May 7, 1999
Mr. John Sailer
Nordic Construction
309 West Harmony Road
Fort Collins, Colorado 80526
Re: Remax
4703A Boardwalk
Fort Collins, Colorado
Project No. 20991016
We are transmitting:
® Field Data
Regarding:
Irerracon
301 N. Howes • P.O. Box 503
Fort Collins, Colorado 80521-0503
1970)484-0359 Fax: f970)484 0454
® herewith
❑ under separate cover
❑ Laboratory Data ❑ Report ❑ Revised Report
❑
Compacted Fills
❑
Footings
❑
Concrete
❑
Asphalt
❑
Aggregate
❑
Concrete Reinforcing
Steel
❑
Permeability Test
❑
Location Diagram
❑
Soil Samples
❑
Construction Material
Samples
❑
Moisture -Density
❑
Grain Size Analysis
®
Masonry
❑
R-Value
❑ General Information
❑ Certifications
❑ Resumes
❑ Other
❑ Report will follow under
separate cover
On -site observation services were provided ❑ Full Time ® Part Time
We have not been asked to interpret the data or to make design and/or construction
recommendations based on the data, and cannot assume responsibility or liability for interpretation
of this data by others.
Sincerely,
TERR j VaG.
by:
lam'
Richard Hoskinson eeks, P.E.
Engineering Technician Engineer
Enc/Copies to: (3) Addressee
Arizona ■ Arkansas R Colorado ■ Idaho ■ Illinois ■ Iowa ■ Kansas ■ Minnesota ■ Missouri ■ Montana
Nebraska ■ Nevada ■ New Mexico 0 North Dakota ■ Oklahoma ■ Tennessee ■ Texas ■ Utah In Wisconsin ■ Wyoming
Quality Engineering Since 1966
May 7, 1999
Mr. Gary Nordic
Nordic Construction
309 West Harmony Road
Fort Collins, Colorado 80526
Re: Remax Building
Lot 1, Miramont Office Park
Fort Collins, Colorado
Project No. 20991016
We are transmitting:
® herewith
❑ under separate cover
Irerracon
301 N. Howes • P.O. Box 503
Fed Collins, Colorado 80521-0503
(970)484-0359 Fax: (970) 484-0454
® Field Data ❑ Laboratory Data ❑ Report ❑ Revised Report
Regarding:
❑
Compacted Fills
❑
Footings
❑
Concrete
❑
Asphalt
❑
Aggregate
❑
Concrete Reinforcing
Steel
❑
Permeability Test
❑
Location Diagram
❑
Soil Samples
❑
Construction Material
Samples
❑
Moisture -Density
❑
Grain Size Analysis
®
Masonry
❑
R-Value
❑ General information
❑ Certifications
❑ Resumes
❑ Other
❑ Report will follow under
separate cover
On -site observation services were provided ❑ Full Time ® Part Time
We have not been asked to interpret the data or to make design and/or construction
recommendations based on the data, and cannot assume responsibility or liability for interpretation
of this data by others.
Sincerely,
T!!ERRRACON n �j
/chneider,
Connie J. E.I.T.
Geotechnical Engineer
Enc/Copies to: (3) Addressee
by:
G. Weeks, P.E.
tural Engineer
Arizona ■ Arkansas ■ Colorado ■ Idaho ■ Illinois ■ Iowa ■ Kansas ■ Minnesota ■ Missouri ■ Montana
Nebraska ■ Nevada ■ New Mexico ■ North Dakota ■ Oklahoma ■ Tennessee ■ Texas ■ Utah ■ Wisconsin ■ Wyoming
Ouality Engineering Since 1965
No Text
May 20, 1999
Mr. John Sailer
Nordic Construction
P.O. Box 271970
Fort Collins, Colorado 80527
Re: Remax
4703A Boardwalk
Fort Collins, Colorado
Project No. 20991016
We are transmitting:
® Field Data
Regarding:
Irerracon
301 N. Howes • P.O. Box 503
Fed Collins, Colorado 80521-0503
(970) 484-0359 Fax: (970) 484-0454
® herewith
❑ under separate cover
❑ Laboratory Data ❑ Report ❑ Revised Report
❑
Compacted Fills
❑
Footings
❑
Concrete
❑
Asphalt
❑
Aggregate
❑
Concrete Reinforcing
Steel
❑
Permeability Test
❑
Location Diagram
❑
Soil Samples
❑
Construction Material
Samples
❑
Moisture -Density
❑
Grain Size Analysis
®
Masonry
❑
R-Value
❑ General Information
❑ Certifications
❑ Resumes
❑ Other
❑ Report will follow under
separate cover
On -site observation services were provided ❑ Full Time ® Part Time
We have not been asked to interpret the data or to make design and/or construction
recommendations based on the data, and cannot assume responsibility or liability for interpretation
of this data by others.
Sincerely,
TERRACON
Connie J. Schneider, E.I.T.
Field Engineer
Enc/Copies to: (3) Addressee
Reviewed by:
Richer, P.E.
Department Manager/Engineer
Arinna ■ Arkansas ■ Colorado ■ Idaho ■ Illinois ■ Iowa ■ Kansas ■ Minnesota ■ Missouri ■ Montana
Nebraska ■ Nevada ■ New Mexico ■ North Dakota ■ Oklahoma ■ Tennessee ■ Texas ■ Utah ■ Wisconsin III Wyoming
Quality Engineering Since 1966
lrerracon
301 North Howes Street
Fort Collins, Colorado 80521
970 484-0359 FAX 970 484-0454
REPORT OF. MASONRY OBSERVATION
CLIENT:
Nordic Construction
PO Box 271970
Fort Collins, CO 80527
PROJECT:
Remax Building
Lot 1, Miramont Office Park
Fort Collins, Colorado
CONTRACTOR:
Nordic Construction
DATE & TIME:
5113199 9:45 AM
REPORT NO.:
4
PROJECT NO.:
20991016
WEATHER CONDITIONS:
Sunny, calm
INSPECTOR:
Connie Schneider
LOCATION AND DESCRlPTIONI:OF WORK 71
GRID & ELEVATION:
Elevator shaft at 19'
MASONRY UNITS:
Hollow block 8 x 8 x 16"
REINFORCEMENT:
Vertical - #6 rebar in grout cells
Horizontal - 2 - #4 rebar in bond beams
GROUTING:
Observed grout placement
SUMMARY
COMMENTS:
Placement in general accordance with plans
DISCREPANCIES NOTED:
None noted or observed during periodic observation on 5/13/99
May 20, 1999
Mr. John Sailer
Nordic Construction
P.O. Box 271970
Fort Collins, Colorado 80527
Re: Remax
4703A Boardwalk
Fort Collins, Colorado
Project No. 20991016
We are transmitting:
® Field Data
Regarding:
Irerracon
301 N. Howes • P.O. Box 503
Fon Collins, Colorado 80521-0503
(970)484-0359 Fax'.(970)484-0454
o aVl,,l�
MAY P, 4 1999
® herewith
❑ under separate cover
❑ Laboratory Data ❑ Report ❑ Revised Report
❑
Compacted Fills
❑
Footings
❑
Concrete
❑
Asphalt
❑
Aggregate
❑
Concrete Reinforcing
Steel
❑
Penneability Test
❑
Location Diagram
❑
Soil Samples
❑
Construction Material
Samples
❑
Moisture -Density
❑
Grain Size Analysis
®
Masonry
❑
R-Value
❑ General Information
❑ Certifications
❑ Resumes
❑ Other
❑ Report will follow under
separate cover
On -site observation services were provided ❑ Full Time ® Part Time
We have not been asked to interpret the data or to make design and/or construction
recommendations based on the data, and cannot assume responsibility or liability for interpretation
of this data by others.
Sincerely,
TERRACON
Z�/�(o/reHeider, E.I.T.
Field Engineer
Reviewed by:
avid A. Richer, P.E.
Department Manager/Engineer
Enc/Copies to: (3) Addressee -
Arizona ■ Arkansas ■ Colorado ■ Idaho ■ Illinois ■ Iowa ■ Kansas ■ Minnesota ■ Missoun ■ Montana
Nebraska ■ Nevada ■ New Mexico ■ North Dakota • Oklahoma ■ Tennessee ■ Texas ■ Utah IN Wisconsin ■ Wyoming
Ouagty Engineering Since 1965
rracon
301 North Howes Street
Fort Collins, Colorado 80521
(9701484-0359 FAY (970)48
CLIENT: Nordic Construction
PO Box 271970
Fort Collins. CO 80527
GROUTING:
Remax Building
Lot 1, Miramont Office Park
Construction
calm
shaft at 19'
8x8x16"
or
i
May 7, 1999
Mr. Gary Nordic
Nordic Construction
309 West Harmony Road
Fort Collins, Colorado 80526
Re: Remax Building
Lot 1, Miramont Office Park
Fort Collins, Colorado
Project No. 20991016
We are transmitting:
® Field Data
Regarding:
Irerracon
301 N. Howes • P.O. Box 503
Fort Collins, Colorado 60521-0503
(970)484-0359 Fax:(970)484-0454
® herewith
❑ under separate cover
❑ Laboratory Data ❑ Report ❑ Revised Report
❑
Compacted Fills
❑
Location Diagram
❑ General Information
❑
Footings
❑
Soil Samples
❑ Certifications
❑
Concrete
❑
Construction Material
❑ Resumes
❑
Asphalt
Samples
❑ Other
❑
Aggregate
❑
Moisture -Density
❑ Report will follow under
❑
Concrete Reinforcing
❑
Grain Size Analysis
separate cover
Steel
®
Masonry
❑
Permeability Test
❑
R-Value
On -site observation services were provided ❑ Full Time ® Part Time
We have not been asked to interpret the data or to make design and/or construction
recommendations based on the data, and cannot assume responsibility or liability for interpretation
of this data by others.
Sincerely,
TERRACON
aae�
Connie J. Schneider, E.I.T.
Geotechnical Engineer
Weeks, P.E.
31 Engineer
Arizona ■ Arkansas ■ Colorado ■ Idaho ■ Illinois ■ Iowa ■ Kansas ■ Minnesota ■ Missouri ■ Montana
Nebraska ■ Nevada ■ New Mexico ■ North Dakota ■ Oklahoma ■ Tennessee ■ Texas ■ Utah ■ Wisconsin ■ Wyoming
Quality Engineering Since 1965
Irerracon
301 North Hawes Street
Fort Collins, Colorado W521
970) 48"369 FAX (970) 4844454
..
... .
. ... .. .... ............. -
.... . ...... :!;1::::N: r .....................
....... . ..... RePORT.OF1VIA9.ONIkY..,08SERVATtON
CLIENT:
Nordic Construction
309 West Harmony Road
Fort Collins, CO 80526
PROJECT.,
Remax Building
Lot 1, Miramont Office Park
Fort Collins, Colorado
CONTRACTOR:
Nordic Construction
DATE & TIME:
5JW99 10:30 AM
REPORT NO.:
3
PROJECT NO.:
20991016
WEATHER CONDITIONS:
Partly cloudy, windy
INSPECTOR:
Connie Schneider
..... .....
LOCATION AND DESCRIPTION; WORK
GRID & ELEVATION:
Elevator shaft
MASONRY UNITS:
Hollow block 8 x 8 x 16'
REINFORCEMENT:
Vertical - #6 rebar in grout cells
Horizontal - 2 - #4 rebar in bond beams
'GROUTING:
N. .... .
....... ..... ..... . .... ....
.... ...... nn .-SUMMARK.: ..........
n.:.
COMMENTS:
Placement in general accordance with plans
DISCREPANCIES NOTED:
None
May 20, 1999
Mr. John Sailer
Nordic Construction
P.O. Box 271970
Fort Collins, Colorado 80527
Re: Remax
4703A Boardwalk
Fort Collins, Colorado
Project No. 20991016
We are transmitting:
® Field Data
Regarding:
Irerracon
301 N. Howes • P.O. Box 503
Fort Collins, Colorado 80521-0503
(970) 484�0359 Fax: (970) 484-0454
® herewith
❑ under separate cover
❑ Laboratory Data ❑ Report ❑ Revised Report
❑
Compacted Fills
❑
Footings
❑
Concrete
❑
Asphalt
❑
Aggregate
❑
Concrete Reinforcing
Steel
❑
Permeability Test
❑
Location Diagram
❑
Soil Samples
❑
Construction Material
Samples
❑
Moisture -Density
❑
Grain Size Analysis
®
Masonry
❑
R-Value
❑ General Information
❑ Certifications
❑ Resumes
❑ Other
❑ Report will follow under
separate cover
On -site observation services were provided ❑ Full Time ® Part Time
We have not been asked to interpret the data or to make design and/or construction
recommendations based on the data, and cannot assume responsibility or liability for interpretation
of this data by others.
Sincerely,
TTEERRRACON/�
Connie J. Schneider, E.I.T.
Field Engineer
Enc/Copies to: (3) Addressee
Reviewed by:
David A. Richer, P.E.
Department Manager/Engineer
Arizona I• Arkansas ■ Colorado ■ Idaho ■ Illinois ■ Iowa I• Kansas ■ Minnesota ■ Missouri ■ Montana
Nebraska ■ Nevada • New Mexico if North Dakota ! Oklahoma ■ Tennessee ■ Texas ■ Utah MI Wisconsin ■ Wyoming
Quality Engineering since 1965
lrerracon
301 North Howes Street
Fort Collins, Colorado 80521
970 484-0359 FAX 970 484-0454
REPORT OF MASONRY OBSERVATION
CLIENT:
Nordic Construction
PO Box 271970
Fort Collins, CO 80527
PROJECT:
Remax Building
Lot 1, Miramont Office Park
Fort Collins, Colorado
CONTRACTOR:
Nordic Construction
DATE & TIME:
5/13/99 9:45 AM
REPORT NO,:
4
PROJECT NO.:
20991016
WEATHER CONDITIONS:
Sunny, calm
INSPECTOR:
Connie Schneider
LOCATION AND DESCRIPTION:OF WORK
GRID & ELEVATION:
Elevator shaft at 19'
MASONRY UNITS:
Hollow block 8 x 8 x W
REINFORCEMENT:
Vertical - #6 rebar in grout cells
Horizontal - 2 - #4 rebar in bond beams
GROUTING:
Observed grout placement
SUMMARY
COMMENTS:
Placement in general accordance with plans
DISCREPANCIES NOTED:
None noted or observed during periodic observation on 5/13/99
p
Irerracon
301 North Howes Street
Fort Collins, Colorado 80521
(970) 484-0359 FAX (9701484-0454
. .......
....... ...
%
............ 7.REPORT ORM,*ONRYORSERVATION
CLIENT:
Nordic Construction
309 West Harmony Road
Fort Collins, CO 80526
PROJECT:
Remax
4703A Boardwalk
Fort Collins, Colorado
CONTRACTOR:
Nordic Construction
DATE & TIME:
4127/99
REPORT NO.:
1
PROJECT NO.:
20991016
WEATHER CONDITIONS:
Sunny, slight overcast
INSPECTOR:
Richard Hoskinson
...... . .....
LOCATION:NNN.1
_0
AND DESCRIPTION -OF WORK
GRID & ELEVATION:
Elevator CMU walls
Elevation 8'-0" from top of footing
MASONRY UNITS:
Hollow block 8x8x16'
REINFORCEMENT:
Vertical #6 into grout cells
GROUTING:
Did not grout this day
N: ........... . . ..... .
..........SUMMARY...........
COMMENTS:
Contractor was instructed to provide cleanouts at grout cells and to strike off excessive mortar fins prior
to pouring grout. The contractor agreed to provide minimum requirements for high lift grouting.
DISCREPANCIES NOTED:
See comments above.
�if 11 1 11.
Irerracon
301 North Hawes Street
Fort Collins, Colorado 80521
(970) 484-0359 FAX (9701484-0454
..... . . . .... .
. .. .. .... ..
. .....
. .... .......
REPORT OF Y OBSERVATION .... ......... .. . .
Nordic -donstruction
309 West Harmony Road
Fort Collins, CO 80526
PROJECT:
Remax
4703A Boardwalk
Fort Collins, Colorado
CONTRACTOR:
Nordic Construction
DATE &TIME:
4/28/99
REPORT NO.:
2
1 PROJECT NO.:
20991016
WEATHERCONDITIONS:
Overcast
INSPECTOR:
Richard Hoskinson
..
............TW
LOCATION AND t$,CRIPTiONOP.:..:WORK III''���::::::::..:.�.
.. ..... .....
GRID & ELEVATION:
Elevator CMU walls all four sides)
Elevation 8'-0" from to of footing
MASONRY UNITS:
Hollow black 8x8x16*
REINFORCEMENT:
Vertical #6 into grout cells
Horizontal (2) #4 into bond beam
GROUTING:
Observed placement of grout into grout cells and bond beam
... .. . .... .
:NNN: ................. .
............... .. ........
........... sUMMAky ............. . . ........
. ............ ............... ............
COMMENTS:
Contractor advised to provide 1-11T key way at to of bond beam
Work observed performed to minimum requirements
DISCREPANCIES NOTED:
None
May 7, 1999
Mr. John Sailer
Nordic Construction
309 West Harmony Road
Fort Collins, Colorado 60526
Re: Remax
4703A Boardwalk
Fort Collins, Colorado
Project No. 20991016
We are transmitting:
® herewith
❑ under separate cover
Irerracon
301 N. Howes • P.O. Box 503
Fort Collins, Colorado 80521-0503
(970) 484-0359 Fax: (970) 484-0454
® Field Data ❑ Laboratory Data ❑ Report ❑ Revised Report
Regarding:
❑
Compacted Fills
❑
Footings
❑
Concrete
❑
Asphalt
❑
Aggregate
❑
Concrete Reinforcing
Steel
❑
Permeability Test
❑
Location Diagram
❑
Soil Samples
❑
Construction Material
Samples
❑
Moisture -Density
❑
Grain Size Analysis
®
Masonry
❑
R-Value
❑ General Information
❑ Certifications
❑ Resumes
❑ Other
❑ Report will follow under
separate cover
On -site observation services were provided ❑ Full Time ® Part Time
We have not been asked to interpret the data or to make design and/or construction
recommendations based on the data, and cannot assume responsibility or liability for interpretation
of this data by others.
Sincerely,
TE R v' w d by:
Richard Hoskinson a G. Weeks, P.E.
Engineering Technician I ctural Engineer
Enc/Copies to: (3) Addressee
Arizona ■ Arkansas ■ Colorado ■ Idaho ■ Illinois ■ Iowa ■ Kansas ■ Minnesota ■ Missouri ■ Montana
Nebraska ■ Nevada ■ New Mexico ■ North Dakota ■ Oklahoma ■ Tennessee ■ Texas ■ Utah IF Wisconsin ■ Wyoming
Quality Engineering Since 1965
Irerracon
301 North Hawes Street
Fort Collins, Colorado 80521
(970) 484-0359 FAX 970) 484-0454
REPORT. OF. MASONRY OBSERVATION
CLIENT:
Nordic Construction
309 West Harmony Road
Fort Collins, CO 80526
PROJECT:
Remax
4703A Boardwalk
Fort Collins, Colorado
CONTRACTOR:
Nordic Construction
DATE & TIME:
4/27/99
REPORT NO.;
I
PROJECT NO.:
20991016
WEATHER CONDITIONS:
Sunny, slight overcast
INSPECTOR:
Richard Hoskinson
t::::; :N: .. .........
LOCATIONANDOESGRIPTIO OFWORKNO
GRID & ELEVATION:
Elevator CMU walls
Elevation 8'-0" from to of footing
MASONRY UNITS:
Hollow block 8x8x16*
REINFORCEMENT:
Vertical #6 into grout cells
GROUTING:
bid not grout this day
N.
::N., NN", ..... ...... N..,
t_
. ....... . ...... .
SUMMARY t N-I
COMMENTS:
Contractor was instructed to provide cleanouts at grout cells and to strike off excessive mortar fins prior
to pouring grout. The contractor agreed to provide minimum requirements for high lift grouting.
DISCREPANCIES NOTED:
See comments above.
'1rerracon
301 North Howes Street
Fort Collins, Colorado 80521
(970) 484-0359 FAX J970) 484-0454
i tz
:REPORT.W.. VAS0NRY..0.8SERVAT.10N.::::
..... . ..... -
CLIENT:
Nordic Construction
309 West Harmony Road
Fort Collins, CO 80526
PROJECT:
Remax
4703A Boardwalk
Fort Collins, Colorado
CONTRACTOR:
Nordic Construction
DATE & TIME:
4/28/99
REPORT NO.:
2
1 PROJECT NO.:
20991016
WEATHER CONDITIONS:
Overcast
INSPECTOR:
Richard Hoskinson
z ..........
.-LQCA7ION 1 AND DESCRIPTION OPWORK t N:
GRID & ELEVATION:
Elevator CMU walls all four sides)
Elevation 8'-0" from top of footing
MASONRY NITS:
Hollow block 8x8x16'
REINFORCEMENT:
Vertical #6 into grout cells
Horizontal (2) #4 into bond beam
GROUTING:
r
Observed Rlacement of grout into grout cells and bond beam
N t:
..................... -
SUMMARY........ ... . ......
COMMENTS:
Contractor advised to provide 1-1/2" key wayat to of bond beam
Work observed performed to minimum requirements
DISCREPANCIES NOTED:
None
1
May 7, 1999
Mr. John Sailer
Nordic Construction
309 West Harmony Road
Fort Collins, Colorado 80526
Re: Remax
4703A Boardwalk
Fort Collins, Colorado
Project No. 20991016
We are transmitting:
® Field Data
Regarding:
Irerracon
301 N. Howes • P.O. Box 503
Fort Collins, Colorado 80521-0503
(970) 484-0359 Fax: (970) 484-0454
® herewith
❑ under separate cover
❑ Laboratory Data ❑ Report ❑ Revised Report
❑
Compacted Fills
❑
Footings
❑
Concrete
❑
Asphalt
❑
Aggregate
❑
Concrete Reinforcing
-Steel
❑
Permeability Test
❑
Location Diagram
❑
Soil Samples
❑
Construction Material
Samples
❑
Moisture -Density
❑
Grain Size Analysis
®
Masonry
❑
R-Value
❑ General Information
❑ Certifications
❑ Resumes
❑ Other
❑ Report will follow under
separate cover
On -site observation services were provided ❑ Full Time ® Part Time
We have not been asked to interpret the data or to make design and/or construction
recommendations based on the data, and cannot assume responsibility or liability for interpretation
of this data by others.
iy
TER
9L N
Richard Hoskinson
Engineering Technician
Enc/Copies to: (3) Addressee
by:
G. Weeks, P.E.
lure[ Engineer
Arizona ■ Arkansas ■ Colorado ■ Idaho ■ Illinois ■ Iowa ■ Kansas ■ Minnesota ■ Missouri ■ Montana
Nebraska ■ Nevada ■ New Mexico ■ North Dakota ■ Oklahoma to Tennessee ■ Texas ■ Utah ■ Wisconsin In Wyoming
quality, Engineering Sines 1965
C,
Irerracon
301 North Howes Street
Fort Collins, Colorado 80521
(970) 484-0359 FAX (970) 484-0454
............
. ..... ..
............ — ..... ..............
.. .......... ......:-REPORTOF MASONRY.08SERVATION ..........
CLIENT:
Nordic Construction
309 West Harmony Road
Fort Collins, CO 80526
PROJECT:
Remax
4703A Boardwalk
Fort Collins, Colorado
CONTRACTOR:
Nordic Construction
DATE & TIME:
4/27/99
REPORT NO.:
I
PROJECT NO.:
20991016
WEATHER CONDITIONS:
Sunny, slight overcast
INSPECTOR:
Richard Hoskinson
,.::::;:.:.:.....L0CA110N ANDDESCRIPTION OFzWORK--f=:
GRID & ELEVATION:
Elevator CMU walls
Elevation 8'-0" from top of footing
MASONRY UNITS:
Hollow block 8x8x16'
REINFORCEMENT:
Vertical #6 into grout cells
GROUTING:
Did not grout this day
............ . ..........
............... ..........
z...SUMMARY..-: ... ............ 11, . .........
COMMENTS:
Contractor was instructed to provide cleanouts at grout cells and to strike off excessive mortar fins prior
to pouring grout. The contractor agreed to provide minimum requirements for high lift grouting.
DISCREPANCIES NOTED:
See comments above.
K
A-
Irerracon
301 North Howes Street
Fort Collins, Colorado 80521
(970) 484-0359 FAX (970) 484-0454
.. .. .......... ......... .....
CLIENT:
Nordic Construction
309 West Harmony Road
Fort Collins, CO 80526
PROJECT:
Remax
4703A Boardwalk
Fort Collins, Colorado
CONTRACTOR:
Nordic Construction
DATE & TIME:
4/28/99
REPORT NO.:
2
PROJECT NO.:
20991016
WEATHER CONDITIONS:
Overcast
INSPECTOR:
Richard Hoskinson
.....................
..... .......
-
LOCATION AND�DESCRIPTIONQFWORK
GRID & ELEVATION:
Elevator CMU walls all foursides
Elevation V-0" from to of footing
MASONRY UNITS:
0 ow block 8x8x16'
REINFORCEMENT:
Vertical #6 into grout cells
Horizontal (2) #4 into bond beam
Observed placement of grout into grout cells and bond beam
SUMMARY ....... .. ... ....... ...... ....... ... ...... ....
z ........................... . .......... . ..... .........
COMMENTS:
Contractor advised to provide 1-112" key way at to of bond beam
Work observed performed to minimum requirements
DISCREPANCIES NOTED:
None