21-24. Information is included on Site Plan.
25. Landscaping on west side of building is included on Site Plan as discussed
with Kirsten Whetstone.
26.1 Colorado Department of Social Services has been contacted to ensure
compliance for licensing requirements.
27. Information is included on Site Plan.
April 5, 1993
Oakwood School
1401 W Mountain Ave
Ft Collins, Co 80521
Kirsten Whetstone
Planning Department
City of Ft Collins
281 N College Ave
Ft Collins, Co 80522
RESPONSE TO COMMENTS FOR NCL SITE PLAN REVIEW
The following is our response to written comments from the Planning Department
dated March 18, 1993, regarding the Oakwood School Site Plan submittal. We believe
that our response satisfies all the requirements of the Ft Collins Planning Department.
1. Relevant building and fire codes will be adhered to.
2. Electrical load increase will be coordinated with Light and Power.
3. A Traffic Impact Analysis is being completed by Matthew Delich and will
be delivered to Kirsten Whetstone by April 15, 1993.
4. Detailed in item #4 on the Statement of Planning Objectives.
5. Leslie Bryson at Parks & Recreation has been contacted. The plan for park
use is detailed in item #5 of the Statement of Planning Objectives.
6-7. Final form for NCL Site Plan submitted April 7, 1993.
8. Plans for alley paving are being completed by Northern Engineering and
will be submitted upon completion.
9-13. Requested information has been included on the Site Plan.
14. General Notes
1-14 Listed on Site Plan.
15 See #3 & #6 on Statement of Planning Objectives.
16 Listed on Site Plan.
Plant Notes
1-10 All points will be complied with and listed on Site Plan.
15. Sign permit will be applied for before signs are erected.
16-18. Information is included on Site Plan.
19. Planting Schedule is included on Site Plan.