HomeMy WebLinkAboutGREENBRIAR VILLAGE PUD THIRD - Filed GC-GENERAL CORRESPONDENCE - 2004-08-06Commi., v Planning and Environment L ervices
—� Planning Department
City of Fort Collins
June 24, 1994
Ed Zdenek
ZTI Group/Architects
1220 South College Avenue
Fort Collins, CO. 80524
Dear Ed,
The intent of this letter is to update you on the City's position
concerning the status of the Greenbriar Village P.U.D., Third
Filing - Final. that was originally submitted on March 31, 1994 for
review as a combined Preliminary/Final. The item was scheduled to
go to the Planning and Zoning Board on May 23, 1994 for a decision.
City staff felt that there were outstanding storm drainage and
natural areas issues significant enough to delay approval of the
Final P.U.D. and, therefore, the item was approved by the Board on
May 23rd as a Preliminary only. No new information addressing these
issues has been provided since the Preliminary approval.
I was informed by Glen Schlueter of the Stormwater Utility on
Wednesday, June 22, 1994, that Joe Marcisofsky of Structured
Engineering, the engineer of record on the project, has withdrawn
his drainage report and plans from the review process. Based on
this event, the project is now incomplete and cannot automatically
proceed in the City's development review process. You must submit
a complete drainage report and plans on any of the upcoming
submittal dates (please see the attached Revised 1994 Development
Review Schedule), which would initiate the review process and place
you on schedule to be on the agenda for the Planning and Zoning
Board public hearing date that corresponds to the date of
submittal.
I can be reached at 221-6750 if you have any questions.
S' cereely,
Steve Olt -
Project Planner
cc: Bob Blanchard, Chief Planner
Kerrie Ashbeck
Stormwater Utility
Natural Resources
file/Project Planner
"?1 %A)r0l "ollr4c -1:r nun n 0- oo;�, ��(1 �„ ` • rc�rt o ins. �. Li_�_ -ol ((3) -21-1,.r0
Commu y Planning and Environmental
Office of the Director
City of Fort Collins
To:
Ed Zdenek, I
From:
Greg Byrne
Subject:
Greenbriar 3 d Fil
Date:
June 5, 199
.vices
Ed, 1 have reviewed the issues surrounding the common property line between your project and
the Stormwater Utility. At your request, my goal has been to arrive at the minimum necessary
actions you must take in order to proceed with development of lots 14 through 18, and lots 21
through 24 At your option, you may (1) revise the Greenbriar 3rd Filing utility plans, or (2)
submit a new plan detail, to reflect current conditions and the following requirements:
An easement should be shown on the Northeast corner of Lot 14 Greenbriar 3rd filing.
This easement should be dedicated to the public for drainage coming across Willox Lane.
Riprap shall be placed along that easement on Lot 14 to protect that lot from potential
erosion problems.
2 Grade the detention pond shoreline to the north of the rear property line of lots 14
through 18 and 21 through 24 of Greenbriar 3rd tiling . The grading shall be done at a
maximum 4 to 1 side slope. The shoreline shall be graded down from an elevation of
4966.0 at the north lot line of Greenbriar 3rd Filing lots down to an elevation of 4961
within the Greenbriar Pond.
3. The graded pond shoreline shall be seeded with a native seed mix. Construction activities
associated with the Greenbriar 3rd Filing development shall be done in a manner that
would preserve existing vegetation except as shown on the approved Greenbriar 3rd filing
plans or any amendment to these plans. No riprap is required.
The plan must reflect existing improvements to the Greenbriar detention pond outfall_
Limits of grading disturbance associated with Greenbriar 3rd Filing construction activities
shall be delineated in these revisions-
281 N. College Avenue • P.O. Box 580 • Fort Collins, CO 80522-0580
(970) 221-6601 • FAX (970) 224-6171 • TDD (970) 224-6002
Ed Zdenek
Page 2
June 5, 1997
The City is to complete the re -design and the construction of the Greenbriar pond outfall pipe
along Redwood street. The City reserves the right to seek reimbursement for the over -sizing of
that pipe from a 15 inch size pipe to a 24 inch size pipe from a point along Redwood Street to
Conifer Street.
I understand that Mike Herzig has approved the legal description for the easement referenced in
item 91, above, but has not yet received the dedication.
Finally, a revised development agreement must be executed to reflect these solutions, and to
eliminate the prior references to the pond and natural area. Mike Herzig is currently preparing the
new document.
I have instructed the involved staff to treat any information requests or submittals from you with
immediate attention, and to assist you in reaching final approval and release as soon as possible.
I will be out of town from June I 1 through July 1. Bob Blanchard will be acting on my behalf
during my absence, and I have briefed him on these issues.
cc: John Fischbach
Bob Blanchard
Bob Smith
Mike Herzig
Basil Hamdan
SI
No Text
City Attori j
City of Fort Collins
August 19, 1997
Rick Zier, Esq.
318 Canyon Avenue
Suite 201
Ft. Collins, CO 80521
Re: Greenbriar Village PUD Third Filing Amendment Agreement No. 2
Dear Rick:
Enclosed is the City's proposed Amendment Agreement No. 2 regarding Greenbriar Village
PUD Third Filing. A couple of days ago you called to advise that your client was unwilling to
execute the enclosed agreement unless the last paragraph was amended to contain a sentence
which would indicate that nothing in the amendment would constitute a waiver of either parties
right to seek damages from the other for breach of the development agreement. I have discussed
this matter with members of the City's staff and I am prepared to agree to your request with the
suggestion of a further change to ensure that it is clear that the sentence whereby the parties agree
not to waive any rights also is not read to imply an admission by either party of wrong doing or
to constitute a waiver of the right of either party to raise any defenses against any such damage
actions. Accordingly, I would recommend that the language to be added to the closing paragraph
be amended to read as follows:
Nothing in this Amendment Agreement No. 2 shall be construed to waive,
remove, limit, or abridge in any manner or to any extent either party's right to
seek damages from the other for breach of the Development Agreement between
them dated May 28, 1996, which occurred prior to the date hereof, or to defend
against any such actions for damages, and by execution hereof, neither party
admits to any breach of the development agreement.
I am persuaded, following discussions with numerous members of the City staff, that the City is
fully capable of defending against any actions for damages that may be brought by your client.
From the facts that I have ascertained, I do not believe that the City is going to serve well as a
deep -pocket from which a wellspring of money will flow to your client in their efforts to "seek
damages" and I would suggest that litigation will not be a profitable enterprise for them.
As an alternative to the sentence that you are proposing, and which obviously contemplates
litigation, the City is prepared to purchase some of the items that were listed on Exhibit C of the
Development Agreement at the costs listed thereon from your clients. The City is prepared to
300 LaPorte Avenue • P.O. Box 580 • Fort Collins, CO 80522-0580 • (970) 221-6520 • FAX (970) 221-6327
Rick Zier, Esq.
August 19, 1997
Page 2
purchase the items listed on Exhibit "C" of the Development Agreement at the listed cost under
entry A -Ecology of Pond, B-Lidstone/Anderson work, C(1)-Survey, C(4)-Design, and D-
Landscape Architect. The total payment that the City would make for these items is $11,462.00.
The terms upon which the City would be willing to purchase the above -mentioned items are that
all original work under those items be delivered to the City in good condition and your clients
waive and relinquish any right to "seek damages" for breach of the Development Agreement.
Essentially, the sentence that you are proposing to insert into the Amendment Agreement would
be reversed so that it would in fact constitute a waiver. In addition, if such an agreement can be
reached, I have been advised by the stormwater utility that your clients could also remove the fill
dirt that is presently inundated in the pond as that fill dirt is identified according the plan that we
prepared by JR Engineering Ltd. The excavation limits would have to be negotiated with the
City since shore protection has been eliminated from the construction plans.
Please advise as to how your clients which to proceed.
Sincerely,
I/
W. Paul Eckman
Deputy City Attorney
WPE/pec
attachment
Transport )n Services
Engineering Department
City of Fort Collins
City of Fort Collins
Memorandum
DATE: August 30, 1997
TO: All interested Parties
FROM: Rick Richter, Pavement Management Engineer. kF_
RE: Greenbriar Village P.U.D, 3rd Filing
The purpose of this memo is to outline the City's Engineering Department's requirements for the
release of a Certificate of Occupancy for Lot 16 Greenbriar Village P.U.D, 3rd Filing,( address
638 Bayberry Circle). The pavement on Bayberry Circle will need to be replaced to the City's
standards from Willox Lane to the west line of Cranberry Court. Bayberry Circle will then need to
be barricaded with Type III barricades on the west line of Cranberry Court. All City required
signage (traffic and street name) will need to be placed according to the City's Standards. The
broken concrete curb and sidewalk will need to be replaced according to the City's Standards, or
an escrow account will need to be established for the concrete repairs. Not withstanding the
conditions as stated in the Development Agreement dated May 29, 1996 and Amendment No I
dated March 24, 1997.
In order to release a Certificate of Occupancy for lot 7 (house under construction) the pavement
on Bayberry Circle will need to be replaced to the City's standards from the west line Cranberry
Court to the west lot line of lot 7. And the pavement on Cranberry Court will need to be replaced
to the City's standards.
Please be aware that prior to the City Engineering Department release of any future building
permits for Greenbriar Village P.U.D, 3rd Filing the streets need to be constructed with at least
the base course completed, to the City's standard. The conditions as stated in the Development
Agreement dated May 28, 1996 and Amendment No 1 dated March 24, 1997 will still apply.
Revised as per meeting Friday Arigust 29, 1997:
The Certificate of Occupancy for Lot 16 Greenbriar Village P.U_D, 3rd Filing,( address 638
�tiI \nrth G.lIlr11c V'cnuc • PO. Box -,80 • Port Collins, CO W;22-0580 • (970) 221-(*0
Bayberry Circle) was released with the following conditions
1.) The paving of Bayberry Circle as outlined in this Memo will need to be completed within 45
days of issuance of the Certificate of Occupancy.
2.) Type III barricades with the "Road Closed" and "Construction Traffic Only" will be erected at
both ends of Bayberry Circle by Saturday August 30, 1997 at the cost of the developer.
3.) The Escrow for this development will be reexamined and increased if necessary.
All other requirements outlined in this Memo are valid and will be enforced.
The conditions outlined in the revision of this Memo relate only to the issuance of the Certificate
of Occupancy for Lot 16 Greenbriar Village P.U.D, 3rd Filing. Any future Certificate of
Occupancies for this P.U.D. will not be issued until all requirements are satisfied.
Community Planning and Environmental Services
Natural Resources Department
City of Fort Collins
December 21, 1995
Mr. Edward G. Zdenek
ZTI Group, Development
1220 S. College Ave.
Fort Collins, CO 80524
RE: Release of lots on Greenbriar P.U.D., Third Filing
Dear Ed:
Wednesday morning (12/20/95) Glen Schlueter of the City Stormwater Utility, Mike
Herzig of Engineering, and I met on the Greenbriar site to evaluate what additional information
and/or actions were needed before the City can release the the development and building lots
(which border City property to the north) for construction. It was observed that the plans appear
inconsistent with the existing site conditions, particularly with regards to the planned transition to
the City -owned property to the north. It also appears that the site and utility plans do not clearly
show all wetland and open water areas which will be affected by the proposed project's design
and construction.
As you are aware, a hold exists on the development proceeding until until the developer
provides additional information sufficient to determine how the grading would transition between
the back lot lines and the wetland/wildlife habitat mitigation area which was being planned on the
City property to the north. The developer has wetland mitigation responsibilities for wetlands
which have been (or will be) disturbed by the construction of some of the Greenbriar lots. This
responsibility is tied to a note which was placed on the Greenbriar P.U.D. 3rd Filing Final Site
plan as approved by the Planning and Zoning Board on September 26, 1994. This note states the
following:
Due to the development of lots 14, 15, and 16 a loss of approximately 0.7
acres will result. Of the 0.7 acres, wetlands constitute only a small portion, so
the majority of the area lost would be an open water body. ZTI would
mitigate the area lost by constructing a pond greater than open waters that
would be lost, an island within the pond for wildlife habitat, and a like kind
mitigation area on the west side of the pond would be greater than 1:1
mitigation for the fringing wetlands that now occur on the east side of the
open body of water.
This note ties the mitigation of the wetlands and pond disturbance area to the natural area
"'I V''. C ollo,gr Am. • P0. Buy )SO • Fort Collins, ( 0 SO�22-0580 • (970) 221-6600 • PA\ (970) 221-6378
plan being developed for the property to the north, at a ratio of one to one, like -kind replacement.
Natural Resource staff has communicated and met with the developer over the last several years
regarding the creation of a joint storm water detention and natural area plan which would
encompass the needed mitigation as well as provide some value to the developer, the
neighborhood, and the community at large. It is our understanding that the developer now wishes
to withdraw from the larger scope of planning for this natural area because the funds the
developer intended to use to complete the project have been found to be unavailable. In addition,
the developer would like to have the above mentioned lots approved and released for
construction, without being linked to the development of the natural area.
City staff is willing to accomodate the developer's requests, as long as the developer has
met his responsibilities in providing a transition (acceptable to the City) between the lots and the
City owned property, and that the mitigation of wetland and pond disturbances resulting from
Greenbriar P.U.D., Third Filing is complete. As was intended by the hold which was initially
placed on these lots, the developer and City staff must now pay close attention to the transition
area at the lot -to -natural area/stormwater facility transition and interface. We are requesting that
the developer resurvey and map the topographic, pond, and wetland features of the City owned
property for an area defined by an east to west line located 100 feet to the north of the
northernmost point of the northern property line common to lots 22 and 23 for this development.
Once this area has been surveyed and mapped on a site plan, showing the relationship with the
adjacent lots, the developer will need to arrange to meet with Mike Herzig, Glen Schlueter, Rob
Wilkinson and others as appropriate. At that meeting, staff and the developer will generate a
conceptual plan for the transition area defined by the 100 foot line. The developer will then need
to revise the utility plans, site plan, landscape plan, and other planning documents as needed,
processing an administrative change to the site plan if such is required. Following these actions,
the developer will be responsible for construction of the transition area in accordance with the the
mutually generated plans. It is staff understanding that pond and wetland mitigation shall be
reflected on the above plans.
In addition, the developer needs to be ready to discuss water right related questions with
regard to the City owned area to the north. Construction materials were borrowed from the site,
and at the direction of the developer (after concept discussions with City staff, but without formal
approvals), the borrow pit was deepened to accomodate a pond. In excavating to this depth, the
groundwater surface was exposed, resulting in a possible liability to the City with regard to
Colorado water law, and a requirement to augment for evaporative loss associated with
groundwater exposed by excavation. Since the developer has stated in the past that water rights
are available for the pond, he must provide sufficient rights to cover the constructed pond, or the
material removed must be replaced to a degree necessary to eliminate the exposed groundwater
surface.
As a part of this process, City staff will arrange a site visit by the Army Corps of
Engineers (to be attended by both staff and the developer) to determine the range of site
modifications which will be allowable by Section 404 of the Clean Water Act. The date of this
meeting will be dependent on the availability of the Corps of Engineers representative, but it
would be desirable that this meeting be held prior to the meeting at which conceptual plans for the
transition area are developed.
In the mean time if the developer wishes to proceed with of the development prior to
completing these items, the development agreement can be completed with the condition that a
hold will exist on the: development of the lots bordering the pond, and that construction activities
shall not be allowed on these lots until all plans are revised and approved by the City. In addition,
no building permits will be issued by the City until the grading of the lots and the transition area is
completed and certified as to its proper construction. Please let Mike Herzig (Ph. 221-6750)
know if you wish to proceed in this way, and he will complete the drafting of the development
agreement.
Sincerely,
Rob Wilkinson
Senior Environmental Planner
CC:
John Fischbach
Greg Byrne
Gary Diede
Ron Phillips
Bob Smith
Bob Blanchard
Basil Hamdan
Mike Herzig
Ed Lawler
Steve Olt
Glen Schlueter
Tom Shoemaker
JRE eering, Ltd.
4R 12 South College Avenue
Fort Collins, Colorado 80525
(970) 282-4335 • FAX (970) 282-4340
November 8, 1996
Mr. Ward Stanford
Development Review
City of Fort Collins
281 North College Avenue
Fort Collins, CO 80522
Re: Greenbriar Wetland Pond - P,'oposed De -watering Plan
Dear Ward:
4935 North 30th Street
Colorado Springs, Colorado 80919
(719) 593-2593 • FAX (719) 528-6613
6110 Greenwood Plaza Blvd.
Englewood, Colorado 80111
(303) 740-9393 • FAX (303) 721-9019
Please find attached a drawing depicting the proposed de -watering plan for the Greenbriar Wetland
Pond. Our client. Ed Zdenek, has requested that we provide you with this drawing and a summary
of the field operation used to de -water the pond, which will be as follows:
I) Water will be pumped from the pond into the existing 15" outfall pipe.
�) The water will flow to the south along the east side of Redwood Street to an existing
manhole, and then to the west across Redwood Street in the existing 15" pipe.
;) A small temporary holding pond will be excavated at the existing exit to this pipe.fhis pond
is onl} to provide a %olume of water in order for the second pump to operate.
dl A second pump will pump water from the temporary pond across a vacant field to the west.
which is a possible future tiling of Greenbriar Village, to the outfall channel of the Evergreen
West Pond- Ibis pumping will all be done by hose. there will be no open channel.
Please reyicw this plan. as soon as possible. and respond to myself or Ed /denck. If we can be of
further assistance. please do not hesitate to call.
thank )'Oil_
Sincerely.
JR Fngineering, Ltd.
I "Celt �1 ate nnan
I'n�je�t Inuanccr
GREENBRIAR WETLAND POND
PROPOSED DEWATERING PLAN
N
300 150 0 300 600 w
r-- --- —
U SCAI F. 1 = 300' wo
Io
13
0
w
GREENBRIAR
SECOND FILING
I
EXiS-INC—�
ourFA_
PAP_ �.
7
I �
vZ
PUMP \
GREENBRIAR
WETLAND PON&\\
IQz
w J
z w
GREENBRIAR
I w o
FUTURE FILING
I oz
Q
PUMP
> N
i w
rFMP",RARE
SMAL_
PON
NAKOMIS
SUBDIVISION
GREENBRIAR
THIRD FILING
CONIFER STREET
REDw00D
C,ti,�
JREngineering, Ltd.
4812 South College Avenue
Fort Collins, Colorado 80525
(970) 282.-4335 • FAX (970) 2824340
January 14, 1997
Mr. Glen Schlueter
City of Fort Collins
Stormwater Utility
235 Mathews Street
Fort Collins, Colorado 80524
RE: Greenbriar Wetland Pond - Review Comments
Fort Collins, Colorado
Dear Glen:
4935 North 30th Street
Colorado Springs, Colorado 80919
(719) 593-2593 • FAX (719) 528-6613
6110 Greenwood Plaza Blvd.
Englewood, Colorado 80111
(303) 740-9393 • FAX (303) 721-9019
JR Engineering, Ltd. is pleased to submit the revised plans for the Greenbriar Village P.U.D., Third
Filing, Wetland Pond for your review and approval. The revised plans and this letter address
Stormwater's review comments of January 3, 1997. The hydraulic and hydrologic evaluation of the
site were performed in accordance with the specifications set forth in the City of Fort Collins'
"Storm Drainage Design and Criteria Manual".
Note: The Stormwater comments are shown in regular text. A Engineering, Ltd.'s discussion for
each item is shown in italics.
1. The submittal needs to be accompanied with a letter describing the submitted plan and
calculations. The letter must be signed and stamped, along with a statement of compliance
with City criteria.
This letter is intended to describe the submitted plans. It also provides the statement of
compliance with City criteria.
The requested calculations are attached.
2. The pipe outlet at the southeast corner of the pond is shown to discharge directly into the side
of the swale and then turn ninety degrees. Superelevation should be considered at this
location because of the sudden change in direction. Rip -rap protection is needed at the
outlet. It is recommended that the pipe and headwall be angled downstream to prevent any
potential erosion and superelevation problems.
The grading plan has been revised to allow flows from this pipe to be conveyed in a swale
across the northeast corner of Lot 14 of Greenbriar Village P. U. D., Third Filing. A
drainage easement shall be granted across said Lot 14, as shown on the plans, to be
recorded by separate document. Design calculations for the Swale and for rip -rap
�0
Recycled
Mr. Glen Schlueter
January 14, 1997
Page 2
protection at the outlet of the pipe are attached to this letter.
Design calculations have also been provided for all other pipes outletting to this pond, and
rip -rap protection has been shown on the plans.
3. Please provide documentation from the Master Plan of the needed detention volume. Please
verify that the rating curve assumed in the Master Plan is consistent with the proposed pond
grading.
The needed detention volume for the pond is 7.2 acre-feet, as shown in the report entitled
"Final Report, Greenbriar-Evergreen Basin, Master Drainage Study ", prepared by Lidstone
& Anderson. Inc., dated May 1, 1996. The proposed pond grading shown on the revised
plans provides a detention volume of 7.26 acre-feet (see attached calculations).
The proposed grading and the 15 inch RCP outlet pipe are consistent with the outlet shown
in the above reference drainage study and, therefore, the rating curve should be consistent.
The required detention volume will begin accumulating at elevation 4962.50, the invert
elevation of the aforementioned 15 inch RCP outfall pipe. At the 100-year water surface
elevation of 4964.00, the proposed detention storage will be 7.26 acre-feet and the proposed
discharge in the outlet pipe will be approximately 4.7 cfs.
4. Please provide a cross-section of the swale east of Redwood. The cross-section must show
the 100-year depth and freeboard. Provide a sidewalk culvert at the crossing..
A cross-section of this swale has been provide on the revised plans and design calculations
are attached with this letter.
The sidewalk culvert has been shown on the revised plans to be constructed when the City
of Fort Collins' constructs the future sidewalk.
Please show the limits of the drainage easement dedicated for the pond. The inlet swales
should also be within the drainage easement.
In a telephone conversation with Matt Fater of Stormwater on January 14, 1997, it was
confirmed that a drainage easement will not be required for this pond as it lies within City
property.
in addition to these comments, all redline comments shown on Stormwater's review set have been
addressed on the revised plans.
Mr. Glen Schlueter
January 14, 1997
Page 3
If you have any questions regarding the procedures, methodology, or results presented herein, please
do not hesitate to contact us at your convenience.
Sincerely,
JR Engineering, Ltd.
F. Scott Waterman, E.I.
Project Engineer
Davi lockeman, F'
Project Manager
Attachments