HomeMy WebLinkAboutWESTFIELD PARK PUD - Filed DCP-DEV. CONSTRUCTION PERMIT - 2005-08-31DEVELOPMENT CONSTRUCTION PERMIT
Permit Number: 00-03
Issuance Date: ,,/ - '7 -c �-
Project Name: Westfield Park PUD - Phase 2
Project A.K.A.: n/a
Project Location: Located along Seneca Street south of West Horsetooth Road, north
of West Harmony Road and west of South Shields Street.
Permittee: George Hart, Progressive Living Structures, Inc.
City and developer contacts: See attached Exhibit `A "for names and phone numbers of all
contact persons for this project.
Fees: Permit Application Fee (paid at the time of application) $300.00 paid
Construction Inspection Fee (paid prior to issuance of this permit) $15,587.80
Total $15,887.80
Development Bond or other approved security:
Amount of security deposited with the City to guarantee the completion of all public
improvements to be constructed as shown on the approved plans for the development:
N/A SEi 4 i T/tc aF> D L—E7
Form of security deposited with the City: N/A
PERFORMANCES REQUIREMENTS OF THIS PERMIT:
The Permittee shall be responsible to require their Project Engineer to incorporate into all
design drawings and specifications the certification of all materials testing by an Engineer.
The Penuittee shall have an Engineer prepare revised design drawings and secure City
approval for all revisions to the Utility Plans and related documents. The Permittee shall
have an Engineer represent, as required by the City in the Development Agreement, that the
improvements are constructed in conformance with the approved Utility Plans and the
standards and specifications of the City. The Permittee shall provide "as -constructed" plans
prepared by an Engineer prior to the City's acceptance of the constructed public
improvements. (All references above to the terms "Project Engineer" and "Engineer" shall
mean a Professional Engineer licensed in Colorado.)
All contractors who perform work on this project must be bonded and licensed in
EXHIBIT "A"
DEVELOPMENT PROJECT CONTACT PERSONS
PROJECT NAME: Westfield Park PUD — Phase 3
CITY STAFF CONTACT PERSONS:
DEVELOPMENT ENGINEER: Mark McCallum, City of Fort Collins, 281 N. College
Avenue, Fort Collins, CO 80522
970/221.6605 ext. 7656
CONSTRUCTION INSPECTOR: Lance Newlin, City of Fort Collins, 281 N. College Avenue,
Fort Collins, CO 80522
970/221.6605
CURRENT PLANNER: Steve Olt, City of Fort Collins, 281 N. College Avenue, Fort
Collins, CO 80522
970/221.6750 ext. 6341
WATER UTILITIES ENGINEER: Roger Buffington, 700 Wood Street, Fort Collins, CO
80521
970/221.6854
STORMWATER ENGINEER: Jay Barber, 700 Wood Street, City of Fort Collins, CO
80521
970/221.6063
EROSION CONTROL INSPECTOR: Bob Zakely, 700 Wood Street, City of Fort Collins, CO
80521
970/221.6063
NATURAL RESOURCES: Kim Kreimeyer, City of Fort Collins, 281 N. College
Avenue, Fort Collins, CO 80522
970/221.6750 ext. 6641
TRAFFIC OPERATIONS: Ward Stanford, 700 Wood Street, City of Fort Collins, CO
80521
970/221.6820
STREET CLOSURES: N/A
TRANSPORTATION PLANNING: Kathleen Reavis, 210 East Olive Street, City of Fort Collins,
CO 80524
970/224.6140
FORESTRY: Tim Buchanan, City of Fort Collins, 281 N. College Avenue,
Fort Collins, CO 80522
970/221.6361
1
LIGHT AND POWER: Doug Martine, 700 Wood Street, City of Fort Collins, CO
80521
970/224.6152
DEVELOPER'S CONTACT PERSONS:
PROJECT MANAGER: George Hart, Progressive Living Structures, Inc., 4190
North Garfield, Loveland CO 80538
Office: 970/669.0870
Mobile: 970/567.0199
fax: 970/669.8299
E-mail: ghart@progliv.com
DEVELOPER: Leo Schuster, Progressive Living Structures, Inc., 4190
North Garfield, Loveland CO 80538
Office: 970/669.0870
fax: 970/669.8299
E-mail: Schuster@progliv.com
OWNER(S): Progressive Living Structures, Inc., 4190 North Garfield,
Loveland CO 80538
Office: 970/669.0870
fax: 970/669.8299
ARCHITECT/PLANNER: n/a
PROJECT ENGINEER: Brian Shear PE, Shear Engineering, 4836 South College
Avenue, Suite 12, Fort Collins, CO 80525
Office: 970/226.5334
fax: 970/282.0311
GENERAL CONTRACTOR: Bill Nicholl, Gerrard Excavating, 1739 South County Road
13C, Loveland, CO 80538
Office: 970/669.1463
Fax: 970/669.1964
GRADING CONTRACTOR: n/a
UTILITY CONTRACTOR: n/a
CONCRETE CONTRACTOR
(for flat work): n/a
CONCRETE CONTRACTOR
(For Structures): n/a
N
City Attorney
City of Fort Collins
February 24, 2000
Todd W. Rogers, Esquire
WYATT b1ARTELL WEAVER & ROGERS LLC
222 West Magnolia
Fort Collins, CO 80521
Dear Todd:
VIA FAX TO: (970) 484-1170
ORIGINAL TO FOLLOW VIA lsT CLASS MAIL
RE: Westfield Park P.U.D.
I am in receipt of your February 23, 2000 letter proposing to settle the dispute between your
client and the City regarding Westfield Park P.U.D. upon the basis that your client will pay the new
permit and inspection fees for the balance of Westfield Park P.U.D. (Phases II and III), but that your
client would not be required to provide the development bond or the recently extended maintenance
and repair guarantees nor the collateral security related to those guarantee extensions. I have
discussed this with City Engineer Cam McNair and am authorized to accept your offer, which I do
hereby accept on behalf of the City.
I think you are correct that we ought to formalize this agreement through some
supplementation or amendment of the development agreement. I will commence work on that
amendment and forward a copy to you for your review right away.
:;kman
Deputy City Attorney
WPE:med
PC: Cam McNair, City Engineer
300 LdPnrle Avenue • P.O. Box 580 • Fort Collins, CO 505"-0;80 • r97o) --i _ ;,n . Ga r roam 1�1 �,
Citv of Fort Collins
Transportation Services
Engineering Department
DEVELOPMENT CONSTRUCTION PERMIT
Permit Number: 01-09 Issuance Date:
Project Name: Westfield Park PUD — Phase 3
Project A.K.A.: n/a
Project Location: Located along Seneca Street south of West Horsetooth Roac
of West Harmony Road and west of South Shields Street.
Permittee: George Hart, Progressive Living Structures, Inc.
City and developer contacts: See attached Exhibit `;A "for names and phone numbers of all
contact persons for this project.
Fees: Permit Application Fee (paid at the time of application) $300.00 paid
Construction Inspection Fee (paid prior to issuance of this permit) $10,005.40
Total $10,005.40
Development Bond or other approved security:
Amount of security deposited with the City to guarantee the completion of all public
improvements to be constructed as shown on the approved plans for the development:
N/A
Form of security deposited with the City: N/A
PERFORMANCE REQUIREMENTS OF THIS PERMIT:
l . The Permittee shall be responsible to require their Project Engineer to incorporate into all
design drawings and specifications the certification of all materials testing by an Engineer.
The Permittee shall have an Engineer prepare revised design drawings and secure City
approval for all revisions to the Utility Plans and related documents. The Permittee shall
have an Engineer represent, as required by the City in the Development Agreement, that the
improvements are constructed in conformance with the approved Utility Plans and the
standards and specifications of the City. The Permittee shall provide "as -constructed" plans
�81 ,North Cnllc;'c :lvenuC • P.C. Box 80 • Port Collins, CO 80532-0780 • (970) 221-o605
DEVELOPMENT CONSTRUCTION PERMIT
Permit Number: 00-03 Issuance Date: - 7:7; —e �
Project Name: Westfield Park PUD - Phase 2
Project A.K.A.: n/a
Project Location: Located along Seneca Street south of West Horsetooth Road, north
of West Harmony Road and west of South Shields Street.
Permittee: George Hart, Progressive Living Structures, Inc.
City and developer contacts: See attached Exhibit "A "for names and phone numbers of all
contact persons for this project.
Fees: Permit Application Fee (paid at the time of application) $300.00 paid
Construction Inspection Fee (paid prior to issuance of this permit) $15,587.80
Total $15,887.80
Development Bond or other approved security:
Amount of security deposited with the City to guarantee the completion of all public
improvements to be constructed as shown on the approved plans for the development:
N/A <_�E 4 i rAc ►t ✓D LX_--TcR
Form of security deposited with the City: N/A
PERFORMANCE REQUIREMENTS OF THIS PERMIT:
The Permittee shall be responsible to require their Project Engineer to incorporate into all
design drawings and specifications the certification of all materials testing by an Engineer.
The Permittee shall have an Engineer prepare revised design drawings and secure City
approval for all revisions to the Utility Plans and related documents. The Permittee shall
have an Engineer represent, as required by the City in the Development Agreement, that the
improvements are constructed in conformance with the approved Utility Plans and the
standards and specifications of the City. The Permittee shall provide "as -constructed" plans
prepared by an Engineer prior to the City's acceptance of the constructed public
improvements. (All references above to the terms "Project Engineer" and "Engineer" shall
mean a Professional Engineer licensed in Colorado.)
2. All contractors who perform work on this project must be bonded and licensed in
03-29-00 0521 CHECK 15567.80
conformance with City requirements.
Construction time restrictions: N/A
4. The applicant understands that additional permits may be required for this development
project and the applicant shall secure those permits directly from the issuing departments.
This permit, along with a complete set of all approved plans and documents for this project
(utility plans, site plan, landscape plan, development agreement, soils report, pavement
design, traffic study, drainage report, plat easements and any other official documents), shall
be kept on the development site available for use by City staff doing inspections.
6. Permit Expiration (in accordance with Section 29-12 of the Transitional Land Use
Regulations or Section 2.6.3(K) of the Land Use Code, whichever is applicable):
a. If construction has not begun within sixty (60) days from the date of issuance
of this permit, this permit shall expire and the applicant will forfeit the
permit fee paid for this permit, whereupon the applicant must re -apply for a
new permit.
b. In addition, this permit shall expire one year from the date of issuance. The
applicant may apply for an extension by reapplication at least two weeks prior
to the expiration date. Such application shall contain information sufficient
to justify the granting of the extension. An extension maybe granted for up
to six months.
Building permits and certificates of occupancy will only be issued when all conditions
contained in the Development Agreement and Sections 3.3.2(C) and (D) of the Land Use
Code or Sections 29-678 and 29-679 of the Transitional Land Use Regulations, whichever
is applicable, are met. If the Development Agreement does not specify times for completion
of public improvements, or if there is no Development Agreement, then the improvement
requirements specified in Section 24-95 of the City Code shall apply, which provides that
construction of all improvements shall be required prior to the time of issuance of the first
building permit.
8. Acceptance by the City of the public improvements shall be after (1) final inspection has been
conducted by the City; (2) punch list items from the final inspection are completed and
accepted by the City; and (3) required certifications from the licensed professional engineer
that improvements are completed to City standards, specifications and approved Utility
Plans; and the "as -constructed" plans have been received accepted by the City.
e N1/
9. The warranty on street improvements is for five (5 year$ m the date of acceptancedry the
10. The City Erosion Control Inspector must be notified at least twenty-four (24) hours prior to
any planned construction on this project. All required perimeter silt fencing and other
erosion/sediment control best management practices (BMP's) that can be installed prior to
construction must be in place and inspected by the City Erosion Control Inspector before any
land disturbing activity begins.
11. Other conditions:
Pcrmittee's acknowledgment signature:
By signing this permit I acknowledges that I am acting with the knowledge, consent, and authority of
the owners of the property (including all owners having legal or equitable interest in the real property,
as defined in Section 1-2 of the City Code; and including common areas legally connected to or
associated with the property which is the subject of this application) without whose consent and authority
the requested action could not lawfully be accomplished. Pursuant to said authority, I hereby permit City
officials to enter upon the property for purposes of inspection and, if necessary, to enter upon such
property to perform work required of the applicant if the applicant were to fail to perform the required
work. I also acknowledge that I have read this permit document with all its requirements and
conditions, and I agree to all of the terms and conditions so stated in this permit.
Applicant/Project Manager's Signature: ��11 _Date: 3 30 00
Approval for issuance: YY
City Engineer Approval: , 1 2 Date: li - 3 - ci- 1
(Permit Issuance Date)
EXHIBIT "A"
DEVELOPMENT PROJECT CONTACT PERSONS
PROJECT NAME: Westfield Park PUD — Phase 2
CITY STAFF CONTACT PERSONS:
DEVELOPMENT ENGINEER: Tim Blandford, City of Fort Collins, 281 N. College Avenue,
Fort Collins, CO 80522
970/221.6605 ext. 7128
CONSTRUCTION INSPECTOR: Jeff Baldwin, City of Fort Collins, 281 N. College Avenue,
Fort Collins, CO 80522
970/217.8899
CURRENT PLANNER: Steve Olt, City of Fort Collins, 281 N. College Avenue, Fort
Collins, CO 80522
970/221.6750 ext. 6341
WATER UTILITIES ENGINEER: Roger Buffington, 700 Wood Street, Fort Collins, CO
80521
970/221.6854
STORMWATER ENGINEER: Jay Barber, 700 Wood Street, City of Fort Collins, CO
80521
970/221.6063
EROSION CONTROL INSPECTOR: Bob Zakely, 700 Wood Street, City of Fort Collins, CO
80521
970/221.6063
NATURAL RESOURCES: Kim Kreimeyer, City of Fort Collins, 281 N. College
Avenue, Fort Collins, CO 80522
970/221.6750 ext.6641
TRAFFIC OPERATIONS: Ward Stanford, 700 Wood Street, City of Fort Collins, CO
80521
970/221.6820
STREET CLOSURES: N/A
TRANSPORTATION PLANNING: Kathleen Reavis, 210 East Olive Street, City of Fort Collins,
CO 80524
970/224.6140
FORESTRY: Tim Buchanan, City of Fort Collins, 281 N. College Avenue,
Fort Collins, CO 80522
970/221.6361
LIGHT AND POWER: Doug Martine, 700 Wood Street, City of Fort Collins, CO
80521
970/224.6152
DEVELOPER'S CONTACT PERSONS:
PROJECT MANAGER: George Hart, Progressive Living Structures, Inc., 4190
North Garfield, Loveland CO 80538
Office: 970/669.0870
Mobile: 970/567.0199
fax: 970/669.8299
E-mail: ghart@progliv.com
DEVELOPER: Leo Schuster, Progressive Living Structures, Inc., 4190
North Garfield, Loveland CO 80538
Office: 970/669.0870
fax: 970/669.8299
E-mail: lschuster@progliv.com
OWNER(S): Progressive Living Structures, Inc., 4190 North Garfield,
Loveland CO 80538
Office: 970/669.0870
fax: 970/669.8299
ARCHITECT/PLANNER: n/a
PROJECT ENGINEER:
Brian Shear PE, Shear Engineering, 4836 South College
Avenue, Suite 12, Fort Collins, CO 80525
Office: 970/226.5334
fax: 970/282.0311
GENERAL CONTRACTOR:
Bill Nichol], Gerrard Excavating, 1739 South County Road
13C, Loveland, CO 80538
Office: 970/669.1463
Fax: 970/669.1964
GRADING CONTRACTOR:
n/a
UTILITY CONTRACTOR:
n/a
CONCRETE CONTRACTOR
(for flat work):
n/a
CONCRETE CONTRACTOR
(For Structures): n/a
PAVING CONTRACTOR:
LANDSCAPE CONTRACTOR:
OUTSIDE CONTACT PERSONS:
U.S. WEST:
n/a
n/a
Joyce Takamoto, 124 W. Magnolia, Fort Collins, CO
80521
970/224.7473
AT&T CABLE SERVICES: Dennis Greenwalt, 1201 University Avenue, Fort Collins,
CO 80521
970/226.3104
PUBLIC SERVICE COMPANY: Jim Slagle, 1901 East Horsetooth Road, Fort Collins, CO
80525
970/225.7843
POUDRE FIRE AUTHORITY: Ron Gonzales, 102 Remington Street, Fort Collins, CO
80524
970/221.6570
3
conformance with City requirements.
Construction time restrictions: N/A
4. The applicant understands that additional permits may be required for this development
project and the applicant shall secure those permits directly from the issuing departments.
5. This permit, along with a complete set of all approved plans and documents for this project
(utility plans, site plan, landscape plan, development agreement, soils report, pavement
design, traffic study, drainage report, plat easements and any other official documents), shall
be kept on the development site available for use by City staff doing inspections.
Permit Expiration (in accordance with Section 29-12 of the Transitional Land Use
Regulations or Section 2.6.3(K) of the Land Use Code, whichever is applicable):
a. If construction has not begun within sixty (60) days from the date of issuance
of this permit, this permit shall expire and the applicant will forfeit the
permit fee paid for this permit, whereupon the applicant must re -apply for a
new permit.
In addition, this permit shall expire one year from the date of issuance. The
applicant may apply for an extension by reapplication at least two weeks prior
to the expiration date. Such application shall contain information sufficient
to justify the granting of the extension. An extension may be granted for up
to six months.
Building permits and certificates of occupancy will only be issued when all conditions
contained in the Development Agreement and Sections 3.3.2(C) and (D) of the Land Use
Code or Sections 29-678 and 29-679 of the Transitional Land Use Regulations, whichever
is applicable, are met. If the Development Agreement does not specify times for completion
of public improvements, or if there is no Development Agreement, then the improvement
requirements specified in Section 24-95 of the City Code shall apply, which provides that
construction of all improvements shall be required prior to the time of issuance of the first
building permit.
8. Acceptance by the City of the public improvements shall be after (1) final inspection has been
conducted by the City; (2) punch list items from the final inspection are completed and
accepted by the City; and (3) required certifications from the licensed professional engineer
that improvements are completed to City standards, specifications and approved Utility
Plans; and the "as -constructed" plans have been received accepted by the City.
Coe 0
9. The warranty on street improvements is for year r in the date of acceptance.by-the-
UIMMAMR .: FMILip
10. The City Erosion Control Inspector must be notified at least twenty-four (24) hours prior to
any planned construction on this project. All required perimeter silt fencing and other
erosion/sediment control best management practices (BMP's) that can be installed prior to
construction must be in place and inspected by the City Erosion Control Inspector before any
land disturbing activity begins.
11. Other conditions:
Permittee's acknowledgment signature:
By signing this permit I acknowledges that I am acting with the knowledge, consent, and authority of
the owners of the property (including all owners having legal or equitable interest in the real property,
as defined in Section 1-2 of the City Code; and including common areas legally connected to or
associated with the property which is the subject of this application) without whose consent and authority
the requested action could not lawfully be accomplished. Pursuant to said authority, I hereby permit City
officials to enter upon the property for purposes of inspection and, if necessary, to enter upon such
property to perform work required of the applicant if the applicant were to fail to perform the required
work. I also acknowledge that I have read this permit document with all its requirements and
conditions, and I agree to all of the terms and conditions so stated in this permit.
Applicant/Project Manager's Signature: Date: 3 30Oo
Approvaiforissuance:
City Engineer Approval: -- 1 �1 Date:
�; (Permit Issuance Date)
EXHIBIT "A"
DEVELOPMENT PROJECT CONTACT PERSONS
PROJECT NAME: Westfield Park PUD — Phase 2
CITY STAFF CONTACT PERSONS:
DEVELOPMENT ENGINEER: Tim Blandford, City of Fort Collins, 281 N. College Avenue,
Fort Collins, CO 80522
970/221.6605 ext. 7128
CONSTRUCTION INSPECTOR: Jeff Baldwin, City of Fort Collins, 281 N. College Avenue,
Fort Collins, CO 80522
970/217.8899
CURRENT PLANNER: Steve Olt, City of Fort Collins, 281 N. College Avenue, Fort
Collins, CO 80522
970/221.6750 ext. 6341
WATER UTILITIES ENGINEER: Roger Buffington, 700 Wood Street, Fort Collins, CO
80521
970/221.6854
STORMWATER ENGINEER: Jay Barber, 700 Wood Street, City of Fort Collins, CO
80521
970/221.6063
EROSION CONTROL INSPECTOR: Bob Zakely, 700 Wood Street, City of Fort Collins, CO
80521
970/221.6063
NATURAL RESOURCES: Kim Kreimeyer, City of Fort Collins, 281 N. College
Avenue, Fort Collins, CO 80522
970/221.6750 ext. 6641
TRAFFIC OPERATIONS: Ward Stanford, 700 Wood Street, City of Fort Collins, CO
80521
9701221.6820
STREET CLOSURES: N/A
TRANSPORTATION PLANNING: Kathleen Reavis, 210 East Olive Street, City of Fort Collins,
CO 80524
970/224.6140
FORESTRY: Tim Buchanan, City of Fort Collins, 281 N. College Avenue,
Fort Collins, CO 80522
970/221.6361
LIGHT AND POWER: Doug Martine, 700 Wood Street, City of Fort Collins, CO
80521
970/224.6152
DEVELOPER'S CONTACT PERSONS:
PROJECT MANAGER: George Hart, Progressive Living Structures, Inc., 4190
North Garfield, Loveland CO 80538
Office: 970/669.0870
Mobile: 970/567.0199
fax: 970/669.8299
E-mail: ghart@progliv.com
DEVELOPER: Leo Schuster, Progressive Living Structures, Inc., 4190
North Garfield, Loveland CO 80538
Office: 970/669.0870
fax: 970/669.8299
E-mail: Schuster@progliv.com
OWNER(S): Progressive Living Structures, Inc., 4190 North Garfield,
Loveland CO 80538
Office: 970/669.0870
fax: 970/669.8299
ARCHITECT/PLANNER: n/a
PROJECT ENGINEER: Brian Shear PE, Shear Engineering, 4836 South College
Avenue, Suite 12, Fort Collins, CO 80525
Office: 970/226.5334
fax: 970/282.0311
GENERAL CONTRACTOR: Bill Nicholl, Gerrard Excavating, 1739 South County Road
13C, Loveland, CO 80538
Office: 970/669.1463
Fax: 970/669.1964
GRADING CONTRACTOR: n/a
UTILITY CONTRACTOR: n/a
CONCRETE CONTRACTOR
(for flat work): n/a
CONCRETE CONTRACTOR
(For Structures): n/a
PAVING CONTRACTOR: n/a
LANDSCAPE CONTRACTOR: n/a
OUTSIDE CONTACT PERSONS:
U.S. WEST: Joyce Takamoto, 124 W. Magnolia, Fort Collins, CO
80521
970/224.7473
AT&T CABLE SERVICES: Dennis Greenwalt, 1201 University Avenue, Fort Collins,
CO 80521
970/226.3104
PUBLIC SERVICE COMPANY: Jim Slagle, 1901 East Horsetooth Road, Fort Collins, CO
80525
970/225.7843
POUDRE FIRE. AUTHORITY: Ron Gonzales, 102 Remington Street, Fort Collins, CO
80524
970/221.6570
3
City of Fort Collins
Transportation Services
Frigineering Department
DEVELOPMENT CONSTRUCTION PERMIT
Permit Number: 01-09 Issuance Date:
Project Name: Westfield Park PUD — Phase 3
ProjectA.RA.: n/a
Project Location: Located along Seneca Street south of West Horsetooth Road, north
of West Harmony Road and west of South Shields Street.
Permittee: George Hart, Progressive Living Structures, Inc.
City and developer contacts: See attached Exhibit `A "for names and phone numbers of all
contact persons for this project.
Fees: Permit Application Fee (paid at the time of application) $300.00 paid
Construction Inspection Fee (paid prior to issuance of this permit) $10,005.40
Total $10,005.40
Development Bond or other approved security:
Amount of security deposited with the City to guarantee the completion of all public
improvements to be constructed as shown on the approved plans for the development:
N/A ca .\il.\Cr1c-�LtTlt
Form of security deposited with the City: N/A
PERFORMANCE REQUIREMENTS OF THIS PERMIT:
The Permittee shall be responsible to require their Project Engineer to incorporate into all
design drawings and specifications the certification of all materials testing by an Engineer.
The Permittee shall have an Engineer prepare revised design drawings and secure City
approval for all revisions to the Utility Plans and related documents. The Permittee shall
have an Engineer represent, as required by the City in the Development Agreement, that the
improvements are constructed in conformance with the approved Utility Plans and the
standards and specifications of the City. The Permittee shall provide "as -constructed" plans
I tII ( Alr,q,• Acrntic • P.O. Box ;80 • 1-ort Collins, CO 807;12-0;,ail • 0 01 01 1-66(i;
prepared by an Engineer prior to the City's acceptance of the constructed public
improvements. (All references above to the terms "Project Engineer" and "Engineer" shall
mean a Professional Engineer licensed in Colorado.)
2. All contractors who perform work on this project must be bonded and licensed in
conformance with City requirements.
Construction time restrictions: N/A
4. The applicant understands that additional permits may be required for this development
project and the applicant shall secure those permits directly from the issuing departments.
5. This permit, along with a complete set of all approved plans and documents for this project
(utility plans, site plan, landscape plan, development agreement, soils report, pavement
design, traffic study, drainage report, plat easements and any other official documents), shall
be kept on the development site available for use by City staff doing inspections.
6. Permit Expiration (in accordance with Section 29-12 of the Transitional Land Use
Regulations or Section 2.6.3(K) of the Land Use Code, whichever is applicable):
a. If construction has not begun within sixty (60) days from the date of issuance
of this permit, this permit shall expire and the applicant will forfeit the
permit fee paid for this permit, whereupon the applicant must re -apply for a
new permit.
b. In addition, this permit shall expire one year from the date of issuance. The
applicant may apply for an extension by reapplication at least two weeks prior
to the expiration date. Such application shall contain information sufficient
to justify the granting of the extension. An extension may be granted for up
to six months.
Building permits and certificates of occupancy will only be issued when all conditions
contained in the Development Agreement and Sections 3.3.2(C) and (D) of the Land Use
Code or Sections 29-678 and 29-679 of the Transitional Land Use Regulations, whichever
is applicable, are met. If the Development Agreement does not specify times for completion
of public improvements, or if there is no Development Agreement, then the improvement
requirements specified in Section 24-95 of the City Code shall apply, which provides that
construction of all improvements shall be required prior to the time of issuance of the first
building permit.
Acceptance by the City of the public improvements shall be after (1) final inspection has been
conducted by the City; (2) punch list items from the final inspection are completed and
accepted by the City; and (3) required certifications from the licensed professional engineer
that improvements are completed to City standards, specifications and approved Utility
Plans; and the "as -constructed" plans have been received and accepted by the City.
9. The warranty on street improvements is for five (5) years from the date of acceptance by the
City of the completed improvements, in accordance with Sections 29-13 and 29-14 of the
Transitional Iand Use Regulations and/or Sections 2.2.3(C)(3)(g), 3.3.1(C)(2), and 3.3.2(C)
of the Land Use Code, as applicable.
10. The City Erosion Control Inspector must be notified at least twenty-four (24) hours prior to
any planned construction on this project. All required perimeter silt fencing and other
erosion/sediment control best management practices (BMP's) that can be installed prior to
construction must be in place and inspected by the City Erosion Control Inspector before any
land disturbing activity begins.
Permittee's acknowledgment signature:
By signing this permit I acknowledges that I am acting with the knowledge, consent, and authority of
the owners of the property (including all owners having legal or equitable interest in the real property,
as defined in Section 1-2 of the City Code; and including common areas legally connected to or
associated with the property which is the subject of this application) without whose consent and authority
the requested action could not lawfully be accomplished. Pursuant to said authority, I hereby permit City
officials to enter upon the property for purposes of inspection and, if necessary, to enter upon such
property to perform work required of the applicant if the applicant were to fail to perform the required
work. I also acknowledge that I have read this permit document with all its requirements and
conditions, and I agree to all of the terms and conditions so stated in this permit.
Z
Applicant/Project Manager's Signature: Date:
X744�
Approval for issuance:
City Engineer Approval: V t� t'\ -"� Date:
(Permit Issuance Date)