HomeMy WebLinkAbout630 SOUTH MELDRUM STREET - Filed CS-COMMENT SHEETS - 2005-03-01Douglas Coates & Associates
P.O. Box 2653
Cheyenne, Wyoming 82003
August 13, 2002
City of Fort Collins
Community Planning and Environmental Services
281 N. College Ave.
Fort Collins, CO 80522-0580
RE: Response to Conceptual Review
Dear Sir or Madam:
Listed below is our response to the conceptual review comments for the Church of Jesus Christ
of hater Day Saints at 630 South Meldrum, Fort Collins Colorado.
Zoning:
1. Application for major amendment.
2. The site will be brought into compliance.
3. Amount of existing parking exceeds the required number of parking spaces for the
church/class use.
4. Site landscaping will comply.
Light and Power:
The Power Company will install a pad mounted transformer. (3 phase)
2. Utilities are shown on the plans.
3. 3 phase power is being brought to the building.
4. A service lateral and weatherhead shall be run overhead from the nearest single phase,
pole mounted transformer.
Poudre Fire Authority.
1. Building will be fire sprinkled.
2. Fire alarm system will be provided.
Water/Wastewater:
No changes.
Water meter is in an existing exterior meter pit.
Landscape irrigation will comply with standards.
Engineering:
Street oversize fee = 3,744 x $1.61 = $6,027.84
See Landscape Plan.
Since we have received the verbal `ok' to submit mylars for approval, please find attached 2 sets of
mylars for your signatures and three drainage reports for your records. Once the signatures are on the
mylars, please let us know when we can pick up a set of mylars for our records. If you have any
questions concerning these issues, please call us as soon as possible. Thank you for working with us
cc: Mr. Douglas Coates, Architect
file, 3583rspl.wpd
Douglas Coates & Associates
X0 P.O. Box 2653
AM Cheyenne, Wyoming 82003
December 6, 2002
City of Fort Collins
281 N. College Dr.
Fort Collins, CO 80522
RE: Fort Collins Institute
630 S. Meldrum
Fort Collins, CO
Dear Reviewers:
I am enclosing revised plans and comments for this project. Please note that the site plan and
utility plan are the same sheet.
Your comments have been incorporated into the plan unless noted herein or on the letter from
Park Engineering.
F, nkineerint;:
1. There will not be a temporary modular in the parking lot.
Storm Water:
1. The shrubs selected will not interfere with the water flow.
Please let me know if you need anything further.
Sincerely,
��
Doug aI s L. Coates, AIA
Enclosure: Park Engineering letter
UILDING PERMIT REVIEW
REVISION SHEET
City of Fort Collins
ENGINEERING
DATE: 12.16..02 TO: ENGINEERING
PROJECT: ]Fort Collins Institute (LDS Church) Building
Permit Review
PLANNER: Katie Moore
City comments must be received in Engineering Department by:
January 3, 2002
❑ No Problems
AProblems or Concerns (see below or attached)
Comments:
• l e apset�-
i
�leaSe- IV1CL �A& ci� Cktl 5� rC. ce 61oc_ -
t 6s.� — C.\OOd�f�
will vac be
r ,vV-0 Lp-
Date: signature:
Check here if you wish to receive copies of revisions:
❑ Plat ❑ Site ❑ Drainage Report ❑ Other
;E�tility 0 Redline Utility []Landscape
FM
PARK ENGINEERING
CONSULTANTS
January 22, 2003
City of Fort Collins
Design Review Team
Fort Collins, CO 80525
RE: Fort Collins Institute
Ladies & Gentlemen,
The following are: our responses to your comments regarding the aforementioned project dated
December 12, 2002.
ENGINEERING:
1. Acknowledged. The PE and Indemnification statements have been added to the plans.
Please see: the revised plans.
2. Acknowledged. The City's Signature Block has been added to the plans. Please see the
revised plans.
3. Acknowledged. The highlighted notes have been added to the plans. Please see the revised
plans.
4. Acknowledged. The Details have been enlarged to be legible. Please see the revised plans.
STORMWATF;R UTILITY:
1. Acknowledged. Please see the attached plans.
Please see attached 3 sets of mylars for your signatures (I for your records, 1 for our records, I for
the Architect). Once the signatures are on the mylars, please let us know when we can pick up the
additional sets for our records, and to make copies for Sealed plans. If you have any questions
concerning these issues, please call us as soon as possible. Thank you for working with us on this
David Mayeda
cc: Mr. Douglas Coates, Architect
file, 3583rsp2.wpd
420 21 st Ave. Suite 101 • Longmont, CO 80501 • (303) 651-6626 • FAX (303) 651-0331
E-mail don@,parkengineering.net
BUILDING PERMIT
REVIEW
City of Fort Collins COMMENT SHEET
Engineering
DATE: 1.22.03 DEPT: &�lvv-Ln
PROJECT: Fort Collins Institute Addition (LDS Church
Please return comments to: Katie Moore, Engineering Dept.
All comments must be received by: 1.29.03
❑ No Problems
)1Problems or Concerns (see below or attached)
Comments:
Date: Signature:
PLEASE SEND COPIES OF MARKED REVISIONS
❑ Plat 0 Site 0 Utility 11 Landscape 0 Drainage Report ❑ NO COMMENTS -SUBMIT MYLARS
2. Larimer County street over size fee = 3,744 x $.10 = $374.40
3. Any damage to curb, gutter, and sidewalk shall be replaced.
4. A traffic impact study will not be required.
5. Street and alleys are paved.
6. Utility plans will be submitted.
Storm Drainage:
l . New development fee = $.95/s.f. x 3744 square foot addition = $356.67
2.-5. Park Engineering has submitted the Drainage Study.
Transportation Planning:
1. ADA accessible parking is existing.
2. Bicycle parking rack is existing.
Natural Resources:
l . One significant tree will be removed. Trees will be planted at 1400 Lynwood to replace
this tree, as there is no room on site for more trees.
2. Adequate space is available.
3. Dust Control Permit will be filed.
4. Native plantings will be utilized where applicable.
Current Planning:
1. NCB zoning district standards will be followed.
2. Land Use Code standards will be followed.
Advanced Planning:
l . Landmark Preservation Commission will be contacted. The building was built in 1963
with the addition being built in 1965.
Please let me know if any of my replies are not acceptable. Please feel free to contact me at:
Phone: 307-635-4922
Fax: 307-433-8931
E-mail: dcu r�) dpa3hscoate__s comm
Sincerely,
Douglas L. Coates, AIA
CC: William Mikkelsen
file
JUN-14-2002 FRI 01:59 PM DENVER PROJECT MGT OFF FAX NO. 3037971610
P. 02/04
CONCEPTUAL REVIEW STAFF COMMENTS
MEETING DATE: May 6, 2002
ITEM: Church of Jesus Christ of Later Day Saints
APPLICANT: William C. Mikkelsen
3263 Fraser Street, Suite 1
Aurora, CO 80011
LAND USE DATA: A request to add a 3,000 sq.ft. building addition to the existing
church at 630 South Meldium. The property is within the City of Fort Collins and is
currently zoned NCB — Neighborhood Conservation Buffer District. The following
departmental agencies have offered comments for this proposal.
COMMENTS:
Zoning:
I. The use is permitted within the NCB Zoning District. The addition may be
reviewed as a major amendment.
2. Any addition greater than 25 percent of the existing building area will require the
site to be brought into compliance with the current development standards in
Articles 3 and 4 of the Land Use Code.
3. The number of off-street parking spaces will be subject to the uses proposed
within the project. Residential uses will have a minimum number of off-street
parking spaces, subject to the standards Section 3.2.2(K)(1) of the Land Use
Code. Non-residential uses will have a maximum number of off-street parking
spaces, subject to the requirements in Section 3.2.2(K)(2) of the Land Use Code.
All parking lots will be subject to the design standards in Section 3.2.2(C) of the
Land Use Code.
4. Site landscaping will be subject to the landscaping and tree protection standards
in Section 3.2.1 of the Land Use Code.
Light and Power-
1. If there is an increase in power load, the applicant will need to complete a
commercial service form. The applicant will need to pay for the difference in
power supply.
2. The applicant will need to show the location of utility boxes, meters and service
lines on the utility drawings and site plan.
3. Three phase power is located in the alley, will need a transformer location to
accommodate.
4. Power can be supplied to temporary buildings from the existing source.
COMMUNIFYPLANNING AND ENVIRONMENTAL SERVICES 7,81 N. College Ave. P.O. Box 580 Fort Collins, CO SM22-0580 (970)221-6750
CURRENT PLANNING I) PARTMLIVT
JCN-14-2002 FRI 02:00 PM DENVER PROJECT MGT OFF FAX NO, 3037971610 P. 04/04
Natural Resources:
I. Any existing trees that are proposed to be removed will need to be reviewed by
the City Forester (Tim Buchanan — (970) 221-6361). Significant trees that must
be removed will need to mitigated.
2. The City requests that the applicant provide adequate room within the trash
enclosure for recycling and use a single trash hauler to minimize trips.
3. A Fugitive Dust Control Permit will need to be filed with Larimer County.
4. The Natural Resources Department requests that the applicant pursues and uses
native plants and grasses as much as possible within the project.
Current Planning:
1. The property will be subject to the design and land use standards within the NCB
zoning district.
2. The project will be subject to the design standards in Section 3.5.3 of the Land
Use Code.
Advanced Planning:
1. The proposed development includes buildings which may be eligible for local
landmark designation. Any alteration, demolition, or addition to the structure
must first be reviewed by the Iandmark Preservation Commission.
3
JUN-14-2002 FRI 01:59 PM DENVER PROJECT MGT OFF FAX NO. 3037971610
P. 03/04
l'oudre Fire Authority:
I. Buildings with greater than 5,000 sq.ft. of floor area will need to be fire
sprinklered, or be compartmented into smaller units with firewalls.
2. A fire alarm may need to be provided.
Water/Wastewater:
I. The applicant is not proposing any changes to the existing service.
2. The water meter may need to be moved if it is within the building.
3. The water conservation standards for landscape and irrigation will apply.
Engineering:
1. Street Oversizing Fee for Fort Collins of $1.52/sq.ft. for the addition will apply.
The applicant may contact Maa Baker at (970) 224-6108 for an estimate of the
fees.
2. Larimer County Street oversizing fees will apply as well.
3. The applicant will need to replace or repair any damaged curb, gutter and
sidewalk along their portion of street frontage.
4. A Traffic Impact Study may need to be submitted for this project. The applicant
will need to contact Eric Bracke at (970) 224-6062 for a seeping meeting.
5. Adjacent street frontages and the alley will need to be improved or built to the
Larimer County Urban Area Street Standards.
6. Utility plans, development agreement and a development construction permit
will need to be prepared for this project.
Storm Drainage:
1. This site is in the Old Town drainage basin where the new development fees are
$4,150/acre which is subject to the runoff coefficient reduction. This is if there
is an increase in imperviousness greater than 350 square feet.
2. The site is in Stormwater Inventory map #7I. A copy can be obtained from the
Utilities office at 700 Wood Sheet.
3. The Old Town masterplan used a 60% imperviousness so as long as the site does
not exceed that, including'/2 the street and 1/2 the alley, onsite detention is not
required for water quantity. However, water quality extended detention is
required to treat the runoff.
4. Existing imperviousness is grandfathered so it can be counted to offset the new
building imperviousness.
5. The standard drainage and erosion control reports and construction plans are
required if there is an increase in imperviousness greater than 350 square feet
and they must be prepared by a professional engineer registered in Colorado.
Transportation Planning:
1. Handicap parking spaces will need to be provided and meet ADD accessibility
requirements.
2. Bicycle parking will need to be provided in a convenient location adjacent to the
residential units, unless garages are provided.
2
BUILDING PERMIT
REVIEW
City of Fort Collins COMMENT SHEET
Engineering
DATE: 8.20.02 DEPT: E-Y � r,
PROJECT: Fort Collins Institute Addition (LIDS Church)
Please return comments to: Katie Moore, Engineering Dept.
All comments must be received by 9.11.02
❑ No Problems
J9 Problems or Concerns (see below or attached)
Comments:
f � w�. G ��CG
pi -u, Gle yla_(Zt�_
�3vkovv r
�, Plea -Se- c���CY2v.-izc�� ¢.XSSZ�� i1�Y1'ls Vls.�prz=�obe� ;�rvS �oi �"^J
�'hzC� c��V✓Ik�,tiS�cti� pc A ":V..c� Stu�tS �5ic� v OIL c we%Y
Ail a �stv r �e� L �rs r� + I se- t".y, on
�� `` t), co
Date: I I /) , 02— Signature: 26t i
PLEASE SEND COPIES OF MARKED REVISIONS
0 Plat Site OlUtiliity gLandscape ❑ Drainage Report 0 NO COMMENTS -SUBMIT MYLARS
BUILDING PERMIT
REVIEW
City of Fort Collins COMMENT SHEET
Engineering
DATE: 8.20.02 DEPT: Xc- ELF A-fhr+
PROJECT: Fort Collins Institute Addition (LDS Church)
Please return comments to: Katie Moore, Engineering Dept.
All comments must be received by: 9.11.02
❑ No Problems
ErVioblems or Concerns (see below or attached)
Comments:
WILL. REFC� ADDRk1.i / To CCFECK .SIZE OF GAI SEQVIGE
AND SIZE OF &ftl PIETER TD HANOLE h110E0 WhO
u WIL1 NEED EXISTIN.I> d- FUT'VRE GftI L.OROI.
VPrrRIFUEjr OR
ARY RELOCATION OF EXI17-1r4G FACIIITIR-f WILL BE !-T
OWNERS E)CPENSE.
RECEIVED
Spp 1 1 ZQQ?
�"Rc;v7 ?BANNING
Date: X-G-O? Signature: P-,&�XJ_/../i
PLEASE SEND COPII:S OF MARKED REVISIC5NS
0 Plat 0 Site 0 Utility 0 Landscape ❑ Drainage Report 0 NO COMMENTS -SUBMIT MYLARS
City of Fort Collins
DATE: 8.20.02
BUILDING PERMIT
REVIEW
COMMENT SHEET
DEPT:
PROJECT: Fort Collins Institute Addition (LDS Church)
Please return comments to: Katie Moore, Engineering Dept.
All co ments must be received by: 9.11.02
1No Problems
❑ Problems or Concerns (see below or attached)
Comments:
RECEIVED
- JRRENT PLANK NG
Date: Signature: /1 S
PLEASE SEND COPIES OF MARKED REVISIONS
"Plat � Site 0 Utility RKandscape 0 Drainage Report 11 NO COMMENTS -SUBMIT MYLARS
E
November 20, 2002
City of Fort Collins
Design Review Team
Fort Collins, CO 80525
RE: Fort Collins Institute
Ladies & Gentlemen,
PARK ENGINEERING
CONSULTANTS
The following are our responses to your comments regarding the aforementioned project dated August
20, 2002.
ENGINEERING:
1. Acknowledged. Please see the updated Notes from the LCUASS. Please see the revised
plan.
2. Acknowledged. Line types and shading have been incorporated into the plan. Please see
the revised plan.
3. Acknowledged. Dimensions of existing improvements have been added to the plan. Please
see the revised plan.
4. Acknowledged. The Sidewalk Chase Detail has been revised. Please see the revised plan.
5. See Landscape Plan.
6. Acknowledged
WATER/WASTEWATER:
1. See Landscape Plan.
2. Acknowledged.
4"x4"x4" Tapping Saddle has been added to the plan. Please see the revised
plan.
3. Acknowledged.
The proposed fire line has been labeled and dimensioned. Please see the
revised plan.
4. Acknowledged.
Existing improvements have been labeled on the plan. Please see the revised
plan.
5. Acknowledged.
Thrust block detail has been added to the plan. Please see the revised plan.
6. Acknowledged.
The general note has been added to the plan. Please see the revised plan.
7. The proposed 4"
fire line does not have to be increased for flows.
8. Acknowledged.
STORMWATER UTILITY:
1. Acknowledged. The drainage report has been submitted and reviewed with staff. The
attache report is the outcome of said discussions and revisions. Please see the attached plan
and report.
2. Acknowledged. Please see the attached legal description for the Drainage Easement for
recordation.