HomeMy WebLinkAboutCITY OF FORT COLLINS UTILITY SERVICE CENTER DECEMBER 2002 - Filed CS-COMMENT SHEETS - 2003-07-07Current Planning im
DATE: May 30, 2002 TO: Engineering
PROJECT: #16-90D City of Fort Collins Utility Service Center —
Amended ODP Minor Amendment
A11 comments must be received by Ted Shepard no later than the staff
review meeting:
June 19, 2002
Note -Please identify your redlines for future reference
Nance (please print)
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
_Plat _Site _Drainage Report _Other
_Utility _Redline Utility _Landscape
6a
City of Fort Collins
Project Comments Sheet
Selected Departments
City of Mort Collins
Department: Engineering
Date: June 28, 2002
Project:
CITY OF FORT COLLINS UTILITY SERVICE CENTER PDPlREPLAT
All comments must be received by TED SHEPARD in Current Planning no later than
the staff review meeting:
June 26, 2002
Note - Please identify your redlines for future reference
Issue Contact: Dave Stringer
Topic: General
10
Need to add signature block for ELCO
11
Is signature block required for Griffin Drain ownership?
12
Add note to demo plan about remove and replace any damaged curb and gutter on
Elm Street in area to be constructed
13
Call out curb and gutter type, Elm Street and parking lot
14
Show location of Griffin Drain on x-section sheet CS302
15
Will existing Fire hydrant on Elm need to be relocated? The valve may be in Gutter
or curb head
16
Appears off -site easements are require for pond, retaining wall and trail
Signature
Date
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
Plat Site Drainage Report Other
Utility Redline Utility Landscape
Page 1
17
How will existing alley terminate at the North end?
18
Provide elevations of existing gutter at Loomis and Elm for tie in points
Page 2
Project Comments Sheet
(imfi6g�!0J, Selected Departments
City of Fort Collins "'
2s
Department: Engineering
Date: October 9, 2002
Project:
CITY OF FORT COLLINS UTILITY SERVICE CENTER PDP/REPLAT &
FINAL COMPLIANCE
All comments must be received by TED SHEPARD in Current Planning no later than
the staff review meeting:
October 09, 2002
Note - Please identify your redlines for future reference
Issue Contact: Dave Stringer
Topic: Plat
60
NW corner/NE1/4/NW1/4 is not described,
61
NW corner not discribed,
62
This product will be hard to scan due to text format refer to appendix E-6 in recently
approved LUCASS for guidance
Topic: Utility plans
59
Engineering ready, for Mylars, Still need approval from other departments.
Easements need to go to Council for approval
Signature Date
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
Plat _ Site Drainage Report Other
Utility _ Redline Utility Landscape
Page 1