HomeMy WebLinkAboutPOUDRE VALLEY HOSPITAL - Filed SEPD-SURFACE EXPLORATION/PAVEMENT DESIGN REPORT - 2017-12-14PVH Right Turn Lane at Lemay Ave. and Robertson St. ■ Fort Collins, Colorado
March 20, 2017 ■ Terracon Project No. 20175015
Responsive ■ Resourceful ■ Reliable EXECUTIVE SUMMARY 1
EXECUTIVE SUMMARY
A geotechnical exploration has been performed for the proposed PVH Right Turn Lane to be
constructed at the intersection of Lemay Avenue and Robertson Street in Fort Collins, Colorado.
Two (2) borings designated as Boring No. 1 and Boring No. 2, were performed to depths of
approximately 10½ feet below existing site grades. This report specifically addresses the
recommendations for the proposed turn lane
Based on the information obtained from our subsurface exploration and laboratory testing program,
the following geotechnical considerations were identified and will need to be considered:
n Subsurface conditions encountered in our exploratory borings generally consisted of about
0.5 feet of grass and organic soil over about 10 feet of sandy lean clay. Boring logs are
presented in the Exploration Results section of this report.
n Soft lean clay soils were encountered within the upper approximately 4 to 10½ feet of the
borings completed at this site. These materials can be susceptible to disturbance and
loss of strength under repeated construction traffic loads and unstable conditions could
develop. Stabilization of soft soils may be required at some locations to provide adequate
support for construction equipment and proposed structures. Terracon should be
contacted if these conditions are encountered to observe the conditions exposed and to
provide guidance regarding stabilization (if needed).
n On-site soils typically appear suitable for use as general engineered fill and backfill on the
site provided they are placed and compacted as described in this report. Import materials (if
needed) should be evaluated and approved by Terracon prior to delivery to the site.
Earthwork recommendations are presented in the Site Preparation section of this report.
n Recommended Pavement thicknesses for this project include 6 inches of asphalt over 8
inches of aggregate base course in the proposed turn lane. Additional pavement section
alternatives and discussion are presented in the report.
n As discussed in the Grading and Drainage section of this report, surface drainage should
be designed, constructed and maintained to provide rapid removal of surface water runoff
away from the existing and proposed pavements. Water should not be allowed to pond
adjacent on pavements and conservative irrigation practices should be followed to avoid
wetting pavement subgrade. Excessive wetting of subgrade can cause movement and
distress to pavements.
n Close monitoring of the construction operations and implementing drainage
recommendations discussed herein will be critical in achieving the intended foundation, slab
and pavement performance. We therefore recommend that Terracon be retained to monitor
this portion of the work.
PVH Right Turn Lane at Lemay Ave. and Robertson St. ■ Fort Collins, Colorado
March 20, 2017 ■ Terracon Project No. 20175015
Responsive ■ Resourceful ■ Reliable EXECUTIVE SUMMARY 2
This summary should be used in conjunction with the entire report for design purposes. It should
be recognized that details were not included or fully developed in this section, and the report must
be read in its entirety for a comprehensive understanding of the items contained herein. The section
titled GENERAL COMMENTS should be read for an understanding of the report limitations.
PVH Right Turn Lane at Lemay Ave. and Robertson St. ■ Fort Collins, Colorado
March 20, 2017 ■ Terracon Project No. 20175015
Responsive ■ Resourceful ■ Reliable
REPORT TOPICS*
Project Description
Site Conditions
Exploration and Testing Procedures
Field Exploration
Laboratory Testing
Geotechnical Characterization
Laboratory Testing
Corrosion Protection (Water-Soluble Sulfates)
Groundwater
Geotechnical Overview
Low Strength Soils
Site Preparations
Excavation
Subgrade Preparation
Fill Materials
Compaction Requirements
Utility Trench and Backfill
Grading and Drainage
Exterior Slab Design and Construction
Pavements
Pavements – Subgrade Preparation
Pavements – Design Recommendations
Pavements – Construction Considerations
Pavements – Maintenance
General Comments
ATTACHMENTS
Site Locations
Exploration Plan
Exploration Results (Boring Logs and Laboratory Data)
Supporting Information (General Notes and USCS, etc.)
*This is a paper rendition of a web-based Geotechnical Engineering Report.
PVH Right Turn Lane at Lemay Ave. and Robertson St. ■ Fort Collins, Colorado
March 20, 2017 ■ Terracon Project No. 20175015
Responsive ■ Resourceful ■ Reliable PROJECT DESCRIPTION 1
PROJECT DESCRIPTION
Our initial understanding of the project was provided in our proposal and was discussed in the
project planning stage. A period of collaboration has transpired since the project was initiated
and our final understanding of the project conditions is as follows:
Item Description
Project location
The project location is on north-bound Lemay Avenue between East Pitkin
Street and Robertson Street, near the southern entrance to Poudre Valley
Hospital.
Proposed
construction
The proposed right-turn lane will begin approximately 60 feet north of East Pitkin
Street and extend north to Robertson Street. All access/drive approaches will
be rigid (concrete) pavement sections, whereas the turn lane will be asphalt.
The existing curb and gutter as well as a portion of the landscaped areas will be
demolished. A mill and overlay is planned for the western-most portion of the
turn lane.
Pavements
Traffic loads were provided by the City of Fort Collins for this project:
73,000 ESALs (10 EDLA).
PVH Right Turn Lane at Lemay Ave. and Robertson St. ■ Fort Collins, Colorado
March 20, 2017 ■ Terracon Project No. 20175015
Responsive ■ Resourceful ■ Reliable SITE CONDITIONS 1
SITE CONDITIONS
The following description of site conditions is derived from our site visit in association with the
field exploration as well as our review of publically available geologic maps, topographic maps
and aerial photographs.
Item Description
Location
The proposed right turn lane will be constructed on north-bound Lemay
Avenue between East Pitkin Street and Robertson Avenue at the southern
entrance to Poudre Valley Hospital (PVH). The approximate
latitude/longitude of the turn lane is N 40.57108°/W 105.05776° at the
entrance to PVH.
Existing
improvements
North-bound Lemay Avenue is constructed with asphalt. The curb, gutter,
and sidewalk are concrete. Three existing light poles are within the proposed
construction zone. East of the sidewalk, grass-covered areas extend from
the Pitkin Street to Robertson Street. A landscaped berm and entrance sign
are located on the southeast corner of Robertson Street.
Existing topography Lemay Avenue gently slopes to the south and east at this location.
PVH Right Turn Lane at Lemay Ave. and Robertson St. ■ Fort Collins, Colorado
March 20, 2017 ■ Terracon Project No. 20175015
Responsive ■ Resourceful ■ Reliable EXPLORATION AND TESTING PROCEDURES 1
EXPLORATION AND TESTING PROCEDURES
Based on our understanding of the project as noted in Project Understanding, we developed
the following scope of services for field exploration and laboratory testing for this project.
Field Exploration
Our field exploration work included the drilling and sampling of exploratory soil borings consistent
with the following schedule. Proposed borings were completed to the planned depths below
existing site grades or to practical auger refusal, if shallower.
Number of Borings Boring Depth (ft.) Planned Location
2 10 East of the existing sidewalk on the shoulder of the
proposed turn lane.
Locations of soil borings are provided on our Exploration Plan. The locations of exploration
points were established in the field by Terracon’s exploration team using a measuring wheel and
a hand-held GPS unit to establish boring locations with reference to known points. The accuracy
of the exploration points is usually within 10 feet of the noted location. A ground surface elevation
at each boring location was obtained by Terracon using an engineer’s level and referencing an on-
site benchmark.
The borings were drilled with a Geoprobe limited access drill rig with solid-stem augers. Disturbed
samples were obtained at selected intervals utilizing a 2-inch outside diameter, split-spoon
sampler and a 3-inch outside diameter, ring-barrel sampler. A disturbed bulk sample was
obtained from auger cuttings. Penetration resistance values were recorded in a manner similar to
the standard penetration test (SPT). This test consists of driving the sampler into the ground with
a 140-pound hammer free-falling through a distance of 30 inches. The number of blows required
to advance the ring-barrel sampler 12 inches (18 inches for standard split-spoon samplers, final
12 inches are recorded) or the interval indicated, is recorded as a standard penetration resistance
value (N-value). The blow count values are indicated on the boring logs at the respective sample
depths. Ring-barrel sample blow counts are not considered N-values.
A CME automatic SPT hammer was used to advance the samplers in the borings performed on this
site. A greater efficiency is typically achieved with the automatic hammer compared to the
conventional safety hammer operated with a cathead and rope. Published correlations between the
SPT values and soil properties are based on the lower efficiency cathead and rope method. This
higher efficiency affects the standard penetration resistance blow count value by increasing the
penetration per hammer blow over what would be obtained using the cathead and rope method. The
effect of the automatic hammer's efficiency has been considered in the interpretation and analysis of
the subsurface information for this report.
PVH Right Turn Lane at Lemay Ave. and Robertson St. ■ Fort Collins, Colorado
March 20, 2017 ■ Terracon Project No. 20175015
Responsive ■ Resourceful ■ Reliable EXPLORATION AND TESTING PROCEDURES 2
The standard penetration test provides a reasonable indication of the in-place density of sandy
type materials, but only provides an indication of the relative stiffness of cohesive materials since
the blow count in these soils may be affected by the moisture content of the soil. In addition,
considerable care should be exercised in interpreting the N-values in gravelly soils, particularly
where the size of the gravel particle exceeds the inside diameter of the sampler.
Our exploration team prepared field boring logs as part of the drilling operations. These field logs
include visual classifications of the materials encountered during drilling and our interpretation of
the subsurface conditions between samples. Groundwater measurements were obtained in the
borings at the time of site exploration. Final boring logs were prepared from the field logs. The
final boring logs represent the engineer's interpretation of the field logs and include modifications
based on observations and tests of the samples in the laboratory.
All borings were backfilled immediately after their completion with flow-fill. Excess auger cuttings
were disposed of on the site by spreading in the area of each exploration point. Because backfill
material often settles below the surface after a period of time, you should observe the exploration
points periodically for signs of depressions and backfill them if necessary.
Laboratory Testing
The soil samples retrieved during the field exploration were returned to the laboratory for
observation by the project geotechnical engineer. At that time, the field descriptions were
reviewed and an applicable laboratory testing program was formulated to determine engineering
properties of the subsurface materials.
Laboratory tests were conducted on selected soil samples. The results of these tests are
presented on the boring logs and in this appendix. The test results were used for the geotechnical
engineering analyses, and the development of pavement and earthwork recommendations. The
laboratory tests were performed in general accordance with applicable locally accepted
standards. Soil samples were classified in general accordance with the Unified Soil Classification
System described in the Supporting Information section of this report. Procedural standards
noted in this report are for reference to methodology in general. In some cases, variations to
methods are applied as a result of local practice or professional judgment.
n Water content n Plasticity index
n Grain-size distribution
n Consolidation/swell
n Water-soluble sulfate content
n Dry density
n R-value
PVH Right Turn Lane at Lemay Ave. and Robertson St. ■ Fort Collins, Colorado
March 20, 2017 ■ Terracon Project No. 20175015
Responsive ■ Resourceful ■ Reliable GEOTECHNICAL CHARACTERIZATION 1
GEOTECHNICAL CHARACTERIZATION
Specific conditions encountered at each boring location are indicated on the individual boring logs.
Stratification boundaries on the boring logs represent the approximate location of changes in soil
types; in situ, the transition between materials may be gradual. Details for each of the borings can
be found in Exploration Results. A discussion of field sampling and laboratory testing procedures
and test results are presented in Exploration and Testing Procedures. Based on the results of
the borings, subsurface conditions on the project site can be generalized as follows:
Material Description Approximate Depth to
Bottom of Stratum Consistency/Density/Hardness
Vegetative layer and organic soil About ½ to 1 feet below
existing site grades. --
Clay with varying amounts of sand To the maximum depth of
exploration of about 10½ feet.
Stiff (at about 2 to 3 feet) to soft to
medium stiff (at depths of
approximately 4 feet and greater)
Laboratory Testing
Representative soil samples were selected for swell-consolidation testing and exhibited 0.4 to 0.5
percent swell when wetted. A composited bulk sample of site soils was selected for plasticity
testing exhibited moderate plasticity with a liquid limit of 31 and a plasticity index of 19, as well as
an R-value of 16. Laboratory test results are presented in the Exploration Results section of this
report.
Corrosion Protection (Water-Soluble Sulfates)
Results of water-soluble sulfate testing indicate that ASTM Type I portland cement should be
specified for all project concrete on and below grade. Foundation concrete should be designed
for low sulfate exposure in accordance with the provisions of the ACI Design Manual, Section
318, Chapter 4.
Groundwater
The boreholes were observed while drilling and after completion for the presence and level of
groundwater. Groundwater was not observed in the borings while drilling, or for the short duration
that the borings were allowed to remain open. However, this does not necessarily mean the borings
terminated above groundwater. Due to the low permeability of the soils encountered in the borings,
a relatively long period of time may be necessary for a groundwater level to develop and stabilize in
a borehole in these materials. Long term observations in piezometers or observation wells sealed
PVH Right Turn Lane at Lemay Ave. and Robertson St. ■ Fort Collins, Colorado
March 20, 2017 ■ Terracon Project No. 20175015
Responsive ■ Resourceful ■ Reliable GEOTECHNICAL CHARACTERIZATION 2
from the influence of surface water are often required to define groundwater levels in materials of
this type.
Groundwater level fluctuations occur due to seasonal variations in the amount of rainfall, runoff
and other factors not evident at the time the borings were performed. Therefore, groundwater
levels during construction or at other times in the life of the structure may be higher or lower than
the levels indicated on the boring logs. The possibility of groundwater level fluctuations should
be considered when developing the design and construction plans for the project.
PVH Right Turn Lane at Lemay Ave. and Robertson St. ■ Fort Collins, Colorado
March 20, 2017 ■ Terracon Project No. 20175015
Responsive ■ Resourceful ■ Reliable GEOTECHNICAL OVERVIEW 1
GEOTECHNICAL OVERVIEW
Based on subsurface conditions encountered in the borings, the site appears suitable for the
proposed construction from a geotechnical point of view provided certain precautions and design
and construction recommendations described in this report are followed. We have identified a
geotechnical condition, potentially soft, low strength clay soils, which could impact design,
construction and performance of the proposed turn lane. This condition will require particular
attention in project planning, design and during construction and discussed in greater detail in the
following sections.
Low Strength Soils
Soft lean clay soils were encountered within the upper approximately 4 to 10 feet of the borings
completed at this site. These materials can be susceptible to disturbance and loss of strength
under repeated construction traffic loads and unstable conditions could develop. Stabilization of
soft soils may be required at some locations to provide adequate support for construction
equipment and proposed structures. Terracon should be contacted if these conditions are
encountered to observe the conditions exposed and to provide guidance regarding stabilization
(if needed).
PVH Right Turn Lane at Lemay Ave. and Robertson St. ■ Fort Collins, Colorado
March 20, 2017 ■ Terracon Project No. 20175015
Responsive ■ Resourceful ■ Reliable SITE PREPARATION 1
SITE PREPARATION
Prior to placing any fill, strip and remove existing vegetation, sidewalks, and any other deleterious
materials from the proposed construction area. Stripped organic materials should be wasted from
the site or used to re-vegetate landscaped areas or exposed slopes after completion of grading
operations. Prior to the placement of fills, the site should be graded to create a relatively level
surface to receive fill, and to provide for a relatively uniform thickness of fill beneath proposed
structures.
The following presents recommendations for site excavation, subgrade preparation and
placement of engineered fills on the project. All earthwork on the project should be observed and
evaluated by Terracon on a full-time basis. The evaluation of earthwork should include
observation of over-excavation operations, testing of engineered fills, subgrade preparation,
subgrade stabilization, and other geotechnical conditions exposed during the construction of the
project.
Excavation
It is anticipated that excavations for the proposed construction can be accomplished with
conventional earthmoving equipment. Excavations into the on-site soils will encounter weak and/or
saturated soil conditions with possible caving conditions.
The soils to be excavated can vary significantly across the site as their classifications are based
solely on the materials encountered in widely-spaced exploratory test borings. The contractor
should verify that similar conditions exist throughout the proposed area of excavation. If different
subsurface conditions are encountered at the time of construction, the actual conditions should be
evaluated to determine any excavation modifications necessary to maintain safe conditions.
The subgrade soil conditions should be evaluated during the excavation process and the stability
of the soils determined at that time by the contractors’ Competent Person. Slope inclinations flatter
than the OSHA maximum values may have to be used. The individual contractor(s) should be
made responsible for designing and constructing stable, temporary excavations as required to
maintain stability of both the excavation sides and bottom. All excavations should be sloped or
shored in the interest of safety following local, and federal regulations, including current OSHA
excavation and trench safety standards.
As a safety measure, it is recommended that all vehicles and soil piles be kept a minimum lateral
distance from the crest of the slope equal to the slope height. The exposed slope face should be
protected against the elements
PVH Right Turn Lane at Lemay Ave. and Robertson St. ■ Fort Collins, Colorado
March 20, 2017 ■ Terracon Project No. 20175015
Responsive ■ Resourceful ■ Reliable SITE PREPARATION 2
Subgrade Preparation
After deleterious materials have been removed from the construction area and the required
subgrade reached, the top 8 inches of the exposed ground surface should be scarified, moisture
conditioned, and recompacted to at least 95 percent of the maximum dry unit weight as
determined by AASHTO T99 before any new fill or pavement is placed.
After the bottom of the excavation has been compacted, engineered fill can be placed to bring the
pavement subgrade to the desired grade. Engineered fill should be placed in accordance with
the recommendations presented in subsequent sections of this report.
The stability of the subgrade may be affected by precipitation, repetitive construction traffic or
other factors. If unstable conditions develop, workability may be improved by scarifying and
drying. Alternatively, over-excavation of wet zones and replacement with granular materials may
be used, or crushed gravel and/or rock can be tracked or “crowded” into the unstable surface soil
until a stable working surface is attained. Lightweight excavation equipment may also be used to
reduce subgrade pumping.
Fill Materials
The on-site soils or approved granular and low plasticity cohesive imported materials may be used
as fill material. The soil removed from this site that is free of organic or objectionable materials,
as defined by a field technician who is qualified in soil material identification and compaction
procedures, can be re-used as fill for the pavement subgrade. It should be noted that on-site
materials will require reworking to adjust the moisture content to meet the compaction criteria.
Imported soils (if required) should meet the following material property requirements:
Gradation Percent finer by weight (ASTM C136)
4” 100
3” 70-100
No. 4 Sieve 50-100
No. 200 Sieve 60 (max.)
Soil Properties Values
Liquid Limit 35 (max.)
Plastic Limit 6 (max.)
PVH Right Turn Lane at Lemay Ave. and Robertson St. ■ Fort Collins, Colorado
March 20, 2017 ■ Terracon Project No. 20175015
Responsive ■ Resourceful ■ Reliable SITE PREPARATION 3
Compaction Requirements
Engineered fill should be placed and compacted in horizontal lifts, using equipment and procedures
that will produce recommended moisture contents and densities throughout the lift.
Item Description
Fill lift thickness
9 inches or less in loose thickness when heavy, self-
propelled compaction equipment is used
4 to 6 inches in loose thickness when hand-guided
equipment (i.e. jumping jack or plate compactor) is used
Minimum compaction requirements 95 percent of the maximum dry unit weight as determined by
AASHTO T99
Moisture content cohesive soil (clay) -1 to +3 % of the optimum moisture content
Moisture content cohesionless soil
(sand) -3 to +3 % of the optimum moisture content
1. We recommend engineered fill be tested for moisture content and compaction during placement.
Should the results of the in-place density tests indicate the specified moisture or compaction limits
have not been met, the area represented by the test should be reworked and retested as required
until the specified moisture and compaction requirements are achieved.
2. Specifically, moisture levels should be maintained low enough to allow for satisfactory compaction to
be achieved without the fill material pumping when proofrolled.
3. Moisture conditioned clay materials should not be allowed to dry out. A loss of moisture within these
materials could result in an increase in the material’s expansive potential. Subsequent wetting of these
materials could result in undesirable movement.
Utility Trench Backfill
All trench excavations should be made with sufficient working space to permit construction including
backfill placement and compaction.
All underground piping within or near the proposed construction should be designed with flexible
couplings, so minor deviations in alignment do not result in breakage or distress. Utility knockouts
should be oversized to accommodate differential movements. It is imperative that utility trenches be
properly backfilled with relatively clean materials. If utility trenches are backfilled with relatively
clean granular material, they should be capped with at least 18 inches of cohesive fill in non-
pavement areas to reduce the infiltration and conveyance of surface water through the trench
backfill.
It is strongly recommended that a representative of Terracon provide full-time observation and
compaction testing of trench backfill within pavement areas.
PVH Right Turn Lane at Lemay Ave. and Robertson St. ■ Fort Collins, Colorado
March 20, 2017 ■ Terracon Project No. 20175015
Responsive ■ Resourceful ■ Reliable SITE PREPARATION 4
Grading and Drainage
All grades must be adjusted to provide effective drainage during construction and maintained
throughout the life of the proposed project. Infiltration of water into excavations must be prevented
during construction. Landscape irrigation adjacent to pavements should be minimized or
eliminated. Water permitted to pond near or adjacent to the turn lane (either during or post-
construction) can result in significantly higher soil movements than those discussed in this report.
As a result, any estimations of potential movement described in this report cannot be relied upon
if positive drainage is not obtained and maintained, and water is allowed to infiltrate the fill and/or
subgrade.
Flatwork and pavements will be subject to post-construction movement. Maximum grades
practical should be used for paving and flatwork to prevent areas where water can pond. In
addition, allowances in final grades should take into consideration post-construction movement
of flatwork, particularly if such movement would be critical. Where paving or flatwork abuts
structural elements, care should be taken that joints are properly sealed and maintained to
prevent the infiltration of surface water.
Exterior Slab Design and Construction
Exterior slabs on-grade, exterior architectural features, and utilities founded on, or in backfill or
the site soils will likely experience some movement due to the volume change of the material.
Potential movement could be reduced by:
n Minimizing moisture increases in the backfill;
n Controlling moisture-density during placement of the backfill;
n Using designs which allow vertical movement between the exterior features and
adjoining structural elements; and
n Placing control joints on relatively close centers.
PVH Right Turn Lane at Lemay Ave. and Robertson St. ■ Fort Collins, Colorado
March 20, 2017 ■ Terracon Project No. 20175015
Responsive ■ Resourceful ■ Reliable PAVEMENTS 1
PAVEMENTS
Pavements – Subgrade Preparation
On most project sites, the site grading is accomplished relatively early in the construction phase.
Fills are typically placed and compacted in a uniform manner. However as construction proceeds,
the subgrade may be disturbed due to utility excavations, construction traffic, desiccation, or
rainfall/snow melt. As a result, the pavement subgrade may not be suitable for pavement
construction and corrective action will be required. The subgrade should be carefully evaluated
at the time of pavement construction for signs of disturbance or instability. We recommend the
pavement subgrade be thoroughly proofrolled with a loaded tandem-axle dump truck prior to final
grading and paving. All pavement areas should be moisture conditioned and properly compacted
to the recommendations in this report immediately prior to paving.
Pavements – Subgrade Stabilization with Geosynthetic
Terracon has worked closely with Connell Resources, who is the general contractor performing
the turn-lane construction. During the demolition process and initial grading, Terracon was
informed by Connell Resources the subgrade exhibited pumping and stabilization will likely be
required. We recommend placing a layer of soil stabilization and reinforcement geosynthetic
fabric below new aggregate base course and asphalt pavements. We recommend a uniform
pavement section for all traffic areas at this site consisting of 6 inches of asphaltic concrete over
8 inches of aggregate base course underlain by a layer of geotextile. The geosynthetic should
consist of a single layer of Mirafi® RS580i or engineer approved equivalent placed at the base of
the new aggregate base course.
It is our understanding the proposed turn-lane is at or near the preliminary subgrade elevation
and deleterious materials have been removed from the construction area. Prior to placing any
component of the new pavement section, the subgrade should be scarified to a depth of 8 inches,
moisture conditioned to within 2 percent of optimum moisture content and compacted to at least
95 percent of the maximum dry unit weight as determined by AASHTO T99. Terracon anticipates
subgrade soils will need to be dried to achieve recommended moisture contents prior to
compaction. If areas of the subgrade remain unstable and compaction is not readily achieved
due to unstable subgrade conditions caused elevated moisture levels, the subgrade soils should
be dried and rough graded to proposed subgrade conditions.
After the subgrade has been properly prepared, the geosynthetic fabric should be placed over the
subgrade. Aggregate base course should be placed and compacted on top of the layer of
geosynthetic layer. Terracon recommends avoiding construction traffic on the geosynthetic layer
prior to placement of the aggregate base course; it may be necessary to place the aggregate
base course out in front of the construction equipment. Once the aggregate base course has been
placed, the entire area should be proofrolled.
PVH Right Turn Lane at Lemay Ave. and Robertson St. ■ Fort Collins, Colorado
March 20, 2017 ■ Terracon Project No. 20175015
Responsive ■ Resourceful ■ Reliable PAVEMENTS 2
Pavements – Design Recommendations
Design of pavements for the project have been based on the procedures outlined in the 1993
Guideline for Design of Pavement Structures prepared by the American Association of State
Highway and Transportation Officials (AASHTO) and the Larimer County Urban Area Street
Standards (LCUASS).
Soil samples of subgrade materials selected for swell-consolidation testing swelled approximately
0.4 to 0.5 percent when wetted under an applied pressure of 150 psf which is less than the
maximum 2 percent criteria established for determining if swell-mitigation procedures in the
pavement sections are required per LCUASS standards. Therefore, swell-mitigation of the
subgrade materials prior to pavement operations is not required.
The City of Fort Collins provided traffic numbers for the proposed turn lane, which included PVH’s
development plan. An 18-kip equivalent single-axle load (ESAL) of 73,000 was used in our
pavement thickness design.
For flexible pavement design, a terminal serviceability index of 2.5 was utilized along with an inherent
reliability of 90 percent and a design life of 20 years. Using the correlated design R-value of 16,
appropriate ESAL, environmental criteria and other factors, the structural numbers (SN) of the
pavement sections were determined on the basis of the 1993 AASHTO design equation.
For access drives and approaches, a rigid pavement design analysis was completed based upon
AASHTO design procedures. Rigid pavement design is based on an evaluation of the Modulus
of Subgrade Reaction of the soils (k-value), the Modulus of Rupture of the concrete, and other
factors previously outlined. The design k-value of 100 for the subgrade soil was determined by
correlation to the laboratory test results. A modulus of rupture of 600 psi (working stress 450 psi)
was used for pavement concrete. The rigid pavement thickness for each traffic category was
determined on the basis of the AASHTO design equation.
Recommended minimum pavement sections are provided in the table below.
Traffic Area Alternative
Recommended Pavement Thicknesses (Inches)
Asphaltic
Concrete
Surface
Aggregate
Base Course 1
Portland
Cement
Concrete
Total
Turn lane A 6 8 - 14
Access drives A - - 5 5
1 A single layer of geosynthetic (Mirafi RS580i or approved equivalent) should be uniformly placed between
the subgrade and aggregate base course.
PVH Right Turn Lane at Lemay Ave. and Robertson St. ■ Fort Collins, Colorado
March 20, 2017 ■ Terracon Project No. 20175015
Responsive ■ Resourceful ■ Reliable PAVEMENTS 3
Aggregate base course (if used on the site) should consist of a blend of sand and gravel which
meets strict specifications for quality and gradation. Use of materials meeting Colorado
Department of Transportation (CDOT) Class 5 or 6 specifications is recommended for aggregate
base course. Aggregate base course should be placed in lifts not exceeding 6 inches and
compacted to a minimum of 95 percent of the maximum dry unit weight as determined by
AASHTO T99.
Asphaltic concrete should be composed of a mixture of aggregate, filler and additives (if required)
and approved bituminous material. The asphalt concrete should conform to approved mix
designs stating the Superpave properties, optimum asphalt content, job mix formula and
recommended mixing and placing temperatures. Aggregate used in asphalt concrete should
meet particular gradations. Material meeting CDOT Grading S specifications or equivalent is
recommended for asphalt concrete. Mix designs should be submitted prior to construction to
verify their adequacy. Asphalt material should be placed in maximum 3-inch lifts and compacted
within a range of 92 to 96 percent of the theoretical maximum (Rice) density (ASTM D2041).
Where rigid pavements are used, the concrete should be obtained from an approved mix design
with the following minimum properties meeting CDOT Class P, produced from an approved mix
design with the following minimum properties:
Properties Value
Compressive strength 4,200 psi
Cement type Type I or II portland cement
Entrained air content (%) 4 to 8
Concrete aggregate Minimum 55 percent AASHTO M43 size No.357 or
No. 467
Concrete should be deposited by truck mixers or agitators and placed a maximum of 90 minutes
from the time the water is added to the mix. Longitudinal and transverse joints should be provided
as needed in concrete pavements for expansion/contraction and isolation per ACI 325. The
location and extent of joints should be based upon the final pavement geometry. Joints should
be sealed to prevent entry of foreign material and doweled where necessary for load transfer.
Although not required for structural support, a minimum 4-inch thick aggregate base course layer
is recommended for the PCC pavements to help reduce the potential for slab curl, shrinkage
cracking, and subgrade “pumping” through joints. Proper joint spacing will also be required for
PCC pavements to prevent excessive slab curling and shrinkage cracking.
PVH Right Turn Lane at Lemay Ave. and Robertson St. ■ Fort Collins, Colorado
March 20, 2017 ■ Terracon Project No. 20175015
Responsive ■ Resourceful ■ Reliable PAVEMENTS 4
Pavement performance is affected by its surroundings. In addition to providing preventive
maintenance, the civil engineer should consider the following recommendations in the design and
layout of pavements:
n Site grades should slope a minimum of 2 percent away from the pavements;
n The subgrade and the pavement surface have a minimum 2 percent slope to promote proper
surface drainage;
n Consider appropriate edge drainage and pavement under drain systems;
n Install pavement drainage surrounding areas anticipated for frequent wetting;
n Install joint sealant and seal cracks immediately;
n Seal all landscaped areas in, or adjacent to pavements to reduce moisture migration to
subgrade soils; and
n Placing compacted, low permeability backfill against the exterior side of curb and gutter.
Pavements – Construction Considerations
Openings in pavement, such as landscape islands, are sources for water infiltration into
surrounding pavements. Water collects in the islands and migrates into the surrounding subgrade
soils thereby degrading support of the pavement. This is especially applicable for islands with
raised concrete curbs, irrigated foliage, and low permeability near-surface soils. The civil design
for the pavements with these conditions should include features to restrict or to collect and
discharge excess water from the islands. Examples of features are edge drains connected to the
storm water collection system or other suitable outlet and impermeable barriers preventing lateral
migration of water such as a cutoff wall installed to a depth below the pavement structure.
Pavements – Maintenance
Preventative maintenance should be planned and provided for an ongoing pavement
management program in order to enhance future pavement performance. Preventive
maintenance consists of both localized maintenance (e.g. crack and joint sealing and patching)
and global maintenance (e.g. surface sealing). Preventative maintenance is usually the first
priority when implementing a planned pavement maintenance program and provides the highest
return on investment for pavements.
PVH Right Turn Lane at Lemay Ave. and Robertson St. ■ Fort Collins, Colorado
March 20, 2017 ■ Terracon Project No. 20175015
Responsive ■ Resourceful ■ Reliable GENERAL COMMENTS 1
GENERAL COMMENTS
Our work is conducted with the understanding of the project as described in the proposal, and will
incorporate collaboration with the design team prior to completing our services. Terracon has
requested verification of all stated assumptions. Revision of our understanding to reflect actual
conditions important to our work will be based on these verifications and will be reflected in the
final report. The design team should collaborate with Terracon to confirm these assumptions.
The design team should also collaborate with Terracon to prepare the final design plans and
specifications. This facilitates the incorporation of our opinions related to implementation of our
geotechnical recommendations.
Our analysis and opinions are based upon our understanding of the geotechnical conditions in
the area, the data obtained from the site exploration performed and from our understanding of the
project. Variations will occur between exploration point locations, across the site, or due to the
modifying effects of construction or weather. The nature and extent of such variations may not
become evident until during or after construction. So, Terracon should be retained to provide
observation and testing services during grading, excavation, foundation construction and other
earth-related construction phases of the project. If variations appear, we can provide further
evaluation and supplemental recommendations. If variations are noted in the absence of our
observation and testing services on-site, we should be immediately notified so that we can provide
evaluation and supplemental recommendations.
Our scope of services does not include either specifically or by implication any environmental or
biological (e.g., mold, fungi, bacteria) assessment of the site or identification or prevention of
pollutants, hazardous materials or conditions. If the owner is concerned about the potential for
such contamination or pollution, other studies should be undertaken.
Our services and any correspondence are intended for the exclusive use of our client for specific
application to the project discussed and are accomplished in accordance with generally accepted
geotechnical engineering practices. No warranties, either express or implied, are intended or
made.
Site characteristics as provided are for design purposes and not to estimate excavation cost. Any
use of our report in that regard is done at the sole risk of the excavating cost estimator as there
may be variations on the site that are not apparent in the data that could significantly impact
excavation cost. Any parties charged with estimating excavation costs should seek their own site
characterization for that specific purposes to obtain the specific level of detail necessary for
costing. Site safety, and cost estimating including, excavation support, and dewatering
requirements/design are the responsibility of others. In the event that changes in the nature,
design, or location of the project are planned, our conclusions and recommendations shall not be
considered valid unless we review the changes and either verify or modify our conclusions in
writing.
SITE LOCATION MAP
PVH Lemay Right Turn Lane at Robertson
Street
South Lemay Avenue and Robertson Street
Fort Collins, CO
TOPOGRAPHIC MAP IMAGE COURTESY OF THE U.S. GEOLOGICAL SURVEY
QUADRANGLES INCLUDE: FORT COLLINS, CO (1984).
1901 Sharp Point Dr Ste C
Fort Collins, CO 80525-4429
20175015
Project Manager:
Drawn by:
Checked by:
Approved by:
KFS
EDB
EDB
1”=2,000’
3/6/17
Project No.
Scale:
File Name:
Date:
EDB
SITE
LEGEND
B1 Proposed boring locations
Temporary benchmark, southwest corner of
TBM concrete foundation (100.0)
EXPLORATION PLAN
PVH Lemay Right Turn Lane at Robertson
Street
South Lemay Avenue and Robertson Street
Fort Collins, CO
1901 Sharp Point Dr Ste C
Fort Collins, CO 80525-4429
DIAGRAM IS FOR GENERAL LOCATION ONLY, AND IS
NOT INTENDED FOR CONSTRUCTION PURPOSES
20175015
AERIAL PHOTOGRAPHY PROVIDED
BY MICROSOFT BING MAPS
KFS
EDB
EDB
AS SHOWN
3/6/17
Scale:
Project Manager:
Drawn by:
Checked by:
Approved by:
Project No.
File Name:
Date:
EDB
7-7
2-2
2-2-3
N=5
0.5
10.5
GRASS/ORGANICS, 6 inches
SANDY LEAN CLAY (CL), brown, soft to stiff
increased sand content; reddish brown
Boring Terminated at 10.5 Feet
18
14
20
107
94
96.5
86.5
+0.5/150
GRAPHIC LOG
Stratification lines are approximate. In-situ, the transition may be gradual. Hammer Type: Automatic
THIS BORING LOG IS NOT VALID IF SEPARATED FROM ORIGINAL REPORT. GEO SMART LOG-NO WELL 20175015.GPJ TERRACON_DATATEMPLATE.GDT 3/16/17
FIELD TEST
RESULTS
DEPTH
LOCATION
Latitude: 40.571° Longitude: -105.05783°
See Exploration Plan
Page 1 of 1
Advancement Method:
4" Continuous flight auger
Abandonment Method:
Backfilled with flow fill
1901 Sharp Point Dr Ste C
Fort Collins, CO
Notes:
Project No.: 20175015
Drill Rig: Geoprobe
Boring Started: 3/6/2017
BORING LOG NO. B-1
CLIENT: Poudre Valley Hospital
Driller: T. Pocock
Boring Completed: 3/6/2017
PROJECT: PVH Right Turn Lane at Lemay Ave. and
Robertson St.
Lemay Avenue at Robertson Street
Fort Collins, Colorado
SITE:
No free water observed
WATER LEVEL OBSERVATIONS
PERCENT FINES
WATER
CONTENT (%)
DRY UNIT
WEIGHT (pcf)
LL-PL-PI
ATTERBERG
LIMITS
ELEVATION (Ft.)
Surface Elev.: 97.2 (Ft.)
SAMPLE TYPE
5-5
2-2
2-2-2
N=4
0.5
10.5
GRASS/ORGANICS, 6 inches
SANDY LEAN CLAY (CL), brown, soft to medium stiff
increased sand content
Boring Terminated at 10.5 Feet
17
18
23
105
101
95.5
85.5
+0.4/150
GRAPHIC LOG
Stratification lines are approximate. In-situ, the transition may be gradual. Hammer Type: Automatic
THIS BORING LOG IS NOT VALID IF SEPARATED FROM ORIGINAL REPORT. GEO SMART LOG-NO WELL 20175015.GPJ TERRACON_DATATEMPLATE.GDT 3/16/17
FIELD TEST
RESULTS
DEPTH
LOCATION
Latitude: 40.57083° Longitude: -105.05783°
See Exploration Plan
Page 1 of 1
Advancement Method:
4" Continuous flight auger
Abandonment Method:
Backfilled with flow fill
1901 Sharp Point Dr Ste C
Fort Collins, CO
Notes:
Project No.: 20175015
Drill Rig: Geoprobe
Boring Started: 3/6/2017
BORING LOG NO. B-2
CLIENT: Poudre Valley Hospital
Driller: T. Pocock
Boring Completed: 3/6/2017
PROJECT: PVH Right Turn Lane at Lemay Ave. and
Robertson St.
Lemay Avenue at Robertson Street
Fort Collins, Colorado
SITE:
No free water observed
WATER LEVEL OBSERVATIONS
PERCENT FINES
WATER
CONTENT (%)
DRY UNIT
WEIGHT (pcf)
LL-PL-PI
ATTERBERG
LIMITS
ELEVATION (Ft.)
Surface Elev.: 95.9 (Ft.)
SAMPLE TYPE
0
10
20
30
40
50
60
0 20 40 60 80 100
CL or OL CH or OH
ML or OL
MH or OH
Boring ID Depth PL PI Fines
P
L
A
S
T
I
C
I
T
Y
I
N
D
E
X
LIQUID LIMIT
"U" Line
SANDY LEAN CLAY
AASHTO
"A" Line
31 19 12 67
LL
Bulk
ATTERBERG LIMITS RESULTS
ASTM D4318
0 - 4
Description
A-6 (6)
PROJECT NUMBER: 20175015
PROJECT: PVH Right Turn Lane at Lemay Ave.
and Robertson St.
SITE: Lemay Avenue at Robertson Street
Fort Collins, Colorado CLIENT: Poudre Valley Hospital
1901 Sharp Point Dr Ste C
Fort Collins, CO
LABORATORY TESTS ARE NOT VALID IF SEPARATED FROM ORIGINAL REPORT. ATTERBERG LIMITS-AASHTO 20175015.GPJ TERRACON_DATATEMPLATE.GDT 3/16/17
CL-ML
0
5
10
15
20
25
30
35
40
45
50
55
60
65
70
75
80
85
90
95
100
100 10 1 0.1 0.01 0.001
6 16
20 30
40
GRAIN SIZE DISTRIBUTION
U.S. SIEVE OPENING IN INCHES
Boring ID Depth USCS Classification AASHTO Classification LL
D100 D30
Cc Cu
Boring ID Depth D60 %Clay
31
U.S. SIEVE NUMBERS
SILT OR CLAY
4 1.5 50
6 8 200
10 14
19 3.9 29.3
Bulk
1 4
3/4 1/2
60
fine
HYDROMETER
PL PI
D10 %Gravel %Sand %Silt
19 12
3/8 3 100
3 2 140
COBBLES GRAVEL SAND
coarse medium
GRAIN SIZE IN MILLIMETERS
PERCENT FINER BY WEIGHT
coarse fine
SANDY LEAN CLAY (CL) A-6 (6)
Bulk 66.8
0 - 4
0 - 4
ASTM D422 / ASTM C136
PROJECT NUMBER: 20175015
-2.0
-1.5
-1.0
-0.5
0
0.5
1.0
1.5
2.0
100 1,000 10,000
AXIAL STRAIN, %
PRESSURE, psf
SWELL CONSOLIDATION TEST
ASTM D4546
NOTES: Sample exhibited 0.5 percent swell when inundated at an applied pressure of 150 psf.
Lemay Ave. and Robertson St.
SITE: Lemay Avenue at Robertson Street
Fort Collins, Colorado
PROJECT: PVH Right Turn Lane at
PROJECT NUMBER: 20175015
CLIENT: Poudre Valley Hospital
1901 Sharp Point Dr Ste C
Fort Collins, CO
Specimen Identification Classification , pcf
107 18
WC, %
B-1 2 - 3 ft Lean CLAY with sand
LABORATORY TESTS ARE NOT VALID IF SEPARATED FROM ORIGINAL REPORT. 65155045-SWELL/CONSOL 20175015.GPJ TERRACON_DATATEMPLATE.GDT 3/16/17
-2.0
-1.5
-1.0
-0.5
0
0.5
1.0
1.5
2.0
100 1,000 10,000
AXIAL STRAIN, %
PRESSURE, psf
SWELL CONSOLIDATION TEST
ASTM D4546
NOTES: Sample exhibited 0.4 percent swell when inundated at an applied load of 150 psf.
PROJECT: PVH Right Turn Lane at
Lemay Ave. and Robertson St. PROJECT NUMBER: 20175015
SITE: Lemay Avenue at Robertson Street
Fort Collins, Colorado CLIENT: Poudre Valley Hospital
1901 Sharp Point Dr Ste C
Fort Collins, CO
Specimen Identification Classification , pcf
101 18
WC, %
B-2 4 - 5 ft Lean CLAY with sand
LABORATORY TESTS ARE NOT VALID IF SEPARATED FROM ORIGINAL REPORT. 65155045-SWELL/CONSOL 20175015.GPJ TERRACON_DATATEMPLATE.GDT 3/16/17
1901 Sharp Point Drive Suite C
Fort Collins, Colorado 80525
(970) 484-0359 FAX (970) 484-0454
CLIENT: PVH DATE OF TEST: 3/8/17
PROJECT: PVH right turn lane at Lemay Ave. and Robertson St.
LOCATION: Bulk @ 0'-4'
TERRACON NO. 20175015 CLASSIFICATION: Sandy Lean Clay (CL)
TEST SPECIMEN NO. 1 2 3
COMPACTION PRESSURE (PSI) 45 80 120
DENSITY (PCF) 97.3 100.8 106.0
MOISTURE CONTENT (%) 25.9 24.4 21.1
EXPANSION PRESSURE (PSI) -1.05 -0.87 -1.02
HORIZONTAL PRESSURE @ 160 PSI 143 135 127
SAMPLE HEIGHT (INCHES) 2.48 2.48 2.43
EXUDATION PRESSURE (PSI) 190.6 238.9 318.5
CORRECTED R-VALUE 6.0 10.6 17.8
UNCORRECTED R-VALUE 6.0 10.6 18.4
R-VALUE @ 300 PSI EXUDATION PRESSURE = 16
AASHTO T190
PRESSURE OF COMPACTED SOIL
RESISTANCE R-VALUE & EXPANSION
SAMPLE DATA TEST RESULTS
0
10
20
30
40
50
60
70
80
90
100
0 100 200 300 400 500 600 700 800
R-VALUE
EXUDATION PRESSURE - PSI
3/12/2017 20175015
PVH Right Turn Lane at Lemay Ave. and Robertson St. Fort Collins, Colorado
500 to 1,000
> 8,000
4,000 to 8,000
2,000 to 4,000
1,000 to 2,000
less than 500
Unconfined Compressive Strength
Qu, (psf)
Modified
Dames &
Moore Ring
Sampler
Grab
Sample
Standard
Penetration
Test
Trace
PLASTICITY DESCRIPTION
Water levels indicated on the soil boring logs are
the levels measured in the borehole at the times
indicated. Groundwater level variations will occur
over time. In low permeability soils, accurate
determination of groundwater levels is not possible
with short term water level observations.
DESCRIPTION OF SYMBOLS AND ABBREVIATIONS
GENERAL NOTES
> 30
11 - 30
Low 1 - 10
Non-plastic
Plasticity Index
#4 to #200 sieve (4.75mm to 0.075mm
Boulders
Cobbles 12 in. to 3 in. (300mm to 75mm)
Gravel 3 in. to #4 sieve (75mm to 4.75 mm)
Sand
Silt or Clay Passing #200 sieve (0.075mm)
Particle Size
Water Level After
a Specified Period of Time
Water Level After a
Specified Period of Time
Water Initially
Encountered
Soil classification is based on the Unified Soil Classification System. Coarse Grained Soils have more than 50% of their dry
weight retained on a #200 sieve; their principal descriptors are: boulders, cobbles, gravel or sand. Fine Grained Soils have less
than 50% of their dry weight retained on a #200 sieve; they are principally described as clays if they are plastic, and silts if they
are slightly plastic or non-plastic. Major constituents may be added as modifiers and minor constituents may be added
according to the relative proportions based on grain size. In addition to gradation, coarse-grained soils are defined on the basis
of their in-place relative density and fine-grained soils on the basis of their consistency.
Unless otherwise noted, Latitude and Longitude are approximately determined using a hand-held GPS device. The accuracy of
such devices is variable. Surface elevation data annotated with +/- indicates that no ctual topographical survey was conducted
to confirm the surface elevation. Instead, the surface elevation was approximately determined from topographic maps of the
area.
GRAIN SIZE TERMINOLOGY
RELATIVEFINES PROPORTIONS OF SAND AND GRAVEL RELATIVE PROPORTIONS OF
DESCRIPTIVE SOIL CLASSIFICATION
UNIFIED SOIL CLASSIFICATION SYSTEM
Criteria for Assigning Group Symbols and Group Names Using Laboratory Tests A
Soil Classification
Group
Symbol Group Name B
Coarse Grained Soils:
More than 50% retained
on No. 200 sieve
Gravels:
More than 50% of
coarse fraction retained
on No. 4 sieve
Clean Gravels:
Less than 5% fines C
Cu 4 and 1 Cc 3 E GW Well-graded gravel F
Cu 4 and/or 1 Cc 3 E GP Poorly graded gravel F
Gravels with Fines:
More than 12% fines C
Fines classify as ML or MH GM Silty gravel F,G,H
Fines classify as CL or CH GC Clayey gravel F,G,H
Sands:
50% or more of coarse
fraction passes No. 4
sieve
Clean Sands:
Less than 5% fines D
Cu 6 and 1 Cc 3 E SW Well-graded sand I
Cu 6 and/or 1 Cc 3 E SP Poorly graded sand I
Sands with Fines:
More than 12% fines D
Fines classify as ML or MH SM Silty sand G,H,I
Fines classify as CL or CH SC Clayey sand G,H,I
Fine-Grained Soils:
50% or more passes the
No. 200 sieve
Silts and Clays:
Liquid limit less than 50
Inorganic:
PI 7 and plots on or above “A” line J CL Lean clay K,L,M
PI 4 or plots below “A” line J ML Silt K,L,M
Organic:
Liquid limit - oven dried
0.75 OL
Organic clay K,L,M,N
Liquid limit - not dried Organic silt K,L,M,O
Silts and Clays:
Liquid limit 50 or more
Inorganic:
PI plots on or above “A” line CH Fat clay K,L,M
PI plots below “A” line MH Elastic Silt K,L,M
Organic:
Liquid limit - oven dried
0.75 OH
Organic clay K,L,M,P
Liquid limit - not dried Organic silt K,L,M,Q
Highly organic soils: Primarily organic matter, dark in color, and organic odor PT Peat
A Based on the material passing the 3-inch (75-mm) sieve
B If field sample contained cobbles or boulders, or both, add “with cobbles
or boulders, or both” to group name.
C Gravels with 5 to 12% fines require dual symbols: GW-GM well-graded
gravel with silt, GW-GC well-graded gravel with clay, GP-GM poorly
graded gravel with silt, GP-GC poorly graded gravel with clay.
D Sands with 5 to 12% fines require dual symbols: SW-SM well-graded
sand with silt, SW-SC well-graded sand with clay, SP-SM poorly graded
sand with silt, SP-SC poorly graded sand with clay
E Cu = D60/D10 Cc =
10 60
2
30
D x D
(D )
F If soil contains 15% sand, add “with sand” to group name.
G If fines classify as CL-ML, use dual symbol GC-GM, or SC-SM.
H If fines are organic, add “with organic fines” to group name.
I If soil contains 15% gravel, add “with gravel” to group name.
J If Atterberg limits plot in shaded area, soil is a CL-ML, silty clay.
K If soil contains 15 to 29% plus No. 200, add “with sand” or “with gravel,”
whichever is predominant.
L If soil contains 30% plus No. 200 predominantly sand, add “sandy” to
group name.
M If soil contains 30% plus No. 200, predominantly gravel, add
“gravelly” to group name.
N PI 4 and plots on or above “A” line.
O PI 4 or plots below “A” line.
P PI plots on or above “A” line.
Q PI plots below “A” line.
LOCATION AND ELEVATION NOTES
SAMPLING WATER LEVEL FIELD TESTS
N
(HP)
(T)
(DCP)
UC
(PID)
(OVA)
Standard Penetration Test
Resistance (Blows/Ft.)
Hand Penetrometer
Torvane
Dynamic Cone Penetrometer
Unconfined Compressive
Strength
Photo-Ionization Detector
Organic Vapor Analyzer
Medium
Over 12 in. (300 mm) 0
>12
5-12
<5
Percent of
Dry Weight
Major Component of Sample Term
Modifier
With
Trace
Descriptive Term(s) of
other constituents
Modifier >30
<15
Percent of
Dry Weight
Descriptive Term(s) of
other constituents
With 15-29
High
Descriptive Term
(Consistency)
0 - 6
Standard Penetration or
N-Value
Blows/Ft.
CONSISTENCY OF FINE-GRAINED SOILS
Hard
Very Loose
Loose
Medium Dense
Dense
Very Dense
Descriptive Term
(Density)
Standard Penetration
or N-Value
Blows/Ft.
Ring Sampler
Blows/Ft.
0 - 3
4 - 9 7 - 18
10 - 29 19 - 58
30 - 50 59 - 98
> 30
> 50 > 99 Very Stiff
Stiff
Medium Stiff
Soft
Very Soft
(50% or more passing the No. 200 sieve.)
Consistency determined by laboratory shear strength testing, field visual-manual
procedures or standard penetration resistance
STRENGTH TERMS
RELATIVE DENSITY OF COARSE-GRAINED SOILS
(More than 50% retained on No. 200 sieve.)
Density determined by Standard Penetration Resistance
0 - 1
2 - 4
4 - 8
8 - 15
15 - 30
PROJECT: PVH Right Turn Lane at Lemay Ave.
and Robertson St.
SITE: Lemay Avenue at Robertson Street
Fort Collins, Colorado CLIENT: Poudre Valley Hospital
1901 Sharp Point Dr Ste C
Fort Collins, CO
LABORATORY TESTS ARE NOT VALID IF SEPARATED FROM ORIGINAL REPORT. GRAIN SIZE: USCS & AASHTO COMBINED 20175015.GPJ TERRACON_DATATEMPLATE.GDT 3/16/17
WATER LEVEL
OBSERVATIONS
DEPTH (Ft.)
5
10
SWELL-CONSOL /
LOAD (%/psf)
WATER LEVEL
OBSERVATIONS
DEPTH (Ft.)
5
10
SWELL-CONSOL /
LOAD (%/psf)