This letter is to inform you that the work on the Cottonwood Glen Neighborhood Park
needs to stop as of 5:00 p.m., Friday August 20, 1999. The only work allowed is to
continue dewatering the irrigation pond, maintain the erosion control fences, and other
things Bob needs to do at the site to maintain a readiness. No construction equipment is
to be active on the site.
The City's best intentions are to allow work to resume Thursday, August 26, 1999.
This work stoppage is not due to any fault of Environmental Concerns. The City is
completing our review process and feels it is in our best interest to stop the project until
our reviews are completed.
I will keep you informed daily of our progress on this matter.
Sincerely;
Craig L. Foreman.
Manager Park Planning and Development
cc Jim Hume
=Sl \ou,h Coile�,e Avenue • Frrt Collins, CO ��0�=� • (9i0) Z^_1-6360 •Fax (970) ^�1-6586
Cultural ',ibrary and Recreational Service
Park Planning & Development Division
City of Fort Collins
DATE: May 3, 1999
TO: Distribution List
FROM: Craig Foreman, Park Planning and Development Manager
RE: Cottonwood Glen Neighborhood Park
Cottonwood Glen Park is an 11-acre neighborhood park planned to be construction at the
south end of Overland Trail Road. The park is a day -use park with no lighted fields. The
Spring Creek Trail will be extended into the park as part of this project. A connection to
Olander School from the park will also be constructed as part of this project.
Park Planner in charge of the park is Craig L. Foreman who can be reached at 96618.
The public process involved two neighborhood meetings. Each meeting had a mailing
area that was bounded by Drake Road on the north, Taft Hill Road on the east, and
Horsetooth Road on the south.
The park is zoned "POL" on the City of Fort Collins Zoning Map (from GIS) dated June
12, 1998 and has a Level I review process.
The park vas designed with a landscape plan prepared by professional landscape
architects. The tree planting plan has been preliminarily reviewed by the City Forester.
Existing trees will be protected during construction per City Forester's specification. The
park road south from the end of Overland Trail Road is not a City street. The parking lot
interior landscaping is calculated to be about 10%. The park site will be planted with
fescue and native (-trasses to conserve water.
The park has been designed to allow for pedestrian and bicycle access. The existing
sidewalk at the end of Overland Trail Road will be extended into the park. This sidewalk
will connect to park facilities, the Spring Creek Trail, and the path to Olander School.
Bicycle racks will be provided at the park. Park facilities (parking lot, ballfield, multi -use
court, restroom, and shelter) are all handicap accessible. The paved parking lot will
accommodate normal park activities on a daily basis. Two handicap -parking stalls are
included in the 27-car asphalt parking lot. Additional parking along the park road south
from Overland Trail Road will accommodate parking needs in the spring when the
baseball and soccer fields are both in use. The park is not lighted except for pedestrian
and security lights.
281 North College avenue • Fort Coilins, CO 80324 • (070) 221-o360 • Fax (970) 221-6586
A fire hydrant is planned to be located near the new asphalt parking lot to provide
coverage for the park structures. A stormwater report has been prepared for the park
development.
The park design incorporates the required buffer along Spring Creek and is adjacent to
Pineridge Natural Area. The design is acceptable to the Natural Resource Staff and
Natural Resource Advisory Board.
A professional architect designed the park buildings. The structures were designed to be
compatible with. the natural features around and in the park. Structure designs meet
current City Building Codes.