HomeMy WebLinkAboutASPEN HEIGHTS - Filed GC-GENERAL CORRESPONDENCE - 2016-06-09City of
F6rt Collins
September 23, 2013
Larry C. Owen, P.E.
Owen Consulting Group, Inc.
3715 Shallow Pond Dr.
Fort Collins, Co 80528
Planning, Development & Transportation
Engineering Department
281 North College Avenue
P.O. Box 580
Fort Collins, CO 80522.0580
970.221.6605
970.221.6378 - fax
fcgov. com/engineering
Re: Aspen Heights - variance for driveway setback and cover over utility lines in the streets
Dear Larry,
This letter is in response to the two variance request letters sent to me dated July 1, 2013 regarding a variance
request to the minimum off street parking setback distance and (Fig 19-6) and to Section 12.2.2 regarding the
minimum depth requirement for utilities.
I will address each of the variance requests as I understand them to be:
1. The variance request to reduce the parking setback from 50 feet to 40 feet is granted.
2. The variance request to reduce the cover over the NECCO pipes under Lupine Street to 1.6 feet (from top
of pipe to top of asphalt at the north flowline) is granted with the condition that the street area over the
pipes is constructed in concrete from a point approximately 20 feet east of the pipes to a point
approximately 20 feet west of the inlets located west of the NECCO pipes.
3. The variance request to reduce the cover over the storm pipe crossing on Blue Spruce Drive, just north of
New Vine Drive, to 2.5 feet is granted pr6vided that the concrete cross pan at this intersection is extended
north so that the concrete street extends approximately 20 feet north of the storm pipe.
4. The variance request to reduce the cover over the interim storm pipe in Redwood Street is granted on the
basis that at such time as the ultimate improvements are constructed that the portion of the pipe system that
does not meet minimum cover requirements is removed at that time.
These requests does not set precedence or change the application of our design standards in other situations. If you
have any questions, please contact me at 221-6573.
Sincerely,
Sheri L. Langenberger, P.E.
Attachments
cc: Ted Shepard, City of Fort Collins
file
Culvert Calculator Report
Aspen Heights - Lupine Street Culverts
Solve For. Headwater Elevation
Culvert Summary
Allowable HW Elevation
4,964.00 ft
Headwater Depth/Height
1.81
Computed Headwater Elev,
4,962.81 ft
Discharge
159.40 efs
Inlet Control HW Elev.
4.962.44 ft
Taiiwater Elevation
4,960.54 ft
Outlet Control HW Elev.
4,962.81 ft
Control Type
Outlet Control
Grades
Upstream Invert
Length
4,959.18 ft
124.00 ft
Downstream Invert
Constructed Slope
4,958.80 ft
0.003065 ft/ft
Hydraulic Profile
Profile CompositeM2PressureProfile
Slope Type Mild
Flow Regime Subcritical
Velocity Downstream 8.44 ft/s
Depth, Downstream
Normal Depth
Critical Depth
Critical Slope
1.74 it
N/A it
1.74 ft
0.007616 ft/ft
Section
Section Shape Horizontal Ellipse
Section Material Concrete
Section Size 24x38 inch
Number Sections 4
Mannings Coefficient
Span
Rise
0.013
3.15 ft
2.00 ft
Outlet Control Properties
Outlet Control HW Elev.
Ke
4,962.81 ft
0.20
Upstream Velocity Head
Entrance Loss
0.95 It
0.19 ft
Inlet Control Properties
Inlet Control HW Elev. 4,962.44 ft
Grooieiehlsy"h headwall (horizontal ellipse)
K 0.00180
M 2.50000
C 0.02920
Y 0.74000
Flow Control
Area Full
HDS 5 Chart
HDS 5 Scale
Equation Form
Submerged
20.4 ft2
29
2
1
Project Engineer. LARRYOWEN8BBFWdministrator
main channel culverts under lupine - revised 12-02... CAME Academic SitsExton CulvertMaster v3.3 [03.03.00.041
Culvert Calculator Report
Aspen Heights - Lupine Street Culverts
Solve For. Headwater Elevation
Culvert Summary
Allowable HW Elevation
Computed Headwater Elevi
Inlet Control HW Elev.
Outlet Control HW Elev.
4,964.00 ft
4,965.77 It
4,964.93 ft
4,965.77 ft
Headwater Depth/Height
Discharge
Tailwater Elevation
Control Type
3.30
239.67 cfs
4,960.98 it
Outlet Control
Grades
Upstream Invert
Length
4,959.18 it
124.00 it
Downstream Invert
Constructed Slope
4,958.80 it
0.003065 Wit
Hydraulic Profile
Profile PressureProfile
Slope Type N/A
Flow Regime N/A
Velocity Downstream 11.75 ft/s
Depth, Downstream
Normal Depth
Critical Depth
Critical Slope
2.18 it
N/A ft
1.93 ft
0.017022 ft/ft
Section
Section Shape Horizontal Ellipse
Section Material Concrete
Section Size 2038 inch
Number Sections 4
Mannings Coefficient
Span
Rise
0.013
3.15 it
2.00 It
Outlet Control Properties
Outlet Control HW Elev.
Ke
4,985.77 It
0.20
Upstream Velocity Head
Entrance Loss
2.15 It
0.43 it
Inlet Control Properties
Inlet Control HW Elev. 4,964.93 It
Gkbtf XW projecting (horizontal ellipse)
K 0.00450
M 2.00000
C 0.03170
Y 0.69000
Flow Control
Area Full
HDS 5 Chart
HDS 5 Scale
Equation Form
Submerged
20.4 f 2
29
3
1
Project Engineer: LARRYOWENSBBFkAdministrator
main channel culverts under lupine - revised 12-02... CAME Academic 81teExton CulvertMaster v3.3 (03.03.00.04]
C..1.+� 1YrfZf'
Air I AW 0,,440W'7dGE 11A1
Culvert Calculator Report
Aspen Heights - Lupine Street Culverts
Solve For: Discharge
Culvert Summary
Allowable HW Elevation
4,964.00 ft
Computed Headwater Elevi
4,964.00 ft
Inlet Control HW Elev.
4,963.20 ft
Outlet Control HW Elev.
4,964.00 ft
Grades
Headwater Depth/Height 2.41
Discharge 190.28 cis
Tailwater Elevation 4,960.98 ft
Control Type Outlet Control
Upstream Invert 4,959.18 ft Downstream Invert 4,958.80 ft
Length 124.00 ft Constructed Slope 0.003065 ft/ft
Hydraulic Profile
Profile
PressureProttle
Depth, Downstream
2.18 ft
Slope Type
N/A
Normal Depth
N/A ft
Flow Regime
WA
Critical Depth
1.84 ft
Velocity Downstream
9.33 NO
Critical Slope
0.010555 ft(ft
Section
Section Shape Horizontal Ellipse
Mannings Coefficient
0.013
Section Material
Concrete
Span
3.15 ft
Section Size
24x38 inch
Rise
2.00 ft
Number Sections
4
Outlet Control Properties
Outlet Control HW Elev.
4,964.00 ft
Upstream Velocity Head
1.35 ft
Ke
0.20
Entrance Loss
0.27 ft
Inlet Control Properties
Inlet Control HW Elev.
4,963.20 ft
Flow Control
Submerged
Groalslairl5joh headwall (horizontal ellipse)
Area Full
20.4 ft'
K
0.00180
HDS 5 Chart
29
M
2.50000
HDS 5 Scale
2
C
0.02920
Equation Form
1
Y
0.74000
Project Engineer. LARRYOWEN8BBFWdministrator
main channel culverts under lupine - revised 12-02... CAIHE Academic SiteExton CulvertMaster v3.3 [03.03.00.04)
Aspen Heights - Street Overtopping at Lupine Culverts - Interim
Project Description
Solve For Headwater Elevation
Input Data
Discharge
49.39
ft'!s
Crest Elevation
4964.00
ft
Tailwater Elevation
4960.98
ft
Crest Surface Type Paved
Crest Breadth
30.00
ft
Crest length
55.00
ft
Results
Headwater Elevation
4964.45
ft
Headwater Height Above Crest
0.45
ft
Tailwater Height Above Crest
-3.02
ft
Weir Coefficient
3.00
US
Submergence Factor
1.00
Adjusted Weir Coefficient
3.00
US
Flow Area
24.61
ft2
Velocity
2.01
ft/s
Wetted Perimeter
55.89
ft
Top Width
55.00
ft
61261201312:43:20 PM
Bentley Systems, Inc. Haested Methods SO M0ti0061wMaster V814SELECTsedes 1) [08.11.01.03)
27 Slemons, Company Drive Suite 200 W Watertown, CT 06786 USA +1-203-766-1666 Page 1 of 1
INTERIM OUTFALL CROSSING OF REDWOOD ST.
ALTERNATE PROFILES
Alignment — (STORM 500) — (22) STA:—0+50.00 THRU 1+50.00
-0+50
4970 -4--
STATION
TOP = 4956.75t
IE IN - 4952.75
IE IN = 4952.75
IE OUT = 4952.09
PIPE - (505�
90 LF OF 19 X3O' FRCP
4960 a O.2O9 GRADE.
N
M11
STOW MANHOLE 11MM,
TOP = 4957.25t
IE IN = 4951.41
IE IN = 4951.90
IE OUT = 4951.41
FFPIIPE - (316)
' PVC
AN. SEWER
4
1+00 1+50
I ' 4970
4960
mm=�11�
:in■■■■
�.i11�1A11■
=�■■WPAI �■■ - -.
PIPE - _(Mn--L
O 0.5Ox GRAD
r
INLET - (5O6)
STA 1+30 06
C DITCH INLET
M = 4954.64f
UT = 4952.93
4940 4940
—0+5b 0+00 1+00 1+50
STATION
,b-�
arm w
reset-e- ..-yn, `v�
COWEN
CONSULTING
MEMORANDUM
To: Meeting participants per introductory paragraph
CC:
From: Larry C. Owen, P.E.
Date: May 17, 2013
Proj. No.: 11-358 Project Name: Aspen Heights
Subject: Mtg with City Staff re Dry Creek Floodplain and CLOMR (5-14-13)
Following are notes of a meeting with City staff regarding the Dry Creek floodplain and the need
and responsibility for preparation of a Conditional Letter Of Map Revision (CLOMR) addressing
the impacts to the currently mapped floodplain due to construction of road and related
improvements within the floodway. Attendees at the meeting included, from the City of Fort
Collins, Marsh Hilmes-Robinson, Jon Haukaas, Glen Schlueter, Sheri Langenberger; from
Poudre Fire Authority, Jim Lynxwiler; from Aspen Heights, Ryan Fetgatter, Robert Scholz, Fred
Munoz; and from the consultant team, Lucia Liley, Rich Shannon, Larry Owen.
1. City Staff opened with the position that the CLOMR must be approved before the Utilities
Plans can be approved, and no construction of public improvements can be commenced
until the Utilities Plans are approved.
2. Construction of New Vine Drive and Redwood Street will impact the area mapped by FEMA
as floodway, and thus a CLOMR is required.
3. The CLOMR must reflect the changing hydrology upstream of the mapped floodway, as well
as the impacts to the floodway due to surface changes within the floodway associated with
the proposed construction of New Vine Drive and Redwood Street.
4. The analysis and engineering associated with the CLOMR must also consider possible
impacts to downstream and adjacent property. Changes due to construction in the existing
floodway / floodplain cannot exacerbate flooding in the Old Town North property or any
properties downstream of Redwood Street and the Lake Canal.
a. Downstream property owners (Raptor Center, Alta Vista subdivision) are apparently
concerned about putting water back into the Dry Creek channel.
b. Seme-The Raptor Center, a downstream property owners hasve made modifications to
the Dry Creek channel, supposedly to alleviate seepage, and these modifications niay
have Fedused eliminated the low flow the -capacity of the channel so the to Gamey
anticipated larger storm flows will enter the old Dry Creek channel only after the Lake
Canal capacity is exceeded.
5. The engineering associated with the construction of New Vine Drive and Redwood Street
must provide for conveyance of flood flows beneath Redwood St., but not beneath the Lake
Canal
a. Low flows can be discharged into the Lake Canal, as happens now.
3715 Shallow Pond Dr., Fort Collins, CO 80528 - Phone (970) 226-0264 • Fax (970) 226-3760
Aspen Heights Student Housing
Notes of 5-14-13 Mtg with City Staff re CLOMR
Page 2 of 4
b. High flows can overtop the Lake Canal (assumes that the Lake Canal will be flowing at
capacity at this stage) and pass into the downstream Dry Creek channel, again as
currently happens.
c. These discharge scenarios are considered to be historic conditions.
6. The Developer's team expressed concern that the time required to process the CLOW
through the City and FEMA reviews would unduly delay, and potentially kill the student
housing project.
a. It was pointed out that because of the student housing nature of this project, there is an
inflexible completion date for the project.
b. If the houses comprising the project are not ready for occupancy in August of the target
year, prior to students returning to start classes, the next opportunity to lease the
accommodations is one full year later. Such a delay would be a fatal flaw.
7. The consultant team reiterated their previous understanding that processing of the CLOMR
and City review and approval of the construction activities that would impact the current
floodplain (specifically, construction of New Vine Drive and Redwood Street) could be
separated from the remainder of the project (possibly in a separate stand alone filing), such
that approval and construction of the public and private improvements outside the floodplain
boundaries could proceed concurrent with the processing of the CLOMR. City staff agreed
that this is possible only through the PDP stage. The utility plans must be completed, which
includes the CLOMR and final design approval before the project can proceed to the DCP
(Development Construction Permit) stage.
8. The consultant team stated that the proposed improvements to New Vine Drive and
Redwood Street are not necessary to accommodate the traffic that will be generated by the
Aspen Heights development, and that a preliminary assessment of traffic impacts, without
improvements to either of those two streets, indicated continued satisfactory operation of the
existing streets and intersections that would receive the site -generated traffic. Such a traffic
study has not been submitted to or reviewed by the City.
9. A request was made again that the work within the floodplain be separated from the balance
of the project work, in order to allow review and approval of the majority of the project to
proceed. It was clarified that the developer is not seeking to avoid making the off -site
improvements; only to avoid a delay that would jeopardize the whole project.
10. Jon Haukaas indicated that he is willing to look at phasing of the project, provided that City
requirements are met. He reiterated that the City will -cannot sign off on public
improvements that are linked to the CLOMR until the CLOMR is approved_; This is a FEMA
requirement and it could OR GFdeF to avoid the possible need to remove and replace
constructed improvements in the event that FEMA's review of the CLOMR identifies needed
design revisions.
11. In further discussions of the ramifications of delaying the construction of New Vine Drive and
Redwood Street, concern was raised regarding the lack of a second access to the portion of
the proposed development in the southwest quadrant of the property that would most
closely be served by the proposed intersection of Blue Spruce Drive and New Vine Drive.
There was speculation that Poudre Fire Authority may restrict development of that
southwest quadrant until such time as the second access is completed.
Aspen Heights Student Housing
Notes of 5-14-13 Mtg with City Staff re CLOMR
Page 3 of 4
12. Jim Lynxwiler (PFA) was asked to join the meeting, and after examining the development
plan and discussing the situation with City staff and the development team, concluded that
PFA would likely allow development to proceed throughout the entire site, on the condition
that a second means of emergency access is provided to the southwest quadrant of the site.
Two possible emergency access options were discussed and determined to be acceptable:
a. Complete Blondel Street in Old Town North (OTN) and a sufficient portion of New Vine
Drive to provide an acceptable link across to the south end of Blue Spruce Drive in
Aspen Heights. This option would likely require finished construction of the full cross-
section of Blondel Street and opening of the street to public traffic. The City would
probably not allow gating off of a road (even a gravel surfaced road) within a dedicated
public right-of-way. (Really? I thought Sheri was going to check to see if it could be
gravel if it was gated for emergency access. Mavbe there have been conversations
since the meeting.)
b. Construction of a temporary emergency access way from Lupine Drive to Echo Mountain
Lane, at the northeast corner of the southwest quadrant of the project site. This
temporary emergency access would have to have an all-weather surface, capable of
supporting fire apparatus.
13. Jim acknowledged that PFA will have adequate access to the site from east and west along
Conifer Street, without completion of Redwood Street.
14. Further discussion of a separation and temporary deferment of the construction of New Vine
Drive and Redwood Street led to the following requirements and agreements between City
staff and the Developer's team:
a. The Developer must demonstrate, via a TIS addendum, that the absence of New Vine
Drive and Redwood Street will not result in an unacceptable Level of Service (LOS) on
existing nearby streets or at existing intersections (Conifer / Redwood, Conifer / Blue
Spruce, Conifer / College).
b. The Developer must assure the City that the proposed New Vine Drive and Redwood
Street improvements will be constructed as soon as possible. It was indicated by the
Developer that this work would, in all likelihood, be completed prior to the issuance of
iY -keCertificates of Occu ancy for the houses within Aspen Heights,
c. In order for the City to process the New Vine Drive and Redwood Street improvements
separately from the balance of the project, these will likely have to be treated as a
separate filing, so that the FDP submittal for the first filing can be approved and
processed. Elements of work in the second filing would include the road improvements
and the associated storm drainage infrastructure.
d. Underground utilities within the floodplain could be approved by the City and constructed
prior to approval of the CLOMR, provided that the existing ground surface within the
floodplain is restored exactly to preconstruction conditions. This would require a detailed
survey, prior to commencement of construction and careful restoration of all disturbed
areas. A City -issued Floodplain Use Permit would be required and a Zero Rise
Certification of flood elevations.
e. The underground utilities that could be installed under the Floodplain Use Permit include
the water main in Vine Drive and the outfall piping from the interim detention basin along
Redwood Street to the discharge point at the Lake Canal.
Aspen Heights Student Housing
Notes of 5-14-13 Mtg with City Staff re CLOMR
Page 4 of 4
15. Finally, there was discussion regarding the need to ensure that the work within the New
Vine Drive and Redwood Street rights -of -way that is subject to URA funding is commenced
prior to the deadline set out in the URA Development Agreement. Since the CLOMR is
covered under the URA funding agreement, it must be completed within the prescribed time
frame.
CG OWEN
CONSULTING
GROUP, INC.
July 1, 2013
City of Fort Collins
Engineering Development Review
281 N. College Ave
Fort Collins, CO 80522
Attention: Ms. Sheri Langenberger
RE: Aspen Heights Student Housing
Driveway Area Setbacks
Dear Sheri,
Project File #: 11-385
Following is a synopsis of the analysis done to determine the required setbacks for the
respective off-street parking areas within the Aspen Heights Student Housing project. The
analysis demonstrates that a setback of 40 feet is appropriate for all but two of the parking
areas. A Modification of Standards is requested for those two parking areas.
The Traffic Impact Study (TIS) prepared for the project predicts that the Average Daily Trip
(ADT) total that will be generated by the development will be 2,180 vpd, based on a resident
population of 716 students. The ADT total is equivalent to 3.04 trip ends per day per student.
The daily traffic volume to and from the respective parking areas is calculated based on the
number and type of housing units served by that parking area and the student occupancy rate of
the respective buildings. The attached spreadsheet (Sht 1 of 2) demonstrates that no parking
area driveway has an ADT greater than 750. All parking areas are accessed from public streets
classified as "local". Thus, per LCUASS Figure 19-6, the required setback distance from the
street flow line to the nearest parking stall will be determined by the average daily traffic volume
in the adjacent street.
For this analysis, distribution of the total predicted site generated traffic to the local streets in
the development area (Lupine Drive and Blue Spruce Drive) is taken to be proportionate to the
peak hour traffic volumes at the access points, as presented in the TIS. The spreadsheet
attached shows that approximately 26% of the daily traffic (561 ADT) will access the site via
Conifer Street and Blue Spruce Drive North; approximately 22% of the daily traffic (478 ADT)
will access the site via New Vine Drive and Blue Spruce Drive South; and approximately 52% of
the daily traffic (1,140 ADT) will access the site via Redwood Street and Lupine Drive East.
Since the traffic volumes on Blue Spruce Drive North and South are both well below 750 vpd,
the applicable setback for all parking areas accessed via Blue Spruce Drive is 40 feet, per
LCUASS Figure 19-6.
The maximum daily traffic volume on Lupine Drive, at the Redwood Street intersection, is
greater than 750 vpd. However, not all traffic entering or exiting the site via this intersection will
travel the full length of Lupine Drive. Instead, certain volumes of traffic will enter or exit the
street at the various driveways served by Lupine Drive. The number of vehicles entering or
exiting the street will typically be proportionate to the resident population served by those
driveways and corresponding parking areas. Therefore, the traffic volume in the street will
3715 Shallow Pond Dr., Fort Collins, CO 80528 • Phone (970) 226-0264 • Fax (970) 226-3760
a -,. _.� �� ►,.� =-ter �r.,r�r�.�� � a . r/w1�J. wI Will of
Sol
A m_
OWEN
G CONSULTING
GROUP, INC.
May 15, 2014 Project File #: 11-385
City of Fort Collins
Engineering Development Review
281 N. College Ave
Fort Collins, CO 80522
Attention: Ms. Sheri Langenberger
RE: Aspen Heights Student Housing
Interim Detention Basin Outfall — Design Revisions
Dear Sheri,
In preparation for construction of the interim outfall from the Aspen Heights Detention Basin to
the Lake Canal, we undertook a program to better refine the horizontal and vertical locates of the
existing utilities in the area where the proposed outfall will cross the Redwood St. alignment and
downstream from there to the discharge point at the Lake Canal. The supplementary investigation
revealed several conflicts between underground utilities and the outfall pipe, as proposed and
approved. Therefore, we have revised the alignment and profile of the outfall to avoid the conflicts
and ensure that the required horizontal and vertical separations from existing utilities are maintained.
Along with specific revisions to the outfall piping, the revised design also reflects elements of the
pending design of Redwood Street, incorporated to ensure that the ultimate design will be
compatible with the design for the future completion of Osiander St. in Old Town North, and to
accommodate the installation of a box culvert to convey remnant Dry Creek flows beneath Redwood
St. and into the historic drainage channel to the Lake Canal.
To accomplish these objectives, it was necessary to add one further manhole, and to relocate
the three downstream legs of the interim outfall. The overall design concept for the outfall has not
changed from that originally proposed and approved. Two sections of the pipe will continue to
function as inverted siphons, and will retain water, and a portion of the first pipe run downstream of
the detention basin outlet structure will also not completely drain, but the rest of the pipes will drain
by gravity. This revised design represents a significant reduction in the length of non -free -draining
pipes compared to the previous design (439 ft vs. 646 ft).
The proposed revised design for the interim outfall is shown on the attached drawings. I hope
that you will find these acceptable and authorize work to proceed on the installation of the piping
without delay. If you have questions or comments regarding this submittal, please call me. Thank
you for your attention to this matter.
Yours truly,
Owen i Group, Inc.
Larry C. Owen, P.E.
Enclosures
cc: Glen Schlueter
3715 Shallow Pond Dr., Fort Collins, CO 80528 - Phone (970) 226-0264 Fax (970) 226-3760
Aspen Heights
11 /SV2011
UTILITY COORDINATION ATTENDANCE SHEET
Contact name
Zq,.,-Ct/ 0f,,,l
Company Name
/J
tJE.✓ Ce.✓sdt�►-ii✓ C�sea v •�
Address�r
c a men � C.aMC as�.hc�
Phone Number/email address
c�.rr-
7� l ►-�-�= .i gb5-'mil
L G H T q-
°Iic�• 7�i1• loloC��
f?d- z.Z41• rolsZ
7-1 r✓e Qq FG ,*7bV,
�ylptl'l�n,✓ �� n e�
Rov. C:t .
Gy
as �- "O t
Gr Ga � n e � �c o�, cow►
�{o�s� Su�tlly�
G L/A lLe-,JT Pc, G
oZ ( - & 317'-3
�x�QSDIe C'DPa�sn
Owen
as iar�{
Ms. Sheri Langenberger
RE. Aspen Heights Student Housing — Off-street Parking Area Setbacks
July 1, 2013
Page 2 of 2
decrease with increasing distance from the access point at Redwood Street. The analysis
presented in the attached spreadsheet shows that the daily traffic volume on Lupine Street
drops below the 750-vpd threshold at the first pair of driveways west of Redwood Street, and at
all locations west of the first two driveways, the street ADT will be less than 750 vpd. Since the
driveway volumes are also less than 750 vpd, the required setback distance for the first parking
stalls in each of these subsequent parking areas is 40 feet.
The only parking areas where the criteria for the 40-foot setback are exceeded are the first
pair of driveways west of Redwood Street. Given that these driveways are only two of the 17
driveways in the development, we request that a Modification of Standards be allowed for these
two driveways.
We trust that you will find the information presented here to be sufficient and acceptable. If
you have questions or comments regarding this submittal, please contact me immediately and I
will be pleased to discuss any items with you. Thank you for your consideration of this request.
Yours truly,
Owen Con roup, Inc.
Larry C. Owen, P.E.
Attachments
4
Z
mo
0w
>$
p0
,
g
"a
5
s
01
W V
OIJ
�1D+L
V
N
W+
W /JOP
ag
m000)wD
SL
o
4
R
m
001+
N
N
O
OD
+
G
>9
mOA
wa
g•
+
V N
CI V
O !C
9RO15
��
mvv�ma
P�
�m
aW+
oo+
A
4,
ooa
1
1�yy
Q1
g
ONN
O
AA
V NO
Or1
ON
g
m0
0w
m
m
V
CC V
NNtl1
C
>�
mvc�c'�aoa
s
W
N O
O
O+
Amg
4
a
y 0
0 0
O' in I
I
c
e
w
� m
J L
DJ
> I
0
w'r
D
Z
A
W
W
N
N
i
i
O
0000000�
_D
m
O
a
-
p
a
3
vi
N
o�
01-4C
N
N
CL
o
la
a
v
FAO?
V
A((O
W4
v
la��ip
W
0)
O
-4W
CO
Al
OD
D
�v
A
2
a
m
v
co
0
m
z
m
G)
c
v
m
z
0
'c'^
L'
z
G)
�t R.O.W.
I
I
IPrivate
IParking
- -
Minimum Off Street Parking
I Setback Distance to any parking stalls or drive aisle.
(See Table below)
Back of
Sidewalk
MINIMUM OFF STREET PARKING SETBACK DISTANCES (FT.)
PARKING
LOT
STREET CLASSIFICATION
Volume
(AD-0
Local
Collector
Arterial
< 100
ADT
100-750
ADT
j > 750
! ADT
<100
20'
40'
40'
59
50' 1
i
100-750
29
40
50'
50'
75'
>750
NA
50'
50'
60'
100'
MINIMUM OFF STREET PARKING SETBACK DISTANCE
LARIMER COUNTY DESIGN REVISION NO: I FIGURE
URBAN AREA FIGURE i%ATLW. n03 fin+ ono In e
OWE N
(; CONSULTING
GROUP, INC.
July 1, 2013 Project File #: 11-385
City of Fort Collins
Engineering Development Review
281 N. College Ave
Fort Collins, CO 80522
Attention: Ms. Sheri Langenberger
RE: Aspen Heights Student Housing
Utility Crossings — Depth of Cover
Dear Sheri,
There are two locations where we believe that it is not practical to provide three feet of cover
over utility pipes crossing beneath public streets. Accordingly, we are hereby requesting that a
Modification of Standards be allowed at each of these two locations. Details of the subject crossings
are presented below in support of our request.
The first location is at the crossing beneath Lupine Drive of the culvert pipes in the main north-
~ ,ram
south drainage channel. The design presented in the FDP drawings for the Aspen Heights project
provides 2.0 feet of cover at the street centerline. The attached figure shows a cross-section ' 0�
through the channel, the culverts and the underlying NECCO piping at the crossing point.
The elevation and gradient of the main drainage channel are governed by 1) the invert
elevations of the existing culverts beneath Conifer Street, at the upstream end of the channel, 2) the
design of the NECCO detention basin, at the downstream end of the channel, and 3) the design of
the underlying NECCO storm drain piping, throughout the length of the channel. The size of the
culverts beneath Lupine Drive is driven by the hydraulic capacity required to convey the ultimate
design flow in the channel, per the NECCO hydrologic analysis and the drainage analysis for the
Aspen Heights site. In order to convey the ultimate 100-year design flow in the channel (159.4 cfs)
beneath Lupine Drive, without overtopping the street, four 24" x 38" HERCP culverts are required.
In the near term, prior to completion of the NECCO system upstream and downstream of the
Aspen Heights site, the north -south channel through the site will also carry flows that will ultimately
be conveyed in the NECCO storm drain beneath the channel. Thus, the near term peak flow in the
channel will be somewhat greater than the ultimate 100-year flow. The near -term peak flow in the
channel is estimated to be 239.7 cfs. If this 100-yr flow is experienced, prior to the completion of the
NECCO system, a portion of the flow in the channel will overtop the street. Analysis shows that the
depth of overtopping will be slightly less than 6 inches. However, in order for the overtopping to
occur at the channel crossing, and for the overtopping flow to reenter the channel downstream of the
street, the profile of Lupine Drive must include a low point coincident with the channel crossing. That
is the condition presented in the current design.
The profile of Lupine Drive is mandated by the overall grading of the development site. To raise
the elevation of Lupine Drive at the channel crossing would necessitate raising grades throughout a
substantial area of the site in order for the site to drain efficiently. Because there is very little relief
throughout the site, overall, the street profile grades are also relatively flat, both east and west of the
channel crossing. Raising the elevation of the street by one foot at the channel crossing would
reduce the profile grade west of the crossing to approximately 0.51 % and would reverse the gradient
3715 Shallow Pond Dr., Fort Collins, CO 80528 • Phone (970) 226-0264 Fax (970) 226-3760
Ms. Sheri Langenberlger
RE., Aspen Heights Student Housing — Request for Modification of Standards
July 1, 2013
Page 2 of 2
east of the crossing, such that the street gradient would fall continuously from Blue Spruce Drive to a
point well east of the channel crossing. This would substantially alter the site drainage regime, as
well as adding substantially to the amount of fill required to grade the site. Thus, we are requesting
that the proposed design at the Lupine Drive crossing be approved.
To minimize the risk of reflective cracking of the pavement in the vicinity of the channel crossing,
we propose, as part of this request, to replace the asphalt pavement, throughout the full width of the
street and the length of the channel crossing, with a reinforced concrete slab pavement. Details of
the slab design, as well as the backfill around the culverts supporting the slab, will be finalized in
conjunction with the final design of the pavement section(s) throughout the balance of the site.
The second location for which a Modification of Standards is requested is the crossing of the
detention basin interim outfall piping beneath Redwood Street. As currently designed, the cover
over the pipe is 2.22 feet at the west flow line of the street, 3.07 feet at the street center line, and
2.78 feet at the east flow line.
The elevation of the outfall pipe has been lowered as much as possible, and use of HERCP pipe
has been specified to reduce the vertical dimension of the pipe. Further lowering of the pipe is
prevented by the existing sanitary sewer main in Redwood St. The sewer main is laid at minimum
gradient, so it cannot be lowered. Consideration was given to lowering the profile of the outfall such
that it would pass beneath the sanitary sewer main, however, to do so would result in this section of
the outfall being at an elevation more than nine feet below grade and more than five feet below the
invert of the Lake Canal at the discharge point.
As we have discussed previously, the shallow invert elevation of the Lake Canal (4952.2 ft), will
result in all outfall piping set below that elevation remaining continuously surcharged, or partially
inundated, until such time as the permanent NECCO outfall is installed. By installing this section of
the outfall at the elevation shown in the current design, none of the interim outfall piping, with the
exception of the section crossing New Vine Drive, will remain completely surcharged. Several runs
of pipe near the downstream end will remain partially inundated, but none completely. A backflow
prevention flap at the outfall will prevent water from the Lake Canal entering the outfall piping.
A request for a Modification of Standards is requested for this location. Given the limited
magnitude of the reduced cover over the outfall pipe, no other mitigating design revisions are
proposed for this location.
I trust that you will find the information presented here to be sufficient and acceptable. If you
have further questions or comments regarding these requests, please contact me immediately to
discuss them. Thank you for your consideration.
Yours truly,
Owen Cons roup, Inc.
Larry C. Owen, P.E.
Attachments
• 1:
TJVT.JV
4963.53
4964.99
I11
l 1 1
PT.
B EV.rr"N
4963.33
cn
.`Qo
4964 99
��
(nW
p°K
15+00
w
r- r. p
49 63.20
3
r- m
o rn
m 0 0
�M>
4964.94
�0
�
1' m
4963.17
,-
4964.34
4963.24
4959.22
4963.35
4963.39
16+00
4963.45
�, a,
0
p
�D
4964.08
A 0
4963.55
z
m
m
0
0
4964.03
16+50
4963.65
<_
U)
N D
m
O) CA)
0
(1) -A
M
m�
D0
z�
D
z
2.01 ft
A�
j u LO-Z
m T
fA p rn
12
>i
zQ
rn0
r m
VZM
M(@
PVC: 14+71.99 -v -oo
EL: 4963.36 S S
�X
cn • • �
V V -+
pW �T..
PVT: 15+41.99
EL: 4963.21
IllO)w
L
AT10N