HomeMy WebLinkAboutWEST RANGE FORT COLLINS - Filed DCP-DEV. CONSTRUCTION PERMIT - 2013-10-23DEVELOPMENT CONSTRUCTION PERMIT
Permit Number: 13-27 Issuance Date: 1011412013
Project Name: West Range Fort Collins
Project Location: Northwest corner of Meldrum Street and Laurel Street
Permittee: Doug Mavbon Brinkman Construction
City and developer contacts: See attached Exhibit "A" for names and phone numbers of all
contact persons for this project.
Fees: Permit Application Fee ($400.00 paid 09/20/2013 check# 41328) $ Paid
Construction Inspection Fee ($1,254.10 paid 10/14/13 check #1004) $ Paid
Total $ 0.00
Development Bond or other approved security:
Amount of security deposited with the City to guarantee the completion of all public
improvements to be constructed as shown on the approved plans for the development.
$ 24,806.50
Form of security deposited with the City: check # 1005
PERFORMANCE REQUIREMENTS OF THIS PERMIT:
1. The Permittee shall be responsible to require their Project Engineer to incorporate into all design
drawings and specifications the certification of all materials testing by an Engineer. The Permittee
shall have an Engineer prepare revised design drawings and secure City approval for all revisions to
the Utility Plans and related documents. The Perm' ittee shall have an Engineer represent, as required
by the City in the Development Agreement, that the improvements are constructed in conformance
with the approved Utility Plans and the standards and specifications of the City. The Permittee shall
provide "as -constructed" plans prepared by an Engineer prior to the City's acceptance of the
constructed public improvements. (All references above to the terms "Project Engineer" and
"Engineer" shall mean a Professional Engineer licensed in Colorado.)
2. All contractors who perform work on this project must be bonded and licensed in conformance
with City requirements.
Development Construction Permit, Page 2/5
3. Construction time restrictions:
4. The applicant understands that additional permits may be required for this development project
and the applicant shall secure those permits directly from the issuing departments.
5. This permit, along with a complete set of all approved plans and documents for this project
(utility plans, site plan, landscape plan, development agreement, soils report, pavement design, traffic
study, drainage report, plat easements and any other official documents), shall be kept on the
development site available for use by City staff doing inspections.
6. Permit Expiration (in accordance with Section 29-12 of the Transitional Land Use Regulations or
Section 2.6.3(K) of the Land Use Code, whichever is applicable):
a. If construction has not begun within sixty (60) days from the date of issuance of this
permit, this permit shall expire and the applicant will forfeit the permit fee paid for this
permit, whereupon the applicant must re -apply for a new permit.
b. In addition, this permit shall expire one year from the date of issuance. The applicant
may apply for an extension by reapplication at least two weeks prior to the expiration date.
Such application shall contain information sufficient to justify the granting of the extension.
An extension may be granted for up to six months.
7. Building permits and certificates of occupancy will only be issued when all conditions contained
in the Development Agreement and Sections 3.3.2(C) and (D) of the Land Use Code or Sections 29-
678 and 29-679 of the Transitional Land Use Regulations, whichever is applicable, are met. If the
Development Agreement does not specify times for completion of public improvements, or if there is
no Development Agreement, then the improvement requirements specified in Section 24-95 of the
City Code shall apply, which provides that construction of all improvements shall be required prior
to the time of issuance of the first building permit.
8. Acceptance by the City of the public improvements shall be after (1) final inspection has been
conducted by the City; (2) punch list items from the final inspection are completed and accepted by
the City; and (3) required certifications from the licensed professional engineer that improvements
are completed to City standards, specifications and approved Utility Plans; and the "as -constructed"
plans have been received and accepted by the City.
9. The warranty on street improvements is for five (5) years from the date of acceptance by the City
of the completed improvements, in accordance with Sections 29-13 and 29-14 of the Transitional
Land Use Regulations and/or Sections 2.2.3(C)(3)(g), 3.3.1(C)(2), and 3.3.2(C) of the Land Use
Code, as applicable.
10. The City Erosion Control Inspector must be notified at least twenty-four (24) hours prior to any
Development Construction Permit, Page 3/5
planned construction on this project. All required perimeter silt fencing and other erosion/sediment
control best management practices (BMP's) that can be installed prior to construction must be in
place and inspected by the City Erosion Control Inspector before any land disturbing activity begins.
11. No work (including grading) shall be started in State Highway right-of-way until a permit is
issued by the Colorado Department of Transportation to allow such work to begin.
12. Other conditions: All construction traffic for the project is to access the site directly off
of West Laurel Street, west of Arthur Concrete Box Culvert, or off of the alley behind the site
entering and exitinia to South Sherwood Street to avoid crossing and unnecessary loading on Arthurs
Irrigation Concrete Box Culvert structures.
Permittee's acknowledgment signature:
By signing this permit I acknowledges that I am acting with the knowledge, consent, and authority of
the owners of the property (including all owners having legal or equitable interest in the real property, as
defined in Section 1-2 of the City Code; and including common areas legally connected to or associated
with the property which is the subject of this application) without whose consent and authority the
requested action could not lawfully be accomplished. Pursuant to said authority, I hereby permit City
officials to enter upon the property for purposes of inspection and, if necessary, to enter upon such
property to perform work required of the applicant if the applicant were to fail to perform the required
work. I also acknowledge that I have read this permit document with all its requirements and
conditions, and I agree to all of the terms and conditions sq stated in this permit.
Applicant/Project Manager, s Signature: ,J Date: AA 11114�'13
Approval for issuance:
City Engineer Approva `/ -z Date:
(Permit Issuance Date)
Development Construction Permit, Page 4/5
EXHIBIT `A'
DEVELOPMENT PROJECT CONTACT PERSONS
Project Name: West Range Fort Collins
Name, address and numbers
City Staff Contact Persons:
Development Engineer: Tyler Siegmund
281 N. College Avenue, Fort Collins, CO 80524
(970) 221-6501
Construction Inspector: Steve Cicione
281 N. College Avenue, Fort Collins, CO 80524
(970) 221-6605
Cell (970) 692-4418
Water Utilities Engineer/ Wastewater Engineer:
Roger Buffington
700 Wood Street, Fort Collins, CO 80521
(970) 221-6854
Erosion Control Inspector: Jesse Schlam
700 Wood Street, Fort Collins, CO 80521
(970) 224-6700
Natural Resources: Lindsay Ex
281 N. College Avenue, Fort Collins, Co 80524
(970) 224-6143
Traffic Operations: Joe Olson
625 Ninth Street, Fort Collins, Co 80524
(970) 221-6062
Street closures: Syl Mireles
625 Ninth Street, Fort Collins, Co 80524
(970) 221-6815
Forestry: Tim Buchanan
215 N. Mason St., Fort Collins, Co 80524
(970) 221-6361
Light and Power: Doug Martine
700 Wood Street, Fort Collins, Co 80521
(970) 221-6700
Page 4 of 5
Development Construction Permit, Page 515
Developer's Contact Persons:
Project Manager: Brandon Grebe
Blue Ocean Enterprises, LLC
401 Mountain Ave, Suite 400, Fort Collins, CO 80521
(970) 498-2216
(970) 566-9111
Brandon. GrebekBlueocean-inc. com
Owner: Dan Corah
West Range Fort Collin, LLC
8347 West Range Cove, Memphis, TN 38125
(901) 333-2785
DCorah@Pikes.org
Project Engineer: Nick Haws
Northern Engineering Services, Inc.
200 S College Ave, Suite 10, Fort Collins, CO 80524
(970) 221-4158
Nickknorthernen ineering com
Architect/Planner: Marcel Van Garderen
Vaught Frye Larson Architects
401 Mountain Ave, Fort Collins, CO 80521
(970) 224-1191
General Contractor: Doug Maybon
Brinkman Construction
3003 East Harmony Rd, Suite4300, Fort Collins, CO 80525
(970) 267-0954
Doug. MaybonkBrinkmanpartners.com
Page 5 of 5