HomeMy WebLinkAboutRIVERSIDE COMMUNITY SOLAR GARDEN - FDP - FDP140027 - SUBMITTAL DOCUMENTS - ROUND 1 - REVISIONSRESPONSES TO STAFF COMMENTS ROUND 2
CLEAN ENERGY COLLECTIVE RESPONSES IN ALL CAPS BELOW
Comment Summary:
Department: Planning Services
Contact: Ryan Mounce, 970-224-6186, rmounce@fcgov.com
Topic: General
Comment Number: 1 Comment Originated: 08/19/2014
09/16/2014: The landscaping provided along the fence should still be varied with several types of
species to avoid creating a monoculture and to add depth and variety to the overall field of view. A
prior suggestion was to replace some of the serviceberry with chokecherries.
ADDED MORE CHOKECHERRIES AND REPLACED SERVICE BERRY
Comment Number: 5 Comment Originated: 08/20/2014
08/20/2014: At the final plan stage, further notes or details may need to be added to the site and
landscape plan as we learn more about a potential Art in Public Places component to the project.
NOTED
Comment Number: 6 Comment Originated: 09/16/2014
09/16/2014: In addition to the scattered site plan notes, we may wish to a table summarizing the
public improvements to be installed, the responsible entity, and the timeline or phasing of each
improvement. We will continue to discuss this item internally for possible implementation at the Final
Plan stage or in the development agreement.
TO BE INCLUDED IN EITHER FINAL PLAN SET OR AS A SEPARATE DEVELOPMENT
AGREEMENT PER RYAN MOUNCE EMAIL CORRESPONDANCE FROM 10.1.14.
Comment Number: 7 Comment Originated: 09/16/2014
09/16/2014: Other general planning sheet typos/fixes:
- Sheet 2, General Note 2: change "places" to "placed."
- Sheets 1, 2 & 4: Please change the wording from "planning development boundary" to "project
development boundary" and expand this area to include all of the main parcel and those other areas
outside the main parcel where improvements will be included.
- Sheet 3: The fencing detail should be updated to reflect the split-rail style of fencing, rather than the
game fence. Wherever possible, lines drawings should be substituted for photos in the detail
sections as these typically do not record well from mylar sheets at low resolutions.
- Sheet 4: In the plant schedule 3 chokecherry's are shown to be planted, but I don't see their
location or symbols on the landscape plan. Can we double-check on this?
- Sheet 4: There is a hatching artifact partially obscuring the tree auger clearance table.
ALL EDITS UNDER COMMENT 7 HAVE BEEN COMPLETED
Department: Engineering Development Review
Contact: Tyler Siegmund, 970-221-6501, tsiegmund@fcgov.com
Topic: General
Comment Number: 1 Comment Originated: 08/19/2014
08/19/2014: Please add the standard note to the site plan:
Any damaged curb, gutter and sidewalk existing prior to construction, as well as streets, sidewalks,
curbs and gutters, destroyed, damaged or removed due to construction of this project, shall be
replaced or restored to City of Fort Collins standards at the Developer's expense prior to the
acceptance of completed improvements and/or prior to the issuance of the first Certificate of
Occupancy
REPLACED NOTE 6 WITH THIS LANGUAGE
Comment Number: 4 Comment Originated: 08/19/2014
09/17/2014: Please depict the new handicap ramp on the site plan
COMPLETE
08/19/2014: The existing handicap ramp along E Mulberry St, adjacent to the site, does not comply
with current ADA standards. Replacement of the deficient ramp to current standards will need to be
completed with this project
COMPLETE
Comment Number: 8 Comment Originated: 09/17/2014
09/17/2014: Please add the standard city signature block to the plan and details sheet.
COVER SHEET ONLY – COMPLETE
Comment Number: 9 Comment Originated: 09/19/2014
09/19/2014: Please separate the planning documents (site plan, landscape plan, etc.) from the utility
plan documents (sheet 5, site details, etc.). The all-weather access drive plan, profile and detail
need to be removed from the site plan and incorporated into the utility plan docs. Please add a cover
sheet for the utility plan (sheet 5) and a general notes sheet. Please contact me to discuss
TWO SETS OF PLANS HAVE BEEN SUBMITTED: PLAN SET AND UTILITY SET
Comment Number: 10 Comment Originated: 09/19/2014
09/19/2014: An alignment will needed for the sidewalk along Riverside.
COMPLETE – SEE UTILITY PLAN SET
Comment Number: 11 Comment Originated: 09/19/2014
09/19/2014: The minimum standard for a public sidewalk is 6 inches thick. The multimodal path
cross section shows 4 inches. Please revise.
COMPLETE
Comment Number: 12 Comment Originated: 09/19/2014
09/19/2014: The access ramp detail on sheet 5 is blurry and will not scan well when the plans are
recorded. I can provide a pdf of the detail if needed.
FIXED – COMPLETE
Comment Number: 13 Comment Originated: 09/19/2014
09/19/2014: A development agreement and letter of understanding for the sidewalk will need to be
executed at final, prior to approval of the project.
TO BE COMPLETED AT FINAL SUBMITTAL OR AS A DEVELOPMENT AGREEMENT
Department: Environmental Planning
Contact: Kate Rentschlar, 970-224-6086, krentschlar@fcgov.com
Topic: General
Comment Number: 9 Comment Originated: 08/19/2014
08/19/2014: Was an assessment ever performed to look at the possibility of removing the asphalt
along the upper bank?
COMPLETE AND SUBMITTED
Comment Number: 10 Comment Originated: 08/19/2014
08/19/2014: If the building is going to be demolished - please ensure the interior is surveyed prior to
demolition to make sure bats or owls are not utilizing the building.
COMPLETE
Topic: Landscape Plans
Comment Number: 5 Comment Originated: 08/19/2014
09/17/2014: We are meeting with City staff on Friday to determine how to meet this Code section.
RECEIVED NOTES AND MADE CHANGES TO PLAN SET
08/19/2014: Section 4.17(D)(1)(a) of the Land Use Code calls for a "continuous landscape buffer
along the River". To help meet this, additional native shrubs should be planted in a natural manner
between the development and the River.
COMPLETE
Comment Number: 7 Comment Originated: 08/19/2014
08/19/2014: Areas within the habitat buffer that are bare or disturbed will need to be re-seeded.
ADDED NOTE TO LANDSCAPE PLAN
Comment Number: 8 Comment Originated: 08/19/2014
08/19/2014: Species in the seed mixes need to be provided.
SEED MIX PROVIDED BY KATE. NATIVE SEED MIX SEE LEGEND
Department: Forestry
Contact: Tim Buchanan, 970-221-6361, tbuchanan@fcgov.com
Topic: Landscape Plans
Comment Number: 2 Comment Originated: 08/20/2014
08/20/2014: Along Riverside wide grouping of Autumn Brilliance Serviceberry are shown. Consider
using theMnative chokecherry or another native drought tolerant shrub in place of the A.B.
Serviceberry as the native choke cherry has much better xeric adaptation. A substantial water
berm/basin around these plants would help for establishment. Please provide landscape note that
describes how these plants will be irrigated to establishment.
ADDED CHOKECHERRIES
08/20/2014: Along Riverside wide grouping of Autumn Brilliance Serviceberry are shown. Consider
using the native chokecherry or another native drought tolerant shrub in place of the A.B.
Serviceberry as the native choke cherry has much better xeric adaptation. A substantial water
berm/basin around these plants would help for establishment. Please provide landscape note that
describes how these plants will be irrigated to establishment.
Comment Number: 3 Comment Originated: 09/19/2014
09/19/2014: Forestry recommends that native chokecherry be used in place of the Autumn Brilliance
Serviceberry. Please change Autumn Brilliance Serviceberry to native chokecherry as the latter is
much more adapted to xeric conditions.
The planting detail should show the 3 inch to 5 inch water saucer around the individual plants.
Please show in the planting detail the distance between the concrete sidewalk and center of plant as
5 feet instead of 2 feet minimum to allow for the potential 10 foot spread of chokecherry. Remove
reference to juniper in the shrub planting detail.
Please add additional information to general note number 1 that says in effect the following. All
shrubs and trees shall be hand watered to establishment for a minimum of three years. The
frequency and amount of irrigation water applied shall following the recommendations of a qualified
landscape horticulturist. The qualified horticulturist shall make inspections of trees and shrubs during
the three year establishment period and may advise increased irrigation frequency or extra years of
irrigation to ensure establishment.
SEE DETAIL NOTES – COMPLETE
Department: Light And Power
Contact: Doug Martine, 970-224-6152, dmartine@fcgov.com
Topic: General
Comment Number: 1 Comment Originated: 08/08/2014
08/08/2014: No comments.
Department: PFA
Contact: Jim Lynxwiler, 970-416-2869, jlynxwiler@poudre-fire.org
Topic: General
Comment Number: 2 Comment Originated: 09/16/2014
09/16/2014: SECURITY GATES
I've included appropriate code language pertaining to the gate access to assist with the rest of your
site plan. The gate width is required to be 20' minimum which is what it appears to be on your plans.
A swinging gate with a simple padlock is satisfactory as long as we can cut it.
IFC 503.6: The installation of security gates across a fire apparatus access road shall be approved
by the fire chief. Where security gates are installed, they shall have an approved means of
emergency operation. The security gates and the emergency operation shall be maintained
operational at all times.
COMPLETE - NOTED
Gates securing fire apparatus access roads shall comply with all of the following criteria:
1. The minimum gate width for vehicle access shall be 20 feet.
2. Gates shall be of the swinging or sliding type.
3. Construction of gates shall be of materials that allow manual operation by one person.
4. Gate components shall be maintained in an operative condition at all times and replaced or
repaired when defective.
5. Electric gates shall be equipped with a means of opening the gate by fire department personnel
for emergency access. Emergency opening devices shall be approved by the fire code official.
6. Manual opening gates shall not be locked with an unapproved padlock, or chain and padlock,
unless they are capable of being opened by means of forcible entry tools or when a key box
containing the key(s) to the lock is installed at the gate location.
7. Gate design and locking device specifications shall be submitted for approval by the fire code
official prior to installation.
COMPLETE - NOTED
Department: Stormwater Engineering
Contact: Jesse Schlam, 970-218-2932, jschlam@fcgov.com
Topic: Erosion Control
Comment Number: 4 Comment Originated: 09/15/2014
09/15/2014: This project seems unique and will need to describe/calculate the total disturbed area to
see if erosion control materials need to be submitted per City Design Standards. If the total disturbed
area is >10,000 sq-ft then Erosion Control material will need to be submitted and reviewed per City
Standards. If >1 acre then State stormwater construction permits will need to be pulled per State
Regs. Some concern about the longterm erosion impacts of storm water running off the Solar arrays
might cause sediment transportation from the site. How is this to be prevented / addressed? If you
need clarification concerning this section, or if there are any questions please contact Jesse Schlam
970-218-2932 or email @ jschlam@fcgov.com
DISTURBANCE AND EARTHWORK NOTED ON UTILITIES PLAN SET. SEPARATE
DRAINAGE PLAN SUBMITTED.
Contact: Mark Taylor, 970-416-2494, mtaylor@fcgov.com
Topic: Floodplain
Comment Number: 2 Comment Originated: 08/25/2014
08/25/2014: On the Site Plan, please show and label the Poudre River 100-year floodplain and
floodway boundaries.
COMPLETE
Contact: Wes Lamarque, 970-416-2418, wlamarque@fcgov.com
Topic: General
Comment Number: 3 Comment Originated: 08/25/2014
08/25/2014: Since the site plan now may require paved entrance and a paved sidewalk system,
conveyance needs to be documented and shown to meet City criteria as well as providing water
quality mitigation for the new impervious area.
FLOW WILL BE CONVEYED PER HISTORIC THROUGH CURB AND GUTTER IN WATER
RECLAMATION FACILITY DRIVE TO INLET. SEE NOTES ON PLAN SETS.
Comment Number: 5 Comment Originated: 09/19/2014
09/19/2014: Please provide standard asphalt paving for the access drive up to the security gate
where the grades are steep.
COMPLETE
Comment Number: 6 Comment Originated: 09/19/2014
09/19/2014: Please provide the amended soil mix that is to be used in the bio-swale and show on
the landscape plan.
COMPLETE
Comment Number: 7 Comment Originated: 09/19/2014
09/19/2014: Please revise the cross-section of the drive per discussions in the staff meeting
regarding forcing drainage to flow in the middle of the drive.
COMPLETE
Department: Technical Services
Contact: Jeff County, 970-221-6588, jcounty@fcgov.com
Topic: Landscape Plans
Comment Number: 1 Comment Originated: 08/14/2014
09/15/2014: There is text that needs to be masked. See redlines.
08/14/2014: There are line over text issues. See redlines.
CORRECTED
Comment Number: 12 Comment Originated: 09/15/2014
09/15/2014: The lighter text shown will not scan or reproduce. Please darken it up. See redlines.
CORRECTED
Topic: Site Plan
Comment Number: 3 Comment Originated: 08/14/2014
09/15/2014: Please remove one of the "Of" in the sub-title. See redlines.
08/14/2014: Please add "City Of Fort Collins" to the sub-title on sheet 1. See redlines.
CORRECTED
Comment Number: 5 Comment Originated: 08/14/2014
09/15/2014: This has not been corrected. The abbreviated legal description from the County
Assessor is not acceptable. Please use a legal from a deed, and provide a copy of the deed used.
08/14/2014: The legal description on sheet 1 is not acceptable. We require an accurate verified
description of the property.
CORRECTED
Comment Number: 6 Comment Originated: 08/14/2014
09/15/2014: There is text that needs to be masked. See redlines.
08/14/2014: There are line over text issues. See redlines.
CORRECTED
Comment Number: 7 Comment Originated: 08/14/2014
09/15/2014: These still need to be cleaned up.
08/14/2014: Please improve the quality of the PV Array Racking System & Typical Mesh Fence
details. See redlines.
CORRECTED
Comment Number: 8 Comment Originated: 08/14/2014
09/15/2014: These have not been corrected.
08/14/2014: Please sharpen up the text in the Inverter Pad details. It is very pixelated and hard to
read. See redlines.
CORRECTED
Comment Number: 9 Comment Originated: 09/15/2014
09/15/2014: Please improve the quality of the Owner Certification/Planning Approval signature
blocks. See redlines.
CORRECTED
Comment Number: 10 Comment Originated: 09/15/2014
09/15/2014: The lighter text shown will not scan or reproduce. Please darken it up. See redlines.
CORRECTED
Comment Number: 11 Comment Originated: 09/15/2014
09/15/2014: Please change the font style on the elevations. You can not read these. See redlines.
CORRECTED
Department: Traffic Operation
Contact: Martina Wilkinson, 970-221-6887, mwilkinson@fcgov.com
Topic: General
Comment Number: 2 Comment Originated: 08/19/2014
09/16/2014: The trail is now shown at 10 ft, but it is unclear how the eastern end connects to the
sidewalk along Mulberry.
08/19/2014: Transportation Planning staff notes that the trail shown along the SW border of the
property needs to be 10 feet wide, a hard surface, and the eastern end needs to connect to the
existing sidewalk along Mulberry.
CORRECTED
Comment Number: 4 Comment Originated: 09/16/2014
09/16/2014: The trail is shown to be construct 'by others'. Will this be built at the same time as the
solar garden or at a later time? How is this envisioned to be built (and by whom) in the future?
CLEAN ENERGY COLLECTIVE WILL BE RESPONSIBLE FOR CONSTRUCTING THE
SIDEWALK/MULTIMODAL TRAIL, BUT FORT COLLINS UTILITIES WILL REIMBURSE CLEAN
ENERGY COLLECTIVE FOR THE DESIGN AND BUILD EXPENSES ASSOCIATED WITH THE
TRAIL AS WELL AS THE LANDSCAPE PLAN FOR THE HABITAT BUFFER ZONE AREA.