HomeMy WebLinkAbout430 N COLLEGE AVE - SPECIAL INSPECTIONS - 2/21/2018February 21", 2018
Brian Hood
2537 Research Blvd., Suite 200
Fort Collins, Colorado 80526
Re: CSU Powerhouse Forklift Ramp
Fort Collins, Colorado
Deal- Brian:
v ' 70 ?t-PO
41JVA, Incorpomted
` 213 Linden Street.
Suite 200
Fort C05M CO 80524
970,225.9099
infoDivajva.com
www.jvajva.com
3v CofILr
U
As per your request, JVA, Inc. visited the Project site once prior to construction, and twice during
construction. We observed the following:
1) Existing conditions. Subsequent to observing the existing conditions, we produced sketches
indicating ramp reinforcing and concrete specifications.
2) Initial concrete demolition and ramp grading.
3) In -place ramp reinforcing.
4) Final concrete placement.
We also reviewed progress photographs sent to us by Erik Larson of the CSU Energy Institute.
In our opinion, the ramp excavation, reinforcing, and concrete placement matched, or exceeded, the
requirements outlined in the design sketches produced by JVA Inc.
Please feel free to contact us if you have questions or if we may be of further service.
Sincerely,
JVA, Inc.
LOW
Steve Carpenter, PE, LEED
Principal
02/21/2018