July 25, 2012
Glen Schlueter
City of Fort Collins Stormwater
700 Wood Street
Fort Collins, CO 80522
RE: 2545 Research Blvd Expansion
Dear Glen,
The owners of the existing building at 2545 Research Boulevard at proposing to construct a 4600
square foot expansion on the northeast side of the building In order to construct this addition, the
existing drive through lanes, canopy and access drive will be removed. It was calculated that
approximately 11,500 square feet of imperviousness will be removed and approximately 7,000
square feet of imperviousness will be constructed resulting in a net reduction of imperviousness
on site of 4,500 square feet. Because a reduction in imperviousness is anticipated, no further
drainage calculations have been completed and no additional detention will be provided.
The majority of the runoff from this building will discharge onto the landscaped area and flow to
the existing on site storm or to the existing street. This flow through the landscaping will
provide some level of water quality enhancement for this runoff.
I appreciate your time and consideration in reviewing this submittal. Please call if you have any
questions.
MA120065 2545 Research Blvd July 6, 2012
Comments on utility plans:
The two following notes need to be added to the overall utility plan sheet:
• Limits of street cut are approximate. Final limits are to be determined
in the field by the City Engineering Inspector. All repairs to be in
accordance with City street repair standards.
• Damaged curb, gutter and sidewalk existing prior to construction, as
well as streets, sidewalks, curbs and gutters, destroyed, damaged or
removed due to construction of this project, shall be replaced or
restored in like kind at the Developer's expense prior to the
acceptance of completed improvements and/or prior to the issuance of
the first Certificate of Occupancy. The limits of the repairs will be
identified in the field by the City Engineering Inspector prior to and
over the course of the project and will not be shown on the plans.
Detail 1601 also needs to be added to the plans.
By: Sheri Langenberger