Miry of Fort Collins
4/4/2008 Date:
HILTON GARDEN INN AT PRESTON CENTER MAJOR AMENDMENT
- TYPE II
SELECTION CRITERIA: Status = All
ISSUES:
Department: Engineering Issue Contact: Dan DeLaughter
Topic: Details
Number:13 Created:3/7/2006 Resolved
[3/7/06] Please add the following LCUASS details to the plan set: 701, 702, 707.
Number:46 Created:4125/2006 Resolved
[4/25/06] RESOLVED at 4/26/06 meeting- this is not a ramp.
Please provide a construction detail of the truck ramp on the south side of the building,
including elevations.
Topic: General
Number:5 Created:3/7/2006 Resolved
[3/7/06] Reference the soils report on the cover or notes sheet.
Number:6 Created:3/7/2006 Resolved
[3/7/06] Note #48 Approved Variances does not appear correct. Is this left over from
another project? No variances have been approved yet.
Number:8 Created:3/712006 Resolved
[4125/061 An access ramp should at least be included next to the handicap space on the
north sideof the building.
[3/7/06] There is only one access ramp shown to get to the building from the parking lot.
Number:9 Created:3/7/2006 Pending
[7/3/06] Repeat
[6/14/061 1 have not received a letter of intent for this.
[4/25/06] Resolved at 4/26/06 meeting: Applicant is limiting grading to on -site, and will obtain
a letter from the adjacent landowner indicating willingness to allow minimal staging on their
property.
[3/7/06] A small amount of offsite grading is shown on the west side of the site. This will
require a grading easement from the owner.
Number:10 Created:3/7/2006 Resolved
[3/7/06] It is difficult to tell what is existing and what is new. What does "match existing"
mean at the driveway entrance?
Number: 12
Created:3/7/2006 Resolved
Page 1
[3/7/06] Wall detail shows a maximum of 29", but you have some wall segments that are
well over this height. Please provide another detail for the higher walls.
Number:14 Created:3/7/2006 Resolved
[3/7/06] Provide a signature line for your engineer on the cover sheet.
Number:15 Created:3/7/2006 Resolved
[3/7/06] The title block lists the property as Lot 1. From the Preston Center plat, it appears
that it should be Lot 2.
Number:16 Created:3/7/2006 Resolved
[4125/061
[3/7/06] Please see redlines for additional changes.
Number:17 Created:3/7/2006 Resolved
[3/7/06] Is there an existing drivecut to be closed on Gifford Ct? If so, label on the plans that
it is to be removed and replaced.
Number:48 Created:4/25/2006 Resolved
[6/14/061
[4/25/06] Sheet 6: North arrow points east. Also, no scale is shown for the storm profile.
Number:49 Created:4/25/2006 Resolved
[6114/06] Repeat
[4/251061 On the wall detail, please include locations of any utility lines (telephone), and
easement boundaries. Provide a separate wall detail for the stacked retaining walls showing
their locations relative to each other, and any easements. My concern is that the lower wall
will be under extra loads from the upper wall and retained earth, that it may not be designed
to handle.
Number:50 Created:4/26/2006 Resolved
[4/26/06] deleted
Number:54 Created:6/14/2006 Pending
[7/3/06]
[6/14/061 See redlines for additional minor comments.
Number:55 Created:6/14/2006 Resolved
[6/14/061 For all existing easements, please note how they were dedicated (Existing
Preston Center 1st plat, or provide reception #). You could do this with a general note
saying "all existing easements were dedicated with the Preston Center First Flg. Plat unless
otherwise specified.
Number:56 Created:6/14/2006 Resolved
[6/14/061 Repeat, on sheet 3, the linetypes and weights need to be fixed. Existing utilities
should be light and/or dashed. Existing electric looks new, and electric service looks
existing. Be sure that the lines on the plan match the legend. Also, add proposed utilities to
the legend.
Number: 57
[7/3/06] Repeat
Created:6/14/2006 Resolved
Page 2
[6/14/061 Do you have an agreement to do the offsite pavement cut shown to connect to the
8" water line on the north of the site? It appears that the cut is planned to cross onto the
adjacent property.
Number:58 Created:6/14/2006 Resolved
[6/14/061 Please add city standard street cut note to sheet 4 for where the curb cut is being
closed: "Limits of street cut are approximate. Final limits are to be determined in the field by
the City Engineering Inspector. All repairs to be in accordance with City street repair
standards."
Number:59 Created:6/14/2006 Pending
[7/3/06] The detail is illegible due to hatching pattern used.
[6/14/061 We will need a construction detail for the several areas where storm pipe is shown
crossing under retaining walls. Details should be called out by number on the plan sheets.
Number:60 Created:6/14/2006 Pending
[7/3106] Repeat
[6/14/06] Sheet 5: scanability issue in the detention pond area.
Number:61 Created:6/14/2006 Resolved
[6/14/061 Mid -block pedestrian ramps in public ROW should be city standard details. The
separate detail provided for them may be used on -site only.
Number:62 Created:6/14/2006 Pending
[7/3/06] Easement documents have not yet been received. They must be submitted before
the plans can be approved.
[6/14/061 Emergency access easements are shown on the site plan but not utility plans.
Any easements to be dedicated by separate document must be submitted to engineering
with appropriate TDRF and filing fees.
Number:63 Created:6/14/2006 Pending
[7/3/06] Repeat
[6/14/061 Fix overlapping text issues (especially problematic on the grading plan).
Number:64 Created:7/3/2006 Pending
[7/3/06] Limits of the proposed drainage easement are not clear. Where is the north
boundary?
Number:65 Created:7/3/2006 Pending
[7/3/06] Please adjust the text style on the existing contours. It is the same as the proposed.
Number:66 Created:7/3/2006 Pending
[7/3/06] There is still a very small amount of offsite grading shown on the west side of the
site,
Number:67 Created:7/3/2006 Pending
[7/3/06] Please call out the sheet # or detail # for the sidewalk chase on your grading plan.
Number:68 Created:7/3/2006 Pending
[713/06] Fix the hatch pattern for the construction entrance on sheet 5. In the legend it
shows up as solid black.
Page 3
Number: 69
[7/3/06]deleted
Created:7/3/2006 Resolved
Number:70 Created:7/5/2006 Pending
[7/5/06] 30' Emergency Access is shown on the north side on the site plan but not on the
utility plans. Please coordinate.
Number:71 Created:715/2006 Pending
[7/5/06] Where is the raised crosswalk detail that is called out on sheet 4?
Number:72 Created:7/5/2006 Pending
[7/5/06] Please dimension parking stalls on the utility plans.
Number 73 Created:7/5/2006 Pending
[7/5/06] Please coordinate all dimensions and layout between the site plan and utility plans.
Several dimensions are slightly different. Refer to redlines
Number: 74
deleted
Created:7/10/2006 Resolved
Topic: grading plan
Number:43 Created:4/25/2006 Resolved
[6/14/06] still missing
[4/25/061 Show proposed contours on the grading plan. They were on the last submittal but
seem to have disappeared.
Number:44 Created:4/25/2006 Resolved
[4125/06) Top of wall locations are not provided at all on the eastern portion of the lower
retaining wall, or on a large portion of the upper wall. These elevations are needed to verify
the wall's height.
Number:45 Created:4/25/2006 Resolved
[4/25/061 Will the drainage easement vacation be done by a replat or by a separate
document? If it is done by separate document, Transportation Development Review fees
and filing fees will apply. A legal description and exhibit showing the portion to be vacated
will be required at the time of final compliance. Fees for vacation are $400, and for
dedication are $250 (plus filing fees).
Number:47 Created:4/25/2006 Resolved
[6/14/061 repeat
[4/251061 Easement is labeled as "proposed easement." Please specify what type.
Topic: Landscape plan
Number:20 Created:3/712006 Resolved
[3/7/06] Label and dimension all easements and Right of Way.
Topic: Overall Utility Plan
Number:7 Created:3/7/2006 Resolved
[3/7/06] Please label and dimension all existing and proposed easements.
Page 4
Number:11 Created:3/712006 Resolved
[4/25/06] 1 will send an e-mail to the utilities to verify they don't need the easement, but the
applicant should coordinate with Qwest regarding the existing telephone line. This should
be addressed prior to hearing. A letter of intent from the phone company and positive
confirmation that the easement is not needed by other utilities will be accepted in lieu of an
official variance request.
[3/7/06] Retaining walls cannot be located within a utility easement without the permission
of all utilities. An existing telephone line is shown directly under one of the walls. If
permitted, a detail should be included to show how this will work.
Topic: Site Plan
Number:18 Created:3/7/2006 Resolved
[3/7/06] Change all dimensions to engineering type.
Number:19 Created:3/7/2006 Resolved
[3/7/06] Label and dimension all easements and Right of Way.
Department: Transportation Planning Issue Contact: David Averill
Topic: Overall Utility Plan
Number:53 Created:6/13/2006 Unresolved
[6/13/06] Sheet 3 of Utility Plans - please call out the bicycle parking or add the symbol to
the legend. Thanks.
Topic: Utility plan
Number:23 Created:3/21/2006 Resolved
[4/241061 1 don't recall what the response to this comment was the last round. How will
pedestrian access be enhanced?
[3/211061 No connecting walkway is present.
Number:24 Created:3/21/2006 Resolved
(3/21/061 Please show the location of bicycle racks on utility plans.
Page 5