HomeMy WebLinkAboutWILLOW LANE - Filed CS-COMMENT SHEETS - 2005-09-02City of Fort Collins
Current Planning
DATE: Dec.. 21 ,98
PROJECT
COMMENT SHEET
DEPT: ENGINEERING
PROJECT: xr 3 to -9 g M i ricl 4MLMA ntt'hj
Willow Lane Townhomes Minor Amendment December 21, 1998
Provide Legal descriptions, from a licensed surveyor, for the areas that are proposed to be
vacated for the garages. An 8 'h x 11 or 8 '/z x 14 size sketch of the proposed vacation is also
needed as an exhibit and for recording purposes.
Show on the plans the changes necessary to provide the proposed turn around/ hammerhead
needed for PEA. Does this effect the location of the proposed vacations? If so the utilities will
need to be routed again for verification that the new location(s) are not a problem. If this occurs
a sketch of the areas proposed for vacation with dimensions will need to be provided. Routing
and response will take approx 3 weeks.
If the areas proposed for vacation have not changed - I need the legals and sketch by December
30" in order to get the easement vacation on the January 21" Planing and Zoning Board agenda.
A filing fee for the easement vacation will be needed. This will be requested once the
information is received and the number of pages to be recorded is known.
Date: 1t/zi / Signature: Awe
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS:
Plat >( Site _ Drainage Report _ Other
P4'utility — Redline Utility p� Landscape
City of Fort Collins
Current Plannim
DATE:
PROJECT
COMMENT SHEET
DEPT: ENGINEERING
I
PROJECT:,Uc� ��Y��z �tiu rti�u,L
Willow Lane Town homes Buildings Ma and Na
Site Plan
September 8, 1998
Show the retaining wall proposed on the south side of the property.
The proposed garages are in parking access and utility easements - The easements will need to
be vacated where the garages are. Attached is an information sheet on the process. Provide a
plan showing the areas proposed for vacation (dimensioned from property line). If this plan is
larger than 8 '/2 by 14 provide 10 copies of it.
On a few of the buildings the building line touches a property/easement line. The building line
needs to reflect all eaves/overhangs on the buildings as no structures are allowed in easements.
Grading plan
• This sheet needs to be numbered I of 5 sheets
Increase the test size of the text indicating which buildings these are.
The southern parking space closest to Ross Drive has been eliminated, please show this.
Utility Plan
• Show the proposed retaining wall on this plan.
• The site layout is not quite the same as the site plan.
• Modify general note 47 to indicate the requirement for notification of the erosion control
inspector prior to the start of work also.
• Add the following to the general notes: The developer is responsible for all costs for the initial
instillation of traffic signing and striping for this development related to the development local
street operations. In addition the developer is responsible for all costs for traffic signing and
striping related to directing traffic access to and from the development (e.g. All signing and
striping for a right turn lane into the development site).
• Note #9 under the general notes that were added 8/ 11/94 is also new - bubble this also.
(Continued on next page)
Date: Signature: -
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS:
Plat '/' Site _ Drainage Report _ Other
-'�IIdility �-,<$edline Utility _ 7 dscape
Willow Lane Town homes Buildings Ma and Na (page 2 of 2) September 8, 1998
These Are Also Needed
• Provide a driveway cut detail
• Provide curb, gutter and sidewalk detail
• Provide additions to existing walk detail