HomeMy WebLinkAboutBELLA VIRA - Filed BC-BRIDGES & CULVERTS - 2008-02-06PROJECT DESCRIPTION QUALITY CONTROL Project is a 14'-0" x 4'-0" cast -in -place box extension to on existing box crossing Overland Trail 1. The Contractor is responsible for quality control, including workmanship and materials Rood at the Pleasant Valley Lake Canl furnished by his subcontractors and suppliers. The project name is 'Bella Vira". 2. Inspection or testing by the Owner does not relieve the Contractor of his responsibility to perform the Work in accordance with the Contract Documents. GENERAL APPLICATION 3. Workmanship. The Contractor is responsible and shall bear the cost of correcting work which does not conform to the specified requirements. 1. These drawings must be used in conjunction with the civil drawings on the project to clearly define oil requirements for construction. 4. Correct deficient work by means acceptable to the Engineer. The cost of extra work incurred by the Engineer to approve corrective work shall be borne by the Contractor. 2. No Contractor should attempt to bid or construct any portion of this project without consulting the project civil, municipality, mechanical, and electrical specifications, QUALITY ASSURANCE and/or General Notes. J. These General Notes ore intended to function as the structural portion of project specifications. 1. Owner will engage a qualified Testing Agency, approved by the Engineer to perform 4. All things which, in the opinion of the Contractor, appear to be deficiencies, omissions, tests and inspections required by these General Notes. contradictions or ambiguities in the drawings shall be brought to the attention of 2. Testing Agency shall comply with ASTM E329 and shall furnish a certificate of compliance, the Structural Engineer. Corrections or written interpretations shall be issued before signed by the Professional Engineer responsible for management of the Agency. affected work may proceed. 3. The Professional Engineer must be registered in the state where the project is located. 5. The Contractor shall inform the Structural Engineer, clearly and explicitly in writing 4. See General Notes above for required testing and inspection. of any deviation or substitution from requirements of the contract documents. Contractor shall not be relieved of any requirement of the contract documents by virtue of the SPECIAL INSPECTION Structural Engineer's review of shop drawings, project data, etc., unless the Contractor has clearly and explicitly informed the Structural Engineer in writing of any deviations or substitutions at time of submission. 1. Special inspection is required for the following: DESIGN CRITERIA a. Inspection of subgrode preparation operations by Geotechnical Engineer b, Placement of concrete reinforcement prior to closing of formwork and placing 1. Design Codes and Criteria for Construction: of concrete. a. AASHTO c. Concrete placement and strength testing. b. Colorado Department Of Transportation, d. Inspect all anchor bolts and embedments cast into concrete. c. City of Fort Collins 2. All welding with the exception of shop welding done in on approved fabricator's shop. 2. Superimposed Gravity Loading: PER SHEET S2.00 The Contractor shall be responsible for notifying Special Inspector 72 hours in advance J. All references are latest edition unless noted otherwise. of required inspections for scheduling purposes. Failure to meet observation schedules may require removal (for inspection purposes) any finishes that have be subsequently EXISTING CONSTRUCTION installed. Approval by the special Inspector does not preclude observation by the Engineer of Record and approval by the FOR does not preclude the inspection process by the Special Inspector and nay other code requirements for inspection. Removal and replacement of Information on existing construction taken from drawings provided by any finishes and/or froming damaged by the finish removal process or as required for 1• corrective action shall be at the Contractor's expense, not the Owner, Engineer nor Jonathan Sweet, P.E. Jim Sell Design, Inc. 153 West Mountain Ave. Fort Collins, Structural Observer, CO 80524 Phone: (970) 484-1921 Fax: (970) 484-2443 J. A pre -construction meeting including the Engineer of Record, the Contractor, Special All information, dimensions, elevations, etc. shall be considered approximate and shall Inspector, and appropriate Subcontractors shall be held to review the details of the 2. be field verified by contractor prior to ordering and/or fabricating material. structural systems to be inspected. Report all discrepancies to the Construction Manager and Engineers. 4. TWH may also provide verbal instructions to field supervision personnel as needed to 3 In as much as the addition, remodeling, retrofit, renovation or rehabilitation of an ensure that the observed work conforms to contract documents, and will follow up site 4 existing building requires that certain assumptions ore made regarding existing conditions. observations with a written report of items observed with noted deficiencies. The contractor must immediately notify the structural engineer if any existing condition deviates from those indicated in the contract documents. \ Contractor shall verify all existing conditions prior to ordering materials or proceeding \ 5. with new work in areas affected by existing conditions. Structural Engineer shall be \ informed in writing of conflicts between existing and proposed new construction. \ No openings nor any changes or additions shall be made in any existing structural elements ` 6. without written approval of the Structural Engineer. Where the function of on existing element as structural or non-structural is unclear, the determination of its function - - will be mode solely by the structural engineer. GEOTECHNICAL NOTES \ \ 1. Presumed bearing value of soil is to be con/firmed at time of construction. See Foundation Note 1. v 2. Bearing values are based upon telephone conversation with Lester Litton, P.E. Earth \ \ \ \ Engineering Consultants, on March 1, 2007 and letter doted May 24, 2007 project 1062104. \, See foundation Note 2. \ \ \ \ J. Provide free -draining sub grade preparation per 2/S1.00 per geotechnical recommendations. \ \ FOUNDATIONS \ \ 1. SOILS ENGINEER: \ \ \ \ \ i. Provide an open excavation inspection SUB GRADE a geotechnical engineer licensed \ \ \ _ \ \ \ r OVER EXCAVATION in Colorado. Geotechnical engineer shallll prepare a letter report confirming \ \ \ � � \ \ / \ presumed soils criteria prior to construction of foundations. Do not \ \ construct work until confirmation o/ presumed criteria has been received by \ \ \ Structural Engineer. A copy of the letter of confirmation shall be submitted \ o T/ WALL v to the City. �vT \ 2. Foundation and retaining walls have been designed for the following assumed design \ \ \ \ ` = 5121.84' pressures: \ moldy v A i. Presumed Bearing Pressure 2000 psf, 0 minimum \ \ 4%fe \ ` \ \ Cq \ C ii. Active Pressure 45 psf/ft iii. At Rest Pressure 60 ps//ft \ v v A I A iv. Passive Pressure 250 psf/ft T/ WALL A V. Friction Coefficient 0.35 v v V� v •- - 512259' J. See sheet 52.00 for box culvert sections and notes. \ VA 4. All fill material shall be compacted in accordance with recommendations of CDOT. Measurement FO and payment provisions do not apply. Contractor shall include cost of COOT specified \ \ \ bockfill materials in the cost of the work. \ 5. Provide shoring and protection from the elements for excavation bottoms and sides as `\ required to promote safety, prevent caving and washing, and to prevent undercutting \ S3.0 of footings after they have been placed. 6. Brace oil foundation walls against which bockfill is to be placed until floor slobs k at the top and bottom of the wall are in place. = 7. Contractor shall provide continuous site drainage by o mechanical method to control 8 surface and underground water as required to maintain a dry working site. MISCELLANEOUS NOTES 1. The Contractor is solely responsible for all safety regulations, programs and precautions g related to all work on this project. 8 NVERT ELEV. o -V WALL 512259' 2. The Contractor Is solely responsible for the protection of persons and property either z on or adjacent to the project and shall protect if against injury, damage, or loss, z z RE: 33.00 AND �\ Q 3 S4.00 FOR 3. Means and methods of construction and erection of structural materials ore solely the RETAINING WALL,. _ Contractors responsibility. DESIGN, IYP. 4. The structure is designed to function as a unit upon completion of construction of the project and then, only to support the design loads indicated. The contractor is responsible for means, methods and sequence of construction and the adequacy of the L structure to support Inds occurring during construction of the project. Furnish all temporary bracing, shoring, and/or support as may be required. V WALL 5. No openings or any change in size, dimension or location shall be mode in any structural element written approval of the Structural Engineer. = 5121.84' 6. Show all openings through structural members on shop drawings and submit for review. Openings not shown on structural drawings are subject to acceptance and shall be specifically indicated for review and acceptance. 7. No structural modifications, alterations, or repairs shall be made without prior review by Structural Engineer. Submit details. SUBMITTALS 1. Manufacturers Data: Submit two (2) copies of manufacturer's specifications and installation instructions for each product specified. Indicate by transmittal form that a copy of each instruction has been distributed to the appropriate contractor. 2. Shop Drawings: Submit one (1) reproducible and five (5) prints of each shop drawing. Reproducible copies of contract documents shall not be used as shop drawings. Shop drawings shall be reviewed by Contractor prior to submission. Drawings shall bear Contractors approval stamp accepting responsibility for coordination of dimensions shown in the contract documents, quantities and coordination with other trades. Drawings not bearing Contractor's stomp may be rejected at the discretion of the Architect or Structural Engineer. Reproducible prints will be returned with the Architect/ Engineer comments. Allow 14 calendar days in the Structural Engineers office for review of shop drawings. J. Requests for Information (RFI) may use the Contractor's standard forms. Contractor shall send doted RFI information requests in writing when schedule and cost impacts are anticipated. Contractor may request information verbally if no cost or schedule impact is anticipated. 4. Submittals: a. Concrete Mix Design b. Reinforcing bar shop drawings c. Handrail shop drawings SCALE : 1/8" = 1'-0" 1'-4 LAYOUT PLAN r \ ,�v \ � I EXISTING CONCRETE ENCASED � Qo V DUCT BANK, FIELD VERIFY 1 \ V A \ \ ALIGN INSIDE WALLS OF \ \ o \ NEW BOX WITH WALLS I \ i OF EXISTING BOX, TYP. KZ v 2 S200 / 2 \ Sd00 I , \ k / i 3 SL00 I 6 � I EXISTING HEADWALL, DEMO PARAPET PER 1/S2.00 I NOTE. CONFIRM 3'-0" I FLOW LINE, ALL ELEVATIONS SHOWN WITH CIVIL + / - RE: CIVIL I ENGINEER 10'-0" SIDEWALK, 3'-2" RE CIVIL I � \ r \ I I � \ \ OTPVLCPfAN.dwg 2 MAX 1 INVERT ELEV. SEE 3/S1.00 wo o� O U Z U �w RAW SCALE 1 " = 4'-0" 3 53.00 V WALL \ ` = 512259' RE: S4.00 FOR WINGWALL 'BEYOND', RE: S3.00 FOR _ SPECIFIC WALL DETAILS v INVERT ELEV. = 5117,34' PAVEMENT. RE: CIVIL 14'-0" PERPENDICULAR Tw (15'-6" +/- SKEW LENGTH) I i 1 = r J I f 1 GENERAL LAYOUT SHOWN SEE SHEET S2.00 FOR BOX DIMENSIONS AND REINFORCING V, v�vvvv� v%�� COMPACTED ON SITE MATERIAL COOT STRUCTURAL ' BACK FILL CLASS 1 PROVIDE 3'-0" CLASS 7 REJECT" SUBGRADE BASE PREPARATION BOX CROSS SECTION 20060630 SECTIONS.dwq RE: S2.00 FOR REINFORCING SCHEDULE AND DIMENSIONS 4"0 DRAIN TIED TO RETAINING WALL DRAIN BEYOND 10'-0" SIDEWALK 2' WEST 1}" COMPRESSIBLE POLYETHYLENE WRAP OVER TOP OF DUCT SEE 5/S3.00 EXISTING CONCRETE ENCASED J O DUCT BANK, FIELD VERIFY ELEVATION T/ DUCT = 5110.21' PER MINA SURVEY RE: CIVIL FLOW LINE, 5119.44 +/- SIDEWALK AT MID -WALL, RE., CIVIL SHT 27 SLOPES, RE: CIVIL T GENERAL LAYOUT SHOWN SEE SHEET S3.00 FOR SPECIFIC DETAIL AT PARAPET HEADWALLS AND WINGWALLS BEYOND REMOVE EXISTING HEADWALL AND REINFORCE ADJACENT SLAB, RE 1/S2.00 T/ WALL w 5117.57' r ��' -7 B/ SLAB - EXISTING CULVERT, FIELD VERIFY SLOPES, RE CIVIL INVERT ELEV. 5111.38' `./ CULVERT, %i\\ i \% FIELD VERIFY ' EAST HATCH INDICATES EXISTING CULVERT TO REMAIN PROVIDE SUBGRADE BASE PREPARATION, RE.' 2/S1.00 UTILITY NOTES O FUTURE 4"0 (8) < EXISTING DUCT VERIFY W/ UTILITIES CONDUIT LOCATIONS SCHEMATIC LONGITUDINAL SECTION iI nn�ini� ninATui SCALE I" = 4'-0 Structural Drawing List *** INCLUDED WHEN SHOWN NUMBERED *** S1.00 BOX CULVERT PLAN AND SECTIONS S2.00 TYPICAL BOX CULVERT REINFORCING S3.00 WING WALLS FOR BOX CULVERT S4.00 HEAD WALL ELEVATIONS AND RAIL DETAILS 20060630 SECTIONS.dwq BOX CULVERT KEY MAP FORT COLLINS - LOVELAND WATER DISTRICT SOUTH FORT COLLINS SANITATION DISTRICT Mr. Micha . Di I ullio, INVI r Date ---f x� / L • ZO- s5 Mr. T amll, P.E., District Engineer Date All changes, addendums, additions, deletions and modifications to these drawings must be approved, in writing, by the Fort Collins -Loveland Water District and the South Fort Collins Sanitation District. PLEASANT VALLEY AND LAKE CANAL COMPANY Approval Block REVIE,.�;D BY THE PLEASANT VALLEY AND LAKE CANAL COMPANY ON THIS (r DAY OF. 20L'9'fHIS PLAT HAS BEEN SIGNED BY THE PLEASANT VALLEY AND LAKE CANAL COMPANY, BUT THIS SHALL NOT MEAN IT APPROVES THE ENGINEERING, SURVEYING, DESIGN, CONSTRUCTION, OR OTHER PROFESSIONAL WORK. THE SIGNATURES MEAN ONLY THAT THE COMPANY HAS SEEN THE SHEETS, SIGNED, AND COOPERATED WITH THE OWNER IN PROVIDING INFORMATION. THE OWNER AND THE PROFESSIONALS IT HAS EMPLOYED ARE SOLELY RESPONSIBLE FOR THE END RESULT. ROBERT UNDERHILL, PRESIDENT City of Fort Collins, Colorado UTILITY AN Approval APPROVED. I q City Engineer y Date Ci CHECKED BY: Water& Wastewater Utility Date CHECKED BY: -- Stormwater Utility Date A,14 CHECKED BY: Traffic Engineer _ Date CHECKED BY: rewEiG Date AJA- _ CHECKED BY'. Environmental Planner Date o� N o `v d v a n v.. m C O a j d s o- C yC �.O C T C s2owo0 � aEz �«E o d o o v � y E v� 2 a. .a2 o y m E am L Po dod I/I U j U ` UI ma N W r Q Dz 7 1! �� L M 33 30 Q� x U m c k d N z Zg ® U a E 8 E L n o in 0 0 0 W L J N w O al' U0 w3 0o VIa of ME N 'O m 0 0 o m o o w z co 0-1- 0- 0Z Z 0 i= ''W^^ V! Z < > Z _J W 0. la- W J U 0 W Sheet S1.00 C-3 2154 h1 C1 C 1 (TYP.) @ 6" cD N C 2 (TYP.) > @ 6» C2 TW x 7 A d 1 BARS @ 1'-6" MAX. (72) -- #4 (TYPICAL) TOP AND BOTTOM OF TOP AND BOTTOM SLABS (CONT.) t 2 @ 6° t 1 @ 6" 2" CLEAR OPTIONAL CONSTRUCTION JOINT (TYPICAL) 4'-0" H x 14'-0"* W BOX t1,b1 #7 h1 4-6 Tt=15.0 t2,b2 #8 h2 4-6 Tb=12 w1,w2 #4 v1 4-11 TW=12.0 c 1 #7 v2 2-8 R=4-0 c2 #8 v3 28 S=15-6 USE "BLACK" REINFORCING, U.N.O. b 2 @ 6" ADOPTED FROM CDOT M.601-1 d 1 BAR TYPICAL N W1, I Ig W2 W 2 (TYP.) r @ 6„ > S = 15'-6" (SKEWED) 3 CLEAR SPAN = 14'-0" PERPENDICULAR TO WALLS WIDTH CDOT "NON-STANDARD" BOX DETAIL SCALE : N.T.S. 494CDOTBOX SCALE : N.T.S. 494CDOTBOX �{ TW SEE S3.00 FOR ^ ,� PARAPET CONDITION " AND REINFORCING CONSTF ( EXPOSE AND LA MIN. LAP SPLICE LENGTH TYP. r DEMO EXISTING PARAPET HEADWALL AND SHORE EXISTING BOX UNTIL NEW SLAB REACHES DESIGN STRENGTH r6"6" TOP SLAB / REINFORCING (TYPICAL) 'UCTION JOINT YPICAL) � I EXISTING REBAR P WITH NEW J BARS 6 TOTAL SKEWED J BARS 6 TOTAL SKEWED BOTTOM SLAB REINFORCING (TYPICAL) EXISTING -- SPAN (FT.) J BAR SIZE (#) 15-6 9 ADDED BARS AT EDGE, SKEW PARALLEL TO EXISTING FACE PROVIDE J-BAR REINFORCING IN NEW BOX ABUTTING EXIST ADDED EXTENSION NOT TO SCALE CONSTRUCTION JOINT DETAIL FOR STAGED CONSTRUCTION SCALE N.T.S. 494COOTBOX GENERAL NOTES 1. ALL CONCRETE SHALL BE CDOT CLASS D (BOX CULVERT) 5000 PSI MIX. 2. ALL CONSTRUCTION JOINTS SHALL BE THOROUGHLY CLEANED BEFORE FRESH CONCRETE IS POURED. 3. ALL CONSTRUCTION JOINTS NOT SHOWN ON THE PLANS SHALL BE APPROVED BY THE ENGINEER. 4. THE CONTRACTOR IS RESPONSIBLE FOR THE STABILITY OF THE STRUCTURE DURING CONSTRUCTION. 5. STRUCTURE EXCAVATION AND BACKFILL SHALL BE IN ACCORDANCE WITH THESE DOCUMENTS. NO CDOT PAYMENT PROVISIONS ARE APPLICABLE, PROJECT IS TO BE BUILT ON A LUMP SUM BASIS. 6. FOR THIS CULVERT SPAN A FOUNDATION INVESTIGATION AND REPORT ARE REQUIRED BY THE CITY. 7. DO NOT BACKFILL UNTIL TOP SLAB HAS REACHED DESIGN STRENGTH, CC. 8. SPLICE QUANTITIES FOR LONGITUDINAL AND TRANSVERSE BARS ARE NOT INCLUDED. 9. GRADE 60 REINFORCING STEEL IS REQUIRED. 10. THE MINIMUM LAP SPLICE LENGTH FOR REINFORCING BARS SHALL BE: BAR SIZE: #4 #5 #6 1 #7 1 #8 #9 #10 #11 SPLICE LENGTH: 1'-10" 2'-5" 3'-1" 3'-11" 11. ALL DIMENSIONS ARE PERPENDICULAR TO THE CENTERLINE OF THE BOX. 12. ALL TRANSVERSE REINFORCING SHALL BE SKEWED TO THE CENTERLINE OF THE BOX AS SHOWN IN 4/S2.00. 13. FILL HEIGHT IS THE DISTANCE MEASURED FROM TOP OF TOP SLAB TO TOP OF PAVEMENT. 14. ALL EXPOSED CONCRETE CORNERS SHALL BE CHAMFERED �/4 IN. DESIGN DATA: 16TH EDITION OF THE AASHTO STANDARD SPECIFICATIONS FOR HIGHWAY BRIDGES STRENGTH DESIGN METHOD UNIT STRESSES: f y = 60,000 psi., VC = 5,000 psi., LOADING DATA: LIVE LOAD = AASHTO, HS 25-44 -- USED 1.25x HS-20 LOADING DEAD LOAD CASE 1: VERTICAL EARTH LOAD = 120 LBS./CU. FT. HORIZONTAL EARTH LOAD = 30 LBS./CU.FT. DEAD LOAD CASE 2: VERTICAL EARTH LOAD = 120 LBS./CU. FT. HORIZONTAL EARTH LOAD = 60 LBS./CU. FT. FUTURE ASPHALT OVERLAY = 48 LBS./SQ. FT. LIVE LOAD SURCHARGE ON EXTERIOR WALLS = 2 FT. OF EARTH FORT COLLINS - LOVELAND WATER DISTRICT SOUTH FORT COLLINS � SAN11'ATION DISTRICT Mr. MichaerD. DiTullio, Manager Date Mr. Te rrill, P E., Disltict Engineer Date All changes, addendums, additions, deletions and modifications to these drawings must be approved, in writing, by the Fort Collins -Loveland Water District and the South Fort Collins Sanitation District. PLEASANT VALLEY AND LAKE CANAL COMPANY Approval Block REVIEWED BY THE PLEASANT VALL Y AND LAKE CANAL COMPANY ON THIS DAY O, 20�THIS PLAT HAS BEEN SIGNED BY THE PLEASANT VALLEY AND LAKE CANAL COMPANY, BUT THIS SHALL NOT MEAN IT APPROVES THE ENGINEERING, SURVEYING, DESIGN, CONSTRUCTION, OR OTHER PROFESSIONAL WORK. THE SIGNATURES MEAN ONLY THAT THE COMPANY HAS SEEN THE SHEETS, SIGNED, AND COOPERATED WITH THE OWNER IN PROVIDING INFORMATION. THE OWNER AND THE PROFESSIONALS IT HAS EMPLOYED ARE SOLELY RESPONSIBLE FOR THE END RESULT. ROBERT UNDERHILL, PRESIDENT City of Fort Collins, Colorado UTILITY APPROVED: Vpproval it �7A eg {-City Engineer Date CHECKED BY: —�k — waterBWastewaterUtlllty Date CHECKED BY: /1/. ,d . / -i/-i Storm�.lwaterr�JJULlty Date CHECKED BY: A),* Traffic Engineer Date CHECKED BY: /ice-rrgi�,� / -RB • O$ �lQNi t' Po,.,ilbS Date CHECKED BY: Environmental Planner Date N r� a bw � o Z ® l� Z LL ® W /yJ- i QZ E0 W M N b O F g N zgZ s ow ® U a s E e m 3 g m N � o w It L N � Z w F G > S an c�tn w3 N CID m co O m o w Z 0 O S VI = Q Y d13 M3 oZ W J (� VU � > X� g mo m eJ W U� Sheet S2.00 C - 3 2 of 4 2154 v to r- (V Ih 1 V 4" ,. 6" 4" SECTION A -A i' CHAMFER i" CHAMFER CONTINUE HORIZONTAL �•. :f REINFORCING THROUGH 1 • • I[NOTCH, PILASTER, RE: 3/S3.00 (6)-#7 VERTICAL W/ ro •� #3 TIES ® 12" O.C. I •�'a '�° DEEP FORMED TYP. i i• BRICK FACING NOT SHOWN FOR CLARITY PARAPET DETAIL SCALE 13/4 — 1 -D 10060630 PARAPET DETAIL.dwg !4)-j"012" EPDXY ANCHOR BOLTS W10x22 (MODIFIED) POST F J"xl4"xl T/ WALL = 5122.59' 4" BRICK VENEER, PROVIDE MASONRY ANCHORS ® 24" O.C., TYP. VERTICAL AND HORIZONTAL GALVANIZED RAIL AND POSTS AS PER FORT 1'-4" COLLINS STANDARD 4" STANDARD PIPE TYP. 6" STANDARD PIPE Jit5-j" FLANGE R AND J" WEB R (OR W10x19, MODIFIED) (2)-#5 CONT. W/ #3 TIES 0 6" O.C. A A T/ WALL = 5122,59' �— STANDARD HOOK, TYP. i • Z BARS, (3)-#8 TOP AND BOTTOM • SLOPES RE: ELEV. #5 ® 6" O.C. 10'k36" \x F_ #5 ®6" O.C. — �<N, #4 ®6" O.C. CONCRETE FINISH CLASS 5 / J��j, 4912" E.F. HORIZ PLACE ONLY ALONG EXPOSED FACE OF CONCRETE BOTH SIDES, TYP. a •'•°• ♦ , 3)#8 BARS J" CHAMFER AT TRANSITION, TYP. INVERT EL EV.( = 5111.34' PARAPET DETAI L SCALE : 3/4" - 1'-0" 20060630 PARAPET DENL.dwg ADD (2)-#8 TOP CONTINUE TOP HORIZONTAL REINFORCING THROUGH VOIDED SLAB 3'-4" VERIFY IN FIELD ADD #7 ® 12" O.C. x 8'-0" BOTTOM CENTERED, TRANSVERSE ACROSS DUCT BANK �a—IF — ----7' • — • • • • • Z • a2T • • [� LIVERI'FY '-DUCT BANK, ° 1}- COMPRESSIBLE POLYETHYLENE IN FIELD WRAP OVER TOP OF DUCT, TYP. FULL LENGTH e a a° a = 5119.23' VOIDED SLAB DETAIL SCALE : 3/4 - 1 -G 20060630 PARAPET DETVL.dwg 10'-7" -4"1 3'-10" It'-41, 3'-10" �'-4" 3'-10" ROAD SIDE RETAINING WALL ELEVATION SCALE : 1/4" = i'-0" 10'- 20060630 ELEVATIONS.dwg I.J.I JLVL „ .,.v� vr• ....�� AND FOOTING SIZE 3n II'-" LF OF RETAINING WALL AND REINFORCING 16'-10ty" (SKEW) 11'-3g" LF OF RETAINING WALL INVERT SIDE RETAINING WALL ELEVATION SCALE : 1/4" = 1'-0" 20060630 ELEVATIONS.dwg FORT COLLINS - LOVEI.AND WATER DISTRICT SOUTH FORT COLLINS SANITATION DISTRICT t z- tl-o7 Mr. Michael I . iTullio, Manager Date Mr. 'e arnll, P.E , Distnct Engineer Date All changes, addendums, additions, deletions and modifications to these drawings must be approved, in writing, by the Fort Collins -Loveland Water District and the South Fort Collins Sanitation District. PLEASANT VALLEY AND LAKE CANAL COMPANY Approval Block REVIEWED BY THE PLEASANT VALLEY AND LAKE CANAL COMPANY ON THIS DAY OFqMMal 20C. j�HIS PLAT HAS BEEN SIGNED BY THE PLEASANT VALLEY AND LAKE CANAL COMPANY, BUT THIS SHALL NOT MEAN IT APPROVES THE ENGINEERING, SURVEYING, DESIGN, CONSTRUCTION, OR OTHER PROFESSIONAL WORK, THE SIGNATURES MEAN ONLY THAT THE COMPANY HAS SEEN THE SHEETS, SIGNED, AND COOPERATED WITH THE OWNER IN PROVIDING INFORMATION. THE OWNER AND THE PROFESSIONALS IT HAS EMPLOYED ARE SOLELY RESPONSIBLE FOR THE END RESULT. ROBERT UNDERHILL. PRESIDENT City of Fort C lins, Colorado UTILITY P An Approval APPROVED:\Alv �Q{ Z O" Date CHECKED BY: AAEngtneer ••,City N�'C Water & Wastewater Utility Date CHECKED BY: &.4. Stormwater Utility Date NA CHECKED BY: Traffic Engineer Date CHECKED BY: '729' C. f'4 firr Fe,"946'117 Date AA CHECKED BY: Environmental Planner Date N Qj C (+1 0 C a 15 w � @ z > v, ® ® V z m LL 7 Y N ri 3� xOU m �= Cz o z5NM ®J 0 o� 0 r 0 m o p 0 J N J0 z W Qlh UN W 3 00 to rn N } m } to O m U O 0 W z CD �a o 3 w3 alp 0� 0z J Sheet S3.00 Sheet 3 of 4 C-� 2154 M C.>