May 20, 2002
Basil Harridan
City of Fort Collins Engineering
P.O. Box 580
Fort Collins, CO 80521
RE: Response to Redlined Plan dated May 10, 2002
Provincetowne PUD, Filing #2
Dear Basil:
COLORADO
Littleton
8232 E. Park Meadows Drive
Littleton, CO 80124
303.708-0500
Fax 303.708.0400
Email: info@manhard.com
ILLINOIS
Vernon Hills
847.634.5550
Downers Grove
630.515.8500
We have received your redlined drawing for the Provincetowne, PUD Filing #2 Trilby Road
sanitary sewer. We have provided the following written response and the enclosed final
drawing for your review. A mylar drawing has been sent to Mr. Terry Farrill for approval and
will then be forwarded to you.
1. The proposed ground above pipe would leave no cover contrary to your statement in
the response letter. Please provide minimum cover above the pipe.
Response: The cover shown above the 24" storm pipe has been proposed so that
the pipe daylights into the channel. Therefore, no cover is needed at that
location (the flared end section). In the future, the sidewalk will be extended
and improvements to this area will be required. The future sidewalk will be at
approximately 4959.0, while the top of the 24" will be at approximately 4957.0,
resulting in a clearance of 2 feet. These proposed future improvements are not
shown on this plan since they are not to be constructed at this time.
If you should have any questions, please do not hesitate to contact me.
Yours truly,
MANHARD CONSULTING, LTD.
Sean Be' ins, P. .
Project Manager
SB/jlp
cc: Sheri Wamhoff, City of Fort Collins Engineering
Terry Farrill, Fort Collins/Loveland Water and Sanitation District
P: 0cfcc/documents/review comments/5-20-02
Engineers
Surveyors
Planners
MANHARD
CONSULTING
April 23, 2002
Sheri Wamhoff
City of Fort Collins Engineering
281 North College Avenue
Fort Collins. CO 80522
RE: Response to Comments Dated April 17, 2002
Provincetowne PUD, Filing #2
Dear Sheri:
C_OLORADO
Littleton
II232 E Pa,k Moadom,s Dnvr
LillIelon, C0 801 11
101.708 0500
F, 305.708A400
Email: Ink,(!n,anhardrum
ILLINOIS
Vernon Hills
847.614, 5550
Downers Grove
630.111 58500
We have received your comments for the Provincetowne, PUD Filing #2 Trilby Road sanitary
sewer. We have provided the following written responses and a revised plan for your review.
1. Need to work with the district on providing easements for this line and the installation
of it outside of the row.
Response: The sewer will now end at the property line and will no longer need an
easement.
2. Show the channel in its existing condition. How much cover is above this line? The
culvert will need to be extended in the future. Is there clearance so that this line can
be extended in the future? Show where the culvert would sit over the sewer line, the
culvert will need to be extended beyond the sidewalk with future improvements.
Response: There is adequate clearance for the culvert to be extended in the
future. The crossing is shown on the profile.
3. Need to number this sheet as a part of the original set.
Response: The sheet number has been changed to 62A of 99.
If you should have any questions, please do not hesitate to contact me.
Yours truly,
MANHARD CONSULTING, LTD. engineers
Surveyors
Planners
Sean Berzins, P.E.
Project Manager
SB/jlp
P: kbcfcc/documents/review comments/4-23-02
Services
Engineering Department
City of Fort Collins
May 17, 2002
Jim Pearson
KB Homes Colorado Inc.
8401 East Belleview Ave, Ste 200
Denver, Co 80237
Re: Provincetowne PUD Filing 2 ditch lateral and diversion structure construction.
Dear Jim;
It was brought to our attention by Steve Dyekman the Superintendent for the North Louden Ditch that some work
was occurring on the lateral that extends eastward from the Benson Reservoir that they were not aware of and not all
of the work being done is acceptable to them. It appears the work being done is shown on the approved Utility Plans
for this project. However, the Utility Plans do not contain the Ditch Companies/ Owners approval as required by
Section 1.2.7 of the Storm Drainage Design Criteria and Construction Standards.
In accordance with these standards the Developer is responsible for contacting the Ditch Company and obtaining the
appropriate ditch company signatures prior to submitting for City review and approval. The City Natural Resources
Department has also indicated to me that they told Manhard Engineering (the design consultant) that they needed to
work with the Lateral owner and get there approval for all work associated with and/or would impact the lateral. It
does not appear that this was done.
In order to correct this error KB Homes needs to work with the lateral owner to obtain approval for the work
associated with the lateral, correct problems with the diversion structure (correct gate placement and make sure that
the water will go into the appropriate ditch when the gate for that ditch is opened) and provide an easement adequate
for maintenance of the lateral. Approval can be signatures on the existing plans showing approval of existing
designs or signature on revised plans. Any revisions to the plans also need to be reviewed and approved by the City.
Let us know within 2 weeks of the date of receiving this letter as to your planed course of action and anticipated
timeline.
If you have any questions, please contact Sheri Wamhoff at 221-6750.
Sincerely,
Sheri L. Wamhofi; P.E.
cc: Teresa England, KB Homes Colorado Inc.
Steve Dyekman, North Louden Ditch Superintendent
Cam McNair, City of Fort Collins City Engineer
Lance Newlin, City of Fort Collins Engineering Inspection
Glen Schlueter, City of Fort Collins Stormwater Utility
Mark Sears, City of Fort Collins Natural Resources
Doug Moore, City of Fort Collins Natural Resources
file