HomeMy WebLinkAboutLAKEVIEW ON THE RISE - Filed FDT-FIELD DENSITY TEST - 2019-08-16 (2)HMAC FIELD DENSITY TEST REPORT
Report Number:
Service Date:
Report Date:
Task:
Client
20181040.0280
08/07/19
08/13/19
Asphalt
Signature Construction LLC
Attn: Matt Boyle
720 3rd Ave SW
Carmel, IN 46032-2036
1901 Sharp Point Dr, Ste C
Fort Collins, CO 80525-4429
970-484-0359
Lakeview on the Rise Apartment Development
6740 South College Avenue
Fort Collins, CO
Project
Project Number: 20181040
Lab Test Data
Comp.
Max.
Project Requirements
Comp.
Min.
Mat.
Material Information
Thickness
Min.
Density
Reference
Laboratory
No. Reference Number Classification and Description Test Method (pcf) (in) (%) (%)
1 Connell Mix 154.2 92 96
Field Test Data
Test Pave. Mat. Density Length
Nuclear Core
Density
Core
Factor
Correction
Density
Corrected
Comp.
No. Test Location Lift No. (%)
Core Data
(pcf) (in) (pcf) (pcf) (pcf)
Southeast Corner of Stoney Brook road/Debra Drive
24 See Diagram Bottom 1 143.3 93
25 See Diagram Bottom 1 144.0 93
26 See Diagram Bottom 1 145.1 94
27 See Diagram Bottom 1 144.3 94
28 See Diagram Bottom 1 143.8 93
29 See Diagram Bottom 1 144.0 93
30 See Diagram Bottom 1 145.0 94
Comments:
Datum: Bottom = Bottom Mat Std. Cnt. M: 619 Std. Cnt. D: 1973
ASPHALT DENSITY TESTING REPORT
Report Number: 20181040.0280
Service Date: 08/07/19 1901 Sharp Point Dr, Ste C
Report Date: 08/13/19 Fort Collins, CO 80525-4429
Task: Asphalt 970-484-0359
Client Project
Signature Construction LLC Lakeview on the Rise Apartment Development
Attn: Matt Boyle 6740 South College Avenue
720 3rd Ave SW Fort Collins, CO
Carmel, IN 46032-2036
Project Number: 20181040
Services: Perform in-place density tests to determine degree of compaction.
Terracon Rep.: Taylor Keller
Reported To: Jeff with Connell
Contractor: Connell
Report Distribution:
(1) Signature Construction LLC, Matt
Boyle
(1) Connell Resources Inc, Jeff Laugel
(1) Signature Construction LLC, Taylor
Elizalde
(1) Signature Construction LLC, Trevor
Rine
Reviewed By: ____________________________________
(1) Terracon Consultants, Inc., Eric
Bernhardt
Craig L. Nelson
Project Manager
The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client
indicated above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable to
the actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical materials.
BC0001, 10-16-13, Rev.10 Page 1 of 1
North
South
HMAC FIELD DENSITY TEST REPORT
Report Number:
Service Date:
Report Date:
Task:
Client
20181040.0282
08/07/19
08/13/19
Asphalt
Signature Construction LLC
Attn: Matt Boyle
720 3rd Ave SW
Carmel, IN 46032-2036
1901 Sharp Point Dr, Ste C
Fort Collins, CO 80525-4429
970-484-0359
Lakeview on the Rise Apartment Development
6740 South College Avenue
Fort Collins, CO
Project
Project Number: 20181040
Lab Test Data
Comp.
Max.
Project Requirements
Comp.
Min.
Mat.
Material Information
Thickness
Min.
Density
Reference
Laboratory
No. Reference Number Classification and Description Test Method (pcf) (in) (%) (%)
1 Connell Mix 154.2 92 96
Field Test Data
Test Pave. Mat. Density Length
Nuclear Core
Density
Core
Factor
Correction
Density
Corrected
Comp.
No. Test Location Lift No. (%)
Core Data
(pcf) (in) (pcf) (pcf) (pcf)
North End of Debra Drive
31 See Diagram Bottom 1 143.4 93
32 See Diagram Bottom 1 144.0 93
33 See Diagram Bottom 1 144.5 94
34 See Diagram Bottom 1 143.8 93
35 See Diagram Bottom 1 144.3 94
Comments:
Datum: Bottom Mat Std. Cnt. M: 619 Std. Cnt. D: 1973
Test and/or retest results on this report meet project requirements as noted above.
S/N: 60674 Make: Troxler Model: 3430 Last Cal. Date: 01/31/2019
ASPHALT DENSITY TESTING REPORT
Report Number: 20181040.0282
Service Date: 08/07/19 1901 Sharp Point Dr, Ste C
Report Date: 08/13/19 Fort Collins, CO 80525-4429
Task: Asphalt 970-484-0359
Client Project
Signature Construction LLC Lakeview on the Rise Apartment Development
Attn: Matt Boyle 6740 South College Avenue
720 3rd Ave SW Fort Collins, CO
Carmel, IN 46032-2036
Project Number: 20181040
Services: Perform in-place density tests to determine degree of compaction.
Terracon Rep.: Taylor Keller
Reported To: Jeff with Connell
Contractor: Connell
Report Distribution:
(1) Signature Construction LLC, Matt
Boyle
(1) Connell Resources Inc, Jeff Laugel
(1) Signature Construction LLC, Taylor
Elizalde
(1) Signature Construction LLC, Trevor
Rine
Reviewed By: ____________________________________
(1) Terracon Consultants, Inc., Eric
Bernhardt
Craig L. Nelson
Project Manager
The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client
indicated above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable to
the actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical materials.
BC0001, 10-16-13, Rev.10 Page 1 of 1
North
South
HMAC FIELD DENSITY TEST REPORT
Report Number:
Service Date:
Report Date:
Task:
Client
20181040.0283
08/08/19
08/13/19
Asphalt
Signature Construction LLC
Attn: Matt Boyle
720 3rd Ave SW
Carmel, IN 46032-2036
1901 Sharp Point Dr, Ste C
Fort Collins, CO 80525-4429
970-484-0359
Lakeview on the Rise Apartment Development
6740 South College Avenue
Fort Collins, CO
Project
Project Number: 20181040
Lab Test Data
Comp.
Max.
Project Requirements
Comp.
Min.
Mat.
Material Information
Thickness
Min.
Density
Reference
Laboratory
No. Reference Number Classification and Description Test Method (pcf) (in) (%) (%)
1 Connell Mix 154.2 92 96
Field Test Data
Test Pave. Mat. Density Length
Nuclear Core
Density
Core
Factor
Correction
Density
Corrected
Comp.
No. Test Location Lift No. (%)
Core Data
(pcf) (in) (pcf) (pcf) (pcf)
Southeast Corner of Stoney Brook Road / Debra Drive
36 See Diagram Bottom 1 144.0 93
37 See Diagram Bottom 1 143.6 93
38 See Diagram Bottom 1 144.2 94
39 See Diagram Bottom 1 143.7 93
40 See Diagram Bottom 1 145.0 94
41 See Diagram Bottom 1 144.3 94
42 See Diagram Bottom 1 144.2 94
43 See Diagram Bottom 1 143.9 93
44 See Diagram Bottom 1 144.6 94
ASPHALT DENSITY TESTING REPORT
Report Number: 20181040.0283
Service Date: 08/08/19 1901 Sharp Point Dr, Ste C
Report Date: 08/13/19 Fort Collins, CO 80525-4429
Task: Asphalt 970-484-0359
Client Project
Signature Construction LLC Lakeview on the Rise Apartment Development
Attn: Matt Boyle 6740 South College Avenue
720 3rd Ave SW Fort Collins, CO
Carmel, IN 46032-2036
Project Number: 20181040
Services: Perform in-place density tests to determine degree of compaction.
Terracon Rep.: Taylor Keller
Reported To: Jeff with Connell
Contractor: Connell
Report Distribution:
(1) Signature Construction LLC, Matt
Boyle
(1) Connell Resources Inc, Jeff Laugel
(1) Signature Construction LLC, Taylor
Elizalde
(1) Signature Construction LLC, Trevor
Rine
Reviewed By: ____________________________________
(1) Terracon Consultants, Inc., Eric
Bernhardt
Craig L. Nelson
Project Manager
The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client
indicated above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable to
the actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical materials.
BC0001, 10-16-13, Rev.10 Page 1 of 1
North
South
45 See Diagram Bottom 1 143.4 93
Comments:
Datum: Std. Cnt. M: Std. Cnt. D:
Test and/or retest results on this report meet project requirements as noted above.
S/N: Make: Model: Last Cal. Date:
Services: Perform in-place density tests to determine degree of compaction.
Reported To:
Contractor:
Report Distribution:
(1) Signature Construction LLC, Matt Boyle (1) Connell Resources Inc, Jeff Laugel
(1) Signature Construction LLC, Taylor Elizalde (1) Signature Construction LLC, Trevor Rine
(1) Terracon Consultants, Inc., Eric Bernhardt
Jeff with Connell
Connell
Craig L. Nelson
Project Manager
Reviewed By:
Terracon Rep.: Taylor Keller
Test Methods: ASTM D2950
The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client indicated
above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable to the actual samples
tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical materials.
CR0025, 11-16-12, Rev.6 Page 1 of 1
Services: Perform in-place density tests to determine degree of compaction.
Reported To:
Contractor:
Report Distribution:
(1) Signature Construction LLC, Matt Boyle (1) Connell Resources Inc, Jeff Laugel
(1) Signature Construction LLC, Taylor Elizalde (1) Signature Construction LLC, Trevor Rine
(1) Terracon Consultants, Inc., Eric Bernhardt
Jeff with Connell
Connell
Craig L. Nelson
Project Manager
Reviewed By:
Terracon Rep.: Taylor Keller
Test Methods: ASTM D2950
The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client indicated
above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable to the actual samples
tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical materials.
CR0025, 11-16-12, Rev.6 Page 1 of 1
Test and/or retest results on this report meet project requirements as noted above.
S/N: 60674 Make: Troxler Model: 3430 Last Cal. Date: 01/31/2019
Services: Perform in-place density tests to determine degree of compaction.
Reported To:
Contractor:
Report Distribution:
(1) Signature Construction LLC, Matt Boyle (1) Connell Resources Inc, Jeff Laugel
(1) Signature Construction LLC, Taylor Elizalde (1) Signature Construction LLC, Trevor Rine
(1) Terracon Consultants, Inc., Eric Bernhardt
Jeff with Connell
Connell
Craig L. Nelson
Project Manager
Reviewed By:
Terracon Rep.: Taylor Keller
Test Methods: ASTM D2950
The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client indicated
above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable to the actual samples
tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical materials.
CR0025, 11-16-12, Rev.6 Page 1 of 1