HomeMy WebLinkAboutSPRING CREEK CENTER PUD - Filed CS-COMMENT SHEETS - 2005-07-13DATE: 11/20/02
REVISION
COMMENT SHEET
DEPT: ENGINEERING
PROJECT: Spring Creek Center Pud
ENGINEER: Sheri Wamhoff
❑ No Problems
ET 5rroblems or Concerns (see below or attached)
Comments:
Spring Creek Center PUD revisions November 20, 2002
• The revisions do not need to be noted on the cover sheet as there are no changes shown on this sheet.
• Sheet 2 — need to bubble all the areas that have changed since the original plan approval. Need to adjust
the information on the culverts under Midpoint Drive. The revision needs to be number 1 as it is the first
revision on this sheet.
• Sheet 3 — The revisions need to start at number 1 on each sheet and be numbered consecutively after
that. It doesn't matter that the same change maybe another number on another sheet.
• Sheet 4 —The first revision doesn't need to be noted since it was a brand new sheet that was signed and
nothing was bubbled. Need to bubble everything that has changed and show the change at the
intersection.
• Sheet 5 —As with sheet 4 the first item listed doesn't need to be. Adjust the numbering.
• Sheet 6 — adjust the numbering to start at 1 and go up from there. Need to make the changes to the
information called out for the Midpoint Drive intersection and bubble all the changes made.
• Sheet 7 — Missing the shading in Pond 3 that was originally shown. Need to adjust the numbering.
• Sheet 9, 12 and '12a — Adjust the numbering.
• Sheet 10 — Need to show the proposed changes to the intersection on all the views. Unable to check the
design as we do not have turning templates for a 1" = 30' scale (do have 1 "=50' though). Need to include
all the previous notes that were on the details. Adjust the numbering to start at 1.
• Landscape plan -- Need to show al the utilities on the plan — main lines and services. Need to make sure
that the landscaping is meeting the separation requirements.
• Site Plan — the wrong scale is on the plan.
Date: November 20, 2002 Signajritfe
PLEASE SEND COPIES OF MARKED REV - IONS
❑ Plat 0 Site,(}ility ❑ Landscape ❑ Drainage Report ❑ NO COMMENT -SUBMIT MYLARS
PROJECT
COMMENT SHEET
City of Fort Collins
Current Planning
DATE: ember 27, 1996 DEPT: 04�r fZJ
PROJECT: #17-90C Spring Creek Center PUD -Preliminary
PLANNER: Mike Ludwig
All comments must be received by: Monday, December 16, 1996
�+t�wK�he�ih v� Goisfrercf b o� �uc ✓eacwa y5 ui'/l ✓egu e
>iC�i iar.nan/ t7•rGf f'iha� iG�%S /n✓es%7�ya /-rbvrs RS Gam/ a$ lAa vesnCn
✓C. r�ak%l ka. /�ai��u/ate rL�le.-e5t rn .�v-c�mvrvv.rv/f'S
fv /die t'�ferral �ba�.-mays, �T�mbe.-lr�•c ��C /�.vs�«f�
Date: l2 1319 Signature
CHECK: IF YOU WISH TO RECEIVE PLAT
COPIES OF REVISIONS SITE
❑ LANDSCAPE
[� UTILITY
PROJECT
COMMENT SHEET
City of Fort Collins
Current Planning
DATE: November 27, 1996 DEPT: Engineering
PROJECT: #17-90C Spring Creek Center PUD - Preliminary
PLANNER: Mike Ludwig
All comments must be received by: Monday, December 16, 1996
Soils Report:
• Recommends perimeter drains - sump and pump system or daylight to Spring
Creek (o.k. to daylight to Spring Creek with Stormwater as part of drainage
design)
Traffic Study:
• City Traffic 'Engineer has requested that the curb cuts along Midpoint Drive be
consolidated into one
• Study is based on Timberline/ Midpoint intersection being a right-in/right-out in
the short range. However, there is no discussion about whether this assumption
was made because there will eventually be a median in Timberline since it is a
major arterial, when there will be the need for a median in Timberline, and/or if
the median is needed to be constructed as a result of this development or at a
certain phase of this development. Please clarify. (According to the City's
Timberline project engineers, the City has no plans for improving Timberline
south of Prospect Road at this time other than some changes to the lane striping
when the Timberline extension is complete.)
Date: 12�12Itib Signature K`
CHECK: IF YOU WISH TO RECEIVE El PLAT
COPIES OF REVISIONS SITE
® LANDSCAPE
$� UTILITY
Site Plan:
• City staff wiill discuss whether or not the City wants to pay for reconstructing the
sidewalk on Prospect Road to the new standard detached walk where it is
possible along the frontage of this site. Due to the existing street trees behind
the walk, it is unlikely that the City will want to relocate and reconstruct the
sidewalk at this time.
• Eliminate the "bump out' in the sidewalk around the existing fire hydrant on
Specht Point Road. Relocate the fire hydrant and leave the sidewalk in its
standard location along the r.o.w. line.
• Label all parkway and sidewalk widths including any existing sidewalks
(Prospect)
• Driveways must intersect Specht Point Road at 900 for at least 50 feet back from
the travelway. Since these will be relatively high volume driveways it is important
that drivers are able to approach the intersection at the best possible angle for
visibility. Also, angled driveways result in vehicles stopping at awkward
approach angles in and out of the driveway and often obstruct the access
altogether.
• The car wash exit on Lot 1 conflicts with the entrance and exit to Lot 1
Plat:
• Clarify the r.o.w. dedication (existing and/or proposed) for all streets around the
perimeter of the site - especially Timberline Road.
• The minimum required utility easement width along Timberline Road and
Prospect Road is 15 feet and 9 feet along Specht Point and Midpoint.
Utility Plans
• See comments on site plan, etc.
• It is not clear from the plans what the proposed improvements to Timberline
Road are - there are no dimensions, no clear distinction between existing and
proposed asphalt, curb and gutter, improvements across Spring Creek (e.g.
sidewalk), striping and lane configuration Timberline, etc. Even though this is a
preliminary, there should be some basic information to show what is proposed
and existing in terms of street improvements.
• Provide the preliminary off -site design for the ultimate width of Timberline Road
to the south, where Timberline Road will be centered on the section line, and
show the curvature and transition to the Spring Creek bridge (being the ultimate
east curb line). Set the curb and gutter location along this property based on
that design. Mike Herzig has some background on what was planned for the
Timberline alignment south of Prospect and how it would transition to the south
to be centered along the section line.
The only improvements the City has planned for Timberline south of Prospect, as
described previously, are changes to the striping and laneage (existing free right,
and left/ through will be reconfigured for a dedicated left turn lane and a
through/right).
The new street standards require a 4.5 foot wide sidewalk on Midpoint and
Specht Point and a 6 foot parkway width - label all parkway and sidewalk width
around the perimeter of the site and provide additional sidewalk easement where
necessary.
PROJECT
COMMENT SHEET
City of Fort Collins
Current Planning
DATE: November 27, 1996 DEPT: Mapping
PROJECT: #17-90C Spring Creek Center PUD -Preliminary
PLANNER: Mike Ludwig
All comments must be received by: Monday, December 16, 1996
�vIck pjc, M.
Date: Signature
CHECK IF YOU WISH TO RECEIVE ❑ PLAT
COPIES OF REVISIONS ❑ SITE
❑ LANDSCAPE
❑ UTILITY
REVISION
COMMENT SHEET
DATE: 12/11/02 DEPT: Engineering
PROJECT: Slpring Creek Center Pud
This is a combined minor amendment and revision to the project
ENGINEER: Sheri Wamhoff
All comments must be received by: 12/30/02
❑ Igo Problems
roblems or Concerns (see below or attached)
Comments:
Spring Creek Center Revisions
Sheets 2 and 6 — include all the area that is being changed in the bubble.
Sheet 10 — Missing the striping #'s and letters on the details and the table that contained this information which was
on the plans previously. This needs to be put back on the plans.
Missing some notes that were on this sheet previously. Add in the island elevations and curve #'s and length #'s
back on the island detail. Also missing a prior note from this detail.
The island detail for template — if this was added just for my use I don't need it now that the proposed changes are
shown on the Timberline Road and Midpoint Drive striping plan. It is at a scale that I can use the turning template
on. It is tight, but better than existing condition.
Date: /� SigUature:
PLEASE SEND COPIES OF MARKED REVISIONS
❑ Plat ❑ Site ❑ Utility 0 Landscape ❑ Drainage Report 11 NO COMMENTS -SUBMIT MYLARS
a
PROJECT
6
COMMENT SHEET
City of Fort Collins
Current Planning
DATE: February 8, 1999 TO: Engineering
PROJECT: #2-99 Advanced Energy, Buildings 7 & 8 — Final
Plan (LUC)
All comments must be received by Steve Olt no later than the staff
review meeting:
Wednesday, March 3, 1999
Advanced Energy, Buildings 7 and 8
March 8, 1999
• Provide the additional easements needed as identified by stormwater
• Please make the project name on the Title Sheet read "Advanced Energy, Buildings 7 and 8"
• Add Timberline Road plan and profile and striping sheet to the index and number it as sheet 9
of 13
On Timberline Road plan and profile and striping sheet.
• The design of Timberline and the right turnlane is not adequate
• For the asphalt pavement joint detail - the cut and additional pavement needs to be in
accordance with the City of Fort Collins 'Street Repair and Reconstruction Standards and
Guidelines'
• For including this sheet in this set - do not provide the storm sewer references or the Specht
Point Road striping plan as this project will not be putting those improvements in.
• This page needs to be numbered as a part of this set of plans and labeled with this projects
name and not Spring Creek Centers.
• For additional comments on this sheet see Traffic Operations comments (for advanced energy,
buildings 7 and 8) dated 2/27/99 and comments from Tim Blandford on Spring Creek Center
returned previously.
Date: 3� 9/ Signature: ('5• W/lfjli/
CHECK HERE IF YOU WISE TO RECER COPIES OF REVISIONS
Plat a Site _ Drqc Report _ Olff
�x Ugly o, Reda Utility _ Iaads* OWN&i
City of Fort Collins
k«*
tit9(o
REVISION
COMMENT SHEET
DATE: January 26, 1999 TO: Engineering
PROJECT: #17-9OD Spring Creek Center P.U.D. — Final
(LDGS)
All comments must be received by Bob Blanchard no later than the staff
review meeting:
Wednesday, February 17, 1999
❑ No Comment
❑� Problems or Concerns (see below or attached)
MAJOR COMMENTS AND CONCERNS WITH THE UTILITY PLANS
o Update the General Notes.
o Reference the new vertical control. The City no longer uses the Black Bolt Survey.
o East Prospect Road is classified as an arterial street. You will need to dedicate an additional 7.5
feet along the frontage of the property per the City Code.
o You will need to dedicate a 15 foot utility easement along East Prospect Road.
T+mbertine-Road-folio ws-{he-section line -front -Of -this -Project— f-that-is-therase,-You-n,v"'-n�
additional-2G-6-feet-0f-RBW-dedication per-the-lty-C-ede.-
o The utility easement along Timberline Road needs to be a 15 foot utility easement per the street
standards.
o Midpoint Drive is classified as a collector street on the Master Street Plan. You will need to
dedicate an additional 3 feet of ROW along the frontage of the property per the City Code.
o Please add the maintenance guarantee and repair guarantee notes to the plat.
0 The Director of Engineering is now referred to the City Engineer. Please modify the plat to reflect
this change.
continue to page 2
Date:
v �
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
✓ Plat ✓ Site Drainage Report _ Other
✓ Utility ✓ Redline Utility ✓ Landscape �-
DATE: May 6, 1998 DEPT: Engineering
PROJECT: #17-90D Spring Creek Center P.U.D. - (LDGS) Final
PLANNER: Mike Ludwig
ENGINEER: Michael Dean
All comments must be received no later than the staff review meeting:
Wednesday, May 6, 1998
PLAT
Provide a legal description and a statement of ownership and maintenance.
Provide a copy of the Plat in the Utility Plans.
Provide cross access easements where needed.
UTILITY PLAN
Swale 12 is located within the Public R.O.W. and needs to be moved on to the Spring Creek
Center Site. The sidewalk should be located within the Public R.O.W..
The site has a poor circulation pattern that results in conflicting left hand turns which are a
safety concern.
Prepare cost estimate for future construction of the local street portion of Timberline Rd.
Improvements for escrow purposes.
** See redline plans for additional comments **
Date: MAY I:i 19�P Signature:^ AI
Please send copies of marked revisions
✓Plat ✓Site
Utility ,Landscape
�M
City of Fort Collins
REVISION
li!.'
COMMENT SHEET
DATE: January 21, 1998 DEPT: Engineering
PROJECT: #17-90D Spring Creek Center P.U.D. - (LDGS) Final
PLANNER: Mike Ludwig
ENGINEER: Michael Dean
All comments must be received no later than the staff review meeting:
Wednesday, February 11, 1998
PLAT
Title of Plat should read "A Plat of Spring Creek Center P.U.D. being a replat of Tract A,
Centerpoint Park.
Provide a legal description and a statement of ownership and maintenance.
Use the new Attorney's certificate language attached.
Provide a copy of the Plat in the Utility Plans.
Additional comments provided by the Mapping Division.
UTILITY PLAN
Swale 12 is located within the Public R.O.W. and needs to be moved on to the Spring Creek
Center Site. The sidewalk should be located within the Public R.O.W..
The T.I.S. does not appear to be accurate please revise and resubmit. The Business Park Land
Use classification is too vague without knowing the proposed tenants.
The site has a poor circulation pattern that results in conflicting left hand turns which are a
safety concern.
Prepare cost estimate for future construction of the local street portion of Timberline Rd.
Improvements for escrow purposes.
** See redline plans for additional comments **
Date:/ 1��8 Signature:
Please send copies of marked revisions _Zflat Site
Utility _�fandscape
City of Fort Collins
REVISION
COMMENT SHEET
DATE: Lary 21, 1998 TO: Mapping
PROJECT: #17-90D Spring Creek Center P.U.D.- (LDGS)
Final
All comments must be received by Mike Ludwig no later than the staff
review meeting;:
Wednesday, February 11,1998
IH7
—• rrow5 61P� c � Ii
rC P :,
�_ 1
LD+ � i �� P`> .) �IUIl )71 Ct i �C'F -
1. Ex�i-�
.J� % /lC OuTE2 /3o✓rvoAn� GCofes-j-y{c.'- CUg✓c`S (�a NeT
�1il r
MA-i TI-fc: TIZ� vfojs ID"q-r(C c-N'r rLR�- /�^'S ��� AtTH
L7
00.,J- _%/>rJ0 i?N-i
C Loic' _
Date:
Signature:
CM HERE EI YOU WISH TO RECEIVE COPIES OF REVISIONS
,[ Plat _ Sid; _ Drainage Report _ Mer
Utility _ Roche Utility _ Landscape
REVISION
COMMENT SHEET
DATE: it 10, 1997 DEPT: Engineering
PROJECT: Spring Creek Center P.U.D.
PLANNER: Mike Ludwig
FrIoUn0AeX ✓ie..0000i..J%(_
(.t5/S://GnJ �0MpP/•
Pr F �). 5�, ,P cam.,//j?lk
iN ze-csf /-rc sfJ•
2. loco- 7-
.-4- fr, s -
�,� -�e rs ee �•w �� � e
�wA-/
N ,N4er 4r,lu*l
/Qc & ct
s/.v c G 7 s
�fi([ /P e /.��7 Kt m6 e/ /A! L
�L/%2e o2.. lj ! %7D at die.
3, j.a�c �.v�e �cco✓a,�
ek L aQ:c�C �.au v- JJ P /4+ 4U f
ovcec/
1
Date: /7 _Signature:
d cross- Sec_Al • f 04
90.,. 7 C.-ce l
f-1"
PROJECT
COMMENT SHEET
City of Fort Collins
Current Planning
DATE: February 6, 1997 DEPT: Engineering
PROJECT: REVISIONS #17-90C Spring Creek Center -
Preliminary
PLANNER: Mike Ludwig
All comments must be received by:
• On the final plans please show what obstacles are in the way that are causing
the sidewalk to have to meander along Specht Point Road. Depending on the
nature of the obstruction to placing the sidewalk in its standard location, it may
be that the obstruction should be moved (i.e. relocating a fire hydrant) rather
than meander the walk in this one location.
• The preliminary proposed striping plan for Timberline Road was very useful. The
plan has been filed,the City Engineering Department's preliminary P.U.D. file for
future reference. W
Date: t,- Signature L 1ify -