HomeMy WebLinkAboutCLARENDON HILLS THIRD - Filed GC-GENERAL CORRESPONDENCE - 2003-07-07ELOPMENT
Ms. Linda Ripley January 4, 1989
Project Planner
Planning Department
City of Fort Collins
3"00 Laporte Avenue
Fort Collins, Colorado 80522
Re: Clarendon Hills Third Filing
Final Subdivision
Dear Linda,
lie are pleased to provide two sets of revised Utility Plans
and three copies of the revised Final Drainage Study for the
referenced project as requested.
We are in the process of finalizing agreements with adjacent
property owners that are affected by improvements in this third
filing of Clarendon Hills.
Until I talked with Mike Hertzig this morning, we were going
to request a variance to the Street Standard for two curves on
Rochelle Circle. I agreed with Mike to look closer at these two
"L" intersections and comply with the City Standard unless there
are significant problems in doing so. I will be meeting with
Mike to resolve this, and to discuss the Subdivision Agreement,
later this week.
We would like, however, to request a variance to the City of
Fort Collins Storm Drainage Design Criteria, City of Fort
Collins, May, 1984, for the following situation:
During a 100 year storm, the storm water runoff on the south
side of cul—de—sac "c" ponds to a depth of 2.4 feet at Catch
Basin #1, which is in excess of the 1.5 feet of depth allowed by
City Standard. The Standard is given in Table 4-4, Page 4-6 of
the referenced design criteria.
The standard is not met because during the very large storm
runoff, storm water runoff is being released both in an
underground pipe culvert and in a overland surface channel to
drain the storm water from this location to a detention pond
located downstream. By building the standard catch basin and
drive over curb, gutter and sidewalk at this location, the
L10ert, or low point, of the Swale is 0.7 feet above the gutter.
Land Development Services 117 East Mountain Avenue • Suite 201 Fort Collins, Colorado 80524 3031493-4624
deflection immediately after installation, backfill, and
ecmpaction shall not exceed 5% of the base inside pipe diameter
as recommended by the Uni-Bell Plastic Pipe Association. These
Deflection Inspection Tests shall be verified by the Public
Improvement Inspector. Deflection exceeding 5% shall be
corrected prior to initial acceptance. The maximum allowable
final deflection prior to the expiration of the guarantee period
shall not exceed 5%. The City of Aurora at its option can
require deflection tests by the Contractor on any section of
pipe during the warranty period.
An;y pipe damaged during installation or exceeding 5% deflection
shall be removed, replaced or repaired at the Contractor's cost
and in a timely manner. The method of repair will be at the
sole discretion of the Project Engineer.
-3-
Mr. Mike Hertzig April 28, 1989
Development Coordinator
Planning Department
City of Fort Collins
300 Laporte Avenue
Fort Collins, CO. 80522
RE: Clarendon Hills Third Filing
Irrigation System in Northwest Corner
Dear Mike,
As requested by Lance Newlin of Engineering Services, this
letter is written to certify that the fifteen (15) inch diameter
pipe culvert designed to pass irrigation water in the referenced
location of the referenced project is designed to operate under a
"gravity" type of system. As such, the system is not anticipated
to be under pressure during irrigation water flow — or at any
other time.
Also, regarding the ditch company approval requested by
Lance in a conversation with Dick Schmidt of Schmidt Earth
Builders, their is no ditch company ownership of the irrigation
ditch lateral mentioned above. Instead, as discussed among Gary
Nordick, Susan Hayes, Paul Eckmann, you and I prior to final
approval by the Planning and Zoning Commission, the ditch is a
lateral on Clarendon Hill Associates' property.
As owners of the property and ditch, no ditch company action
is required relative to the improvements. If there are questions
or comments, please let me know. Thank you!
Sincerely,
Dennis L. Donovan, P.E.
Land Development Services
4924 S. Shields
Fort Collins, Colorado 80526
cc Lance Newlin k1-
Engineering Services
City of Fort Collins
DATE: May 11, 1989
TO: Gary Diede, Director of Engineering
FROM: Rick Richter, Civil Engineer I /?C P,
RE: ADS Stormwater Pipe
Following is a list of questions I would have addressed by ADS Inc.:
1. Our construction standards now allow only concrete storm sewer pipe
under streets. The concrete pipe specification requires a rubber or
plastic gasket. Will ADS Inc. do some exfiltration testing to show a
comparison between the ADS N-12 and properly installed concrete pipe?
2. Our construction standards now require all storm water conduits to have
sufficient structural strength to withstand the AASHTO HS-20-44
loading. Will ADS N-12 meet this standard?
3. In our meeting with ADS Inc. Jim Heintz said he had some test data on
the shrinkage of their pipe under a deep fill section. Is there any
data on the shrinkage of the pipe under more shallow fills and how the
shrinkage increases with the fill? My concern is the void that is
created after shrinkage.
The above are cents by Mike Herzig and myself.
LAND
MEgLOPIMENT
�7C
R?* Richter June 8, 1989
Development Services
City of Fort Collins
300 Laporte Avenue
Fort Collins, Colorado 80522
Re: Clarendon Hills Third Filing
Matters Related to the Pavement Design Report
Dear Rick,
We are pleased to provide information regarding the design
of the street subgrade drainage system recommended in the
referenced report from Empire Laboratories datel May 25, 1989.
Transmitted with this brief summary letter, please find
three sets of prints of Sheets 5 and 6 of the project';,
construction drawings (utility plans) showing the "sub --drain''
location and construction details. The subgrade drain has been
installed in Langdale and Cul-de-sac "E", but not in Rochelle
Circle.
Pursuant to Neil Sherrod and I meeting with you and other
staff a week ago today, we have tried to address the items t at
were left to be accomplished after that discussion. We have had
additional test holes dug in the street, inspected by Empire and
finally determined the horizontal limits of the necessGry street
drain improvements.
I have discussed the best apparent solution to the design
criteria and the construction requirements with the contractors,
Neil, Jeff Smith from ADS, Gary Nordick, and some members of City
Staff. The result is reflected on the transmitted drawings.
Regarding the Storm Drainage Utility requirements, a
separate amendment to the storm drainage report is being prepared
now. In a phone conversation with Susan Hayes, I explained that
we were required to tie in the street sub -grade drainage system
into the storm sewer to rid the streets in the third filing from
possible perched water conditions in the top three feet of the
subgrade.
Susan asked that the information be provided in writing that
I orally presented at that time. Although the information will
be provided in the amendment to the report, a brief summary is
provided as follows:
L05Land Development Services 117 East Mountain Avenue • Suite 201 Fort Collins, Colorado 80524 303/493-4624
The property is along a ridge. There are no potential
subdrainage flows that will enter this filing from off —site. The
only water that will enter the subgrade drain will be from
percolation into lawns fronting on the streets. It is not
anticipated that that will lead to a large amount of water
anywhere in the system.
In the areas where the bedrock is within three feet of the
finished street subgrade elevation, whatever lawn watering or
storm water that can infiltrate the soil and reach the bedrock
will flow (trickle) into the street subdrain. From there to the
outlet into the 10 foot storm drainage catch basin, efficient
flow is ensured via the 6 inch perforated drain and trench —full
of 3/4 inch rock.
Based on the design recommendation
(which might be considerably higher than
in fact) their might be 12 cubic feet pe
the 10 foot inlet. Even if this occured
was occuring, the combined flow of both
would not exceed the capacity of the sys
constructed.
for discharge by Empire
what will be experienced
r second of disharge at
while the 100 year storm
sources of runoff still
tem that was designed and
Regarding water quality, I told Susan that the flows will be
from underground flows along perched bedrock conduits. Normally,
I think flows from these sources are relatively clean.
We appreciate your continued cooperation and assistance in
resolving this matter and continuing to strive to make this
subdivision a quality statement in Fort Collins. We would like
to have Engineering Services now work with us on further testing
and inspection that will allow base course materials to start
being placed.
Thank you Rick! I will follow up soon.
incerely,
��Xzj�y i) er�j
Dennis L. Donovan, P.E.
Managing Partner
Land Development Services
4924 S. Shields
Fort Collins, CO. 80526
Phone (303)-225-9244
cc Gary Nordick
Susan Hayes
Neil Sherrod
Schmidt Earth Builders
Flatiron Paving, now Western Mobile
Otil,INS 10��C
CI
9TER DIS�4~G
June 30, 1989
Gary Nordic
309 W. Harmony Road
Fort Collins,, Co 80525
RE: Clarendon Hills, Third Filing
Dear Gary,
This letter is to advise you that the Fort Collins - Loveland
Water District and the South Fort Collins Sanitation District
have accepted the water and sanitary sewer lines on the above
mentioned project. Expiration of the warranty period will be one
year from the above acceptance date.
If you have any quentions, please feel free to call.
sincerely,
r_ may,
Michael DiTullio
District Manager
xc: Terry Farrill, Systems Engineer
Dean Hill, Operations Supervisor
Helen West, Office Manager
Dennis Donovan
<\CLOSE.OUT\CLARHIL3.ACP>
1700 South College Avenue
Fort Collins, Colorado 80525roru��
Telephone 226-3104 -- 669-4321
s.
Citv of Fort Collins
July 5, 1989
Develop►.tent Services
Engineering Department
Gary Nordic
309 W. Harmony Road
Fort Collins, Colorado 80525
01COMRINOWNSUMrl' �� ► M�: ►
This letter is to inform you that the streets, curb and gutter, and walk
constructed to date on Langdale Drive, Hinsdale Drive from the tie-in to
Langdale Drive, Langdale Court, and cul-de-sacs A through D in Clarendon
Hills, Third Filing, have been inspected and accepted by the City pending
the normal contractor warranty period.
NOTE: This does not release the contractors or developer from any punch
list items that: might arise during the course of construction or any damage
that might occur during construction.
Sincerely,
Lance Newlin
Engineering Construction Inspector
',10 1 1P0rte A%enue • P.O. Boy 580 • Fort Collins, CO 80522-0580 (303) 221-6605
Develol ent Services
Engineering Department
City of Fort Collins
November 24, 1989
Nordic Construction Company
309 W. Harmony Road
Fort Collins, Colorado 80525
Re: Clarendon Hills 3rd Filing
Dear Mr. Nordic:
The intent of this letter is to remind you of the City Storm Drainage
Department requirements regarding development of certain lots within the
Clarendon Hills 3rd Filing. The development agreement for this
subdivision, under special Conditions, paragraphs i,ii, a and b, restricts
the building of homes on portions of Langdale and Hinsdale Drives. The
following lots; are required to have the adjacent storm drainage channel
construction certified as to its conformance with the approved utility
plans prior to the issuance of Building Permits and again before release of
Certificates of Occupancy.
Lot 10 - 839 Langdale
11 -
833
It
12 -
827
if
15 -
809
If
16 -
803
it
20 -
727
it
21 -
721
It
22 -
715
it
Lot 30 -
4924
Hinsdale
31 -
4918
if
32 -
4912
33 -
609
"
300 LaPorte Avenue • 1'.0. Box 580 • Fort Collins. CO 80522-0580 • (303) 221-6605
Nordic Construction Company
Page Two
With the start of construction in this development, I ask that the initial
certification be submitted to Susan Hayes in our Storm Drainage Department
as soon as possible, with the follow-up recertification- prior to home
builders requesting their C.O's.
Hopefully, we will then be able to avoid any delays in the issuance of
Building Permits and Certificates of Occupancy for the above lots.
Thank you in advance for your cooperation in this matter and if you have
any questions, please call me at 221-6605.
Sincerely,
T yam
David Stringer
Chief Construction Inspector
cc: Susan Hayes
14;LC &-Y1,94/,13 iT�"
Ms. Susan Hayes December 5, 1989
Engineering Department
Storm Drainage Division
City of Fort Collins
235 Mathews
Fort Collins, CO. 80524
RE: Letter of Certification and
Final Storm Drainage Report
Clarendon Hills Third Filing
Dear Susan,
This letter is written to provide certification that most of
the storm drainage improvements required for the referenced
subdivision for a minor and major (i.e. 2 and 100 year) design
storms have been constructed and are in good operating condition
at this time.
The only improvements not completed include the small
drainage swale along the north side of Lots 84 and 85 and the
extension of a swale, and/or concrete gutter pan, on the south
side of Lots 4 and 5.
It is recommended that all other Lots in the Third Filing be
granted building permits upon request, and that a certificate of
occupancy be granted for Lot 30 upon request. I have reviewed
the improvements located in the 30 foot drainage easement on the
east side of Lot 30, and the grading is essentially unchanged
from that grading achieved prior to the building permit for Lot
30 issued by the City of Fort Collins.
The Amendment to the Final Drainage Report, along with the
supporting information, is enclosed with this letter.
I would be happy to.certify that any particular lot has been
constructed to satisfy City of Fort Collins Storm Drainage
Utility requirements, upon request of the property owner, and
confirmation that the final grading does indeed conform to said
requirements.
Sincerely,
Dennis"L. Donovan, P.E.
Managing Partner
Land Development Services
4924 S. Shields
Fort Collins, Colorado 80526
The flow in the Swale is an additional 1.7 feet lc-pn I. -
carry the additional flow away from the cul —de—sac dur1ng a ;"?
Year storm. This causes the Ponded depth of stormwater to be '.4
feet over the gutter grade at Catch Basin 41.
The depth of storm water runoff in the gutter, is within the
allowable 1.5 feet within 40 feet to the Nast and within 85 feet
to the west of the catch basin.
This condition will cause some additional depth of storm
water in the gutter at the driveway -'or Lots C3, and :2
(depending on the placement of the driveway For Lot 32) during
major storms. The homes themselves will not be affected on t;ese
lots, as their foundations are to be set at a minirnum of ? feet
above the maximum storm water elevation.
We will meet with Susan Hayes later this week to discuss the
variance request.
Than: you for your continued assistance in the review and
Processing of this Phase of the Clarendon Hills Subdivision. We.
look forward to completing the requirements by January 17th for
the January 23rd Planning and Zoning Meeting.
Sincerely,
Dennis L. Donovan, P.E.
GotiLINS-,I
0
w �
d
DIS't41.
December 7, 1.989
Mr. Gary Nordic
309 West Harmony Road
Fort Collins, Colorado 80525
RE: Clarendon Hills, Third Filing, Phase 2
Dear Gary:
This letter is to advise you that the Fort Collins -Loveland Water
District and the South Fort Collins Sanitation District have
accepted the water and sanitary sewer lines on the above mentioned
project. Expiration of the warranty period will be one year from
the above acceptance date.
If you have any questions, please feel free to call.
Sincerely,
Michael DiTullio
District Manager
xc: Terry Farrill, Systems Engineer
Dean Hill, Operations Supervisor
Helen West, Office Manager
Dennis Donovan k-'-_
4700 South College Avenue
Fort Collins, Colorado 80525
Telephone 226-31.04 -- 669-4321
Develc _:vent Services
Engineering Department
December 15, 1989
Gary Nordic
309 W. Harmony Road
Fort Collins, Colorado 80525
TO WHOM IT MAY CONCERN:
This letter is to inform you that the streets, curb, gutter and walk
constructed as of August 26, 1989 on Langdale Drive, Langdale Court (north
and south), Hinsdale Drive, Rochelle Circle, Hinsdale Court and cul-de-sacs
"A" thru "E" in Clarendon Hills, 3rd Filing, have been inspected and
accepted by the City pending the normal contractor warranty period.
NOTE: This dcxs not release the contractors or developer from any punch
list items that might arise during the course of construction or any damage
that might occur during construction.
sincerely,
Lance Newlin
Engineering Construction Inspector
cc: Dennis Donavan
n S W Inc
COLORADO REGISTERED PROFESSIONAL ENGINEERS & LAND SURVEYORS
P.O.Box 1391 Fort Collins, CO. 80522 PHONE (303)484-0533
September 27, 1990
Garth Development Inc.
c/o Mr. George A. Holter
3509 South Mason St.
Fort Collins, CO. 80525
Re: Drainage Ditch South of Lot 22, Clarendon Hills
Subdivision, Third Filing, Larimer County Colorado.
r
Dear Mr. Holter,
As per your request, a site inspection was performed on Lot
22, Clarendon Hills Subdivision, Third Filing, Larimer County
Colorado, on February 27, and March 16, 1990, to check the
condition of the drainage ditch south of this lot.
The drainage ditch condition was the same as before the open
hole was excavated for Lot 22, Clarendon Hills Subdivision, Third
Filing, Larimer County Colorado.
If you have any questions or need more information, and if
we may be of further assistance please don't hesitate to call our
office. 484-0533.
Sincerely,
M amed S: oray'eth
Professional Engineer
Colorado Reg. P.E. 23019
STEWART&ASSOCIATES
Consulting Engineers and Surveyors
October 2, 1990
Mr. Robert Smith
Storm Drainage Utility
City of Fort Collins
P.O. Box 580
Fort Collins, Colorado 80522
Dear Bob:
This is to certify to you that I have inspected the final grading
of Lot 16, Clarendon Hills, Third Filing. The address is 803 Langdale
Drive, and the contractor was Dick Pitner. The drainage swale in the
20—foot drainage easement at the rear of the lot was graded as per the
grading plan that is a part of the utility plans. The drainage is
Easterly and is contained within the drainage easement.
If you have any questions regarding this matter, please call.
Sincerely,
Richard A. Rutherford, P.E. & L.S.
President
jrr
cc: Engineering Inspection
James H. Stewart
and Associates, Inc.
214 N. Howes Street
PO Box 429
Ft. Collins, CO 80522
303/482-9331
Utilitv Sei ,, ices
Stormwater
October 26, 1990
Gary Nordick
Nordic Construction
309 W. Harmony Road
Fort Collins, CO 80526
RE: Clarendon Hills 4th and 5th Filings
Burns Trib ary and Fossil Creek Stability Analysis
Dear Gary:
The purpose of this letter is to document the cost sharing
agreement between the City and the Developer of Clarendon Hills for
the services to be provided by Lidstone and Anderson. These
services are described in the Scope of Work titled, "Channel
Stability Analyses, Burns Creek and Fossil Creek, Clarendon Hills
Development .in Fort Collins" (copy attached) .
The costs will be shared as follows. Tasks 1 through 7 and Task
10 will be :split evenly between the Stormwater Utility and the
Developer. If during the course of the project additional work is
required in any of these tasks the sharing of the additional cost
will be negotiated. The cost of Task 8, Evaluation and Design of
Hydraulic Structures, including any additional cost due to changes,
will be the responsibility of the Developer. The cost of Task 9,
Evaluation and Design of Hydraulic Structures Identified in the
Fossil Creek Drainageway Study, including any additional cost due
to changes, will be the responsibility of the Stormwater Utility.
Based on the cost estimate provided by Lidstone and Anderson, the
Developer's :share is $5,094 and the Utility's is $5,876.
The costs which are reimbursable by the Utility will be included
in Exhibit B of the Development Agreement. The agreement must be
signed before we can reimburse the Developer.
235 Mathev s • P.O. Box 580 • Fort Collins, CO 80522-0580 • (303) 22"1-6589
If you have any questions or do not agree with the statements made
in this letter please contact me as soon as possible at 221-6589.
If I do not hear from you by Monday, November 5, 1990 I will assume
that we are in agreement.
Sincerely,
Susan Duba Hayes, P.E.
Civil Engineer II
Attachment
cc: Dennis Donovan
Engineering File
Utility S ices
Sto rmwater
City of Fort Collins
April 11, 1991
Mr. Gary Nordick
Nordic Construction Company
309 W. Harmony Road
Fort Collins, Colorado 80526
Re: Clarendon Hills 3rd Filing, Landscaping in Drainageways
Dear Gary:
Per your request, I am documenting the results of our meeting of April 4,
1991. The purpose of this meeting was to discuss landscaping guidelines
for your use in evaluating proposed landscape plans, specifically with
respect to landscaping in designated drainage channels.
When reviewing the proposed landscape plans it is important to remember the
purpose of the channels. Their primary function is to carry stormwater
flows safely through the site, therefore it is of the utmost importance not
to impede the flows. This still allows leeway in designing an aesthetic
landscape treatment, but the following must be adhered to:
Grading/Alignment: lot line elevations shall not deviate from the grades
shown on the approved plans. This is to ensure that flows are not blocked
from one property to the next, nor are there any abrupt drops in the chan-
nel invert that may be a potential erosion problem. Channel alignment can
vary from the alignment shown on the approved plans, for instance by adding
gentle curves. However, a constant slope must be maintained through the
lot.
Fencing: all lot line fencing over a drainage channel shall provide a min-
imum of one foot clearance from the bottom of the fence to the channel
invert. This opening may be screened but only with material that has a
minimum of 2"x4" openings. Wire mesh is not allowed. Hinged gates may
also be installed that will be pushed open by the water. It should be made
clear to the homeowner that any screening or hinged gate may accumulate
trash and it is their responsibility to keep the opening clear of debris so
as not to impede flows.
Channel Treatment: the channel may be lined with a variety of groundcover
materials such as grass, cobble, gravel, and landscaping bark. It is
important that when the groundcover material is installed that the invert
of the channel is not raised. Over -excavation may be required in order to
install larger material such as cobble.
?» • P.O. Boy �80 -• Fort Collin,,, CO 'W:;224)5'+o • (303) 221-6�;89
Vegetation: the use of trees and shrubs is encouraged, but placement of
the plantings is very important. Trees and shrubs shall be planted above
the high water- line of the channel. For instance, if the water will get
one foot deep and the channel sideslopes are 4:1, then trees and shrubs
must be planted a minimum of 4 feet away from the channel centerline. For
trees or shrubs that grow large, some additional distance should be added
to allow for growth without impeding the channel flow. The only vegetation
allowed in the channel itself are flexible plantings such as flowers or
decorative gr�Lsses that will lay over and not impede the flow of the water.
Even flexible plantings may cause the water surface level to rise due to
the increased friction, so homeowners may see the water spread outside the
defined channel during large flows.
It is often difficult to determine exact planting locations on a landscape
plan or to tell the relationship of the plantings to the drainage channel.
To ease your review I suggest that you require a cross-section view of the
channel on all. landscape plants that shows the limits of the channel treat-
ment, location of trees and shrubs with respect to the high water line, and
any planting proposed in the channel itself. This will help you determine
if the requirements outlined herein are being met.
I hope that this information is helpful in your review of the landscape
plans. If you have questions or would like guidance on a specific lands-
cape plan pleELse call me at 221-6589.
Sincerely,
Susan L. Duba Hayes, P.E.
Civil Engineer II
cc: Engineering File
LAND
MEgLOPIMENT
ES
Ms. Linda Ripley January 19, 1988
Project Planner
Planning Department
'. ity of Fort: Collins
300 Laporte Avenue
Dort Collins, Colorado 80522
Re: Clarendon Hills Third Filing
Final Subdivision Approval
Dear Linda,
We are pleased to provide the final mylars aiid documents to
ccmp).ete our submittal for the referenced project. The submitted
materials are as follows:
A. Original myl ar drawings of the Final Subdivision Plat.
R. Original mylar drawings of the Utility Plans, ;s:i�jned by the
owner, aLtorney, lender, and the water and sanitation district
representatives.
C;. Two (2) copies of the Final Drainage Study as requested by
..'usan Hayes.
I:. An APPI.TCATI.ON__FOR- ENCROACHMENT tlPOiv-_Pl.1$LIC_RIGHT-G-F_ WAY for
the Iand,,capo irrigation systeri crossings under some of the
streets and cul--de-sacs.
E. An original signed agreement by the property owners adjacent
to the east of Clarendon Hills Third Filing relative to
irrigation .and storm drainage improvements. Once the third
filing has been approved by the City, the agreement will be
recorded at the County, and a copy will be providt:d for your
files.
Mike Hertzi.g has a signed original easement for utilities
and storm drainage across Lot 18 of Clarendon Hills Third Filing
a, required, as well as the original subdivision ayreemnent, in
his possession.
We are pleased to inform you that no variances to City
Standards are requested, or neec :ssary. We wexe abs_e to resolve
Staff concerns prior to this submittal.
U16Land Development Services 117 East Mountain Avenue • Suite 201 Fort Collins, Colorado 80524 303/493-4624
Thank you for the professional manner in which the project
was reviewed and processed by Staff. It has been a pleasure, and
we are looking forward to the development and ultimate build -out
of this project. If anything further needs to be addressed,
please call Rob Persichitte or me.
Sincerely,
Dennis L. Donovan, P. E.
cc Mike Hertzig v
Susan Hayes
Gary Nordick
Rob Persichitte
Develoht_., Services
Engineering Department
City of Fort Collins
March 23, 1989
Gary Nordic
Nordic Construction and Development
309 W. Harmony Road
Fort Collins, Colorado 80525
Re: Special conditions to encroachment permit number 1-89 for
Clarendon Hills Associates
Dear Mr. Nordic:
Encroachment permit number 1-89 has been approved by the City with the
following conditions:
1. Use class 200 / DR 14 polyvinyl chloride pipe, not schedule 200, as the
casing pipe under the street rights -of -way.
2. Backfill the pipe trench with non -shrink fill material. This fill will
act as bedding material as well as trench backfill and will extend from
top to bottom of the trench. (specifications are attached)
3. The responsibility for maintenance of this pipe, trench and street
wearing surface rests solely with Clarendon Hills Associates who shall
hold the City harmless of any liability which should arise as a result
of this encroachment.
4. The Associates will crnTply within 3 working days, if the City requests
repairs to the system, pipe, trench or street surface.
5. Prior to making any repairs, changes or abandoning the system, which
are not at the request of the City, all appropriate permits are to be
obtained.
300 LaPorte Avenue - 11.0. 13o\ ;ti0 - Fort Collins, CO 80533-0580 - (303) 221-o(IW;
Z
Gary Nordic
Page Two
6. All location changes, deletions or additions are to be shown on an "as
constructed" drawing submitted to the City Engineers office after the system
has been installed.
7. The City reserves the right to require the removal of this system from the
public rights -of -way at any time as outlined in Chapter 23 - 81 of the
Code of the City of Fort Collins.
8. A copy of the encroachment permit shall be recorded with the County Clerk
and Recorder.
If you have any questions, please feel free to contact me at 221-6605.
Sincerely,
Dave Stringer
Chief Construction Inspector
PUBLIC WORKS DEPARTMENT
April 13, 1989
Advanced Drainage Systems, Inc.
2808 S. Wheeling Way
Aurora, CO 8�001 4
ATTENTION: Jim Heintz
SUBJECT: New Plastic Pipe Specification for the
City of Aurora
Dear Mr. Heintz:
Engineering Design Division
1470 South Havana Street
Aurora, Colorado 80012
303/695-7300
The City of Aurora has finished a draft of the new plastic pipe
specification. We are currently reviewing the specification "in-house"
and plan to adopt the specification June 1, 1989.
At this time: we would like to give your company the opportunity to review
the specification and make comments. I would appreciate receiving your
review by April 28, 1989.
If you have any questions please call.
Sincerely,
i
Rick Hunter
Design Engineer
RH/me
Enclosure
(TO BE ADDED TO THE SPECIAL CONDITIONS)
PLASTIC GRAVITY DRAIN PIPE AND FITTINGS
I. GENERAL
This specification is intended to cover plastic gravity drain pipe
and fittings suitable for underground gravity transportation of
storm and waste water. The pipe and fittings shall meet all
specifications of the manufacturer and conform to ASTM and AASHTO
requirements regarding the specified pipe.
Plastic! pipe may be smooth wall, corrugated or externally ribbed and
may be manufactured of polyethylene (PE) or poly (vinyl chloride)
(PVC). The material specifications are:
Polyethylene (PE)
Corrugated - AASHTO M294 Corrugated Polyethylene Pipe, 2—to==2-4
.; n
Ribbed - ASTM F894 Polyethylene (PE) Large Diameter Profile
Wall Sewer and Drain Pipe
Poly (Vinyl Chloride) (PVC)
Ribbed - ASTM F794 Poly (Vinyl Chloride (PVC) Large -Diameter
Ribbed Gravity Sewer Pipe and Fittings Based on
Controlled Inside Diameter
II. PIPE DIMENSIONS
Wall thickness shall be the minimum required by the manufacturer and
meet ASTM and AASHTO requirements for the type, diameter and class
of pipe shown on the drawings. Pipe shall be measured according to
ASTM 21122. The diameter indicated on the plans shall mean the
nominal_ inside diameter of the pipe.
III. FITTINGS, JOINTS AND GASKETS
All fittings, joints and gaskets shall be as recommended by the
manufacturer and installed according to the recommendations of the
manufacturer. Fittings, joints and gaskets shall be of such quality
and type that they shall not reduce or impair the overall integrity
or function of the pipeline. Joints and gaskets shall show no sign
of leakage when tested according to ASTM D3212. Pipe gaskets shall
meet ASTM F477 specifications.
Corrugated polyethylene pipe is not approved for use as wastewater
transmission piping.
EDS.8006
-1-
IV. MATERIAL STORAGE
Pipe and fittings shall be carefully stored to maintain the
condition of the pipe as manufactured. Pipe shall be stored on a
flat surface to protect the pipe from deformation due to temperature
fluctuations and stress fatigue. Pipe shall be stored to prevent
dirt or mud from entering the pipe. The inside of the pipe shall be
free of dirt and mud prior to placement. Pipe shall be protected
from exposure to ultraviolet radiation per manufacturer's
recommendations. Severe discoloration of the pipe material shall be
evidence of ultraviolet damage and the pipe shall be rejected and
removed from the project at the discretion of the Project Engineer.
V. INSTALLATION
Pipe shall be ins�alled in full compliance with ASTM Standard D2321
unless otherwise noted in this specifications.
Pipe shall be installed using Class "B" Alternate Bedding, as
detailed in these specifications, with the granular material brought
up to a minimum of twelve (12) inches of depth over the top of the
pipe. Bedding material shall be hand placed and compacted under
haunches of pipe to insure uniform support. Bottom of trench shall
be on undisturbed soils or fully compacted bedding material and on
grade to provide uniform support along the barrel of the pipe. Bell
holes shall be made at each joint.
Backfill shall be compacted as required on the plans and
specifications. Random tests for compaction may be made at all
elevations of the trench sections to insure proper compaction around
the pipe. Sufficient backfill shall be placed on the barrel of each
pipe section to secure the pipe against flotation from water in the
trench or subsurface water.
Care shall be taken to insure a clean line. Whenever pipe laying is
not in progress pipe plugs shall be installed at each end of the
pipe.
VI. TESTING AFTER CONSTRUCTION
A. GENERAL Plastic Gravity Sewer Pipe shall be tested in
accordance with this section as well as in accordance with other
sections of these specifications after the pipe is in place and
backfilled. Any testing required by the Contractor prior to
backfilling, except soil testing, shall be supplied by the
Contractor at the Contractor's expense.
B. MAXIMUM DEFLECTION TEST Deflection Inspection Tests shall be
conducted immediately upon completion of the entire sewer and
prior to final acceptance. The maximum allowable initial pipe
-2-