Date:
Gerry Paul, Purchasing Director
(if greater than $60,000)
DocuSign Envelope ID: EDFF10BB-1BCB-476B-8A0A-605467E990F1
12/14/2020
12/14/2020
12/14/2020
12/14/2020
City Hall
Liebert Replacement
Presented to:
Presented by:
December 8, 2020
DocuSign Envelope ID: EDFF10BB-1BCB-476B-8A0A-605467E990F1
Job Number Registered Quotation Number Presentation Date Page
Q-12-2020-202798 December 8, 2020 2 of 7
BY AND BETWEEN:
Contractor
Tolin Mechanical Systems
2020 Airway Avenue
Fort Collins, CO 80524
Customer
City of Fort Collins
300 Laporte Avenue
Fort Collins, CO 80521
PROJECT LOCATION: 300 Laporte Avenue
Fort Collins, CO 80521
PROJECT DESCRIPTION: City Hall – Liebert Replacement
We are pleased to offer our proposal to replace the Liebert CRAC East unit serving the IT Data
Center at City Hall. The unit has been scheduled due to age, condition and use of R22 refrigerant.
Liebert is the preferred manufacture, and the system has been requested to match the CRAC West
design to include a drycooler instead of an air cooled condensing unit. It has been recommended
by the manufacture to have a dedicated drycooler to each CRAC to ensure sufficient redundancy is
in place and the desired capacities are attained. The new Liebert system will be procured by the
City of Fort Collins. The proposal is based upon a site visit on 12/03/20. Below is our suggested
scope of work.
DocuSign Envelope ID: EDFF10BB-1BCB-476B-8A0A-605467E990F1
Job Number Registered Quotation Number Presentation Date Page
Q-12-2020-202798 December 8, 2020 3 of 7
OUR PROPOSAL INCLUDES THE FOLLOWING:
General Construction Activities:
• Provide permit
• Provide new equipment startup and commissioning to ensure proper operation
• Provide one-year warranty on new equipment, materials, and installation craftsmanship
• Provide a clean and safe work environment
• Provide engineering package (mechanical, electrical, structural)
Demolition:
• Provide labor and materials to recover existing refrigerant prior to removal
• Provide labor and materials to disconnect, demo and cap existing refrigeration lines as
necessary
• Provide labor and materials to disconnect electrical and control wiring to unit for removal
• Provide labor and materials to demo and haul offsite the indoor CRAC unit
• Provide labor and materials to demo and haul offsite the outdoor condensing unit using
crane services
• Provide labor and materials to recycle the existing equipment per applicable
environmental codes and regulations
New Work:
• Provide labor and materials to install (1) Indoor CRAC Unit
o Liebert, Model #: DS077KUA10I252S
o 77kW (22 TON)
o Downflow (RA top/SA bottom)
o Paradenser TM Heat Exchanger
o 14 gauge welded frame
o EC Motor
o Infrared Humidifier
o Dual Refrigeration Circuits
o A-Frame Evaporator Coil
o Liebert iCOM Control w/HD Display
Base Communications & Connectivity includes one Ethernet port and one
RS-485 port on iCOM controller, dedicated to supporting BACnet IP,
Modbus TCP/IP, BACnet 485 , Modbus 485 and SNMP v1/v2c/v3
o Locking Disconnect Switch
o Smoke Detector
DocuSign Envelope ID: EDFF10BB-1BCB-476B-8A0A-605467E990F1
Job Number Registered Quotation Number Presentation Date Page
Q-12-2020-202798 December 8, 2020 4 of 7
o Condensate Pump
o 12” floor stand
o 460/3/60
o 65,000A SCCR
•Provide labor and materials to install steel structure base for new Drycooler
•Provide labor and materials for necessary roof work associated with new structure
•Provide labor and materials to install (1) Outdoor Liebert Drycooler
o Liebert, Model#: DD0650A40
o 6 Fan Standard Drycooler
o 105F outdoor ambient
o 460/3/60
o Disconnect Switch
o Dual Pump Model D5ANT
o 15 gal expansion tank, ASME rated
•Provide labor and materials to install copper supply and return condenser water piping
from outdoor drycooler to indoor CRAC unit
•Provide labor and materials to install piping insulation on new condenser water piping
•Provide labor and materials to install plenum return transition ductwork from new CRAC
unit to ceiling grid
•Provide labor and materials to fill new condenser water loop with 40% glycol/water
mixture
OUR PROPOSAL EXCLUDES THE FOLLOWING:
Providing any labor, materials, or equipment for work not explicitly detailed in the above scope,
including but not limited to:
•Labor outside normal business hours, 7:30 a.m. to 4:30 p.m. Monday through Friday
•Taxes
•Payment or performance bonding
•Liebert equipment (Provided by COF)
•Electrical (larger wire may be required for outdoor drycooler, Tolin will help determine
this will manufacture)
•Ceiling grid
•Drywall patching/panting
•Relocation of roof ballast rock & pavers work (if necessary)
•Controls (Integration to BAS & Liebert lead/lag controls)
•Hazardous material testing and abatement
•Any provision of temporary heating, cooling, ventilation or exhaust
DocuSign Envelope ID: EDFF10BB-1BCB-476B-8A0A-605467E990F1
Job Number Registered Quotation Number Presentation Date Page
Q-12-2020-202798 December 8, 2020 5 of 7
PRICING SUMMARY
BASE SCOPE
CRAC EAST LIEBERT REPLACEMENT/RETROFIT .......................................................................... $74,860
Labor $48,082
Materials $25,375
Warranty, Permits $1,403
ACCEPTED (INITIAL) ___________ DECLINED (INITIAL) ___________
PAYMENT SCHEDULE
City of Fort Collins and Tolin Agreement 8909:
HVAC Contractors
“This Agreement is the property of Tolin and is provided for the Customer's use only. Tolin
guarantees the price stated in this Agreement for thirty (30) days from the proposal date.”
Tolin Mechanical Systems Company Customer
Brian Carpenter, PE
Project Sales / Energy Engineer
Title
December 8, 2020
Date
Signature or PO#
Print Name and Title
Date
DocuSign Envelope ID: EDFF10BB-1BCB-476B-8A0A-605467E990F1